CN114033483A - A construction method suitable for tailings filling process in collapse pits - Google Patents

A construction method suitable for tailings filling process in collapse pits Download PDF

Info

Publication number
CN114033483A
CN114033483A CN202111402725.XA CN202111402725A CN114033483A CN 114033483 A CN114033483 A CN 114033483A CN 202111402725 A CN202111402725 A CN 202111402725A CN 114033483 A CN114033483 A CN 114033483A
Authority
CN
China
Prior art keywords
filling
retaining wall
slurry
height
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202111402725.XA
Other languages
Chinese (zh)
Other versions
CN114033483B (en
Inventor
王邦策
李琦
骆溶
班振兴
侯大德
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Magang Mining Resources Group Gushan Mining Co ltd
Central South University
Anhui Maanshan Iron and Steel Mining Resources Group Co Ltd
Original Assignee
Anhui Magang Mining Resources Group Gushan Mining Co ltd
Central South University
Anhui Maanshan Iron and Steel Mining Resources Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Magang Mining Resources Group Gushan Mining Co ltd, Central South University, Anhui Maanshan Iron and Steel Mining Resources Group Co Ltd filed Critical Anhui Magang Mining Resources Group Gushan Mining Co ltd
Priority to CN202111402725.XA priority Critical patent/CN114033483B/en
Publication of CN114033483A publication Critical patent/CN114033483A/en
Application granted granted Critical
Publication of CN114033483B publication Critical patent/CN114033483B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • E21F15/005Methods or devices for placing filling-up materials in underground workings characterised by the kind or composition of the backfilling material
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • E21F15/02Supporting means, e.g. shuttering, for filling-up materials
    • E21F15/04Stowing mats; Goaf wire netting; Partition walls
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/18Special adaptations of signalling or alarm devices
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • G06F30/27Design optimisation, verification or simulation using machine learning, e.g. artificial intelligence, neural networks, support vector machines [SVM] or training a model
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/02Agriculture; Fishing; Forestry; Mining
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W30/00Technologies for solid waste management
    • Y02W30/50Reuse, recycling or recovery technologies
    • Y02W30/91Use of waste materials as fillers for mortars or concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Evolutionary Computation (AREA)
  • General Physics & Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • Artificial Intelligence (AREA)
  • Geometry (AREA)
  • Software Systems (AREA)
  • Medical Informatics (AREA)
  • Computer Vision & Pattern Recognition (AREA)
  • Agronomy & Crop Science (AREA)
  • Animal Husbandry (AREA)
  • Marine Sciences & Fisheries (AREA)
  • Computer Hardware Design (AREA)
  • Health & Medical Sciences (AREA)
  • Economics (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a construction method suitable for a collapse pit tailing filling process, and relates to the technical field of underground mining. The construction method suitable for the collapse pit tailing filling process specifically comprises the following operations: s1, preparing tailing filling slurry and calculating pipeline conveying parameters, wherein the filling slurry is tailing produced by mine beneficiation or solid waste of mine surface waste stone. According to the construction method suitable for the collapse pit tailing filling process, the collapse area is backfilled by tailings, and the safe stacking is realized, so that the problem of tailing stacking can be solved, the potential safety hazard in the collapse area can be eliminated, huge social benefits and economic benefits are achieved, a large amount of land is saved, and the engineering quantity and cost for geological disaster treatment in the later stage of a mine are greatly reduced.

Description

Construction method suitable for collapse pit tailing filling process
Technical Field
The invention relates to the technical field of underground mining, in particular to a construction method suitable for a collapse pit tailing filling process.
Background
The tailings are solid wastes obtained after mining enterprises extract useful components in the ores, are discharged to the ground surface, and occupy a large amount of land resources. The collapse pit is a caving area formed after the mine adopts an underground mining mode to cause surface subsidence, the damage to the surface environment is huge, a large amount of land resource damage, ecological environment damage and water resource waste are caused, and the treatment cost is high.
Disclosure of Invention
Technical problem to be solved
Aiming at the defects of the prior art, the invention provides a construction method suitable for a collapse pit tailing filling process, and solves the problems that a collapse pit is a caving area formed after a mine adopts an underground mining mode to cause surface subsidence, the damage to the surface environment is huge, a large amount of land resources are damaged, the ecological environment is damaged, water resources are wasted, and the treatment cost is high.
(II) technical scheme
In order to achieve the purpose, the invention is realized by the following technical scheme: a construction method suitable for a collapse pit tailing filling process specifically comprises the following operations:
s1, preparing tailing filling slurry and calculating pipeline conveying parameters, wherein the filling slurry is prepared from tailing produced by mine beneficiation or solid waste of mine surface waste stone, and the concrete operation is as follows:
the whole tailings are loaded into a storage bin by a loader, cement is directly conveyed to an inlet of a stirrer through a cement bin, a gate and a variable-frequency speed-regulating star-shaped feeder, a spray nozzle is arranged at the inlet of the stirrer, and proper water is sprayed according to the moisture conditions of various materials before mixing, so that the moisture content of the mixture reaches the requirement required for filling. And (3) pressurizing and conveying the stirred finished product to a goaf through a filling ore pulp regulating system by a concrete pump, wherein the whole process is a continuous working process.
Fill water may be directed from a peripherally adjacent source and downhole. The filling water can be recycled, and the designed water supply system comprises a clean water pool, a filling water pool, a water pump, an electromagnetic flowmeter, a valve and the like. The regulating valve can control the water spraying amount in unit time, and the three-way joint is installed on the pipeline for cleaning equipment to prevent slurry from adhering to wall and sprinkling. Before filling, the equipment and the pipeline are wetted by filling water to prevent slurry from sticking to the wall, and after filling, the filling equipment and the filling pipeline are cleaned by clear water to prevent pipe blockage and corrosion of alkaline water to the equipment when filling is started. The water used in the filling mortar is completely pumped from the reservoir by a water pump. The guide pipe drainage water and cleaning water when starting up and stopping in production can utilize reservoir water reconstructed in mining areas as a water source. Because adopt full tailings or hierarchical cemented filling, lead to the pit to gush water mud content and increase, need set up the sedimentation tank, can make full use of idle tunnel.
Since many influence factors exist and many influence factors (such as roughness of a conveying pipeline and the like) are difficult to quantitatively calculate, for the sake of safety, different formulas are adopted for calculation respectively in the research, and then the maximum value is taken as the resistance loss (hydraulic gradient) value of the filling slurry conveying.
A. The formula for calculating the resistance loss of the heterogeneous mortar is as follows:
Figure BDA0003371618890000021
in the formula: gamma raymTailings density, 2.79t/m3
v is the working flow rate, 1.64 m/s;
i0the hydraulic gradient of the clear water is calculated according to the following formula
Figure BDA0003371618890000022
Lambda-clear water friction resistance coefficient, calculated as
Figure BDA0003371618890000023
K3-the pipeline laying coefficient is taken as 1.1;
K4-the pipe connection quality factor is taken to be 1.15;
Cv-volume concentration, calculated according to the following formula:
Figure BDA0003371618890000031
γjfull-tail mortar density of 1.79t/m3
γ0Density of water, t/m3
Cx-coefficient of sedimentation resistance, calculated according to the following formula:
Figure BDA0003371618890000032
in the formula: dcpAverage particle size of fillers, cm, dcp=0.127mm;
Omega-mean settling velocity of the particles, cm/s,
ω=123.04dcp 1.1m-1)0.7=0.74cm/s。
calculated to obtain Cx=28.6;im=0.1187mH2O/m=1187Pa/m。
B. For homogeneous mortars, the slurry resistance loss can be calculated according to the diffusion theory:
im=i0γj/γ (6)
substituting the relevant parameters into the above formula to obtain im=0.0748mH2O/m=748Pa/m。
In conclusion, the final hydraulic gradient of the mortar takes the maximum value.
C. Pipeline local resistance calculation
The local resistance of the pipeline mainly refers to installation resistance, pipeline elbow resistance and resistance generated by sudden enlargement or reduction of the pipeline. The resistance of the curve is estimated according to 8% of the loss of the pipeline along the way, and the local resistance of all the pipelines along the way is obtained, namely:
ioffice=8%i (7)
D. Pipeline total resistance calculation
The total resistance of the pipeline is calculated by the following formula:
H=Hz+HJ+HG (8)
in the formula: h, total conveying resistance of the filling slurry, namely working resistance of a conveying pump body, namely MPa;
HZ-the total resistance of the horizontal straight pipe section, MPa, of the filling slip delivery;
HJ-local resistance to the transport of the filling slip, MPa;
HG-the magnitude of the resistance loss or drag reduction caused by elevation difference during filling slurry transportation, MPa;
s2, using the collapse region range detection and analysis method, specifically operating as follows:
forming a three-dimensional visual digital model of a mining area according to a mining exploration line profile and a surface topography, forming an initial stress balance state according to the ground stress, simulating mining ore bodies section by section and caving overlying rocks to form a collapse pit according to a mining planning sequence, carrying out comparative analysis on the collapse pit and the mining situation, disclosing a mining covering layer and an overlying rock motion rule and a dynamic development process in a moving range by adopting a method of organically integrating numerical simulation analysis and mining planning, carrying out comparative analysis on a collapse area plane range obtained by simulation and a result obtained by surface aerial photography, and finally determining the collapse area range to be treated;
s3, planning the filling zones in the well: and the whole filling sequence of the underground goaf is carried out from the lower middle section to the upper middle section, and in order to avoid large-area collapse caused by goaf instability, the goaf of the lower middle section is completely filled with the roof and then is turned to the upper middle section for filling. Until the end of all filling, the specific operations are as follows:
according to the filling characteristics and the filling time sequence, the acting force of the formed filling body on the filling retaining wall is considered to be gradually reduced along with the gradual dehydration, sedimentation, condensation and hardening of the filling slurry, the acting force of the filling retaining wall by the filling slurry which is not condensed and hardened is the largest when the filling retaining wall is just filled into a stope goaf, therefore, the stress condition of the filling retaining wall when the filling slurry just enters the goaf is only analyzed, and the specific stress condition of the filling retaining wall at the moment is divided into two types:
A. the height of the surface of the filling slurry is lower than or equal to that of the filling retaining wall
The filling retaining wall is mostly rectangular in shape, the height is represented by H, the width is represented by W, and the volume weight gamma of filling slurry isLiquid for treating urinary tract infectionVolume weight after dehydration gammaThreshing deviceAnd the height of the filling slurry surface is calculated from the bottom of the filling retaining wall and is expressed by h, and the stress of the filling retaining wall is calculated according to the following formula:
Figure BDA0003371618890000051
total pressure
Figure BDA0003371618890000052
The bending moment of the filling retaining wall is as follows:
Figure BDA0003371618890000053
the maximum bending moment is:
Figure BDA0003371618890000054
maximum bending moment action point:
Figure BDA0003371618890000055
B. the height of the surface of the filling slurry is higher than that of the filling retaining wall
When the filling slurry surface is higher than the filling retaining wall, the stress condition of the filling retaining wall is calculated as follows:
q=γliquid for treating urinary tract infection(h-H)+γLiquid for treating urinary tract infection*Z (14)
The total pressure P of the filling retaining wall is as follows:
Figure BDA0003371618890000056
the bending moment of the filling retaining wall is as follows:
Figure BDA0003371618890000057
the maximum bending moment and the action point are respectively as follows:
Figure BDA0003371618890000058
Figure BDA0003371618890000059
wherein m is 3h2-3Hh+H2
It can be seen from the above formula that when the slurry surface of the filling slurry is lower than or equal to the height of the filling retaining wall, the distribution force q acting on the filling retaining wall is in direct proportion to the first square of the filling height h, the total pressure P is in direct proportion to the square of the filling height h and the first square of the width W, and the maximum bending moment Mmax is in direct proportion to the cube of the filling height h; when the filling slurry surface is higher than the filling retaining wall, the stress magnitude P and the maximum bending moment Mmax of the filling retaining wall are increased along with the increase of the height of the filling retaining wall. Therefore, the greatest factor affecting the safety of the filled retaining wall is the filling height h. Therefore, when the filling retaining wall is arranged, the height of the arrangement position of the filling retaining wall is considered in an important way, and then the filling retaining wall is comprehensively considered to be established.
According to the theoretical analysis, when the initial filling height is larger than the height of the filled retaining wall, the retaining wall is stressed greatly and the stability of the retaining wall is not facilitated; therefore, the first fill level should not generally be higher than the wall level. Therefore, according to the type that the height of the filling slurry surface is lower than or equal to that of the filled retaining wall, the total pressure, the maximum bending moment and the action point of the retaining wall at different filling heights are calculated by the formulas (10), (12) and (13).
Calculating the safety factors of retaining walls in different forms according to the stress change condition of the retaining wall, and designing the forming of the retaining wall and the tailing filling heights in different stages;
s4, calculating the stress parameters of the underground plugging wall and designing the filling height, wherein the calculation method of the stress of the underground plugging wall is as follows: according to the filling characteristics and the filling time sequence, the acting force of the formed filling body on the filling retaining wall is gradually reduced along with the gradual dehydration, sedimentation, coagulation and hardening of the filling slurry, namely the acting force of the non-coagulated and hardened filling slurry on the filling retaining wall is the largest when the filling slurry is filled into the stope goaf, so that the stress condition of the filling retaining wall when the filling slurry just enters the goaf is only analyzed, and the specific stress condition of the filling retaining wall at the moment is divided into two types, namely the filling slurry surface height is lower than or equal to the height of the filling retaining wall, and the filling slurry surface height is higher than the height of the filling retaining wall.
(III) advantageous effects
The invention provides a construction method suitable for a collapse pit tailing filling process. The method has the following beneficial effects:
according to the construction method suitable for the collapse pit tailing filling process, the collapse area is backfilled by tailings, and the safe stacking is realized, so that the problem of tailing stacking can be solved, the potential safety hazard in the collapse area can be eliminated, huge social benefits and economic benefits are achieved, a large amount of land is saved, and the engineering quantity and cost for geological disaster treatment in the later stage of a mine are greatly reduced.
Drawings
FIG. 1 is a schematic diagram of a design method of structural parameters of an underground plugging wall according to the invention;
FIG. 2 is a schematic view of the invention when the slurry level is higher than the retaining wall.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-2, the present invention provides a technical solution: a construction method suitable for a collapse pit tailing filling process specifically comprises the following operations:
s1, preparing tailing filling slurry and calculating pipeline conveying parameters, wherein the filling slurry is prepared from tailing produced by mine beneficiation or solid waste of mine surface waste stone, and the concrete operation is as follows:
the whole tailings are loaded into a storage bin by a loader, cement is directly conveyed to an inlet of a stirrer through a cement bin, a gate and a variable-frequency speed-regulating star-shaped feeder, a spray nozzle is arranged at the inlet of the stirrer, and proper water is sprayed according to the moisture conditions of various materials before mixing, so that the moisture content of the mixture reaches the requirement required for filling. And (3) pressurizing and conveying the stirred finished product to a goaf through a filling ore pulp regulating system by a concrete pump, wherein the whole process is a continuous working process.
Fill water may be directed from a peripherally adjacent source and downhole. The filling water can be recycled, and the designed water supply system comprises a clean water pool, a filling water pool, a water pump, an electromagnetic flowmeter, a valve and the like. The regulating valve can control the water spraying amount in unit time, and the three-way joint is installed on the pipeline for cleaning equipment to prevent slurry from adhering to wall and sprinkling. Before filling, the equipment and the pipeline are wetted by filling water to prevent slurry from sticking to the wall, and after filling, the filling equipment and the filling pipeline are cleaned by clear water to prevent pipe blockage and corrosion of alkaline water to the equipment when filling is started. The water used in the filling mortar is completely pumped from the reservoir by a water pump. The guide pipe drainage water and cleaning water when starting up and stopping in production can utilize reservoir water reconstructed in mining areas as a water source. Because adopt full tailings or hierarchical cemented filling, lead to the pit to gush water mud content and increase, need set up the sedimentation tank, can make full use of idle tunnel.
Since many influence factors exist and many influence factors (such as roughness of a conveying pipeline and the like) are difficult to quantitatively calculate, for the sake of safety, different formulas are adopted for calculation respectively in the research, and then the maximum value is taken as the resistance loss (hydraulic gradient) value of the filling slurry conveying.
A. The formula for calculating the resistance loss of the heterogeneous mortar is as follows:
Figure BDA0003371618890000081
in the formula: gamma raymTailings density, 2.79t/m3
v is the working flow rate, 1.64 m/s;
i0the hydraulic gradient of the clear water is calculated according to the following formula
Figure BDA0003371618890000082
Lambda-clear water friction resistance coefficient, calculated as
Figure BDA0003371618890000083
K3-the pipeline laying coefficient is taken as 1.1;
K4-the pipe connection quality factor is taken to be 1.15;
Cv-volumeThe concentration was calculated as follows:
Figure BDA0003371618890000084
γjfull-tail mortar density of 1.79t/m3
γ0Density of water, t/m3
Cx-coefficient of sedimentation resistance, calculated according to the following formula:
Figure BDA0003371618890000091
in the formula: dcpAverage particle size of fillers, cm, dcp=0.127mm;
Omega-mean settling velocity of the particles, cm/s,
ω=123.04dcp 1.1m-1)0.7=0.74cm/s。
calculated to obtain Cx=28.6;im=0.1187mH2O/m=1187Pa/m。
B. For homogeneous mortars, the slurry resistance loss can be calculated according to the diffusion theory:
im=i0γj/γ (6)
substituting the relevant parameters into the above formula to obtain im=0.0748mH2O/m=748Pa/m。
In conclusion, the final hydraulic gradient of the mortar takes the maximum value.
C. Pipeline local resistance calculation
The local resistance of the pipeline mainly refers to installation resistance, pipeline elbow resistance and resistance generated by sudden enlargement or reduction of the pipeline. The resistance of the curve is estimated according to 8% of the loss of the pipeline along the way, and the local resistance of all the pipelines along the way is obtained, namely:
ioffice=8%i (7)
D. Pipeline total resistance calculation
The total resistance of the pipeline is calculated by the following formula:
H=Hz+HJ+HG (8)
in the formula: h, total conveying resistance of the filling slurry, namely working resistance of a conveying pump body, namely MPa;
HZ-the total resistance of the horizontal straight pipe section, MPa, of the filling slip delivery;
HJ-local resistance to the transport of the filling slip, MPa;
HG-the magnitude of the resistance loss or drag reduction caused by elevation difference during filling slurry transportation, MPa;
s2, using the collapse region range detection and analysis method, specifically operating as follows:
forming a three-dimensional visual digital model of a mining area according to a mining exploration line profile and a surface topography, forming an initial stress balance state according to the ground stress, simulating mining ore bodies section by section and caving overlying rocks to form a collapse pit according to a mining planning sequence, carrying out comparative analysis on the collapse pit and the mining situation, disclosing a mining covering layer and an overlying rock motion rule and a dynamic development process in a moving range by adopting a method of organically integrating numerical simulation analysis and mining planning, carrying out comparative analysis on a collapse area plane range obtained by simulation and a result obtained by surface aerial photography, and finally determining the collapse area range to be treated;
s3, planning the filling zones in the well: and the whole filling sequence of the underground goaf is carried out from the lower middle section to the upper middle section, and in order to avoid large-area collapse caused by goaf instability, the goaf of the lower middle section is completely filled with the roof and then is turned to the upper middle section for filling. Until the end of all filling, the specific operations are as follows:
according to the filling characteristics and the filling time sequence, the acting force of the formed filling body on the filling retaining wall is considered to be gradually reduced along with the gradual dehydration, sedimentation, condensation and hardening of the filling slurry, the acting force of the filling retaining wall by the filling slurry which is not condensed and hardened is the largest when the filling retaining wall is just filled into a stope goaf, therefore, the stress condition of the filling retaining wall when the filling slurry just enters the goaf is only analyzed, and the specific stress condition of the filling retaining wall at the moment is divided into two types:
A. the height of the surface of the filling slurry is lower than or equal to that of the filling retaining wall
The filling retaining wall is mostly rectangular in shape, the height is represented by H, the width is represented by W, and the volume weight gamma of filling slurry isLiquid for treating urinary tract infectionVolume weight after dehydration gammaThreshing deviceAnd the height of the filling slurry surface is calculated from the bottom of the filling retaining wall and is expressed by h, and the stress of the filling retaining wall is calculated according to the following formula:
Figure BDA0003371618890000101
total pressure
Figure BDA0003371618890000102
The bending moment of the filling retaining wall is as follows:
Figure BDA0003371618890000111
the maximum bending moment is:
Figure BDA0003371618890000112
maximum bending moment action point:
Figure BDA0003371618890000113
B. the height of the surface of the filling slurry is higher than that of the filling retaining wall
When the filling slurry surface is higher than the filling retaining wall, the stress condition of the filling retaining wall is calculated as follows:
q=γliquid for treating urinary tract infection(h-H)+γLiquid for treating urinary tract infection*Z (14)
The total pressure P of the filling retaining wall is as follows:
Figure BDA0003371618890000114
the bending moment of the filling retaining wall is as follows:
Figure BDA0003371618890000115
the maximum bending moment and the action point are respectively as follows:
Figure BDA0003371618890000116
Figure BDA0003371618890000117
wherein m is 3h2-3Hh+H2
It can be seen from the above formula that when the slurry surface of the filling slurry is lower than or equal to the height of the filling retaining wall, the distribution force q acting on the filling retaining wall is in direct proportion to the first square of the filling height h, the total pressure P is in direct proportion to the square of the filling height h and the first square of the width W, and the maximum bending moment Mmax is in direct proportion to the cube of the filling height h; when the filling slurry surface is higher than the filling retaining wall, the stress magnitude P and the maximum bending moment Mmax of the filling retaining wall are increased along with the increase of the height of the filling retaining wall. Therefore, the greatest factor affecting the safety of the filled retaining wall is the filling height h. Therefore, when the filling retaining wall is arranged, the height of the arrangement position of the filling retaining wall is considered in an important way, and then the filling retaining wall is comprehensively considered to be established.
According to the theoretical analysis, when the initial filling height is larger than the height of the filled retaining wall, the retaining wall is stressed greatly and the stability of the retaining wall is not facilitated; therefore, the first fill level should not generally be higher than the wall level. Therefore, according to the type that the height of the filling slurry surface is lower than or equal to that of the filled retaining wall, the total pressure, the maximum bending moment and the action point of the retaining wall at different filling heights are calculated by the formulas (10), (12) and (13).
Calculating the safety factors of retaining walls in different forms according to the stress change condition of the retaining wall, and designing the forming of the retaining wall and the tailing filling heights in different stages;
s4, calculating the stress parameters of the underground plugging wall and designing the filling height, wherein the calculation method of the stress of the underground plugging wall is as follows: according to the filling characteristics and the filling time sequence, the acting force of the formed filling body on the filling retaining wall is gradually reduced along with the gradual dehydration, sedimentation, coagulation and hardening of the filling slurry, namely the acting force of the non-coagulated and hardened filling slurry on the filling retaining wall is the largest when the filling slurry is filled into the stope goaf, so that the stress condition of the filling retaining wall when the filling slurry just enters the goaf is only analyzed, and the specific stress condition of the filling retaining wall at the moment is divided into two types, namely the filling slurry surface height is lower than or equal to the height of the filling retaining wall, and the filling slurry surface height is higher than the height of the filling retaining wall.
Examples
The ore deposit of the ore industry company of the Ningshan mountain is mined underground, the ore deposit of the Ningshan mountain of the ore deposit of the ore of the Ningshan of the ore. The maximum collapse depth was measured at the surface to be 9.38 m. By 8 months of 2020, the surface of the late peace mountain section has formed a cave-in pit of approximately 50 km 3,
the tailing slurry is difficult to convey due to the fact that the whole tailing slurry of the Hemithan mountain is fine in granularity and strong in viscosity, particularly after a curing agent is added, the conveying difficulty of the tailing slurry is increased suddenly, so that the tailing slurry is low in granularity, a large amount of water is consumed, underground drainage capacity is increased, and drainage cost is increased.
Through the contrast of filling volume statistics and collapse district rising height, there may be the dead zone collapse pit overburden stratum inside, easily in the inside water drum that forms of overburden stratum, there is the risk of surging suddenly, causes great impact kinetic energy to the shutoff wall, and shutoff wall intensity needs scientific calculation mode.
According to the design method suitable for the collapse pit tailing filling process, the tailings are used for backfilling, the safe stacking is realized, the problem of tailing stacking is solved, potential safety hazards in a collapse area are eliminated, and the method has great social benefits and economic benefits.
In summary, according to the construction method suitable for the collapse pit tailing filling process, the collapse area is backfilled by the tailings, and the safe stacking is realized, so that the problem of tailing stacking can be solved, the potential safety hazard in the collapse area can be eliminated, huge social benefits and economic benefits are achieved, a large amount of land is saved, and the engineering quantity and cost for geological disaster treatment in the later stage of the mine are greatly reduced.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (1)

1. A construction method suitable for a collapse pit tailing filling process is characterized by comprising the following steps: the specific operation is as follows:
s1, preparing tailing filling slurry and calculating pipeline conveying parameters, wherein the filling slurry is prepared from tailing produced by mine beneficiation or solid waste of mine surface waste stone, and the concrete operation is as follows:
the whole tailings are loaded into a storage bin by a loader, cement is directly conveyed to an inlet of a stirrer through a cement bin, a gate and a variable-frequency speed-regulating star-shaped feeder, a spray nozzle is arranged at the inlet of the stirrer, and proper water is sprayed according to the moisture conditions of various materials before mixing, so that the moisture content of the mixture reaches the requirement required for filling. And (3) pressurizing and conveying the stirred finished product to a goaf through a filling ore pulp regulating system by a concrete pump, wherein the whole process is a continuous working process.
Fill water may be directed from a peripherally adjacent source and downhole. The filling water can be recycled, and the designed water supply system comprises a clean water pool, a filling water pool, a water pump, an electromagnetic flowmeter, a valve and the like. The regulating valve can control the water spraying amount in unit time, and the three-way joint is installed on the pipeline for cleaning equipment to prevent slurry from adhering to wall and sprinkling. Before filling, the equipment and the pipeline are wetted by filling water to prevent slurry from sticking to the wall, and after filling, the filling equipment and the filling pipeline are cleaned by clear water to prevent pipe blockage and corrosion of alkaline water to the equipment when filling is started. The water used in the filling mortar is completely pumped from the reservoir by a water pump. The guide pipe drainage water and cleaning water when starting up and stopping in production can utilize reservoir water reconstructed in mining areas as a water source. Because adopt full tailings or hierarchical cemented filling, lead to the pit to gush water mud content and increase, need set up the sedimentation tank, can make full use of idle tunnel.
Since many influence factors exist and many influence factors (such as roughness of a conveying pipeline and the like) are difficult to quantitatively calculate, for the sake of safety, different formulas are adopted for calculation respectively in the research, and then the maximum value is taken as the resistance loss (hydraulic gradient) value of the filling slurry conveying.
A. The formula for calculating the resistance loss of the heterogeneous mortar is as follows:
Figure FDA0003371618880000011
in the formula: gamma raymTailings density, 2.79t/m3
v is the working flow rate, 1.64 m/s;
i0the hydraulic gradient of the clear water is calculated according to the following formula
Figure FDA0003371618880000021
Lambda-clear water friction resistance coefficient, calculated as
Figure FDA0003371618880000022
K3-the pipeline laying coefficient is taken as 1.1;
K4-the pipe connection quality factor is taken to be 1.15;
Cv-volume concentration, calculated according to the following formula:
Figure FDA0003371618880000023
γjfull-tail mortar density of 1.79t/m3
γ0Density of water, t/m3
Cx-coefficient of sedimentation resistance, calculated according to the following formula:
Figure FDA0003371618880000024
in the formula: dcpAverage particle size of fillers, cm, dcp=0.127mm;
Omega-mean settling velocity of the particles, cm/s,
ω=123.04dcp 1.1m-1)0.7=0.74cm/s。
calculated to obtain Cx=28.6;im=0.1187mH2O/m=1187Pa/m。
B. For homogeneous mortars, the slurry resistance loss can be calculated according to the diffusion theory:
im=i0γj/γ (6)
substituting the relevant parameters into the above formula to obtain im=0.0748mH2O/m=748Pa/m。
In conclusion, the final hydraulic gradient of the mortar takes the maximum value.
C. Pipeline local resistance calculation
The local resistance of the pipeline mainly refers to installation resistance, pipeline elbow resistance and resistance generated by sudden enlargement or reduction of the pipeline. The resistance of the curve is estimated according to 8% of the loss of the pipeline along the way, and the local resistance of all the pipelines along the way is obtained, namely:
ioffice=8%i (7)
D. Pipeline total resistance calculation
The total resistance of the pipeline is calculated by the following formula:
H=Hz+HJ+HG (8)
in the formula: h, total conveying resistance of the filling slurry, namely working resistance of a conveying pump body, namely MPa;
HZ-the total resistance of the horizontal straight pipe section, MPa, of the filling slip delivery;
HJ-local resistance to the transport of the filling slip, MPa;
HG-the magnitude of the resistance loss or drag reduction caused by elevation difference during filling slurry transportation, MPa;
s2, using the collapse region range detection and analysis method, specifically operating as follows:
forming a three-dimensional visual digital model of a mining area according to a mining exploration line profile and a surface topography, forming an initial stress balance state according to the ground stress, simulating mining ore bodies section by section and caving overlying rocks to form a collapse pit according to a mining planning sequence, carrying out comparative analysis on the collapse pit and the mining situation, disclosing a mining covering layer and an overlying rock motion rule and a dynamic development process in a moving range by adopting a method of organically integrating numerical simulation analysis and mining planning, carrying out comparative analysis on a collapse area plane range obtained by simulation and a result obtained by surface aerial photography, and finally determining the collapse area range to be treated;
s3, planning the filling zones in the well: and the whole filling sequence of the underground goaf is carried out from the lower middle section to the upper middle section, and in order to avoid large-area collapse caused by goaf instability, the goaf of the lower middle section is completely filled with the roof and then is turned to the upper middle section for filling. Until the end of all filling, the specific operations are as follows:
according to the filling characteristics and the filling time sequence, the acting force of the formed filling body on the filling retaining wall is considered to be gradually reduced along with the gradual dehydration, sedimentation, condensation and hardening of the filling slurry, the acting force of the filling retaining wall by the filling slurry which is not condensed and hardened is the largest when the filling retaining wall is just filled into a stope goaf, therefore, the stress condition of the filling retaining wall when the filling slurry just enters the goaf is only analyzed, and the specific stress condition of the filling retaining wall at the moment is divided into two types:
A. the height of the surface of the filling slurry is lower than or equal to that of the filling retaining wall
The filling retaining wall is mostly rectangular in shape, the height is represented by H, the width is represented by W, and the volume weight gamma of filling slurry isLiquid for treating urinary tract infectionVolume weight after dehydration gammaThreshing deviceAnd the height of the filling slurry surface is calculated from the bottom of the filling retaining wall and is expressed by h, and the stress of the filling retaining wall is calculated according to the following formula:
Figure FDA0003371618880000041
total pressure
Figure FDA0003371618880000042
The bending moment of the filling retaining wall is as follows:
Figure FDA0003371618880000043
the maximum bending moment is:
Figure FDA0003371618880000044
maximum bending moment action point:
Figure FDA0003371618880000045
B. the height of the surface of the filling slurry is higher than that of the filling retaining wall
When the filling slurry surface is higher than the filling retaining wall, the stress condition of the filling retaining wall is calculated as follows:
q=γliquid for treating urinary tract infection(h-H)+γLiquid for treating urinary tract infection*Z (14)
The total pressure P of the filling retaining wall is as follows:
Figure FDA0003371618880000051
the bending moment of the filling retaining wall is as follows:
Figure FDA0003371618880000052
the maximum bending moment and the action point are respectively as follows:
Figure FDA0003371618880000053
Figure FDA0003371618880000054
wherein m is 3h2-3Hh+H2
It can be seen from the above formula that when the slurry surface of the filling slurry is lower than or equal to the height of the filling retaining wall, the distribution force q acting on the filling retaining wall is in direct proportion to the first square of the filling height h, the total pressure P is in direct proportion to the square of the filling height h and the first square of the width W, and the maximum bending moment Mmax is in direct proportion to the cube of the filling height h; when the filling slurry surface is higher than the filling retaining wall, the stress magnitude P and the maximum bending moment Mmax of the filling retaining wall are increased along with the increase of the height of the filling retaining wall. Therefore, the greatest factor affecting the safety of the filled retaining wall is the filling height h. Therefore, when the filling retaining wall is arranged, the height of the arrangement position of the filling retaining wall is considered in an important way, and then the filling retaining wall is comprehensively considered to be established.
According to the theoretical analysis, when the initial filling height is larger than the height of the filled retaining wall, the retaining wall is stressed greatly and the stability of the retaining wall is not facilitated; therefore, the first fill level should not generally be higher than the wall level. Therefore, according to the type that the height of the filling slurry surface is lower than or equal to that of the filled retaining wall, the total pressure, the maximum bending moment and the action point of the retaining wall at different filling heights are calculated by the formulas (10), (12) and (13).
Calculating the safety factors of retaining walls in different forms according to the stress change condition of the retaining wall, and designing the forming of the retaining wall and the tailing filling heights in different stages;
s4, calculating the stress parameters of the underground plugging wall and designing the filling height, wherein the calculation method of the stress of the underground plugging wall is as follows: according to the filling characteristics and the filling time sequence, the acting force of the formed filling body on the filling retaining wall is gradually reduced along with the gradual dehydration, sedimentation, coagulation and hardening of the filling slurry, namely the acting force of the non-coagulated and hardened filling slurry on the filling retaining wall is the largest when the filling slurry is filled into the stope goaf, so that the stress condition of the filling retaining wall when the filling slurry just enters the goaf is only analyzed, and the specific stress condition of the filling retaining wall at the moment is divided into two types, namely the filling slurry surface height is lower than or equal to the height of the filling retaining wall, and the filling slurry surface height is higher than the height of the filling retaining wall.
CN202111402725.XA 2021-11-24 2021-11-24 A Construction Method Applicable to Tailings Filling Technology of Subsidence Pit Active CN114033483B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111402725.XA CN114033483B (en) 2021-11-24 2021-11-24 A Construction Method Applicable to Tailings Filling Technology of Subsidence Pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111402725.XA CN114033483B (en) 2021-11-24 2021-11-24 A Construction Method Applicable to Tailings Filling Technology of Subsidence Pit

Publications (2)

Publication Number Publication Date
CN114033483A true CN114033483A (en) 2022-02-11
CN114033483B CN114033483B (en) 2023-07-18

Family

ID=80145346

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111402725.XA Active CN114033483B (en) 2021-11-24 2021-11-24 A Construction Method Applicable to Tailings Filling Technology of Subsidence Pit

Country Status (1)

Country Link
CN (1) CN114033483B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115167155A (en) * 2022-09-07 2022-10-11 北京首钢矿山建设工程有限责任公司 Intelligent mixed preparation method for filling body in mine goaf
CN116663782A (en) * 2023-07-28 2023-08-29 中国环境科学研究院 A tailings greenhouse gas emission accounting method, electronic equipment and storage medium
CN116578813B (en) * 2023-07-07 2023-09-15 中南大学 Calculation method and system for final settling velocity of irregular particles in Newtonian fluid
CN116842623A (en) * 2023-08-30 2023-10-03 武汉科技大学 Stability calculation analysis, reinforcement methods and systems of filled retaining walls
CN118114334A (en) * 2023-11-08 2024-05-31 北京金诚信矿山技术研究院有限公司 A method, system and device for determining a design scheme of a filling retaining wall
CN119393181A (en) * 2025-01-03 2025-02-07 烟台安达环保科技有限公司 A coal mine underground filling method using gold mine overflow tailings

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2055218C1 (en) * 1992-08-10 1996-02-27 Научно-исследовательский, проектный и конструкторский институт горного дела и металлургии цветных металлов Method for different strength backfills of underground drifts and device for implementation the same
CN102434204A (en) * 2011-10-13 2012-05-02 金川集团有限公司 Mine waste rock and all tailing pipeline conveying filling system and filling method using same
CN105422068A (en) * 2015-11-12 2016-03-23 中国石油天然气股份有限公司 Method for developing heavy oil reservoirs by combining horizontal well staged volume fracturing and fracturing-packing
CN106088107A (en) * 2016-06-20 2016-11-09 中钢集团马鞍山矿山研究院有限公司 A kind of method that tailings impoundment produces surface subsidence hole, mine in Caving Method with Large Space
US20160348507A1 (en) * 2014-05-08 2016-12-01 China University Of Mining And Technology Water-preserved-mining roof-contacted filling method for controlling fissure of overlying strata and surface subsidence
CN107975044A (en) * 2016-10-24 2018-05-01 南京梅山冶金发展有限公司 A kind of method that Caving Method with Large Space mine is backfilled using tailing surface subsidence hole
CN108915765A (en) * 2018-07-02 2018-11-30 北京科技大学 A kind of underground crude tailings-barren rock Paste-filling System and placement method
CN109706952A (en) * 2018-12-25 2019-05-03 中建四局第六建筑工程有限公司 Large-scale well-sinking construction method
CN110382435A (en) * 2016-10-26 2019-10-25 加利福尼亚大学董事会 Upgrading reconstruction concrete product manufactures effectively integrating in generating equipment

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2055218C1 (en) * 1992-08-10 1996-02-27 Научно-исследовательский, проектный и конструкторский институт горного дела и металлургии цветных металлов Method for different strength backfills of underground drifts and device for implementation the same
CN102434204A (en) * 2011-10-13 2012-05-02 金川集团有限公司 Mine waste rock and all tailing pipeline conveying filling system and filling method using same
US20160348507A1 (en) * 2014-05-08 2016-12-01 China University Of Mining And Technology Water-preserved-mining roof-contacted filling method for controlling fissure of overlying strata and surface subsidence
CN105422068A (en) * 2015-11-12 2016-03-23 中国石油天然气股份有限公司 Method for developing heavy oil reservoirs by combining horizontal well staged volume fracturing and fracturing-packing
CN106088107A (en) * 2016-06-20 2016-11-09 中钢集团马鞍山矿山研究院有限公司 A kind of method that tailings impoundment produces surface subsidence hole, mine in Caving Method with Large Space
CN107975044A (en) * 2016-10-24 2018-05-01 南京梅山冶金发展有限公司 A kind of method that Caving Method with Large Space mine is backfilled using tailing surface subsidence hole
CN110382435A (en) * 2016-10-26 2019-10-25 加利福尼亚大学董事会 Upgrading reconstruction concrete product manufactures effectively integrating in generating equipment
CN108915765A (en) * 2018-07-02 2018-11-30 北京科技大学 A kind of underground crude tailings-barren rock Paste-filling System and placement method
CN109706952A (en) * 2018-12-25 2019-05-03 中建四局第六建筑工程有限公司 Large-scale well-sinking construction method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115167155A (en) * 2022-09-07 2022-10-11 北京首钢矿山建设工程有限责任公司 Intelligent mixed preparation method for filling body in mine goaf
CN116578813B (en) * 2023-07-07 2023-09-15 中南大学 Calculation method and system for final settling velocity of irregular particles in Newtonian fluid
CN116663782A (en) * 2023-07-28 2023-08-29 中国环境科学研究院 A tailings greenhouse gas emission accounting method, electronic equipment and storage medium
CN116663782B (en) * 2023-07-28 2023-10-10 中国环境科学研究院 A tailings greenhouse gas emission accounting method, electronic equipment and storage medium
CN116842623A (en) * 2023-08-30 2023-10-03 武汉科技大学 Stability calculation analysis, reinforcement methods and systems of filled retaining walls
CN116842623B (en) * 2023-08-30 2023-11-10 武汉科技大学 Method and system for calculating, analyzing and reinforcing stability of filling retaining wall
CN118114334A (en) * 2023-11-08 2024-05-31 北京金诚信矿山技术研究院有限公司 A method, system and device for determining a design scheme of a filling retaining wall
CN119393181A (en) * 2025-01-03 2025-02-07 烟台安达环保科技有限公司 A coal mine underground filling method using gold mine overflow tailings

Also Published As

Publication number Publication date
CN114033483B (en) 2023-07-18

Similar Documents

Publication Publication Date Title
CN114033483A (en) A construction method suitable for tailings filling process in collapse pits
CN108915765B (en) Underground full tailing-waste stone paste filling system and filling method
CN103291325B (en) The preventing control method of Coal-mining Above Confined-water floor strata gushing water
CN102418555B (en) Method for filling mine goaf by utilizing high-concentration all tailing cement
CN104405436B (en) A kind of method improving ore body Tight filling rate
CN1165667C (en) Method for filling cavities with aggregate
CN106121722A (en) A kind of method quickly constructing fire dam
CN113339056A (en) Fluidized gangue layer surface subsequent filling system and method
CN111978018B (en) Size and form control method for high-concentration slurry filling pier column in cavity type goaf
CN113339058A (en) Fluidized gangue layer adjacent surface subsequent filling system and method
WO2019105162A1 (en) Microbial modification filling-based coal mining method
CN107975044B (en) Method for backfilling collapse method mine by utilizing tailing surface collapse pits
CN201041052Y (en) Stope filling paste preparation system
CN110307034A (en) Strip Grouting Filling Method in Goaf
Liu Technologies and practices of mechanized backfill mining for water protection with aeolian sand paste-like
CN105971605B (en) A kind of underground mines exploration without waster method
CN109577988A (en) A kind of blind oblique vertical shaft parallel construction method of metal mine
CN109899070B (en) Non-solid waste filling mining method for gently inclined medium-thick ore bodies based on ellipsoid drawing structure
CN106065782A (en) A kind of big flow high concentration structure stream full tail sand cemented filling technique
CN106088107B (en) A kind of tailings impoundment is in the method in Caving Method with Large Space production mine surface subsidence hole
CN104763467B (en) Obturation and its placement method and system for Hazard in Deep Metal Mines goaf
Emad et al. Backfill practices for sublevel stoping system
CN109555559A (en) A kind of metal mine km grade interior shaft water control technique method
Wu et al. Development and challenge of paste technology in China
Kouame et al. A study of technical measures for increasing the roof-contacted ratio in stope and cavity filling

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant