CN114215961B - A construction method suitable for pipeline engineering support structures in landslide areas - Google Patents
A construction method suitable for pipeline engineering support structures in landslide areas Download PDFInfo
- Publication number
- CN114215961B CN114215961B CN202111514550.1A CN202111514550A CN114215961B CN 114215961 B CN114215961 B CN 114215961B CN 202111514550 A CN202111514550 A CN 202111514550A CN 114215961 B CN114215961 B CN 114215961B
- Authority
- CN
- China
- Prior art keywords
- pipeline
- pipe
- trench
- construction
- slide
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/024—Laying or reclaiming pipes on land, e.g. above the ground
- F16L1/028—Laying or reclaiming pipes on land, e.g. above the ground in the ground
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
- E02D17/207—Securing of slopes or inclines with means incorporating sheet piles or piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/024—Laying or reclaiming pipes on land, e.g. above the ground
- F16L1/06—Accessories therefor, e.g. anchors
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/024—Laying or reclaiming pipes on land, e.g. above the ground
- F16L1/06—Accessories therefor, e.g. anchors
- F16L1/11—Accessories therefor, e.g. anchors for the detection or protection of pipes in the ground
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L55/00—Devices or appurtenances for use in, or in connection with, pipes or pipe systems
- F16L55/02—Energy absorbers; Noise absorbers
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L57/00—Protection of pipes or objects of similar shape against external or internal damage or wear
- F16L57/02—Protection of pipes or objects of similar shape against external or internal damage or wear against cracking or buckling
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A10/00—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
- Y02A10/23—Dune restoration or creation; Cliff stabilisation
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
技术领域Technical field
本发明属于施工技术领域,具体涉及一种适用于滑坡区管道工程支护结构的施工方法。The invention belongs to the field of construction technology, and specifically relates to a construction method suitable for pipeline engineering support structures in landslide areas.
背景技术Background technique
管道施工中不可避免地要穿越表土层滑坡发育区,虽然在施工前期对滑坡进行了治理,使滑坡处于稳定状态。但是在强降雨或地震等因素影响下,表层土体会发生蠕变或者较大的移动,造成小范围滑坡。由于表部土体发生移动,进而推动管道变形,甚至造成管道折断破坏,给管道运营和周围环境造成重大危害。因此对表土层滑坡区管道采取合理的防护措施是非常必要的。During pipeline construction, it is inevitable to cross the landslide development area in the topsoil. Although the landslide was controlled in the early stage of construction, the landslide was kept in a stable state. However, under the influence of factors such as heavy rainfall or earthquakes, the surface soil will creep or move significantly, causing small-scale landslides. Due to the movement of the surface soil, the pipeline will be deformed and even broken, causing major harm to the pipeline operation and the surrounding environment. Therefore, it is very necessary to take reasonable protective measures for pipelines in surface soil landslide areas.
发明内容Contents of the invention
本发明提供了一种适用于滑坡区管道工程支护结构的施工方法,目的在于解决上述技术问题。The present invention provides a construction method suitable for pipeline engineering support structures in landslide areas, aiming to solve the above technical problems.
为此,本发明采用如下技术方案:To this end, the present invention adopts the following technical solutions:
一种适用于滑坡区管道工程支护结构的施工方法,具体按以下步骤进行:A construction method suitable for supporting structures of pipeline projects in landslide areas, specifically according to the following steps:
1)抗滑桩施工:按照管道施工图,沿管道延伸方向在管道左右两侧竖直打孔,形成桩孔,在桩孔内浇筑混凝土形成抗滑桩;1) Anti-slide pile construction: According to the pipeline construction drawing, drill holes vertically on the left and right sides of the pipeline along the direction of the pipeline extension to form pile holes, and pour concrete in the pile holes to form anti-slide piles;
2)预应力锚杆施工:抗滑桩养护完成后,在靠近山体一侧抗滑桩桩顶面连接预应力锚杆,锚杆锚固段穿过滑面固定于滑坡基岩层;2) Prestressed anchor construction: After the anti-slide pile maintenance is completed, the prestressed anchors are connected to the top of the anti-slide piles on the side of the mountain, and the anchoring section of the anchor rod passes through the sliding surface and is fixed to the landslide bedrock layer;
3)管沟施工:在两排抗滑桩之间开挖用于放置管道的沟渠,并在沟渠中施工管沟;3) Pipe trench construction: Excavate a trench for placing pipes between two rows of anti-slide piles, and construct a pipe trench in the trench;
4)管道安装:管沟施工完成后,将管道吊运放置于管沟内;管道上间隔安装减震件,所述减震件设于管道和沟渠的两侧壁之间;减震件包括依次固定连接的直板、弹簧和弧板,直板紧靠沟渠侧壁,弧板紧靠管道外壁;4) Pipeline installation: After the construction of the pipe trench is completed, the pipe is lifted and placed in the pipe trench; shock-absorbing parts are installed at intervals on the pipe, and the shock-absorbing parts are located between the pipe and the two side walls of the trench; the shock-absorbing parts include The straight plate, spring and arc plate are fixed in sequence, the straight plate is close to the side wall of the ditch, and the arc plate is close to the outer wall of the pipe;
5)管道回填:在管沟顶部放置沟盖,然后回填沟渠,将管沟埋设于地表之下;5) Pipe backfilling: Place a trench cover on the top of the trench, then backfill the trench to bury the trench beneath the surface;
6)连接梁施工:在两排抗滑桩顶绑扎连系筋形成钢筋网,钢筋网四周固定模板后浇筑混凝土,形成连接梁,浇筑时连接梁上预留锚杆孔;6) Construction of connecting beams: tie connecting bars on top of two rows of anti-slide piles to form a steel mesh. Fix the formwork around the steel mesh and then pour concrete to form a connecting beam. During pouring, anchor holes are reserved on the connecting beams;
7)锚杆张拉锁定:待连接梁成型稳固后,在连接梁上设置台座并对锚杆(6)进行张拉锁定。7) Anchor tension and locking: After the connecting beam is firmly formed, set a pedestal on the connecting beam and tension and lock the anchor (6).
进一步地,靠近山体一侧建造有至少两排抗滑桩。Furthermore, at least two rows of anti-slide piles are built near the side of the mountain.
进一步地,所述抗滑桩为微型螺纹桩。Further, the anti-slide piles are micro-threaded piles.
进一步地,所述桩孔内浇筑的混凝土为短切玄武岩纤维混凝土。Further, the concrete poured in the pile hole is chopped basalt fiber concrete.
进一步地,所述管道外壁包覆有EPS柔性材料。Further, the outer wall of the pipeline is covered with EPS flexible material.
进一步地,所述弹簧表面包覆有防水防腐材料。Furthermore, the surface of the spring is covered with waterproof and anti-corrosion material.
本发明的有益效果在于:The beneficial effects of the present invention are:
1.管道两侧的抗滑桩不仅可以平衡山侧滑体推力,也可平衡河侧荷载,在滑坡变形过程中有效保护管道,有效防止管道变形及破坏;1. The anti-slide piles on both sides of the pipeline can not only balance the thrust of the mountain side sliding body, but also balance the load on the river side, effectively protect the pipeline during the landslide deformation process, and effectively prevent pipeline deformation and damage;
2.采用螺纹桩作为抗滑桩,施工简便,排土少,无振动,对周围土体扰动小,并对周围土体有挤密作用,发挥支挡作用的同时也可增强滑坡土体自身稳定性;2. Use threaded piles as anti-slide piles, which are easy to construct, have less soil discharge, no vibration, little disturbance to the surrounding soil, and have a squeezing effect on the surrounding soil. They not only play a supporting role but also strengthen the landslide soil itself. stability;
3.螺纹桩桩身采用短切玄武岩纤维混凝土材料,相比传统素混凝土螺纹桩,可提高其抗裂性能和抗冲击性能,从而提高管道的正常使用寿命;3. The threaded pile body is made of chopped basalt fiber concrete material. Compared with traditional plain concrete threaded piles, its crack resistance and impact resistance can be improved, thereby increasing the normal service life of the pipeline;
4.连接梁将管道两侧的抗滑桩连接成共同加固体,提高了支护结构的支护性能;4. The connecting beam connects the anti-slide piles on both sides of the pipeline into a common reinforcement, improving the support performance of the support structure;
5.管道外周包覆EPS柔性材料,防止施工时管道受损出现裂缝;管道两侧设置减震件,可以有效缓冲滑坡推力,减小管道振动,有效保护管道安全。5. The outer circumference of the pipeline is covered with EPS flexible material to prevent pipeline damage and cracks during construction; shock absorbers are installed on both sides of the pipeline to effectively buffer the landslide thrust, reduce pipeline vibration, and effectively protect pipeline safety.
附图说明Description of the drawings
图1是本发明管道的结构示意图;Figure 1 is a schematic structural diagram of the pipeline of the present invention;
图2是本发明减震件的结构示意图;Figure 2 is a schematic structural diagram of the shock absorber of the present invention;
图3是本发明抗滑桩的剖面示意图;Figure 3 is a schematic cross-sectional view of the anti-slide pile of the present invention;
图中:1-抗滑桩,2-管沟,3-管道,4-减震件,41-直板,42-弹簧,43-弧板,5-连接梁,6-锚杆。In the picture: 1-anti-slide pile, 2-pipe trench, 3-pipe, 4-shock absorbing parts, 41-straight plate, 42-spring, 43-arc plate, 5-connecting beam, 6-anchor rod.
具体实施方式Detailed ways
下面结合附图对本发明作进一步说明:The present invention will be further described below in conjunction with the accompanying drawings:
一种适用于滑坡区管道工程支护结构的施工方法,具体按以下步骤进行:A construction method suitable for supporting structures of pipeline projects in landslide areas, specifically according to the following steps:
1)抗滑桩施工:首先在滑坡区域规划管道走向,绘制管道设计施工图,确定管道3埋深,根据埋深确定桩孔的标深和施工位置;桩机进场就位,按照管道设计施工图,沿管道延伸方向在管道3左右两侧竖直打孔,形成桩孔;为提高支护及抗滑性能,靠近山体一侧可钻至少两排桩孔;1) Construction of anti-slide piles: First, plan the direction of the pipeline in the landslide area, draw the pipeline design and construction drawings, determine the burial depth of pipeline 3, and determine the depth of the pile hole and construction location according to the burial depth; the pile driver is put in place, and the pile driver is put in place according to the pipeline design According to the construction drawing, holes are drilled vertically on the left and right sides of Pipe 3 along the direction of the pipeline extension to form pile holes; in order to improve the support and anti-slip performance, at least two rows of pile holes can be drilled on the side of the mountain;
打孔时,桩机控制钻杆对准设计桩位,启动桩机,控制中空钻杆下降,钻杆下降速度与旋转速度的关系为:钻杆每下降一个螺距,同时顺时针旋转一周;钻进到设计深度时,钻杆上升速度与旋转速度的关系为:钻杆每上升一个螺距,同时逆时针旋转一周,从而形成较完整的螺纹桩孔。钻杆在上升的同时通过中空钻杆内的注浆管向孔内注射短切玄武岩纤维混凝土,混凝土凝固后形成抗滑桩1;When drilling, the pile driver controls the drill rod to align with the designed pile position, starts the pile driver, and controls the hollow drill rod to descend. The relationship between the drill rod descending speed and the rotation speed is: each time the drill rod descends by one pitch, it rotates clockwise for one revolution at the same time; When reaching the design depth, the relationship between the rising speed of the drill pipe and the rotation speed is: each time the drill pipe rises by one pitch, it rotates counterclockwise for one revolution at the same time, thus forming a more complete threaded pile hole. While the drill pipe is rising, chopped basalt fiber concrete is injected into the hole through the grouting pipe in the hollow drill pipe. After the concrete solidifies, an anti-slide pile 1 is formed;
短切玄武岩纤维混凝土拌制:采用强制式搅拌机,拌合时先将纤维与砂、石、水泥等同时加入搅拌机。先干拌后湿拌,搅拌时间严格按照规范要求,以保证纤维能够在混凝土中混合均匀。Mixing of chopped basalt fiber concrete: Use a forced mixer. When mixing, add the fiber, sand, stone, cement, etc. to the mixer at the same time. Dry mix first and then wet mix. The mixing time is strictly in accordance with the specifications to ensure that the fibers can be mixed evenly in the concrete.
2)预应力锚杆施工:抗滑桩1养护完成后,在靠近山体一侧抗滑桩1的桩顶平面设置带倾斜角度的预应力锚杆6,锚杆6锚固段穿过滑面固定于滑坡基岩层。带倾斜角度的预应力锚杆6可提高张拉力,从而提高抗滑桩1的侧向抗压强度。2) Prestressed anchor construction: After the maintenance of the anti-slide pile 1 is completed, a prestressed anchor 6 with an inclined angle is set on the top plane of the anti-slide pile 1 close to the mountain side, and the anchor section of the anchor 6 is fixed through the sliding surface. in the landslide bedrock layer. The prestressed anchor rod 6 with an inclined angle can increase the tensile force, thereby increasing the lateral compressive strength of the anti-slide pile 1.
3)管沟施工:在两排抗滑桩1之间开挖用于放置管道3的沟渠,开挖深度大于管道3的标深;在沟渠中施工混凝土管沟2,混凝土管沟2的横截面呈矩形或U形,为缩短工期,混凝土管沟2可采用预制件;施工时,将预制件依次紧靠放置于沟渠内,两预制件接口处浇筑混凝体,提高预制件连接强度。3) Pipe trench construction: Excavate a trench for placing pipeline 3 between two rows of anti-sliding piles 1, and the excavation depth is greater than the marked depth of pipeline 3; construct concrete pipe trench 2 in the trench, and the horizontal direction of concrete pipe trench 2 The cross-section is rectangular or U-shaped. In order to shorten the construction period, the concrete pipe trench 2 can use prefabricated parts; during construction, the prefabricated parts are placed closely in the trench one after another, and concrete is poured at the interface of the two prefabricated parts to improve the connection strength of the prefabricated parts.
4)管道安装:管沟施工完成后,将管道3吊运放置于管沟2内,管道3需居中放置于管沟2中心。然后在管道3上安装减震件4,相邻减震件4间隔0.8-1.5m。减震件4包括依次固定连接的直板41、弹簧42和弧板43,弧板43的弧度与管道3外壁相契合;直板41紧靠沟渠侧壁,弧板43紧靠管道3外壁(如图2所示)。减震件4用于提高管道3的稳定性,在地震时,减震件4起缓冲作用,可降低管道3左右方向的摆动幅度,防止管道3由于振幅过大,导致管道3出现裂缝甚至断裂。此外,由于管道3在输送物质过程中存在小幅度振动,减震件4也可降低管道3的振幅,防止管道3出现微裂纹,提高管道3寿命。4) Pipeline installation: After the pipe trench construction is completed, pipe 3 is lifted and placed in pipe trench 2. Pipeline 3 needs to be placed centrally in the center of pipe trench 2. Then install the shock-absorbing parts 4 on the pipe 3, and the adjacent shock-absorbing parts 4 are spaced 0.8-1.5m apart. The shock absorber 4 includes a straight plate 41, a spring 42 and an arc plate 43 that are fixedly connected in sequence. The curvature of the arc plate 43 matches the outer wall of the pipeline 3; the straight plate 41 is close to the side wall of the ditch, and the arc plate 43 is close to the outer wall of the pipeline 3 (as shown in the figure) shown in 2). The shock-absorbing part 4 is used to improve the stability of the pipeline 3. During an earthquake, the shock-absorbing part 4 plays a buffering role, which can reduce the swing amplitude of the pipe 3 in the left and right directions and prevent the pipe 3 from cracking or even breaking due to excessive amplitude. . In addition, since the pipeline 3 vibrates at a small amplitude during the transportation of materials, the shock absorber 4 can also reduce the amplitude of the pipeline 3, prevent micro-cracks in the pipeline 3, and increase the life of the pipeline 3.
此外,管道3外壁包覆有EPS柔性材料,防止在吊运时损伤管道3;弹簧42表面包覆有防水防腐材料,防止弹簧42由于生锈导致弹性下降,提高弹簧42的使用寿命。In addition, the outer wall of the pipe 3 is covered with EPS flexible material to prevent damage to the pipe 3 during lifting; the surface of the spring 42 is covered with waterproof and anti-corrosion materials to prevent the elasticity of the spring 42 from decreasing due to rust and increase the service life of the spring 42.
5)管道回填:在管沟2上方放置沟盖,沟盖之间无需浇筑混凝土,便于后期进行管道3维修作业;然后回填沟渠,将回填土夯实,抗滑桩1的桩头露出至夯土外。5) Pipe backfilling: Place a trench cover above the pipe trench 2. No concrete is required to be poured between the trench covers to facilitate later maintenance of pipeline 3. Then backfill the trench, compact the backfill soil, and expose the pile head of the anti-slip pile 1 to the rammed soil. outside.
6)连接梁施工:在抗滑桩1桩顶绑扎连系筋形成钢筋网,钢筋网完全覆盖两侧的抗滑桩1;钢筋网四周固定模板后进行浇筑,形成连接梁5;浇筑时注意在锚杆6端部套PVC管,留出锚杆孔。6) Construction of connecting beam: tie the connecting bars on the top of the anti-slide pile 1 to form a steel mesh. The steel mesh completely covers the anti-slide piles 1 on both sides; fix the formwork around the steel mesh and then pour it to form the connecting beam 5; pay attention when pouring Cover the PVC pipe at the end of anchor rod 6, leaving an anchor hole.
7)锚杆张拉锁定:待连接梁5成型稳固后,在连接梁5上设置台座并进行锚杆6张拉锁定,即完成施工作业。7) Anchor rod tensioning and locking: After the connecting beam 5 is formed and stabilized, a pedestal is set on the connecting beam 5 and the anchor rod 6 is tensioned and locked to complete the construction operation.
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111514550.1A CN114215961B (en) | 2021-12-13 | 2021-12-13 | A construction method suitable for pipeline engineering support structures in landslide areas |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111514550.1A CN114215961B (en) | 2021-12-13 | 2021-12-13 | A construction method suitable for pipeline engineering support structures in landslide areas |
Publications (2)
Publication Number | Publication Date |
---|---|
CN114215961A CN114215961A (en) | 2022-03-22 |
CN114215961B true CN114215961B (en) | 2023-10-27 |
Family
ID=80701178
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202111514550.1A Active CN114215961B (en) | 2021-12-13 | 2021-12-13 | A construction method suitable for pipeline engineering support structures in landslide areas |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114215961B (en) |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CH610966A5 (en) * | 1976-07-22 | 1979-05-15 | Willi Steiner | Rock or slope revetment and method of constructing it |
JP2006104761A (en) * | 2004-10-05 | 2006-04-20 | Public Works Research Institute | Method of increasing strength of landslide preventive pile |
CN103437370A (en) * | 2013-07-31 | 2013-12-11 | 广州市设计院 | Method and supporting structure for slip resisting and soil retaining of abrupt slope |
CN107795758A (en) * | 2017-10-30 | 2018-03-13 | 中石化重庆天然气管道有限责任公司 | A kind of pipeline geological disaster protector and its installation and application |
CN108086352A (en) * | 2018-02-01 | 2018-05-29 | 云南新创新交通建设股份有限公司 | A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure |
CN110439011A (en) * | 2019-09-04 | 2019-11-12 | 中国电建集团中南勘测设计研究院有限公司 | A kind of side slope antiskid supporting construction and its construction method |
CN112144548A (en) * | 2020-08-29 | 2020-12-29 | 兰州理工大学 | A kind of semi-buried multifunctional frame support structure and construction method thereof |
CN212691194U (en) * | 2020-05-14 | 2021-03-12 | 陕西江豪建筑工程有限公司 | Natural gas pipeline protection device |
CN112503247A (en) * | 2020-11-27 | 2021-03-16 | 浙江世润建创科技发展有限公司 | Slope section water pipeline and construction method thereof |
CN113700981A (en) * | 2021-09-03 | 2021-11-26 | 中国石油大学(华东) | A bury ground pipeline landslide protector for protection of pipeline weak link |
-
2021
- 2021-12-13 CN CN202111514550.1A patent/CN114215961B/en active Active
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CH610966A5 (en) * | 1976-07-22 | 1979-05-15 | Willi Steiner | Rock or slope revetment and method of constructing it |
JP2006104761A (en) * | 2004-10-05 | 2006-04-20 | Public Works Research Institute | Method of increasing strength of landslide preventive pile |
CN103437370A (en) * | 2013-07-31 | 2013-12-11 | 广州市设计院 | Method and supporting structure for slip resisting and soil retaining of abrupt slope |
CN107795758A (en) * | 2017-10-30 | 2018-03-13 | 中石化重庆天然气管道有限责任公司 | A kind of pipeline geological disaster protector and its installation and application |
CN108086352A (en) * | 2018-02-01 | 2018-05-29 | 云南新创新交通建设股份有限公司 | A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure |
CN110439011A (en) * | 2019-09-04 | 2019-11-12 | 中国电建集团中南勘测设计研究院有限公司 | A kind of side slope antiskid supporting construction and its construction method |
CN212691194U (en) * | 2020-05-14 | 2021-03-12 | 陕西江豪建筑工程有限公司 | Natural gas pipeline protection device |
CN112144548A (en) * | 2020-08-29 | 2020-12-29 | 兰州理工大学 | A kind of semi-buried multifunctional frame support structure and construction method thereof |
CN112503247A (en) * | 2020-11-27 | 2021-03-16 | 浙江世润建创科技发展有限公司 | Slope section water pipeline and construction method thereof |
CN113700981A (en) * | 2021-09-03 | 2021-11-26 | 中国石油大学(华东) | A bury ground pipeline landslide protector for protection of pipeline weak link |
Non-Patent Citations (2)
Title |
---|
刘金涛.管道横穿滑坡相互作用大尺度模型试验研究.《中国硕士学位论文全文数据库 工程科技Ⅰ辑》.2013,第B019-132页. * |
赵晓刚、戴琳等.埋地管道新型预应力抗滑桩的应用.《油气储运》.2001,第20卷(第12期),第56-58页. * |
Also Published As
Publication number | Publication date |
---|---|
CN114215961A (en) | 2022-03-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101250886B (en) | Method for reinforcing masonry structure building base | |
US10738436B1 (en) | Tubular foundation for onshore wind turbine generators | |
CN103321246B (en) | Underground diaphragm wall based foundation pit construction method | |
CN108150190B (en) | Unevenly-pressured shallow tunnel rock crusher section excavates safeguard structure and construction method | |
CN110629671A (en) | A suspension bridge anchorage and its construction method | |
CN104196014A (en) | Combined rock-embedded anchor cable slide-resistant pile where round steel is implanted and construction method thereof | |
CN105970973A (en) | Soft soil foundation pit double-row piles supporting structure considering soil-arch and deformation space effect | |
CN210106749U (en) | Counter-force structure of soft soil foundation super large section push pipe jacking operation | |
CN214363508U (en) | Foundation pit supporting structure | |
CN212001248U (en) | A pile foundation joist balance-weight retaining wall structure in high-intensity earthquake area | |
CN114215961B (en) | A construction method suitable for pipeline engineering support structures in landslide areas | |
CN106988337A (en) | Reinforcing method for reducing uneven settlement of strip-shaped shallow foundation house | |
CN216664179U (en) | Supporting construction suitable for pipeline engineering in landslide area | |
CN207314353U (en) | A kind of supporting construction applied to foundation pit | |
CN116607548A (en) | Side slope supporting structure and side slope supporting method | |
CN110106930B (en) | Iron tower foundation reinforcement protection method | |
KR20130073336A (en) | Pile structure and construction methods | |
CN108360585A (en) | Close on the underpinning method and building composite foundation of side slope Tall Building Foundation | |
CN114508113A (en) | Construction method of waist-supported anti-sliding pile structure | |
CN207405630U (en) | A kind of novel small-sized box drain reinforcement system | |
KR101020217B1 (en) | Rock construction using anchor and construction method | |
JP2022060628A (en) | Base-enlarged foundation structure, composite foundation structure of reinforced soil and construction method thereof | |
CN111893829A (en) | A roadbed protection structure | |
CN218233492U (en) | A Supporting Structure for Deep Foundation Pit in Binary Stratum of Upper Soil and Lower Rock | |
CN220225382U (en) | Light side slope reinforcing retaining structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |