CN114016516A - Concrete-steel structure mixed angle brace construction method - Google Patents

Concrete-steel structure mixed angle brace construction method Download PDF

Info

Publication number
CN114016516A
CN114016516A CN202111316108.8A CN202111316108A CN114016516A CN 114016516 A CN114016516 A CN 114016516A CN 202111316108 A CN202111316108 A CN 202111316108A CN 114016516 A CN114016516 A CN 114016516A
Authority
CN
China
Prior art keywords
layer
support
supporting
concrete
forming
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111316108.8A
Other languages
Chinese (zh)
Inventor
刘定武
卢华
郁健
张云
田钦先
田伟
付汝宾
刘兴盛
徐磊
徐东方
聂志平
李櫪
谢博章
魏新山
吴汝琴
郑钰昌
崔怡恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No 1 Construction Engineering Co Ltd of Guizhou Construction and Engineering Group
Original Assignee
No 1 Construction Engineering Co Ltd of Guizhou Construction and Engineering Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No 1 Construction Engineering Co Ltd of Guizhou Construction and Engineering Group filed Critical No 1 Construction Engineering Co Ltd of Guizhou Construction and Engineering Group
Priority to CN202111316108.8A priority Critical patent/CN114016516A/en
Publication of CN114016516A publication Critical patent/CN114016516A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a concrete-steel structure mixed angle brace construction method, which comprises the following steps in sequence: forming the anti-slide pile and the crown beam: pouring anti-slide piles and crown beams on the side soil layer of the road side of the public line and the side soil layer of the subway line, wherein the crown beams are formed on the tops of the anti-slide piles; forming an early warning layer: and forming an early warning layer capable of observing the support deformation of the support structure on the anti-slide pile and the crown beam. After vehicles running on the road side soil layer of the public road and the road side soil layer of the subway line enable the supporting structure to support deformation, due to the fact that the early warning layer formed by pouring steel bars and concrete exists, the concrete on the early warning layer can crack and can be observed visually and quickly through naked eyes, the problem that deformation cannot be observed visually at present is solved, and the effect of early warning in advance is achieved.

Description

Concrete-steel structure mixed angle brace construction method
Technical Field
The invention relates to a concrete-steel structure mixed angle brace construction method, and belongs to the technical field of building construction.
Background
When building high-rise building, need carry out deep digging to the building foundation, though can make high-rise building obtain good ground after deep digging, nevertheless also can make deep basal pit foundation side slope appear the danger of collapsing, especially the deep basal pit appears with triangle-shaped, and when both sides limit corresponds for highway and subway line, it is especially important to the protection that deep basal pit side slope collapses.
In order to effectively protect the collapse of the side slope at the triangular position of the deep foundation pit, the angle supporting layer and the upright post are used for effectively protecting the side slope at the triangular position of the deep foundation pit by using the angle supporting layer and the upright post of the deep and large foundation pit horizontal shear-resistant structure with the Chinese patent publication No. CN 103967018B.
Disclosure of Invention
In order to solve the technical problem, the invention provides a concrete-steel structure mixed angle brace construction method.
The invention is realized by the following technical scheme.
The invention provides a concrete-steel structure mixed angle brace construction method, which comprises the following steps in sequence:
forming the anti-slide pile and the crown beam: pouring anti-slide piles and crown beams on the side soil layer of the road side of the public line and the side soil layer of the subway line, wherein the crown beams are formed on the tops of the anti-slide piles;
forming an early warning layer: and forming an early warning layer capable of observing the support deformation of the support structure on the anti-slide pile and the crown beam.
The early warning layer is formed as follows: digging up dregs to elevation that the foundation ditch is expected to form early warning layer space, the supporting beam section, early warning waist rail, ox horn roof beam use reinforcing bar and mix earth and pour the shaping and form the early warning layer, reinforcing bar and mix earth pour the shaping structure for can observing the supporting structure and take place the early warning layer that supports deformation, the degree of depth that anti-slide pile and crown beam were implanted to early warning waist rail, ox horn roof beam is not less than thirty centimetres.
And between the step of forming the anti-slide pile and the crown beam and the step of forming the early warning layer, the step of forming the upright post pile is further included.
The forming steps of the upright post pile are as follows: and forming the upright post pile in the middle of the third edge of the triangular pre-excavation forming of the deep foundation pit.
After the upright post pile forming step, forming a support wale of a support layer, wherein the support wale of the support layer is formed by: continuously excavating the foundation pit to an elevation, wherein the foundation pit is expected to form slag soil in a supporting layer space, forming a supporting waist beam of the supporting layer on the anti-slide pile, and embedding an embedded part in the supporting waist beam; repeating the step of forming the supporting layer until the supporting wale of the other supporting layer below is formed;
after the step of forming the supporting wale of the supporting layer, the method further comprises a supporting layer building, wherein the supporting layer building is as follows: each supporting layer is provided with three supporting layer supporting beams; the two supporting layer supporting beams on the long side can slide on the supporting frame, the supporting frame is welded on the upright post pile, and the support of the upright post pile reduces the winding degree of the supporting layer supporting beams; supporting layer supporting beam one end is connected with the built-in fitting through the head of living, and the other end is direct to be welded with the built-in fitting, and the basic part and the built-in fitting welding of the head of living, basic part and the straight section of thick bamboo section sliding fit of flange, flange are connected with supporting layer supporting beam through the bolt, and two oblique building blocks are installed in the through-hole inclined plane that sets up on the basic part through running through.
After the supporting layer is built, prestress application is further included, and the prestress application is as follows: exerting pressure on the flange, sliding on the base part to the flange, knocking the two inclined building blocks to match the inclination, enabling the supporting layer supporting beams to reach a pre-tightening stable supporting state, welding and fixing the base part and the flange straight cylinder section, and fixing the two supporting layer supporting beams on the long edge on the supporting frame by welding the I-shaped beam on the supporting frame after each supporting layer is in the same state.
The invention has the beneficial effects that: after vehicles running on the road side soil layer of the public road and the road side soil layer of the subway line enable the supporting structure to support deformation, due to the fact that the early warning layer formed by pouring steel bars and concrete exists, the concrete on the early warning layer can crack and can be observed visually and quickly through naked eyes, the problem that deformation cannot be observed visually at present is solved, and the effect of early warning in advance is achieved.
Drawings
FIG. 1 is a schematic structural view after the construction and molding of the present invention;
FIG. 2 is a schematic top view of the support layer and the anti-slide pile after construction and forming according to the present invention;
FIG. 3 is a schematic diagram of the construction of the articulating head of the present invention;
FIG. 4 is a schematic view of the support frame of the present invention mounted on a support waist;
in the figure: 1-road side soil layer of the highway; 2-side soil layer of subway line; 3-anti-slide pile; 4-a crown beam; 5-early warning layer; 51-a support beam section; 52-early warning waist rail; 53-ox horn beam; 6-a support layer; 61-supporting wale; 62-embedded parts; 63-living head; 631-a base member; 632-a flange; 633-oblique building blocks; 64-supporting layer support beams; 7-a support frame; 8-vertical column pile.
Detailed Description
The technical solution of the present invention is further described below, but the scope of the claimed invention is not limited to the described.
See fig. 1-4.
The invention relates to a concrete-steel structure mixed angle brace construction method, which comprises the following steps in sequence:
forming the anti-slide pile and the crown beam: a plurality of pile holes are respectively drilled in a road side soil layer 1 of a public road and a road side soil layer 2 of a subway, anti-slide piles 3 and crown beams 4 are poured in the pile holes, and the crown beams 4 are formed on the tops of the anti-slide piles 3.
Forming the upright post pile: digging a pile hole in the middle of the third edge of the triangular pre-digging forming of the deep foundation pit, placing a steel pipe and a reinforcement cage formed by the upright post pile 8 into the pile hole, pouring concrete, and filling a gap between the upright post pile 8 and the pile hole with fine sand after forming.
Forming an early warning layer: excavating the slag soil predicted to form the space of the early warning layer 5 of the foundation pit to an elevation, pre-supporting a supporting beam section 51, an early warning waist beam 52 and a ox horn beam 53 forming space of the early warning layer 5 on the top of a vertical column pile 8 by using a template, then pouring and forming the supporting beam section 51, the early warning waist beam 52 and the ox horn beam 53 which are extended out of the early warning layer 5 by using reinforcing steel bars and concrete, connecting the top of the vertical column pile 8 with the middle part of the early warning layer 5 through bolts, and implanting anti-slide piles 3 and crown beams 4 into the early warning waist beam 52 and the ox horn beam 53 with the depth not less than thirty centimeters;
after vehicles running on the soil layer 1 on the side of the highway line and the soil layer 2 on the side of the subway line enable the supporting structure to be supported and deformed, the early warning layer 5 formed by pouring steel bars and concrete exists, the concrete on the early warning layer 5 can crack and can be visually and quickly observed through naked eyes, the problem that deformation cannot be visually observed at present is solved, and the early warning effect is achieved.
Forming a support waist beam of the support layer: removing the template of the early warning layer 5, continuously excavating foundation pits to estimate the slag soil in the space of the supporting layer 6 to reach the elevation, forming a supporting waist beam 61 of the supporting layer 6 on the anti-slide pile 3 by using concrete, and pre-burying an upper embedded part 62 on the supporting waist beam 61; repeating the step of forming the supporting layer until the supporting wale of the other supporting layer below is formed;
building a supporting layer: a plurality of steel pipes are welded on site to form supporting layer supporting beams 64 of the supporting layer 6, and each supporting layer is provided with three supporting layer supporting beams 64; the two support layer support beams 64 on the long side can slide on the support frame 7 and are welded and reinforced with each other by using a connecting piece, the support frame 7 is welded on the upright post 8, and the support of the upright post 8 reduces the winding degree of the support layer support beams 64; two ends of the supporting layer supporting beam 64 are directly welded with the embedded part 62; or one end of the supporting layer supporting beam 64 is connected with the embedded part 62 through the movable head 63, the other end of the supporting layer supporting beam 64 is directly welded with the embedded part 62, at the moment, the base part 631 of the movable head 63 is welded with the embedded part 62, the base part 631 is in straight cylinder section sliding fit with the flange 632, the flange 632 is connected with the supporting layer supporting beam 64 through bolts, and two inclined building blocks 633 are installed through the inclined plane of the through hole formed in the base part 631.
Applying prestress: apply pressure to flange 632 through using hydraulic equipment, slide on basic piece 631 to flange 632, strike two oblique building block 633 cooperation slopes for supporting layer supporting beam 64 reaches pretension steady support state, with basic piece 631 and the straight section of cylinder welded fastening of flange 632, after all being in the same state to every supporting layer, fix two supporting layer supporting beam 64 on long limit on support frame 7 through welding the I-beam at support frame 7.

Claims (10)

1. The concrete-steel structure mixed angle brace construction method is characterized by comprising the following steps of:
forming the anti-slide pile and the crown beam: pouring anti-slide piles (3) and crown beams (4) on the side of a road side soil layer (1) of a public road and a side soil layer (2) of a subway line, wherein the crown beams (4) are formed on the tops of the anti-slide piles (3);
forming an early warning layer: and forming an early warning layer capable of observing the support deformation of the support structure on the anti-slide pile (3) and the crown beam (4).
2. The concrete-steel structure hybrid gusset construction method according to claim 1, wherein the early warning layer is formed by: dig the dregs to the elevation that the foundation ditch is expected to form early warning layer (5) space, supporting beam section (51), early warning waist rail (52), ox horn roof beam (53) use reinforcing bar and concrete to pour the shaping and form early warning layer (5), reinforcing bar and concrete pour the shaping structure and for observing that supporting structure takes place to support the early warning layer of deformation, early warning waist rail (52), the degree of depth that anti-slide pile (3) and crown beam (4) were implanted in ox horn roof beam (53) is not less than thirty centimetres.
3. The concrete-steel structure hybrid corner brace construction method according to claim 1, further comprising the step of forming a stud pile between the step of forming the slide-resistant pile and the crown beam to the step of forming the early warning layer.
4. The concrete-steel structure hybrid gusset construction method of claim 2, wherein the post pile is formed by the steps of: and forming the upright post pile (8) in the middle of the third edge of the triangular pre-excavation forming of the deep foundation pit.
5. The concrete-steel structure hybrid gusset construction method as set forth in claim 4, wherein: and after the upright post pile forming step, forming a support wale further comprising a support layer.
6. The concrete-steel structure hybrid corner brace construction method of claim 5, wherein the support wale of the support layer is formed as: continuously excavating the residual soil in the space of the support layer (6) which is expected to be formed in the foundation pit to the elevation, forming a support waist beam (61) of the support layer (6) on the anti-slide pile (3), and pre-burying an embedded part (62) on the support waist beam (61); and repeating the step of forming the supporting layer to form the supporting wale of other supporting layers below.
7. The concrete-steel structure hybrid corner brace construction method according to claim 5, further comprising a support layer building after the support wale forming step of the support layer.
8. The concrete-steel structure hybrid gusset construction method according to claim 7, wherein the support layer is constructed by: three support layer support beams (64) per support layer; two supporting layer supporting beams (64) on the long side can slide on the supporting frame (7), and the supporting frame (7) is welded on the upright post pile (8); one end of a supporting layer supporting beam (64) is connected with an embedded part (62) through a movable joint (63), the other end of the supporting layer supporting beam is directly welded with the embedded part (62), a base part (631) of the movable joint (63) is welded with the embedded part (62), the base part (631) is in sliding fit with a straight cylinder section of a flange (632), the flange (632) is connected with the supporting layer supporting beam (64) through bolts, and two inclined building blocks (633) are installed on a through hole inclined plane arranged on the base part (631) in a penetrating mode.
9. The concrete-steel structure hybrid corner brace construction method according to claim 8, further comprising applying a prestress after the supporting layer construction step.
10. The concrete-steel structure hybrid gusset construction method of claim 9, wherein the pre-stressing is: pressure is applied to the flange (632), the flange (632) slides on the base part (631), the two inclined building blocks (633) are knocked to match the inclination, so that the support layer support beam (64) reaches a pre-tightening stable support state, the base part (631) and the straight cylinder section of the flange (632) are welded and fixed, and after each support layer is in the same state, the two support layer support beams (64) on the long side are fixed on the support frame (7) through welding an I-beam on the support frame (7).
CN202111316108.8A 2021-11-08 2021-11-08 Concrete-steel structure mixed angle brace construction method Pending CN114016516A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111316108.8A CN114016516A (en) 2021-11-08 2021-11-08 Concrete-steel structure mixed angle brace construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111316108.8A CN114016516A (en) 2021-11-08 2021-11-08 Concrete-steel structure mixed angle brace construction method

Publications (1)

Publication Number Publication Date
CN114016516A true CN114016516A (en) 2022-02-08

Family

ID=80062645

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111316108.8A Pending CN114016516A (en) 2021-11-08 2021-11-08 Concrete-steel structure mixed angle brace construction method

Country Status (1)

Country Link
CN (1) CN114016516A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115627771A (en) * 2022-10-13 2023-01-20 广东省基础工程集团有限公司 Foundation pit supporting structure
CN118997179A (en) * 2024-10-23 2024-11-22 中交第一航务工程局有限公司 Deep foundation pit concrete steel support combined structure and construction method thereof

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103967018A (en) * 2014-05-09 2014-08-06 深圳市工勘岩土集团有限公司 Deep and large foundation pit angle supporting horizontal shearing resistance structure
CN104912098A (en) * 2015-06-01 2015-09-16 中建四局第六建筑工程有限公司 Combined construction method for supporting beam plate and structural plate of deep foundation pit
CN206616421U (en) * 2017-03-01 2017-11-07 广州地铁设计研究院有限公司 A kind of interim bedding structure across Metro station excavation
CN208167749U (en) * 2018-04-18 2018-11-30 中铁十九局集团轨道交通工程有限公司 Stable steel purlin support system in Deep Foundation Pit of Metro Stations digging process
CN109403342A (en) * 2018-10-31 2019-03-01 中建局集团建设发展有限公司 A kind of foundation pit mixing support construction and its construction method
CN209636806U (en) * 2018-12-11 2019-11-15 宏润建设集团股份有限公司 A kind of steel support structure
CN209779634U (en) * 2018-11-20 2019-12-13 中铁十二局集团第四工程有限公司 Assembled reinforced concrete bearing structure suitable for subway station foundation ditch
CN210151752U (en) * 2019-04-04 2020-03-17 广州市市政工程设计研究总院有限公司 A kind of foundation pit steel roof support
CN211228518U (en) * 2019-09-05 2020-08-11 中铁十六局集团北京轨道交通工程建设有限公司 A steel tube support structure
WO2020173100A1 (en) * 2019-02-26 2020-09-03 济南轨道交通集团有限公司 Reinforcement apparatus and construction method for local freezing reinforcement of deep foundation pit in water-rich sand gravel stratum
CN112813991A (en) * 2021-01-06 2021-05-18 安徽省公路桥梁工程有限公司 Excavation and support construction method for deep foundation pit of subway transfer station
CN113502828A (en) * 2021-07-23 2021-10-15 上海宝冶集团有限公司 Processing method for early warning of deep foundation pit

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103967018A (en) * 2014-05-09 2014-08-06 深圳市工勘岩土集团有限公司 Deep and large foundation pit angle supporting horizontal shearing resistance structure
CN104912098A (en) * 2015-06-01 2015-09-16 中建四局第六建筑工程有限公司 Combined construction method for supporting beam plate and structural plate of deep foundation pit
CN206616421U (en) * 2017-03-01 2017-11-07 广州地铁设计研究院有限公司 A kind of interim bedding structure across Metro station excavation
CN208167749U (en) * 2018-04-18 2018-11-30 中铁十九局集团轨道交通工程有限公司 Stable steel purlin support system in Deep Foundation Pit of Metro Stations digging process
CN109403342A (en) * 2018-10-31 2019-03-01 中建局集团建设发展有限公司 A kind of foundation pit mixing support construction and its construction method
CN209779634U (en) * 2018-11-20 2019-12-13 中铁十二局集团第四工程有限公司 Assembled reinforced concrete bearing structure suitable for subway station foundation ditch
CN209636806U (en) * 2018-12-11 2019-11-15 宏润建设集团股份有限公司 A kind of steel support structure
WO2020173100A1 (en) * 2019-02-26 2020-09-03 济南轨道交通集团有限公司 Reinforcement apparatus and construction method for local freezing reinforcement of deep foundation pit in water-rich sand gravel stratum
CN210151752U (en) * 2019-04-04 2020-03-17 广州市市政工程设计研究总院有限公司 A kind of foundation pit steel roof support
CN211228518U (en) * 2019-09-05 2020-08-11 中铁十六局集团北京轨道交通工程建设有限公司 A steel tube support structure
CN112813991A (en) * 2021-01-06 2021-05-18 安徽省公路桥梁工程有限公司 Excavation and support construction method for deep foundation pit of subway transfer station
CN113502828A (en) * 2021-07-23 2021-10-15 上海宝冶集团有限公司 Processing method for early warning of deep foundation pit

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115627771A (en) * 2022-10-13 2023-01-20 广东省基础工程集团有限公司 Foundation pit supporting structure
CN118997179A (en) * 2024-10-23 2024-11-22 中交第一航务工程局有限公司 Deep foundation pit concrete steel support combined structure and construction method thereof
CN118997179B (en) * 2024-10-23 2025-01-28 中交第一航务工程局有限公司 A deep foundation pit concrete steel support composite structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN113482011B (en) Large-diameter PHC pipe pile and cast-in-situ bored pile combined foundation pit supporting structure and method
CN206721894U (en) Adjustable prestress device for foundation pit support
CN101538833B (en) Vertical subsection double-wall steel cofferdam water stopping construction method
CN109356169A (en) A kind of foundation pit row pile support system and construction method thereof
CN205875209U (en) Temporary road surface system supports with concrete and closes subway station half range bedding structure of establishing
CN106759461A (en) Resist grand supporting construction
CN109403654A (en) A kind of underpinning method of existing building structure
CN209040150U (en) A kind of rigid frame formula peg board retaining wall
CN208152052U (en) Steel sheet pile underground structure of controllable deformation
CN114016516A (en) Concrete-steel structure mixed angle brace construction method
CN209179021U (en) A foundation pit row pile support system
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN214530750U (en) Bridge pile foundation structure suitable for rock mass abrupt slope
CN110258600B (en) Vertical cofferdam construction method suitable for deepwater area
CN209412681U (en) Trestle work structure
CN112627035A (en) Design and construction method of large-span Bailey steel trestle
CN108951647A (en) Construction method for supporting is excavated in hole in the hole of open trench tunnel
CN114351567B (en) Road bridge connection structure and construction method
CN107299640A (en) A kind of variable cross-section well shaft type ground continuous wall base and its construction method
CN214832726U (en) Supporting structure for pipe-jacking working well in deep soft soil area
CN112227391B (en) Ecological steel sheet pile island-building cofferdam and construction method
CN110939139B (en) Pile-sheet wall structure and construction method based on rigid contact of special-shaped retaining wall behind piles
CN112878216A (en) Suspension type railway underpass box culvert jacking track reinforcing method
CN219653491U (en) Steel construction abutment suitable for steel trestle
CN112575777A (en) Frame reinforcing system and method for high-speed railway pier foundation penetrating through under channel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20220208