CN114109026B - Tool and construction method for plugging joints in masonry exterior wall - Google Patents

Tool and construction method for plugging joints in masonry exterior wall Download PDF

Info

Publication number
CN114109026B
CN114109026B CN202111412424.5A CN202111412424A CN114109026B CN 114109026 B CN114109026 B CN 114109026B CN 202111412424 A CN202111412424 A CN 202111412424A CN 114109026 B CN114109026 B CN 114109026B
Authority
CN
China
Prior art keywords
masonry
traction rope
square wood
keel
square
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111412424.5A
Other languages
Chinese (zh)
Other versions
CN114109026A (en
Inventor
董京京
李坤明
施得银
周蓉
周国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Group Co Ltd
East China Engineering Co Ltd of China Railway Construction Group Co Ltd
Original Assignee
China Railway Construction Group Co Ltd
East China Engineering Co Ltd of China Railway Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Group Co Ltd, East China Engineering Co Ltd of China Railway Construction Group Co Ltd filed Critical China Railway Construction Group Co Ltd
Priority to CN202111412424.5A priority Critical patent/CN114109026B/en
Publication of CN114109026A publication Critical patent/CN114109026A/en
Application granted granted Critical
Publication of CN114109026B publication Critical patent/CN114109026B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/001Corner fastening or connecting means for forming or stiffening elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/06Tying means; Spacers ; Devices for extracting or inserting wall ties
    • E04G17/065Tying means, the tensional elements of which are threaded to enable their fastening or tensioning
    • E04G17/0655Tying means, the tensional elements of which are threaded to enable their fastening or tensioning the element consisting of several parts
    • E04G17/0658Tying means, the tensional elements of which are threaded to enable their fastening or tensioning the element consisting of several parts remaining completely or partially embedded in the cast material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明公开了一种砌体外墙塞缝的工具及施工方法,包括结构梁、砌体墙、木胶板、方木次龙骨、方木主龙骨、螺纹钢、螺杆、PVC套管、固定螺母、方木龙骨、加固铁盘、加固螺母、铁环、牵引绳。本发明的有益效果是:将外侧模板与固定卡件与牵引绳结合,使用方便快捷的模板固定方法代替传统的外侧塞缝;并将传统的两侧塞缝方法,优化为内侧固定,一次施工成型,施工质量好;一名施工人员使用牵引绳与卡具即可完成整个工序的施工工作,方便快捷;另使用本发明,不用等待细石砼强度,可缩短该工序的施工时间一半以上。

Figure 202111412424

The invention discloses a tool and a construction method for plugging joints in a masonry exterior wall, comprising structural beams, masonry walls, wood plywood, square wood secondary keels, square wood main keels, threaded steel, screw rods, PVC sleeves, fixing Nuts, square wooden keels, reinforced iron plates, reinforced nuts, iron rings, and traction ropes. The beneficial effects of the present invention are: the outer formwork is combined with the fixing clip and the traction rope, and the convenient and fast formwork fixing method is used to replace the traditional outer side plugging; Forming and good construction quality; one construction worker can complete the construction work of the whole process by using the traction rope and clamps, which is convenient and fast; in addition, the invention does not need to wait for the strength of fine stone concrete, which can shorten the construction time of this process by more than half.

Figure 202111412424

Description

一种砌体外墙塞缝的工具及施工方法Tool and construction method for plugging joints in masonry exterior wall

技术领域technical field

本发明涉及一种砌体外墙塞缝的施工工具,具体为一种砌体外墙塞缝的工具及施工方法,属于工程施工卡件技术领域。The invention relates to a construction tool for plugging joints of masonry external walls, in particular to a tool and a construction method for plugging joints of masonry external walls, belonging to the technical field of engineering construction clips.

背景技术Background technique

砌体顶部塞缝作为砌筑工程施工的一个必要的工序,其施工质量、密实度直接关系着外墙防水的效果。As a necessary process of masonry construction, the top plugging of masonry is directly related to the waterproof effect of the external wall in terms of its construction quality and compactness.

尤其在选用附着式提升脚手架的高层建筑施工中,目前施工现场无有效的措施工具进行砌体外墙顶部塞缝施工,普遍采用的方法为普遍采用微膨胀细石混凝土从两侧施工,封堵时先从一侧进行,待凝固后再行填塞另一侧。这种方法均存在施工复杂、工时较长、对外脚手架依赖性较强,容易产生误差及塞缝不密实的问题。Especially in the construction of high-rise buildings with attached lifting scaffolding, there are currently no effective measures and tools on the construction site for the construction of the top of the masonry exterior wall. When starting from one side, fill the other side after solidification. This method all has the problems of complex construction, long working hours, strong dependence on external scaffolding, prone to errors and incomplete plugging.

发明内容Contents of the invention

本发明的目的就在于为了解决问题而提供一种砌体外墙塞缝的工具及施工方法。The object of the present invention is just to provide a kind of tool and the construction method of masonry exterior wall plugging seam in order to solve the problem.

本发明通过以下技术方案来实现上述目的:一种砌体外墙塞缝的工具及施工方法,包括The present invention achieves the above object through the following technical solutions: a tool and a construction method for plugging joints in masonry exterior walls, including

外侧模板,其设置在结构梁与砌体墙的外侧,且其由紧贴在所述结构梁与砌体墙外侧壁上的木胶板、呈水平状贴合在所述木胶板外侧的方木次龙骨、呈竖直状贴合在所述方木次龙骨外侧的方木主龙骨构成;The outer formwork is arranged on the outside of the structural beam and the masonry wall, and it is composed of a wooden plywood that is closely attached to the outside wall of the structural beam and the masonry wall, and is horizontally attached to the outside of the wooden plywood. A square wood sub-keel, a square wood main keel fitted vertically on the outside of the square wood sub-keel;

内侧固定卡件,其设置在所述结构梁与砌体墙的内侧,且其由呈竖直状紧贴在所述结构梁与砌体墙内侧壁上的方木龙骨、贴合在所述方木龙骨外侧的加固铁盘构成;The inner fixing clip is arranged on the inner side of the structural beam and the masonry wall, and it is made of a square wooden keel that is vertically attached to the inner wall of the structural beam and the masonry wall, and is attached to the Reinforced iron plate on the outside of the square wooden keel;

拉结组件,其用于连接在外侧模板与内侧固定卡件之间,且其由穿过所述结构梁与砌体墙之间缝隙处的螺杆、与所述螺杆一端焊接并呈水平状贴合在所述方木主龙骨外侧的螺纹钢,与所述螺杆另一端螺纹咬合连接并位于所述加固铁盘外侧的加固螺母构成。The tie assembly is used to connect between the outer formwork and the inner fixing clip, and it is composed of a screw passing through the gap between the structural beam and the masonry wall, welded to one end of the screw and attached horizontally The threaded steel on the outside of the main keel of the square wood is screwed with the other end of the screw and is formed by a reinforcement nut located on the outside of the reinforcement iron plate.

作为本发明再进一步的方案:所述方木次龙骨分别贴合在螺杆所穿过缝隙处的上下侧,所述方木主龙骨分别设置在螺杆的两侧,且所述木胶板、方木次龙骨以及方木主龙骨之间通过钢钉固定为一个整体。As a further solution of the present invention: the square wood sub keels are attached to the upper and lower sides of the gap where the screw passes through, the square wood main keels are respectively arranged on both sides of the screw rod, and the wood plywood, square wood The wooden secondary keel and the square wooden main keel are fixed as a whole by steel nails.

作为本发明再进一步的方案:所述螺杆上螺纹套设有用于夹紧固定所述方木主龙骨的加固螺母。As a further solution of the present invention: the threaded sleeve on the screw rod is provided with a reinforcement nut for clamping and fixing the main keel of the square wood.

作为本发明再进一步的方案:所述螺杆穿过结构梁与砌体墙之间缝隙处的杆身上套设有PVC套管。As a further solution of the present invention: the screw rod passes through the gap between the structural beam and the masonry wall and is covered with a PVC sleeve.

作为本发明再进一步的方案:所述方木龙骨分别设置在螺杆的两侧。As a further solution of the present invention: the square wooden keels are respectively arranged on both sides of the screw rod.

作为本发明再进一步的方案:所述螺杆穿过内侧固定卡件的一端焊接固定有铁环。As a further solution of the present invention: one end of the screw passing through the inner fixing clip is welded and fixed with an iron ring.

一种砌体外墙塞缝的工具的施工方法,其施工方法包括以下步骤:A construction method of a tool for plugging joints of a masonry exterior wall, the construction method comprising the following steps:

步骤一、砌体墙施工完成14天后,由上一层板面用牵引绳将外侧整体模板从楼外侧放下,从下一层砌体墙顶部缝隙中用铁钩将牵引绳拉入楼内侧,收紧牵引绳将螺杆拉入楼内侧,利用内侧方木龙骨、加固铁盘以及加固螺母将模板加固牢固,松开牵引绳开始塞缝作业;Step 1: 14 days after the masonry wall construction is completed, the outer overall formwork is lowered from the outside of the building with a traction rope on the upper deck, and the traction rope is pulled into the inside of the building with an iron hook from the gap at the top of the masonry wall of the next floor. Tighten the traction rope to pull the screw into the inside of the building, use the inner square wooden keel, reinforced iron plate and reinforcement nuts to reinforce the formwork firmly, loosen the traction rope to start the caulking operation;

步骤二、塞缝作业完成后,拉紧牵引绳,松开内侧加固螺母以及卸下加固圆盘后将牵引绳利用预留PVC套管的内部孔道将外侧整体模板下方到下一层,在下一层砌体墙缝隙用铁钩将牵引绳拉入楼内侧,重复以上作业;Step 2. After the caulking operation is completed, tighten the traction rope, loosen the inner reinforcement nut and remove the reinforcement disc, and then use the traction rope to use the internal channel of the reserved PVC casing to lower the outer overall formwork to the next layer. Pull the traction rope into the inner side of the building with an iron hook in the gap of the masonry wall, and repeat the above operations;

步骤三、PVC套管的内部PVC孔道后期用发泡胶填塞密实。Step 3, the inner PVC channel of the PVC casing is filled with foam glue in the later stage.

本发明的有益效果是:将外侧模板与固定卡件与牵引绳结合,使用方便快捷的模板固定方法代替传统的外侧塞缝;并将传统的两侧塞缝方法,优化为内侧固定,一次施工成型,施工质量好;一名施工人员使用牵引绳与卡具即可完成整个工序的施工工作,方便快捷;另使用本发明,不用等待细石砼强度,可缩短该工序的施工时间一半以上。The beneficial effects of the present invention are: the outer formwork is combined with the fixing clip and the traction rope, and the convenient and fast formwork fixing method is used to replace the traditional outer side plugging; Forming and good construction quality; one construction worker can complete the construction work of the whole process by using the traction rope and clamps, which is convenient and fast; in addition, the invention does not need to wait for the strength of the fine stone concrete, which can shorten the construction time of this process by more than half.

附图说明Description of drawings

图1为本发明剖面结构示意图;Fig. 1 is the cross-sectional structure schematic diagram of the present invention;

图2为本发明外侧模板平面结构示意图;Fig. 2 is a schematic diagram of the planar structure of the outer formwork of the present invention;

图3为本发明内侧固定卡件平面结构示意图。Fig. 3 is a schematic diagram of the planar structure of the inner fixing clip of the present invention.

图中:1、结构梁,2、砌体墙,3、木胶板,4、方木次龙骨,5、方木主龙骨,6、螺纹钢,7、螺杆,8、PVC套管,9、固定螺母,10、方木龙骨,11、加固铁盘,12、加固螺母,13、铁环,14、牵引绳。In the figure: 1. Structural beam, 2. Masonry wall, 3. Wood plywood, 4. Square wood secondary keel, 5. Square wood main keel, 6. Rebar, 7. Screw rod, 8. PVC casing, 9 , fixed nut, 10, square wooden keel, 11, reinforced iron plate, 12, reinforced nut, 13, iron ring, 14, traction rope.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

实施例一Embodiment one

请参阅图1~3,一种砌体外墙塞缝的工具,包括Please refer to Figures 1 to 3, a tool for plugging joints in masonry exterior walls, including

外侧模板,其设置在结构梁1与砌体墙2的外侧,且其由紧贴在所述结构梁1与砌体墙2外侧壁上的木胶板3、呈水平状贴合在所述木胶板3外侧的方木次龙骨4、呈竖直状贴合在所述方木次龙骨4外侧的方木主龙骨5构成;The outer formwork is arranged on the outer side of the structural beam 1 and the masonry wall 2, and it is attached to the said structural beam 1 and the outer side wall of the masonry wall 2 by the wooden plywood 3 in a horizontal shape. The square wood sub-keel 4 on the outside of the wood plywood 3 is formed by the square wood main joist 5 attached to the outside of the square wood sub-keel 4 in a vertical shape;

内侧固定卡件,其设置在所述结构梁1与砌体墙2的内侧,且其由呈竖直状紧贴在所述结构梁1与砌体墙2内侧壁上的方木龙骨10、贴合在所述方木龙骨10外侧的加固铁盘11构成;The inner fixed clip is arranged on the inner side of the structural beam 1 and the masonry wall 2, and it is composed of a square wooden keel 10 that is vertically attached to the inner wall of the structural beam 1 and the masonry wall 2, It is composed of a reinforced iron plate 11 attached to the outside of the square wooden keel 10;

拉结组件,其用于连接在外侧模板与内侧固定卡件之间,且其由穿过所述结构梁1与砌体墙2之间缝隙处的螺杆7、与所述螺杆7一端焊接并呈水平状贴合在所述方木主龙骨5外侧的螺纹钢6,与所述螺杆7另一端螺纹咬合连接并位于所述加固铁盘11外侧的加固螺母12构成。The tie assembly is used to connect between the outer formwork and the inner fixing clip, and it is welded to one end of the screw rod 7 through the screw rod 7 passing through the gap between the structural beam 1 and the masonry wall 2 The threaded steel 6 attached horizontally to the outside of the square timber main keel 5 is screw-engaged with the other end of the screw rod 7 and is formed by a reinforcement nut 12 located on the outside of the reinforcement iron plate 11 .

在本发明实施例中,所述方木次龙骨4分别贴合在螺杆7所穿过缝隙处的上下侧,所述方木主龙骨5分别设置在螺杆7的两侧,且所述木胶板3、方木次龙骨4以及方木主龙骨5之间通过钢钉固定为一个整体,以确保木胶板3能够紧固的贴合在结构梁1与砌体墙2外侧壁上。In the embodiment of the present invention, the square wood sub keels 4 are attached to the upper and lower sides of the gap where the screw rod 7 passes through, the square wood main keels 5 are respectively arranged on both sides of the screw rod 7, and the wood glue The board 3 , the square wood secondary keel 4 and the square wood main keel 5 are fixed as a whole by steel nails to ensure that the wood plywood 3 can be firmly attached to the structural beam 1 and the outer wall of the masonry wall 2 .

在本发明实施例中,所述螺杆7上螺纹套设有用于夹紧固定所述方木主龙骨5的加固螺母12,使螺杆7与外侧模板组合固定在一起,进而便于施工人员通过铁钩进行整体的移动。In the embodiment of the present invention, the threaded sleeve on the screw rod 7 is provided with a reinforcement nut 12 for clamping and fixing the square timber main keel 5, so that the screw rod 7 and the outer formwork are combined and fixed together, which is convenient for construction personnel to pass through the iron hook. Make an overall move.

在本发明实施例中,所述螺杆7穿过结构梁1与砌体墙2之间缝隙处的杆身上套设有PVC套管8,进行填缝作业时,可避免将螺杆7埋入塞缝混凝土内,以确保可将螺杆7抽出进行二次使用。In the embodiment of the present invention, the screw rod 7 passes through the gap between the structural beam 1 and the masonry wall 2 and is covered with a PVC sleeve 8, so that the screw rod 7 can be avoided from being buried in the plug during the caulking operation. In the joint concrete, to ensure that the screw rod 7 can be extracted for secondary use.

实施例二Embodiment two

请参阅图1~3,一种砌体外墙塞缝的工具,包括Please refer to Figures 1 to 3, a tool for plugging joints in masonry exterior walls, including

外侧模板,其设置在结构梁1与砌体墙2的外侧,且其由紧贴在所述结构梁1与砌体墙2外侧壁上的木胶板3、呈水平状贴合在所述木胶板3外侧的方木次龙骨4、呈竖直状贴合在所述方木次龙骨4外侧的方木主龙骨5构成;The outer formwork is arranged on the outer side of the structural beam 1 and the masonry wall 2, and it is attached to the said structural beam 1 and the outer side wall of the masonry wall 2 by the wood plywood 3 in a horizontal shape. The square wood sub-keel 4 on the outside of the wood plywood 3 is formed by the square wood main joist 5 attached to the outside of the square wood sub-keel 4 in a vertical shape;

内侧固定卡件,其设置在所述结构梁1与砌体墙2的内侧,且其由呈竖直状紧贴在所述结构梁1与砌体墙2内侧壁上的方木龙骨10、贴合在所述方木龙骨10外侧的加固铁盘11构成;The inner fixed clip is arranged on the inner side of the structural beam 1 and the masonry wall 2, and it is composed of a square wooden keel 10 that is vertically attached to the inner wall of the structural beam 1 and the masonry wall 2, It is composed of a reinforced iron plate 11 attached to the outside of the square wooden keel 10;

拉结组件,其用于连接在外侧模板与内侧固定卡件之间,且其由穿过所述结构梁1与砌体墙2之间缝隙处的螺杆7、与所述螺杆7一端焊接并呈水平状贴合在所述方木主龙骨5外侧的螺纹钢6,与所述螺杆7另一端螺纹咬合连接并位于所述加固铁盘11外侧的加固螺母12构成。The tie assembly is used to connect between the outer formwork and the inner fixing clip, and it is welded to one end of the screw rod 7 through the screw rod 7 passing through the gap between the structural beam 1 and the masonry wall 2 The threaded steel 6 attached horizontally to the outside of the square timber main keel 5 is screw-engaged with the other end of the screw rod 7 and is formed by a reinforcement nut 12 located on the outside of the reinforcement iron plate 11 .

在本发明实施例中,所述方木龙骨10分别设置在螺杆7的两侧,拧紧固定螺母9时,可使加固铁盘11油两侧的方木龙骨10进行支撑,确保受力平衡。In the embodiment of the present invention, the square wooden keels 10 are arranged on both sides of the screw rod 7 respectively. When the fixing nuts 9 are tightened, the square wooden keels 10 on both sides of the reinforced iron plate 11 can be supported to ensure the force balance.

在本发明实施例中,所述螺杆7穿过内侧固定卡件的一端焊接固定有铁环13,且所述铁环13上连接有牵引绳14,可通过收紧牵引绳14将外侧模板定位到合适位置,然后固定内侧固定卡件收紧模板进行塞缝作业,作业完成后松开内部卡具,放松牵引绳14到下一层,利用铁钩将牵引绳14拉入下一层工作面后重复上述作业。In the embodiment of the present invention, an iron ring 13 is welded and fixed on the end of the screw rod 7 passing through the inner fixing clip, and a traction rope 14 is connected to the iron ring 13, and the outer formwork can be positioned by tightening the traction rope 14 to the proper position, then fix the inner fixing clamps to tighten the formwork to carry out the caulking operation, loosen the internal clamps after the work is completed, loosen the traction rope 14 to the next layer, and use the iron hook to pull the traction rope 14 into the working surface of the next layer Then repeat the above operation.

实施例三Embodiment Three

一种砌体外墙塞缝的工具的施工方法,其施工方法包括以下步骤:A construction method of a tool for plugging joints of a masonry exterior wall, the construction method comprising the following steps:

步骤一、砌体墙2施工完成14天后,由上一层板面用牵引绳14将外侧整体模板从楼外侧放下,从下一层砌体墙2顶部缝隙中用铁钩将牵引绳14拉入楼内侧,收紧牵引绳14将螺杆7拉入楼内侧,利用内侧方木龙骨10、加固铁盘11以及加固螺母12将模板加固牢固,松开牵引绳14开始塞缝作业;Step 1: 14 days after the construction of the masonry wall 2 is completed, the outer overall formwork is lowered from the outside of the building with the traction rope 14 on the upper deck, and the traction rope 14 is pulled with an iron hook from the gap at the top of the masonry wall 2 of the next floor Enter the inner side of the building, tighten the traction rope 14 to pull the screw rod 7 into the inner side of the building, use the inner square wooden keel 10, the reinforcement iron plate 11 and the reinforcement nut 12 to reinforce the formwork firmly, loosen the traction rope 14 and start the seam operation;

步骤二、塞缝作业完成后,拉紧牵引绳14,松开内侧加固螺母12以及卸下加固圆盘11后将牵引绳14利用预留PVC套管11的内部孔道将外侧整体模板下方到下一层,在下一层砌体墙2缝隙用铁钩将牵引绳14拉入楼内侧,重复以上作业;Step 2. After the caulking operation is completed, tighten the traction rope 14, loosen the inner reinforcement nut 12 and remove the reinforcement disc 11, and then use the traction rope 14 to use the internal channel of the reserved PVC casing 11 to lower the outer overall formwork to the bottom. One floor, pull the traction rope 14 into the inner side of the building with an iron hook in the 2 gaps of the masonry wall of the next floor, and repeat the above operations;

步骤三、PVC套管11的内部PVC孔道后期用发泡胶填塞密实。Step 3, the inner PVC channel of the PVC sleeve 11 is filled and compacted with styrofoam in the later stage.

工作原理:施工人员将外侧模板与卡具固定牢固,将牵引绳14与螺杆7连接,通过收紧牵引绳14将外侧模板定位到合适位置,然后固定内侧卡具收紧模板进行塞缝作业,作业完成后松开内部卡具,放松牵引绳14到下一层,利用铁钩将牵引绳14拉入下一层工作面后重复上述作业。Working principle: The construction personnel fix the outer formwork and the jig firmly, connect the traction rope 14 with the screw rod 7, position the outer formwork to a proper position by tightening the traction rope 14, and then fix the inner fixture to tighten the formwork to perform the caulking operation. Unclamp internal fixture after operation is finished, loosen traction rope 14 to next floor, utilize iron hook to repeat above-mentioned operation after traction rope 14 is pulled into next floor working face.

对于本领域技术人员而言,显然本发明不限于上述示范性实施例的细节,而且在不背离本发明的精神或基本特征的情况下,能够以其他的具体形式实现本发明。因此,无论从哪一点来看,均应将实施例看作是示范性的,而且是非限制性的,本发明的范围由所附权利要求而不是上述说明限定,因此旨在将落在权利要求的等同要件的含义和范围内的所有变化囊括在本发明内。不应将权利要求中的任何附图标记视为限制所涉及的权利要求。It will be apparent to those skilled in the art that the invention is not limited to the details of the above-described exemplary embodiments, but that the invention can be embodied in other specific forms without departing from the spirit or essential characteristics of the invention. Accordingly, the embodiments should be regarded in all points of view as exemplary and not restrictive, the scope of the invention being defined by the appended claims rather than the foregoing description, and it is therefore intended that the scope of the invention be defined by the appended claims rather than by the foregoing description. All changes within the meaning and range of equivalents of the elements are embraced in the present invention. Any reference sign in a claim should not be construed as limiting the claim concerned.

此外,应当理解,虽然本说明书按照实施方式加以描述,但并非每个实施方式仅包含一个独立的技术方案,说明书的这种叙述方式仅仅是为清楚起见,本领域技术人员应当将说明书作为一个整体,各实施例中的技术方案也可以经适当组合,形成本领域技术人员可以理解的其他实施方式。In addition, it should be understood that although this specification is described according to implementation modes, not each implementation mode only contains an independent technical solution, and this description in the specification is only for clarity, and those skilled in the art should take the specification as a whole , the technical solutions in the various embodiments can also be properly combined to form other implementations that can be understood by those skilled in the art.

Claims (5)

1. The utility model provides a brickwork outer wall caulking joint's instrument which characterized in that: comprises that
The outer side template is arranged on the outer sides of the structural beam (1) and the masonry wall (2) and consists of a wood veneer board (3) tightly attached to the outer side walls of the structural beam (1) and the masonry wall (2), a square wood secondary keel (4) horizontally attached to the outer side of the wood veneer board (3) and a square wood main keel (5) vertically attached to the outer side of the square wood secondary keel (4);
the inner side fixing clamping piece is arranged on the inner sides of the structural beam (1) and the masonry wall (2) and is formed by a square wood keel (10) which is vertically clung to the inner side walls of the structural beam (1) and the masonry wall (2) and a reinforcing iron plate (11) which is clung to the outer side of the square wood keel (10);
the drawknot component is used for being connected between the outer template and the inner side fixing clamp part and consists of a screw rod (7) penetrating through a gap between the structural beam (1) and the masonry wall (2), deformed steel bars (6) welded with one end of the screw rod (7) and horizontally attached to the outer side of the square wood main keel (5) and reinforcing nuts (12) in threaded engagement with the other end of the screw rod (7) and positioned on the outer side of the reinforcing iron disc (11);
the square wood secondary keels (4) are respectively attached to the upper side and the lower side of the gap where the screw (7) penetrates, the square wood main keels (5) are respectively arranged on the two sides of the screw (7), and the wood rubber plate (3), the square wood secondary keels (4) and the square wood main keels (5) are fixed into a whole through steel nails;
one end of the screw (7) penetrating through the inner side fixing clamping piece is fixedly welded with an iron ring (13), and a traction rope (14) is connected onto the iron ring (13).
2. The tool for plugging the seams of the exterior walls of the masonry, according to claim 1, wherein: the screw rod (7) is provided with a reinforcing nut (12) in a threaded sleeve manner, and the reinforcing nut is used for clamping and fixing the square wood main keel (5).
3. The tool for plugging the seams of the exterior walls of the masonry, according to claim 1, wherein: the screw rod (7) penetrates through a PVC sleeve (8) on a rod body at a gap between the structural beam (1) and the masonry wall (2).
4. The tool for plugging the seams of the exterior walls of the masonry, according to claim 1, wherein: the square wood keels (10) are respectively arranged on two sides of the screw (7).
5. A construction method of the tool for plugging the seams of the exterior wall of the masonry based on the claim 1 is characterized in that: the construction method comprises the following steps:
step one, after the masonry wall (2) construction is completed for 14 days, an outer-side integral template is put down from the outer side of a building by using a traction rope (14) on the upper plate surface, the traction rope (14) is pulled into the inner side of the building by using an iron hook from a gap at the top of the next masonry wall (2), a screw rod (7) is pulled into the inner side of the building by tightening the traction rope (14), the template is firmly reinforced by using an inner-side square wood keel (10), a reinforcing iron disc (11) and a reinforcing nut (12), and the traction rope (14) is loosened to start caulking operation;
step two, after the seam plugging operation is completed, the traction rope (14) is tensioned, the inner side reinforcing nut (12) is loosened, the inner pore canal of the reserved PVC sleeve (11) is utilized to enable the traction rope (14) to be below the outer side integral formwork to the next layer after the reinforcing disc (11) is detached, the traction rope (14) is pulled into the inner side of the building through an iron hook in the seam of the next layer of masonry wall (2), and the operation is repeated;
and step three, filling and compacting the PVC pore channel in the PVC sleeve (11) by using foaming glue at the later stage.
CN202111412424.5A 2021-11-25 2021-11-25 Tool and construction method for plugging joints in masonry exterior wall Active CN114109026B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111412424.5A CN114109026B (en) 2021-11-25 2021-11-25 Tool and construction method for plugging joints in masonry exterior wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111412424.5A CN114109026B (en) 2021-11-25 2021-11-25 Tool and construction method for plugging joints in masonry exterior wall

Publications (2)

Publication Number Publication Date
CN114109026A CN114109026A (en) 2022-03-01
CN114109026B true CN114109026B (en) 2023-04-14

Family

ID=80373047

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111412424.5A Active CN114109026B (en) 2021-11-25 2021-11-25 Tool and construction method for plugging joints in masonry exterior wall

Country Status (1)

Country Link
CN (1) CN114109026B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114704080A (en) * 2022-04-28 2022-07-05 北京中铁建建筑科技有限公司 Aluminum template and PC (polycarbonate) component combined mold hanging system and construction method
CN117266383B (en) * 2023-08-02 2025-12-19 中建新疆建工集团第一建筑工程有限公司 Shear force wall screw hole shutoff instrument

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106812219A (en) * 2017-03-14 2017-06-09 中国十七冶集团有限公司 Filling wall top stuff up a crack construction method

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5154241B2 (en) * 2008-01-24 2013-02-27 シーアイ化成株式会社 Water stop ring and water stop construction method for concrete structures
CN102635179A (en) * 2012-05-02 2012-08-15 魏勇 Device for preventing beam or beamless slab filler wall top from cracking and construction method
CN204983647U (en) * 2015-09-01 2016-01-20 云南建工集团有限公司 Design instrument formula aluminum alloy template
CN206539005U (en) * 2016-08-01 2017-10-03 中国建筑第八工程局有限公司 Formwork structure for narrow and small movement joint both sides shear wall construction
CN109653382A (en) * 2018-11-27 2019-04-19 上海宝冶集团有限公司 Gap construction technology at the top of masonry wall between main structure
CN110454479A (en) * 2019-08-07 2019-11-15 郑素青 A kind of bolt installation method of narrow space
CN110905219A (en) * 2019-12-02 2020-03-24 淙创(上海)企业管理咨询中心 Frame structure and filler wall interface combined anti-crack structure and construction method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106812219A (en) * 2017-03-14 2017-06-09 中国十七冶集团有限公司 Filling wall top stuff up a crack construction method

Also Published As

Publication number Publication date
CN114109026A (en) 2022-03-01

Similar Documents

Publication Publication Date Title
CN104695703B (en) Exempt from boring shear wall construction template system and shear wall construction method
CN112854745A (en) Construction process of assembled building aluminum alloy template
CN114109026B (en) Tool and construction method for plugging joints in masonry exterior wall
CN108005387A (en) A kind of assembled wallboard and the cast-in-place main body method for synchronously constructing of shear wall with short piers
CN110145124A (en) A reinforcement tool and its construction method for controlling the quality of horizontal stubble of shear walls
CN110630011A (en) Template reinforcing system for double shear walls at deformation joint and construction method thereof
CN106906841A (en) One kind is used for lateral wall form bracing system construction
CN112112265A (en) A dry-connected prefabricated beam-column connection node and construction method
CN203403670U (en) unsupported formwork system
CN111719856A (en) Bare concrete construction formwork system and construction method thereof
CN111364664B (en) Construction technology of steel truss floor deck without demolition bottom formwork
CN110512776B (en) Construction method of assembled steel structure multi-cavity steel plate composite shear wall
CN210976588U (en) Template reinforcing system for double shear walls at deformation joint
CN109457960B (en) Adjustable universal mold for integrally assembling cast-in-situ stair steps
CN110939216A (en) Plaster-free wall based on gypsum hollow building blocks
CN206158172U (en) Entrance to a cave template
CN201321720Y (en) Ring-beam no-putlog-hole template erecting device in brick and concrete structure construction
CN111335358A (en) Immersed tube tunnel end mold, end mold supporting platform and construction method thereof
CN217151210U (en) Shear wall template reinforced structure
AU2021105980A4 (en) Construction method for impervious concrete for mbbr water treatment process structure
CN118049049A (en) General column hoop and construction method for cast-in-situ special-shaped frame column by using general column hoop
CN104453235A (en) Convertor station firewall construction technology
CN211873413U (en) Plaster-free wall based on gypsum hollow building blocks
CN210288448U (en) Slope formwork support system
CN212336412U (en) An assembled wall connection structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: No.88 Guangming Road, Huaqiao Town, Kunshan City, Suzhou City, Jiangsu Province

Applicant after: China Railway Construction Group East China Engineering Co.,Ltd.

Applicant after: CHINA RAILWAY CONSTRUCTION GROUP Co.,Ltd.

Address before: 215332 rooms 808 and 809, No. 2, xugongqiao Road, Huaqiao Town, Kunshan City, Suzhou City, Jiangsu Province

Applicant before: China Railway Construction Group East China Engineering Co.,Ltd.

Applicant before: CHINA RAILWAY CONSTRUCTION GROUP Co.,Ltd.

CB02 Change of applicant information
GR01 Patent grant
GR01 Patent grant