CN113898051A - Sponge urban road grading drainage system in collapsible loess stratum - Google Patents

Sponge urban road grading drainage system in collapsible loess stratum Download PDF

Info

Publication number
CN113898051A
CN113898051A CN202111227247.3A CN202111227247A CN113898051A CN 113898051 A CN113898051 A CN 113898051A CN 202111227247 A CN202111227247 A CN 202111227247A CN 113898051 A CN113898051 A CN 113898051A
Authority
CN
China
Prior art keywords
road
pipe
water
layer
drainage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111227247.3A
Other languages
Chinese (zh)
Inventor
佘芳涛
吴征奇
周庆怡
周伟踪
张彬
付炜烨
张赛赛
刘乐乐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xi'an University of Technology
Original Assignee
Xi'an University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xi'an University of Technology filed Critical Xi'an University of Technology
Priority to CN202111227247.3A priority Critical patent/CN113898051A/en
Publication of CN113898051A publication Critical patent/CN113898051A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • E—FIXED CONSTRUCTIONS
    • E03—WATER SUPPLY; SEWERAGE
    • E03F—SEWERS; CESSPOOLS
    • E03F1/00—Methods, systems, or installations for draining-off sewage or storm water
    • E03F1/002—Methods, systems, or installations for draining-off sewage or storm water with disposal into the ground, e.g. via dry wells
    • E—FIXED CONSTRUCTIONS
    • E03—WATER SUPPLY; SEWERAGE
    • E03F—SEWERS; CESSPOOLS
    • E03F3/00—Sewer pipe-line systems
    • E03F3/02—Arrangement of sewer pipe-lines or pipe-line systems
    • E—FIXED CONSTRUCTIONS
    • E03—WATER SUPPLY; SEWERAGE
    • E03F—SEWERS; CESSPOOLS
    • E03F3/00—Sewer pipe-line systems
    • E03F3/04—Pipes or fittings specially adapted to sewers
    • E—FIXED CONSTRUCTIONS
    • E03—WATER SUPPLY; SEWERAGE
    • E03F—SEWERS; CESSPOOLS
    • E03F5/00—Sewerage structures
    • E03F5/10—Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
    • Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/30—Flood prevention; Flood or storm water management, e.g. using flood barriers
    • Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00—Water conservation; Efficient water supply; Efficient water use
    • Y02A20/40—Protecting water resources

Landscapes

  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Sewage (AREA)

Abstract

本发明公开了一种湿陷性黄土地层中海绵城市道路分级排水系统,包括路缘调蓄箱,路缘调蓄箱设于路面与绿化带交界处,路缘调蓄箱靠近绿化带的侧面开口与一级排水管相连,隔水墙设于路缘调蓄箱下部,两隔水墙中间由上至下依次设有植被种植层、碎石层、灰土垫层和防渗膜,渗流箱位于灰土垫层内,渗流箱靠近道路方向的侧面自下而上设有两开口分别与二级排水管、三级排水管相连,且二级排水管、三级排水管皆穿过隔水墙至道路侧边缘,二级排水管接入雨水井或市政管网,三级排水管通过直角弯头接入位于隔水墙外侧、埋设于道路下方的导水砂井,透水管沿道路纵向设于靠近碎石层中间下部。能够有效排除路面积水,适用范围广,可避免道路发生破坏。

Figure 202111227247

The invention discloses a grading drainage system for a sponge city road in a collapsible loess stratum, comprising a curb adjustment and storage box, the curb adjustment and storage box is arranged at the junction of the road surface and the green belt, and the curb adjustment and storage box is close to the side of the green belt The opening is connected to the first-level drainage pipe, and the water barrier is set at the lower part of the curb adjustment and storage tank. The vegetation planting layer, the gravel layer, the lime-soil cushion and the anti-seepage membrane are arranged in the middle of the two water barriers from top to bottom, and the seepage box is arranged. Located in the lime-soil cushion, the side of the seepage box close to the road is provided with two openings from bottom to top, which are respectively connected to the secondary drainage pipe and the tertiary drainage pipe, and both the secondary drainage pipe and the tertiary drainage pipe pass through the water barrier. To the side edge of the road, the secondary drainage pipe is connected to the rainwater well or the municipal pipe network, and the tertiary drainage pipe is connected to the water-conducting sand well located on the outside of the water barrier and buried under the road through a right-angle elbow. The permeable pipe is arranged longitudinally along the road. in the lower part of the middle near the gravel layer. It can effectively remove road surface water, has a wide range of applications, and can avoid road damage.

Figure 202111227247

Description

Sponge urban road grading drainage system in collapsible loess stratum
Technical Field
The invention relates to the technical field of sponge city construction, in particular to a graded drainage system for a sponge city road in a collapsible loess stratum.
Background
Along with the high-speed development of economy, the contradiction of serious shortage of water resources, serious water ecological pollution problem, uneven water resource space-time distribution and the like in China is increasingly prominent, and huge hidden dangers are brought to city management and people safety. The problems of waterlogging, heat island effect, water pollution, overwhelming drainage pipe network and the like of the city caused by 'waterlogging when raining and drought after raining', and a set of system is urgently needed to solve the influence caused by disasters, so that the sponge city can develop the rainwater system with low influence and can be transported. The sponge city, as the name suggests just builds the city into a "cavernosum", full play its absorb water, infiltration, stagnant water, retaining, water purification drainage and water use function, play the effect such as flood storage drainage, water resources are kept in good care, rain sewage purifies and replenish groundwater, solve the problem from the source, can improve water resource utilization and effectively alleviate city flood calamity.
The proportion of roads in urban construction is large, particularly motor vehicle lanes, the requirement on the strength of the roads is high, the strength is difficult to meet when pervious concrete is adopted, so that the roads are mostly hardened pavements, and road water accumulation is easily caused during rainstorm. The non-permeable pavement greatly increases the drainage pressure and surface runoff of a city, and the road is seriously polluted by traffic, so that a sponge city needs to be reasonably utilized, a road drainage system is scientifically designed, and the harmonious development of nature and the city is promoted.
The collapsible loess foundation is soaked in water under certain pressure, and has fast destruction, low strength, great settlement, inclination and cracking of the roadbed and high use performance. In the construction of sponge urban roads in collapsible loess strata, the harm caused by collapsible nature needs to be fully considered, and at present, no effective scheme for the construction of sponge urban road drainage systems exists in the collapsible loess strata.
Chinese patent application CN 213296166U discloses a sponge urban road green median, which comprises a gravel layer, a fine sand layer, an artificial packing layer, a soil planting layer, a gravel layer and a water-absorbing piece, wherein the rainwater purified and stored in the gravel layer is transported by the water-absorbing piece for plants, thereby improving the utilization rate of the rainwater and reducing the road ponding. The following problems still remain: 1) the water drawing device has a simple structure, the service life of the water drawing piece is not long, once the water drawing piece is damaged, the arrangement of the whole green belt can not play a role so as to realize the recycling of water resources, the water drawing device is divided into three layers, green belt vegetation is irrigated, rainwater is discharged into a municipal pipe network and deep water guide, the three layers are mutually independent, and the system stability is better; 2) the gravel layer is laid under the root system of the vegetation, which is not beneficial to the growth of the root system of the vegetation, especially for plants with deeper root systems such as trees, and the invention is provided with a vegetation planting layer, the gravel layers are laid under the vegetation planting layer, and the gravel layers with different thicknesses are alternately arranged along the longitudinal direction of the road, so that the plants with different root system depths can be planted respectively; 3) the invention only has the functions of absorbing, permeating, stagnating, storing, purifying, draining and using water, and cannot meet the drainage requirement of the sponge urban road in the collapsible loess stratum, and the invention is additionally provided with the functions of water isolation and water guide.
Chinese patent application CN 108999056 a discloses sponge urban road rainwater integration circulation processing system, including rainwater collection unit, rainwater processing unit and rainwater utilization unit, the rainwater is abandoned class through the initial stage earlier, utilizes membrane biological reaction pond to purify afterwards, passes through sensor control sprinkler at last, realizes the utilization of rainwater. However, two problems still exist: 1) the system is too complex in structure, the difficulty of the rainwater circulating collection and treatment device in underground facility arrangement is large, the road is paved in a permeable way, the subgrade is damaged by the wet collapse, and the system is not suitable for the loess area, the road of the system has a certain gradient to flow to a green belt to collect rainwater on the basis of hardening the road surface, the system is arranged near the green belt to remove the accumulated water on the road surface, and the wet collapse of the loess is fully considered; 2) only collect, handle and discharge into municipal pipe network through the rainwater and be not enough to deal with bad weather, municipal pipe network pressure is great when rainstorm, can't fully get rid of surface ponding.
Disclosure of Invention
Technical problem to be solved
Aiming at the defects of the prior art, the invention provides a grading drainage system for sponge urban roads in a collapsible loess stratum.
(II) technical scheme
In order to achieve the purpose, the invention provides the following technical scheme: a graded drainage system for sponge urban roads in collapsible loess strata comprises a curb storage box, a water-stop wall and a seepage box, wherein the curb storage box is arranged at the junction of a road surface and a green belt, a side opening of the curb storage box close to the green belt is connected with a first-level drainage pipe, the water-stop wall is arranged at the lower part of the curb storage box, a vegetation planting layer, a gravel layer, an ash soil cushion layer and an anti-seepage film are sequentially arranged between the two water-stop walls from top to bottom, the seepage box is positioned in the ash soil cushion layer, two openings are arranged at the side of the seepage box close to the road direction from bottom to top and are respectively connected with a second-level drainage pipe and a third-level drainage pipe, the second-level drainage pipe and the third-level drainage pipe all penetrate through the water-stop wall to the road side edge, the second-level drainage pipe is connected with a rainwater well or a municipal pipe network, the third-level drainage pipe is connected with a water guiding sand well which is positioned outside the water-stop wall and is buried under the road through a right-angle elbow, the water permeable pipe is longitudinally arranged near the middle lower part of the gravel layer along the road.
Preferably, the curb storage box is a cuboid and is arranged along the longitudinal whole course of the road, the height of the curb storage box is 30cm, the height of the portion above the ground is 20cm, the portion below the ground is 10cm, the portion, below an opening, of the side surface of the curb storage box close to the road direction, which exceeds the road surface portion and is close to the green belt direction is poured by pervious concrete, and the rest portions are poured by common concrete; curb regulation case is close to the side of road direction and is equipped with the trompil along the longitudinal interval of road, and the trompil is located 15cm above the road surface, and inside is equipped with double-deck filter screen.
Preferably, the length of the water-stop wall is equal to that of the curb storage box, the water-stop wall is arranged along the longitudinal whole course of the road, and the height of the water-stop wall is from the bottom of the curb storage box to the bottom of the lime soil cushion layer.
Preferably, the height of one-level drain pipe and curb regulation and storage case side opening junction is the same with the road surface height, and the one-level drain pipe passes vegetation planting layer to rubble layer top.
Preferably, the rubble layer sets up first rubble layer and second rubble layer along the vertical alternation of road, and the lime soil bed course top is located to the equipartition, and wherein, second rubble layer thickness is 1/3 of first rubble layer thickness, all is the vegetation planting layer more than the second rubble layer.
Preferably, the contact surfaces of the gravel layer, the vegetation planting layer and the lime soil cushion layer are all provided with permeable geotextile.
Preferably, the seepage flow box is the cuboid, arranges along the vertical interval of road, adopts the fine aggregate concrete material, and rainwater in the seepage flow box is earlier through second grade drain pipe row rainwater well or municipal pipe network, and when the incasement water level rose to a take the altitude, the rainwater flowed in vertical water guide sand pit through tertiary drain pipe.
Preferably, the water guide sand well is excavated to a position below a soil layer boundary layer, a PVC anti-seepage cylinder is sunk along the well wall, and sand is filled in the anti-seepage cylinder.
Preferably, the pipe top of permeating water and the pipe half interval on week evenly are equipped with the trompil in aperture, and the pipe of permeating water locates gravel layer bottom intermediate position, is located the intraformational pipe portion of permeating water of first rubble, and the aperture trompil is established to the bottom, is located the intraformational pipe portion of permeating water of second rubble, and the trompil is not established to the bottom.
Preferably, the open pore of the bottom of the permeable pipe is connected with one end of a drainage connecting pipe, the other end of the drainage connecting pipe is connected into the top opening of the seepage box and is positioned in the permeable pipe part of the second gravel layer, and the bottom of the permeable pipe is not provided with a drainage connecting pipe, the seepage box and other subsequent drainage structures.
(III) advantageous effects
The invention provides a grading drainage system for sponge urban roads in a collapsible loess stratum. The method has the following beneficial effects: the invention provides a sponge urban road graded drainage system suitable for a collapsible loess stratum, which is used for removing road accumulated water in three mutually independent stages, is suitable for light rain, medium rain, heavy rain and even heavy rain, and is additionally provided with a lime soil cushion layer, an impermeable film and a water-proof wall for water insulation and a vertical water-guiding sand well for water guiding on the basis of water absorption, permeation, stagnation, storage, purification, drainage and use in a sponge city, so that water can be effectively prevented from permeating into the collapsible stratum, and the loess roadbed is prevented from being collapsed and damaged. The system can realize graded drainage: firstly, the rainwater storage tank can absorb initial rainwater to irrigate plants on the vegetation planting layer, the plants can play roles of purified water and stagnant water, and when the water amount is too large, on one hand, rainwater can permeate into the gravel layer through the vegetation planting layer, and on the other hand, rainwater can directly flow into the gravel layer through the primary water drainage pipe; secondly, the rainwater filtered by the crushed stone layer can be discharged into a rainwater well or a municipal pipe network; thirdly, when the rainfall is too big, in order to prevent that the ground from taking place the collapsible destruction and municipal pipe network pressure is too big, the accessible water guide sand well is with the leading-in non-collapsible stratum of rainwater. The invention is stable and reliable, can effectively discharge accumulated water on the road surface, has wide application range and can avoid the damage of the road.
Drawings
FIG. 1 is a schematic overall structure of the present invention;
FIG. 2 is a cross-sectional view of a subterranean formation according to the present invention;
FIG. 3 is a longitudinal cross-sectional view of the present invention;
FIG. 4 is a schematic view of the connection between the permeable pipe and the infiltration tank of the present invention.
In the figure, 1, a curb storage box, 2, holes, 3, a filter screen, 4, a water-stop wall, 5, a vegetation planting layer, 6, a first gravel layer, 6a, a second gravel layer, 7, permeable geotextile, 8, a lime soil cushion layer, 9, an impermeable membrane, 10, a first-stage drain pipe, 10a, a drainage connecting pipe, 10b, a second-stage drain pipe, 10c, a third-stage drain pipe, 11, a permeable pipe, 12, a seepage box, 13, a right-angle elbow, 14, a water-guiding sand well, 15, an impermeable cylinder, 16, a soil layer boundary layer and 17, a rainwater well or a municipal pipe network.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
As shown in fig. 1 to 4, the present invention provides a technical solution: a graded drainage system for sponge urban roads in collapsible loess strata, which comprises a curb storage tank 1, the curb storage box 1 is arranged at the junction of the road surface and the green belt, an opening at one side of the curb storage box 1 close to the green belt is connected with a primary drain pipe 10, the water-stop walls 4 are arranged at the lower part of the curb storage box 1, a vegetation planting layer 5, a gravel layer, a lime soil cushion layer 8 and an impermeable membrane 9 are sequentially arranged between the two water-stop walls 4 from top to bottom, the seepage box 12 is positioned in the lime soil cushion layer 8, the side surface of the seepage box 12 close to the road direction is provided with two openings from bottom to top which are respectively connected with a secondary drainage pipe 10b and a tertiary drainage pipe 10c, and both pipes pass through the water-stop wall 4 to the side edge of one side of the road, the secondary drainage pipe 10b is connected to a catch basin or municipal pipe network 17, the third-stage drainage pipe 10c is connected to a water guide sand well 14 which is positioned outside the water separation wall 4 and buried below a road through a right-angle elbow 13;
the water permeable pipes 11 are longitudinally arranged near the lower part of the middle of the gravel layer along a road so as to collect rainwater filtered by the gravel layer, the top parts and the upper half parts of the peripheries of the water permeable pipes 11 are uniformly provided with the open holes 2 at intervals, the water permeable pipes 11 are arranged in the middle of the bottom of the gravel layer, the water permeable pipes 11 positioned in the first gravel layer 6 are provided with the open holes 2 at the bottom, the water permeable pipes 11 positioned in the second gravel layer 6a are provided with no open holes 2 at the bottom;
one end of the drainage connecting pipe 10a is connected with the open pore 2 at the bottom of the permeable pipe 11, the other end is connected with the top opening of the seepage box 12, the drainage connecting pipe 10a and the seepage box 12 are not arranged at the bottom of the permeable pipe 11 part of the second gravel layer 6a.
Furthermore, the curb storage box 1 is a cuboid and is arranged along the longitudinal whole course of the road, the height of the curb storage box is 30cm, the height of the portion above the ground is 20cm, the height of the portion below the ground is 10cm, the portion, close to the road, of the side surface of the box body is higher than the road surface, the portion, close to the side surface of the green belt, below the opening is poured by pervious concrete, the rest portions are poured by common concrete, and the curb storage box 1 can play a role in adjusting and distributing rainwater.
Furtherly, 1 sides of curb regulation case that is close to the road direction are equipped with trompil 2 along the longitudinal interval of road, and surface ponding is more, and when the concrete part of permeating water did not reach to get rid of ponding, the rainwater flows into the box through 2 trompils that the aperture is big, and trompil 2 is located 15cm above the road surface department, and inside is equipped with double-deck filter screen 3, intercepts great debris such as branches and leaves, rubbish.
Further, the length of the water-stop wall 4 is equal to that of the curb storage box 1, the water-stop wall is arranged along the longitudinal whole course of the road, and the water-stop wall is arranged from the bottom of the curb storage box 1 to the bottom of the lime soil cushion layer 8, so that the water in the green belt can be prevented from permeating the roads on two sides to cause the damage of the wet fall.
Further, the height and the road surface height of one- level drain pipe 10 and 1 side opening junction of curb regulation case are the same, make the rainwater of regulation incasement satisfy the vegetation and plant 5 required backs in layer, can in time discharge through one-level drain pipe 10, avoid the rainwater accumulation too much to flow back to the road surface, and one-level drain pipe 10 passes vegetation and plants 5 to rubble layer tops, emits into the rubble layer with the rainwater.
Further, the rubble layer sets up first rubble layer 6 and second rubble layer 6a along the vertical turn of road, 8 tops in the lime soil bed course are located to the equipartition, and wherein, second rubble layer 6a thickness is 1/3 of first rubble layer 6 thickness, all be vegetation planting layer 5 more than the second rubble layer 6a for the different plant of root system degree of depth can be planted along the road green belt line, plant the layer 5 selective plant that the root system is lighter if lie in vegetation planting on first rubble layer 6, like ground quilt class, and lie in vegetation planting layer 5 on second rubble layer 6a, because rubble layer thickness is little, soil planting layer thickness is big, can plant the darker arbor class of root system and bush class etc..
Furthermore, all be equipped with the geotechnological cloth 7 that permeates water on the contact surface of rubble layer and vegetation planting layer 5, grey soil bed course 8, make the tiny particle such as soil and silt can not get into seepage flow box 12 through the rubble layer, play the filtering action.
Further, the diaphragm wall 4 can prevent that the rainwater from to the collapsible stratum of both sides infiltration road below, the collapsible stratum of rainwater infiltration to greenbelt below can be avoided to lime soil bed course 8 and prevention of seepage membrane 9, and the water proof effect through diaphragm wall 4, lime soil bed course 8 and prevention of seepage membrane 9 can be avoided the collapsible loess stratum to take place the collapsible destruction.
Further, seepage case 12 is the cuboid, arranges along road longitudinal separation, adopts the fine aggregate concrete material, and rainwater in the seepage case 12 passes through second grade drain pipe 10b earlier and discharges into catch basin or municipal pipe network 17, and when the rainfall is great, incasement water level rises to a take the altitude, and the rainwater flows in vertical water guide sand well 14 through tertiary drain pipe 10c, accomplishes deep water guide, seepage case 12 can adjust, alleviate municipal pipe network pressure when the rainfall is great, makes the road drainage unobstructed, can establish the sponge city better.
Furthermore, the water guide sand well 14 is excavated below a soil layer boundary layer 16, a PVC anti-seepage cylinder 15 sinks along the well wall, sand is filled in the anti-seepage cylinder 15, and the water guide sand well has good water guide performance and can guide part of rainwater into a non-collapsible stratum.
Example (b): in the rainfall, the invention is divided into three stages of drainage. Firstly, as the hardened road surface is in a certain slope, rainwater is collected to the outer side of the curb storage box 1 and enters the box body from the permeable concrete on the side (which can pass through the opening 2 when the rainfall is large), and the rainwater in the box initially permeates into the vegetation planting layer 5 through the permeable concrete on the inner side; secondly, along with the rise of the water level in the box, rainwater flows into the gravel layer through the primary water discharge pipe 10, is collected through the water permeable pipe 11 in the gravel layer and is conveyed to the seepage box 12, and the rainwater in the seepage box 12 can be discharged into a rainwater well or a municipal pipe network 17 through the secondary water discharge pipe 10b when the water quantity is small and the water level is low; thirdly, when rainstorm or continuous rainfall occurs, the water level in the seepage box 12 rises to the interface of the three-level drainage pipe 10c, the three-level drainage pipe 10c is connected into the vertical water guiding sand well 14, and rainwater is guided into the lower part of the soil layer boundary layer 16, so that graded drainage of the road is realized. Meanwhile, the lime soil cushion layer, the impermeable film and the water-stop wall can play a water-stop role, and rainwater can be effectively prevented from permeating a collapsible stratum.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising an … …" does not exclude the presence of other identical elements in a process, method, article, or apparatus that comprises the element.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (10)

1.一种湿陷性黄土地层中海绵城市道路分级排水系统,其特征在于,包括路缘调蓄箱(1)、隔水墙(4)、渗流箱(12)、透水管(11),所述路缘调蓄箱(1)设于路面与绿化带交界处,所述路缘调蓄箱(1)靠近绿化带的侧面开口与一级排水管(10)相连,隔水墙(4)设于路缘调蓄箱(1)下部,两隔水墙(4)中间由上至下依次设有植被种植层(5)、碎石层、灰土垫层(8)和防渗膜(9),渗流箱(12)位于灰土垫层(8)内,所述渗流箱(12)靠近道路方向的侧面自下而上设有两开口分别与二级排水管(10b)、三级排水管(10c)相连,且二级排水管(10b)、三级排水管(10c)皆穿过隔水墙(4)至道路侧边缘,所述二级排水管(10b)接入雨水井或市政管网(17),所述三级排水管(10c)通过直角弯头(13)接入位于隔水墙(4)外侧、埋设于道路下方的导水砂井(14),所述透水管(11)沿道路纵向设于靠近碎石层中间下部。1. a sponge city road graded drainage system in a collapsible loess stratum, is characterized in that, comprises curb adjustment and storage tank (1), water barrier (4), seepage box (12), permeable pipe (11), The curbside storage tank (1) is arranged at the junction of the road surface and the green belt, and the side opening of the curbside storage tank (1) close to the green belt is connected to the primary drain pipe (10), and the water barrier (4) ) is located at the lower part of the road edge regulating and storage box (1), and the middle of the two water partition walls (4) is sequentially provided with a vegetation planting layer (5), a gravel layer, a lime-soil cushion (8) and an anti-seepage membrane (5) from top to bottom. 9), the seepage box (12) is located in the lime-soil cushion (8), and the side of the seepage box (12) close to the road direction is provided with two openings from bottom to top, which are respectively connected to the secondary drainage pipe (10b) and the tertiary drainage pipe. The pipes (10c) are connected, and the secondary drainage pipes (10b) and the tertiary drainage pipes (10c) pass through the water partition wall (4) to the side edge of the road, and the secondary drainage pipes (10b) are connected to the rainwater well or A municipal pipe network (17), the tertiary drainage pipe (10c) is connected to a water-conducting sand well (14) located on the outside of the water barrier (4) and buried under the road through a right-angle elbow (13), and the water-permeable well (14) is provided. The pipe (11) is arranged at the lower part near the middle of the gravel layer along the longitudinal direction of the road. 2.根据权利要求1所述的一种湿陷性黄土地层中海绵城市道路分级排水系统,其特征在于:所述路缘调蓄箱(1)为长方体,沿道路纵向全程布设,高30cm,地面以上部分高20cm,地面以下部分为10cm,靠近道路方向的路缘调蓄箱(1)侧面超出路面部分和靠近绿化带方向的侧面所设开口以下部分由透水混凝土浇筑,其余部分均由普通混凝土浇筑;所述路缘调蓄箱(1)靠近道路方向的侧面沿道路纵向间隔设有开孔(2),开孔(2)位于路面以上15cm处,内部设有双层滤网(3)。2. The grading drainage system for sponge city roads in a collapsible loess stratum according to claim 1, characterized in that: the curb adjustment and storage box (1) is a rectangular parallelepiped, and is longitudinally arranged along the road in the whole process, with a height of 30cm, The height of the part above the ground is 20cm, and the part below the ground is 10cm. The side of the curb storage tank (1) close to the road direction is beyond the road surface and the part below the opening set on the side near the green belt direction is poured with permeable concrete, and the rest are made of ordinary Concrete pouring; openings (2) are provided at the side of the curb adjustment and storage box (1) close to the road direction along the longitudinal direction of the road, the openings (2) are located 15cm above the road surface, and a double-layer filter screen (3) is arranged inside ). 3.根据权利要求1所述的一种湿陷性黄土地层中海绵城市道路分级排水系统,其特征在于:所述隔水墙(4)长度与路缘调蓄箱(1)长度相等,沿道路纵向全程布设,高度为路缘调蓄箱(1)底部至灰土垫层(8)底部。3. The sponge city road graded drainage system in a collapsible loess stratum according to claim 1, characterized in that: the length of the water barrier (4) is equal to the length of the curb adjustment and storage box (1), The length of the road is longitudinally laid out, and the height is from the bottom of the curb storage tank (1) to the bottom of the lime-soil cushion (8). 4.根据权利要求1所述的一种湿陷性黄土地层中海绵城市道路分级排水系统,其特征在于:所述一级排水管(10)与路缘调蓄箱(1)侧面开口连接处的高度与路面高度相同,一级排水管(10)穿过植被种植层(5)至碎石层顶部。4. The grading drainage system for sponge city roads in a collapsible loess stratum according to claim 1, characterized in that: the first-level drainage pipe (10) is connected to the side opening of the curb adjustment and storage box (1). The height is the same as that of the road surface, and the primary drainage pipe (10) passes through the vegetation planting layer (5) to the top of the gravel layer. 5.根据权利要求1所述的一种湿陷性黄土地层中海绵城市道路分级排水系统,其特征在于:所述碎石层沿道路纵向交替设置第一碎石层(6)和第二碎石层(6a),均布设于灰土垫层(8)顶部,其中,第二碎石层(6a)厚度为第一碎石层(6)厚度的1/3,第二碎石层(6a)以上皆为植被种植层(5)。5. The sponge city road graded drainage system in a collapsible loess stratum according to claim 1, wherein the gravel layer is alternately arranged with a first gravel layer (6) and a second gravel layer along the longitudinal direction of the road. The stone layers (6a) are evenly arranged on the top of the lime-soil cushion layer (8), wherein the thickness of the second gravel layer (6a) is 1/3 of the thickness of the first gravel layer (6), and the thickness of the second gravel layer (6a) is ) above are all vegetation planting layers (5). 6.根据权利要求1所述的一种湿陷性黄土地层中海绵城市道路分级排水系统,其特征在于:所述碎石层与植被种植层(5)、灰土垫层(8)的接触面上皆设有透水土工布(7)。6. The sponge city road graded drainage system in a collapsible loess layer according to claim 1, characterized in that: the contact surface of the gravel layer and the vegetation planting layer (5) and the lime-soil cushion layer (8) Both are provided with permeable geotextiles (7). 7.根据权利要求1所述的一种湿陷性黄土地层中海绵城市道路分级排水系统,其特征在于:所述渗流箱(12)为长方体,沿道路纵向间隔布置,采用细石混凝土材质,渗流箱(12)内的雨水先通过二级排水管(10b)排入雨水井或市政管网(17),箱内水位上升至一定高度时,雨水经三级排水管(10c)导入竖向导水砂井(14)。7. The sponge city road graded drainage system in a collapsible loess stratum according to claim 1, wherein the seepage box (12) is a rectangular parallelepiped, arranged at intervals along the road longitudinally, and is made of fine stone concrete, The rainwater in the seepage tank (12) is firstly discharged into the rainwater well or the municipal pipe network (17) through the secondary drain pipe (10b), and when the water level in the tank rises to a certain height, the rainwater is guided into the vertical guide through the tertiary drain pipe (10c). Water sand wells (14). 8.根据权利要求1所述的一种湿陷性黄土地层中海绵城市道路分级排水系统,其特征在于:所述导水砂井(14)开挖至土层分界层(16)以下,沿井壁沉入PVC的防渗筒(15),防渗筒(15)内部填砂。8. The sponge city road graded drainage system in a collapsible loess stratum according to claim 1, characterized in that: the water-conducting sand well (14) is excavated to below the soil layer boundary layer (16), along the The wall of the well is sunk into the PVC anti-seepage cylinder (15), and the interior of the anti-seepage cylinder (15) is filled with sand. 9.根据权利要求1所述的一种湿陷性黄土地层中海绵城市道路分级排水系统,其特征在于:所述透水管(11)顶部和管周上半部分间隔均匀设有小孔径的开孔(2),透水管(11)设于碎石层底部中间位置,位于第一碎石层(6)内的透水管(11)部分,底部设大孔径开孔(2),位于第二碎石层(6a)内的透水管(11)部分,底部不设开孔(2)。9. The sponge city road graded drainage system in a collapsible loess stratum according to claim 1, characterized in that: the top of the permeable pipe (11) and the upper half of the pipe circumference are evenly provided with small aperture openings at intervals. The hole (2), the permeable pipe (11) is arranged in the middle of the bottom of the crushed stone layer, and is located in the part of the permeable pipe (11) in the first crushed stone layer (6). The part of the permeable pipe (11) in the gravel layer (6a) has no opening (2) at the bottom. 10.根据权利要求1所述的一种湿陷性黄土地层中海绵城市道路分级排水系统,其特征在于:所述透水管(11)底部的开孔(2)与排水连接管(10a)一端相连,排水连接管(10a)另一端接入渗流箱(12)的顶部开口,位于第二碎石层(6a)的透水管(11)部分,底部不布设排水连接管(10a)与渗流箱(12)后续排水结构。10. A sponge city road graded drainage system in a collapsible loess stratum according to claim 1, characterized in that: the opening (2) at the bottom of the permeable pipe (11) and one end of the drainage connecting pipe (10a) The other end of the drainage connection pipe (10a) is connected to the top opening of the seepage box (12), which is located in the permeable pipe (11) part of the second gravel layer (6a), and the drain connection pipe (10a) and the seepage box are not arranged at the bottom. (12) Subsequent drainage structure.
CN202111227247.3A 2021-10-21 2021-10-21 Sponge urban road grading drainage system in collapsible loess stratum Pending CN113898051A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111227247.3A CN113898051A (en) 2021-10-21 2021-10-21 Sponge urban road grading drainage system in collapsible loess stratum

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111227247.3A CN113898051A (en) 2021-10-21 2021-10-21 Sponge urban road grading drainage system in collapsible loess stratum

Publications (1)

Publication Number Publication Date
CN113898051A true CN113898051A (en) 2022-01-07

Family

ID=79026027

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111227247.3A Pending CN113898051A (en) 2021-10-21 2021-10-21 Sponge urban road grading drainage system in collapsible loess stratum

Country Status (1)

Country Link
CN (1) CN113898051A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116537156A (en) * 2023-04-20 2023-08-04 中交(天津)生态环保设计研究院有限公司 Construction method of three-stage vacuum preloading drainage system for ecological dredging bottom mud of river, lake and reservoir

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101206057B1 (en) * 2011-12-15 2012-11-29 주식회사 승원엔지니어링 drainage and vegetation structure for sidewalk
KR101222885B1 (en) * 2012-07-06 2013-01-17 (주)청운환경기술 The rainwater gatherring system
CN107975124A (en) * 2017-11-30 2018-05-01 西安理工大学 Sponge city sand drain system
CN110004792A (en) * 2018-11-07 2019-07-12 河北农业大学 A water storage structure for green belts and roads between them
CN110042724A (en) * 2019-04-30 2019-07-23 中国市政工程西北设计研究院有限公司 Collapsible Loess District road sponge facility rainwater catchment system and exhaust system
CN110847196A (en) * 2019-10-18 2020-02-28 西安理工大学 A Loess Plateau Ecological Governance Structure and Its Governance Method Considering Solar Energy Utilization

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101206057B1 (en) * 2011-12-15 2012-11-29 주식회사 승원엔지니어링 drainage and vegetation structure for sidewalk
KR101222885B1 (en) * 2012-07-06 2013-01-17 (주)청운환경기술 The rainwater gatherring system
CN107975124A (en) * 2017-11-30 2018-05-01 西安理工大学 Sponge city sand drain system
CN110004792A (en) * 2018-11-07 2019-07-12 河北农业大学 A water storage structure for green belts and roads between them
CN110042724A (en) * 2019-04-30 2019-07-23 中国市政工程西北设计研究院有限公司 Collapsible Loess District road sponge facility rainwater catchment system and exhaust system
CN110847196A (en) * 2019-10-18 2020-02-28 西安理工大学 A Loess Plateau Ecological Governance Structure and Its Governance Method Considering Solar Energy Utilization

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116537156A (en) * 2023-04-20 2023-08-04 中交(天津)生态环保设计研究院有限公司 Construction method of three-stage vacuum preloading drainage system for ecological dredging bottom mud of river, lake and reservoir

Similar Documents

Publication Publication Date Title
EP0734478B1 (en) Underground drainage system
CN207727714U (en) Sponge urban ecology filtration system
CN211057960U (en) Stepped rainwater storage and purification ecological retention system
CN109356225A (en) A kind of Multifunctional rain ecological utilization system
CN103088897A (en) Green community impact resistance rainwater ecological utilization system
CN110042724A (en) Collapsible Loess District road sponge facility rainwater catchment system and exhaust system
CN103603320A (en) LID (low impact development) type rainwater ditch and design and calculation method for same
CN110468947A (en) Ecological tree pond
CN106193261A (en) A kind of Collapsible Loess District rain flood harvests step man-made lake system and method for designing
CN111535098A (en) Rainwater drainage system for green belts and sidewalks of town roads and construction method
CN113818534B (en) Biological detention facility for sponge urban road
CN113863465A (en) Ecological drainage system of sponge urban road
CN207062672U (en) A kind of permeable pavement structure
CN113402120A (en) Ecological interception system of agricultural non-point source pollution
CN108867806B (en) Rainwater garden for rainwater collection, recycling and reuse
CN216786729U (en) Prevent road surface ponding's novel ecology road structure that permeates water
CN213653722U (en) Adjustable storage and permeable sponge city rainwater pipe network system for building communities
CN106088295A (en) Method and system for controlling and utilizing rainwater by modifying existing facilities
CN222834686U (en) A road drainage system for rainy areas
CN210916859U (en) Rainwater collecting, utilizing and discharging system for road sponge facilities in collapsible loess areas
JP2802282B2 (en) Rechargeable storage facility
CN205295848U (en) Firm type ecology system of mating formation of permeating water
CN211200669U (en) Ecological tree pond
CN112144345A (en) Ecological building block drainage gutter and parameter determination method thereof
CN116084231B (en) Sponge city structure for low-influence development of roads and rainwater regulation and storage method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20220107