CN114215961A - Construction method suitable for pipeline engineering supporting structure in landslide area - Google Patents

Construction method suitable for pipeline engineering supporting structure in landslide area Download PDF

Info

Publication number
CN114215961A
CN114215961A CN202111514550.1A CN202111514550A CN114215961A CN 114215961 A CN114215961 A CN 114215961A CN 202111514550 A CN202111514550 A CN 202111514550A CN 114215961 A CN114215961 A CN 114215961A
Authority
CN
China
Prior art keywords
pipeline
construction
trench
pile
sliding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202111514550.1A
Other languages
Chinese (zh)
Other versions
CN114215961B (en
Inventor
吴红刚
孟建
关伟
李永强
张俊德
吴道勇
赵鑫
王永翔
唐林
韦洪
刘旭
吕小强
庞伟军
杨昊天
王德双
王瑜鑫
苟海瑞
焦海平
张雄伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou University
Northwest Research Institute Co Ltd of CREC
Original Assignee
Guizhou University
Northwest Research Institute Co Ltd of CREC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou University, Northwest Research Institute Co Ltd of CREC filed Critical Guizhou University
Priority to CN202111514550.1A priority Critical patent/CN114215961B/en
Publication of CN114215961A publication Critical patent/CN114215961A/en
Application granted granted Critical
Publication of CN114215961B publication Critical patent/CN114215961B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/06Accessories therefor, e.g. anchors
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/06Accessories therefor, e.g. anchors
    • F16L1/11Accessories therefor, e.g. anchors for the detection or protection of pipes in the ground
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L55/00Devices or appurtenances for use in, or in connection with, pipes or pipe systems
    • F16L55/02Energy absorbers; Noise absorbers
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L57/00Protection of pipes or objects of similar shape against external or internal damage or wear
    • F16L57/02Protection of pipes or objects of similar shape against external or internal damage or wear against cracking or buckling
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/23Dune restoration or creation; Cliff stabilisation

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明公开了一种适用于滑坡区管道工程支护结构的施工方法,支护结构包括沟渠、管道和支护结构;沟渠埋设于地表之下,管道放置于沟渠中,所述管道与沟渠的两内壁之间设有减震件,所述减震件包括多个且间隔设置;支护结构包括位于沟渠两侧的抗滑桩,所述抗滑桩的顶部浇筑有连接梁;靠近山体一侧的抗滑桩上还连接有预应力锚杆,所述锚杆的锚固段穿过滑面固定于滑坡基岩层。施工方法包括以下步骤:1)抗滑桩施工;2)预应力锚杆施工;3)管沟施工;4)管道安装;5)管道回填;6)连接梁施工;7)锚杆张拉锁定;管道两侧的微型抗滑桩群不仅可以平衡山侧滑体推力,也可以承担河侧荷载作用,在滑坡变形过程中有效保护管道,防止其变形破坏。

Figure 202111514550

The invention discloses a construction method suitable for a pipeline engineering supporting structure in a landslide area. The supporting structure includes a ditch, a pipeline and a supporting structure; Between the two inner walls, there are shock-absorbing parts, and the shock-absorbing parts include a plurality of them and are arranged at intervals; the supporting structure includes anti-sliding piles located on both sides of the ditch, and the top of the anti-sliding piles is poured with connecting beams; The anti-sliding piles on the side are also connected with prestressed anchor rods, and the anchoring sections of the anchor rods are fixed to the landslide bedrock layer through the sliding surface. The construction method includes the following steps: 1) construction of anti-sliding piles; 2) construction of prestressed bolts; 3) construction of pipe trenches; 4) installation of pipes; 5) backfilling of pipes; 6) construction of connecting beams; ; The miniature anti-slide pile groups on both sides of the pipeline can not only balance the thrust of the mountain side slide body, but also bear the load on the river side, effectively protect the pipeline in the process of landslide deformation and prevent its deformation and damage.

Figure 202111514550

Description

Construction method suitable for pipeline engineering supporting structure in landslide area
Technical Field
The invention belongs to the technical field of construction, and particularly relates to a construction method suitable for a pipeline engineering supporting structure in a landslide area.
Background
The pipeline construction inevitably needs to pass through a topsoil landslide growing area, although the landslide is treated in the early stage of construction, so that the landslide is in a stable state. However, under the influence of factors such as heavy rainfall or earthquake, the surface soil body can creep or move greatly, and a small-range landslide is caused. Because the surface soil body moves, the pipeline is pushed to deform, even the pipeline is broken and damaged, and great harm is caused to the pipeline operation and the surrounding environment. Therefore, it is necessary to take reasonable protective measures for pipelines in the landslide area of the surface soil layer.
Disclosure of Invention
The invention provides a construction method suitable for a pipeline engineering supporting structure in a landslide area and aims to solve the technical problem.
Therefore, the invention adopts the following technical scheme:
a construction method suitable for a pipeline engineering supporting structure in a landslide area is specifically carried out according to the following steps:
1) and (3) constructing the slide-resistant pile: according to a pipeline construction drawing, vertically punching holes on the left side and the right side of a pipeline along the extending direction of the pipeline to form pile holes, and pouring concrete in the pile holes to form anti-slide piles;
2) and (3) prestressed anchor rod construction: after the maintenance of the anti-slide pile is finished, connecting a pre-stressed anchor rod on the pile top surface of the anti-slide pile close to one side of the mountain, and fixing an anchor rod anchoring section on a landslide foundation layer by penetrating through a sliding surface;
3) construction of pipe ditches: excavating a ditch for placing a pipeline between the two rows of anti-slide piles, and constructing a pipe ditch in the ditch;
4) installing a pipeline: after the pipe ditch construction is finished, hoisting and placing the pipeline in the pipe ditch; shock absorbing pieces are arranged on the pipeline at intervals and are arranged between the pipeline and two side walls of the ditch; the shock absorption piece comprises a straight plate, a spring and an arc plate which are fixedly connected in sequence, the straight plate is close to the side wall of the ditch, and the arc plate is close to the outer wall of the pipeline;
5) backfilling a pipeline: placing a trench cover at the top of the pipe trench, then backfilling the trench, and burying the pipe trench under the ground surface;
6) construction of a connecting beam: binding tie bars at the tops of the two rows of anti-slide piles to form a reinforcing mesh, fixing templates around the reinforcing mesh, pouring concrete to form a connecting beam, and reserving anchor rod holes on the connecting beam during pouring;
7) tensioning and locking an anchor rod: after the connecting beam is formed stably, a pedestal is arranged on the connecting beam, and the anchor rod (6) is tensioned and locked.
Further, at least two rows of anti-slide piles are built on one side close to the mountain.
Further, the slide-resistant pile is a micro threaded pile.
Further, the concrete poured in the pile hole is chopped basalt fiber concrete.
Further, the outer wall of the pipeline is coated with an EPS flexible material.
Further, the surface of the spring is coated with a waterproof and anticorrosive material.
The invention has the beneficial effects that:
1. the anti-slide piles on the two sides of the pipeline can balance thrust of a landslide body and river side load, effectively protect the pipeline in the landslide deformation process and effectively prevent the pipeline from deforming and damaging;
2. the screw pile is adopted as the anti-slide pile, so that the construction is simple and convenient, the soil discharge is less, no vibration is caused, the disturbance to the surrounding soil body is small, the compaction effect is realized on the surrounding soil body, the support effect is exerted, and the stability of the landslide soil body can be enhanced;
3. the pile body of the screw pile is made of chopped basalt fiber concrete material, compared with the traditional plain concrete screw pile, the anti-cracking performance and the shock resistance of the screw pile can be improved, so that the normal service life of the pipeline is prolonged;
4. the connecting beams connect the anti-slide piles on the two sides of the pipeline into a common reinforcing body, so that the supporting performance of the supporting structure is improved;
5. the EPS flexible material is coated on the periphery of the pipeline, so that the pipeline is prevented from being damaged and cracked during construction; the pipeline both sides set up the damper, can effectively cushion landslide thrust, reduce pipeline vibration, effectively protect pipeline safety.
Drawings
FIG. 1 is a schematic structural view of the pipe of the present invention;
FIG. 2 is a schematic view of the construction of the shock absorbing member of the present invention;
figure 3 is a schematic cross-sectional view of a slide pile according to the invention;
in the figure: 1-slide-resistant pile, 2-pipe trench, 3-pipeline, 4-shock-absorbing piece, 41-straight plate, 42-spring, 43-arc plate, 5-connecting beam and 6-anchor rod.
Detailed Description
The invention will be further described with reference to the accompanying drawings in which:
a construction method suitable for a pipeline engineering supporting structure in a landslide area is specifically carried out according to the following steps:
1) and (3) constructing the slide-resistant pile: firstly, planning the pipeline trend in a landslide area, drawing a pipeline design construction drawing, determining the buried depth of a pipeline 3, and determining the standard depth and the construction position of a pile hole according to the buried depth; the pile driver enters a field to be in place, and holes are vertically punched on the left side and the right side of the pipeline 3 along the extending direction of the pipeline according to a pipeline design construction drawing to form pile holes; in order to improve the supporting and anti-sliding performance, at least two rows of pile holes can be drilled on one side close to the mountain;
when punching, the stake machine control drilling rod aims at design stake position, starts the stake machine, and the decline of control cavity drilling rod, the drilling rod descending speed is with the relation of rotational speed: when the drill rod descends one pitch, the drill rod rotates one circle clockwise; when the drill rod is drilled to the designed depth, the relationship between the rising speed of the drill rod and the rotating speed is as follows: and when the drill rod rises by one thread pitch, the drill rod rotates anticlockwise by one circle, so that a relatively complete threaded pile hole is formed. When the drill rod rises, the chopped basalt fiber concrete is injected into the hole through a grouting pipe in the hollow drill rod, and the anti-slide pile 1 is formed after the concrete is solidified;
mixing short basalt fiber concrete: a forced stirrer is adopted, and during mixing, the fibers, sand, stone, cement and the like are added into the stirrer at the same time. The dry mixing is firstly carried out, then the wet mixing is carried out, and the mixing time strictly meets the standard requirement so as to ensure that the fibers can be uniformly mixed in the concrete.
2) And (3) prestressed anchor rod construction: after the maintenance of the anti-slide pile 1 is finished, a prestressed anchor rod 6 with an inclination angle is arranged on the pile top plane of the anti-slide pile 1 close to one side of the mountain, and the anchoring section of the anchor rod 6 penetrates through the sliding surface and is fixed on the landslide foundation layer. The prestressed anchor 6 with the inclination angle can improve the tensile force, thereby improving the lateral compressive strength of the slide-resistant pile 1.
3) Construction of pipe ditches: excavating a ditch for placing a pipeline 3 between the two rows of anti-slide piles 1, wherein the excavation depth is greater than the standard depth of the pipeline 3; constructing a concrete pipe ditch 2 in the ditch, wherein the cross section of the concrete pipe ditch 2 is rectangular or U-shaped, and the concrete pipe ditch 2 can adopt prefabricated parts for shortening the construction period; during construction, the prefabricated members are sequentially and closely placed in the ditch, and concrete is poured at the joints of the two prefabricated members, so that the connection strength of the prefabricated members is improved.
4) Installing a pipeline: after the pipe ditch construction is finished, the pipeline 3 is hoisted and placed in the pipe ditch 2, and the pipeline 3 needs to be placed in the center of the pipe ditch 2. Then, damper members 4 are installed on the pipe 3 with a space of 0.8-1.5m between adjacent damper members 4. The shock-absorbing part 4 comprises a straight plate 41, a spring 42 and an arc plate 43 which are fixedly connected in sequence, and the radian of the arc plate 43 is matched with the outer wall of the pipeline 3; the straight plates 41 abut the trench sidewalls and the arcuate plates 43 abut the outer walls of the pipe 3 (as shown in figure 2). The damping piece 4 is used for improving the stability of the pipeline 3, and when an earthquake occurs, the damping piece 4 plays a role in buffering, so that the swing amplitude of the pipeline 3 in the left and right directions can be reduced, and the pipeline 3 is prevented from cracking or even breaking due to overlarge amplitude. In addition, because pipeline 3 has small amplitude vibration in the transported substance process, damper 4 also can reduce the amplitude of pipeline 3, prevents that pipeline 3 from appearing the crazing crack, improves pipeline 3 life-span.
In addition, the outer wall of the pipeline 3 is coated with EPS flexible materials, so that the pipeline 3 is prevented from being damaged during lifting; the surface of the spring 42 is coated with a waterproof and anticorrosive material, so that the elasticity of the spring 42 is prevented from being reduced due to rusting, and the service life of the spring 42 is prolonged.
5) Backfilling a pipeline: a trench cover is arranged above the pipe trench 2, concrete does not need to be poured between the trench covers, and the later maintenance operation of the pipeline 3 is facilitated; and then backfilling the ditch, tamping the backfilled soil, and exposing the pile head of the slide-resistant pile 1 out of the tamped soil.
6) Construction of a connecting beam: binding tie bars at the pile tops of the anti-slide piles 1 to form a reinforcing mesh, wherein the reinforcing mesh completely covers the anti-slide piles 1 on the two sides; fixing a template around the reinforcing mesh, and pouring to form a connecting beam 5; when pouring, the end of the anchor rod 6 is sleeved with a PVC pipe, and an anchor rod hole is reserved.
7) Tensioning and locking an anchor rod: after the connecting beam 5 is stably formed, a pedestal is arranged on the connecting beam 5, and the anchor rods 6 are tensioned and locked, so that the construction operation is completed.

Claims (6)

1.一种适用于滑坡区管道工程支护结构的施工方法,其特征在于,具体按以下步骤进行:1. a construction method that is applicable to the pipeline engineering supporting structure in the landslide area, is characterized in that, is specifically carried out according to the following steps: 1)抗滑桩施工:按照管道施工图,沿管道(3)延伸方向在管道(3)左右两侧竖直打孔,形成桩孔,在桩孔内浇筑混凝土形成抗滑桩(1);1) Construction of anti-sliding piles: According to the pipeline construction drawing, vertically punch holes on the left and right sides of the pipeline (3) along the extension direction of the pipeline (3) to form pile holes, and pour concrete into the pile holes to form the anti-sliding piles (1); 2)预应力锚杆施工:抗滑桩(1)养护完成后,在靠近山体一侧抗滑桩(1)桩顶面连接预应力锚杆(6),锚杆(6)锚固段穿过滑面固定于滑坡基岩层;2) Prestressed anchor construction: After the anti-sliding pile (1) maintenance is completed, connect the prestressed anchor (6) to the top surface of the anti-sliding pile (1) on the side near the mountain, and the anchoring section of the anchor (6) passes through The sliding surface is fixed on the bedrock layer of the landslide; 3)管沟施工:在两排抗滑桩(1)之间开挖用于放置管道(3)的沟渠,并在沟渠中施工管沟(2);3) Pipe trench construction: excavate a trench for placing the pipeline (3) between the two rows of anti-sliding piles (1), and construct a pipe trench (2) in the trench; 4)管道安装:管沟(2)施工完成后,将管道(3)吊运放置于管沟(2)内;管道(3)上间隔安装减震件(4),所述减震件(4)设于管道(3)和沟渠的两侧壁之间;减震件(4)包括依次固定连接的直板(41)、弹簧(42)和弧板(43),直板(41)紧靠沟渠侧壁,弧板(43)紧靠管道(3)外壁;4) Pipeline installation: After the construction of the pipe trench (2) is completed, lift the pipe (3) and place it in the pipe trench (2); 4) It is located between the pipe (3) and the two side walls of the ditch; the shock absorber (4) includes a straight plate (41), a spring (42) and an arc plate (43) which are fixedly connected in sequence, and the straight plate (41) is close to the On the side wall of the ditch, the arc plate (43) is close to the outer wall of the pipe (3); 5)管道回填:在管沟(2)顶部放置沟盖,然后回填沟渠,将管沟(2)埋设于地表之下;5) Pipe backfill: place a trench cover on top of the trench (2), then backfill the trench, and bury the trench (2) under the surface; 6)连接梁施工:在两排抗滑桩(1)顶绑扎连系筋形成钢筋网,钢筋网四周固定模板后浇筑混凝土,形成连接梁(5),浇筑时连接梁(5)上预留锚杆孔;6) Connecting beam construction: tie the connecting bars on the top of the two rows of anti-sliding piles (1) to form a steel mesh, fix the formwork around the steel mesh and then pour concrete to form a connecting beam (5), which is reserved on the connecting beam (5) during pouring Anchor hole; 7)锚杆张拉锁定:待连接梁(5)成型稳固后,在连接梁(5)上设置台座并对锚杆(6)进行张拉锁定。7) The anchor rod is tensioned and locked: After the connecting beam (5) is formed and stabilized, a pedestal is set on the connecting beam (5) and the anchor rod (6) is tensioned and locked. 2.根据权利要求1所述的适用于滑坡区管道工程支护结构的施工方法,其特征在于,靠近山体一侧建造有至少两排抗滑桩(1)。2. The construction method suitable for a pipeline engineering supporting structure in a landslide area according to claim 1, characterized in that, at least two rows of anti-slide piles (1) are built near the side of the mountain. 3.根据权利要求1所述的适用于滑坡区管道工程支护结构的施工方法,其特征在于,所述抗滑桩(1)为微型螺纹桩。3 . The construction method suitable for a pipeline engineering support structure in a landslide area according to claim 1 , wherein the anti-sliding pile ( 1 ) is a micro-threaded pile. 4 . 4.根据权利要求1所述的适用于滑坡区管道工程支护结构的施工方法,其特征在于,所述桩孔内浇筑的混凝土为短切玄武岩纤维混凝土。4 . The construction method of claim 1 , wherein the concrete poured in the pile hole is chopped basalt fiber concrete. 5 . 5.根据权利要求1所述的适用于滑坡区管道工程支护结构的施工方法,其特征在于,所述管道(3)外壁包覆有EPS柔性材料。5 . The construction method suitable for a pipeline engineering support structure in a landslide area according to claim 1 , wherein the outer wall of the pipeline ( 3 ) is covered with EPS flexible material. 6 . 6.根据权利要求1所述的适用于滑坡区管道工程支护结构的施工方法,其特征在于,所述弹簧(42)表面包覆有防水防腐材料。6 . The construction method suitable for a pipeline engineering support structure in a landslide area according to claim 1 , wherein the surface of the spring ( 42 ) is covered with waterproof and anti-corrosion materials. 7 .
CN202111514550.1A 2021-12-13 2021-12-13 A construction method suitable for pipeline engineering support structures in landslide areas Active CN114215961B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111514550.1A CN114215961B (en) 2021-12-13 2021-12-13 A construction method suitable for pipeline engineering support structures in landslide areas

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111514550.1A CN114215961B (en) 2021-12-13 2021-12-13 A construction method suitable for pipeline engineering support structures in landslide areas

Publications (2)

Publication Number Publication Date
CN114215961A true CN114215961A (en) 2022-03-22
CN114215961B CN114215961B (en) 2023-10-27

Family

ID=80701178

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111514550.1A Active CN114215961B (en) 2021-12-13 2021-12-13 A construction method suitable for pipeline engineering support structures in landslide areas

Country Status (1)

Country Link
CN (1) CN114215961B (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH610966A5 (en) * 1976-07-22 1979-05-15 Willi Steiner Rock or slope revetment and method of constructing it
JP2006104761A (en) * 2004-10-05 2006-04-20 Public Works Research Institute Method of increasing strength of landslide preventive pile
CN103437370A (en) * 2013-07-31 2013-12-11 广州市设计院 Method and supporting structure for slip resisting and soil retaining of abrupt slope
CN107795758A (en) * 2017-10-30 2018-03-13 中石化重庆天然气管道有限责任公司 A kind of pipeline geological disaster protector and its installation and application
CN108086352A (en) * 2018-02-01 2018-05-29 云南新创新交通建设股份有限公司 A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure
CN110439011A (en) * 2019-09-04 2019-11-12 中国电建集团中南勘测设计研究院有限公司 A kind of side slope antiskid supporting construction and its construction method
CN112144548A (en) * 2020-08-29 2020-12-29 兰州理工大学 A kind of semi-buried multifunctional frame support structure and construction method thereof
CN212691194U (en) * 2020-05-14 2021-03-12 陕西江豪建筑工程有限公司 Natural gas pipeline protection device
CN112503247A (en) * 2020-11-27 2021-03-16 浙江世润建创科技发展有限公司 Slope section water pipeline and construction method thereof
CN113700981A (en) * 2021-09-03 2021-11-26 中国石油大学(华东) A bury ground pipeline landslide protector for protection of pipeline weak link

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH610966A5 (en) * 1976-07-22 1979-05-15 Willi Steiner Rock or slope revetment and method of constructing it
JP2006104761A (en) * 2004-10-05 2006-04-20 Public Works Research Institute Method of increasing strength of landslide preventive pile
CN103437370A (en) * 2013-07-31 2013-12-11 广州市设计院 Method and supporting structure for slip resisting and soil retaining of abrupt slope
CN107795758A (en) * 2017-10-30 2018-03-13 中石化重庆天然气管道有限责任公司 A kind of pipeline geological disaster protector and its installation and application
CN108086352A (en) * 2018-02-01 2018-05-29 云南新创新交通建设股份有限公司 A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure
CN110439011A (en) * 2019-09-04 2019-11-12 中国电建集团中南勘测设计研究院有限公司 A kind of side slope antiskid supporting construction and its construction method
CN212691194U (en) * 2020-05-14 2021-03-12 陕西江豪建筑工程有限公司 Natural gas pipeline protection device
CN112144548A (en) * 2020-08-29 2020-12-29 兰州理工大学 A kind of semi-buried multifunctional frame support structure and construction method thereof
CN112503247A (en) * 2020-11-27 2021-03-16 浙江世润建创科技发展有限公司 Slope section water pipeline and construction method thereof
CN113700981A (en) * 2021-09-03 2021-11-26 中国石油大学(华东) A bury ground pipeline landslide protector for protection of pipeline weak link

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘金涛: "管道横穿滑坡相互作用大尺度模型试验研究" *
赵晓刚、戴琳等: "埋地管道新型预应力抗滑桩的应用" *

Also Published As

Publication number Publication date
CN114215961B (en) 2023-10-27

Similar Documents

Publication Publication Date Title
JP6166264B2 (en) How to build a retaining wall
US10738436B1 (en) Tubular foundation for onshore wind turbine generators
JP2018024982A (en) Reinforcement method and reinforcement structure of existing pile foundation
CN103774674B (en) A kind of steel pipe underpinned pile and anchor pole deep foundation pit supporting structure and construction method thereof
CN105672450A (en) Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure
CN111042161B (en) A flexible treatment structure for high slopes with landslide accumulation and its construction method
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN109763852B (en) A kind of advance support structure suitable for loose stratum and its construction method
CN215669468U (en) Expand end concrete PHC strength nature stake
JP2013023978A (en) Method for reinforcing foundation for small-scale building
CN115233689A (en) Combined type enclosure structure for soft soil foundation pit and construction method thereof
CN109989414B (en) Assembled foundation
CN111305220A (en) Concrete support and structural top plate combined building system based on permanent and temporary combination and construction method thereof
CN114215961A (en) Construction method suitable for pipeline engineering supporting structure in landslide area
CN218233492U (en) A Supporting Structure for Deep Foundation Pit in Binary Stratum of Upper Soil and Lower Rock
CN216664179U (en) Supporting construction suitable for pipeline engineering in landslide area
CN206368375U (en) A kind of electric power pylon basis
CN113463682B (en) Corrugated plate retaining wall structure and construction method thereof
CN212506314U (en) A kind of pile-anchor support foundation pit deepening reinforcement support structure
CN116607548A (en) Side slope supporting structure and side slope supporting method
CN212896374U (en) Foundation pit support structure located in underground space of existing building
KR20130073336A (en) Pile structure and construction methods
CN210049264U (en) Assembled foundation
CN114508113A (en) Construction method of waist-supported anti-sliding pile structure
JP4968676B2 (en) Pile foundation reinforcement method using increased piles

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant