CN113431075A - Herringbone pile anchor assembly type foundation suitable for low-voltage power transmission line - Google Patents

Herringbone pile anchor assembly type foundation suitable for low-voltage power transmission line Download PDF

Info

Publication number
CN113431075A
CN113431075A CN202110851781.5A CN202110851781A CN113431075A CN 113431075 A CN113431075 A CN 113431075A CN 202110851781 A CN202110851781 A CN 202110851781A CN 113431075 A CN113431075 A CN 113431075A
Authority
CN
China
Prior art keywords
short pile
foundation
anchor
pile
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110851781.5A
Other languages
Chinese (zh)
Inventor
张文翔
吴树涛
郭向华
陈旭林
阮文明
李鹏晖
陈孝湘
翁兰溪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Construction Branch of State Grid Fujian Electric Power Co Ltd
Ningde Power Supply Co of State Grid Fujian Electric Power Co Ltd
PowerChina Fujian Electric Power Engineering Co Ltd
Original Assignee
Construction Branch of State Grid Fujian Electric Power Co Ltd
Ningde Power Supply Co of State Grid Fujian Electric Power Co Ltd
PowerChina Fujian Electric Power Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Construction Branch of State Grid Fujian Electric Power Co Ltd, Ningde Power Supply Co of State Grid Fujian Electric Power Co Ltd, PowerChina Fujian Electric Power Engineering Co Ltd filed Critical Construction Branch of State Grid Fujian Electric Power Co Ltd
Priority to CN202110851781.5A priority Critical patent/CN113431075A/en
Publication of CN113431075A publication Critical patent/CN113431075A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/50Anchored foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • E02D5/523Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
    • E02D5/526Connection means between pile segments

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Foundations (AREA)

Abstract

本发明涉及一种适用于低压输电线路的人字形桩锚装配式基础,包括装配式短桩基础,所述装配式短桩基础的外侧设置有四个锚杆,所述装配式短桩基础包括顶节短桩和底节短桩,所述顶节短桩的底部设置有卯眼,所述底节短桩的顶部设置有榫头,顶节短桩和底节短桩通过卯眼和榫头连接固定;所述每个锚杆均在装配式短桩基础的外侧壁呈斜向下设置,所述锚杆包括锚筋和设置的锚筋外部的细石混凝土;本发明在装配式短桩基础的周围通过45度斜向下的锚杆基础组成了人字形的基础型式,该种基础可以通过锚杆抵抗基础的抗拔以及水平力,通过装配式短桩基础抵抗基础的下压力,该基础型式核心为装配式的短桩基础,可大大的减少基础开挖的面积,提高基础的水保效益。

Figure 202110851781

The invention relates to a herringbone pile-anchor assembled foundation suitable for low-voltage transmission lines, including an assembled short pile foundation, four anchor rods are arranged on the outer side of the assembled short pile foundation, and the assembled short pile foundation includes The top section short pile and the bottom section short pile, the bottom section of the top section short pile is provided with a mortise, the top section of the bottom section short pile is provided with a tenon, and the top section short pile and the bottom section short pile are connected by the socket eye and the tenon Fixing; each anchor rod is arranged obliquely downward on the outer side wall of the prefabricated short pile foundation, and the anchor rod includes the anchor bar and the fine stone concrete outside the set anchor bar; the present invention is used in the prefabricated short pile foundation. A herringbone foundation type is formed around the 45-degree inclined downward anchor bolt foundation. This kind of foundation can resist the pull-out and horizontal force of the foundation through the bolt, and resist the down pressure of the foundation through the assembled short pile foundation. The core of the type is an assembled short pile foundation, which can greatly reduce the area of foundation excavation and improve the soil and water conservation benefits of the foundation.

Figure 202110851781

Description

Herringbone pile anchor assembly type foundation suitable for low-voltage power transmission line
Technical Field
The invention relates to a herringbone pile anchor assembly type foundation applicable to a low-voltage power transmission line, which is applied to the technical field of power transmission lines.
Background
In order to develop mechanical construction of the foundation, more and more foundation types are used as assembly type foundations, and in order to meet the requirements of uplift resistance, pressing-down resistance and horizontal bearing capacity of the foundation, the existing mountain assembly type foundations mainly adopt large-excavation plate type assembly type foundations, the area of original state soil excavation can be increased in a large area through the foundation types, large-area large excavation of the original state soil and the water conservation problem of a tower foundation are caused, and the difficulty of water conservation measures is increased.
Disclosure of Invention
In order to solve the technical problems, the invention provides the herringbone pile anchor assembly type foundation suitable for the low-voltage transmission line, which can effectively reduce the excavation area of original soil of the foundation and reduce the difficulty of water conservation measures.
The technical scheme of the invention is as follows:
a herringbone pile anchor assembly type foundation suitable for a low-voltage transmission line comprises an assembly type short pile foundation, wherein four anchor rods are arranged on the outer side of the assembly type short pile foundation, the assembly type short pile foundation comprises a top section short pile and a bottom section short pile, a mortise is arranged at the bottom of the top section short pile, a tenon is arranged at the top of the bottom section short pile, and the top section short pile and the bottom section short pile are connected and fixed through the mortise and the tenon; every stock all is the slant and sets up at the lateral wall on assembled stub basis, the stock includes the outside pea gravel concreten of anchor bar and the anchor bar that sets up.
The included angles between the anchor bars and the center of the tower are +/-45 degrees and +/-135 degrees respectively, and the inclination of the anchor rods in the vertical direction is 35-45 degrees.
The top section stub is of a prefabricated square reinforced concrete structure, an anchor rod preformed hole matched with the anchor rod is formed in the top section stub, and first bearing parts are arranged on four side wall surfaces of the top section stub.
The center of the top surface of the top section short pile is provided with an inward concave mortise.
The inside first stub owner muscle of a plurality of that is provided with of top festival stub, first stub owner muscle is along the peripheral equidistance distribution of top festival stub, and the outside of first stub owner muscle sets up first stub stirrup, and the inside of every first bearing portion all is provided with first bracket reinforcing bar net piece, is provided with first connection strengthening rib in the mortise, and first connection strengthening rib outside sets up first connection stirrup.
A first preformed hole is further formed in the top section stub, and a first reinforcing steel bar mesh is arranged outside the first preformed hole.
The bottom section stub is of a prefabricated square reinforced concrete structure, an anchor rod preformed hole matched with the anchor rod is formed in the bottom section stub, and second bearing parts are arranged on four side wall surfaces of the bottom section stub.
The center of the top face of the bottom section stub is integrally connected with a tenon matched with the mortise, a second preformed hole matched with the first preformed hole is formed in the tenon, and a second reinforcing steel bar net piece is arranged outside the second preformed hole.
The inside a plurality of second stub owner muscle that is provided with of end section stub, the peripheral equidistance distribution of second stub owner muscle along end section stub, the outside of second stub owner muscle sets up second stub stirrup, and the inside of every second bearing portion all is provided with second bracket reinforcing bar net piece, is provided with the second in the tenon and connects the strengthening rib, and the second is connected the strengthening rib outside and is set up the second and connect the stirrup.
A construction method of a herringbone pile anchor assembly type foundation suitable for a low-voltage power transmission line comprises the following specific steps:
s1, construction preparation, namely, producing the prefabricated short pile foundation according to the design requirement, and paying attention to the fact that anchor rod preformed holes in different directions need to be staggered in the production process so as to avoid conflict between the horizontal direction and the vertical direction;
s2, transporting the prefabricated short pile foundation, anchor bars and other materials to the site, keeping the site flat, and carrying out surface soil stripping work in the area to be excavated with the stripping thickness of 10 cm;
s3, excavating a base plane of a soil layer and a rock stratum according to the designed gradient, wherein the size d of the base in the horizontal direction is 20mm larger than the side of the assembly type short pile base (one side is 10mm), and then excavating vertically to the designed depth;
s4, placing the bottom section stub into the hole by using a hoisting device, aligning and assembling the mortise of the top section stub and the tenon at the top of the bottom section stub, penetrating the first preformed hole and the second preformed hole by using a bolt, and further screwing and fixing the bolt to a designed torque;
s5: positioning the anchor bars at the positions and angles through anchor bar preformed holes, drilling holes at the given positions and angles, and strictly ensuring the drilling positions and the drilling angles;
s6, lowering the anchor rods through the anchor rod preformed holes, and fixing the anchor rods on the first bracket reinforcing steel bar mesh sheet and the second bracket reinforcing steel bar mesh sheet respectively through bolts;
s7, pouring fine stone concrete to complete the construction of the anchor rod part;
and S8, pouring cement mortar into the gap between the assembled stub foundation and the rock mass, recovering the upper soil body, and performing surface soil recovery when the soil reaches the ground surface by 10 cm.
The invention has the following beneficial effects:
1. the invention provides a novel herringbone pile anchor assembly type foundation structure, which consists of two parts, wherein the center of the assembly type foundation is an assembly type short pile foundation with a rock embedding section, the periphery of the assembly type short pile foundation is an anchor rod foundation with 45-degree inclined downward, the downward pressing bearing capacity of an iron tower is borne by the assembly type short pile foundation, the upward pulling bearing capacity and the horizontal bearing capacity are borne by the anchor rods, and the foundation type can reduce the excavation area of original state soil of the foundation and reduce the difficulty of water conservation measures; assuming a 110kV double-circuit line, the buried depth of a general fabricated plate type foundation is 2.5, the width of a substrate is 3m, the volume of a soil body to be excavated according to excavation of one foundation at 45 degrees is about 45 cubic meters, and the surface soil stripping area is 64 square meters. If the foundation type is adopted, the pile diameter is about 1m, the earth volume excavation is about 18 cubic meters, 60% is saved for the assembled plate type foundation, the surface soil stripping area is 25 square meters, and the foundation type has great environmental benefit compared with the assembled plate type foundation, and the foundation type saves 60%.
2. By utilizing the exposed detailed structure of the main reinforcement, the connection strength of the anchor rod and the precast concrete pile is improved, the precast concrete pile is overlapped by adopting the steel bars, and the steel bars at the connection part are connected in an encrypted manner, so that the strength requirement of the connection part is ensured.
3. The top section stub and the bottom section stub provided by the invention are connected by adopting a mortise and tenon structure, so that the field assembly of an assembled pile foundation is facilitated, large-scale equipment is not required, and the construction is convenient and efficient.
4. The invention provides a novel construction method of an assembly type foundation, which comprises three stages of assembly type pile foundation construction, anchor rod construction and connection of two foundations, and is convenient for implementation and application of the foundation type.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic view of a connecting structure of a top section stub and a bottom section stub of the present invention;
FIG. 3 is a schematic structural view of the anchor rod of the present invention;
FIG. 4 is a schematic top view of the anchor rod and fabricated spud foundation of the present invention;
FIG. 5 is a side cross-sectional view of a top section spud according to the invention;
FIG. 6 is a top cross-sectional view of a top section spud according to the invention;
FIG. 7 is a schematic diagram of the position structure of the first preformed hole according to the present invention;
FIG. 8 is a schematic structural view of a stub of the present invention;
FIG. 9 is a side cross-sectional view of a bottom section spud according to the present invention;
FIG. 10 is a schematic diagram of the second preformed hole according to the present invention;
the reference numbers in the figures denote:
1. an assembled stub foundation; 2. an anchor rod; 3. jacking short piles; 4. bottom section short piles; 8. a first pressure-receiving portion; 9. reserving a hole in the anchor rod; 10. b, mortise drilling; 12. a first stub main reinforcement; 13. a first connecting reinforcing rib; 14. a first stub stirrup; 15. a first bracket steel mesh sheet; 17. a first preformed hole; 18. a first reinforcing mesh sheet; 19. a tenon; 20. a second stub main reinforcement; 21. a second stub stirrup; 22. a second bracket reinforcing mesh sheet; 23. a second connecting reinforcing rib; 24. a second connector stirrup; 25. a second preformed hole; 26. a second reinforcing mesh sheet; 27. anchoring ribs; 28. fine stone concrete; 29. and a second bearing part.
Detailed Description
The invention is described in detail below with reference to the figures and the specific embodiments.
The herringbone pile-anchor assembly type foundation suitable for the low-voltage transmission line comprises an assembly type short pile foundation 1, wherein four anchor rods 2 are arranged on the outer side of the assembly type short pile foundation 1, the assembly type short pile foundation 1 comprises a top section short pile 3 and a bottom section short pile 4, a mortise 10 is arranged at the bottom of the top section short pile 3, a tenon 19 is arranged at the top of the bottom section short pile 4, and the top section short pile 3 and the bottom section short pile 4 are fixedly connected through the mortise 10 and the tenon 19; every stock 2 all is the slant and sets up at the lateral wall of assembled stub basis 1, stock 2 includes anchor bar 27 and the outside pea gravel concret 28 of anchor bar 27 that sets up.
The included angles between the anchor bars 27 and the center of the tower are +/-45 degrees and +/-135 degrees respectively, and the inclination of the anchor rod 2 in the vertical direction is 35-45 degrees.
The top section stub 3 is of a prefabricated square reinforced concrete structure, the top section stub 3 is provided with an anchor rod preformed hole 9 matched with the anchor rod 2, and four side wall surfaces of the top section stub 3 are provided with first bearing parts 8.
The center of the top surface of the top section stub 3 is provided with an inward concave mortise 10.
The inside first stub owner muscle 12 that is provided with a plurality of top festival stub 3, first stub owner muscle 12 distributes along the peripheral equidistance of top festival stub 3, and the outside of first stub owner muscle 12 sets up first stub stirrup 14, and every first bearing portion 8's inside all is provided with first bracket reinforcing bar net piece 15, is provided with first connection strengthening rib 13 in the mortise 10, and first connection strengthening rib 13 outside sets up first connection stirrup.
A first preformed hole 17 is further formed in the top section stub 3, and a first reinforcing steel bar net piece 18 is arranged outside the first preformed hole 17.
The bottom section stub 4 is of a prefabricated square reinforced concrete structure, the anchor rod preformed hole 9 matched with the anchor rod 2 is formed in the bottom section stub 4, and second bearing parts 29 are arranged on four side wall surfaces of the bottom section stub 4.
The center of 4 top faces of bottom section stub is integrative to be connected with the tenon 19 with mortise 10 looks adaptation, offer the second preformed hole 25 with first preformed hole 17 looks adaptation on the tenon 19, the outside of second preformed hole 25 is provided with second reinforcing bar net piece 26.
Bottom segment stub 4 is inside to be provided with a plurality of second stub owner muscle 20, second stub owner muscle 20 distributes along the peripheral equidistance of bottom segment stub 4, and the outside of second stub owner muscle 20 sets up second stub stirrup 21, and the inside of every second bearing portion 29 all is provided with second bracket reinforcing bar net piece 22, is provided with second connection strengthening rib 23 in the tenon 19, and second connection strengthening rib 23 outside sets up second connection stirrup 24.
A construction method of a herringbone pile anchor assembly type foundation suitable for a low-voltage power transmission line comprises the following specific steps:
s1, construction preparation, namely, producing the prefabricated short pile foundation 1 according to design requirements, wherein the anchor rod preformed holes 9 in different directions need to be staggered in the production process so as to avoid conflict between the horizontal direction and the vertical direction;
s2, transporting the prefabricated assembly type short pile foundation 1, the anchor bars 27 and other materials to the site, keeping the site flat, and carrying out surface soil stripping work in the area to be excavated, wherein the stripping thickness is 10 cm;
s3, excavating a base plane of a soil layer and a rock stratum according to the designed gradient, wherein the size d of the base in the horizontal direction is 20mm (one side is 10mm) larger than the side 1 of the assembly type short pile foundation, and then excavating vertically to the designed depth;
s4, placing the bottom section stub 4 into the hole by using a hoisting device, aligning and assembling the mortise 10 of the top section stub 3 and the tenon 19 at the top of the bottom section stub 4, penetrating a bolt through the first reserved hole 17 and the second reserved hole 25, and further screwing the bolt to a designed torque;
s5: positioning the anchor bars 27 at the positions and angles of the anchor bars 27 through the anchor rod preformed holes 9, and drilling holes at the given positions and angles, wherein the drilling positions and the drilling angles need to be strictly ensured;
s6, lowering the anchor rod 2 through the anchor rod preformed hole 9, and fixing the anchor rod 2 on the first bracket reinforcing mesh sheet 15 and the second bracket reinforcing mesh sheet 22 through bolts respectively;
s7, pouring fine stone concrete 28 to complete the construction of the anchor rod 2;
and S8, pouring cement mortar into the gap between the assembled stub foundation 1 and the rock mass, recovering the upper soil body, and performing surface soil recovery when the soil reaches the ground surface by 10 cm.
The middle of the structure of the invention is an assembly type short pile foundation partially embedded with rock, the periphery of the assembly type short pile foundation forms a herringbone foundation type through an anchor rod foundation inclined downwards at 45 degrees, the foundation can resist the pulling resistance and horizontal force of the foundation through the anchor rod, the downward pressure of the foundation is resisted through the assembly type short pile foundation, and as the core of the foundation type is the assembly type short pile foundation, the foundation excavation area can be greatly reduced, and the water conservation benefit of the foundation is improved.
The above description is only an embodiment of the present invention, and not intended to limit the scope of the present invention, and all modifications of equivalent structures and equivalent processes performed by the present specification and drawings, or directly or indirectly applied to other related technical fields, are included in the scope of the present invention.

Claims (10)

1.一种适用于低压输电线路的人字形桩锚装配式基础,其特征在于:包括装配式短桩基础(1),所述装配式短桩基础(1)的外侧设置有四个锚杆(2),所述装配式短桩基础(1)包括顶节短桩(3)和底节短桩(4),所述顶节短桩(3)的底部设置有卯眼(10),所述底节短桩(4)的顶部设置有榫头(19),顶节短桩(3)和底节短桩(4)通过卯眼(10)和榫头(19)连接固定;所述每个锚杆(2)均在装配式短桩基础(1)的外侧壁呈斜向下设置,所述锚杆(2)包括锚筋(27)和设置的锚筋(27)外部的细石混凝土(28)。1. A herringbone pile-anchor prefabricated foundation suitable for low-voltage transmission lines is characterized in that: comprising an prefabricated short pile foundation (1), the outer side of the prefabricated short pile foundation (1) is provided with four anchor rods (2), the prefabricated short pile foundation (1) includes a top section short pile (3) and a bottom section short pile (4), and the bottom section of the top section short pile (3) is provided with a socket (10), The top of the bottom section short pile (4) is provided with a tenon (19), and the top section short pile (3) and the bottom section short pile (4) are connected and fixed by the socket (10) and the tenon (19); The bolts (2) are arranged obliquely downward on the outer side wall of the prefabricated short pile foundation (1), and the bolts (2) include anchor bars (27) and fine stones outside the set anchor bars (27). Concrete (28). 2.如权利要求1所述的一种适用于低压输电线路的人字形桩锚装配式基础,其特征在于:所述锚筋(27)与塔位中心的夹角分别是±45度以及±135度,锚杆(2)的垂直方向倾斜度为35-45度。2. A herringbone pile-anchor prefabricated foundation suitable for low-voltage transmission lines as claimed in claim 1, characterized in that: the included angles between the anchor bars (27) and the center of the tower position are ±45 degrees and ±45 degrees respectively. 135 degrees, the vertical inclination of the anchor rod (2) is 35-45 degrees. 3.如权利要求1所述的一种适用于低压输电线路的人字形桩锚装配式基础,其特征在于:所述顶节短桩(3)为预制的方形钢筋混凝土结构,顶节短桩(3)开设有与锚杆(2)相适配的锚杆预留孔(9),顶节短桩(3)的四个侧壁面上均设置有第一承压部(8)。3. A herringbone pile-anchor prefabricated foundation suitable for low-voltage transmission lines as claimed in claim 1, characterized in that: the top section short pile (3) is a prefabricated square reinforced concrete structure, and the top section short pile is a prefabricated square reinforced concrete structure. (3) An anchor rod reserved hole (9) adapted to the anchor rod (2) is opened, and first pressure bearing parts (8) are provided on the four side walls of the top section short pile (3). 4.如权利要求3所述的一种适用于低压输电线路的人字形桩锚装配式基础,其特征在于:所述顶节短桩(3)顶部面的中心开设有向内凹陷的卯眼(10)。4. A herringbone pile-anchor prefabricated foundation suitable for low-voltage transmission lines as claimed in claim 3, characterized in that: the center of the top surface of the top section short pile (3) is provided with an inwardly concave eyelet (10). 5.如权利要求4所述的一种适用于低压输电线路的人字形桩锚装配式基础,其特征在于:所述顶节短桩(3)内部设置有若干个第一短桩主筋(12),所述第一短桩主筋(12)沿顶节短桩(3)的外围等距分布,第一短桩主筋(12)的外部设置第一短桩箍筋(14),每个第一承压部(8)的内部均设置有第一牛腿钢筋网片(15),卯眼(10)内设置有第一连接加强筋(13),第一连接加强筋(13)外部设置第一连接箍筋。5. A herringbone pile-anchor prefabricated foundation suitable for low-voltage transmission lines according to claim 4, characterized in that: the top section short pile (3) is provided with several first short pile main bars (12). ), the first short pile main reinforcement (12) is equally spaced along the periphery of the top section short pile (3), and first short pile stirrups (14) are arranged outside the first short pile main reinforcement (12). A first corbel steel mesh (15) is arranged inside a pressure-bearing portion (8), a first connecting reinforcing rib (13) is arranged in the socket (10), and the first connecting reinforcing rib (13) is arranged outside The first connecting stirrups. 6.如权利要求5所述的一种适用于低压输电线路的人字形桩锚装配式基础,其特征在于:所述顶节短桩(3)内部还开设有第一预留孔(17),第一预留孔(17)的外部设置有第一加强钢筋网片(18)。6. A herringbone pile-anchor prefabricated foundation suitable for low-voltage transmission lines as claimed in claim 5, characterized in that: the top section short pile (3) is also provided with a first reserved hole (17) inside , a first reinforcing steel mesh sheet (18) is arranged outside the first reserved hole (17). 7.如权利要求1所述的一种适用于低压输电线路的人字形桩锚装配式基础,其特征在于:所述底节短桩(4)为预制的方形钢筋混凝土结构,底节短桩(4)开设有与锚杆(2)相适配的锚杆预留孔(9),底节短桩(4)的四个侧壁面上均设置有第二承压部(29)。7. A herringbone pile-anchor prefabricated foundation suitable for low-voltage transmission lines as claimed in claim 1, characterized in that: the bottom section short pile (4) is a prefabricated square reinforced concrete structure, and the bottom section short pile (4) An anchor rod reserved hole (9) adapted to the anchor rod (2) is opened, and second pressure bearing parts (29) are provided on the four side walls of the bottom section short pile (4). 8.如权利要求7所述的一种适用于低压输电线路的人字形桩锚装配式基础,其特征在于:所述底节短桩(4)顶部面的中心一体连接有与卯眼(10)相适配的榫头(19),所述榫头(19)上开设有与第一预留孔(17)相适配的第二预留孔(25),第二预留孔(25)的外部设置有第二加强钢筋网片(26)。8. A herringbone pile-anchor prefabricated foundation suitable for low-voltage transmission lines as claimed in claim 7, characterized in that: the center of the top surface of the bottom section short pile (4) is integrally connected with a socket (10). ) matching tenon (19), the tenon (19) is provided with a second reserved hole (25) that is matched with the first reserved hole (17), the second reserved hole (25) is A second reinforcing steel mesh sheet (26) is provided outside. 9.如权利要求8所述的一种适用于低压输电线路的人字形桩锚装配式基础,其特征在于:所述底节短桩(4)内部设置有若干个第二短桩主筋(20),所述第二短桩主筋(20)沿底节短桩(4)的外围等距分布,第二短桩主筋(20)的外部设置第二短桩箍筋(21),每个第二承压部(29)的内部均设置有第二牛腿钢筋网片(22),榫头(19)内设置有第二连接加强筋(23),第二连接加强筋(23)外部设置第二连接箍筋(24)。9. A herringbone pile-anchor prefabricated foundation suitable for low-voltage transmission lines as claimed in claim 8, characterized in that: the bottom section short piles (4) are provided with several second short pile main bars (20). ), the second short pile main bars (20) are equally spaced along the periphery of the bottom section short piles (4), and second short pile stirrups (21) are arranged outside the second short pile main bars (20). A second corbel steel mesh (22) is arranged inside the two pressure-bearing parts (29), a second connecting reinforcing rib (23) is arranged inside the tenon (19), and a second connecting reinforcing rib (23) is arranged outside the second connecting reinforcing rib (23). Two connecting stirrups (24). 10.一种适用于低压输电线路的人字形桩锚装配式基础的施工方法,具体步骤如下:10. A construction method for a herringbone pile-anchor prefabricated foundation suitable for low-voltage transmission lines, the specific steps are as follows: S1:施工准备,按照设计要求生产预制设计要求的装配式短桩基础(1),在生产过程中需要注意不同方向的锚杆预留孔(9)需要错开,以免其在水平方面与垂直方向产生冲突;S1: Construction preparation, produce the prefabricated short pile foundation (1) required by the prefabricated design according to the design requirements. During the production process, it is necessary to pay attention to the need to stagger the reserved holes (9) for anchor bolts in different directions, so as to avoid the horizontal and vertical directions. conflict; S2:将预制完成的装配式短桩基础(1)以及锚筋(27)等材料运输至现场,保持场地平整,在拟开挖的区域进行表土剥离工作,剥离厚度为10cm;S2: transport the prefabricated prefabricated short pile foundation (1) and anchor bars (27) and other materials to the site, keep the site level, and carry out topsoil stripping work in the area to be excavated, with a stripping thickness of 10cm; S3:按照设计的坡度开挖土层与岩层的基面,基底的水平方向尺寸d比装配式短桩基础(1)边长大20mm(一边为10mm),而后垂直开挖至设计深度;S3: Excavate the base surface of the soil layer and the rock layer according to the designed slope, the horizontal dimension d of the base is 20mm longer than the assembled short pile foundation (1) on one side (one side is 10mm), and then excavate vertically to the design depth; S4:采用起吊装置将底节短桩(4)放入孔内,并且将顶节短桩(3)的卯眼(10)与底节短桩(4)顶部的榫头(19)对齐拼装,而后用螺栓穿过第一预留孔(17)和第二预留孔(25),进一步将螺栓拧固到设计扭矩;S4: adopt the lifting device to put the bottom section short pile (4) into the hole, and align and assemble the socket (10) of the top section short pile (3) and the tenon (19) on the top of the bottom section short pile (4), Then use bolts to pass through the first reserved hole (17) and the second reserved hole (25), and further tighten the bolts to the design torque; S5:将锚筋(27)通过锚杆预留孔(9)定位锚筋(27)的位置与角度,并且在给定的位置和角度钻孔,需要严格保证钻进位置和钻进角度;S5: Position the anchor rib (27) through the anchor rod reserved hole (9) to locate the position and angle of the anchor rib (27), and drill holes at a given position and angle. The drilling position and drilling angle need to be strictly guaranteed; S6:通过锚杆预留孔(9)下放锚杆(2),并且将锚杆(2)通过螺栓分别固定在第一牛腿钢筋网片(15)上和第二牛腿钢筋网片(22)上;S6: lower the anchor rod (2) through the anchor rod reserved hole (9), and fix the anchor rod (2) on the first corbel steel mesh sheet (15) and the second corbel steel mesh sheet ( 22) on; S7:灌细石混凝土(28),完成锚杆(2)部分的施工;S7: pour fine stone concrete (28), and complete the construction of the bolt (2) part; S8:灌水泥砂浆至装配式短桩基础(1)与岩体的缝隙中,恢复上部土体,待到地表10cm时,进行表土回复工作。S8: Cement mortar is poured into the gap between the prefabricated short pile foundation (1) and the rock mass, and the upper soil mass is restored. When the surface is 10 cm above the surface, the surface soil restoration work is carried out.
CN202110851781.5A 2021-07-27 2021-07-27 Herringbone pile anchor assembly type foundation suitable for low-voltage power transmission line Pending CN113431075A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110851781.5A CN113431075A (en) 2021-07-27 2021-07-27 Herringbone pile anchor assembly type foundation suitable for low-voltage power transmission line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110851781.5A CN113431075A (en) 2021-07-27 2021-07-27 Herringbone pile anchor assembly type foundation suitable for low-voltage power transmission line

Publications (1)

Publication Number Publication Date
CN113431075A true CN113431075A (en) 2021-09-24

Family

ID=77761991

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110851781.5A Pending CN113431075A (en) 2021-07-27 2021-07-27 Herringbone pile anchor assembly type foundation suitable for low-voltage power transmission line

Country Status (1)

Country Link
CN (1) CN113431075A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20220042273A1 (en) * 2020-07-14 2022-02-10 Mark Anthony S. Dimitrijevic Structural support and stabilization assemblies and methods for installing same

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6665990B1 (en) * 2000-03-06 2003-12-23 Barr Engineering Co. High-tension high-compression foundation for tower structures
CN101691759A (en) * 2009-09-04 2010-04-07 中国电力工程顾问集团东北电力设计院 Construction method for digging composite environmental protection base of anchorage bar adding rock
CN204780975U (en) * 2015-06-30 2015-11-18 丽水市正阳电力设计院有限公司 A four return circuit terminal steel pipe poles are drawn and are dug compound basis of anchor log for medium voltage electric distribution circuit
CN205242427U (en) * 2015-10-30 2016-05-18 瀚川基业(北京)科技有限公司 Novel iron tower basis
CN208072439U (en) * 2018-03-27 2018-11-09 淮海工学院 A kind of assembly concrete cushion cap and micro-pile combined basis
CN210395412U (en) * 2019-06-27 2020-04-24 中国电力工程顾问集团西南电力设计院有限公司 Prestressed anchor pile uplift foundation suitable for overhead transmission line in mountain area
CN210712905U (en) * 2019-06-17 2020-06-09 国核电力规划设计研究院重庆有限公司 Novel bionic tree root foundation
CN211446901U (en) * 2019-11-23 2020-09-08 武汉金涛岩土工程有限公司 Combined precast pile
CN112982468A (en) * 2019-12-18 2021-06-18 烟台三维岩土工程技术有限公司 Anchoring technology and construction method for marine large-diameter tubular pile foundation

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6665990B1 (en) * 2000-03-06 2003-12-23 Barr Engineering Co. High-tension high-compression foundation for tower structures
CN101691759A (en) * 2009-09-04 2010-04-07 中国电力工程顾问集团东北电力设计院 Construction method for digging composite environmental protection base of anchorage bar adding rock
CN204780975U (en) * 2015-06-30 2015-11-18 丽水市正阳电力设计院有限公司 A four return circuit terminal steel pipe poles are drawn and are dug compound basis of anchor log for medium voltage electric distribution circuit
CN205242427U (en) * 2015-10-30 2016-05-18 瀚川基业(北京)科技有限公司 Novel iron tower basis
CN208072439U (en) * 2018-03-27 2018-11-09 淮海工学院 A kind of assembly concrete cushion cap and micro-pile combined basis
CN210712905U (en) * 2019-06-17 2020-06-09 国核电力规划设计研究院重庆有限公司 Novel bionic tree root foundation
CN210395412U (en) * 2019-06-27 2020-04-24 中国电力工程顾问集团西南电力设计院有限公司 Prestressed anchor pile uplift foundation suitable for overhead transmission line in mountain area
CN211446901U (en) * 2019-11-23 2020-09-08 武汉金涛岩土工程有限公司 Combined precast pile
CN112982468A (en) * 2019-12-18 2021-06-18 烟台三维岩土工程技术有限公司 Anchoring technology and construction method for marine large-diameter tubular pile foundation

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20220042273A1 (en) * 2020-07-14 2022-02-10 Mark Anthony S. Dimitrijevic Structural support and stabilization assemblies and methods for installing same

Similar Documents

Publication Publication Date Title
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN106013171B (en) A kind of semi-rigid supporting construction semi-flexible and method of deep-foundation side wall
CN107119712A (en) Multi-arch retaining wall and construction method thereof
CN104452784A (en) Composite bolt pile used for slope strengthening and construction technique of composite bolt pile
CN110241828A (en) The outer sealing construction method for supporting of anchor in a kind of row's grating tubular pole grouting behind shaft or drift lining
CN110820793A (en) Composite foundation for collapsible loess area and construction method
CN110777836A (en) Reinforced concrete plate-anchor rod composite foundation and using method thereof
CN112095656A (en) A tension-compression composite prestressed anchor cable retaining wall structure
CN115821972B (en) A prefabricated rock anchor foundation for power transmission lines and its construction method
CN101691760B (en) Composite foundation combining anchor rods with excavation and construction method thereof
CN101718098B (en) A kind of micro-pile combined excavation and excavation composite foundation and its construction method
CN101793027A (en) Core-grouted static pressure anchor rod pile
CN108330963A (en) A kind of constructing device for inside soil body existing pile foundation pile extension
CN206768860U (en) Multi-arch retaining wall
CN206800370U (en) It is a kind of to excavate the continuous side wall supporting and retaining system protective construction in underground without fertile groove
CN201502065U (en) A type of composite foundation for bolt combined excavation
CN109989414B (en) Assembled foundation
CN210263075U (en) A rear grouting inner anchor and outer water stop support system for grid-type pipe piles
CN119553690A (en) Composite foundation pit water-stopping retaining structure system and its construction method under complex geological conditions
CN119163029A (en) A combined support of piles and concrete walls and its construction method
CN118461655A (en) A steel pipe support grouting small diameter steel pipe pile foundation structure
CN111305220A (en) Concrete support and structural top plate combined building system based on permanent and temporary combination and construction method thereof
CN106223344A (en) A kind of ground line piled anchor framework foundation pit supporting method
CN206368375U (en) A kind of electric power pylon basis
CN215105479U (en) Foundation rock anchor pile plate type foundation of tower crane

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210924