CN114592678A - High-rise embracing column wall connecting piece and setting method thereof - Google Patents
High-rise embracing column wall connecting piece and setting method thereof Download PDFInfo
- Publication number
- CN114592678A CN114592678A CN202210227469.3A CN202210227469A CN114592678A CN 114592678 A CN114592678 A CN 114592678A CN 202210227469 A CN202210227469 A CN 202210227469A CN 114592678 A CN114592678 A CN 114592678A
- Authority
- CN
- China
- Prior art keywords
- scaffolding
- column
- scaffold
- rod
- rise
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/04—Means for fastening, supporting, or bracing scaffolds on or against building constructions
- E04G5/046—Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffoldings on walls
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/001—Safety or protective measures against falling down relating to scaffoldings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/007—Devices and methods for erecting scaffolds, e.g. automatic scaffold erectors
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明公开了一种高层高抱柱连墙件及其设置方法,涉及建筑施工技术领域。包括外脚手架外立杆和框架柱,所述外脚手架外立杆前后均排列设置,所述外脚手架外立杆的右侧面相对应位置均设置有外脚手架内立杆,所述外脚手架外立杆右侧面从下至上依次均匀设置有外脚手架外大横杆,所述外脚手架内立杆的左侧面从下至上依次均匀设置有外脚手架内大横杆,所述外脚手架外立杆与外脚手架内立杆之间从下至上依次均匀设置有外脚手架小横杆,所述框架柱的左侧面设置有抱柱内横杆。本发明解决了建筑物大层高楼层间外脚手架的连墙件无法设置的问题,提高外脚手架整体稳定性,确保外脚手架搭设的安全性能,对建筑项目安全及标准化施工有重要意义。The invention discloses a high-rise high-column-connecting wall piece and a setting method thereof, and relates to the technical field of building construction. It includes an outer scaffolding outer pole and a frame column, the outer scaffolding outer poles are arranged in front and back, and the right side of the outer scaffolding outer pole is provided with an outer scaffolding inner pole, and the outer scaffolding is standing outside. The right side of the rod is evenly provided with the outer scaffolding large transverse rod from bottom to top, the left side of the outer scaffolding inner vertical rod is uniformly arranged with the outer scaffolding inner large transverse rod from bottom to top, and the outer scaffolding outer vertical rod Small crossbars of the outer scaffolding are evenly arranged from bottom to top between the inner vertical rods of the outer scaffolding, and the left side of the frame column is provided with an inner crossbar that holds the column. The invention solves the problem that the connecting wall parts of the outer scaffolding between the large and high floors of the building cannot be installed, improves the overall stability of the outer scaffolding, ensures the safety performance of the erection of the outer scaffolding, and is of great significance to the safety and standardization of construction projects.
Description
技术领域technical field
本发明涉及建筑施工技术领域,具体为一种高层高抱柱连墙件及其设置方法。The invention relates to the technical field of building construction, in particular to a high-rise high-column-connecting wall piece and a method for setting the same.
背景技术Background technique
在建筑施工中多需要搭设脚手架,脚手架是为了保证各施工过程顺利进行而搭设的工作平台,按搭设的位置分为外脚手架、里脚手架;按材料不同可分为木脚手架、竹脚手架、钢管脚手架;按构造形式分为立杆式脚手架、桥式脚手架、门式脚手架、悬吊式脚手架、挂式脚手架、挑式脚手架、爬式脚手架。Scaffolding is often required in construction. Scaffolding is a working platform set up to ensure the smooth progress of each construction process. According to the erection position, it can be divided into outer scaffolding and inner scaffolding; according to different materials, it can be divided into wooden scaffolding, bamboo scaffolding and steel pipe scaffolding. ; According to the structural form, it is divided into vertical scaffolding, bridge scaffolding, portal scaffolding, suspended scaffolding, hanging scaffolding, pick-up scaffolding and climbing scaffolding.
现有技术中,建筑施工中难免存在层高较大的楼层,在进行落地式脚手架搭设时,会存在某一较大层高及框架柱之间连墙件与外脚手架的连接点较小,导致外脚手架整体稳定性较差,存在倾覆的风险,使用安全度不高。In the prior art, it is unavoidable that there are floors with larger heights during construction. When the floor-standing scaffolding is erected, there will be a certain larger height and the smaller connection points between the wall pieces and the outer scaffolding between the frame columns. As a result, the overall stability of the outer scaffold is poor, there is a risk of overturning, and the use safety is not high.
发明内容SUMMARY OF THE INVENTION
针对现有技术的不足,本发明提供了一种高层高抱柱连墙件及其设置方法,以解决上述背景技术中提出的问题。In view of the deficiencies of the prior art, the present invention provides a high-rise high-column-connecting wall piece and a method for setting the same, so as to solve the problems raised in the above-mentioned background art.
为实现上述目的,本发明提供如下技术方案:一种高层高抱柱连墙件,包括外脚手架外立杆和框架柱,所述外脚手架外立杆前后均排列设置,所述外脚手架外立杆的右侧面相对应位置均设置有外脚手架内立杆,所述外脚手架外立杆右侧面从下至上依次均匀设置有外脚手架外大横杆,所述外脚手架内立杆的左侧面从下至上依次均匀设置有外脚手架内大横杆,所述外脚手架外立杆与外脚手架内立杆之间从下至上依次均匀设置有外脚手架小横杆,所述框架柱的左侧面设置有抱柱内横杆,所述框架柱的右侧面设置有抱柱外横杆,所述抱柱内横杆与抱柱外横杆的上表面位于前后框架柱的前后侧面均设置有抱柱纵杆,所述抱柱纵杆与外脚手架内大横杆和外脚手架外大横杆相连接,所述抱柱纵杆的上表面位于框架柱前后侧面均设置有水平斜杆,且水平斜杆抱柱内横杆、外脚手架内大横杆和外脚手架外大横杆相连接,所述外脚手架外立杆和外脚手架内立杆上设置有加强机构。In order to achieve the above purpose, the present invention provides the following technical solutions: a high-rise high-rise column-connecting wall piece, comprising an outer scaffolding outer pole and a frame column, the outer scaffolding outer poles are arranged in front and rear, and the outer scaffolding outer poles are arranged in a row. Corresponding positions on the right side are provided with inner poles of the outer scaffold, and the right side of the outer pole of the outer scaffold is uniformly arranged with large cross bars of the outer scaffold from bottom to top, and the left side of the inner pole of the outer scaffold is from the bottom to the top. From bottom to top, there are evenly arranged large inner cross bars of the outer scaffolding, and between the outer vertical bars of the outer scaffolding and the inner vertical bars of the outer scaffolding are uniformly arranged with small horizontal bars of the outer scaffolding from bottom to top, and the left side of the frame column is provided with There is an inner cross bar for holding the column, the right side of the frame column is provided with an outer cross bar for holding the column, and the upper surfaces of the inner cross bar for holding the column and the outer cross bar for holding the column are located on the front and rear sides of the front and rear frame columns. Column vertical rod, the column holding vertical rod is connected with the inner large cross rod of the outer scaffold and the outer large horizontal rod of the outer scaffold, and the upper surface of the column holding vertical rod is located on the front and rear sides of the frame column. The inner horizontal bar of the slanting bar holding the column, the inner large horizontal bar of the outer scaffold and the outer large horizontal bar of the outer scaffold are connected, and a reinforcing mechanism is arranged on the outer vertical bar of the outer scaffold and the inner vertical bar of the outer scaffold.
进一步优化本技术方案,所述外脚手架外立杆与外脚手架内立杆之间间距为1800mm,所述外脚手架内立杆的右侧面距离框架柱的左侧面之间距离为250mm。The technical solution is further optimized. The distance between the outer scaffolding outer pole and the outer scaffolding inner pole is 1800mm, and the distance between the right side of the outer scaffolding inner pole and the left side of the frame column is 250mm.
进一步优化本技术方案,所述外脚手架外大横杆、外脚手架内大横杆和外脚手架小横杆据地面200mm设置作为扫地杆,且外脚手架外大横杆与外脚手架内大横杆向上每步的间距为1800mm,所述外脚手架小横杆向上每一步间距为1500mm。This technical solution is further optimized. The outer large horizontal bar of the outer scaffold, the inner large horizontal bar of the outer scaffold and the small outer scaffolding bar are set as sweeping bars according to 200mm of the ground, and the outer large horizontal bar of the outer scaffold and the inner large horizontal bar of the outer scaffold are upward. The interval of each step is 1800mm, and the interval of each step upward of the small cross bar of the outer scaffold is 1500mm.
进一步优化本技术方案,所述水平斜杆上下相邻之间间距为2m-3m间隔设置,所述水平斜杆与外脚手架外大横杆的夹角在30°-60°。The technical solution is further optimized. The interval between the upper and lower adjacent horizontal inclined rods is 2m-3m, and the included angle between the horizontal inclined rod and the outer large horizontal rod of the outer scaffold is 30°-60°.
进一步优化本技术方案,所述加强机构包括水平杆和连接杆,所述水平杆设置于外脚手架外立杆和外脚手架内立杆上,所述水平杆与连接杆相互连接固定,所述加强机构上下之间的间距按3m-3.5m上左右。This technical solution is further optimized. The reinforcing mechanism includes a horizontal rod and a connecting rod. The horizontal rod is arranged on the outer vertical rod of the outer scaffold and the inner vertical rod of the outer scaffold. The horizontal rod and the connecting rod are connected and fixed to each other. The distance between the top and bottom of the mechanism is about 3m-3.5m.
进一步优化本技术方案,所述连接杆预埋于框架柱上。To further optimize the technical solution, the connecting rod is pre-embedded on the frame column.
进一步优化本技术方案,所述外脚手架外立杆、外脚手架内立杆、外脚手架外大横杆、外脚手架内大横杆、外脚手架小横杆、抱柱内横杆、抱柱外横杆、抱柱纵杆、水平斜杆和加强机构之间采用直角扣件或旋转扣件进行加固。This technical solution is further optimized. The outer scaffolding poles, the outer scaffolding inner poles, the outer scaffolding outer large horizontal poles, the outer scaffolding inner large horizontal poles, the outer scaffolding small horizontal poles, the column-holding inner horizontal poles, the column-holding outer horizontal poles. Right-angle fasteners or rotary fasteners are used for reinforcement between the rod, the column-holding longitudinal rod, the horizontal inclined rod and the reinforcement mechanism.
一种高层高抱柱连墙件设置方法,包括以下步骤:A method for setting high-rise high-rise column-connecting wall parts, comprising the following steps:
S1、落地式外脚手架搭设:根据外脚手架搭设参数,使外脚手架内立杆距建筑物边缘250mm前后排列均匀设置,再通过外脚手架内立杆左侧面距外脚手架外立杆右侧面距离为1800mm,使外脚手架小横杆、外脚手架内大横杆和外脚手架外大横杆据地面200mmn作为扫地杆,外脚手架内大横杆和外脚手架外大横杆其上每步间距为1800mm,外脚手架小横杆的每跨间距为1500mm;S1. Floor-standing external scaffolding erection: According to the erection parameters of the external scaffolding, make the inner poles of the outer scaffolding 250mm from the edge of the building evenly arranged in front and back, and then pass the distance between the left side of the inner pole of the outer scaffold and the right side of the outer pole of the outer scaffold It is 1800mm, so that the small crossbar of the outer scaffold, the large crossbar inside the outer scaffold and the large crossbar outside the outer scaffold are 200mmn from the ground as sweeping rods, and the distance between each step on the large crossbar inside the outer scaffold and the large crossbar outside the outer scaffold is 1800mm , the spacing between each span of the small crossbar of the outer scaffold is 1500mm;
S2、上下楼层边梁位置的常规连墙件设置:按照连墙件每两跨的布置参数,在建筑物外边梁内随楼层浇筑混凝土时埋设600mm长的短钢管作为连墙件的连接点,即连接杆,连接杆露出板面300mm,用连接杆即与水平杆拉结,横向水平杆将外脚手架内立杆和外脚手架内立杆与连接点横向拉结;S2. Conventional setting of connecting wall pieces at the edge beam position of upper and lower floors: According to the arrangement parameters of every two spans of connecting wall pieces, when pouring concrete with the floor in the outer side beam of the building, a short steel pipe with a length of 600mm is buried as the connecting point of connecting wall pieces. That is, the connecting rod, the connecting rod is exposed 300mm from the surface of the board, and the connecting rod is used to tie the horizontal rod, and the horizontal horizontal rod ties the inner vertical rod of the outer scaffold and the inner vertical rod of the outer scaffold with the connecting point horizontally;
S3、楼层间“八字抱柱连墙件”设置:在大层高楼层边梁起外脚手架大致两步位置起开始设置,每两步的布置参数设置抱柱外横杆、抱柱内横杆和抱柱纵杆,将抱柱纵杆与外脚手架内大横杆和外脚手架外大横杆进行连接,如果满足“八字抱柱连墙件”的设置要求,在抱柱纵杆上设置水平斜杆,水平斜杆与抱柱内横杆、外脚手架内大横杆、外脚手架外大横杆进行拉结,确保水平斜杆与外脚手架外大横杆的夹角在30°-60°之间,整个外脚手架的八字抱柱连墙件设置完毕。S3. "Eight-character column-column-connecting wall" setting between floors: start the setting from the roughly two-step position of the outer scaffolding on the side beams of the high-rise and high-rise floors, and the layout parameters of each two-step setting are to set the column-holding outer crossbar and the column-holding inner crossbar and the column-holding vertical bar, connect the column-holding vertical bar with the inner large horizontal bar of the outer scaffold and the outer large horizontal bar of the outer scaffold. If it meets the setting requirements of "eight-shaped column-holding-to-wall fittings", set the horizontal bar on the column-holding vertical bar. The inclined rod, the horizontal inclined rod and the inner cross rod of the holding column, the inner large cross rod of the outer scaffold, and the outer large cross rod of the outer scaffold are tied together to ensure that the angle between the horizontal inclined rod and the outer large cross rod of the outer scaffold is 30°-60° In between, the eight-character column and wall parts of the entire outer scaffolding are set up.
有益效果beneficial effect
与现有技术相比,本发明提供了一种高层高抱柱连墙件及其设置方法,具备以下有益效果:Compared with the prior art, the present invention provides a high-rise high-column-connecting wall piece and its setting method, which have the following beneficial effects:
该高层高抱柱连墙件及其设置方法,通过设置水平斜杆,并按两步一设的参数,将抱柱内横杆、外脚手架外大横杆和外脚手架内大横杆进行拉结,解决了建筑物大层高楼层间外脚手架的连墙件无法设置的问题,提高外脚手架整体稳定性,确保外脚手架搭设的安全性能,且施工方便、安全和便宜,对建筑项目安全及标准化施工有重要意义。The high-rise high-holding column-connecting wall piece and its setting method are: by setting the horizontal inclined rod, and according to the parameters set in two steps, the inner crossbar of the holding column, the outer large crossbar of the outer scaffold, and the large inner crossbar of the outer scaffold are tied together, It solves the problem that the connecting wall parts of the external scaffolding between the large and high floors of the building cannot be installed, improves the overall stability of the external scaffolding, ensures the safety performance of the external scaffolding, and the construction is convenient, safe and cheap, and it is safe and standardized for construction projects. have important meaning.
附图说明Description of drawings
图1为本发明提出的一种高层高抱柱连墙件的结构示意图;Fig. 1 is the structural representation of a kind of high-rise high-rise column-connecting wall piece proposed by the present invention;
图2为本发明提出的一种高层高抱柱连墙件的俯视图;Fig. 2 is the top view of a kind of high-rise high-rise column-connecting wall piece proposed by the present invention;
图3为本发明提出的一种高层高抱柱连墙件的图1中A处放大图;Fig. 3 is the enlarged view of A in Fig. 1 of a kind of high-rise high-rise column-connecting wall piece proposed by the present invention;
图4为本发明提出的一种高层高抱柱连墙件的图1中B处放大图;Fig. 4 is an enlarged view at B in Fig. 1 of a kind of high-rise high-rise column-connecting wall piece proposed by the present invention;
图5为本发明提出的一种高层高抱柱连墙件其设置方法的流程示意图。FIG. 5 is a schematic flow chart of a method for arranging a high-rise column-connecting wall piece proposed by the present invention.
图中:1、外脚手架外立杆;2、框架柱;3、外脚手架内立杆;4、外脚手架外大横杆;5、外脚手架内大横杆;6、外脚手架小横杆;7、抱柱内横杆;8、抱柱外横杆;9、抱柱纵杆;10、水平斜杆;11、加强机构;111、水平杆;112、连接杆。In the picture: 1. Outer scaffolding pole; 2. Frame column; 3. Outer scaffolding inner pole; 4. Outer scaffolding outer large horizontal pole; 7. Inner crossbar for holding the column; 8. External crossbar for holding the column; 9. Vertical bar for holding the column; 10. Horizontal oblique rod; 11. Strengthening mechanism; 111. Horizontal rod; 112. Connecting rod.
具体实施方式Detailed ways
下面将结合本发明的实施例,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.
请参考图1-图5,本发明公开了一种高层高抱柱连墙件及其设置方法,包括外脚手架外立杆1和框架柱2,所述外脚手架外立杆1前后均排列设置,所述外脚手架外立杆1的右侧面相对应位置均设置有外脚手架内立杆3,所述外脚手架外立杆1右侧面从下至上依次均匀设置有外脚手架外大横杆4,所述外脚手架内立杆3的左侧面从下至上依次均匀设置有外脚手架内大横杆5,所述外脚手架外立杆1与外脚手架内立杆3之间从下至上依次均匀设置有外脚手架小横杆6,所述框架柱2的左侧面设置有抱柱内横杆7,所述框架柱2的右侧面设置有抱柱外横杆8,所述抱柱内横杆7与抱柱外横杆8的上表面位于前后框架柱2的前后侧面均设置有抱柱纵杆9,所述抱柱纵杆9与外脚手架内大横杆5和外脚手架外大横杆4相连接,所述抱柱纵杆9的上表面位于框架柱2前后侧面均设置有水平斜杆10,且水平斜杆10抱柱内横杆7、外脚手架内大横杆5和外脚手架外大横杆4相连接,所述外脚手架外立杆1和外脚手架内立杆3上设置有加强机构11。Please refer to FIG. 1-FIG. 5, the present invention discloses a high-rise high-column-column-connecting wall piece and its setting method, including an outer scaffolding
具体的,所述外脚手架外立杆1与外脚手架内立杆3之间间距为1800mm,所述外脚手架内立杆3的右侧面距离框架柱2的左侧面之间距离为250mm。Specifically, the distance between the outer scaffolding
本实施方案中,外脚手架外立杆1与外脚手架内立杆3之间具有一定的跨度,且外脚手架内立杆3与框架柱2之间具有一定宽度,使该脚手架放置更加稳定,便于踩踏使用。In this embodiment, there is a certain span between the
具体的,所述外脚手架外大横杆4、外脚手架内大横杆5和外脚手架小横杆6据地面200mm设置作为扫地杆,且外脚手架外大横杆4与外脚手架内大横杆5向上每步的间距为1800mm,所述外脚手架小横杆6向上每一步间距为1500mm。Specifically, the outer
本实施方案中,外脚手架外大横杆4、外脚手架内大横杆5和外脚手架小横杆6使外脚手架外立杆1与外脚手架内立杆3之间更加稳定,使该脚手架的之间结构强度大。In this embodiment, the outer
具体的,所述水平斜杆10上下相邻之间间距为2m-3m间隔设置,所述水平斜杆10与外脚手架外大横杆4的夹角在30°-60°。Specifically, the horizontal
本实施方案中,水平斜杆10使该脚手架受力更加均匀,且强度大,不易出现倾覆。In this embodiment, the horizontal
具体的,所述加强机构11包括水平杆111和连接杆112,所述水平杆111设置于外脚手架外立杆1和外脚手架内立杆3上,所述水平杆111与连接杆112相互连接固定,所述加强机构11上下之间的间距按3m-3.5m上左右。Specifically, the reinforcing
本实施方案中,水平杆111和连接杆112连接,水平杆111与外脚手架外立杆1和外脚手架内立杆3连接,进一步加强该脚手架的强度。In this embodiment, the
具体的,所述连接杆112预埋于框架柱2上。Specifically, the connecting
本实施方案中,连接杆112与框架柱2之间牢固,便于对连接杆112进行安装。In this embodiment, the
具体的,所述外脚手架外立杆1、外脚手架内立杆3、外脚手架外大横杆4、外脚手架内大横杆5、外脚手架小横杆6、抱柱内横杆7、抱柱外横杆8、抱柱纵杆9、水平斜杆10和加强机构11之间采用直角扣件或旋转扣件进行加固。Specifically, the outer scaffolding
本实施方案中,直角扣件或旋转扣件使外脚手架外立杆1、外脚手架内立杆3、外脚手架外大横杆4、外脚手架内大横杆5、外脚手架小横杆6、抱柱内横杆7、抱柱外横杆8、抱柱纵杆9、水平斜杆10和加强机构11之间相互拉结,从而组成一个具有八字抱柱连墙件的脚手架。In this embodiment, the right-angle fasteners or the rotating fasteners make the outer scaffolding
一种高层高抱柱连墙件设置方法,包括以下步骤:A method for setting high-rise high-rise column-connecting wall parts, comprising the following steps:
S1、落地式外脚手架搭设:根据外脚手架搭设参数,使外脚手架内立杆3距建筑物边缘250mm前后排列均匀设置,再通过外脚手架内立杆3左侧面距外脚手架外立杆1右侧面距离为1800mm,使外脚手架小横杆6、外脚手架内大横杆5和外脚手架外大横杆4据地面200mmn作为扫地杆,外脚手架内大横杆5和外脚手架外大横杆4其上每步间距为1800mm,外脚手架小横杆6的每跨间距为1500mm;S1. Erection of floor-standing external scaffolding: According to the erection parameters of the external scaffolding, make the
S2、上下楼层边梁位置的常规连墙件设置:按照连墙件每两跨的布置参数,在建筑物外边梁内随楼层浇筑混凝土时埋设600mm长的短钢管作为连墙件的连接点,即连接杆112,连接杆112露出板面300mm,用连接杆112即与水平杆111拉结,横向水平杆111将外脚手架内立杆3和外脚手架内立杆3与连接点横向拉结;S2. Conventional setting of connecting wall pieces at the edge beam position of upper and lower floors: According to the arrangement parameters of every two spans of connecting wall pieces, when pouring concrete with the floor in the outer side beam of the building, a short steel pipe with a length of 600mm is buried as the connecting point of connecting wall pieces. That is, the connecting
S3、楼层间“八字抱柱连墙件”设置:在大层高楼层边梁起外脚手架大致两步位置起开始设置,每两步的布置参数设置抱柱外横杆8、抱柱内横杆7和抱柱纵杆9,将抱柱纵杆9与外脚手架内大横杆5和外脚手架外大横杆4进行连接,如果满足“八字抱柱连墙件”的设置要求,在抱柱纵杆9上设置水平斜杆10,水平斜杆10与抱柱内横杆7、外脚手架内大横杆5、外脚手架外大横杆4进行拉结,确保水平斜杆10与外脚手架外大横杆4的夹角在30°-60°之间,整个外脚手架的八字抱柱连墙件设置完毕。S3. The setting of "eight-character column-column-connecting wall pieces" between floors: start the setting from the position where the outer scaffolding of the side beam of the large high-rise building is roughly two steps away, and the layout parameters of each two steps are set to hold the outer crossbar of the
本发明的有益效果是:根据外脚手架搭设参数,使外脚手架内立杆3距建筑物边缘250mm前后排列均匀设置,再通过外脚手架内立杆3左侧面距外脚手架外立杆1右侧面距离为1800mm,使外脚手架小横杆6、外脚手架内大横杆5和外脚手架外大横杆4据地面200mmn作为扫地杆,外脚手架内大横杆5和外脚手架外大横杆4其上每步间距为1800mm,外脚手架小横杆6的每跨间距为1500mm,按照连墙件每两跨的布置参数,在建筑物外边梁内随楼层浇筑混凝土时埋设600mm长的短钢管作为连墙件的连接点,即连接杆112,连接杆112露出板面300mm,用连接杆112即与水平杆111拉结,横向水平杆111将外脚手架内立杆3和外脚手架内立杆3与连接点横向拉结,在大层高楼层边梁起外脚手架大致两步位置起开始设置,每两步的布置参数设置抱柱外横杆8、抱柱内横杆7和抱柱纵杆9,将抱柱纵杆9与外脚手架内大横杆5和外脚手架外大横杆4进行连接,如果满足“八字抱柱连墙件”的设置要求,在抱柱纵杆9上设置水平斜杆10,水平斜杆10与抱柱内横杆7、外脚手架内大横杆5、外脚手架外大横杆4进行拉结,确保水平斜杆10与外脚手架外大横杆4的夹角在30°-60°之间,整个外脚手架的八字抱柱连墙件设置完毕,解决了建筑物大层高楼层间外脚手架的连墙件无法设置的问题,提高外脚手架整体稳定性,确保外脚手架搭设的安全性能,且施工方便、安全和便宜,对建筑项目安全及标准化施工有重要意义。The beneficial effects of the invention are: according to the erection parameters of the outer scaffolding, the
尽管已经示出和描述了本发明的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本发明的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本发明的范围由所附权利要求及其等同物限定。Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, and substitutions can be made in these embodiments without departing from the principle and spirit of the invention and modifications, the scope of the present invention is defined by the appended claims and their equivalents.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210227469.3A CN114592678A (en) | 2022-03-08 | 2022-03-08 | High-rise embracing column wall connecting piece and setting method thereof |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210227469.3A CN114592678A (en) | 2022-03-08 | 2022-03-08 | High-rise embracing column wall connecting piece and setting method thereof |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN114592678A true CN114592678A (en) | 2022-06-07 |
Family
ID=81817225
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202210227469.3A Pending CN114592678A (en) | 2022-03-08 | 2022-03-08 | High-rise embracing column wall connecting piece and setting method thereof |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN114592678A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116856670A (en) * | 2023-07-26 | 2023-10-10 | 中天建设集团有限公司 | Double-row column type outer scaffold erecting structure and method for ultra-high super-span building |
| CN119860077A (en) * | 2025-02-27 | 2025-04-22 | 中国五冶集团有限公司 | Anti-overturning stabilizing device and method for scaffold |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN202731280U (en) * | 2012-08-31 | 2013-02-13 | 中国建筑第四工程局有限公司 | Tool type outer scaffold wall connecting piece |
| CN204212385U (en) * | 2014-09-12 | 2015-03-18 | 中国建筑第五工程局有限公司 | Scaffold strengthened by truss |
| CN215055197U (en) * | 2021-03-19 | 2021-12-07 | 上海宝冶集团有限公司 | Outer scaffold drawknot reinforced structure of large-span high-rise building system |
| CN217028024U (en) * | 2022-03-08 | 2022-07-22 | 中国建筑第四工程局有限公司 | High-rise embracing column wall connecting piece |
-
2022
- 2022-03-08 CN CN202210227469.3A patent/CN114592678A/en active Pending
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN202731280U (en) * | 2012-08-31 | 2013-02-13 | 中国建筑第四工程局有限公司 | Tool type outer scaffold wall connecting piece |
| CN204212385U (en) * | 2014-09-12 | 2015-03-18 | 中国建筑第五工程局有限公司 | Scaffold strengthened by truss |
| CN215055197U (en) * | 2021-03-19 | 2021-12-07 | 上海宝冶集团有限公司 | Outer scaffold drawknot reinforced structure of large-span high-rise building system |
| CN217028024U (en) * | 2022-03-08 | 2022-07-22 | 中国建筑第四工程局有限公司 | High-rise embracing column wall connecting piece |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116856670A (en) * | 2023-07-26 | 2023-10-10 | 中天建设集团有限公司 | Double-row column type outer scaffold erecting structure and method for ultra-high super-span building |
| CN119860077A (en) * | 2025-02-27 | 2025-04-22 | 中国五冶集团有限公司 | Anti-overturning stabilizing device and method for scaffold |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110439270B (en) | Construction method of post-cast strip disassembly-free support system | |
| CN111779248B (en) | High formwork system and construction method thereof | |
| CN109898848B (en) | A climbing integral steel platform formwork system and its construction method | |
| CN104631822A (en) | Construction Method of High-rise Reinforced Concrete Elevator Shaft | |
| CN212002170U (en) | Adjustable support for elevator shaft operating platform | |
| CN103276886A (en) | Overhanging frame at position of high-rise building sloping roof outer eave window and construction method thereof | |
| CN114592678A (en) | High-rise embracing column wall connecting piece and setting method thereof | |
| CN105863253A (en) | Integral formwork-supporting type asynchronous casting stairwell wall column formwork supporting system and construction method | |
| CN108252504A (en) | Tube shear wall concrete structure large form hoisting type construction method and constructing device | |
| CN111005547B (en) | Construction method of outer scaffold of two-way bending and twisting staggered floor elevation | |
| CN105019657A (en) | Building construction system | |
| CN217151150U (en) | Overhanging steel truss formwork supporting platform for aluminum mould-full concrete outer wall | |
| CN103410311A (en) | Raising-plate high-formwork construction method of indoor pool | |
| CN217028024U (en) | High-rise embracing column wall connecting piece | |
| CN116696055B (en) | Construction decoration method for cantilever structure of flat roof framework layer | |
| CN208363666U (en) | It is a kind of for build face side construction safety protection frame | |
| CN210086818U (en) | A kind of roof floating plate formwork structure | |
| CN220725767U (en) | Movable high and large formwork support | |
| CN115961770B (en) | A structure and method for erecting a ground-type external scaffolding passing through an overhanging eave | |
| CN207999079U (en) | Overhang large form support device | |
| CN110273538A (en) | A kind of high framed building wall-connecting piece of the big layer of large span and its setting method | |
| CN213297074U (en) | A convenient outer wall cantilever operation frame | |
| CN104878933A (en) | Construction method for setting up over roof curtain wall hanging basket support scaffolding | |
| CN116771105A (en) | A formwork support device with complex frame structure and special-shaped eaves | |
| CN204876579U (en) | Building construction system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20220607 |