CN113998411B - Gantry-type outriggers and double-layer conveyor system for side-by-side layout of the upper conveyor line - Google Patents
Gantry-type outriggers and double-layer conveyor system for side-by-side layout of the upper conveyor line Download PDFInfo
- Publication number
- CN113998411B CN113998411B CN202111231766.7A CN202111231766A CN113998411B CN 113998411 B CN113998411 B CN 113998411B CN 202111231766 A CN202111231766 A CN 202111231766A CN 113998411 B CN113998411 B CN 113998411B
- Authority
- CN
- China
- Prior art keywords
- conveying mechanism
- conveying
- hoop
- type
- beams
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65G—TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
- B65G41/00—Supporting frames or bases for conveyors as a whole, e.g. transportable conveyor frames
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65G—TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
- B65G13/00—Roller-ways
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65G—TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
- B65G37/00—Combinations of mechanical conveyors of the same kind, or of different kinds, of interest apart from their application in particular machines or use in particular manufacturing processes
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Rollers For Roller Conveyors For Transfer (AREA)
Abstract
Description
技术领域technical field
本发明涉及物料输送技术领域,特别是涉及一种用于上层输送线并排布局的龙门式支腿及双层输送系统。The invention relates to the technical field of material conveying, in particular to a gantry-type outrigger and a double-layer conveying system used for the side-by-side arrangement of upper conveying lines.
背景技术Background technique
滚筒输送机可以沿水平或较小的倾斜角输送具有平直底部的成件物品,如板,棒,管,型材,托盘,箱类容器及各种工件。对于非平底物品及柔性物品可借助托盘实现输送。具有结构简单,运转可靠,维护方便,经济,节能等特点,最突出的是他与生产工艺过程能较好地衔接和配套,并具有功能的多样性。The roller conveyor can convey finished items with a flat bottom, such as plates, rods, tubes, profiles, pallets, box containers and various workpieces, along a horizontal or small inclination angle. For non-flat-bottomed items and flexible items, pallets can be used to convey them. It has the characteristics of simple structure, reliable operation, convenient maintenance, economy, energy saving, etc. The most prominent thing is that it can be well connected and matched with the production process, and has a variety of functions.
当下层的输送线紧密排布时,上层的输送线包括电辊筒顶升移载机,导致上层的输送线无法使用普通的支腿来支撑,现有的支腿结构无法满足上层输送线的电辊筒顶升移载设备的支撑要求。When the lower conveying line is closely arranged, the upper conveying line includes an electric roller jacking transfer machine, so that the upper conveying line cannot be supported by ordinary outriggers, and the existing outrigger structure cannot meet the needs of the upper conveying line. Support requirements for electric roller jacking and transferring equipment.
发明内容Contents of the invention
鉴于以上所述现有技术的缺点,本发明要解决的技术问题在于提供一种用于上层输送线并排布局的龙门式支腿及双层输送系统,能够依次并排布置多条上层输送线,并且整体刚强度较大,从而使双层输送系统的集成度更高。In view of the above-mentioned shortcomings of the prior art, the technical problem to be solved by the present invention is to provide a gantry-type outrigger and a double-layer conveying system for the side-by-side layout of the upper-level conveying lines, which can arrange multiple upper-level conveying lines side by side in sequence, and The overall rigidity is higher, so that the integration of the double-layer conveying system is higher.
为了解决上述技术问题,本发明提供一种用于上层输送线并排布局的龙门式支腿,所述上层输送线包括移载输送机构以及与移载输送机构的两端分别衔接的两个上层输送机构,所述龙门式支腿包括:In order to solve the above technical problems, the present invention provides a gantry-type outrigger for the side-by-side layout of the upper conveying line, the upper conveying line includes a transfer conveying mechanism and two upper conveying mechanisms respectively connected to the two ends of the transferring conveying mechanism. mechanism, the gantry outriggers include:
承载横架,承载横架水平布置并且包括垂直相连的两个纵梁和多个横梁,纵梁的长度方向平行于上层输送机构的输送方向,横梁的长度方向垂直于上层输送机构的输送方向,至少两个横梁上设有多个抱箍式安装组件,抱箍式安装组件用于同时连接移载输送机构和上层输送机构;The load-bearing horizontal frame is arranged horizontally and includes two longitudinal beams and multiple cross beams connected vertically. The length direction of the longitudinal beams is parallel to the conveying direction of the upper conveying mechanism, and the length direction of the crossbeams is perpendicular to the conveying direction of the upper conveying mechanism. At least two beams are provided with multiple hoop-type installation components, and the hoop-type installation components are used to simultaneously connect the transfer conveying mechanism and the upper conveying mechanism;
两个支撑立架,两个支撑立架对称设置于承载横架横跨方向上的相对两侧;Two support stands, the two support stands are symmetrically arranged on opposite sides in the transverse direction of the bearing cross frame;
两个斜撑架,两个斜撑架与两个支撑立架对应连接。Two diagonal bracing frames are correspondingly connected with the two supporting stands.
优选地,所述抱箍式安装组件包括主半抱箍和副半抱箍,主半抱箍通过两个连接组件与副半抱箍可拆卸连接,其中一个连接组件用于连接移载输送机构,另一个连接组件用于连接上层输送机构。Preferably, the hoop-type mounting assembly includes a main half hoop and an auxiliary half hoop, the main half hoop is detachably connected to the auxiliary half hoop through two connecting assemblies, one of which is used to connect the transfer conveying mechanism , and another connecting component is used to connect the upper conveying mechanism.
优选地,所述主半抱箍呈U型弯折状,主半抱箍包括与横梁横截面相适配的U型槽部,U型槽部开口处两端对称设有折耳部,所述副半抱箍呈板条状,副半抱箍的两端与两个折耳部分别通过连接组件对应可拆卸连接。Preferably, the main half hoop is in a U-shaped bent shape, and the main half hoop includes a U-shaped groove matching the cross-section of the beam, and folded ears are symmetrically arranged at both ends of the opening of the U-shaped groove, so that The auxiliary half hoop is in the form of slats, and the two ends of the auxiliary half hoop are respectively detachably connected to the two folded ears through connecting components.
优选地,所述支撑立架包括两个支撑立柱以及设于两个支撑立柱之间的增强杆,所述支撑立柱和纵梁之间设有斜撑杆。Preferably, the support stand includes two support columns and a reinforcement bar arranged between the two support columns, and a diagonal brace is provided between the support column and the longitudinal beam.
优选地,所述支撑立柱的底部设有高度调节脚。Preferably, the bottom of the support column is provided with height-adjusting feet.
优选地,所述高度调节脚包括地脚板、设于支撑立柱底部的顶板、固设于地脚板且穿设于顶板的螺纹柱以及均套设于螺纹柱的第一螺母和第二螺母,第一螺母和第二螺母分别抵接所述顶板的上下两面。Preferably, the height adjustment feet include a base plate, a top plate provided at the bottom of the support column, a threaded column fixed on the base plate and pierced through the top plate, and a first nut and a second nut both sleeved on the threaded column. A nut and a second nut abut against the upper and lower surfaces of the top plate respectively.
优选地,所述斜撑架包括斜撑柱、设有斜撑柱上端的安装板以及设有斜撑柱下端的斜撑底板,安装板上设有竖向延伸的高度调节孔,穿设于高度调节孔的斜撑紧固件与支撑立架连接。Preferably, the diagonal brace includes a diagonal brace, a mounting plate provided with an upper end of the diagonal brace, and a diagonal brace bottom plate provided with a lower end of the diagonal brace. The diagonal brace fasteners of the height adjustment holes are connected with the support stand.
本发明还提供一种双层输送系统,包括The present invention also provides a double-layer conveying system, comprising
所述用于上层输送线并排布局的龙门式支腿;The gantry outriggers for the side-by-side layout of the upper conveyor line;
多条上层输送线,所有上层输送线沿平行于横梁长度方向的方向依次分布;A plurality of upper-layer conveying lines, all upper-layer conveying lines are distributed sequentially along the direction parallel to the length direction of the beam;
多条下层输送线,所有下层输送线位于承载横架的下方,所有下层输送线沿平行于横梁长度方向的方向依次分布。A plurality of lower-layer conveying lines, all lower-layer conveying lines are located under the bearing cross frame, and all lower-layer conveying lines are distributed sequentially along the direction parallel to the length direction of the beam.
优选地,所述横梁的数量为三个,其中两个横梁均设有抱箍式安装组件,剩余的一个横梁托持上层输送机构,设有抱箍式安装组件的两个横梁的间距与移载输送机构的尺寸相适配。Preferably, the number of the beams is three, two of which are equipped with hoop-type mounting components, and the remaining beam supports the upper conveying mechanism. The size of the load delivery mechanism is suitable.
优选地,所述双层输送系统还包括过渡输送辊,过渡输送辊位于相邻的两条上层输送线的移载输送机构的间隙处。Preferably, the double-layer conveying system further includes transition conveying rollers, and the transition conveying rollers are located in the gap between the transfer conveying mechanisms of two adjacent upper conveying lines.
如上所述,本发明的用于上层输送线并排布局的龙门式支腿及双层输送系统,具有以下有益效果:在本发明中,承载横架水平布置并且包括垂直相连的两个纵梁和多个横梁,至少两个横梁上设有多个抱箍式安装组件,抱箍式安装组件用于同时连接移载输送机构和上层输送机构。承载横架能够同时承载并排布置的多条上层输送线。两个支撑立架对称设置于承载横架横跨方向上的相对两侧,两个斜撑架与两个支撑立架对应连接,如此设置,能够极大提高龙门式支腿的整体刚强度。因此,本发明的用于上层输送线并排布局的龙门式支腿能够依次并排布置多条上层输送线,并且整体刚强度较大。As mentioned above, the gantry-type outriggers and double-deck conveying system used for the side-by-side layout of the upper conveying line of the present invention have the following beneficial effects: In the present invention, the load-carrying horizontal frame is arranged horizontally and includes two A plurality of crossbeams, at least two crossbeams are provided with a plurality of hoop-type installation components, and the hoop-type installation components are used to simultaneously connect the transfer conveying mechanism and the upper conveying mechanism. The carrying horizontal frame can simultaneously carry multiple upper conveying lines arranged side by side. The two support stands are arranged symmetrically on the opposite sides in the transverse direction of the load-carrying cross frame, and the two diagonal braces are correspondingly connected with the two support stands. Such arrangement can greatly improve the overall rigidity of the gantry-type outriggers. Therefore, the gantry-type outriggers for the side-by-side layout of the upper-layer conveying lines of the present invention can arrange multiple upper-layer conveying lines side by side in sequence, and the overall rigidity is relatively high.
本发明的双层输送系统能够同时依次并排布置多条上层输送线和多条下层输送线,使双层输送系统的集成度更高。The double-layer conveying system of the present invention can arrange a plurality of upper-layer conveying lines and a plurality of lower-layer conveying lines side by side at the same time, so that the integration degree of the double-layer conveying system is higher.
附图说明Description of drawings
图1显示为本发明的用于上层输送线并排布局的龙门式支腿的示意图;Fig. 1 is shown as the schematic diagram of the gantry type support leg that is used for upper conveying line layout side by side of the present invention;
图2显示为图1中A部分的放大图;Figure 2 shows an enlarged view of part A in Figure 1;
图3显示为图1中B部分的放大图;Figure 3 shows an enlarged view of part B in Figure 1;
图4显示为图1中C部分的放大图;Figure 4 shows an enlarged view of part C in Figure 1;
图5显示为龙门式支腿和上层输送线的连接示意图;Figure 5 shows a schematic diagram of the connection between the gantry type legs and the upper conveyor line;
图6显示为本发明的双层输送系统的示意图。Fig. 6 is a schematic diagram of the double-layer conveying system of the present invention.
元件标号说明Component designation description
1 承载横架1 carrying frame
11 纵梁11 stringer
12 横梁12 beams
13 抱箍式安装组件13 Hoop mount assembly
131 主半抱箍131 main half hoop
131a U型槽部131a U-shaped groove
131b 折耳部131b Folded ears
132 副半抱箍132 pairs of half hoops
133 连接组件133 connection components
2 支撑立架2 support stand
21 支撑立柱21 support column
22 增强杆22 reinforcement bar
23 斜撑杆23 Diagonal brace
24 高度调节脚24 height adjustment feet
241 地脚板241 Floor plate
242 顶板242 top plate
243 螺纹柱243 threaded post
244 第一螺母244 first nut
245 第二螺母245 second nut
3 斜撑架3 Diagonal braces
31 斜撑柱31 Diagonal brace
32 安装板32 mounting plate
321 高度调节孔321 height adjustment hole
322 斜撑紧固件322 Diagonal Brace Fasteners
33 斜撑底板33 Diagonal bottom plate
4 上层输送线4 upper conveying line
41 上层输送机构41 Upper conveying mechanism
5 下层输送线5 lower conveying line
6 过渡输送辊6 Transition conveyor roller
具体实施方式Detailed ways
以下由特定的具体实施例说明本发明的实施方式,熟悉此技术的人士可由本说明书所揭露的内容轻易地了解本发明的其他优点及功效。The implementation of the present invention will be illustrated by specific specific examples below, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification.
须知,本说明书所附图中所绘示的结构、比例、大小等,均仅用以配合说明书所揭示的内容,以供熟悉此技术的人士了解与阅读,并非用以限定本发明可实施的限定条件,故不具技术上的实质意义,任何结构的修饰、比例关系的改变或大小的调整,在不影响本发明所能产生的功效及所能达成的目的下,均应仍落在本发明所揭示的技术内容所能涵盖的范围内。同时,本说明书中所引用的如“上”、“下”、“左”、“右”、“中间”及“一”等的用语,亦仅为便于叙述的明了,而非用以限定本发明可实施的范围,其相对关系的改变或调整,在无实质变更技术内容下,当亦视为本发明可实施的范畴。It should be noted that the structures, proportions, sizes, etc. shown in the drawings attached to this specification are only used to match the content disclosed in the specification, for those who are familiar with this technology to understand and read, and are not used to limit the implementation of the present invention. Limiting conditions, so there is no technical substantive meaning, any modification of structure, change of proportional relationship or adjustment of size, without affecting the effect and purpose of the present invention, should still fall within the scope of the present invention. within the scope covered by the disclosed technical content. At the same time, terms such as "upper", "lower", "left", "right", "middle" and "one" quoted in this specification are only for the convenience of description and are not used to limit this specification. The practicable scope of the invention and the change or adjustment of its relative relationship shall also be regarded as the practicable scope of the present invention without any substantial change in the technical content.
如图1和图4所示,本发明提供一种用于上层输送线并排布局的龙门式支腿,上述上层输送线4包括移载输送机构(未予图示)以及与移载输送机构的两端分别衔接的两个上层输送机构41,上述龙门式支腿包括:As shown in Fig. 1 and Fig. 4, the present invention provides a kind of gantry type support leg that is used for the side-by-side arrangement of the upper layer conveying line, and above-mentioned upper
承载横架1,承载横架1水平布置并且包括垂直相连的两个纵梁11和多个横梁12,纵梁11的长度方向平行于上层输送机构41的输送方向,横梁12的长度方向垂直于上层输送机构41的输送方向,至少两个横梁12上设有多个抱箍式安装组件13,抱箍式安装组件13用于同时连接移载输送机构和上层输送机构41;The carrying
两个支撑立架2,两个支撑立架2对称设置于承载横架1横跨方向上的相对两侧;Two support stands 2, the two support stands 2 are symmetrically arranged on the opposite sides in the transverse direction of the load-carrying
两个斜撑架3,两个斜撑架3与两个支撑立架2对应连接。Two diagonal bracing
在本发明中,承载横架1水平布置并且包括垂直相连的两个纵梁11和多个横梁12,至少两个横梁12上设有多个抱箍式安装组件13,抱箍式安装组件13用于同时连接移载输送机构和上层输送机构41。例如,两个横梁12上均设有多个抱箍式安装组件13,其中一个横梁12用于承载上述移载输送机构和其中一个上层输送机构41,另一个横梁12用于承载上述移载输送机构和其中另一个上层输送机构41,也就是说,上述移载输送机构位于两个上层输送机构41之间的空档处,移载输送机构起到输送物料、移出物料或移入物料的功能。承载横架1能够同时承载并排布置的多条上层输送线4。两个支撑立架2对称设置于承载横架1横跨方向上的相对两侧,两个斜撑架3与两个支撑立架2对应连接,如此设置,能够极大提高龙门式支腿的整体刚强度。In the present invention, the load-carrying
因此,本发明的用于上层输送线并排布局的龙门式支腿能够依次并排布置多条上层输送线4,并且整体刚强度较大。Therefore, the gantry-type outriggers for the side-by-side layout of the upper-layer conveying lines of the present invention can arrange a plurality of upper-
如图2所示,为了便于将上述上层输送线4可拆卸地安装于横梁12并且便于调节上层输送线4沿横梁12长度方向上的位置,上述抱箍式安装组件13包括主半抱箍131和副半抱箍132,主半抱箍131通过两个连接组件133(例如螺栓组件)与副半抱箍132可拆卸连接,其中一个连接组件133用于连接移载输送机构,另一个连接组件133用于连接上层输送机构41。As shown in FIG. 2 , in order to facilitate the detachable installation of the above-mentioned upper conveying
进一步的,为了进一步增大上述抱箍式安装组件13对上层输送线4的支撑面积,上述主半抱箍131呈U型弯折状,主半抱箍131包括与横梁12横截面相适配的U型槽部131a,U型槽部131a开口处两端对称设有折耳部131b,上述副半抱箍132呈板条状,副半抱箍132的两端与两个折耳部131b分别通过连接组件133对应可拆卸连接。Further, in order to further increase the support area of the above-mentioned hoop-
为了进一步提高上述支撑立架2的载重能力,上述支撑立架2包括两个支撑立柱21以及设于两个支撑立柱21之间的增强杆22,上述支撑立柱21和纵梁11之间设有斜撑杆23。In order to further improve the load-bearing capacity of the above-mentioned
如图3所示,当场地不平时,上述支撑立柱21的底部设有高度调节脚24,这样能够通过调节高度调节脚24,使承载横架1始终处于水平状态。As shown in FIG. 3 , when the site is uneven, the bottom of the above-mentioned
进一步的,为了简化上述高度调节脚24的结构,上述高度调节脚24包括地脚板241、设于支撑立柱21底部的顶板242、固设于地脚板241且穿设于顶板242的螺纹柱243以及均套设于螺纹柱243的第一螺母244和第二螺母245,第一螺母244和第二螺母245分别抵接上述顶板242的上下两面。Further, in order to simplify the structure of the above-mentioned
如图1和图4所示,当场地不平时,上述斜撑架3包括斜撑柱31、设有斜撑柱31上端的安装板32以及设有斜撑柱31下端的斜撑底板33,安装板32上设有竖向延伸的高度调节孔321,穿设于高度调节孔321的斜撑紧固件322与支撑立架2连接。As shown in Figures 1 and 4, when the site is uneven, the above-mentioned
如图6所示,本发明还提供一种双层输送系统,包括As shown in Figure 6, the present invention also provides a double-layer conveying system, comprising
上述用于上层输送线并排布局的龙门式支腿;The above-mentioned gantry-type outriggers for the side-by-side layout of the upper conveyor line;
多条上层输送线4,所有上层输送线4沿平行于横梁12长度方向的方向依次分布;A plurality of upper-
多条下层输送线5,所有下层输送线5位于承载横架1的下方,所有下层输送线5沿平行于横梁12长度方向的方向依次分布。A plurality of lower-
本发明的双层输送系统能够同时依次并排布置多条上层输送线4和多条下层输送线5,使双层输送系统的集成度更高。The double-layer conveying system of the present invention can arrange a plurality of upper-
为了使其中两个横梁12支撑上述移载输送机构,上述横梁12的数量为三个,其中两个横梁12均设有抱箍式安装组件13,剩余的一个横梁12托持上层输送机构41,设有抱箍式安装组件13的两个横梁12的间距与移载输送机构的尺寸相适配。In order to make two of the
由于相邻的两条上层输送线4存在间隙,为了使相邻的两条上层输送线4的移载输送机构平顺输送物料,上述双层输送系统还包括过渡输送辊6,过渡输送辊6位于相邻的两条上层输送线4的移载输送机构的间隙处。Since there is a gap between the two adjacent upper conveying
综上所述,本发明能够依次并排布置多条上层输送线,并且整体刚强度较大,从而使双层输送系统的集成度更高。所以,本发明有效克服了现有技术中的种种缺点而具高度产业利用价值。To sum up, the present invention can arrange a plurality of upper-layer conveying lines side by side in sequence, and the overall rigidity is relatively high, so that the integration degree of the double-layer conveying system is higher. Therefore, the present invention effectively overcomes various shortcomings in the prior art and has high industrial application value.
上述实施例仅例示性说明本发明的原理及其功效,而非用于限制本发明。任何熟悉此技术的人士皆可在不违背本发明的精神及范畴下,对上述实施例进行修饰或改变。因此,举凡所属技术领域中具有通常知识者在未脱离本发明所揭示的精神与技术思想下所完成的一切等效修饰或改变,仍应由本发明的权利要求所涵盖。The above-mentioned embodiments only illustrate the principles and effects of the present invention, but are not intended to limit the present invention. Anyone skilled in the art can modify or change the above-mentioned embodiments without departing from the spirit and scope of the present invention. Therefore, all equivalent modifications or changes made by those skilled in the art without departing from the spirit and technical ideas disclosed in the present invention should still be covered by the claims of the present invention.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202111231766.7A CN113998411B (en) | 2021-10-22 | 2021-10-22 | Gantry-type outriggers and double-layer conveyor system for side-by-side layout of the upper conveyor line |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202111231766.7A CN113998411B (en) | 2021-10-22 | 2021-10-22 | Gantry-type outriggers and double-layer conveyor system for side-by-side layout of the upper conveyor line |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN113998411A CN113998411A (en) | 2022-02-01 |
| CN113998411B true CN113998411B (en) | 2023-04-14 |
Family
ID=79923669
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202111231766.7A Active CN113998411B (en) | 2021-10-22 | 2021-10-22 | Gantry-type outriggers and double-layer conveyor system for side-by-side layout of the upper conveyor line |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN113998411B (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115743999A (en) * | 2022-11-03 | 2023-03-07 | 珠海格力智能装备有限公司 | Control method and system for material conveying frame and electronic equipment |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US8998160B1 (en) * | 2012-10-01 | 2015-04-07 | Jolt LLC | Conveyor support frame method and apparatus |
| CN204979990U (en) * | 2015-09-28 | 2016-01-20 | 郑州上河电器有限公司 | Tilting electric wire dish rack |
| CN206050805U (en) * | 2016-08-21 | 2017-03-29 | 合肥联鑫智能科技有限公司 | Pipeline single-link line body device |
| CN110789902A (en) * | 2019-11-26 | 2020-02-14 | 懿力创新(厦门)科技有限公司 | Logistics storage center and intelligent transfer station thereof |
| CN112537594A (en) * | 2020-11-30 | 2021-03-23 | 珠海格力智能装备有限公司 | Conveying equipment |
| CN214086127U (en) * | 2020-12-21 | 2021-08-31 | 苏州鸿安机械股份有限公司 | Three-dimensional storage butt-joint system |
| CN113401613A (en) * | 2021-06-29 | 2021-09-17 | 苏州金峰物流设备有限公司 | Vertical sorting system, sorting method thereof and vertical sorting machine |
-
2021
- 2021-10-22 CN CN202111231766.7A patent/CN113998411B/en active Active
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US8998160B1 (en) * | 2012-10-01 | 2015-04-07 | Jolt LLC | Conveyor support frame method and apparatus |
| CN204979990U (en) * | 2015-09-28 | 2016-01-20 | 郑州上河电器有限公司 | Tilting electric wire dish rack |
| CN206050805U (en) * | 2016-08-21 | 2017-03-29 | 合肥联鑫智能科技有限公司 | Pipeline single-link line body device |
| CN110789902A (en) * | 2019-11-26 | 2020-02-14 | 懿力创新(厦门)科技有限公司 | Logistics storage center and intelligent transfer station thereof |
| CN112537594A (en) * | 2020-11-30 | 2021-03-23 | 珠海格力智能装备有限公司 | Conveying equipment |
| CN214086127U (en) * | 2020-12-21 | 2021-08-31 | 苏州鸿安机械股份有限公司 | Three-dimensional storage butt-joint system |
| CN113401613A (en) * | 2021-06-29 | 2021-09-17 | 苏州金峰物流设备有限公司 | Vertical sorting system, sorting method thereof and vertical sorting machine |
Also Published As
| Publication number | Publication date |
|---|---|
| CN113998411A (en) | 2022-02-01 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN206279743U (en) | A kind of tool-type temporary steel support device | |
| CN101942901A (en) | Support frame or scaffold and construction method thereof | |
| CN113998411B (en) | Gantry-type outriggers and double-layer conveyor system for side-by-side layout of the upper conveyor line | |
| CN201771172U (en) | Support rack or scaffold | |
| CN207246180U (en) | A kind of crossbeam and the shelf using the crossbeam | |
| CN210001381U (en) | Arch structure car bottom of elevator | |
| CN101139813A (en) | A kind of steel truss of under-supported bridge | |
| CN202788873U (en) | Combined gantry tunnel lining trolley | |
| CN216234533U (en) | Overhead leg structure and conveying system of conveying mechanism | |
| CN209872068U (en) | A frame-type light composite car floor | |
| CN213011602U (en) | Gantry tool for equipment installation and transportation | |
| CN210365423U (en) | Trestle support with light steel structure | |
| CN109809278B (en) | Frame type lightweight composite car bottom | |
| CN211196946U (en) | Portable plate stacking support | |
| CN223236292U (en) | Prefabricated assembled telescopic steel bar semi-finished product storage rack | |
| CN113401498A (en) | Three-dimensional storage and transfer frame for separated plate components | |
| CN207312205U (en) | A kind of longeron apparatus for placing | |
| CN223937013U (en) | Bridge deck pavement construction platform | |
| CN220906251U (en) | A belt conveyor quick assembly structure | |
| CN220300083U (en) | Elevator well and stand column structure thereof | |
| CN206337801U (en) | Large span is without modulus attachment type raise scaffold | |
| CN213234421U (en) | Stand and station room | |
| CN222745592U (en) | Operation frame | |
| CN222524049U (en) | Tower crane standard knot | |
| CN220866263U (en) | Bracket type goods shelf |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |