CN113882244A - A concrete track bridge pillar system and its adjustment method for dealing with ground subsidence - Google Patents
A concrete track bridge pillar system and its adjustment method for dealing with ground subsidence Download PDFInfo
- Publication number
- CN113882244A CN113882244A CN202111208192.1A CN202111208192A CN113882244A CN 113882244 A CN113882244 A CN 113882244A CN 202111208192 A CN202111208192 A CN 202111208192A CN 113882244 A CN113882244 A CN 113882244A
- Authority
- CN
- China
- Prior art keywords
- concrete
- base
- track
- external thread
- supporting plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/02—Piers; Abutments ; Protecting same against drifting ice
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D22/00—Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/08—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against transmission of vibrations or movements in the foundation soil
Landscapes
- Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Architecture (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a concrete track bridge strut system and an adjustment method for dealing with ground settlement thereof, wherein the system comprises a concrete foundation, a concrete strut, an embedded part and a tray device, wherein the embedded part comprises a bottom plate which is provided with a plurality of studs vertically penetrating through the bottom plate; the tray device comprises a supporting plate, wherein the supporting plate is provided with external thread sleeves which correspond to the studs one by one, the supporting plate is placed on the bottom plate, the external thread sleeves penetrate through mounting holes in a base of the concrete strut, and the upper ends of the studs penetrate through the external thread sleeves and the top surface of the base upwards and then are fixed through first nuts; track daub is poured between the supporting plate and the base. According to the invention, when the ground subsides too much, the concrete strut and the tray device can be taken down from the stud, the adjusting pad is placed, and then the concrete strut and the tray device are installed on the stud, so that the concrete strut can be repeatedly used, the efficiency is improved, and the cost is reduced.
Description
Technical Field
The invention relates to the technical field of concrete track bridges, in particular to a concrete track bridge strut system and an adjusting method for the concrete track bridge strut system to cope with ground settlement.
Background
Urban subways and urban railways are used as main transportation means and play an important role in urban public transportation.
In order to ensure the operation safety, the subway and the urban railway train need to be regularly overhauled and maintained, and for conveniently carrying out the train overhaul work, an inspection pit is usually required to be arranged, but the space of the traditional wall type inspection pit is narrow and small, the permeability is poor, the overhaul work is inconvenient, and the inspection pit is replaced by a railway bridge along with the development of the technology.
The Chinese invention patent CN110761124B discloses an assembled concrete track bridge, which is applied to a motor train overhaul base and a subway train detection field to overhaul motor train units and subway vehicles in the base. The assembled concrete track bridge consists of a concrete strut, a concrete foundation, a steel rail, an elastic strip fastener and an embedded part, wherein the middle part of the concrete strut is a polygonal section and is formed by rectangular sections with four corners being concave arcs; the two ends of the middle part are in smooth transition with the top and the bottom of the concrete strut; oblong through holes are formed in the inner sides of four corners of a rectangular cross section at the bottom of the concrete support column, embedded parts penetrate through the oblong holes to connect the concrete support column with a concrete foundation, and the bottom of the concrete support column and the concrete foundation are leveled and filled through track cement.
However, due to the influence of ground subsidence, particularly in major cities in the Yangtze river delta, North China plain and Fenwei region, the concrete pillars are subsided along with the concrete pillars, so that the track bridge is bent and deformed, and accident potential is generated. For this reason, when the ground subsidence is excessively large, the height of the concrete column needs to be adjusted. Above-mentioned scheme, because concrete pillar and built-in fitting pouring form an organic whole structure, only can break the concrete pillar, the refabrication has caused the period of a project long, intensity of labour is big, problem with high costs.
In view of this, there is a need for structural improvement of the existing concrete track bridge support system to facilitate height adjustment after ground settlement, reduce cost, and improve efficiency.
Disclosure of Invention
In view of the above-mentioned drawbacks, the technical problem to be solved by the present invention is to provide a concrete track bridge support post system and an adjustment method thereof for dealing with ground settlement, so as to solve the problems of long construction period, high labor intensity and high cost caused by that the existing concrete track bridge support post can only be broken and re-made when the ground settlement is too large.
Therefore, the concrete track bridge support column system provided by the invention comprises a concrete foundation and a concrete support column, wherein the concrete foundation is provided with an embedded part, the embedded part comprises a bottom plate, the bottom plate is provided with a plurality of studs vertically penetrating through the bottom plate, and the concrete track bridge support column system further comprises:
the tray device comprises a supporting plate, wherein through holes which correspond to the studs one by one are formed in the supporting plate, external thread sleeves are fixed at the through holes, the inner diameter of each external thread sleeve is larger than the outer diameter of each stud, and the height of each external thread sleeve is smaller than the thickness of a base of the concrete support; the supporting plate is placed on the bottom plate, the external thread sleeve penetrates through the mounting hole in the base, and the upper end of the stud penetrates through the external thread sleeve and the top surface of the base upwards and is fixed through a first nut; track daub is poured between the supporting plate and the base.
In the above technical solution, preferably, the edge of the supporting plate is provided with a coaming, and the track mastic is poured into a space surrounded by the coaming.
In the above technical scheme, preferably, the bounding wall with the clearance between two relative lateral walls of base forms first clearance and second clearance respectively, the bounding wall with the laminating of two other lateral walls of base, first clearance is greater than the second clearance, and the track daub is from first clearance department fills, follows second clearance department flows.
In the above technical solution, preferably, each outer edge of the supporting plate is located outside the bottom plate.
In the above technical solution, preferably, a second nut is disposed on the external thread sleeve, and the second nut abuts against the bottom surface of the base.
In the above technical solution, preferably, track mastic is poured between the mounting hole and the outer wall of the external thread bushing.
In the above technical solution, preferably, an adjusting pad is disposed between the bottom plate and the supporting plate.
In the above technical solution, preferably, the top surface of the coaming is higher than the top surface of the concrete foundation and the bottom surface of the base.
The invention also provides a method for adjusting the concrete track bridge strut system to the ground settlement, which is realized by adopting the concrete track bridge strut system, and the method comprises the following steps:
when the ground subsides and the height of the concrete support needs to be adjusted, the first nut is dismounted, the concrete support and the tray device are hoisted together and pulled out of the stud, the adjusting pad is laid on the top surface of the bottom plate of the embedded part, the concrete support and the tray device are installed on the stud, and the first nut is installed and fastened to enable the supporting plate to be tightly pressed on the adjusting pad on the bottom plate.
According to the technical scheme, the concrete track bridge support column system and the adjustment method thereof for dealing with ground settlement solve the problems that in the prior art, as the concrete support column and the embedded part are poured into an integrated structure, the concrete support column can only be broken and manufactured again, the construction period is long, the labor intensity is high, and the cost is high. Compared with the prior art, the invention has the following beneficial effects:
the concrete support column is installed on the embedded part through the tray device, the tray device comprises a supporting plate, an external thread sleeve which corresponds to the studs on the embedded part in a one-to-one mode is arranged on the supporting plate, the external thread sleeve penetrates through the installation hole in the base, and the upper end of the stud is fixed through a first nut after upwards penetrating through the external thread sleeve and the top surface of the base. When ground subsides too big, can together take off the concrete pillar together with the tray device from the double-screw bolt, place the adjustment on the bottom plate of built-in fitting and fill up the back, install the concrete pillar on the double-screw bolt together with the tray device again, from this, the concrete pillar can used repeatedly, has solved the difficult problem that present concrete track bridge pillar can't adjust the height, and has improved efficiency, the cost is reduced.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments of the present invention or the prior art will be briefly described and explained. It is obvious that the drawings in the following description are only some embodiments of the invention, and that for a person skilled in the art, other drawings can be derived from them without inventive effort.
FIG. 1 is a cross-sectional view of a concrete track bridge stanchion system provided in accordance with the present invention;
FIG. 2 is a schematic view of an embedment of the present invention;
FIG. 3 is a schematic view of a cradle assembly according to the present invention;
fig. 4 is an enlarged view of a portion a in fig. 1.
In fig. 1 to 4, the correspondence between the components is as follows:
the concrete support column 10, the concrete foundation 20, the embedded part 30, the tray device 40 and the track plaster 50;
a base 11, a first nut 12;
a bottom plate 31, a stud 32, and a bent portion 33;
the supporting plate 41, the external thread sleeve 42, the enclosing plate 43, the first gap 44, the second gap 45, the second nut 46 and the adjusting pad 47.
Detailed Description
The technical solutions of the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings, and it is to be understood that the embodiments described below are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments of the present invention without any inventive step, are within the scope of the present invention.
The realization principle of the invention is as follows:
the concrete support column is installed on the embedded part through the tray device, the tray device comprises a supporting plate, an external thread sleeve which corresponds to the stud on the embedded part in a one-to-one mode is arranged on the supporting plate, the external thread sleeve is sleeved on the stud and penetrates through the installation hole in the base, and the upper end of the stud is fixed through a first nut after upwards penetrating out of the external thread sleeve and the top surface of the base.
According to the scheme provided by the invention, after the ground subsidence is too large, the concrete strut and the tray device can be taken down from the stud, the adjusting pad is placed on the bottom plate, and then the concrete strut and the tray device are installed on the stud, so that the concrete strut can be repeatedly used, the efficiency is improved, and the cost is reduced.
In order to make the technical solution and implementation of the present invention more clearly explained and illustrated, several preferred embodiments for implementing the technical solution of the present invention are described below.
It should be noted that the terms of orientation such as "inside, outside", "front, back" and "left and right" are used herein as reference objects, and it is obvious that the use of the corresponding terms of orientation does not limit the scope of protection of the present invention.
Referring to fig. 1, fig. 1 is a cross-sectional view of a concrete track bridge support system according to the present invention.
As shown in fig. 1, the concrete track bridge support column system provided by the invention comprises a concrete support column 10, a concrete foundation 20, embedded parts 30 and a tray device 40, wherein the concrete foundation 20 is provided with the embedded parts 30, the embedded parts 30 are embedded in the concrete foundation 20, and the concrete support column 10 is installed on the embedded parts 30 through the tray device 40.
Referring to fig. 2 again, the embedded part 30 includes a bottom plate 31, and a plurality of studs 32 vertically penetrate through the bottom plate 31, in this embodiment, the base 11 of the concrete pillar 10 is a square or rectangular structure, and 4 studs 32 are arranged corresponding to four corners of the base 11. The stud 32 has a threaded portion at the upper end and a bent portion 33 at the lower end, and the bent portion 33 is bent in a direction in which the ends of two adjacent bent portions 33 are opposed to each other. The part of the stud 32 below the bottom plate 31 is embedded in the concrete foundation 20, and after the embedded part 30 is embedded, the top surface of the bottom plate 31 is not covered with concrete.
Referring to fig. 3 again, the tray device 40 includes a supporting plate 41, which is provided with through holes corresponding to the studs 32 one by one, and an external thread sleeve 42 is fixedly disposed at the through holes, for example, the external thread sleeve 42 is inserted into the through holes to be welded or bonded or fixed by crimping. The inner diameter of the external threaded sleeve 42 is larger than the outer diameter of the stud 32, and a clearance of 2-5mm is arranged between the two, so that the external threaded sleeve 42 is sleeved on the stud 32 and can move axially, and the external threaded sleeve 42 can be inserted and pulled out.
The supporting plate 41 is placed on the bottom plate 31, the external thread sleeve 42 penetrates through the mounting hole in the base 11, and the first nut 12 is installed and fixed after the upper end of the stud 32 penetrates through the external thread sleeve 42 and the top surface of the base 11 upwards. The height of the external thread bush 42 is smaller than the thickness of the base 11 of the concrete column 10, so that the supporting plate 41 can be pressed against the bottom plate 31 by the first nut 12.
Referring to fig. 3, a surrounding plate 43 is disposed on the outer edge of the supporting plate 41, the surrounding plate 43 is rectangular to form a circumferential closed structure, and the surrounding plate 43 can be directly fixed to the supporting plate 41 or can be made into a detachable structure.
Wherein, tray device 40 except can adopting steel, iron material, layer board 41 and bounding wall 43 can also adopt high density polyethylene board, and external screw thread cover 42 can adopt fine reinforcing polyamide 66 of glass, compares with steel, iron material, and non-metallic material is more corrosion-resistant, has prolonged life, also inserts more easily and extracts.
The cross section of the base 11 is rectangular, a first gap 44 and a second gap 45 are respectively formed between the inner wall of the enclosing plate 43 and two opposite side walls of the base 11, the first gap 44 is larger than the second gap 45, the inner wall of the enclosing plate 43 is attached to the other two side walls of the base 11, the track daub 50 is poured from the first gap 44 and flows out from the second gap 45, and when the track daub 50 flows out to the height of 1-2 cm, the track daub 50 stops being poured. This kind of mode of filling from the one end that the clearance is big to the one end that the clearance is little can guarantee that track clay fills the in-process and has fine mobility, and the track clay is more closely knit after filling, guarantees intensity.
The outer edge of the supporting plate 41 is located on the outer side of the bottom plate 31, so that the projection surface of the supporting plate 41 completely covers the bottom plate 31, and the track plaster 50 is prevented from entering between the supporting plate 41 and the bottom plate 31 when the track plaster 50 is poured, and the supporting plate 41 and the bottom plate 31 are easily separated.
The external thread sleeve 42 is provided with a second nut 46, the second nut 46 is abutted against the bottom surface of the base 11, a gap is arranged between the second nut 46 and the supporting plate 41, and the perpendicularity and the height of the concrete support column 10 can be adjusted by adjusting 4 second nuts 46.
An adjusting pad 47 is provided between the bottom plate 31 and the support plate 41 for adjusting the height of the concrete column 10.
The invention provides a concrete track bridge strut system, which comprises the following construction methods:
first, the embedded parts 30 are embedded in the concrete foundation 20.
Then, the pallet means 40 is mounted on the embedment 30, specifically, the male screw housing 42 is fitted over the stud 32, and pressed down so that the pallet 41 is pressed against the base plate 31.
Third, a second nut 46 is mounted on the external threaded sleeve 42.
Fourthly, the mounting hole of the base 11 of the concrete column 10 is inserted into the external thread bush 42, and the bottom surface of the base 11 is abutted against the second nut 46.
Fifthly, the second nuts 46 are adjusted to keep the concrete support column 10 in a vertical state and to meet the design requirements in height.
Sixthly, the first nut 12 is fastened and installed to press the support plate 41 against the base plate 31.
Seventhly, pouring track daub 50 from the first gap 44, and stopping pouring after the track daub flows out from the second gap 45; track mastic 50 is poured between the mounting hole of the base 11 and the outer wall of the externally threaded sleeve 42.
According to the adjusting method for the concrete track bridge support post system to cope with the ground settlement, when the ground settlement is too large and the height of the concrete support post 10 needs to be adjusted, the first nut 12 is firstly dismounted, then the concrete support post 10 and the tray device 40 are lifted together and pulled out from the stud 32, then an adjusting pad is laid on the top surface of the bottom plate 31 of the embedded part 30, then the concrete support post 10 and the tray device 40 are installed on the stud 32, and the first nut 12 is installed and fastened, so that the supporting plate 41 is pressed on the adjusting pad on the bottom plate 31. Appropriate repairs can be made to the concrete surrounding the foundation 11.
With the above description of the specific embodiment, the concrete track bridge support system and the adjustment method thereof for ground settlement provided by the invention have the following advantages compared with the prior art:
firstly, the external thread sleeve on the bracket device is sleeved on the stud of the embedded part and can be inserted and pulled out, when the ground settlement is overlarge, the concrete strut and the tray device can be taken down from the stud, the adjusting pad is placed on the bottom plate of the embedded part, and then the concrete strut and the tray device are installed on the stud, so that the concrete strut can be repeatedly used, the efficiency is improved, and the cost is reduced.
And secondly, a second nut is arranged on the external thread sleeve, the second nut is abutted against the bottom surface of the base, and the verticality and the height of the concrete support can be adjusted through adjusting the second nut.
And thirdly, the outer edge of the supporting plate is fixedly provided with a surrounding plate, and the track cement is poured into the space surrounded by the surrounding plate, so that when the track cement is prevented from being poured, the track cement enters the space between the supporting plate and the bottom plate, and the two problems that the supporting plate and the bottom plate are not easy to loosen are caused.
Fourth, the clearance between two relative lateral walls of bounding wall and base forms first clearance and second clearance respectively, and first clearance is greater than the second clearance, and the track clay pours from first clearance department, flows from second clearance department, can guarantee that the track clay pours the in-process and has fine mobility, and the track clay is more closely knit after pouring, guarantees intensity.
Finally, it should also be noted that the terms "comprises," "comprising," or any other variation thereof, as used herein, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising an …" does not exclude the presence of other identical elements in a process, method, article, or apparatus that comprises the element.
The present invention is not limited to the above-mentioned preferred embodiments, and any structural changes made under the teaching of the present invention shall fall within the scope of the present invention, which is similar or similar to the technical solutions of the present invention.
Claims (9)
1. The utility model provides a concrete track bridge pillar system, includes concrete foundation and concrete support, the concrete foundation is equipped with the built-in fitting, the built-in fitting includes the bottom plate, the bottom plate has the many double-screw bolts that run through its setting perpendicularly, its characterized in that still includes:
the tray device comprises a supporting plate, wherein through holes which correspond to the studs one by one are formed in the supporting plate, external thread sleeves are fixed at the through holes, the inner diameter of each external thread sleeve is larger than the outer diameter of each stud, and the height of each external thread sleeve is smaller than the thickness of a base of the concrete support; the supporting plate is placed on the bottom plate, the external thread sleeve penetrates through the mounting hole in the base, and the upper end of the stud penetrates through the external thread sleeve and the top surface of the base upwards and is fixed through a first nut; track daub is poured between the supporting plate and the base.
2. The concrete track bridge strut system of claim 1, wherein the edge of the support plate is provided with a shroud, and the track mastic is poured into a space enclosed by the shroud.
3. The concrete track bridge strut system of claim 2, wherein the gap between the shroud and the two opposing side walls of the base form a first gap and a second gap, respectively, the shroud abuts the other two side walls of the base, the first gap is larger than the second gap, and the track mastic is poured from the first gap and flows out of the second gap.
4. The concrete track bridge strut system of claim 1, wherein each outer edge of said support plate is located outside of said base plate.
5. The concrete track bridge strut system as in claim 1, wherein said externally threaded sleeve has a second nut, said second nut abutting a bottom surface of said base.
6. The concrete track bridge strut system of claim 1, wherein a track mastic is poured between the mounting hole and an outer wall of the externally threaded sleeve.
7. The concrete track bridge strut system of claim 1, wherein a spacer is provided between said base plate and said support plate.
8. The concrete track bridge strut system of claim 2, wherein the top surface of the coaming is higher than the top surface of the concrete foundation and the bottom surface of the base.
9. A method for adjusting a concrete track bridge support system to ground subsidence, which is implemented by using the concrete track bridge support system of claim 1, the method comprising the steps of:
when the ground subsides and the height of the concrete support needs to be adjusted, the first nut is dismounted, the concrete support and the tray device are hoisted together and pulled out of the stud, the adjusting pad is laid on the top surface of the bottom plate of the embedded part, the concrete support and the tray device are installed on the stud, and the first nut is installed and fastened to enable the supporting plate to be tightly pressed on the adjusting pad on the bottom plate.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202111208192.1A CN113882244B (en) | 2021-10-18 | 2021-10-18 | A concrete rail bridge support system and its adjustment method for coping with ground subsidence |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202111208192.1A CN113882244B (en) | 2021-10-18 | 2021-10-18 | A concrete rail bridge support system and its adjustment method for coping with ground subsidence |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN113882244A true CN113882244A (en) | 2022-01-04 |
| CN113882244B CN113882244B (en) | 2025-06-20 |
Family
ID=79003295
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202111208192.1A Active CN113882244B (en) | 2021-10-18 | 2021-10-18 | A concrete rail bridge support system and its adjustment method for coping with ground subsidence |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN113882244B (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115288009A (en) * | 2022-09-02 | 2022-11-04 | 中铁华铁工程设计集团有限公司 | A replaceable concrete track bridge pillar structure |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2004257098A (en) * | 2003-02-26 | 2004-09-16 | Koken Sangyo Kk | Construction method of structure with footing |
| CN201473888U (en) * | 2009-09-02 | 2010-05-19 | 北京磁通设备制造有限公司 | Elevated rail bridge |
| CN210085936U (en) * | 2018-07-26 | 2020-02-18 | 中铁华铁工程设计集团有限公司 | Assembled concrete track bridge |
| CN112030729A (en) * | 2020-08-26 | 2020-12-04 | 绍兴文理学院 | Prefabricated bridge pier and bearing platform connecting system for assembled beam bridge and construction method of prefabricated bridge pier and bearing platform connecting system |
| CN112111998A (en) * | 2020-10-19 | 2020-12-22 | 中铁第四勘察设计院集团有限公司 | Urban rail transit vehicle base rail support column suitable for fourth rail backflow |
| CN112112180A (en) * | 2020-08-26 | 2020-12-22 | 绍兴文理学院 | A connection system of prefabricated composite piers and caps and construction method thereof |
| CN216108042U (en) * | 2021-10-18 | 2022-03-22 | 中铁华铁工程设计集团有限公司 | Concrete track bridge pillar system |
-
2021
- 2021-10-18 CN CN202111208192.1A patent/CN113882244B/en active Active
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2004257098A (en) * | 2003-02-26 | 2004-09-16 | Koken Sangyo Kk | Construction method of structure with footing |
| CN201473888U (en) * | 2009-09-02 | 2010-05-19 | 北京磁通设备制造有限公司 | Elevated rail bridge |
| CN210085936U (en) * | 2018-07-26 | 2020-02-18 | 中铁华铁工程设计集团有限公司 | Assembled concrete track bridge |
| CN112030729A (en) * | 2020-08-26 | 2020-12-04 | 绍兴文理学院 | Prefabricated bridge pier and bearing platform connecting system for assembled beam bridge and construction method of prefabricated bridge pier and bearing platform connecting system |
| CN112112180A (en) * | 2020-08-26 | 2020-12-22 | 绍兴文理学院 | A connection system of prefabricated composite piers and caps and construction method thereof |
| CN112111998A (en) * | 2020-10-19 | 2020-12-22 | 中铁第四勘察设计院集团有限公司 | Urban rail transit vehicle base rail support column suitable for fourth rail backflow |
| CN216108042U (en) * | 2021-10-18 | 2022-03-22 | 中铁华铁工程设计集团有限公司 | Concrete track bridge pillar system |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115288009A (en) * | 2022-09-02 | 2022-11-04 | 中铁华铁工程设计集团有限公司 | A replaceable concrete track bridge pillar structure |
| CN115288009B (en) * | 2022-09-02 | 2025-04-25 | 中铁华铁工程设计集团有限公司 | A replaceable concrete rail bridge support structure |
Also Published As
| Publication number | Publication date |
|---|---|
| CN113882244B (en) | 2025-06-20 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR100454405B1 (en) | Method for changing steel bridge of supporting rail into concreat bridge | |
| CN215947749U (en) | Prefabricated assembled ballast bed | |
| CN107740342A (en) | Prefabricated assembling type reinforced concrete bridge block and its building method | |
| CN216108042U (en) | Concrete track bridge pillar system | |
| CN113882244B (en) | A concrete rail bridge support system and its adjustment method for coping with ground subsidence | |
| KR20200085573A (en) | Gravity type leveling method for precast members including expansion joint | |
| CN213653175U (en) | Steel temporary bridge structure for road surface excavation construction | |
| CN212715649U (en) | Shear key installation structure | |
| CN222414259U (en) | Prefabricated hollow square column type inspection pit capable of being forward construction column base bolted | |
| CN211228068U (en) | Festival segmentation pier convenient to installation | |
| CN211228923U (en) | Fixing device for pre-buried steel plate under shock insulation support | |
| CN218263465U (en) | Cable tower X supports and sets up | |
| CN112681514A (en) | Assembly type node sleeve and installation method thereof | |
| CN107503368B (en) | Prefabricated assembled steel-concrete structure photovoltaic power generation equipment platform | |
| CN208965391U (en) | A kind of latching mechanism of steel plate combination beam and support | |
| CN215906566U (en) | Track bridge pillar shock mitigation system and shock-absorbing structure thereof | |
| CN215947748U (en) | Prefabricated combined assembled ballast bed | |
| CN116732885A (en) | Construction method of prefabricated pier applicable to areas with larger earthquake fortification intensity | |
| CN207176727U (en) | Prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform | |
| CN217078381U (en) | Assembled concrete track bridge pillar system | |
| CN115434239A (en) | Module type bridge deck safety protection facility and design method | |
| CN209816676U (en) | Ox leg type hoop | |
| CN113737661A (en) | Construction method for steel-concrete combined section of tower base of cable-stayed bridge | |
| CN208965392U (en) | A kind of installation latching mechanism of steel plate combination beam and support | |
| CN114214961B (en) | Integral-lowering underwater bearing platform mounting structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |