CN114248344A - Tubular pile machine-shaping device for construction - Google Patents

Tubular pile machine-shaping device for construction Download PDF

Info

Publication number
CN114248344A
CN114248344A CN202011021802.2A CN202011021802A CN114248344A CN 114248344 A CN114248344 A CN 114248344A CN 202011021802 A CN202011021802 A CN 202011021802A CN 114248344 A CN114248344 A CN 114248344A
Authority
CN
China
Prior art keywords
block
base
screw
limit
building construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202011021802.2A
Other languages
Chinese (zh)
Other versions
CN114248344B (en
Inventor
罗芝棠
甘立华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Shuoxin New Materials Co.,Ltd.
Original Assignee
Huaihua Gangxiang Pipe Pile Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huaihua Gangxiang Pipe Pile Co ltd filed Critical Huaihua Gangxiang Pipe Pile Co ltd
Priority to CN202011021802.2A priority Critical patent/CN114248344B/en
Publication of CN114248344A publication Critical patent/CN114248344A/en
Application granted granted Critical
Publication of CN114248344B publication Critical patent/CN114248344B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B21/00Methods or machines specially adapted for the production of tubular articles
    • B28B21/02Methods or machines specially adapted for the production of tubular articles by casting into moulds
    • B28B21/10Methods or machines specially adapted for the production of tubular articles by casting into moulds using compacting means
    • B28B21/22Methods or machines specially adapted for the production of tubular articles by casting into moulds using compacting means using rotatable mould or core parts
    • B28B21/30Centrifugal moulding
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B17/00Details of, or accessories for, apparatus for shaping the material; Auxiliary measures taken in connection with such shaping
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B17/00Details of, or accessories for, apparatus for shaping the material; Auxiliary measures taken in connection with such shaping
    • B28B17/04Exhausting or laying dust

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Manufacturing & Machinery (AREA)
  • Centrifugal Separators (AREA)
  • Cleaning In General (AREA)

Abstract

本发明公开了一种建筑施工用管桩加工成型装置,包括底座、连接轴、转动轮,所述底座的底部设有基座,所述底座相背的表面上均对称设有限位块,所述基座的侧面设有固定块,所述固定块上设有第一螺杆,所述第一螺杆贯穿基座的端部上设有压块,所述基座相背的表面上均设有两个稳固块,所述稳固块上设有第二螺杆,所述第二螺杆嵌入稳固块内的端部设有卡块,所述基座的内表面设有固定梁,所述固定梁的表面开设有两个限位槽;限位块位于固定梁内,卡块先穿过基座后嵌入限位块上的卡槽,限位块被限位固定,使底座被限位固定,便于安装、拆卸底座,擦拭垫擦拭清理转动轮表面的灰尘杂质,避免转动轮表面因沾染灰尘杂质而增加磨损程度。

Figure 202011021802

The invention discloses a pipe pile processing and forming device for building construction, comprising a base, a connecting shaft and a rotating wheel. The bottom of the base is provided with a base, and the opposite surfaces of the base are symmetrically provided with limit blocks. The side of the base is provided with a fixing block, the fixing block is provided with a first screw, the end of the first screw passing through the base is provided with a pressing block, and the opposite surfaces of the base are provided with Two stabilizing blocks, the second threaded rod is provided on the stabilizing block, the end of the second threaded rod embedded in the stabilizing block is provided with a clamping block, the inner surface of the base is provided with a fixing beam, and the There are two limit grooves on the surface; the limit block is located in the fixed beam, the block first passes through the base and then is inserted into the groove on the limit block, the limit block is limited and fixed, so that the base is limited and fixed, which is convenient for Install and disassemble the base, wipe the dust and impurities on the surface of the rotating wheel with the wiping pad, so as to prevent the surface of the rotating wheel from being contaminated with dust and impurities and increase the degree of wear.

Figure 202011021802

Description

Tubular pile machine-shaping device for construction
Technical Field
The invention belongs to the technical field of building construction material manufacturing and forming equipment, and particularly relates to a pipe pile processing and forming device for building construction.
Background
The centrifugal concrete pile (called prestressed pipe pile for short) has high bearing capacity, convenient construction and short construction period, and is suitable for basic engineering of various geological conditions. The pipe pile is formed by processing a centrifugal machine, the centrifugal machine is necessary equipment for manufacturing a centrifugal concrete pile, after a certain amount of steel bar frameworks and concrete are arranged on a centrifugal concrete pile die, the centrifugal machine drives the pipe pile die to rotate from slow to fast, the concrete is bonded with steel bars for a certain time under the action of centrifugal force in the pipe pile die and is tightly adsorbed on the inner wall of the steel die, and the pipe pile is formed after being compacted and maintained.
When the existing centrifugal machine is used for processing and forming a tubular pile, the riding wheel on the centrifugal machine is abraded, the centrifugal machine is not easy, convenient and flexible to mount and dismount, the riding wheel is stained with dust and impurities, and the abrasion degree of the riding wheel is increased.
Disclosure of Invention
The invention aims to provide a tubular pile processing and forming device for building construction, which solves the problems that when a tubular pile is processed and formed by a centrifugal machine provided in the background technology, a riding wheel on the centrifugal machine is abraded, the centrifugal machine is not simple, convenient and flexible to mount and dismount, the riding wheel is contaminated by dust and impurities, and the abrasion degree of the riding wheel is increased.
In order to achieve the purpose, the invention provides the following technical scheme: the utility model provides a tubular pile machine-shaping device for construction, includes base, connecting axle, rotates the wheel, the bottom of base is equipped with the base, the base is carried on the back mutually all the symmetry on the surface and is equipped with the stopper, the side of base is equipped with the fixed block, be equipped with first screw rod on the fixed block, first screw rod runs through and is equipped with the briquetting on the tip of base, the base is carried on the back mutually all is equipped with two firm pieces on the surface, be equipped with the second screw rod on the firm piece, the tip in the second screw rod embedding firm piece is equipped with the fixture block, the internal surface of base is equipped with fixed beam, two spacing grooves have been seted up on the surface of fixed beam, the inside of fixed beam one end is equipped with spring, movable block.
Preferably, the fixed block is of an L-shaped structure, the first screw rod is connected with the base and the fixed block in a screwing mode through threads, and the first screw rod is connected with the pressing block in a rotating mode.
Preferably, the base comprises a bottom horizontal plate and vertical plates at the sides of the four sides, sliding grooves are symmetrically formed in the bottom horizontal plate of the base, a convex column is arranged at the bottom of the pressing block, and the convex column is matched with the sliding grooves.
Preferably, the stabilizing block is of a hollow structure, the end part of the stabilizing block, far away from the base, is sealed, the second screw penetrates through the stabilizing block, the second screw is screwed with the stabilizing block through threads and is connected with the clamping block in a rotating mode, a through hole communicated with the limiting groove is formed in the base, and the clamping block is matched with the through hole.
Preferably, the inside of fixed beam one end is equipped with the slip chamber, spring one end and pedestal connection and the other end are connected with the fixed beam, the slip chamber communicates with close spacing groove.
Preferably, the limiting block is connected with the base in a welding mode, the limiting block is of an L-shaped structure, the limiting groove is of an L-shaped structure, the limiting block is matched with the limiting groove, a clamping groove is formed in the limiting block, and the clamping block is matched with the clamping groove.
Preferably, the intermediate position on the relative surface of base is equipped with the installation piece, be equipped with the slide bar on the installation piece, the top of slide bar is equipped with the connecting rod, all overlap on the both ends of connecting rod and be equipped with the pad of cleaning of semi-cylindrical shape, be equipped with the gag lever post on the installation piece.
Preferably, the surface of the mounting block is provided with a moving groove with an inverted T-shaped structure, the sliding rod is of a T-shaped structure and is matched with the moving groove, square holes are formed in the mounting block and the sliding rod, the limiting rod is matched with the square holes, the wiping pad is made of sponge materials, and when the limiting rod penetrates through the mounting block and the sliding rod, the wiping pad is tangent to the rotating wheel.
Compared with the prior art, the invention has the beneficial effects that:
1. through the installation piece, slide bar, connecting rod, gag lever post, the pad of cleaning that set up, the position of pad is cleaned in the regulation that can be simple and convenient, nimble, makes to clean the pad and rotate the wheel tangent, cleans the pad and cleans the dust impurity of clearance rotation wheel surface, avoids rotating the wheel surface and increasing the degree of wear because of being infected with dust impurity.
2. Through base, stopper, fixed beam, first screw rod, second screw rod, briquetting, the fixture block that sets up, the stopper is located the fixed beam, and the fixture block passes the draw-in groove on the base back embedding stopper earlier, and the stopper is spacing fixed, makes the base by spacing fixed, the installation of being convenient for, dismantles the base.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic top view of a base according to the present invention;
FIG. 3 is a schematic cross-sectional view of a fixed beam of the present invention;
FIG. 4 is a schematic front view of the fixing block according to the present invention;
FIG. 5 is a schematic top view of the mounting block of the present invention;
in the figure: 1. a base; 2. a connecting shaft; 3. a rotating wheel; 4. a limiting block; 5. a base; 6. a fixed block; 7. a first screw; 8. a stabilizing block; 9. a second screw; 10. mounting blocks; 11. a slide bar; 12. a connecting rod; 13. a limiting rod; 14. briquetting; 15. a fixed beam; 16. a clamping block; 17. a limiting groove; 18. a spring; 19. a moving block; 20. a card slot; 21. the pad is wiped.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1 to 5, the present invention provides a technical solution: a pipe pile processing and forming device for building construction comprises a base 1, a connecting shaft 2 and a rotating wheel 3, wherein a base 5 is arranged at the bottom of the base 1, limiting blocks 4 are symmetrically arranged on the surfaces of the opposite sides of the base 1, a fixing block 6 is arranged on the side surface of the base 5, a first screw 7 is arranged on the fixing block 6, a pressing block 14 is arranged at the end part of the first screw 7 penetrating through the base 5, two stabilizing blocks 8 are arranged on the surfaces of the opposite sides of the base 5, a second screw 9 is arranged on each stabilizing block 8, a clamping block 16 is arranged at the end part of each second screw 9 embedded into each stabilizing block 8, a fixing beam 15 is arranged on the inner surface of the base 5, two limiting grooves 17 are formed in the surface of each fixing beam 15, a spring 18 and a moving block 19 are arranged inside one end of each fixing beam 15, a first hand wheel on each first screw 7 rotates the first screw 7 clockwise from top to bottom, the first screw 7 drives the pressing block 14 to move, the base 1 is driven by the pressing block 14, the limiting block 4 is connected with the fixed beam 15 in a sliding clamping manner, one limiting block 4 drives the moving block 19, the spring 18 is in a contraction state, the second screw 9 rotates clockwise from top to bottom, the second screw 9 drives the clamping block 16 to slide towards the base 5, the clamping block 16 firstly penetrates through the base 5 and then is embedded into the clamping groove 20 on the limiting block 4, the limiting block 4 is limited and fixed, the base 1 is convenient to mount and dismount, the mounting block 10 is arranged at the middle position of the opposite surface of the base 5, the sliding rod 11 is arranged on the mounting block 10, the top end of the sliding rod 11 is provided with the connecting rod 12, the two ends of the connecting rod 12 are respectively sleeved with the semi-cylindrical wiping pad 21, the limiting rod 13 is arranged on the mounting block 10, the connecting rod 12 drives the wiping pad 21 to move, the wiping pad 21 is tangent to the rotating wheel 3, and the wiping pad 21 wipes and cleans dust and impurities on the surface of the rotating wheel 3, the abrasion degree of the surface of the rotating wheel 3 is prevented from being increased due to the contamination of dust and impurities.
In this embodiment, the fixing block 6 is an "L" shaped structure, the first screw 7 is screwed with the base 5 and the fixing block 6 through threads, the first screw 7 is rotatably connected with the pressing block 14, a first hand wheel is disposed on an exposed end of the first screw 7, the first screw 7 is rotated clockwise from top to bottom, and the pressing block 14 is driven by the first screw 7 to move.
In this embodiment, the base 5 includes the bottom horizontal plate and the vertical plate of four sides avris, and the spout has been seted up to the symmetry on the bottom horizontal plate of base 5, and briquetting 14 bottom is equipped with the projection, and the projection matches with the spout, and briquetting 14 is connected with the bottom horizontal plate slip block of base 5, and briquetting 14 is by spacing fixed, has guaranteed that briquetting 14 slides with stable state.
In this embodiment, the end portion of the stabilizing block 8, which is of a hollow structure and the stabilizing block 8 is far away from the base 5, is sealed, the second screw 9 penetrates through the stabilizing block 8, the second screw 9 and the stabilizing block 8 are screwed to be connected through threads, the second screw 9 is rotatably connected with the fixture block 16, a through hole communicated with the limiting groove 17 is formed in the base 5, the fixture block 16 is matched with the through hole, the second screw 9 is rotated clockwise from top to bottom, and the second screw 9 drives the fixture block 16 to slide towards the base 5.
In this embodiment, the inside of fixed beam 15 one end is equipped with the slip chamber, and 18 one end of spring is connected with base 5 and the other end is connected with fixed beam 15, and the slip chamber communicates with similar spacing groove 17, and the base 1 is convenient for install in spacing 4 embedding spacing groove 17.
In this embodiment, stopper 4 and base 1 pass through welded connection, and stopper 4 is "L" type structure, and spacing groove 17 is "L" type structure, and stopper 4 cooperates with spacing groove 17, has seted up draw-in groove 20 on the stopper 4, and fixture block 16 matches with draw-in groove 20, and fixture block 16 imbeds draw-in groove 20 on the stopper 4, and base 1 is by spacing fixed, is convenient for install, dismantles base 1.
In this embodiment, the shifting chute of "T" type structure of invering is seted up on the surface of installation piece 10, slide bar 11 matches with the shifting chute for "T" type structure and slide bar 11, installation piece 10, the square hole has all been seted up on slide bar 11, gag lever post 13 matches with the square hole, it is made by sponge material to clean pad 21, gag lever post 13 runs through installation piece 10, during slide bar 11, it is tangent with runner 3 to clean pad 21, runner 3 is when rotatory, clean pad 21 cleans the dust impurity of clearance runner 3 surface, avoid runner 3 surface increase degree of wear because of being infected with dust impurity.
The working principle and the using process of the invention are as follows:
when a tubular pile forming centrifuge is used for processing a tubular pile, a product is placed on the opposite rotating wheel 3, the rotating wheel 3 rotates to move the sliding rod 11 towards the base 5, the sliding rod 11 is connected with the mounting block 10 in a sliding and clamping mode, the sliding rod 11 drives the connecting rod 12 to move in the same direction, the connecting rod 12 drives the wiping pad 21 to move, the wiping pad 21 is tangent to the rotating wheel 3, the wiping pad 21 wipes and cleans dust impurities on the surface of the rotating wheel 3, and the phenomenon that the surface of the rotating wheel 3 is stained with the dust impurities to increase the abrasion degree is avoided;
when the base 1 is installed, the base 1 is arranged inside the base 5, the limiting block 4 is embedded inside the limiting groove 17 on the fixed beam 15, the first hand wheel on the first screw 7 is pinched, the first screw 7 rotates clockwise from top to bottom, the first screw 7 drives the pressing block 14 to move, the pressing block 14 drives the base 1, the limiting block 4 is connected with the fixed beam 15 in a sliding clamping mode, the limiting block 4 drives the moving block 19, the spring 18 is in a contraction state, the second screw 9 rotates clockwise from top to bottom, the second screw 9 drives the clamping block 16 to slide towards the base 5, the clamping block 16 penetrates through the base 5 and then is embedded into the clamping groove 20 on the limiting block 4, the limiting block 4 is limited and fixed, the base 1 is limited and fixed, and the base 1 is convenient to install and disassemble.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (8)

1.一种建筑施工用管桩加工成型装置,包括底座(1)、连接轴(2)、转动轮(3),其特征在于:所述底座(1)的底部设有基座(5),所述底座(1)相背的表面上均对称设有限位块(4),所述基座(5)的侧面设有固定块(6),所述固定块(6)上设有第一螺杆(7),所述第一螺杆(7)贯穿基座(5)的端部上设有压块(14),所述基座(5)相背的表面上均设有两个稳固块(8),所述稳固块(8)上设有第二螺杆(9),所述第二螺杆(9)嵌入稳固块(8)内的端部设有卡块(16),所述基座(5)的内表面设有固定梁(15),所述固定梁(15)的表面开设有两个限位槽(17),所述固定梁(15)一端的内部设有弹簧(18)、移动块(19)。1. A pipe pile processing and forming device for building construction, comprising a base (1), a connecting shaft (2), and a rotating wheel (3), characterized in that: the bottom of the base (1) is provided with a base (5) , the opposite surfaces of the base (1) are symmetrically provided with limit blocks (4), the side of the base (5) is provided with a fixing block (6), and the fixing block (6) is provided with a first A screw (7), the end of the first screw (7) passing through the base (5) is provided with a pressing block (14), and the opposite surfaces of the base (5) are provided with two stable A block (8), a second screw (9) is provided on the stabilization block (8), and a clamping block (16) is provided at the end of the second screw (9) embedded in the stabilization block (8). The inner surface of the base (5) is provided with a fixed beam (15), the surface of the fixed beam (15) is provided with two limit grooves (17), and one end of the fixed beam (15) is provided with a spring (17). 18), move the block (19). 2.根据权利要求1所述的一种建筑施工用管桩加工成型装置,其特征在于:所述固定块(6)为“L”型结构,所述第一螺杆(7)与基座(5)、固定块(6)均通过螺纹旋合连接,所述第一螺杆(7)与压块(14)转动连接。2. A pipe pile processing and forming device for building construction according to claim 1, characterized in that: the fixing block (6) is an "L"-shaped structure, and the first screw (7) and the base ( 5) The fixing blocks (6) are all connected by screwing, and the first screw (7) is connected with the pressing block (14) by rotation. 3.根据权利要求1所述的一种建筑施工用管桩加工成型装置,其特征在于:所述基座(5)包括底水平板及四边边侧的竖直板,所述基座(5)底水平板上对称开设有滑槽,所述压块(14)底部设有凸柱,所述凸柱与滑槽匹配。3. The device for processing and forming pipe piles for building construction according to claim 1, wherein the base (5) comprises a bottom horizontal plate and vertical plates on four sides, and the base (5) ) The bottom horizontal plate is symmetrically provided with a chute, the bottom of the pressing block (14) is provided with a convex column, and the convex column is matched with the chute. 4.根据权利要求1所述的一种建筑施工用管桩加工成型装置,其特征在于:所述稳固块(8)为中空结构及稳固块(8)远离基座(5)的端部封口,所述第二螺杆(9)贯穿稳固块(8),所述第二螺杆(9)与稳固块(8)通过螺纹旋合连接,所述第二螺杆(9)与卡块(16)转动连接,所述基座(5)上开设有与限位槽(17)连通的通孔,所述卡块(16)与通孔配合。4. A pipe pile processing and forming device for building construction according to claim 1, characterized in that: the stabilizing block (8) is a hollow structure and the end sealing of the stabilizing block (8) away from the base (5) , the second screw (9) penetrates the stabilization block (8), the second screw (9) is connected with the stabilization block (8) by screwing, and the second screw (9) is connected with the clamping block (16) Rotationally connected, the base (5) is provided with a through hole communicating with the limiting groove (17), and the clamping block (16) is matched with the through hole. 5.根据权利要求1所述的一种建筑施工用管桩加工成型装置,其特征在于:所述固定梁(15)一端的内部设有滑动腔,所述弹簧(18)一端与基座(5)连接及另一端与固定梁(15)连接,所述滑动腔与相近的限位槽(17)连通。5. A pipe pile processing and forming device for building construction according to claim 1, characterized in that: one end of the fixed beam (15) is provided with a sliding cavity, and one end of the spring (18) is connected to the base ( 5) Connecting and connecting the other end with the fixed beam (15), and the sliding cavity communicates with the adjacent limiting groove (17). 6.根据权利要求1所述的一种建筑施工用管桩加工成型装置,其特征在于:所述限位块(4)与底座(1)通过焊接连接,所述限位块(4)为“L”型结构,所述限位槽(17)为“L”型结构,所述限位块(4)与限位槽(17)配合,所述限位块(4)上开设有卡槽(20),所述卡块(16)与卡槽(20)匹配。6 . The pipe pile processing and forming device for building construction according to claim 1 , wherein the limiting block ( 4 ) is connected with the base ( 1 ) by welding, and the limiting block ( 4 ) is 6 . "L"-shaped structure, the limit groove (17) is an "L"-shaped structure, the limit block (4) is matched with the limit groove (17), and a card is opened on the limit block (4). A slot (20), the clamping block (16) is matched with the clamping slot (20). 7.根据权利要求1所述的一种建筑施工用管桩加工成型装置,其特征在于:所述基座(5)相对表面的中间位置设有安装块(10),所述安装块(10)上设有滑杆(11),所述滑杆(11)的顶端设有连接杆(12),所述连接杆(12)的两端上均套设有半圆柱形状的擦拭垫(21),所述安装块(10)上设有限位杆(13)。7. A pipe pile processing and forming device for building construction according to claim 1, characterized in that a mounting block (10) is provided in the middle position of the opposite surface of the base (5), and the mounting block (10) ) is provided with a sliding rod (11), the top of the sliding rod (11) is provided with a connecting rod (12), and both ends of the connecting rod (12) are sleeved with semi-cylindrical wiping pads (21). ), a limit rod (13) is provided on the mounting block (10). 8.根据权利要求7所述的一种建筑施工用管桩加工成型装置,其特征在于:所述安装块(10)的表面开设有倒置的“T”型结构的移动槽,所述滑杆(11)为“T”型结构及滑杆(11)与移动槽匹配,所述安装块(10)、滑杆(11)上均开设有方孔,所述限位杆(13)与方孔匹配,所述擦拭垫(21)由海绵材料制造,所述限位杆(13)贯穿安装块(10)、滑杆(11)时,所述擦拭垫(21)与转动轮(3)相切。8 . The device for processing and forming pipe piles for building construction according to claim 7 , wherein the surface of the mounting block ( 10 ) is provided with an inverted "T"-shaped moving groove, and the sliding rod (11) is a "T"-shaped structure and the sliding rod (11) is matched with the moving groove, the mounting block (10) and the sliding rod (11) are provided with square holes, and the limit rod (13) is connected with the square hole. The holes match, the wiping pad (21) is made of sponge material, and when the limiting rod (13) penetrates the mounting block (10) and the sliding rod (11), the wiping pad (21) and the rotating wheel (3) Tangent.
CN202011021802.2A 2020-09-25 2020-09-25 A pipe pile processing and forming device for building construction Active CN114248344B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011021802.2A CN114248344B (en) 2020-09-25 2020-09-25 A pipe pile processing and forming device for building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011021802.2A CN114248344B (en) 2020-09-25 2020-09-25 A pipe pile processing and forming device for building construction

Publications (2)

Publication Number Publication Date
CN114248344A true CN114248344A (en) 2022-03-29
CN114248344B CN114248344B (en) 2023-05-09

Family

ID=80790292

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011021802.2A Active CN114248344B (en) 2020-09-25 2020-09-25 A pipe pile processing and forming device for building construction

Country Status (1)

Country Link
CN (1) CN114248344B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB315120A (en) * 1928-08-07 1929-07-11 Edward Shotton Hume Improvements in and relating to apparatus for the manufacture or lining of pipes by centrifugal action
CN109049321A (en) * 2018-07-26 2018-12-21 无为县红宇通信器材有限责任公司 A kind of electric pole manufacturing cement placing installation
CN209063291U (en) * 2018-07-11 2019-07-05 王安劳 A kind of centrifugal forming device of concrete product
CN210651217U (en) * 2019-07-03 2020-06-02 蒙城宝业建筑工业化有限公司 Concrete wallboard mould
CN210965534U (en) * 2020-04-16 2020-07-10 广州鑫蓬科技有限公司 Centrifuge convenient to use

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB315120A (en) * 1928-08-07 1929-07-11 Edward Shotton Hume Improvements in and relating to apparatus for the manufacture or lining of pipes by centrifugal action
CN209063291U (en) * 2018-07-11 2019-07-05 王安劳 A kind of centrifugal forming device of concrete product
CN109049321A (en) * 2018-07-26 2018-12-21 无为县红宇通信器材有限责任公司 A kind of electric pole manufacturing cement placing installation
CN210651217U (en) * 2019-07-03 2020-06-02 蒙城宝业建筑工业化有限公司 Concrete wallboard mould
CN210965534U (en) * 2020-04-16 2020-07-10 广州鑫蓬科技有限公司 Centrifuge convenient to use

Also Published As

Publication number Publication date
CN114248344B (en) 2023-05-09

Similar Documents

Publication Publication Date Title
CN209901813U (en) Mechanical workpiece high-pressure cleaning device with clamping and positioning functions
CN112885248B (en) Dustproof glass frame for indoor LED display screen
CN209652713U (en) Concrete pavement leveling machine
CN108972472A (en) Rotary clamping device for engineering pipes
CN114248344A (en) Tubular pile machine-shaping device for construction
CN209245171U (en) A kind of dust-proof ball screw assembly,
CN209438720U (en) One kind being convenient for clean hard alloy grinding device
CN211889388U (en) A stainless steel plate fixed plasma cutting device
CN222081680U (en) A slag cleaning device for coal conveyor belt
CN204896682U (en) Clean effectual belt cleaner
CN214449594U (en) A conveying system for napkin printing equipment
CN219345728U (en) Fire control pipeline installation mount for fire engineering
CN218487736U (en) Machining center stand connection structure
CN213271784U (en) Assembly line sensor monitoring devices based on industry cloud
CN209885281U (en) A crystallizer with high efficiency
CN207880856U (en) A kind of scraping knife of spring-layered-type slag cooling machine attachment device
CN211231467U (en) Reservoir gate wire rope cleaning device
CN224016746U (en) A high-rise disc-lock type support frame
CN113522898A (en) Pipeline inner wall dirt cleaning device
CN220919552U (en) Permanent magnet drum-type magnetic separator
CN216427138U (en) Guiding mechanism with automatic steering function for glass cleaning
CN219648282U (en) Pulverized coal cleaning structure in dry coal separator
CN205097014U (en) Micro - electronic grinding of preventing splashing is quick -witted
CN209304221U (en) A steel pipe grinding device for construction
CN220063609U (en) An experimental bench for testing the bending strength of stone

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: A pipe pile processing and forming device for construction

Effective date of registration: 20231115

Granted publication date: 20230509

Pledgee: Hongjiang Huiteng Technology Co.,Ltd.

Pledgor: HUAIHUA GANGXIANG PIPE PILE CO.,LTD.

Registration number: Y2023980065861

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Granted publication date: 20230509

Pledgee: Hongjiang Huiteng Technology Co.,Ltd.

Pledgor: HUAIHUA GANGXIANG PIPE PILE CO.,LTD.

Registration number: Y2023980065861

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240615

Address after: Room 403, 4th Floor, Intersection of National Highway 209 and Heng'an Road, Zhushan Industrial Park, Qiancheng Town, Hongjiang City, Huaihua City, Hunan Province, 418000

Patentee after: Hunan Shuoxin New Materials Co.,Ltd.

Country or region after: China

Address before: 418000 Shuangxi Zhen Yan Jia Tuan Cun, Hongjiang City, Huaihua City, Hunan Province

Patentee before: HUAIHUA GANGXIANG PIPE PILE CO.,LTD.

Country or region before: China

PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: A pipe pile processing and forming device for construction

Granted publication date: 20230509

Pledgee: Hunan Hongjiang rural commercial bank Limited by Share Ltd.

Pledgor: Hunan Shuoxin New Materials Co.,Ltd.

Registration number: Y2025980053344