CN113572179A - 一种基于雷击概率的储能与负荷功率协调控制方法 - Google Patents
一种基于雷击概率的储能与负荷功率协调控制方法 Download PDFInfo
- Publication number
- CN113572179A CN113572179A CN202111112760.8A CN202111112760A CN113572179A CN 113572179 A CN113572179 A CN 113572179A CN 202111112760 A CN202111112760 A CN 202111112760A CN 113572179 A CN113572179 A CN 113572179A
- Authority
- CN
- China
- Prior art keywords
- power
- energy storage
- load
- storage system
- lightning stroke
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000004146 energy storage Methods 0.000 title claims abstract description 146
- 208000025274 Lightning injury Diseases 0.000 title claims abstract description 71
- 238000000034 method Methods 0.000 title claims abstract description 29
- 230000005611 electricity Effects 0.000 claims abstract description 11
- 230000001105 regulatory effect Effects 0.000 claims abstract description 9
- 230000003247 decreasing effect Effects 0.000 claims description 9
- 230000001276 controlling effect Effects 0.000 claims description 8
- 230000008859 change Effects 0.000 claims description 3
- 230000005540 biological transmission Effects 0.000 description 3
- 230000000694 effects Effects 0.000 description 3
- XAGFODPZIPBFFR-UHFFFAOYSA-N aluminium Chemical compound [Al] XAGFODPZIPBFFR-UHFFFAOYSA-N 0.000 description 2
- 229910052782 aluminium Inorganic materials 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 2
- 230000007123 defense Effects 0.000 description 2
- OKTJSMMVPCPJKN-UHFFFAOYSA-N Carbon Chemical compound [C] OKTJSMMVPCPJKN-UHFFFAOYSA-N 0.000 description 1
- 229910000831 Steel Inorganic materials 0.000 description 1
- 229910052799 carbon Inorganic materials 0.000 description 1
- 239000004020 conductor Substances 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000004973 liquid crystal related substance Substances 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Images
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/28—Arrangements for balancing of the load in a network by storage of energy
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06312—Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/007—Arrangements for selectively connecting the load or loads to one or several among a plurality of power lines or power sources
- H02J3/0075—Arrangements for selectively connecting the load or loads to one or several among a plurality of power lines or power sources for providing alternative feeding paths between load and source according to economic or energy efficiency considerations, e.g. economic dispatch
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/12—Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
- H02J3/14—Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load by switching loads on to, or off from, network, e.g. progressively balanced loading
- H02J3/144—Demand-response operation of the power transmission or distribution network
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/28—Arrangements for balancing of the load in a network by storage of energy
- H02J3/32—Arrangements for balancing of the load in a network by storage of energy using batteries with converting means
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2203/00—Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
- H02J2203/10—Power transmission or distribution systems management focussing at grid-level, e.g. load flow analysis, node profile computation, meshed network optimisation, active network management or spinning reserve management
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2203/00—Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
- H02J2203/20—Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B70/00—Technologies for an efficient end-user side electric power management and consumption
- Y02B70/30—Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
- Y02B70/3225—Demand response systems, e.g. load shedding, peak shaving
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E40/00—Technologies for an efficient electrical power generation, transmission or distribution
- Y02E40/70—Smart grids as climate change mitigation technology in the energy generation sector
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S20/00—Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
- Y04S20/20—End-user application control systems
- Y04S20/222—Demand response systems, e.g. load shedding, peak shaving
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Power Engineering (AREA)
- Economics (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Theoretical Computer Science (AREA)
- Marketing (AREA)
- Health & Medical Sciences (AREA)
- General Physics & Mathematics (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- Public Health (AREA)
- Game Theory and Decision Science (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Primary Health Care (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
一种基于雷击概率的储能与负荷功率协调控制方法,通过雷击概率的实时预报,实时调整储能、可调负荷的输出功率。降低雷电存在区域电网同外部电网的联系,即使发生雷击事故,也会降低雷击事故对外部电网的影响,同时也能降低雷电存在区域由于雷击带来的经济损失。为了保证用户用电的满意度,在雷击概率存在的情况下,优先根据雷击概率调节储能系统输出功率,其次再调节可调负荷的功率,起到了潮流转移的目的。本发明在考虑储能调节成本及可调负荷调控的功率补偿成本的基础上,建立了储能输出功率、可调负荷调节功率同区域内雷击概率大小的关系,进而可根据雷击概率的大小对储能系统、可调负荷的功率进行实时调整,有利于降低雷击事故带来的损失。
Description
技术领域
本发明属于电力系统动态防雷技术领域,具体涉及一种基于雷击概率的储能与负荷功率协调控制方法。
背景技术
目前在电力系统防雷领域,主要是采用被动的防雷措施,比如说安装避雷针、避雷线等。这些措施虽可以降低雷击的风险,却是从单一设备的防雷保护出发,无法发挥系统的主动调控能力。传统的防雷措施无法发挥系统主动性,当存在雷击线路概率的时候,系统内只能被动地寄希望于“避雷针”、“避雷线”等装置,没有其他任何主动防御控制措施。因此,传统的防雷措施较为被动。
近年来,动态防雷技术逐渐发展起来,现有技术1(CN110311377B)公开了雷电气候下的源网荷储控制和负荷柔性投切方法,但是并未提供根据雷击概率进行储能和负荷功率的实时调整的具体方法;现有技术2(CN112467740B)公开了基于雷电预警的重要输电通道雷击主动防护方法,但该发明是通过重要输电通道潮流转移对输电通道雷击进行主动防护,并未考虑储能调节成本及可调负荷调控的功率补偿成本来建立储能输出功率、可调负荷调节功率同区域内雷击概率关系,其中储能设备及可调负荷是潮流调整的重点对象,能进一步提高系统防雷的主动性。
发明内容
为解决现有技术中存在的不足,本发明的目的在于,提供一种基于雷击概率的储能与负荷功率协调控制方法。
本发明采用如下的技术方案:
一种基于雷击概率的储能与负荷功率协调控制方法包括以下步骤:
步骤1,对于当前时间间隔进行雷电概率预报数值的采集,当雷电概率预报数值时,进入步骤2;否则采集下一个时间间隔雷电预报概率,重复本步骤; 表示能进行储能及负荷功率调控的最小雷电概率预报数值;所述时间间隔为雷电概率预报周期,等同于储能调控周期,单位为小时;
步骤2,确定储能系统的短时调度成本损耗与可控负荷的负荷调节功率补偿成本函数;
步骤3,建立基于雷击概率的储能功率控制模型;
步骤4,建立基于雷击概率的可调负荷功率控制模型并对可调负荷调节功率进行调整,完成后返回步骤1对下一个时间间隔进行雷电概率预报数值采集以及储能与负荷功率协调控制。
在步骤2中,所述储能系统的短时调度成本损耗满足以下关系式:
其中,为储能系统的短时调度成本损耗,单位为元;为由于充放电电流带来的损耗成本,单价单位为元/(kW)2h,为储能系统的循环次数,单位为次;为储能系统实际功率,单位为kW;为储能系统的投资成本,单位为元/kWh;为雷电概率预报周期,等同于储能调控周期,单位是小时;为储能系统的效率。
在步骤2中,可控负荷的负荷调节功率补偿成本函数为:
、分别为可控负荷功率增加和降低时的用户调节负荷的意愿参数,两者均大于0、小于1,数值越大,表示用户增加负荷功率和降低负荷功率的意愿越强;对于对系统功率负荷调整无需求的行业和用户,和的值为0;对于使用电解铝负荷的行业,因其负荷功率调节容量比正常行业大,和的值为0.5;对于可以随时调节负荷功率的其他行业和用户,和的值大于0.5小于1;
步骤3包括以下步骤:
步骤3.1,确定不考虑储能系统进行功率调控时,系统由于雷击带来的可能损失;
步骤3.2,确定储能系统进行功率调控后,系统由于雷击带来的功率损失;
步骤3.4,依据储能系统的运行约束对储能系统输出功率进行调整。
步骤3.1中确定不考虑储能系统进行功率调控时,系统由于雷击带来的可能损失满足以下关系式:
步骤3.2中储能系统进行功率调控后储能系统由于雷击带来的功率损失满足以下关系式:
在步骤3.3中,储能功率调控前后的损失差值满足以下关系式:
在步骤3.4中,所述储能系统的运行约束为:
其中,SOC min、SOC max分别为储能系统运行所允许的荷电状态最小值和最大值;SOC(t)为储能系统实际的荷电状态;P bamin和P bamax分别为储能系统运行所允许的最小功率和最大功率,P bamin<0,P bamax>0;为储能系统的实际功率;
考虑上述约束后,对储能系统的输出功率的调整方法为:
步骤4包括以下步骤:
步骤4.1,确定储能系统参与功率调控,负荷不进行功率调控时,系统由于雷击带来的可能损失;
步骤4.2,确定储能系统和可控负荷均进行功率调控后储能系统由于雷击带来的可能损失;
步骤4.4,对可调负荷调节功率进行调控。
在步骤4.1中,储能系统参与功率调控,负荷不进行功率调控时,系统由于雷击带来的可能损失满足以下关系式:
在步骤4.2中,储能系统和可控负荷均进行功率调控后储能系统由于雷击带来的可能损失满足以下关系式:
在步骤4.3中,可控负荷调控前后由于雷击带来的可能损失差值函数满足以下关系式:
在步骤4.4中,可调负荷调节功率进行调控的方法为:
本发明的有益效果在于,与现有技术相比,在雷击风险存在的情况下,本发明:
1,能够调控储能装置、可调负荷的功率等,参与系统调整,进一步提高系统防雷的主动性。
2,本发明针对雷电条件下,建立了储能系统及可控负荷功率与雷击概率之间的关系,进而可以根据雷击概率进行储能和负荷功率的实时调整,提高了系统在雷电条件下的主动防御能力,降低雷击事件对不存在雷电区域电网的影响和存在雷电地区的可能损失。
3,本发明还在考虑储能调节成本及可调负荷调控的功率补偿成本的基础上,建立了储能输出功率、可调负荷调节功率同区域内雷击概率大小的关系,进而可根据雷击概率的大小对储能系统、可调负荷的功率进行实时调整,降低雷电存在区域电网同外部电网之间的联系,有利于降低雷击事故对系统带来的危害。
附图说明
图1是本发明一种基于雷击概率的储能与负荷功率协调控制方法的流程图。
具体实施方式
下面结合附图对本申请作进一步描述。以下实施例仅用于更加清楚地说明本发明的技术方案,而不能以此来限制本申请的保护范围。
图1为本发明一种基于雷击概率的储能与负荷功率协调控制方法的流程图,具体包括以下内容:
步骤2,确定储能系统的短时调度成本损耗与可控负荷的负荷调节功率补偿成本函数。
储能的调控成本一方面取决于储能的循环次数,另一方面,放电电流也会增加电池内阻,在考虑着两方面的条件下,可以用下式来确定储能系统的短时调度成本损耗。
其中,为储能系统的短时调度成本损耗,单位为元;为由于充放电电流带来的损耗成本,单价单位为元/(kW)2h,为储能系统的循环次数,单位为次;为储能系统实际功率,单位为kW;为储能系统的投资成本,单位为元/kWh;为雷电概率预报周期,等同于储能调控周期,单位是小时;为储能系统的效率。
可控负荷的负荷调节功率补偿成本函数满足以下关系式:
可控负荷的负荷调节功率补偿成本函数为:
本领域的技术人员可根据实际行业特点、用户特点以及用户负荷特性设定意愿参数;对于对系统功率负荷调整无需求的行业和用户,和的值为0,比如钢铁厂等行业,一般情况下不会按照系统调度调整可控负荷功率;对于使用电解铝负荷的行业,因其负荷功率调节容量比正常行业大,和的值为0.5;对于可以随时调节负荷功率的其他行业和用户,和的值大于0.5小于1,在本实施例中,农村居民负荷用电基本为三级负荷,可以进行短时停电,因此和的值为0.8;
步骤3,建立基于雷击概率的储能功率控制模型。
为了保证用户用电的满意度,优先考虑采用储能设备进行功率调控,承担有雷电概率区域内部分负荷功率。
步骤3.1,确定不考虑储能系统进行功率调控时,系统由于雷击带来的可能损失。
储能不参与调控时,雷击带来的可能损失为:
步骤3.2,确定储能系统进行功率调控后系统由于雷击带来的可能功率损失。
储能功率调控后,储能系统承担一部分功率,此时雷击带来的可能损失为:
储能功率调控前后的期望差值满足以下关系式:
步骤3.4,依据储能系统的运行约束对储能系统输出功率进行调整。
其中,SOC min、SOC max分别为储能系统运行所允许的荷电状态最小值和最大值;SOC(t)为储能系统实际的荷电状态;P bamin和P bamax分别为储能系统运行所允许的最小功率和最大功率,P bamin<0,P bamax>0;为储能系统的实际功率,此文中,因需放电,所以>0。
考虑上述约束后,可得到储能系统的输出功率如下式所示。
步骤4,建立基于雷击概率的可调负荷功率控制模型并对可调负荷调节功率进行调整,完成后返回步骤1对下一个时间间隔进行雷电概率预报数值采集以及储能与负荷功率协调控制。
可调负荷作为一种虚拟储能,也能够起到类似于储能的效果。在储能参与调控的前提下,还可以调控负荷功率,进一步提高系统主动性,降低雷电概率存在区域与外部电网之间的联系,进一步降低雷电带来的可能损失。
步骤4.1,确定储能系统参与功率调控,负荷不进行功率调控时,系统由于雷击带来的可能损失。
蓄电池参与调控、负荷不参与调控的情况下,由于雷击带来的功率损失可有下式确定:
步骤4.2,确定储能系统和可控负荷均进行功率调控后系统由于雷击带来的可能损失。
在负荷参与调控后,由于雷击带来的可能损失,可以由下式计算:
步骤4.3,确定负荷功率调节量的最佳值。
可控负荷调控前后由于雷击带来的可能损失差值函数可用下式表示:
显然,根据可控负荷调控前后由于雷击带来的可能损失差值函数,可以求得负荷功率调节量的最佳值,可用下式表示:
此时,可调负荷参与调节后可使雷击造成的可能损失进一步降低。
步骤4.4,根据负荷功率的调控限值对可调负荷调节功率进行调整。
此时,即可以确定可调负荷调节功率的最优值。
本发明申请人结合说明书附图对本发明的实施示例做了详细的说明与描述,但是本领域技术人员应该理解,以上实施示例仅为本发明的优选实施方案,详尽的说明只是为了帮助读者更好地理解本发明精神,而并非对本发明保护范围的限制,相反,任何基于本发明的发明精神所作的任何改进或修饰都应当落在本发明的保护范围之内。
Claims (13)
1.一种基于雷击概率的储能与负荷功率协调控制方法,其特征在于,所述方法包括:
步骤1,对于当前时间间隔进行雷电概率预报数值的采集,当雷电概率预报数值时,进入步骤2;否则采集下一个时间间隔雷电预报概率,重复本步骤;表示能进行储能及负荷功率调控的最小雷电概率预报数值;所述时间间隔为雷电概率预报周期,等同于储能调控周期,单位为小时;
步骤2,确定储能系统的短时调度成本损耗与可控负荷的负荷调节功率补偿成本函数;
步骤3,建立基于雷击概率的储能功率控制模型;
步骤4,建立基于雷击概率的可调负荷功率控制模型并对可调负荷调节功率进行调整,完成后返回步骤1对下一个时间间隔进行雷电概率预报数值采集以及储能与负荷功率协调控制。
Priority Applications (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111112760.8A CN113572179B (zh) | 2021-09-23 | 2021-09-23 | 一种基于雷击概率的储能与负荷功率协调控制方法 |
PCT/CN2021/139905 WO2023045145A1 (zh) | 2021-09-23 | 2021-12-21 | 一种基于雷击概率的储能与负荷功率协调控制方法 |
US17/686,417 US11444476B1 (en) | 2021-09-23 | 2022-03-04 | Lightning strike probability-based coordinated power control method for energy storage system and load |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111112760.8A CN113572179B (zh) | 2021-09-23 | 2021-09-23 | 一种基于雷击概率的储能与负荷功率协调控制方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113572179A true CN113572179A (zh) | 2021-10-29 |
CN113572179B CN113572179B (zh) | 2022-01-25 |
Family
ID=78174144
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202111112760.8A Active CN113572179B (zh) | 2021-09-23 | 2021-09-23 | 一种基于雷击概率的储能与负荷功率协调控制方法 |
Country Status (2)
Country | Link |
---|---|
CN (1) | CN113572179B (zh) |
WO (1) | WO2023045145A1 (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114977175A (zh) * | 2022-04-27 | 2022-08-30 | 国网江苏省电力有限公司苏州供电分公司 | 一种雷雨风光储一体化电动车充电站响应系统及方法 |
CN115276062A (zh) * | 2022-07-22 | 2022-11-01 | 国网江苏省电力有限公司苏州供电分公司 | 一种基于雷击概率的风储联合系统功率两层调控方法与系统 |
CN115409427A (zh) * | 2022-10-28 | 2022-11-29 | 国网江西省电力有限公司供电服务管理中心 | 居民负荷可用调节容量多状态的评估方法及装置 |
WO2023045145A1 (zh) * | 2021-09-23 | 2023-03-30 | 国网江苏省电力有限公司苏州供电分公司 | 一种基于雷击概率的储能与负荷功率协调控制方法 |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112467740A (zh) * | 2021-01-29 | 2021-03-09 | 国网江苏省电力有限公司苏州供电分公司 | 一种基于雷电预警的重要输电通道雷击主动防护方法 |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20150222118A1 (en) * | 2012-09-14 | 2015-08-06 | Nec Corporation | Power transmission and distribution system, controller, router, power transmission and distribution method, and non-transitory computer readable medium storing program |
CN107732960A (zh) * | 2017-09-18 | 2018-02-23 | 国网甘肃省电力公司电力科学研究院 | 微电网储能系统容量优化配置方法 |
CN109858668B (zh) * | 2018-12-21 | 2021-06-08 | 国网江苏省电力有限公司苏州供电分公司 | 一种雷电气候下电力负荷区域协调预测方法 |
CN112801428B (zh) * | 2021-04-08 | 2021-07-13 | 国网江苏省电力有限公司苏州供电分公司 | 一种基于概率预警的落雷损失预防控制方法 |
CN113572179B (zh) * | 2021-09-23 | 2022-01-25 | 国网江苏省电力有限公司苏州供电分公司 | 一种基于雷击概率的储能与负荷功率协调控制方法 |
-
2021
- 2021-09-23 CN CN202111112760.8A patent/CN113572179B/zh active Active
- 2021-12-21 WO PCT/CN2021/139905 patent/WO2023045145A1/zh unknown
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112467740A (zh) * | 2021-01-29 | 2021-03-09 | 国网江苏省电力有限公司苏州供电分公司 | 一种基于雷电预警的重要输电通道雷击主动防护方法 |
Non-Patent Citations (2)
Title |
---|
IMAN SANJARI等: "A new fuzzy model for investigating the effects of lightning on the risk-based self-scheduling strategy in a smart grid", 《ELECTRICAL POWERANDENERGYSYSTEMS》 * |
方家琨等: "含风电-SMES的电力系统暂态稳定概率评估", 《电力系统保护与控制》 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2023045145A1 (zh) * | 2021-09-23 | 2023-03-30 | 国网江苏省电力有限公司苏州供电分公司 | 一种基于雷击概率的储能与负荷功率协调控制方法 |
CN114977175A (zh) * | 2022-04-27 | 2022-08-30 | 国网江苏省电力有限公司苏州供电分公司 | 一种雷雨风光储一体化电动车充电站响应系统及方法 |
CN114977175B (zh) * | 2022-04-27 | 2024-08-02 | 国网江苏省电力有限公司苏州供电分公司 | 一种雷雨风光储一体化电动车充电站响应系统及方法 |
CN115276062A (zh) * | 2022-07-22 | 2022-11-01 | 国网江苏省电力有限公司苏州供电分公司 | 一种基于雷击概率的风储联合系统功率两层调控方法与系统 |
CN115276062B (zh) * | 2022-07-22 | 2024-04-26 | 国网江苏省电力有限公司苏州供电分公司 | 一种基于雷击概率的风储联合系统功率两层调控方法与系统 |
CN115409427A (zh) * | 2022-10-28 | 2022-11-29 | 国网江西省电力有限公司供电服务管理中心 | 居民负荷可用调节容量多状态的评估方法及装置 |
Also Published As
Publication number | Publication date |
---|---|
CN113572179B (zh) | 2022-01-25 |
WO2023045145A1 (zh) | 2023-03-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN113572179B (zh) | 一种基于雷击概率的储能与负荷功率协调控制方法 | |
CN105515058B (zh) | 一种光伏发电参与的功率就地消纳方法 | |
CN110729726B (zh) | 一种智慧社区能量优化调度方法和系统 | |
WO2013177923A1 (zh) | 风光储联合发电系统日前优化调度方法 | |
CN111244993B (zh) | 一种储能参与电网调峰应用的容量优化配置方法 | |
CN110829408B (zh) | 基于发电成本约束的计及储能电力系统的多域调度方法 | |
CN104807143A (zh) | 基于电能友好空调负荷侧主动需求策略 | |
WO2023197713A1 (zh) | 一种提升配电网韧性的两阶段需求响应策略 | |
CN107666152A (zh) | 分布式光伏电站并网点电压和功率因数越限的控制方法 | |
CN113572180B (zh) | 一种基于雷击概率的储能系统功率调控方法 | |
CN111725827A (zh) | 一种基于荷电状态自调节的储能平滑风电波动的控制方法 | |
CN115511658A (zh) | 一种计及储能装置折损的楼宇能量优化方法 | |
CN103023041B (zh) | 一种智能风电场有功无功功率控制系统 | |
CN111211569A (zh) | 一种柔性负荷参与电网调峰的优化配置方法 | |
CN117254526B (zh) | 一种光储充检微电网一体站能源协同优化控制方法 | |
US11444476B1 (en) | Lightning strike probability-based coordinated power control method for energy storage system and load | |
CN117293812A (zh) | 考虑风电正/反调峰场景的电力系统调度方法 | |
CN110165692B (zh) | 基于光伏-蓄电池-温控负荷的虚拟储能调峰系统与方法 | |
CN116799839A (zh) | 一种多资源协同功率控制方法、装置及电子设备 | |
CN116544992A (zh) | 一种电网侧储能降低变压器损耗的储能控制方法 | |
CN107634542B (zh) | 一种新能源发电系统的并网功率平滑控制方法及控制器 | |
CN114421486B (zh) | 一种电动汽车智能充电控制方法 | |
CN107273673B (zh) | 一种考虑平抑风电波动的空调冷水机组群控方法 | |
CN114566990A (zh) | 一种大规模分布式储能省地协同控制方法 | |
CN207518286U (zh) | 电站内储能系统协同汽轮机组调节级全负荷运行系统 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |