CN113756351A - Construction method for sinking of non-drainage open caisson - Google Patents

Construction method for sinking of non-drainage open caisson Download PDF

Info

Publication number
CN113756351A
CN113756351A CN202111116079.0A CN202111116079A CN113756351A CN 113756351 A CN113756351 A CN 113756351A CN 202111116079 A CN202111116079 A CN 202111116079A CN 113756351 A CN113756351 A CN 113756351A
Authority
CN
China
Prior art keywords
open caisson
sinking
water injection
construction method
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111116079.0A
Other languages
Chinese (zh)
Inventor
项恒
胡小峰
李红涛
宋艳青
崔炎锋
刘祖新
方晓瑞
罗娟
祝晓迪
李瑞娟
雒慧娟
吕加强
雒超
王红梅
王燕芳
黄世东
李长恩
吕宜霏
贾昀
陈江
李�瑞
王跃华
王振华
秦金勇
王育青
李国清
赵玉珍
陈营营
刘亚琼
武钰鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yellow River Construction Engineering Group Co ltd
Original Assignee
Yellow River Construction Engineering Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yellow River Construction Engineering Group Co ltd filed Critical Yellow River Construction Engineering Group Co ltd
Priority to CN202111116079.0A priority Critical patent/CN113756351A/en
Publication of CN113756351A publication Critical patent/CN113756351A/en
Pending legal-status Critical Current

Links

Classifications

    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00—Caissons; Construction or placing of caissons
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00—Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00—Caissons; Construction or placing of caissons
    • E02D23/08—Lowering or sinking caissons
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00—Caissons; Construction or placing of caissons
    • E02D23/08—Lowering or sinking caissons
    • E02D23/14—Decreasing the skin friction while lowering
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00—Production methods
    • E02D2250/003—Injection of material

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses a construction method for sinking a non-drainage open caisson, which comprises the following steps: an open caisson prefabricating step: firstly surveying a working pit with the diameter of 2.5 meters, pouring and forming a first section of edge foot, a second section of edge foot, a third section of edge foot, a bottom beam and a partition wall of the open caisson by times, then arranging a skid bed under the edge feet by adopting a foot-padding method, arranging a sand bed under the skid, expanding layer by layer, and then pouring and forming the wall of the open caisson. The sinking speed of the open caisson can be accelerated through the step of weighting treatment, the overall processing speed is accelerated, the sinking speed can be further accelerated through the step of assisting sinking of the open caisson, and the phenomenon of deviation is avoided, so that the effect of stable sinking is achieved, and the problem that the sinking quality of the open caisson cannot be guaranteed because the problems of inclination, uneven sedimentation, convex sedimentation and the like are easy to occur in the sinking process due to overlarge water pressure difference between the inside and the outside when the existing open caisson is used in a non-drainage sinking method is solved.

Description

Construction method for sinking of non-drainage open caisson
Technical Field
The invention relates to the technical field of open caisson, in particular to a construction method for sinking an open caisson without draining water.
Background
The open caisson is a well tubular structure, but when the existing open caisson is used in a non-drainage sinking method, the problems of inclination, uneven settlement, convex settlement and the like easily occur in the sinking process due to overlarge water pressure difference between the inside and the outside, so that the sinking quality of the open caisson cannot be guaranteed.
Disclosure of Invention
In order to solve the problems in the background art, the invention aims to provide a construction method for sinking a non-drainage open caisson, which has the advantage of stable sinking and solves the problem that the sinking quality of the open caisson cannot be guaranteed because the existing open caisson is easy to incline, unevenly sink, convexly sink and the like in the sinking process due to overlarge difference between the internal water pressure and the external water pressure when the non-drainage sinking method is used.
In order to achieve the purpose, the invention provides the following technical scheme: a construction method for sinking a non-drainage open caisson comprises the following steps: the open caisson prefabricating method comprises the steps of a) open caisson prefabricating; b) erecting a water injection pipe; step c) applying weight treatment; d) assisting sinking of the open caisson; step e) soil body reinforcement; step f), sealing the concrete bottom;
step a) open caisson prefabrication: firstly surveying a working pit with the diameter of 2.5 meters, pouring and forming a first section of edge foot, a second section of edge foot, a third section of edge foot, a bottom beam and a partition wall of the open caisson by times, then arranging a skid bed course under the edge feet by adopting a foot-padding method, arranging a sand bed course under the skid, expanding layer by layer, and then pouring and forming the wall of the open caisson;
step b) erecting a water injection pipe: water jetting pipes are arranged along the periphery of the open caisson, and water is jetted to soil around the open caisson at high pressure in a sectional water injection mode to cut and soften the soil in the side wall area of the open caisson;
step c) applying weight treatment: placing two crawler grab shovels at the top of the open caisson, respectively arranging the two crawler grab shovels between two buttress piers of two side walls on two sides, and supporting the grab shovels by adopting prefabricated steel movable platforms to realize moving and grabbing soil;
step d), sinking assistance of the open caisson: thixotropic slurry is injected to the outer side of the wall of the open caisson by a slurry pump to assist sinking, and the open caisson is corrected in the sinking assisting process;
step e) soil body reinforcement: after the open caisson is sunk to a designed position, grouting is carried out on the soil outside the open caisson by a water jetting pipe in a retreating type sectional grouting mode, and the soil outside the open caisson is reinforced;
step f) concrete bottom sealing: and after the reinforcement treatment is finished, the crawler grab shovel machine is taken out, and then concrete is injected into the bottom of the open caisson through the grouting pump for bottom sealing.
Preferably, the open caisson is prefabricated in the step a), and the integral prefabrication is performed in a sectional prefabrication mode and needs to be sequentially installed.
Preferably, the water injection pipe is erected in the step b), a plurality of water injection holes are formed in the periphery of the water injection pipe at intervals, a plurality of rows of water injection holes are formed along the length direction of the water injection pipe, the distance between every two adjacent water injection holes is 5-10mm, the distance between every two adjacent water injection holes is 10-15mm, and the diameter of each water injection hole is 1 mm.
Preferably, in the step c), the weight is applied, the hoisting height of the crawler grab shovel is 10m, and the crawler grab shovel works for medium-grade hoisting.
Preferably, in the step d), the open caisson is assisted in sinking, and the mud injected by the mud pump is quantitatively injected according to the size of the outer side of the wall of the open caisson, so that excessive mud injection is avoided.
Preferably, in the step e), the soil body is reinforced, and a grouting pipe is adopted during grouting reinforcement and has certain pressure resistance.
Preferably, in the step f), the concrete bottom sealing is performed, and muddy water glass double grout is sprayed during the bottom sealing, so that the soil body is rapidly solidified and compacted, and the double grout adheres the soil body and the open caisson.
Preferably, in the step f), the concrete is subjected to back cover, and after the cement-water glass double slurry is sprayed, the concrete is subjected to air drying treatment by an air drying device.
Compared with the prior art, the invention has the following beneficial effects:
according to the invention, through the open caisson prefabricating step, the size, the framework and the structure of the open caisson can be more stable, and the phenomenon of offset and inclination can be prevented, through the step of additionally arranging the water jetting pipe, the soil around the open caisson can be softened more, the open caisson can sink conveniently, through the step of applying weight treatment, the sinking speed of the open caisson can be accelerated, the integral processing speed is accelerated, through the open caisson sinking assisting step, the sinking speed can be further accelerated, and the phenomenon of offset can be avoided, through the soil body reinforcing step, the soil body outside the open caisson can be fastened more, and the phenomenon of collapse can be avoided.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The invention provides a construction method for sinking a non-drainage open caisson, which comprises the following steps: the open caisson prefabricating method comprises the steps of a) open caisson prefabricating; b) erecting a water injection pipe; step c) applying weight treatment; d) assisting sinking of the open caisson; step e) soil body reinforcement; step f), sealing the concrete bottom;
step a) open caisson prefabrication: firstly surveying a working pit with the diameter of 2.5 meters, pouring and forming a first section of edge foot, a second section of edge foot, a third section of edge foot, a bottom beam and a partition wall of the open caisson by times, then arranging a skid bed course under the edge feet by adopting a foot-padding method, arranging a sand bed course under the skid, expanding layer by layer, and then pouring and forming the wall of the open caisson;
step b) erecting a water injection pipe: water jetting pipes are arranged along the periphery of the open caisson, and water is jetted to soil around the open caisson at high pressure in a sectional water injection mode to cut and soften the soil in the side wall area of the open caisson;
step c) applying weight treatment: placing two crawler grab shovels at the top of the open caisson, respectively arranging the two crawler grab shovels between two buttress piers of two side walls on two sides, and supporting the grab shovels by adopting prefabricated steel movable platforms to realize moving and grabbing soil;
step d), sinking assistance of the open caisson: thixotropic slurry is injected to the outer side of the wall of the open caisson by a slurry pump to assist sinking, and the open caisson is corrected in the sinking assisting process;
step e) soil body reinforcement: after the open caisson is sunk to a designed position, grouting is carried out on the soil outside the open caisson by a water jetting pipe in a retreating type sectional grouting mode, and the soil outside the open caisson is reinforced;
step f) concrete bottom sealing: and after the reinforcement treatment is finished, the crawler grab shovel machine is taken out, and then concrete is injected into the bottom of the open caisson through the grouting pump for bottom sealing.
The invention is further set in that the open caisson is prefabricated in the step a), the whole prefabricated open caisson adopts a sectional prefabricated mode, and the open caisson is required to be sequentially installed.
The invention is further set as that in the step b), the water injection pipe is erected, a plurality of water injection holes are arranged at intervals around the water injection pipe, a plurality of rows are arranged along the length direction of the water injection pipe, the distance between every two adjacent water injection holes is 5-10mm, the distance between every two adjacent water injection holes is 10-15mm, and the diameter of each water injection hole is 1 mm.
The invention is further set in the step c) to carry out weight application treatment, the hoisting height of the crawler grab shovel machine is 10m, and the crawler grab shovel machine works for medium-grade hoisting.
The invention is further set in the step d) of assisting sinking of the open caisson, and the mud injected by the mud pump is quantitatively injected according to the size of the outer side of the open caisson wall, so that excessive mud injection is avoided.
The invention is further set as that the soil body is reinforced in the step e), and a grouting pipe is adopted during grouting reinforcement and has certain pressure resistance.
The invention is further set in the step f) concrete bottom sealing, and muddy water glass double-slurry is sprayed during bottom sealing, so that the soil body is quickly solidified and compacted, and the double-slurry adheres the soil body and the open caisson.
The invention is further set in that the concrete bottom sealing in the step f) is carried out, and air drying treatment is carried out on the cement glass double-slurry through an air drying device after the cement glass double-slurry is sprayed.
The working principle and the using process of the invention are as follows: firstly surveying a working pit with the diameter of 2.5 meters, pouring and forming a first section of blade foot, a second section of blade foot, a third section of blade foot, a bottom beam and a partition wall of the open caisson by times, then arranging a skid bed course under the blade foot by a foot-laying method, arranging a sand bed course under the skid, expanding layer by layer, then pouring and forming the wall of the open caisson, then arranging water injection pipes along the periphery of the open caisson, spraying water to the soil body around the open caisson at high pressure by adopting a sectional water injection method, cutting and softening the soil body in the side wall area of the open caisson, placing two crawler grab shovels at the top of the open caisson, respectively arranging the two crawler grab shovels between two supporting piers on two side walls, supporting by adopting a prefabricated steel movable platform and realizing moving soil grabbing by adopting a slurry pump to carry out auxiliary sinking, injecting thixotropic slurry to the open caisson at the outer side of the open caisson wall by adopting a slurry pump, rectifying the open caisson in the auxiliary sinking process, sinking the open caisson to the design position, injecting slurry to the soil body outside the open caisson by adopting a sectional retreating grouting mode through the water injection pipes, and (3) reinforcing the soil outside the open caisson, and after the reinforcing treatment is finished, taking out the crawler-type grab shovel machine and then injecting concrete into the bottom of the open caisson through an injection pump to seal the bottom, so that the effect of stable sinking is achieved.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (8)

1. A construction method for sinking a non-drainage open caisson is characterized by comprising the following steps: the method comprises the following steps: the open caisson prefabricating method comprises the steps of a) open caisson prefabricating; b) erecting a water injection pipe; step c) applying weight treatment; d) assisting sinking of the open caisson; step e) soil body reinforcement; step f), sealing the concrete bottom;
step a) open caisson prefabrication: firstly surveying a working pit with the diameter of 2.5 meters, pouring and forming a first section of edge foot, a second section of edge foot, a third section of edge foot, a bottom beam and a partition wall of the open caisson by times, then arranging a skid bed course under the edge feet by adopting a foot-padding method, arranging a sand bed course under the skid, expanding layer by layer, and then pouring and forming the wall of the open caisson;
step b) erecting a water injection pipe: water jetting pipes are arranged along the periphery of the open caisson, and water is jetted to soil around the open caisson at high pressure in a sectional water injection mode to cut and soften the soil in the side wall area of the open caisson;
step c) applying weight treatment: placing two crawler grab shovels at the top of the open caisson, respectively arranging the two crawler grab shovels between two buttress piers of two side walls on two sides, and supporting the grab shovels by adopting prefabricated steel movable platforms to realize moving and grabbing soil;
step d), sinking assistance of the open caisson: thixotropic slurry is injected to the outer side of the wall of the open caisson by a slurry pump to assist sinking, and the open caisson is corrected in the sinking assisting process;
step e) soil body reinforcement: after the open caisson is sunk to a designed position, grouting is carried out on the soil outside the open caisson by a water jetting pipe in a retreating type sectional grouting mode, and the soil outside the open caisson is reinforced;
step f) concrete bottom sealing: and after the reinforcement treatment is finished, the crawler grab shovel machine is taken out, and then concrete is injected into the bottom of the open caisson through the grouting pump for bottom sealing.
2. The construction method for sinking a non-draining open caisson according to claim 1, wherein: step a) open caisson prefabrication, wherein the integral prefabrication adopts a sectional prefabrication mode and is required to be sequentially installed.
3. The construction method for sinking a non-draining open caisson according to claim 1, wherein: step b), erecting a water injection pipe, wherein a plurality of water injection holes are formed in the periphery of the water injection pipe at intervals, a plurality of rows are formed in the length direction of the water injection pipe, the distance between every two adjacent water injection holes is 5-10mm, the distance between every two adjacent water injection holes is 10-15mm, and the diameter of each water injection hole is 1 mm.
4. The construction method for sinking a non-draining open caisson according to claim 1, wherein: and c) applying weight, wherein the hoisting height of the crawler grab shovel machine is 10m, and the crawler grab shovel machine works for medium-grade hoisting.
5. The construction method for sinking a non-draining open caisson according to claim 1, wherein: and d) assisting sinking of the open caisson, wherein the mud injected by the mud pump is quantitatively injected according to the size of the outer side of the open caisson wall, so that excessive mud injection is avoided.
6. The construction method for sinking a non-draining open caisson according to claim 1, wherein: and e) soil body reinforcement, wherein a grouting pipe is adopted during grouting reinforcement, and the grouting pipe has certain pressure resistance.
7. The construction method for sinking a non-draining open caisson according to claim 1, wherein: and f) sealing the bottom with concrete, wherein muddy water glass double grout is sprayed during bottom sealing, so that the soil body is quickly solidified and compacted, and the soil body and the open caisson are adhered by the double grout.
8. The construction method for sinking a non-draining open caisson according to claim 7, wherein: and f) sealing the bottom of the concrete, and performing air drying treatment on the cement glass double-slurry through an air drying device after spraying the cement glass double-slurry.
CN202111116079.0A 2021-09-23 2021-09-23 Construction method for sinking of non-drainage open caisson Pending CN113756351A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111116079.0A CN113756351A (en) 2021-09-23 2021-09-23 Construction method for sinking of non-drainage open caisson

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111116079.0A CN113756351A (en) 2021-09-23 2021-09-23 Construction method for sinking of non-drainage open caisson

Publications (1)

Publication Number Publication Date
CN113756351A true CN113756351A (en) 2021-12-07

Family

ID=78797072

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111116079.0A Pending CN113756351A (en) 2021-09-23 2021-09-23 Construction method for sinking of non-drainage open caisson

Country Status (1)

Country Link
CN (1) CN113756351A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN119737157A (en) * 2025-03-05 2025-04-01 中交第一航务工程局有限公司 Vertical shaft with special-shaped grid and its digging and caisson method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0688348A (en) * 1992-09-07 1994-03-29 Toda Constr Co Ltd Construction method of underground skeleton by submersible method and excavated soil unloading device
JP2012092597A (en) * 2010-10-28 2012-05-17 Daiho Constr Co Ltd Press-in caisson and press-in caisson construction method using the press-in caisson
CN105887907A (en) * 2016-05-03 2016-08-24 上海市基础工程集团有限公司 Open caisson sinking and soil-taking machine for soft soil foundation
CN106480897A (en) * 2015-08-31 2017-03-08 陈飞 Large-scale well-sinking sinking construction method
CN107447770A (en) * 2017-08-25 2017-12-08 上海建工二建集团有限公司 A kind of big open caisson of superelevation and construction method
CN111395374A (en) * 2020-03-31 2020-07-10 广东省建筑工程监理有限公司 Construction method of open caisson
CN112252349A (en) * 2020-09-11 2021-01-22 北京市市政二建设工程有限责任公司 Sinking construction method without drainage for open caisson

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0688348A (en) * 1992-09-07 1994-03-29 Toda Constr Co Ltd Construction method of underground skeleton by submersible method and excavated soil unloading device
JP2012092597A (en) * 2010-10-28 2012-05-17 Daiho Constr Co Ltd Press-in caisson and press-in caisson construction method using the press-in caisson
CN106480897A (en) * 2015-08-31 2017-03-08 陈飞 Large-scale well-sinking sinking construction method
CN105887907A (en) * 2016-05-03 2016-08-24 上海市基础工程集团有限公司 Open caisson sinking and soil-taking machine for soft soil foundation
CN107447770A (en) * 2017-08-25 2017-12-08 上海建工二建集团有限公司 A kind of big open caisson of superelevation and construction method
CN111395374A (en) * 2020-03-31 2020-07-10 广东省建筑工程监理有限公司 Construction method of open caisson
CN112252349A (en) * 2020-09-11 2021-01-22 北京市市政二建设工程有限责任公司 Sinking construction method without drainage for open caisson

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN119737157A (en) * 2025-03-05 2025-04-01 中交第一航务工程局有限公司 Vertical shaft with special-shaped grid and its digging and caisson method

Similar Documents

Publication Publication Date Title
CN103741714B (en) Full-cover excavation top-down construction method for underground engineering
CN101294390B (en) Supporting System and Construction Method of Foundation Pit of Partial Central Island with One Level and One Throw
CN105089061B (en) Ultra-deep foundation pit supporting method
CN109026064B (en) Construction method for large-span multi-arch tunnel with semi-bright and semi-dark
CN114673377B (en) Construction methods of retaining the exterior walls of historic buildings and hollowing out the interior and rebuilding them
CN109610881A (en) A construction method for replacing broken columns with prestressed beams in the renovation of existing multi-storey buildings
CN104594361B (en) A kind of I shape fender post and building enclosure also serve as the construction method of agent structure
CN110159294B (en) Construction method for lengthening open cut tunnel at tunnel junction section of high and steep terrain bridge
CN106968256A (en) Foundation ditch assembled steel trestle construction method
CN110863838B (en) Entry structure and construction method of complex and weak surrounding rock tunnel
CN107190782A (en) A kind of poured band of outer wall of basement structure and its construction method
CN115506807B (en) Support structure and construction method of tunnel crossing karst cave
CN111877382A (en) Underground station building method based on open caisson method
CN106836238A (en) A kind of construction method and its structure for falling the vertical floor support replacement of grade formula deep basal pit
CN113217034A (en) Combined primary supporting structure and construction method thereof
CN109899087A (en) A kind of underground structure and construction method of underground excavation and reverse construction of tunnel column
CN107503362A (en) A kind of compound antiskid piling wall retaining structure and construction method suitable for reservoir stability
CN106480891B (en) A kind of shaft construction method
CN114412509B (en) A support method suitable for large deformation of mudstone tunnels
CN110747904A (en) Structural form and construction method of a highway tunnel biased open hole
CN105386779B (en) The counterfort method of large underground structure is built in shallow embedding rock stratum
CN107119695A (en) Operation frame body for canceling basement exterior wall backfill and construction method
CN109403981B (en) Construction process of main body structure of subway shield well
CN113957887B (en) Pile-wall integrated construction method of core barrel
CN115748462A (en) Construction method for small-radius curve cast-in-place box girder

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20211207

RJ01 Rejection of invention patent application after publication