CN113737988B - A vertical prestressed assembly energy dissipation joint wall structure and its assembly method - Google Patents
A vertical prestressed assembly energy dissipation joint wall structure and its assembly method Download PDFInfo
- Publication number
- CN113737988B CN113737988B CN202111043936.9A CN202111043936A CN113737988B CN 113737988 B CN113737988 B CN 113737988B CN 202111043936 A CN202111043936 A CN 202111043936A CN 113737988 B CN113737988 B CN 113737988B
- Authority
- CN
- China
- Prior art keywords
- vertical
- energy
- wall
- prestressed
- prefabricated wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 230000021715 photosynthesis, light harvesting Effects 0.000 title claims abstract description 36
- 238000000034 method Methods 0.000 title claims abstract description 17
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 78
- 239000010959 steel Substances 0.000 claims abstract description 78
- 230000008878 coupling Effects 0.000 claims abstract description 40
- 238000010168 coupling process Methods 0.000 claims abstract description 40
- 238000005859 coupling reaction Methods 0.000 claims abstract description 40
- 210000002435 tendon Anatomy 0.000 claims abstract description 38
- 239000011150 reinforced concrete Substances 0.000 claims abstract description 21
- 239000011374 ultra-high-performance concrete Substances 0.000 claims description 16
- 239000004570 mortar (masonry) Substances 0.000 claims description 11
- 230000002787 reinforcement Effects 0.000 claims description 9
- 238000009434 installation Methods 0.000 claims description 7
- 239000004567 concrete Substances 0.000 claims description 5
- 238000004873 anchoring Methods 0.000 claims description 3
- 239000004574 high-performance concrete Substances 0.000 claims description 2
- 230000008439 repair process Effects 0.000 abstract description 4
- 238000011084 recovery Methods 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 10
- 238000010276 construction Methods 0.000 description 5
- 230000009471 action Effects 0.000 description 4
- 230000008569 process Effects 0.000 description 3
- 230000007812 deficiency Effects 0.000 description 2
- 230000001739 rebound effect Effects 0.000 description 2
- 230000003313 weakening effect Effects 0.000 description 2
- 230000000712 assembly Effects 0.000 description 1
- 238000000429 assembly Methods 0.000 description 1
- 239000002131 composite material Substances 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/56—Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
- E04B2/562—Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with fillings between the load-bearing elongated members
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/388—Separate connecting elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/58—Connections for building structures in general of bar-shaped building elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/92—Protection against other undesired influences or dangers
- E04B1/98—Protection against other undesired influences or dangers against vibrations or shocks; against mechanical destruction, e.g. by air-raids
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/56—Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
- E04B2/58—Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of metal
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/02—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
- E04C3/20—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of concrete or other stone-like material, e.g. with reinforcements or tensioning members
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/01—Reinforcing elements of metal, e.g. with non-structural coatings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/08—Members specially adapted to be used in prestressed constructions
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/02—Conveying or working-up concrete or similar masses able to be heaped or cast
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H9/00—Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
- E04H9/02—Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
- E04H9/021—Bearing, supporting or connecting constructions specially adapted for such buildings
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Environmental & Geological Engineering (AREA)
- Business, Economics & Management (AREA)
- Emergency Management (AREA)
- Mechanical Engineering (AREA)
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
Abstract
Description
技术领域technical field
本发明涉及建筑技术领域,具体公开了一种竖向预应力装配耗能联肢墙结构及其装配方法。The invention relates to the technical field of construction, and specifically discloses a vertical prestressed assembly energy-consuming joint wall structure and an assembly method thereof.
背景技术Background technique
现浇结构和传统的装配整体式剪力墙结构这两种传统的剪力墙结构形式都需要现场湿作业,墙体及连梁配筋构造复杂,现场工程量大,施工质量难以保证。另外这两种剪力墙结构在大震作用下通过延性损伤耗散地震能量,震后结构的损伤以及结构的残余变形很大,修复成本较高或者无法修复,结构只能被推倒重建,造成巨大的浪费。The cast-in-place structure and the traditional assembled integral shear wall structure both require on-site wet work, the wall and coupling beam reinforcement structure is complex, the on-site engineering volume is large, and the construction quality is difficult to guarantee. In addition, these two shear wall structures dissipate seismic energy through ductile damage under the action of a large earthquake. The damage to the structure after the earthquake and the residual deformation of the structure are very large. The repair cost is high or cannot be repaired. The structure can only be knocked down and rebuilt, resulting in Huge waste.
例如申请号为CN200610045465.4的发明专利就公开了一种组合剪力墙,钢筋混凝土墙体两侧设有钢管混凝土边柱,钢管混凝土边柱由体内浇注有混凝土的钢管构成,钢管与墙体内的水平钢筋焊接成一体。该发明公开的组合剪力墙虽然具有承载力高、受力合理、抗震性能好等特点,特别适用于钢一混凝土混合结构的高层建筑。但是其存在上述需要现场湿作业、工程量大,施工质量难以保证以及震后结构的损伤以及结构的残余变形很大,修复成本较高或者无法修复的不足。因此,针对现有现浇结构和传统的装配整体式剪力墙结构的上述不足,本申请提出了一种竖向预应力装配耗能联肢墙结构,该结构上部结构除首层结构外无需现场湿作业,属于干式连接,节能环保,震后利用竖向预应力筋的回弹作用使结构复位,残余变形很小,损伤集中在节点连接处,主要集中可更换的耗能元件上,震后修复简单快捷,可实现震后结构功能的迅速恢复。For example, the invention patent with the application number of CN200610045465.4 discloses a combined shear wall. The reinforced concrete wall is provided with concrete-filled steel tube side columns on both sides. The horizontal steel bars inside are welded into one. Although the composite shear wall disclosed in the invention has the characteristics of high bearing capacity, reasonable stress and good seismic performance, it is especially suitable for high-rise buildings of steel-concrete mixed structure. However, it has the disadvantages of requiring on-site wet operation, large amount of engineering, difficult to guarantee construction quality, large damage to the structure after the earthquake and large residual deformation of the structure, high repair cost or irreparable. Therefore, in view of the above-mentioned deficiencies of the existing cast-in-place structure and the traditional assembled integral shear wall structure, the present application proposes a vertical prestressed assembled energy-consuming joint wall structure, and the upper structure of the structure does not require the first floor structure. Wet work on site, belongs to dry connection, energy saving and environmental protection. After the earthquake, the rebound effect of vertical prestressed ribs is used to reset the structure, the residual deformation is small, and the damage is concentrated at the node connection, mainly on the replaceable energy-consuming components The post-earthquake repair is simple and quick, and the post-earthquake structural function can be quickly restored.
发明内容SUMMARY OF THE INVENTION
本发明的目的是针对现有现浇结构和传统的装配整体式剪力墙结构上述需要现场湿作业、工程量大,施工质量难以保证以及震后结构的损伤以及结构的残余变形很大,修复成本较高或者无法修复的不足,本申请提出了一种竖向预应力装配耗能联肢墙结构及其装配方法用以解决上述技术问题。The purpose of the present invention is that the existing cast-in-place structure and the traditional assembled integral shear wall structure require on-site wet operation, the engineering volume is large, the construction quality is difficult to guarantee, and the damage of the structure after the earthquake and the residual deformation of the structure are very large. Due to the high cost or the deficiencies that cannot be repaired, the present application proposes a vertical prestressed assembly energy-consuming joint wall structure and an assembly method thereof to solve the above technical problems.
本发明是通过以下技术方案实现的:The present invention is achieved through the following technical solutions:
一种竖向预应力装配耗能联肢墙结构,包括竖向节段预制墙肢总成、钢筋混凝土连梁、竖向无粘结预应力筋、预应力钢棒、连梁端部耗能连接接头总成以及竖向墙肢耗能连接接头;A vertical prestressed assembly energy-consuming coupled limb wall structure, comprising a vertical segmental prefabricated wall limb assembly, a reinforced concrete coupling beam, a vertical unbonded prestressed tendon, a prestressed steel rod, and energy dissipation at the end of the coupling beam Connection joint assembly and vertical wall pier energy dissipation connection joint;
其中,所述竖向节段预制墙肢总成包括底层竖向节段预制墙肢和若干加接层竖向节段预制墙肢,所述底层竖向节段预制墙肢和加接层竖向节段预制墙肢上均预留有一排竖向预应力筋孔洞,且一排竖向预应力筋孔洞沿墙肢宽度方向居中布置,所述底层竖向节段预制墙肢和加接层竖向节段预制墙肢的接缝处设置有超高性能混凝土砂浆垫层;Wherein, the vertical segment prefabricated wall pier assembly includes a bottom vertical segment prefabricated wall pier and a plurality of vertical segment prefabricated wall piers of additional layers, the bottom vertical segment prefabricated wall pier and the addition layer vertical segment A row of vertical prestressed rib holes is reserved on each segmental prefabricated wall pier, and a row of vertical prestressed rib holes is centrally arranged along the width direction of the wall pier. The bottom vertical segmental prefabricated wall pier and the joint layer The joints of the vertical segment prefabricated walls are provided with ultra-high performance concrete mortar cushions;
所述竖向无粘结预应力筋放置在每个竖向预应力筋孔洞内,所述竖向无粘结预应力筋的下端预埋锚固在基础上,上端锚固在最顶层的加接层竖向节段预制墙肢顶部;The vertical unbonded prestressed tendons are placed in each of the vertical prestressed rib holes, the lower ends of the vertical unbonded prestressed tendons are pre-embedded and anchored on the foundation, and the upper ends are anchored on the topmost joint layer. The top of the vertical segment prefabricated pier;
所述竖向耗能墙肢耗能连接接头包括多个设置在墙肢前后侧面的第一耗能垫板以及设置在墙肢左右两端面的第二耗能垫板,多个所述第一耗能垫板沿墙肢宽度方向间隔布置,多个所述第一耗能垫板和第二耗能垫板均贯穿底层竖向节段预制墙肢和加接层竖向节段预制墙肢的接缝处设置,所述第一耗能垫板和第二耗能垫板在与接缝处对应的部位设置有削弱截面;The vertical energy-dissipating wall pier energy-dissipating connection joint includes a plurality of first energy-dissipating pads arranged on the front and rear sides of the wall pier and second energy-dissipating pads arranged on the left and right ends of the wall pier. The energy-dissipating pads are arranged at intervals along the width direction of the wall piers, and a plurality of the first energy-consuming pads and the second energy-dissipating pads all pass through the vertical segment prefabricated wall studs on the ground floor and the vertical segment prefabricated wall studs on the attachment layer. The first energy-dissipating pad and the second energy-dissipating pad are provided with weakened cross-sections at the positions corresponding to the joints;
所述连梁端部耗能连接接头总成包括上部免屈曲T型耗能钢板、槽型钢盖板、下部角钢和下部T型摩擦板,所述上部免屈曲T型耗能钢板设置在槽型钢盖板的下方,且槽型钢盖板的一端与上部免屈曲T型耗能钢板之间通过螺栓相连接,另一端预埋在钢筋混凝土连梁的顶部且与钢筋混凝土连梁的上部纵筋相焊接,所述上部免屈曲T型耗能钢板的翼缘、第二耗能垫板以及加接层竖向节段预制墙肢通过水平设置的预应力钢棒相连接,所述下部T型摩擦板的翼缘预埋在钢筋混凝土连梁的下表面且与混凝土连梁的下部纵筋相焊接,所述下部T型摩擦板的腹板开有两条平行的弧形摩擦孔洞,两个所述下部角钢呈前后对称设置,所述T型摩擦板的腹板设置在两个下部角钢之间且通过螺栓将T型摩擦板与两个下部角钢相连接,两个所述下部角钢、第二耗能垫板以及底层竖向节段预制墙肢也通过水平设置的预应力钢棒相连接。The energy-dissipating connection joint assembly at the end of the coupling beam includes an upper buckling-free T-shaped energy-consuming steel plate, a channel-shaped steel cover plate, a lower angle steel and a lower T-shaped friction plate, and the upper buckling-free T-shaped energy-consuming steel plate is arranged on the channel steel. Below the cover plate, one end of the channel-shaped steel cover plate and the upper buckling-free T-shaped energy-dissipating steel plate are connected by bolts, and the other end is pre-buried on the top of the reinforced concrete coupling beam and is connected with the upper longitudinal reinforcement of the reinforced concrete coupling beam. welding, the flange of the upper buckling-free T-shaped energy-dissipating steel plate, the second energy-dissipating backing plate, and the prefabricated wall piers of the vertical section of the added layer are connected by horizontally arranged prestressed steel bars, and the lower T-shaped friction The flange of the plate is pre-buried on the lower surface of the reinforced concrete coupling beam and welded with the lower longitudinal reinforcement of the concrete coupling beam. The web of the lower T-shaped friction plate has two parallel arc-shaped friction holes. The lower angle steel is symmetrically arranged before and after, the web of the T-shaped friction plate is arranged between the two lower angle steels, and the T-shaped friction plate is connected with the two lower angle steels by bolts, and the two lower angle steels, the second lower angle steel are connected. The energy-dissipating backing plates and the prefabricated wall piers of the vertical segments on the ground floor are also connected by the prestressed steel rods arranged horizontally.
作为上述方案的进一步设置,所述底层竖向节段预制墙肢的底部五分之一面积处设置有超高性能混凝土层,且所述超高性能混凝土层的强度不低于120MPa。As a further arrangement of the above solution, an ultra-high-performance concrete layer is provided at the bottom one-fifth of the area of the bottom vertical segment prefabricated wall, and the strength of the ultra-high-performance concrete layer is not less than 120 MPa.
作为上述方案的进一步设置,所述底层竖向节段预制墙肢和加接层竖向节段预制墙肢接缝处的超高性能混凝土砂浆垫层厚度为10-20mm。As a further arrangement of the above solution, the thickness of the ultra-high performance concrete mortar cushion at the joint of the vertical segment prefabricated wall piers of the bottom layer and the vertical segment prefabricated wall piers of the addition layer is 10-20 mm.
作为上述方案的进一步设置,所述第一耗能垫板和第二耗能垫板的削弱截面为向内凹陷的圆弧口。As a further arrangement of the above solution, the weakened cross-sections of the first energy dissipation pad and the second energy dissipation pad are inwardly concave arc openings.
作为上述方案的进一步设置,所述T型耗能钢板的耗能段上开有大量孔洞,大量孔洞形成了削弱面。As a further arrangement of the above solution, the energy dissipation section of the T-shaped energy-consuming steel plate is provided with a large number of holes, and the large number of holes form a weakening surface.
作为上述方案的进一步设置,所述竖向节段预制墙肢总成的顶部和底部标高分别位于楼层标高处。As a further arrangement of the above solution, the top and bottom elevations of the vertical segment prefabricated wall pier assemblies are respectively located at the floor elevations.
作为上述方案的进一步设置,所述竖向预应力筋孔洞沿墙肢长度方向采用集中布置。As a further arrangement of the above solution, the vertical prestressed rib holes are arranged in a concentrated manner along the length direction of the wall pier.
作为上述方案的进一步设置,所述底层竖向节段预制墙肢和加接层竖向节段预制墙肢上开设的竖向预应力筋孔洞的数量不超过五个。As a further arrangement of the above solution, the number of vertical prestressed tendon holes opened on the bottom vertical segment prefabricated wall pier and the addition layer vertical segment prefabricated wall pier is no more than five.
一种竖向预应力装配耗能联肢墙结构的装配方法,包括如下步骤:An assembly method for a vertical prestressed assembly energy-dissipating joint wall structure, comprising the following steps:
1)基础及底层竖向节段预制墙肢采用现浇;1) The prefabricated wall piers of the foundation and the bottom vertical segment shall be cast-in-place;
2)将竖向无粘结预应力筋预埋在基础底部并穿过底层竖向节段预制墙肢上的竖向预应力筋孔洞;2) Pre-embed the vertical unbonded prestressing tendons at the bottom of the foundation and pass through the vertical prestressing tendon holes on the bottom vertical segment prefabricated wall piers;
3)在底层竖向节段预制墙肢的上部铺设超高性能混凝土砂浆垫层,再将加接层竖向节段预制墙肢就位,竖向无粘结预应力筋穿过加接层竖向节段预制墙肢上预留的竖向预应力筋孔洞,并通过螺栓安装第一耗能垫板,通过水平预应力钢棒安装第二耗能垫板及下部角钢;3) Lay ultra-high-performance concrete mortar cushion on the upper part of the vertical segment prefabricated wall piers on the ground floor, and then place the vertical segment prefabricated wall piers of the joint layer in place, and the vertical unbonded prestressed tendons pass through the joint layer. The vertical prestressed rib holes reserved on the prefabricated wall legs of the vertical segment, and the first energy-dissipating backing plate is installed by bolts, and the second energy-consuming backing plate and the lower angle steel are installed by the horizontal prestressing steel rod;
4)将钢筋混凝土连梁吊装就位,使用螺栓固定下部角钢与下部T型摩擦板的腹板,通过水平预应力钢棒安装上部免屈曲T型耗能钢板及第二耗能垫板,并使用螺栓与槽型钢盖板连接;4) Hoist the reinforced concrete coupling beam in place, use bolts to fix the lower angle steel and the web of the lower T-shaped friction plate, install the upper buckling-free T-shaped energy-consuming steel plate and the second energy-consuming backing plate through the horizontal prestressed steel rod, and Use bolts to connect with channel steel cover;
5)最后完成钢筋混凝土连梁的安装,依次完成上部的剪力墙及连梁的安装,最后张拉并锚固竖向无粘结预应力筋即可。5) Finally, complete the installation of reinforced concrete coupling beams, complete the installation of the upper shear walls and coupling beams in turn, and finally stretch and anchor the vertical unbonded prestressed tendons.
作为上述方案的进一步设置,所述竖向无粘结预应力筋长度超过30m时采用分段张拉、分段锚固的方法进行安装竖向无粘结预应力筋。As a further arrangement of the above scheme, when the length of the vertical unbonded prestressed tendon exceeds 30m, the method of segmental tensioning and segmented anchoring is used to install the vertical unbonded prestressed tendon.
本发明提出的竖向预应力装配耗能联肢墙结构上部结构除首层结构外无需现场湿作业,属于干式连接,节能环保,震后利用竖向预应力筋的回弹作用使结构复位,残余变形很小,损伤集中在节点连接处,主要集中可更换的耗能元件上,震后修复简单快捷,可实现震后结构功能的迅速恢复。The upper structure of the vertical prestressed assembly energy-consuming joint wall structure proposed by the present invention does not require on-site wet operation except for the first layer structure, belongs to dry connection, is energy-saving and environmentally friendly, and uses the rebound effect of the vertical prestressing tendons to reset the structure after the earthquake. , the residual deformation is very small, and the damage is concentrated at the node connection, mainly on the replaceable energy-consuming components.
本发明专利与传统技术相比,具有如下优势:Compared with the traditional technology, the patent of the present invention has the following advantages:
(1)通过竖向无粘结预应力筋实现竖向节段墙肢的拼接,结构具有良好的自复位功能。(1) The splicing of the vertical segmental wall piers is realized by the vertical unbonded prestressed tendons, and the structure has a good self-reset function.
(2)竖向节段墙肢沿墙肢长度和宽度方向安装耗能垫板,增强墙肢的耗能能力和连接性能。(2) Install energy-dissipating pads along the length and width of the vertical segment wall piers to enhance the energy dissipation capacity and connection performance of the wall piers.
(3)采用耗能连梁简化了连梁的抗剪设计,增强了连梁在地震作用下的变形及耗能能力。(3) The use of energy dissipation coupling beams simplifies the shear design of the coupling beams and enhances the deformation and energy dissipation capacity of the coupling beams under earthquake action.
(4)节段预制墙肢的顶部和底部采用超高性能混凝土砂浆,避免了施加预应力以及在地震作用下剪力墙接缝处的破坏,简化了剪力墙接缝部位的配筋设计。(4) The top and bottom of the segmental prefabricated walls are made of ultra-high performance concrete mortar, which avoids the application of prestress and the damage of the shear wall joints under the action of earthquakes, and simplifies the reinforcement design of the shear wall joints. .
(5)采用节段预制墙肢可有效减轻吊装的重量,方便现场施工。(5) The use of segmental prefabricated walls can effectively reduce the weight of hoisting and facilitate on-site construction.
附图说明Description of drawings
为了更清楚地说明本发明实施例的技术方案,下面将对实施例描述所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to illustrate the technical solutions of the embodiments of the present invention more clearly, the following briefly introduces the accompanying drawings used in the description of the embodiments. Obviously, the drawings in the following description are only some embodiments of the present invention. For those of ordinary skill in the art, other drawings can also be obtained from these drawings without any creative effort.
图1为本发明的立体结构示意图;Fig. 1 is the three-dimensional structure schematic diagram of the present invention;
图2为本发明的主视平面结构示意图;Fig. 2 is the front view plan structure schematic diagram of the present invention;
图3为本发明的俯视平面结构示意图;Fig. 3 is the top plan structure schematic diagram of the present invention;
图4为本发明的侧视平面结构示意图;Fig. 4 is the side view plan structure schematic diagram of the present invention;
图5为本发明中墙肢、竖向墙肢耗能连接接头的立体结构示意图;Figure 5 is a schematic three-dimensional structural diagram of a wall pier and a vertical wall pier energy-consuming connection joint in the present invention;
图6为本发明中第一耗能垫板的立体结构示意图;FIG. 6 is a schematic three-dimensional structure diagram of a first energy-consuming pad in the present invention;
图7为本发明中第二耗能垫板的立体结构示意图;7 is a schematic three-dimensional structure diagram of a second energy-consuming pad in the present invention;
图8为本发明中上部免屈曲T型耗能钢板、槽型钢盖板的立体结构示意图;Fig. 8 is the three-dimensional structure schematic diagram of the upper buckling-free T-shaped energy-consuming steel plate and the channel-shaped steel cover plate of the present invention;
图9为本发明中下部角钢的立体结构示意图;Fig. 9 is the three-dimensional structure schematic diagram of middle and lower angle steel of the present invention;
图10为本发明下部T型摩擦板的立体结构示意图。FIG. 10 is a schematic three-dimensional structure diagram of the lower T-shaped friction plate of the present invention.
其中:in:
100-竖向节段预制墙肢总成,101-底层竖向节段预制墙肢,102-加接层竖向节段预制墙肢,103-竖向预应力筋孔洞,104-超高性能混凝土砂浆垫层;100-Vertical segment prefabricated wall pier assembly, 101- Vertical segment prefabricated wall pier on the ground floor, 102-Vertical segment prefabricated wall pier of the connecting layer, 103-Vertical prestressed tendon holes, 104-Super high performance concrete mortar cushion;
200-钢筋混凝土连梁,201-上部纵筋,202-下部纵筋;200-reinforced concrete coupling beam, 201-upper longitudinal reinforcement, 202-lower longitudinal reinforcement;
300-竖向无粘结预应力筋,400-预应力钢棒;300-vertical unbonded prestressed tendons, 400-prestressed steel bars;
500-连梁端部耗能连接接头总成,501-上部免屈曲T型耗能钢板,502-槽型钢盖板,503-下部角钢,504-下部T型摩擦板,5041-弧形摩擦孔洞,505-螺栓;500-connecting beam end energy dissipation connection joint assembly, 501-upper buckling-free T-type energy-dissipating steel plate, 502-channel steel cover plate, 503-lower angle steel, 504-lower T-type friction plate, 5041-arc friction hole , 505-bolt;
600-竖向墙肢耗能连接接头,601-第一耗能垫板,602-第二耗能垫板,603-削弱截面。600-vertical wall column energy dissipation connection joint, 601-first energy dissipation pad, 602-second energy dissipation pad, 603-weakened section.
具体实施方式Detailed ways
为了使本技术领域的人员更好地理解本申请方案,下面将结合本申请实施例中的附图,对本申请实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本申请一部分的实施例,而不是全部的实施例。基于本申请中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都应当属于本申请保护的范围。In order to make those skilled in the art better understand the solutions of the present application, the technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present application. Obviously, the described embodiments are only The embodiments are part of the present application, but not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those of ordinary skill in the art without creative work shall fall within the scope of protection of the present application.
需要说明的是,本申请的说明书和权利要求书及上述附图中的术语″第一″、″第二″等是用于区别类似的对象,而不必用于描述特定的顺序或先后次序。应该理解这样使用的数据在适当情况下可以互换,以便这里描述的本申请的实施例。此外,术语″包括″和″具有″以及他们的任何变形,意图在于覆盖不排他的包含,例如,包含了一系列步骤或单元的过程、方法、系统、产品或设备不必限于清楚地列出的那些步骤或单元,而是可包括没有清楚地列出的或对于这些过程、方法、产品或设备固有的其它步骤或单元。It should be noted that the terms "first", "second" and the like in the description and claims of the present application and the above drawings are used to distinguish similar objects, and are not necessarily used to describe a specific sequence or sequence. It is to be understood that the data so used are interchangeable under appropriate circumstances for the embodiments of the application described herein. Furthermore, the terms "comprising" and "having" and any variations thereof, are intended to cover non-exclusive inclusion, for example, a process, method, system, product or device comprising a series of steps or units is not necessarily limited to those expressly listed Rather, those steps or units may include other steps or units not expressly listed or inherent to these processes, methods, products or devices.
需要说明的是,在不冲突的情况下,本申请中的实施例及实施例中的特征可以相互组合。下面将参考附图1~10,并结合实施例来详细说明本申请公开的竖向预应力装配耗能联肢墙结构。It should be noted that the embodiments in the present application and the features of the embodiments may be combined with each other in the case of no conflict. The vertical prestressed assembly energy-dissipating joint wall structure disclosed in the present application will be described in detail below with reference to Figs.
实施例1Example 1
本实施例1提出了一种竖向预应力装配耗能联肢墙结构,其主体结构主要包括竖向节段预制墙肢总成100、钢筋混凝土连梁200、竖向无粘结预应力筋300、预应力钢棒400、连梁端部耗能连接接头总成500以及竖向墙肢耗能连接接头600。This embodiment 1 proposes a vertical prestressed assembled energy-consuming joint wall structure, the main structure of which mainly includes a vertical segment prefabricated wall
在设置时将竖向节段预制墙肢总成100的顶部和底部标高分别位于楼层标高处。其中,竖向节段预制墙肢总成100包括底层竖向节段预制墙肢101和若干加接层竖向节段预制墙肢102,底层竖向节段预制墙肢101和加接层竖向节段预制墙肢102上均预留有一排竖向预应力筋孔洞103,具体设置时一排竖向预应力筋孔洞103的数量不超过五个,并且一排竖向预应力筋孔洞103沿墙肢宽度方向居中布置,同时竖向预应力筋孔洞沿墙肢长度方向采用集中布置。When setting, the top and bottom elevations of the vertical segment prefabricated
在底层竖向节段预制墙肢101和加接层竖向节段预制墙肢102的接缝处设置有超高性能混凝土砂浆垫层104,并且该超高性能混凝土砂浆垫层104厚度为10-20mm。另外还在底层竖向节段预制墙肢101的底部五分之一面积处设置有超高性能混凝土层,并且超高性能混凝土层的强度不低于120MPa。An ultra-high performance
竖向无粘结预应力筋300放置在每个竖向预应力筋孔洞内,竖向无粘结预应力筋300的下端预埋锚固在基础上,上端锚固在最顶层的加接层竖向节段预制墙肢102顶部,并且当竖向节段预制墙肢总成100的高度以及竖向无粘结预应力筋300长度超过30m时采用分段张拉、分段锚固的方法进行安装竖向无粘结预应力筋300。The vertical unbonded
竖向耗能墙肢耗能连接接头600包括多个设置在墙肢前后侧面的第一耗能垫板601以及设置在墙肢左右两端面的第二耗能垫板602,多个第一耗能垫板601沿墙肢宽度方向间隔布置,多个第一耗能垫板601和第二耗能垫板602均贯穿底层竖向节段预制墙肢101和加接层竖向节段预制墙肢102的接缝处设置,第一耗能垫板601和第二耗能垫板602在与接缝处对应的部位设置有削弱截面603,并且第一耗能垫板601和第二耗能垫板602的削弱截面603为向内凹陷的圆弧口,上述结构的设置使得此段能耗垫板形成了耗能段。The vertical energy-consuming wall pier energy-consuming connection joint 600 includes a plurality of first energy-consuming
连梁端部耗能连接接头总成500包括上部免屈曲T型耗能钢板501、槽型钢盖板502、下部角钢503和下部T型摩擦板504。其中上部免屈曲T型耗能钢板501的宽度比槽型钢盖板502的腹板宽度小,并且T型耗能钢板501的耗能段上开有大量孔洞5011,大量孔洞形成了削弱面。上部免屈曲T型耗能钢板501设置在槽型钢盖板502的下方,并且槽型钢盖板502的一端与上部免屈曲T型耗能钢板501之间通过螺栓505相连接,另一端预埋在钢筋混凝土连梁200的顶部且与钢筋混凝土连梁的上部纵筋201以及部分箍筋相焊接。The coupling beam end energy dissipation connection
上部免屈曲T型耗能钢板501的翼缘、第二耗能垫板602以及加接层竖向节段预制墙肢102通过水平设置的预应力钢棒400相连接。下部T型摩擦板504的翼缘预埋在钢筋混凝土连梁200的下表面且与混凝土连梁的下部纵筋202以及部分箍筋相焊接,下部T型摩擦板504的腹板开有两条平行的弧形摩擦孔洞5041。两个下部角钢503呈前后对称设置,T型摩擦板504的腹板设置在两个下部角钢503之间且通过螺栓将T型摩擦板504与两个下部角钢503相连接,两个下部角钢503、第二耗能垫板602以及底层竖向节段预制墙肢101也通过水平设置的预应力钢棒400相连接。The flange of the upper buckling-free T-shaped energy-dissipating
本实施例1设计的竖向预应力装配耗能联肢墙结构在随着结构受到的荷载及变形的增大,结构的受力过程分为三个节段。The vertical prestressed assembled energy-dissipating joint wall structure designed in this Example 1 is divided into three segments in the stress process of the structure as the load and deformation of the structure increase.
第一阶段:结构整体处于弹性状态,连梁端部耗能装置未启动,即连梁端部下部摩擦装置未发生滑动,上部T型耗能段还处于弹性;The first stage: the overall structure is in an elastic state, the energy dissipation device at the end of the coupling beam is not activated, that is, the friction device at the lower part of the end of the coupling beam does not slide, and the upper T-shaped energy dissipation section is still elastic;
第二阶段:连梁端部耗能装置被激活,即连梁端部下部摩擦装置发生滑动产生耗能,上部T型耗能段开始屈服;The second stage: the energy dissipation device at the end of the coupling beam is activated, that is, the friction device at the lower end of the coupling beam slides to generate energy dissipation, and the upper T-shaped energy dissipation section begins to yield;
第三阶段:当下部摩擦装置达到设计变形限值时,剪力墙承担更多的荷载,剪力墙墙肢接缝处张开,耗能垫板开始屈服耗能;The third stage: when the lower friction device reaches the design deformation limit, the shear wall bears more loads, the joints of the shear wall piers open, and the energy dissipation pad begins to yield and consume energy;
第四阶段:卸载后,在预应力筋的回弹力作用下,结构恢复到原来的位置,残余变形较小,仅对屈服耗能装置进行修复更换即可.The fourth stage: after unloading, under the action of the resilience of the prestressed tendons, the structure returns to its original position, and the residual deformation is small, and only the yield energy dissipation device can be repaired and replaced.
实施例2Example 2
实施例2公开了一种竖向预应力装配耗能联肢墙结构的装配方法,包括如下步骤:Embodiment 2 discloses an assembly method for a vertical prestressed assembly of an energy-consuming joint wall structure, comprising the following steps:
步骤一:基础及底层竖向节段预制墙肢101采用现浇;Step 1: Cast-in-place prefabricated
步骤二:将竖向无粘结预应力筋300预埋在基础底部并穿过底层竖向节段预制墙肢101上的竖向预应力筋孔洞103;Step 2: Pre-embed the vertical
步骤三:在底层竖向节段预制墙肢101的上部铺设超高性能混凝土砂浆垫层104,再将加接层竖向节段预制墙肢102就位,竖向无粘结预应力筋300穿过加接层竖向节段预制墙肢102上预留的竖向预应力筋孔洞103,并通过螺栓安装第一耗能垫板601,通过水平预应力钢棒400安装第二耗能垫板602及下部角钢10;Step 3: Lay the ultra-high performance
步骤四:将钢筋混凝土连梁200吊装就位,使用螺栓固定下部角钢503与下部T型摩擦板504的腹板,通过水平预应力钢棒400安装上部免屈曲T型耗能钢板501及第二耗能垫板602,并使用螺栓与槽型钢盖板502连接;Step 4: Lift the reinforced
步骤五:最后完成钢筋混凝土连梁200的安装,依次完成上部的剪力墙及连梁的安装,最后张拉并锚固竖向无粘结预应力筋300即可。Step 5: Finally, the installation of the reinforced
以上仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present invention shall be included in the protection scope of the present invention. Inside.
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202111043936.9A CN113737988B (en) | 2021-09-07 | 2021-09-07 | A vertical prestressed assembly energy dissipation joint wall structure and its assembly method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202111043936.9A CN113737988B (en) | 2021-09-07 | 2021-09-07 | A vertical prestressed assembly energy dissipation joint wall structure and its assembly method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN113737988A CN113737988A (en) | 2021-12-03 |
| CN113737988B true CN113737988B (en) | 2022-05-10 |
Family
ID=78736557
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202111043936.9A Active CN113737988B (en) | 2021-09-07 | 2021-09-07 | A vertical prestressed assembly energy dissipation joint wall structure and its assembly method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN113737988B (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN114622481B (en) * | 2022-03-31 | 2023-05-05 | 中冶集团武汉勘察研究院有限公司 | Double-column type self-resetting pier structure with buckling restrained brace and construction method thereof |
Family Cites Families (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102852244B (en) * | 2012-04-27 | 2014-10-29 | 中国矿业大学 | Detachable self-resetting type energy-dissipation coupling beam |
| CN107299698A (en) * | 2017-06-22 | 2017-10-27 | 同济大学 | A kind of assembled with concealed bracings can recover function Coupled Shear Wall structural system |
| CN108385868B (en) * | 2018-01-24 | 2019-07-26 | 南通蓝科减震科技有限公司 | A kind of energy dissipating coupled shear walls |
| CN108468397B (en) * | 2018-04-20 | 2019-09-03 | 青岛理工大学 | Prefabricated self-restoring energy-dissipating double steel plate slotted shear wall structure |
| CN110080426A (en) * | 2019-04-16 | 2019-08-02 | 浙江科技学院 | Band easily resets the Self-resetting Coupled Shear Wall structure and construction method of replaceable coupling beam |
-
2021
- 2021-09-07 CN CN202111043936.9A patent/CN113737988B/en active Active
Also Published As
| Publication number | Publication date |
|---|---|
| CN113737988A (en) | 2021-12-03 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN112538898B (en) | Self-resetting shearing-constraint buckling damage controllable assembly type beam-column joint | |
| CN208501878U (en) | A kind of Self-resetting prefabrication and assembly construction frame structure interior joint | |
| CN114592436B (en) | Pier capping beam lower support system and construction method thereof | |
| CN216740039U (en) | Self-resetting fabricated composite structure beam column side node with floor | |
| CN107386435A (en) | The assembled of prestressed node connection can recover function steel frame support system | |
| CN104727441A (en) | Prestress assembled concrete beam column joint structure and construction method thereof | |
| CN108978856B (en) | A prefabricated honeycomb beam-slab structure system | |
| CN104179249A (en) | Assembled composite-structure earthquake-resistant wall and assembly method thereof | |
| CN207017483U (en) | The full precast shear wall structural system of regenerative steel skeleton | |
| CN112196098A (en) | Dry-type connection assembly type reinforced concrete frame structure with BRB obliquely and X-shaped arrangement | |
| CN110468987A (en) | A New Buckling-Resistant Bracing-RC Frame with Replaceable Connecting Nodes | |
| CN115653085A (en) | Detachable prefabricated concrete frame structure system | |
| CN111962659A (en) | Prefabricated assembled is from restoring to throne frame overall structure | |
| CN102776829A (en) | Steel pipe concrete combined truss bridge | |
| CN110106985A (en) | A kind of prefabricated assembled SRC column-girder steel cross combined joint | |
| CN113737988B (en) | A vertical prestressed assembly energy dissipation joint wall structure and its assembly method | |
| CN111926690A (en) | Novel pier is assembled in prefabrication | |
| CN216007260U (en) | Rigid connection joint of steel beam and concrete column | |
| CN116043997B (en) | A seismic toughness assembled concrete frame structure and construction method thereof | |
| CN219431008U (en) | Assembled special-shaped column steel frame-supporting structure system capable of recovering functions | |
| CN111622348A (en) | Prestressed self-resetting concrete truss structure and assembling method | |
| CN111424847A (en) | Self-resetting connecting node of steel tube bundle combined shear wall and steel beam | |
| CN116044000B (en) | Assembled self-resetting concrete frame node with high energy consumption and high robustness | |
| CN112095798A (en) | Super high-rise double-layer super large cantilever steel structure | |
| CN113235756B (en) | Assembled eccentric support hinged energy consumption frame system and construction method thereof |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |