CN114197496B - Side slope reinforcing device of railway roadbed and construction method - Google Patents

Side slope reinforcing device of railway roadbed and construction method Download PDF

Info

Publication number
CN114197496B
CN114197496B CN202111544964.9A CN202111544964A CN114197496B CN 114197496 B CN114197496 B CN 114197496B CN 202111544964 A CN202111544964 A CN 202111544964A CN 114197496 B CN114197496 B CN 114197496B
Authority
CN
China
Prior art keywords
pile
slope
reinforced concrete
concrete slab
steel rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202111544964.9A
Other languages
Chinese (zh)
Other versions
CN114197496A (en
Inventor
吴静
王文虎
张乐文
张翔宇
郭德宇
宋志磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University
Original Assignee
Shandong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University filed Critical Shandong University
Priority to CN202111544964.9A priority Critical patent/CN114197496B/en
Publication of CN114197496A publication Critical patent/CN114197496A/en
Application granted granted Critical
Publication of CN114197496B publication Critical patent/CN114197496B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/48Piles varying in construction along their length, i.e. along the body between head and shoe, e.g. made of different materials along their length
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention discloses a side slope reinforcing device of a railway roadbed and a construction method, wherein the side slope reinforcing device comprises a reinforced concrete slab, an anchor rod pile, a tree root pile and a concrete foundation; the anchor rod pile is inserted into the slope surface of the railway roadbed side slope, the reinforced concrete slab is paved on the surface layer of the slope surface, the tree root pile is inserted into the slope toe and is positioned below the reinforced concrete slab, and a concrete foundation is poured at the slope toe; the anchor rod pile and the tree root pile have the same structure and respectively comprise a grout stopping plate, a trapezoidal sleeve and a pile body steel rail; the grout stopping plate is welded at one end of the pile body steel rail, the trapezoid sleeve is sleeved outside the pile body steel rail and fixed together with the pile body steel rail, the grout stopping plate is provided with a grout injecting hole, concrete is poured into the trapezoid sleeve through the grout injecting hole, and the waist plate of the trapezoid sleeve is provided with a plurality of grout outlet holes.

Description

一种铁路路基的边坡加固装置及施工方法Slope reinforcement device and construction method for railway embankment

技术领域technical field

本发明涉及边坡防护工程领域,具体尤其涉及一种针对铁路路基的边坡加固装置及施工方法。The invention relates to the field of slope protection engineering, in particular to a slope reinforcement device and a construction method for railway roadbeds.

背景技术Background technique

旧有的铁路收到周边环境的影响,开始出现各种问题,比如轨道的损蚀,路基的失稳等,这些问题严重影响了铁路交通线路的通行安全和整体服务水平。The old railway was affected by the surrounding environment, and various problems began to appear, such as the erosion of the track, the instability of the roadbed, etc. These problems seriously affected the traffic safety and overall service level of the railway traffic line.

在专利公开号为CN111962532A的申请中,公开了一种对既有铁路路基边坡斜打高压旋喷桩加固的施工方法,该施工方法是利用现有的混凝土桩进行现场浇筑的方式对边坡进行加固,该施工方法施工过程繁琐,且没有进行就地取材,造成了资源的浪费。In the application with the patent publication number of CN111962532A, a construction method for reinforcing the slope of the existing railway subgrade with high-pressure rotary grouting piles is disclosed. The construction method is to use the existing concrete piles to pour the slope For reinforcement, the construction process of this construction method is cumbersome, and no local materials are obtained, resulting in a waste of resources.

发明内容Contents of the invention

为了解决现有技术中存在的技术问题,本发明提出了一种新的铁路路基的边坡加固装置及施工方法,目的在于充分合理利用旧钢轨,对铁路路基边坡进行有效的加固,实现资源的合理利用和优化配置。In order to solve the technical problems existing in the prior art, the present invention proposes a new railway embankment slope reinforcement device and construction method. Reasonable utilization and optimal configuration.

为实现上述目的,本发明采用以下方案:To achieve the above object, the present invention adopts the following scheme:

本发明提出的一种针对铁路路基的边坡加固装置,包括钢筋混凝土板、锚杆桩、树根桩以及混凝土基础;所述的锚杆桩插装在铁路路基边坡的坡面内,钢筋混凝土板铺设在坡面表层,所述的树根桩插装在坡脚且位于钢筋混凝土板下方,在坡脚处浇筑有混凝土基础;The present invention proposes a slope reinforcement device for railway embankment, comprising reinforced concrete slabs, anchor piles, tree root piles and concrete foundations; the anchor piles are inserted into the slope of the railway embankment slope, Concrete slabs are laid on the surface of the slope, the root stakes are inserted at the foot of the slope and located under the reinforced concrete slab, and a concrete foundation is poured at the foot of the slope;

所述的锚杆桩、树根桩的结构相同,各自包括止浆板、梯形套筒以及桩体钢轨;所述的止浆板焊接在桩体钢轨的一端,梯形套筒套装在桩体钢轨外,与桩体钢轨固定在一起,在止浆板上设有注浆孔,通过注浆孔向梯形套筒内浇筑混凝土,在梯形套筒的腰板上设有若干出浆孔。The anchor piles and tree root piles have the same structure, and each includes a slurry-stopping plate, a trapezoidal sleeve and a pile body rail; the described slurry-stopping plate is welded on one end of the pile body rail, and the trapezoidal sleeve is sleeved on the pile body rail Outside, it is fixed with the steel rail of the pile body, and grouting holes are set on the grout stop plate, through which concrete is poured into the trapezoidal sleeve, and several grouting holes are set on the waist plate of the trapezoidal sleeve.

作为进一步的技术方案,所述的钢筋混凝土板内部一部分钢筋由加筋钢轨替代。As a further technical solution, a part of the steel bars inside the reinforced concrete slab is replaced by reinforced steel rails.

作为进一步的技术方案,所述的加筋钢轨包括多根依次排列的钢轨,每根钢轨的轨腰处钻若干连接孔,螺纹钢筋穿过连接孔将多根钢轨连接成一个整体,钢筋末端弯折后与钢轨贴合焊接。As a further technical solution, the reinforced rails include a plurality of rails arranged in sequence, and several connection holes are drilled at the rail waist of each rail, and the threaded steel bars pass through the connection holes to connect the multiple rails into a whole, and the ends of the steel bars are bent After folding, it is welded to the rail.

作为进一步的技术方案,所述的加筋钢轨沿坡面纵向布置,加筋钢轨距钢筋混凝土板底部具有设定的距离,且使用撑筋固定。As a further technical solution, the reinforced steel rails are arranged longitudinally along the slope, the reinforced steel rails have a set distance from the bottom of the reinforced concrete slab, and are fixed with braces.

作为进一步的技术方案,所述的锚杆桩沿水平方向向下打入土体,位于钢筋混凝土板纵向的中间和远离坡脚的一端,共两行,每行打入两根锚杆桩。As a further technical solution, the anchor piles are driven downward into the soil along the horizontal direction, located in the longitudinal middle of the reinforced concrete slab and at the end far away from the slope foot, in two rows, and two anchor piles are driven into each row.

作为进一步的技术方案,所述的桩体钢轨在其连接止浆板的一端设有凹口。As a further technical solution, the pile body rail is provided with a notch at one end connected to the anti-slip plate.

作为进一步的技术方案,所述的梯形套筒的横截面为等腰梯形,在套筒腰板中间部位钻直径圆孔,螺纹钢筋连接梯形套筒与桩体钢轨,两端弯折固定。As a further technical solution, the cross-section of the trapezoidal sleeve is isosceles trapezoidal, and a diameter circular hole is drilled in the middle of the waist plate of the sleeve, and the threaded steel bar connects the trapezoidal sleeve and the rail of the pile body, and the two ends are bent and fixed.

作为进一步的技术方案,所述的止浆板为等腰梯形,止浆板上部为柱状握柄,下部中间为正方体凸口,用以与桩体钢轨凹口贴合后焊接,在凸口左右有注浆孔。As a further technical solution, the slurry stop plate is isosceles trapezoidal, the upper part of the slurry stop plate is a columnar handle, and the middle of the lower part is a cube convex, which is used for welding after fitting with the notch of the rail of the pile body. There are grouting holes.

作为进一步的技术方案,所述的树根桩垂直向下打入土体,在树根桩上部用钢轨焊接。As a further technical solution, the root pile is driven vertically downward into the soil, and the upper part of the root pile is welded with a steel rail.

作为进一步的技术方案,所述的混凝土基础与钢筋混凝土板共同浇筑,用以固定连接钢筋混凝土板与树根桩。As a further technical solution, the concrete foundation and the reinforced concrete slab are poured together to fix and connect the reinforced concrete slab and the tree root pile.

第二方面,本发明还提供了一种针对铁路路基的边坡加固装置的施工方法,包括以下步骤:In a second aspect, the present invention also provides a construction method for a slope reinforcement device for a railway embankment, comprising the following steps:

步骤A,按照设计坡度修整坡面,对钢筋混凝土板进行放样定位确定轴线、轮廓和坡度,确定锚杆桩孔和树根桩孔的位置,开挖钢筋混凝土板基槽与混凝土基础基槽;Step A, modifying the slope according to the design slope, setting out and positioning the reinforced concrete slab to determine the axis, contour and slope, determining the positions of the anchor pile holes and tree root pile holes, and excavating the reinforced concrete slab foundation groove and the concrete foundation groove;

步骤B,对锚杆桩位置采用干钻的方式钻孔,钻孔为贴近锚杆桩的梯形,之后进行清孔处理,将止浆板的凸口与桩体钢轨的凹口贴合后焊接,将梯形套筒套入桩体钢轨,使用钢筋固定梯形套筒与桩体钢轨,后焊接梯形套筒与止浆板,将制备的锚杆桩放入钻孔中,固定好位置后进行注浆处理;Step B: Drilling the position of the anchor pile by dry drilling, the drill hole is a trapezoidal shape close to the anchor pile, and then cleaning the hole, and welding the protrusion of the slurry plate and the notch of the rail of the pile body after fitting , insert the trapezoidal sleeve into the pile rail, use steel bars to fix the trapezoidal sleeve and the pile rail, then weld the trapezoidal sleeve and the slurry plate, put the prepared anchor pile into the drilled hole, fix the position and inject slurry treatment;

步骤C,对树根桩位置采用干钻的方式钻孔,钻孔为贴近树根桩的梯形,之后进行清孔处理,树根桩制备步骤同锚杆桩,将制备的树根桩竖直放入钻孔,进行注浆处理,采用水泥塞封孔,在树根桩上部,用钢轨焊接为一体;Step C, the position of the tree root pile is drilled by dry drilling, the hole is a trapezoidal shape close to the tree root pile, and then the hole is cleaned. The preparation steps of the tree root pile are the same as the anchor pile, and the prepared tree root pile is vertically Put it into the drilled hole, carry out grouting treatment, use cement plug to seal the hole, and weld it with steel rail on the upper part of the tree root pile;

步骤D,在开挖好的基槽中安装钢筋混凝土板与混凝土地基的模板装置,内部使用撑筋将加筋钢轨位置固定,将螺纹钢筋穿插加筋钢轨的圆孔连接,钢筋末端弯折后与加筋钢轨贴合焊接,将混凝土搅拌均匀,往模板中浇筑混凝土,直至混凝土板与混凝土基础成形,浇筑完成后进行洒水养护,最后拆模。Step D, install the reinforced concrete slab and the formwork device of the concrete foundation in the excavated foundation groove, use braces inside to fix the position of the reinforced rail, insert the threaded steel bar through the round hole of the reinforced rail to connect, and bend the end of the steel bar Fitting and welding with the reinforced steel rail, mixing the concrete evenly, pouring concrete into the formwork until the concrete slab and the concrete foundation are formed, after the pouring is completed, sprinkle water for maintenance, and finally remove the formwork.

本发明的有益效果如下:The beneficial effects of the present invention are as follows:

(1)本发明所提供的一种铁路路基的边坡加固装置及施工方法,布置完成后能够对边坡面进行足够有效的约束,防治边坡滑移,可以应用于路基边坡的加固工程。(1) The side slope reinforcement device and construction method of a railway subgrade provided by the present invention can effectively restrain the side slope surface after the arrangement is completed, prevent the side slope from slipping, and can be applied to the reinforcement project of the subgrade side slope .

(2)本发明所提供的一种铁路路基的边坡加固装置及施工方法,钢筋混凝土板、锚杆桩和树根桩中使用废旧钢轨用来代替原有的钢筋笼和钢管,且通过对钢筋混凝土板、锚杆桩和树根桩的结构和构造进行合理设计,一方面达到了合理利用废弃材料,变废为宝,降低成本的目的,另一方面实现了对边坡的加固。(2) a kind of side slope reinforcing device and construction method of railway embankment provided by the present invention, use waste and old steel rail to replace original reinforcement cage and steel pipe in reinforced concrete slab, anchor pile and tree root pile, and by The structure and structure of reinforced concrete slabs, anchor piles and tree root piles are rationally designed. On the one hand, it achieves the purpose of rationally utilizing waste materials, turning waste into treasure, and reducing costs. On the other hand, it realizes the reinforcement of the slope.

(3)本发明所提供的一种铁路路基的边坡加固装置及施工方法,使用梯形套筒,不仅能够固定内部的桩体钢轨,同时相较于常规的圆形套筒,更加节省材料,成本更低。(3) The slope reinforcement device and construction method of a railway embankment provided by the present invention uses a trapezoidal sleeve, which can not only fix the internal pile rail, but also saves materials compared with conventional circular sleeves. The cost is lower.

(4)本发明所提供的一种铁路路基的边坡加固装置及施工方法,使用锚杆桩、钢筋混凝土板与树根桩结合护坡的手段。钢筋混凝土板能够有效地保护坡面不受侵蚀,防止坡面土体的剥落;锚杆桩与树根桩能够在边坡潜在滑动面的不同位置进行支护。(4) A kind of side slope reinforcing device and construction method of railway embankment provided by the present invention use the means of slope protection combined with anchor piles, reinforced concrete slabs and tree root piles. The reinforced concrete slab can effectively protect the slope from erosion and prevent the spalling of the soil on the slope; the anchor piles and tree root piles can support different positions on the potential sliding surface of the slope.

(5)本发明所提供的一种铁路路基的边坡加固装置及施工方法,锚杆桩、树根桩共同与钢筋混凝土板连接,对钢筋混凝土板进行紧密固定。(5) In the slope reinforcement device and construction method of a railway embankment provided by the present invention, the anchor pile and the tree root pile are jointly connected with the reinforced concrete slab, and the reinforced concrete slab is tightly fixed.

附图说明Description of drawings

构成本发明的一部分的说明书附图用来提供对本发明的进一步理解,本发明的示意性实施例及其说明用于解释本发明,并不构成对本发明的不当限定。The accompanying drawings constituting a part of the present invention are used to provide a further understanding of the present invention, and the schematic embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations to the present invention.

图1为边坡与加固布置图;Figure 1 is the slope and reinforcement layout;

图2为加筋钢轨布置示意图;Figure 2 is a schematic diagram of the layout of the reinforced rail;

图3为锚杆桩和树根桩示意图;Fig. 3 is the schematic diagram of anchor pile and tree root pile;

图4为锚杆桩和树根桩细部结构图;Fig. 4 is the detailed structural diagram of anchor pile and tree root pile;

图5为止浆板示意图;Figure 5 is a schematic diagram of a slurry plate;

图6为桩体钢轨示意图;Fig. 6 is a schematic diagram of pile rail;

其中,1、钢筋混凝土板,2、锚杆桩,3、树根桩,4、混凝土基础,5、加筋钢轨,6、螺纹钢筋,7、止浆板,8、梯形套筒,9、桩体钢轨,10、出浆孔,11、螺纹钢筋,12、握柄,13、注浆孔,14、凸口,15、凹口,16、钻孔。Among them, 1. Reinforced concrete slab, 2. Anchor pile, 3. Tree root pile, 4. Concrete foundation, 5. Reinforced steel rail, 6. Threaded steel bar, 7. Grout stopper, 8. Trapezoidal sleeve, 9. Pile rail, 10, grout hole, 11, threaded steel bar, 12, handle, 13, grouting hole, 14, protrusion, 15, notch, 16, bore.

具体实施方式Detailed ways

应该指出,以下详细说明都是例示性的,旨在对本发明提供进一步的说明。除非另有指明,本发明使用的所有技术和科学术语具有与本发明所属技术领域的普通技术人员通常理解的相同含义。It should be noted that the following detailed description is exemplary and intended to provide further explanation of the present invention. Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs.

需要注意的是,这里所使用的术语仅是为了描述具体实施方式,而非意图限制根据本发明的示例性实施方式。如在这里所使用的,除非本发明另外明确指出,否则单数形式也意图包括复数形式,此外,还应当理解的是,当在本说明书中使用术语“包含”和/或“包括”时,其指明存在特征、步骤、操作、器件、组件和/或它们的组合;It should be noted that the terminology used here is only for describing specific embodiments, and is not intended to limit exemplary embodiments according to the present invention. As used herein, unless the invention clearly states otherwise, the singular form is also intended to include the plural form. In addition, it should also be understood that when the terms "comprising" and/or "comprising" are used in this specification, their Indicate the presence of features, steps, operations, means, components and/or combinations thereof;

术语解释部分:本发明中所述的“加筋钢轨”是指钢轨之间通过螺纹钢筋连接,因此将其命名为了“加筋钢轨”。本发明中的“边坡纵向”是指坡线方向。Explanation of terms: The "reinforced steel rail" mentioned in the present invention means that the steel rails are connected by threaded steel bars, so it is named "reinforced steel rail". "Slope longitudinal direction" in the present invention refers to the slope line direction.

本实施例提出了一种针对铁路路基的边坡加固装置,主要由以下部分组成,包括铺设在路基坡面上的钢筋混凝土板1、锚杆桩2、树根桩3以及混凝土基础4;所述的锚杆桩2插装在铁路路基边坡的坡面内,钢筋混凝土板1铺设在坡面表层,所述的树根桩3插装在坡脚且位于钢筋混凝土板下方,在坡脚处浇筑有混凝土基础;锚杆桩2、树根桩3的结构相同,各自包括止浆板、梯形套筒以及桩体钢轨;止浆板焊接在桩体钢轨的一端,梯形套筒套装在桩体钢轨外,与桩体钢轨固定在一起,在止浆板上设有注浆孔,通过注浆孔向梯形套筒内浇筑混凝土,在梯形套筒的腰板上设有若干出浆孔。本发明所提供的经济可靠的边坡加固装置,钢筋混凝土板、锚杆桩和树根桩中使用废旧钢轨用来代替原有的钢筋笼和钢管,且通过对钢筋混凝土板、锚杆桩和树根桩的结构和构造进行合理设计,一方面达到了合理利用废弃材料,变废为宝,降低成本的目的,另一方面实现了对边破的加固。This embodiment proposes a slope reinforcement device for railway subgrade, which mainly consists of the following parts, including a reinforced concrete slab 1 laid on the slope of the subgrade, anchor piles 2, tree root piles 3 and concrete foundation 4; The anchor piles 2 are inserted in the slope of the railway embankment slope, the reinforced concrete slab 1 is laid on the surface of the slope, the root pile 3 is inserted in the foot of the slope and is located below the reinforced concrete slab, and at the foot of the slope A concrete foundation is poured at the place; the structure of the anchor pile 2 and the tree root pile 3 is the same, each including a slurry-stopping plate, a trapezoidal sleeve and a pile rail; the slurry-stopping plate is welded on one end of the pile body rail, and the trapezoidal sleeve is set on the Outside the steel rail of the pile body, it is fixed with the steel rail of the pile body. A grouting hole is provided on the grout stop plate, and concrete is poured into the trapezoidal sleeve through the grouting hole, and several grouting holes are set on the waist plate of the trapezoidal sleeve. In the economical and reliable slope reinforcement device provided by the present invention, the reinforced concrete slab, the anchor pile and the tree root pile use waste steel rails to replace the original steel cage and steel pipe, and through the reinforcement of the reinforced concrete slab, the anchor pile and the The structure and structure of the tree root pile are designed reasonably, on the one hand, it achieves the purpose of rational use of waste materials, turning waste into treasure, and reducing costs, and on the other hand, it realizes the reinforcement of the edge.

进一步,本实施例中在路基坡面上铺设的钢筋混凝土板1内部一部分钢筋由加筋钢轨5替代,相对于现有技术合理利用废弃材料,变废为宝,降低成本。且本实施例中所铺设的钢筋混凝土板1优选的所用混凝土为C25型普通混凝土,厚度优选为0.3m,沿坡面纵向长为6m,水平宽为3m,钢筋混凝土板1沿坡脚覆盖于坡面上,混凝土板入土深度优选为0.2m。进一步的,本实施例中所使用的加筋钢轨采用废弃的50kg/m标准轨和螺纹钢筋连接形成,切割后每根标准轨的长度优选为6m,轨腰处钻孔然后与螺纹钢筋6相连制成加筋钢轨5,加筋钢轨5的标准轨沿坡面纵向布置,优选的,在一块钢筋混凝土板1中的标准轨布置10根,相邻标准轨之间的间隔0.3m,标准轨距钢筋混凝土板1的底部距离为70mm,且使用型号为Φ12HRB400的撑筋固定。Furthermore, in this embodiment, a part of the steel bars inside the reinforced concrete slab 1 laid on the slope of the roadbed is replaced by the reinforced steel rail 5. Compared with the prior art, the waste materials are rationally used to turn waste into wealth and reduce costs. And the preferred concrete used for the reinforced concrete slab 1 laid in the present embodiment is C25 type ordinary concrete, the thickness is preferably 0.3m, the longitudinal length along the slope is 6m, and the horizontal width is 3m. On the slope, the depth of the concrete slab embedded in the soil is preferably 0.2m. Further, the reinforced rails used in this embodiment are formed by connecting discarded 50kg/m standard rails with threaded steel bars. After cutting, the length of each standard rail is preferably 6m, and holes are drilled at the rail waist and then connected with threaded steel bars 6 The reinforced steel rail 5 is made, and the standard rails of the reinforced steel rail 5 are arranged longitudinally along the slope. Preferably, 10 standard rails are arranged in a reinforced concrete slab 1, and the interval between adjacent standard rails is 0.3m. The distance from the bottom of the reinforced concrete slab 1 is 70mm, and it is fixed with a Φ12HRB400 brace.

进一步的,所述的标准轨的轨腰中间钻圆孔,优选的直径为20mm,位于两端的圆孔距钢轨端0.2m,内部圆孔距离为0.4m,且共计15个圆孔,然后采用15根型号为Φ18HRB400的螺纹钢筋6穿插10根加筋钢轨的圆孔连接固定,螺纹钢筋6末端弯折后与钢轨贴合焊接,使得多根标准轨之间连接成一个整体,具有一定的强度。Further, a round hole is drilled in the middle of the rail waist of the standard rail, the preferred diameter is 20mm, the round holes at both ends are 0.2m away from the rail end, and the distance between the inner round holes is 0.4m, and there are 15 round holes in total, and then use 15 threaded steel bars 6 of model Φ18HRB400 are interspersed with the round holes of 10 reinforced steel rails for connection and fixation. The ends of threaded steel bars 6 are bent and welded to the rails, so that multiple standard rails are connected into a whole with a certain strength. .

进一步的,所述的锚杆桩2由止浆板7、梯形套筒8以及桩体钢轨9三部分组成,用以固定边坡土体与钢筋混凝土板1。锚杆桩2沿水平方向向下打入土体,优选的,角度为15°,锚杆桩2位于钢筋混凝土板1纵向的中间和远离坡脚的一端,共两行如图1所示,优选的每行打入两根锚杆桩2,桩距1.5m,锚杆桩2与钢筋混凝土板1侧面距离0.75m,最上方锚杆桩2与钢筋混凝土板1顶面距离为0.3m。Further, the anchor pile 2 is composed of three parts: a grout stop plate 7 , a trapezoidal sleeve 8 and a pile rail 9 , and is used to fix the slope soil and the reinforced concrete slab 1 . Anchor piles 2 are driven downward into the soil along the horizontal direction, preferably, the angle is 15°, anchor piles 2 are located in the middle of the longitudinal direction of the reinforced concrete slab 1 and one end away from the foot of the slope, and there are two rows as shown in Figure 1. Preferably, two anchor piles 2 are driven into each row, the pile distance is 1.5m, the distance between the anchor pile 2 and the side of the reinforced concrete slab 1 is 0.75m, and the distance between the top anchor pile 2 and the top surface of the reinforced concrete slab 1 is 0.3m.

进一步的,所述的桩体钢轨9也采用废弃的50kg/m标准轨,其优选的长度为6m,轨腰中间钻孔16,设置该孔的目的主要是为了浆液可以在桩体钢轨9内部流动;优选为,钻孔16的直径为20mm,位于两段的圆孔距钢轨端距离优选的为0.2m,内部圆孔距离0.4m,因此共计15个。Further, the pile body rail 9 also adopts the discarded 50kg/m standard rail, its preferred length is 6m, and a hole 16 is drilled in the middle of the rail waist. Flow; preferably, the diameter of the borehole 16 is 20mm, the distance between the two round holes and the rail end is preferably 0.2m, and the distance between the inner round holes is 0.4m, so there are 15 holes in total.

进一步的,本实施例中桩体钢轨9在其连接止浆板7的一端,钢轨轨腰中间部位切割下宽度为50mm、深度为50mm的长方体凹口15,当然不难理解的,凹口15还可以是其他形状以及其他尺寸。Further, in this embodiment, the pile body rail 9 cuts a rectangular parallelepiped notch 15 with a width of 50 mm and a depth of 50 mm at the end of the pile body rail 9 connected to the slurry stop plate 7. Of course, it is not difficult to understand that the notch 15 Other shapes and other dimensions are also possible.

进一步的,所述的梯形套筒8,其优选的材料为Q235A碳素结构钢,长为6m,横截面为等腰梯形,内截面上底宽为74mm,下底宽为160mm,高度为155mm,套筒厚度为10mm,在套筒腰板中间部位,距远离止浆板8一端0.2m与3m处钻直径为25mm圆孔,使用型号为Φ18HRB400的螺纹钢筋11连接梯形套筒8与桩体钢轨9,两段弯折固定,套筒腰板1.5m以下均匀钻圆形出浆孔10,出浆孔10的直径优选为10mm。本发明使用梯形套筒,不仅能够固定内部的桩体钢轨,同时相较于常规的圆形套筒,更加节省材料,成本更低。Further, the preferred material of the trapezoidal sleeve 8 is Q235A carbon structural steel, the length is 6m, the cross section is isosceles trapezoidal, the upper bottom width of the inner section is 74mm, the lower bottom width is 160mm, and the height is 155mm , the thickness of the sleeve is 10mm, drill a round hole with a diameter of 25mm in the middle of the waist plate of the sleeve, 0.2m and 3m away from the end of the slurry plate 8, and connect the trapezoidal sleeve 8 and the pile body rail with the threaded steel bar 11 of model Φ18HRB400 9. The two sections are bent and fixed, and the circular slurry hole 10 is evenly drilled below 1.5m of the sleeve waist plate. The diameter of the slurry hole 10 is preferably 10mm. The invention uses the trapezoidal sleeve, which not only can fix the internal pile rail, but also saves more material and lower cost compared with the conventional circular sleeve.

进一步的,所述的止浆板7,其优选的材料为Q235A碳素钢,止浆板7的截面等腰梯形,其尺寸优选的,上底宽为150mm,下底宽为215mm,高为235mm,厚度为10mm,止浆板7上部为柱形握柄12,下部中间为正方体凸口14,长度为30mm,用以与桩体钢轨9的凹口15贴合后焊接,在凸口14左右有两个直径为32mm注浆孔13,止浆板7与梯形套筒8贴合后焊接,注浆孔13的作用主要是用于后期向桩体内部注浆Further, the preferred material of the slurry stop plate 7 is Q235A carbon steel. The cross section of the slurry stop plate 7 is isosceles trapezoidal, and its size is preferred. The width of the upper bottom is 150mm, the width of the lower bottom is 215mm, and the height is 235mm, the thickness is 10mm, the upper part of the slurry plate 7 is a cylindrical handle 12, the middle of the lower part is a cube convex 14, and the length is 30mm, which is used for welding after fitting with the notch 15 of the pile rail 9, and on the convex 14 There are two grouting holes 13 with a diameter of 32mm on the left and right. The grout stop plate 7 and the trapezoidal sleeve 8 are welded after bonding. The function of the grouting holes 13 is mainly used for grouting into the pile body in the later stage.

进一步的,所述的树根桩3,由经过止浆板7、梯形套筒8以及桩体钢轨9三部分组成,结构与锚杆桩2相同,在此不进行赘述了,本实施例中树根桩3的长为6m,位于坡脚处,钢筋混凝土板1下方,垂直向下打入土体,共3根,桩距为1.2m,在3根树根桩上部,用长度为2.5m的钢轨焊接。Further, the tree root pile 3 is composed of three parts passing through the pulp stop plate 7, the trapezoidal sleeve 8 and the pile rail 9, and its structure is the same as that of the anchor pile 2. The root pile 3 has a length of 6m and is located at the foot of the slope, below the reinforced concrete slab 1, and is driven into the soil vertically downwards. There are 3 piles in total with a pile distance of 1.2m. m rail welding.

进一步的,所述的混凝土基础4与钢筋混凝土板1共同浇筑,用以固定连接钢筋混凝土板1与树根桩3,本实施例中混凝土基础材料4优选为C25型普通混凝土,其长为3m,宽为0.5m,高为0.7m,入土深度0.2m。Further, the concrete foundation 4 and the reinforced concrete slab 1 are poured together to fixedly connect the reinforced concrete slab 1 and the tree root pile 3. In this embodiment, the concrete foundation material 4 is preferably C25 type ordinary concrete, and its length is 3m , with a width of 0.5m, a height of 0.7m, and a depth of 0.2m.

进一步的,本实施例还提出了一种利用上述铁路路基的边坡加固装置对边坡进行加固的方法,包括以下步骤:Further, this embodiment also proposes a method for reinforcing the slope using the above-mentioned slope reinforcement device for the railway embankment, including the following steps:

步骤A,按照设计坡度修整坡面,对钢筋混凝土板1进行放样定位确定轴线、轮廓和坡度,确定锚杆桩孔和树根桩孔的位置,开挖钢筋混凝土板1基槽与混凝土基础4基槽,深度0.2m;Step A, modify the slope according to the design slope, carry out lofting and positioning on the reinforced concrete slab 1 to determine the axis, contour and slope, determine the positions of the anchor pile holes and tree root pile holes, excavate the foundation groove of the reinforced concrete slab 1 and the concrete foundation 4 Foundation trench, depth 0.2m;

步骤B,对锚杆桩2位置采用干钻的方式钻孔,钻孔为贴近锚杆桩的梯形,之后进行清孔处理,将止浆板7的凸口14与桩体钢轨9的凹口15贴合后焊接,将梯形套筒套8套入桩体钢轨9,将钢筋11插入到梯形套筒8与桩体钢轨9后,钢筋11固定梯形套筒8与桩体钢轨9,后焊接梯形套筒8与止浆板7,将制备的锚杆桩2放入钻孔中,固定好位置后进行注浆处理,注浆压力为0.3~0.5MPa,保持时间20min,采用水泥塞封孔,封孔深度1.5m;Step B, dry-drilling is used to drill the anchor pile 2, the drill hole is trapezoidal close to the anchor pile, and then the hole cleaning process is carried out, and the protrusion 14 of the grout stop plate 7 and the notch of the pile rail 9 15 Welding after bonding, put the trapezoidal sleeve sleeve 8 into the pile body rail 9, insert the steel bar 11 into the trapezoidal sleeve 8 and the pile body rail 9, fix the trapezoidal sleeve 8 and the pile body rail 9 with the steel bar 11, and then weld Trapezoidal sleeve 8 and grout stop plate 7, put the prepared anchor pile 2 into the borehole, fix the position and perform grouting treatment, the grouting pressure is 0.3-0.5MPa, the holding time is 20min, and the hole is sealed with cement plug , the sealing depth is 1.5m;

步骤C,对树根桩3位置采用干钻的方式钻孔,钻孔为贴近树根桩的梯形,之后进行清孔处理,树根桩3制备步骤同步骤2中的锚杆桩2制作步骤,将制备的树根桩3竖直放入钻孔,进行注浆处理,注浆压力为0.3~0.5Mpa,保持时间20min,采用水泥塞封孔,封孔深度1.5m,在3根树根桩上部,用长度为2.5m的钢轨焊接为一体;Step C: Drilling the position of the tree root pile 3 by means of dry drilling, the drill hole is a trapezoidal shape close to the tree root pile, and then cleaning the hole, the preparation steps of the tree root pile 3 are the same as the production steps of the anchor pile 2 in step 2 , put the prepared tree root pile 3 vertically into the borehole, and perform grouting treatment. The grouting pressure is 0.3-0.5Mpa, and the holding time is 20min. The upper part of the pile is welded together with a steel rail with a length of 2.5m;

步骤D,在开挖好的基槽中安装钢筋混凝土板1与混凝土地基4的模板装置,内部使用撑筋将10根加筋钢轨5位置固定,将螺纹钢筋6穿插过加筋钢轨5连接,螺纹钢筋6末端弯折后与加筋钢轨5贴合焊接,将混凝土搅拌均匀,往模板中浇筑混凝土,直至混凝土板1与混凝土基础4浇筑成形,浇筑完成后进行洒水养护,养护时间不少于7天,最后进行拆模。Step D, install the reinforced concrete slab 1 and the formwork device of the concrete foundation 4 in the excavated foundation trench, use braces inside to fix the position of 10 reinforced steel rails 5, and insert the threaded steel bars 6 through the reinforced steel rails 5 to connect, After the end of the threaded steel bar 6 is bent, it is bonded and welded with the reinforced steel rail 5, the concrete is stirred evenly, and the concrete is poured into the formwork until the concrete slab 1 and the concrete foundation 4 are poured into shape. 7 days, and finally demoulding.

本发明所提供的经济可靠的边坡加固装置,布置完成后能够对边坡面进行足够有效的约束,防治边坡滑移,可以应用于路基边坡的加固工程。The economical and reliable side slope reinforcement device provided by the present invention can sufficiently and effectively restrain the side slope surface after the arrangement is completed, prevent the side slope from slipping, and can be applied to the reinforcement project of the roadbed side slope.

以上所述仅为本发明的优选实施例而已,并不用于限制本发明,对于本领域的技术人员来说,本发明可以有各种更改和变化。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and changes. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention shall be included within the protection scope of the present invention.

Claims (8)

1. A side slope reinforcing device of a railway roadbed is characterized by comprising a reinforced concrete slab, anchor rod piles, tree root piles and a concrete foundation; the anchor rod pile is inserted into the slope surface of the railway roadbed side slope, the reinforced concrete slab is paved on the surface layer of the slope surface, the root pile is inserted into the slope toe and is positioned below the reinforced concrete slab, and a concrete foundation is poured at the slope toe;
the anchor rod pile and the root pile have the same structure and respectively comprise a grout stopping plate, a trapezoidal sleeve and a pile body steel rail; the grout stopping plate is welded at one end of the pile body steel rail, the trapezoid sleeve is sleeved outside the pile body steel rail and fixed with the pile body steel rail, the grout stopping plate is provided with a grout injecting hole, concrete is poured into the trapezoid sleeve through the grout injecting hole, and a waist plate of the trapezoid sleeve is provided with a plurality of grout outlet holes;
the concrete foundation and the reinforced concrete slab are cast together;
part of steel bars in the reinforced concrete slab are replaced by reinforced steel rails;
the reinforced steel rails are longitudinally arranged along the slope, have a set distance from the bottom of the reinforced concrete slab and are fixed by using the supporting ribs;
and waste steel rails are adopted in the reinforced concrete slab, the anchor rod pile and the root pile.
2. The slope reinforcing apparatus for a railroad bed of claim 1, wherein the reinforcement rails include a plurality of rails and reinforcing bars arranged in sequence, a plurality of connecting holes are drilled at the web of each rail, the reinforcing bars pass through the connecting holes to connect the plurality of rails into a whole, and the ends of the reinforcing bars are bent and then welded to the rails.
3. The slope reinforcement for a railroad bed according to claim 1, wherein the anchor piles are driven into the soil body in two rows in the middle of the longitudinal direction of the reinforced concrete slab and at the end away from the toe, and two anchor piles are driven in each row.
4. The slope reinforcement for a railroad bed of claim 1, wherein said piling rail is notched at its end connected to the grout stop.
5. The slope reinforcing apparatus for railroad bed of claim 4, wherein the grout stop plate is an isosceles trapezoid, the upper portion of the grout stop plate is a columnar grip, the middle portion of the lower portion of the grout stop plate is a flange for welding after being attached to the notch of the steel rail of the pile body, and grouting holes are formed on the left and right of the flange.
6. The slope reinforcing apparatus for railroad bed of claim 5, wherein the cross section of the trapezoid sleeve is isosceles trapezoid, a diameter circular hole is drilled in the middle of the sleeve waist plate, and the screw steel bar is connected with the trapezoid sleeve and the pile body steel rail, and both ends are bent and fixed.
7. The slope reinforcing apparatus for a railroad bed according to claim 1, wherein the root piles are driven vertically downward into the soil body, and the upper portions of the root piles are welded by rails.
8. The method for constructing a slope reinforcement apparatus for a railroad bed according to any one of claims 1 to 7, comprising the steps of:
step A, finishing a slope surface according to a designed gradient, lofting and positioning a reinforced concrete plate to determine an axis, an outline and the gradient, determining positions of an anchor rod pile hole and a tree root pile hole, and excavating a reinforced concrete plate foundation trench and a concrete foundation trench;
b, drilling the anchor rod pile position, wherein the drilled hole is a trapezoid close to the anchor rod pile, then cleaning the hole, welding a convex opening of a grout stop plate after being attached to a notch of a pile body steel rail, sleeving a trapezoid sleeve into the pile body steel rail, fixing the trapezoid sleeve and the pile body steel rail by using a steel bar, then welding the trapezoid sleeve and the grout stop plate, placing the prepared anchor rod pile into the drilled hole, and performing grouting treatment after the position is fixed;
c, drilling the position of the root pile, wherein the drilled hole is in a trapezoid shape close to the root pile, then cleaning the hole, the root pile preparation step is the same as that of the anchor rod pile in the step B, the prepared root pile is vertically placed into the drilled hole for grouting treatment, a cement plug is adopted for sealing the hole, and the upper part of the root pile is welded into a whole by a steel rail;
and D, installing a template device of the reinforced concrete slab and the concrete foundation in the excavated foundation trench, fixing the position of the reinforced steel rail by using a supporting rib inside the template device, inserting a twisted steel bar into a circular hole of the reinforced steel rail for connection, bending the tail end of the steel bar, then jointing and welding the bent steel bar and the reinforced steel rail, stirring the concrete, pouring the concrete into the template until the concrete slab and the concrete foundation are formed, maintaining after pouring is finished, and finally removing the template.
CN202111544964.9A 2021-12-16 2021-12-16 Side slope reinforcing device of railway roadbed and construction method Expired - Fee Related CN114197496B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111544964.9A CN114197496B (en) 2021-12-16 2021-12-16 Side slope reinforcing device of railway roadbed and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111544964.9A CN114197496B (en) 2021-12-16 2021-12-16 Side slope reinforcing device of railway roadbed and construction method

Publications (2)

Publication Number Publication Date
CN114197496A CN114197496A (en) 2022-03-18
CN114197496B true CN114197496B (en) 2023-03-10

Family

ID=80654752

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111544964.9A Expired - Fee Related CN114197496B (en) 2021-12-16 2021-12-16 Side slope reinforcing device of railway roadbed and construction method

Country Status (1)

Country Link
CN (1) CN114197496B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115370187A (en) * 2022-09-14 2022-11-22 中铁十局集团有限公司 Method for reinforcing railway contact net stand column in soft soil layer
CN118653498B (en) * 2024-08-21 2024-10-29 中交二公局华西建设有限公司 Protective structure and construction method for high-speed underpass of heavy-load railway
CN119041459B (en) * 2024-11-04 2025-03-04 武汉中交试验检测加固工程有限责任公司 A construction device and method for assembling cast-in-place lattice beams for slope rescue

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101831976A (en) * 2009-12-24 2010-09-15 湖南大学 Prefabricated steel rib bottom plate-concrete overlapped hollow floor system
JP2012145006A (en) * 2011-01-11 2012-08-02 Sasakura Engineering Co Ltd Thermo compressor and seawater desalination system provided with the same
CN208136918U (en) * 2018-03-02 2018-11-23 大连理工大学 A kind of tubular type Soil-Nailing Wall Structure
CN109235465A (en) * 2018-09-20 2019-01-18 中铁二院工程集团有限责任公司 Squeeze into the superpower concrete tubular pile breast wall type packaged combination anti-slide pile structure of prestressing force

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101831976A (en) * 2009-12-24 2010-09-15 湖南大学 Prefabricated steel rib bottom plate-concrete overlapped hollow floor system
JP2012145006A (en) * 2011-01-11 2012-08-02 Sasakura Engineering Co Ltd Thermo compressor and seawater desalination system provided with the same
CN208136918U (en) * 2018-03-02 2018-11-23 大连理工大学 A kind of tubular type Soil-Nailing Wall Structure
CN109235465A (en) * 2018-09-20 2019-01-18 中铁二院工程集团有限责任公司 Squeeze into the superpower concrete tubular pile breast wall type packaged combination anti-slide pile structure of prestressing force

Also Published As

Publication number Publication date
CN114197496A (en) 2022-03-18

Similar Documents

Publication Publication Date Title
CN114197496B (en) Side slope reinforcing device of railway roadbed and construction method
CN108385455A (en) A kind of board-like Construction of Ballastless Track maintenance activity method of cast-in-place railway roadbed
CN106013191A (en) Environmental-friendly grass concrete highway slope protection structure and construction method thereof
CN109611102A (en) A construction method of cold excavation underpass overpass
CN106193141B (en) A kind of impaired pier footing method for reinforcing of earthquake
CN112324475A (en) Method for reinforcing shield tunnel lining structure
CN111335915B (en) Section steel supporting structure and method for repairing damage of tunnel inverted arch crown
CN108166397A (en) Railway frame bridge construction method
CN105951612B (en) Stake head bug repairing and reinforcement structure and its construction method under active service bridge water
CN106320120A (en) Construction process for pile slab type non-soil roadbed highway
CN111648787A (en) A method of using ultra-high performance concrete to reinforce shield tunnel lining structure
CN111577334A (en) Operating tunnel inverted arch repairing method
CN106869151A (en) A kind of bridge construction method of deep foundation ditch
CN201395794Y (en) Foundation pit with concealed columns and soil nailing
CN112144559B (en) Well construction method in high-water-rich loess sand pebble stratum pressure-variable pipe well
CN110055973A (en) Construction space foundation pit enclosure structure and water-stopping method under by high metal bridge in limited time
CN111119928B (en) Novel tunnel primary support structure and construction method
CN101538832B (en) Construction method for controlling two-dimension jacking of large-scale case
CN112096419A (en) Supporting structure and method for repairing tunnel secondary lining damage
CN112048959A (en) A kind of transverse grouting roadbed reinforcement structure and roadbed repair method
CN105442457B (en) Construction structure and method for extending bridge floor plate bridge filled with fine sand
CN106049563A (en) Earthquake damaged bridge pier foundation reinforcing and strengthening system
CN109853624B (en) Extension construction method for existing highway rectangular culvert
CN210946876U (en) Barricade reinforced structure convenient to road surface is widened
CN109577318B (en) Construction method of spiral heat pipe annular convex rib first drainage and then grouting bamboo pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20230310

CF01 Termination of patent right due to non-payment of annual fee