CN114562277B - A variable cross-section tunnel construction method - Google Patents

A variable cross-section tunnel construction method Download PDF

Info

Publication number
CN114562277B
CN114562277B CN202210211699.0A CN202210211699A CN114562277B CN 114562277 B CN114562277 B CN 114562277B CN 202210211699 A CN202210211699 A CN 202210211699A CN 114562277 B CN114562277 B CN 114562277B
Authority
CN
China
Prior art keywords
shield
machine
tunnel
tunnel boring
boring machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202210211699.0A
Other languages
Chinese (zh)
Other versions
CN114562277A (en
Inventor
程永亮
刘智成
马保松
廖鸿雁
王晖
彭正阳
刘学
陈亮
黄胜
张瑞临
麦宇豪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Heavy Industry Group Co Ltd
Guangzhou Metro Group Co Ltd
Sun Yat Sen University
Original Assignee
China Railway Construction Heavy Industry Group Co Ltd
Guangzhou Metro Group Co Ltd
Sun Yat Sen University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Heavy Industry Group Co Ltd, Guangzhou Metro Group Co Ltd, Sun Yat Sen University filed Critical China Railway Construction Heavy Industry Group Co Ltd
Priority to CN202210211699.0A priority Critical patent/CN114562277B/en
Publication of CN114562277A publication Critical patent/CN114562277A/en
Application granted granted Critical
Publication of CN114562277B publication Critical patent/CN114562277B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/01Methods or apparatus for enlarging or restoring the cross-section of tunnels, e.g. by restoring the floor to its original level
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0621Shield advancing devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0692Cutter drive shields
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/08Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield
    • E21D9/087Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield with a rotary drilling-head cutting simultaneously the whole cross-section, i.e. full-face machines
    • E21D9/0873Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield with a rotary drilling-head cutting simultaneously the whole cross-section, i.e. full-face machines the shield being provided with devices for lining the tunnel, e.g. shuttering
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a construction method of a variable-section tunnel, which comprises the steps of constructing a first section of tunnel through a first tunneling machine, arranging a first receiving well for receiving the first tunneling machine at the end position of the first section of tunnel, disassembling and replacing the first tunneling machine into a second tunneling machine in the first receiving well, enabling construction section sizes of the first tunneling machine and the second tunneling machine to be different, converting the first receiving well into an originating well of the second tunneling machine, constructing a second section of tunnel through the second tunneling machine, and arranging a second receiving well for receiving the second tunneling machine at the end position of the second section of tunnel. The functions of receiving and starting can be realized through the same working well, so that the purposes of reducing construction cost and improving construction efficiency are achieved. In addition, the construction of different tunnel sections can be realized, and compared with the traditional integrated switching construction equipment, the construction cost can be effectively reduced, and the construction mode is simple and easy to operate.

Description

Variable-section tunnel construction method
Technical Field
The invention relates to the technical field of underground construction, in particular to a variable section tunnel construction method.
Background
When the subway section tunnel and the platform structure are constructed, the section tunnel is constructed by a common shield method, the platform is constructed by a common open cut method, but the open cut method has great influence on the surrounding environment, and if the platform is constructed by adopting a non-excavation pipe jacking mode, the problem can be avoided.
In the prior art, shield-pipe jacking integrated machine equipment exists, but tunnels constructed by the shield-pipe jacking integrated machine equipment are the same in section size, however, the size difference between the subway section tunnel and the platform end face is large, and therefore the shield-pipe jacking integrated machine equipment is difficult to apply to the working condition of reducing. In addition, the existing shield-pipe jacking all-in-one machine is essentially provided with two systems at the same time to realize the switching of two functions, but the equipment is high in cost, and in the jacking process, the front shield equipment needs to be jacked together, so that the jacking force is increased, and the operation is inconvenient.
Disclosure of Invention
The invention aims to provide a variable section tunnel construction method which can realize construction of different sections of a multi-section tunnel.
In order to solve the technical problems, the invention provides the following technical scheme:
a variable section tunnel construction method comprises the following steps:
Constructing a first section of tunnel through a first heading machine;
setting a first receiving well for receiving the first heading machine at the end position of the first section of tunnel;
In the first receiving well, the first heading machine is disassembled and replaced by a second heading machine, and the construction section sizes of the first heading machine and the second heading machine are different;
Converting the first receiving well into an originating well of the second heading machine;
constructing a second section of tunnel through the second heading machine;
and setting a second receiving well for receiving the second heading machine at the end position of the second section of tunnel.
Preferably, the first heading machine and the second heading machine may be different types of heading machines or different types of heading machines with cutterheads having different diameters.
Preferably, the first heading machine is disassembled and replaced by a second heading machine, and the method specifically comprises the steps of replacing a cutterhead of the first heading machine with a cutterhead with a diameter different from that of the cutterhead, so as to disassemble and replace the first heading machine into the second heading machine, or disassembling and replacing the first heading machine into the second heading machine capable of constructing the section shape different from that of the second heading machine.
The method comprises the steps of removing a front shield, a middle shield and a shell of a shield tail of the shield machine, a segment erector and a shield jack, reserving a shield cutter head, a main driving structure and a screw conveyor, installing a front end shell at the front end of the shield machine, installing a rear end shell at the rear end of the shield machine, and expanding the shield cutter head into a large-diameter pipe jacking cutter head.
Preferably, the first receiving well is converted into an originating well of the second heading machine, and the originating well specifically comprises a jacking pipe counter-force frame, a jacking pipe steel plate and jacking pipe jack equipment which are arranged in the first receiving well, and a receiving base and a guide rail structure in the first receiving well are adjusted for originating of the jacking pipe machine.
The method comprises the steps of removing an outer shell of the pipe jacking machine, adjusting a pipe jacking cutter to be a small-diameter shield cutter, and installing shells of a front shield, a middle shield and a shield tail of the shield machine, a segment erector and a shield jack.
Preferably, the first receiving well is converted into an originating well of the second heading machine, and the method specifically comprises the steps of installing a shield reaction frame and a shield steel plate at the position of a pipe jacking hole outlet, and adjusting a pipe jacking receiving base and a guide rail structure in the first receiving well for originating of the shield machine.
Preferably, two tunnel lines each including a station are constructed, and the two stations are dug by a dug method to form one large-section station.
Preferably, the method for performing the dig-enlarging on the two stations by adopting the dig method specifically comprises the following steps:
Drilling, grouting and reinforcing a part of the platform needing to be dug;
Mechanical station breaking needs to be expanded and (5) digging a pipe jacking segment of the part.
Preferably, after the pipe-jacking segment is broken, the primary support is constructed in a mode of grid arch frames, shotcrete, connecting ribs and reinforcing steel meshes, and the waterproof layer and the secondary lining are constructed after the expansion and the excavation.
Compared with the prior art, the technical scheme has the following advantages:
The invention provides a construction method of a variable-section tunnel, which comprises the steps of constructing a first section of tunnel through a first tunneling machine, arranging a first receiving well for receiving the first tunneling machine at the end position of the first section of tunnel, disassembling and replacing the first tunneling machine into a second tunneling machine in the first receiving well, enabling construction section sizes of the first tunneling machine and the second tunneling machine to be different, converting the first receiving well into an originating well of the second tunneling machine, constructing a second section of tunnel through the second tunneling machine, and arranging a second receiving well for receiving the second tunneling machine at the end position of the second section of tunnel. The functions of receiving and starting can be realized through the same working well, so that the purposes of reducing construction cost and improving construction efficiency are achieved. In addition, the construction of different tunnel sections can be realized, and compared with the traditional integrated switching construction equipment, the construction cost can be effectively reduced, and the construction mode is simple and easy to operate.
Drawings
In order to more clearly illustrate the invention or the technical solutions of the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described, and it is obvious that the drawings in the description below are some embodiments of the invention, and other drawings can be obtained according to these drawings without inventive effort for a person skilled in the art.
FIG. 1 is a schematic flow chart of a method for constructing a variable section tunnel according to an embodiment of the present invention;
fig. 2 is a schematic construction diagram of two subway section tunnels and a station platform tunnel part;
FIG. 3 is a schematic structural view of a shield tunneling machine;
FIG. 4 is a schematic view of a push bench;
FIG. 5 is a layout of the converted push bench and push initiation well;
FIG. 6 is a layout of the converted shield tunneling machine and shield originating well;
Fig. 7 is a cross-sectional view of the double-line station platform tunnel expansion construction.
The reference numerals are as follows:
1 is a shield tunneling machine cutterhead, 2 is a front shield, 3 is a middle shield, 4 is a shield tail, 5 is a screw conveyor, 6 is a shield jack, 7 is a segment erector, 8 is a main driving structure, 9 is a front end housing, 10 is a rear end housing, 11 is a pipe jacking pipe joint, 12 is a pipe jacking jack, 13 is a top iron, 14 is a pipe jacking machine cutterhead, 15 is a push frame, 16 is a pipe jacking steel plate, 17 is a shield tunneling machine receiving base and guide rail structure, 18 is a shield receiving well, 19 is a pipe jacking reaction frame, 20 is a pipe jacking machine receiving base and guide rail structure, 21 is a negative ring segment, 22 is a shield reaction frame, and 23 is a shield steel plate.
Detailed Description
In order that the above-recited objects, features and advantages of the present invention will become more readily apparent, a more particular description of the invention will be rendered by reference to the appended drawings.
In the following description, specific details are set forth in order to provide a thorough understanding of the present invention. The present invention may be embodied in many other forms than those herein described, and those skilled in the art may readily devise numerous other arrangements that do not depart from the spirit of the invention. Therefore, the present invention is not limited by the specific embodiments disclosed below.
The invention provides a variable section tunnel construction method, which is shown in figure 1 and comprises the following steps:
And S100, constructing a first section of tunnel through a first heading machine.
And S200, setting a first receiving well for receiving the first heading machine at the end position of the first section of tunnel.
S300, in the first receiving well, the first heading machine is detached and replaced by the second heading machine. The first heading machine and the second heading machine can be different types of heading machines or the same type of heading machines with cutterheads of different diameters. For example, the first heading machine may be a shield tunneling machine, the second heading machine may be a pipe push bench, and the diameters of the cutter heads of the two may be different. The construction modes of small-diameter shield to large-diameter pipe jacking, large-diameter pipe jacking to small-diameter shield, large-diameter shield to small-diameter pipe jacking, small-diameter pipe jacking to large-diameter shield and the like, and even the conversion of the shield to the pipe jacking with the same section size can be realized. Besides, the first heading machine can be detached and replaced by a second heading machine which can be constructed into different section shapes, such as the conversion of round shield-rectangular pipe jacking equipment with different sizes or the same size.
S400, converting the first receiving well into an originating well of a second heading machine. The functions of receiving and starting can be realized through the same working well, so that the purposes of reducing the construction cost and improving the construction efficiency are achieved.
S500, constructing a second section of tunnel through a second heading machine.
And S600, setting a second receiving well for receiving a second heading machine at the end position of the second section of tunnel. When the number of construction sections exceeds two, the steps can be repeated to achieve the purpose of continuous construction.
The tunnel construction method provided by the embodiment of the invention can be applied to subway tunnel construction and station platform integrated non-excavation construction, and comprises construction from a subway section shield tunnel to a station platform top pipe tunnel and construction from a subway station platform top pipe tunnel to a section shield tunnel, wherein the section size of the station platform top pipe tunnel I is larger than the section size of the section shield tunnel II as shown in figure 2.
1. Construction of a subway section shield tunnel to a station platform top pipe tunnel comprises the following steps:
Arranging a shield receiving well 18 at the end position of the shield segment a, backfilling a structural bottom plate of the receiving well by adopting C35 concrete, and finishing the reinforcement of the soil body of the receiving portal;
Performing shield attitude re-checking measurement, arranging a shield machine receiving base and a guide rail structure 17 in a shield receiving well 18 according to the elevation of a receiving tunnel portal and the central elevation of the shield machine, and performing elevation re-checking after the shield machine is installed;
Chiseling a shield receiving tunnel portal, and installing a receiving tunnel portal waterproof device;
Constructing the section tunnel through a shield tunneling machine;
After the construction of the shield segment a is completed, the shield machine is received through a shield receiving well, and the shield machine is disassembled and replaced into a pipe jacking machine, as shown in fig. 3 and 4, the method specifically comprises the steps of removing unnecessary parts of the pipe jacking machine such as a front shield 2, a middle shield 3 and a shield tail 4 of the shield machine, a pipe segment erector 7, a shield jack 12 and the like, and reserving the needed parts of the pipe jacking machine such as a shield machine cutterhead 1, a main driving structure 8, a screw conveyor 5 and the like;
The shield receiving base and the guide rail structure 17 are adjusted to be used for starting a pipe jacking machine, a front end shell 9 is arranged at the front end of the shield machine, a rear end shell 10 is arranged at the rear end of the shield machine, and the shield machine cutterhead 1 is expanded into a large-diameter pipe jacking machine cutterhead 14;
converting the shield receiving well 18 into a pipe-jacking initiation well, as shown in fig. 5, specifically includes:
A top pipe reaction frame 19 is arranged at a hole outlet A of the shield tunneling machine, a top pipe steel plate 16 is padded behind the top pipe reaction frame 19, the top pipe steel plate 16 is guaranteed to be attached to the surface of a well wall of a top pipe starting well, otherwise, high-strength concrete is poured in a gap to ensure that the stress of a back wall is uniform during top pipe construction, and the top pipe reaction frame 19 not only has enough compressive strength, but also can be adjusted in size according to actual needs so as to adapt to shield receiving wells with different sizes;
Installing a pipe jacking jack 12 to provide advancing power for pipe jacking construction, wherein a hydraulic pump station for a pipe jacking machine adopts a hydraulic pump station of an original shield machine, debugging the whole machine after the installation is finished, and entering the next working procedure after the complete machine is qualified;
installing a sealing curtain cloth rubber plate of the tunnel portal, cleaning the pre-buried bolt holes at the opening of the hole, installing an initial hole curtain cloth rubber plate, a circular plate and the like;
after the precipitation construction outside the pit, arranging horizontal exploratory holes in the range of the opening, checking the reinforcing body quality and the condition of flowing water and sand with errors, ensuring that the exploratory holes are good, no water and sediment flow out, and starting the pipe jacking to start the opening to break, wherein the opening is chiseled from top to bottom;
Thixotropic slurry is injected, and the thixotropic slurry is injected to the outer wall of the pipe joint through a reserved grouting hole of the pipe joint, so that a complete slurry sleeve is formed on the outer wall of the pipe joint 11 of the jacking pipe;
And installing a thrust frame 15, hoisting the jacking pipe section 11, installing a jacking iron 13, and starting jacking construction on the jacking pipe section b after debugging the pipe jacking machine.
2. Construction from a subway station platform pipe jacking tunnel to an interval shield tunnel comprises the following steps:
a pipe jacking receiving well is arranged at the end position of the pipe jacking section b;
in the pipe jacking receiving well, a pipe jacking machine receiving base and a guide rail structure 20 are arranged for the pipe jacking machine to go out of the tunnel;
Constructing a platform through a pipe jacking machine;
after the construction of the top pipe section b is completed and the top pipe bench is discharged to reach a top pipe receiving well, the top pipe bench is disassembled and replaced into a shield machine, as shown in fig. 3 and 4, and the method specifically comprises the steps of disassembling an outer shell of the top pipe bench, adjusting a top pipe cutter 14 into a small-diameter shield cutter 1, and installing a front shield 2, a middle shield 3, a shell of a shield tail 4, a segment erector 7, a shield jack 6 and the like of the shield machine;
Converting the pipe jacking receiving well into a shield starting well, and adjusting the pipe jacking machine receiving base and the guide rail structure 20 to be used for starting of the shield machine;
stratum reinforcement of a shield starting hole;
The shield starting hole is chiseled and the hole sealing device is installed;
An originating guide rail is arranged in the originating tunnel opening of the shield, and a shield reaction frame 22 and a shield steel plate 23 are arranged at the position B of the outlet tunnel opening of the jacking pipe, as shown in FIG. 6;
The negative ring segment 21 is installed in preparation for starting the shield tunneling construction.
The pipe jacking construction and the shield construction are common non-excavation construction technologies in the construction of facilities, and are widely used for laying various tunnels and underground pipelines. The pushing device of the shield tunneling machine is arranged in front, so that the shield tunneling machine is flexible, can perform long-distance construction, can have a certain curve radius, and the push bench is opposite, the push force of the push bench increases along with the increase of the construction distance, and the push force of the shield tunneling is theoretically unchanged along with the distance, so that a tunnel is constructed in a section by adopting a shield tunneling method during subway engineering construction. The invention can realize the expansion construction from the small-size section tunnel to the large-section platform by utilizing the advantages of two non-excavation technologies of shield construction and pipe jacking construction, can finish the adjustment and conversion of equipment by utilizing the prior receiving well structure after the construction of the previous section is finished, and uses the prior receiving well for the originating well of the next section of engineering.
In one embodiment of the present invention, two tunnel lines each including a platform may be constructed by the above construction method, and as shown in fig. 7, the two lines are preferably parallel to each other, and may be constructed sequentially or simultaneously, and after the construction is completed, the two platforms are dug by a dug method to form a large-section platform. The construction process comprises the following steps:
Drilling, grouting and reinforcing a part III to be dug at the platform, and selecting support measures such as advance small-conduit grouting, a pipe curtain method and the like according to the specific spacing of double lines and the quality of surrounding soil mass, so that the construction safety is ensured;
the mechanical breaking platform needs to expand the pipe segment of digging the part, in order to avoid the influence on the structural stability of the pipe segment in the mechanical breaking process, the chiseling sequence is carried out from top to bottom, and concrete is chiseled off and reinforcing steel bars are cut off in a partitioning mode.
After the pipe-jacking segment is broken, the primary support is constructed in a mode of grid arch centering, shotcrete, connecting ribs and reinforcing steel meshes, and waterproof layer and secondary lining construction are carried out after the expansion and excavation.
According to the embodiment, the soil body between the two formed platform tunnels is supported and excavated in a hidden mode, so that the construction process of the large-section station platform is formed, the influence of environment and traffic can be reduced, the construction period is shortened, and the construction risk is reduced.
The tunnel construction method provided by the invention can be applied to underground tunnel engineering such as inter-city railway tunnels and station structures thereof, variable-diameter underground water delivery tunnels, Y-shaped tunnels and the like besides being applied to subway tunnel construction and station platform integrated non-excavation construction. The following description will be given by taking shield-shield tunnel reducing construction as an example:
setting a receiving well at a position where diameter-changing construction is required;
after the construction of the previous shield is finished, the shield machine is received in a receiving well, and a receiving base and a guide rail structure of the shield machine are adjusted to be used for starting the shield machine of the next section of tunnel;
Finishing adjustment of cutterheads with different sizes in a receiving well, and expanding or shrinking the diameters of a front shield, a middle shield and a tail of a shield machine;
and installing a reaction frame structure suitable for the construction of the next section of shield machine, debugging equipment, and preparing for the construction of the next section of shield tunnel with different sizes.
The previous description of the disclosed embodiments is provided to enable any person skilled in the art to make or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the invention. Thus, the present invention is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (4)

1.一种变断面隧道施工方法,其特征在于,包括:1. A variable cross-section tunnel construction method, characterized by comprising: 通过第一掘进机施工第一段隧道;Construction of the first tunnel section by the first tunnel boring machine; 在所述第一段隧道的结束位置设置用于接收所述第一掘进机的第一接收井;A first receiving shaft for receiving the first tunnel boring machine is provided at the end position of the first tunnel section; 在所述第一接收井内,将所述第一掘进机拆换为第二掘进机,所述第一掘进机和所述第二掘进机的施工断面尺寸不同;In the first receiving shaft, the first tunnel boring machine is replaced with a second tunnel boring machine, and the construction section sizes of the first tunnel boring machine and the second tunnel boring machine are different; 将所述第一接收井转换为所述第二掘进机的始发井;Converting the first receiving shaft into a launching shaft of the second tunnel boring machine; 通过所述第二掘进机施工第二段隧道;constructing a second tunnel section by using the second tunnel boring machine; 在所述第二段隧道的结束位置设置用于接收所述第二掘进机的第二接收井;A second receiving shaft for receiving the second tunnel boring machine is provided at the end position of the second tunnel section; 所述第一掘进机和所述第二掘进机为不同类型掘进机、或不同直径刀盘的同类型掘进机;The first tunnel boring machine and the second tunnel boring machine are tunnel boring machines of different types, or tunnel boring machines of the same type with cutter heads of different diameters; 将所述第一掘进机拆换为第二掘进机,具体包括:将所述第一掘进机的刀盘替换为与其直径不同的刀盘,以拆换为第二掘进机,或将所述第一掘进机拆换为可施工出与其不同断面形状的第二掘进机;Replacing the first tunnel boring machine with a second tunnel boring machine specifically includes: replacing the cutterhead of the first tunnel boring machine with a cutterhead having a different diameter from the first tunnel boring machine to replace it with the second tunnel boring machine, or replacing the first tunnel boring machine with a second tunnel boring machine that can construct a cross-sectional shape different from the first tunnel boring machine; 所述第一掘进机为盾构机,所述第二掘进机为顶管机;将所述第一掘进机拆换为第二掘进机,具体包括:拆除所述盾构机的前盾、中盾、盾尾的外壳、管片拼装机、盾构千斤顶,保留盾构机刀盘、主驱动结构和螺旋输送机,在所述盾构机的前端安装前端壳体,在后端安装后端壳体,将所述盾构机刀盘扩展为大直径的顶管机刀盘;The first tunnel boring machine is a shield machine, and the second tunnel boring machine is a pipe jacking machine; replacing the first tunnel boring machine with the second tunnel boring machine specifically includes: removing the outer shells of the front shield, middle shield, and tail shield of the shield machine, the segment assembler, and the shield jack, retaining the shield machine cutter head, the main drive structure, and the screw conveyor, installing a front end shell at the front end of the shield machine, installing a rear end shell at the rear end, and expanding the shield machine cutter head into a large-diameter pipe jacking machine cutter head; 将所述第一接收井转换为所述第二掘进机的始发井,具体包括:在所述第一接收井设置顶管反力架、顶管钢板、顶管千斤顶设备,并调整所述第一接收井内的接收基座和导轨结构,用于所述顶管机的始发;Converting the first receiving well into a launching well of the second tunnel boring machine specifically includes: setting a jacking reaction frame, a jacking steel plate, and a jacking jack device in the first receiving well, and adjusting a receiving base and a guide rail structure in the first receiving well for launching the jacking machine; 或者,所述第一掘进机为顶管机,所述第二掘进机为盾构机;将所述第一掘进机拆换为第二掘进机,具体包括:拆除所述顶管机的外部壳体,将顶管刀盘调整为小直径的盾构刀盘,并安装所述盾构机的前盾、中盾、盾尾的外壳、管片拼装机、盾构千斤顶;Alternatively, the first tunnel boring machine is a pipe jacking machine, and the second tunnel boring machine is a shield machine; replacing the first tunnel boring machine with the second tunnel boring machine specifically comprises: removing the outer shell of the pipe jacking machine, adjusting the pipe jacking cutter head to a shield cutter head with a small diameter, and installing the outer shells of the front shield, middle shield, and tail shield of the shield machine, a segment assembler, and a shield jack; 将所述第一接收井转换为所述第二掘进机的始发井,具体包括:在顶管出洞口位置安装盾构反力架、盾构钢板,并调整所述第一接收井内的顶管接收基座和导轨结构,用于所述盾构机的始发。Converting the first receiving shaft into the starting shaft of the second tunnel boring machine specifically includes: installing a shield reaction frame and a shield steel plate at the top pipe exit position, and adjusting the top pipe receiving base and guide rail structure in the first receiving shaft for the starting of the shield machine. 2.根据权利要求1所述的变断面隧道施工方法,其特征在于,施工两条均包括站台的隧道线路,采用暗挖法对两个站台进行扩挖,以形成一个大断面站台。2. The variable cross-section tunnel construction method according to claim 1 is characterized in that two tunnel lines, both including platforms, are constructed, and the two platforms are expanded by dark excavation to form a large cross-section platform. 3.根据权利要求2所述的变断面隧道施工方法,其特征在于,所述采用暗挖法对两个站台进行扩挖,具体包括:3. The variable cross-section tunnel construction method according to claim 2 is characterized in that the dark excavation method is used to expand the two platforms, specifically comprising: 对站台需要扩挖的部分进行钻孔注浆加固;Drill and grout reinforce the parts of the platform that need to be expanded; 机械破除站台需要扩挖部分的顶管管片。Mechanically break down the platform to expand the pipe segments required. 4.根据权利要求3所述的变断面隧道施工方法,其特征在于,在破除顶管管片之后,采用格栅拱架、喷射混凝土、连接筋和钢筋网的方式施工初期支护,扩挖之后进行防水层和二衬施工。4. The variable cross-section tunnel construction method according to claim 3 is characterized in that after breaking the top pipe segments, initial support is constructed by means of grid arch frame, shotcrete, connecting bars and steel mesh, and waterproof layer and secondary lining construction are carried out after expansion.
CN202210211699.0A 2022-03-04 2022-03-04 A variable cross-section tunnel construction method Active CN114562277B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210211699.0A CN114562277B (en) 2022-03-04 2022-03-04 A variable cross-section tunnel construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210211699.0A CN114562277B (en) 2022-03-04 2022-03-04 A variable cross-section tunnel construction method

Publications (2)

Publication Number Publication Date
CN114562277A CN114562277A (en) 2022-05-31
CN114562277B true CN114562277B (en) 2025-02-11

Family

ID=81717592

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210211699.0A Active CN114562277B (en) 2022-03-04 2022-03-04 A variable cross-section tunnel construction method

Country Status (1)

Country Link
CN (1) CN114562277B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116291497A (en) * 2022-09-09 2023-06-23 中铁工程装备集团有限公司 Variable-diameter tunnel construction method, system and shield equipment
CN116084976A (en) * 2022-09-09 2023-05-09 中铁工程装备集团有限公司 A variable-diameter tunnel construction method, system and shield equipment
CN116006197A (en) * 2022-09-09 2023-04-25 中铁工程装备集团有限公司 Variable-diameter tunnel construction method, system and shield equipment
CN116066136A (en) * 2023-02-23 2023-05-05 中铁工程装备集团有限公司 Underground station and construction method thereof

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08165894A (en) * 1994-12-12 1996-06-25 Minoru Yamamoto Profile section excavation tunnel machine
CN111810184A (en) * 2020-05-28 2020-10-23 中铁十四局集团第三工程有限公司 A kind of variable section tunnel construction method

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07145699A (en) * 1993-11-24 1995-06-06 Nishimatsu Constr Co Ltd Tunnel shield construction method with varying cross-sectional diameter and its shield machine
JP3151357B2 (en) * 1994-08-11 2001-04-03 帝都高速度交通営団 Tunnel construction method
CN2497043Y (en) * 2001-07-17 2002-06-26 天津第二市政公路工程有限公司 Replaceable earth-pressure balancing pipe-jacking entry-driving machine
CN104265321B (en) * 2014-08-06 2016-04-13 上海隧道工程有限公司 Ultra-large type tunneling boring rectangular top pipe tunneling construction method
CN105041327B (en) * 2015-08-27 2017-12-19 北京建工土木工程有限公司 Bored tunnel is counter to dig shield method of reseptance
CN110966009B (en) * 2019-12-31 2022-02-18 中铁第四勘察设计院集团有限公司 Construction method of bifurcated tunnel

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08165894A (en) * 1994-12-12 1996-06-25 Minoru Yamamoto Profile section excavation tunnel machine
CN111810184A (en) * 2020-05-28 2020-10-23 中铁十四局集团第三工程有限公司 A kind of variable section tunnel construction method

Also Published As

Publication number Publication date
CN114562277A (en) 2022-05-31

Similar Documents

Publication Publication Date Title
CN114562277B (en) A variable cross-section tunnel construction method
CN109356596B (en) Method for launching and receiving shield tunneling machine by utilizing recyclable underground continuous wall and steel sleeve
WO2022083096A1 (en) Tunnel excavation method for upper-soft and lower-hard stratum
CN110924961B (en) Construction method for starting shield tunneling machine to pass through existing station
CN111396067B (en) Comprehensive shield steel sleeve receiving construction method in complex environment
CN112160755B (en) Subway line construction method for expanding excavation station after shield tunnel construction in advance
CN108661655A (en) Large-section U-shaped earth pressure balance shield tunnel construction method based on U-shaped shield machine
CN106761814A (en) A kind of pipe curtain and bamboo reinforcement grouted anchor bar combined retaining structure and method
CN114575852A (en) A kind of underground excavation construction method for excavating station on shield tunnel of subway station
CN112031814B (en) A kind of construction method of entering the hole through the shallow heavy load highway
CN211598669U (en) Tunnel collapse cavity backfill structure
CN111075456B (en) Full-section construction structure and construction method for large-section weak stratum tunnel
CN114109421B (en) Construction method for open TBM through long fault fracture zone
CN119021707B (en) A complete set of equipment and construction method for updating the original well of small-diameter rainwater and sewage pipelines
CN113513322A (en) Soil pressure balance jacking construction method for water-rich shallow-buried large-section rectangular jacking pipe
CN111997649A (en) Tunnel-first post-station underground excavation station segment removal construction method and segment removal tool used by same
CN114542083B (en) Construction process method of shallow-buried bias large-section highway tunnel single-side wall pilot pit method
CN106640098B (en) Subway tunnel shield construction method
CN214273663U (en) Weak surrounding rock tunnel geological disaster punishment structure
CN109119943A (en) System of laying optimization method of the cable at push pipe both ends
CN205895258U (en) A sectional type tunnel supporting equips for weak surrounding rock
CN115075832A (en) A construction method for shield machine to get out of trouble
CN115341910A (en) A tunnel construction method with complex geological conditions under expressway and tunnel
CN114592892A (en) Implementation method for pulling out anchor cable of shield tunnel in steel sleeve in soft soil area
CN114439481A (en) Variable cross-section excavation method for underground tunnel with section from small to large

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant