CN114439219A - A retractable floor support truss - Google Patents
A retractable floor support truss Download PDFInfo
- Publication number
- CN114439219A CN114439219A CN202210007923.4A CN202210007923A CN114439219A CN 114439219 A CN114439219 A CN 114439219A CN 202210007923 A CN202210007923 A CN 202210007923A CN 114439219 A CN114439219 A CN 114439219A
- Authority
- CN
- China
- Prior art keywords
- truss
- upper chord
- support
- rectangular tube
- middle section
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/36—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
- E04G11/48—Supporting structures for shutterings or frames for floors or roofs
- E04G11/50—Girders, beams, or the like as supporting members for forms
- E04G11/52—Girders, beams, or the like as supporting members for forms of several units arranged one after another
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/36—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
- E04G11/48—Supporting structures for shutterings or frames for floors or roofs
- E04G11/50—Girders, beams, or the like as supporting members for forms
- E04G11/54—Girders, beams, or the like as supporting members for forms of extensible type, with or without adjustable supporting shoes, fishplates, or the like
- E04G11/56—Girders, beams, or the like as supporting members for forms of extensible type, with or without adjustable supporting shoes, fishplates, or the like of telescopic type
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G17/00—Connecting or other auxiliary members for forms, falsework structures, or shutterings
- E04G17/18—Devices for suspending or anchoring form elements to girders placed in ceilings, e.g. hangers
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
发明公开了一种可伸缩楼板支撑桁架,属于建筑工程的施工方法与措施技术领域。该支撑桁架由上弦中间段矩管、倒三角架、下弦紧线器和桁架支座组成。倒三角架通过矩管焊接而成,结构更稳定,倒三角架上弦杆矩管内孔尺寸与上弦中间段方管一致,上弦中间段矩管每个一段距离钻连接孔,上弦中间段矩管穿入倒三角架上弦杆矩管带连接孔一端,通过插销固定。倒三角架下部腹杆交点与下弦紧线器吊钩连接,实现桁架起拱。倒三角架另一端焊接凹槽连接件,桁架支座通过螺栓与腹板开孔钢梁连接,桁架支座焊接螺母连接螺栓,螺栓上部嵌入凹槽顶起支撑桁架。螺栓通过螺母可以调节支撑桁架高度。通过两侧螺栓顶部在连接件凹槽内可调距离大于上弦中间段矩管钻孔距离和下弦紧线器设计使支撑桁架在一定范围内实现任意尺寸伸缩。
The invention discloses a retractable floor support truss, which belongs to the technical field of construction methods and measures for construction projects. The supporting truss is composed of a rectangular tube in the middle section of the upper chord, an inverted tripod, a lower chord tensioner and a truss support. The inverted tripod is welded by the rectangular tube, and the structure is more stable. The size of the inner hole of the rectangular tube of the upper chord of the inverted tripod is the same as that of the square tube in the middle section of the upper chord. Connecting holes are drilled for each section of the rectangular tube in the middle section of the upper chord, and the rectangular tube in the middle section of the upper chord passes through Insert one end of the upper chord rectangular tube with the connecting hole of the inverted tripod and fix it with a bolt. The intersection point of the lower web rod of the inverted tripod is connected with the hook of the lower string tensioner to realize the truss arching. The other end of the inverted tripod is welded with a groove connector, the truss support is connected to the steel beam with the web opening through bolts, the truss support is welded with nuts to connect the bolts, and the upper part of the bolt is embedded in the groove to support the truss. Bolts through nuts can adjust the height of the support truss. The adjustable distance between the tops of the bolts on both sides in the groove of the connector is greater than the drilling distance of the rectangular tube in the middle section of the upper chord and the design of the tensioner of the lower chord, so that the support truss can achieve any size expansion and contraction within a certain range.
Description
技术领域technical field
本发明涉及建筑结构技术领域,尤其涉及一种楼板支撑桁架。The invention relates to the technical field of building structures, in particular to a floor support truss.
背景技术Background technique
随着我国住宅制度改革体制的日益落实,经济适用房、商品住宅产业发展极为迅速,民用住宅建筑的施工建设也越来越常见。在当今的住宅楼施工建设中,楼面大多都是以现浇混凝土结构为主的,同时整个工程结构也多数以高层框架结构、混凝土结构为主。在工程项目中,因为现浇混凝土结构施工后期经常会受到各种原因的影响而产生一定的质量问题,为此在施工中我们有必要对工程施工进行严格分析,针对混凝土施工质量问题提出应对方法和预防措施,以保证工程的正常开展,为建设高质、安全、可靠的民用住宅楼提供扎实的理论基础。With the increasing implementation of my country's housing system reform system, the affordable housing and commercial housing industries have developed extremely rapidly, and the construction of civil residential buildings has become more and more common. In today's residential building construction, most of the floors are based on cast-in-place concrete structures, and the entire engineering structure is also dominated by high-rise frame structures and concrete structures. In engineering projects, because the cast-in-place concrete structure is often affected by various reasons in the later stage of construction, certain quality problems will occur. Therefore, it is necessary to strictly analyze the engineering construction during the construction, and propose countermeasures for the quality problems of concrete construction. and preventive measures to ensure the normal development of the project and provide a solid theoretical basis for the construction of high-quality, safe and reliable civil residential buildings.
现浇钢筋混凝土楼板是指在现场依照设计位置,进行支模、绑扎钢筋、浇筑混凝土,经养护、拆模板而制作的楼板。传统建筑在楼板工程施工时,一般事先搭设满堂脚手架,在脚手架上铺设模板、钢筋网,再浇捣混凝土,待混凝土达到一定强度时,拆除脚手架与模板。这种建筑施工方法使用范围比较广泛,但需要搭设满堂脚手架,不能多层同时施工,施工进度慢,占用大量周转材料,施工成本高,不适合建筑装配化发展要求。The cast-in-place reinforced concrete floor refers to the floor that is made by supporting the formwork, binding the steel bars, pouring the concrete, curing and dismantling the formwork according to the design position on site. During the construction of floor slab engineering in traditional buildings, scaffolding is generally erected in advance, formwork and steel mesh are laid on the scaffolding, and then concrete is poured. When the concrete reaches a certain strength, the scaffolding and formwork are removed. This building construction method is widely used, but it needs to set up full scaffolding, and cannot construct multiple layers at the same time. The construction progress is slow, it takes up a lot of turnover materials, and the construction cost is high, which is not suitable for the development requirements of building assembly.
发明内容SUMMARY OF THE INVENTION
本发明目的在于解决现有技术中存在的上述技术问题,提供一种可伸缩楼板支撑桁架,适应于一定范围的间距,通用性较好,占用较少周转材料,施工成本低,适合建筑装配化发展要求。The purpose of the present invention is to solve the above-mentioned technical problems existing in the prior art, and to provide a retractable floor support truss, which is suitable for a certain range of spacing, has good versatility, occupies less turnover materials, and has low construction cost, which is suitable for building assembly. development requirements.
为了解决上述技术问题,本发明采用如下技术方案:In order to solve the above-mentioned technical problems, the present invention adopts the following technical solutions:
一种可伸缩楼板支撑桁架,其特征在于:包括上弦中间段矩管、焊接矩管倒三角架、下弦紧线器和桁架支座,所述倒三角架之间所述上弦中间段矩管穿入所述倒三角架上弦矩管内通过所述插销固定;所述支撑桁架下弦设置紧线器,所述紧线器吊钩与所述倒三角架腹杆交点连接。所述支撑桁架端部设置所述凹槽连接件,所述钢梁腹板用螺栓连接所述桁架支座。A retractable floor slab support truss is characterized in that it includes a rectangular tube in the middle section of the upper chord, an inverted triangle of the welding rectangular tube, a wire tensioner for the lower chord and a truss support, and the rectangular tube in the middle section of the upper chord passes between the inverted triangles. The upper chord of the inverted tripod is inserted into the upper chord of the inverted tripod and fixed by the bolt; the lower chord of the supporting truss is provided with a thread tensioner, and the hook of the thread tensioner is connected with the intersection point of the web bar of the inverted tripod. The groove connector is provided at the end of the support truss, and the steel beam web is connected to the truss support by bolts.
所述桁架支座焊接所述螺母连接所述螺栓,所述螺栓上部嵌入所述凹槽连接件顶起所述支撑桁架。The truss support is welded with the nut to connect the bolt, and the upper part of the bolt is embedded in the groove connecting piece to lift the supporting truss.
所述倒三角架由矩管焊接构成。The inverted tripod is formed by welding rectangular tubes.
所述上弦中间段矩管穿入所述倒三角架上弦矩管内通过所述插销固定。The upper chord middle section rectangular tube is inserted into the upper chord rectangular tube of the inverted tripod and is fixed by the latch.
所述支撑桁架下弦设置紧线器,所述紧线器吊钩与所述倒三角架腹杆交点连接。A wire tensioner is arranged on the lower chord of the supporting truss, and the hook of the wire tensioner is connected with the intersection point of the web bar of the inverted tripod.
所述上弦中间段矩管每个一段距离钻连接孔,两侧所述螺栓顶部在所述凹槽连接件内可调距离大于所述上弦中间段矩管钻孔距离。The upper chord middle section rectangular tube is drilled with connecting holes at each distance, and the adjustable distance of the bolt tops on both sides in the groove connecting piece is greater than the drilling distance of the upper chord middle section rectangular tube.
本发明由于采用了上述技术方案,具有以下有益效果:The present invention has the following beneficial effects due to the adoption of the above-mentioned technical solutions:
1、本发明中上弦中间段矩管每隔一段距离设计一个连接孔,使上弦中间段矩管与倒三角架上弦矩管每隔该段距离可以通过插销连接。两侧螺栓顶部在凹槽连接件内可以活动,活动范围大于上弦中间段矩管连接孔距离,使支撑桁架在一定范围内任意长度可以调整。支撑桁架适用于各种板跨情况,是复用率更高,降低单次使用成本。1. In the present invention, the upper chord middle section rectangular tube is designed with a connecting hole at intervals, so that the upper chord middle section rectangular tube and the inverted tripod upper chord rectangular tube can be connected by bolts at intervals of this distance. The tops of the bolts on both sides can be moved in the groove connecting piece, and the moving range is greater than the distance between the connecting holes of the rectangular tube in the middle section of the upper chord, so that the supporting truss can be adjusted at any length within a certain range. The support truss is suitable for various slab span situations, which has a higher reuse rate and reduces the single-use cost.
2、本发明桁架支座焊接螺母连接螺栓,螺栓上部嵌入所述凹槽连接件顶起支撑桁架。在一定范围内高度可以调整,便于楼板调平,使施工质量更高,便于桁架拆卸。2. The welding nut connecting bolt of the truss support of the present invention, the upper part of the bolt is embedded in the groove connecting piece to jack up the supporting truss. The height can be adjusted within a certain range, which is convenient for floor leveling, which makes the construction quality higher and facilitates the dismantling of the truss.
3、本发明倒三角架由矩管焊接构成和上弦中间段矩管穿入倒三角架上弦矩管设计,使施工速度更快,结构强度更高。3. The inverted tripod of the present invention is formed by welding a rectangular tube, and the middle section of the upper chord is inserted into the upper chord rectangular tube of the inverted tripod, so that the construction speed is faster and the structural strength is higher.
4、本发明支撑桁架下弦设置紧线器,紧线器吊钩与倒三角架腹杆交点连接。通过紧线器实现支撑桁架起拱,使得混凝土浇筑后保持支撑桁架没有下挠,且调节更便捷。4. In the present invention, the lower chord of the supporting truss is provided with a thread tightening device, and the hook of the thread tightening device is connected with the intersection point of the web bar of the inverted tripod. The arching of the support truss is realized by the wire tensioner, so that the support truss is not bent downward after the concrete is poured, and the adjustment is more convenient.
附图说明Description of drawings
下面结合附图对本发明作进一步说明:The present invention will be further described below in conjunction with the accompanying drawings:
图1为本发明一种可伸缩楼板支撑桁架的结构示意图;1 is a schematic structural diagram of a retractable floor support truss according to the present invention;
图中,1-倒三角架; 2-钢梁;3-上弦中间段矩管;31-上弦中间段矩管连接孔;4-紧线器;5-支撑桁架支座;6-插销。In the figure, 1 - inverted tripod; 2 - steel beam; 3 - upper chord middle section rectangular tube; 31 - upper chord middle section rectangular tube connecting hole; 4 - wire tensioner; 5 - support truss support; 6 - latch.
图2为由矩管焊接的倒三角架结构示意图;Figure 2 is a schematic diagram of the structure of an inverted tripod welded by a rectangular tube;
图中,11-倒三角架上弦矩管;12-倒三角架腹杆;13-凹槽连接件。In the figure, 11 - upper chord tube of inverted tripod; 12 - web bar of inverted tripod; 13 - groove connector.
图3为本发明支撑桁架与支撑桁架支座连接示意图;FIG. 3 is a schematic diagram of the connection between the supporting truss and the supporting truss bearing of the present invention;
图中,11-倒三角架上弦矩管;12-倒三角架腹杆;13-凹槽连接件;21-钢梁腹板;51-支撑桁架支座螺栓;52-支撑桁架支座螺母。In the figure, 11 - upper chord moment tube of inverted tripod; 12 - web of inverted tripod; 13 - groove connector; 21 - web of steel beam; 51 - support truss bearing bolt; 52 - supporting truss bearing nut.
具体实施方式Detailed ways
如图1所示,为本发明一种可伸缩楼板支撑桁架,包括矩管焊接倒三角架1、钢梁2、上弦中间段矩管3、紧线器4、支撑桁架支座5和插销6。As shown in FIG. 1, it is a telescopic floor support truss of the present invention, including a rectangular tube welding inverted tripod 1, a
如图2所示,为本发明倒三角架由矩管焊接而成,包括倒三角架上弦矩管11、倒三角架腹杆12和凹槽连接件13。As shown in FIG. 2 , the inverted tripod of the present invention is welded by a rectangular tube, including an inverted tripod upper chord
倒三角架1之间上弦中间段矩管3穿入倒三角架上弦矩管11内通过插销6固定;支撑桁架下弦设置紧线器4,紧线器4吊钩与倒三角架腹杆12交点连接。支撑桁架端部设置所述凹槽连接件13,钢梁腹板21用螺栓连接所述支撑桁架支座5。Rectangular tube 3 in the middle section of the upper chord between the inverted tripods 1 is inserted into the upper chord
如图3所示,本发明支撑桁架与支撑桁架支座5连接示意图,支撑桁架支座5包括螺母52和螺栓51。As shown in FIG. 3 , a schematic diagram of the connection between the support truss of the present invention and the
支撑桁架支座5焊接螺母52连接螺栓51,螺栓51上部嵌入所述凹槽连接件13顶起所述支撑桁架。The
上弦中间段矩管3穿入倒三角架上弦矩管11内通过插销6固定。The upper chord middle section rectangular tube 3 penetrates into the upper chord
支撑桁架下弦设置紧线器4,紧线器4吊钩与倒三角架腹杆12交点连接。A wire tensioner 4 is arranged on the lower chord of the supporting truss, and the hook of the wire tensioner 4 is connected to the intersection point of the
上弦中间段矩管3每个一段距离钻连接孔31,两侧螺栓51顶部在所述凹槽连接件13内可调距离大于所述上弦中间段矩管钻孔31距离。The connecting
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210007923.4A CN114439219A (en) | 2022-01-06 | 2022-01-06 | A retractable floor support truss |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210007923.4A CN114439219A (en) | 2022-01-06 | 2022-01-06 | A retractable floor support truss |
Publications (1)
Publication Number | Publication Date |
---|---|
CN114439219A true CN114439219A (en) | 2022-05-06 |
Family
ID=81365500
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210007923.4A Pending CN114439219A (en) | 2022-01-06 | 2022-01-06 | A retractable floor support truss |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114439219A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116677210A (en) * | 2023-05-16 | 2023-09-01 | 精工绿筑科技集团有限公司 | An installation process of a support frame applied to the construction of a prefabricated steel structure floor |
-
2022
- 2022-01-06 CN CN202210007923.4A patent/CN114439219A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116677210A (en) * | 2023-05-16 | 2023-09-01 | 精工绿筑科技集团有限公司 | An installation process of a support frame applied to the construction of a prefabricated steel structure floor |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108755439B (en) | Universal telescopic support frame suitable for V-shaped bridge piers and its installation method | |
CN111794485A (en) | Structure and method of a prefabricated external frameless construction protection platform for shear wall structure | |
CN206070796U (en) | A kind of vertical attachment means of prefabricated assembled shear wall slab | |
CN111173255A (en) | Single-layer overhanging protection platform foundation device | |
CN114439219A (en) | A retractable floor support truss | |
CN216239741U (en) | Formwork system of high-rise cantilever concrete structure | |
CN218990875U (en) | Assembled triangular truss cantilever support frame system | |
CN217106134U (en) | Telescopic floor slab supporting truss | |
CN217028931U (en) | Steel pipe concrete support assembly | |
CN116657875A (en) | Cantilever steel structure construction platform with formwork system and construction method | |
CN212002201U (en) | Single-layer overhanging protection platform foundation structure | |
CN209974169U (en) | Swing arm tower machine beam climbing device | |
CN112127620A (en) | A silo cone shell support formwork platform and its erection method | |
CN220226165U (en) | Cantilever formwork system | |
CN221856179U (en) | An adjustable support frame for installing super-high building steel beams | |
CN111733691A (en) | A connection structure and method of prefabricated column and pile foundation | |
CN110629683A (en) | Composite prefabricated bridge cantilever construction bracket | |
CN221372189U (en) | Support system for open cut tunnel unilateral formwork | |
CN219585711U (en) | Horizontal control device for embedded section of tower crane | |
CN112894743B (en) | A kind of anti-overturning device of concrete prefabricated T beam | |
CN216340936U (en) | A combined reinforcement structure for door and window openings | |
CN119981414A (en) | An unconventional cantilever scaffold and its erection method | |
CN219653947U (en) | Girder steel and concrete PC roof beam connection structure | |
CN223017705U (en) | Lattice column offset reinforcement components | |
CN221702730U (en) | Mounting structure of super high-rise high-altitude large-span prefabricated overhanging arc beam section |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20220506 |