CN113323222B - Assembled type drop suspended ceiling and installation method thereof - Google Patents
Assembled type drop suspended ceiling and installation method thereof Download PDFInfo
- Publication number
- CN113323222B CN113323222B CN202110070120.9A CN202110070120A CN113323222B CN 113323222 B CN113323222 B CN 113323222B CN 202110070120 A CN202110070120 A CN 202110070120A CN 113323222 B CN113323222 B CN 113323222B
- Authority
- CN
- China
- Prior art keywords
- level
- plate
- falling
- curtain box
- line
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
-
- A—HUMAN NECESSITIES
- A47—FURNITURE; DOMESTIC ARTICLES OR APPLIANCES; COFFEE MILLS; SPICE MILLS; SUCTION CLEANERS IN GENERAL
- A47H—FURNISHINGS FOR WINDOWS OR DOORS
- A47H1/00—Curtain suspension devices
- A47H1/10—Means for mounting curtain rods or rails
- A47H1/12—Adjustable mountings
-
- A—HUMAN NECESSITIES
- A47—FURNITURE; DOMESTIC ARTICLES OR APPLIANCES; COFFEE MILLS; SPICE MILLS; SUCTION CLEANERS IN GENERAL
- A47H—FURNISHINGS FOR WINDOWS OR DOORS
- A47H2/00—Pelmets or the like
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/06—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/06—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
- E04B9/12—Connections between non-parallel members of the supporting construction
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/18—Means for suspending the supporting construction
- E04B9/20—Means for suspending the supporting construction adjustable
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/22—Connection of slabs, panels, sheets or the like to the supporting construction
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F19/00—Other details of constructional parts for finishing work on buildings
- E04F19/02—Borders; Finishing strips, e.g. beadings; Light coves
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Curtains And Furnishings For Windows Or Doors (AREA)
Abstract
The invention discloses an assembled drop ceiling and an installation method thereof, wherein the assembled drop ceiling comprises four original wall surfaces and a floor base layer in a room, the original wall surfaces comprise a first wall surface provided with a window, a second wall surface opposite to the window, and third wall surfaces opposite to the other two sides, and the assembled drop ceiling also comprises a high-level plate arranged below the floor base layer, a ceiling curtain box connected with the high-level plate and the first wall surface, a first ceiling drop structure connected with the high-level plate and the second wall surface, and a second ceiling drop structure connected with the high-level plate and the third wall surface. According to the suspended ceiling provided by the invention, the two top hanging angle steels are combined and then locked by the locking bolt, so that the two top hanging angle steels can move up and down, leveling and supporting the square pipe can be realized, the keel hanging piece penetrates into the U-shaped keel, then the U-shaped keel is installed in the keel base and is assembled with the panel into a whole, and the keel hanging piece is hung on the square pipe, so that the panel single-block installation can be realized, the structure is simple, and the installation is rapid and convenient.
Description
Technical Field
The invention relates to the field of industrialized assembly type decoration, in particular to an assembly type drop ceiling and an installation method thereof.
Background
The suspended ceiling of home decoration is a common link in home decoration. The decoration of the whole living room plays a very important role, and the top surface of the living room is properly decorated, so that the indoor environment can be beautified, and a rich and colorful indoor space artistic image can be created. The application of the assembled suspended ceiling in the flat floor slab building is widely used in the market at present, and an applicable suspended ceiling system needs to be designed, especially the requirement on the floor height in the existing home decoration is high, so that the suspended ceiling system occupying a small floor height needs to be designed. And when the assembled suspended ceiling has the modeling, the structure is complex, the installation is difficult, and original vertical frame plates are made by panel slotting and bending processing, and a plurality of rear-mounted structures are needed, so that the production cost and time of the suspended ceiling are greatly improved, the installation process of the suspended ceiling is very complex, and not only is the material cost increased, but also the labor cost and the installation time are increased.
The assembly type suspended ceiling commonly used at present has the following problems:
1. When the traditional assembled suspended ceiling is leveled by using the overhead hanging, the overhead hanging structure is complex, the steps of the installation process are complex, the materials are more, and the cost is high;
2. The traditional assembly type suspended ceiling generally uses wall hanging, namely the panel is lapped on the wall, when the panel needs to be hung on a floor slab, the whole lifting mode is generally used, but the single-block installation mode is lacked, and the application range is limited;
3. when the curtain box exists in the assembled suspended ceiling, the structure is complex, the materials are more, the installation steps are more and the like;
4. the conventional assembled suspended ceiling has complex structure and difficult installation when being molded, and the conventional vertical frame plate is manufactured by grooving, bending and processing the panel, so that the manufacturing process is troublesome, the manufacturing time is long, the industrial production is not facilitated, and a plurality of rear-mounted structures are needed, so that the manufacturing process is very troublesome.
Disclosure of Invention
The invention aims to provide an assembled drop-level suspended ceiling and an installing method thereof, which are applied to installing structures of various assembled suspended ceilings, and can be split and matched with different structures according to conditions.
In order to achieve the above purpose, the invention provides a technical scheme that the invention provides an assembled drop ceiling, which comprises four original wall surfaces in a room and a floor base layer, and is characterized in that the original wall surfaces comprise a first wall surface provided with a window, a second wall surface opposite to the window, and third wall surfaces opposite to the other two sides, and further comprise a high-level plate arranged below the floor base layer, a ceiling curtain box connected with the high-level plate and the first wall surface, a first ceiling drop structure connected with the high-level plate and the second wall surface, and a second ceiling drop structure connected with the high-level plate and the third wall surface;
The upper top hanging angle steel bottom and the top end of the lower top hanging angle steel are locked and fixed through the locking bolt, the bottom end of the lower top hanging angle steel is in a horizontal state, the square tube is horizontally arranged above the bottom end of the lower top hanging angle steel, a plurality of keel hangers are hung on the square tube, the horizontally arranged tee keels are penetrated at the bottom of the keel hangers, the tee keels are embedded into the keel base to form a stable structure, and the keel base is fixedly connected with the upper surface of the panel of the upper level plate;
The suspended ceiling curtain box is arranged below one side of the high-level plate surface plate, which is close to the first wall surface, and comprises a first vertical plate line, a first falling-level vertical plate, a first curtain box back plate, a first angle-setting code and a curtain box panel for installing a curtain, wherein the top end of the first vertical plate line is fixedly connected with the high-level plate surface plate through a screw, the first falling-level vertical plate is vertically hung at the bottom of the first vertical plate line, two clamping grooves are formed in the lower end of the first falling-level vertical plate, the first curtain box back plate is fixedly connected with the first falling-level vertical plate through a clamping connection, the top end of the first curtain box back plate is in contact with the bottom surface of the curtain box panel, the first falling-level vertical plate is fixedly connected with the curtain box panel through the first angle-setting code, and two side edges of the first angle-setting code are respectively fixedly connected with the first falling-level vertical plate and the curtain box panel through a screw;
the high-level panel is provided with a first suspended ceiling falling structure close to one side of the second wall, the first suspended ceiling falling structure comprises a second vertical plate line, a second falling vertical plate, a second curtain box back plate and a second wood-plastic line, the top end of the second vertical plate line is fixedly connected with the high-level panel through screws, the second falling vertical plate is vertically hung at the bottom of the second vertical plate line, one side of the second falling vertical plate is provided with two clamping grooves, one end of the second curtain box back plate is fixedly clamped with the second falling vertical plate, the other end of the second curtain box back plate is fixedly connected with the second wood-plastic line through screws, and the second wood-plastic line is fixedly connected with the second wall through screws;
the high-level board is close to third wall one side below is equipped with the second furred ceiling and falls a level structure, the second furred ceiling falls a level structure and includes third riser line, third and falls a level riser, third curtain box backplate, third wood moulding line, third riser line top with high-level board passes through screw fixed connection, third falls a level riser vertical articulates third riser line bottom, third falls a level riser one side and is equipped with two draw-in grooves, third curtain box backplate one end with third falls a level riser joint fixedly, the third curtain box backplate other end with the line is moulded through screw fixed connection to the third wood, the line is moulded to the third wood with the third wall passes through screw fixed connection.
Further, the two ends of the first falling-stage vertical plate are respectively abutted against the two surfaces of the third wall surface, the two ends of the third falling-stage vertical plate are respectively abutted against the first falling-stage vertical plate and the second wall surface, and the two ends of the second falling-stage vertical plate are respectively abutted against the third falling-stage vertical plate at two sides.
Further, the first curtain box backboard and the first falling-stage vertical plate are the same in length, the second curtain box backboard and the second wood-plastic line are the same as the second falling-stage vertical plate in length, and the third curtain box backboard and the third wood-plastic line are the same as the third falling-stage vertical plate in length.
Further, the curtain box panel comprises a fourth keel, a fourth keel base and a low-level plate, wherein the fourth keel base is embedded into the fourth keel base to form a stable structure, the fourth keel base is fixedly connected with the low-level plate, and one side of the low-level plate is fixedly connected with the first corner printing code through a screw.
Further, the lower plate is close to the edge collecting pieces which are horizontally arranged at two ends of the third wall surface, one side of the edge collecting pieces is fixedly connected with the third wall surface, a batten is arranged in the fourth U-shaped keel in a penetrating mode, the batten extends out of two ends of the fourth U-shaped keel, and two ends of the batten are fixedly connected with the edge collecting pieces of the third wall surface in a lap joint mode respectively.
Further, the edging piece is an aluminum edging piece.
Further, the second wood-plastic line and the third wood-plastic line are porous hollow structures.
Further, the curtain box comprises beautifying lines, and beautifying lines are fixedly connected to the joint of the first falling-stage vertical plate and the bottom end of the first curtain box back plate, the joint of the second falling-stage vertical plate and the bottom end of the second curtain box back plate and the joint of the third falling-stage vertical plate and the bottom end of the third curtain box back plate.
Furthermore, clamping grooves are formed in two sides of the high-level plate surface plate, and clamping blocks are clamped in the clamping grooves between two adjacent high-level plate surface plates.
On the other hand, the invention provides an installation method of the assembled drop-level suspended ceiling, which is characterized by comprising the following steps of:
S1, a line is sprung on an original wall surface and a floor base layer, an upper top hanging angle steel is fixedly arranged on the lower surface of the floor base layer according to the line by using an expansion bolt, then the upper top hanging angle steel and a lower top hanging angle steel are fixed by using a locking bolt and leveled, and a square tube is placed on the lower top hanging angle steel;
S2, splicing high-level board panels on the ground, inserting the Chinese character 'ji' keels into the keel hanging pieces, embedding the Chinese character 'ji' keels into the keel base, fixedly mounting the keel base on the upper surface of the high-level board panels, sequentially assembling all the high-level board panels into a whole, and then lifting the whole high-level board, so that the keel hanging pieces are hung on the square pipes;
S3, fixedly mounting a first vertical plate line on the lower surface of the high-level plate panel, hanging a first falling-level vertical plate on the first vertical plate line, and then assembling a curtain box panel: embedding a fourth U-shaped keel into a fourth keel base, fixing the fourth keel base on the upper surface of a low-level plate, inserting battens into the fourth U-shaped keel, lifting the assembled curtain box panel integrally so that two ends of the battens are lapped above the edge collecting piece, fixing the low-level plate and a first falling-level vertical plate through a first angle code, and finally inserting a first curtain box back plate onto the first falling-level vertical plate;
S4, installing a second wood plastic line according to the elastic line position, fixedly installing a second vertical plate line on the lower surface of the high-level plate surface plate, hanging a second falling-stage vertical plate on the second vertical plate line, then inserting one end of a second curtain box back plate on the second vertical plate line for fixation, and fixing the other end of the second curtain box back plate with the bottom end of the second wood plastic line through a screw;
S5, installing a third wood plastic line according to the elastic line position, fixedly installing a third vertical plate line on the lower surface of the high-level plate surface plate, hanging a third falling-stage vertical plate on the third vertical plate line, then inserting one end of a third curtain box back plate on the third vertical plate line for fixation, and fixing the other end of the third curtain box back plate with the bottom end of the third wood plastic line through a screw;
S6, mounting the beautifying lines to the joint of the first falling-stage vertical plate and the bottom end of the first curtain box backboard, the joint of the second falling-stage vertical plate and the bottom end of the second curtain box backboard, and the joint of the third falling-stage vertical plate and the bottom end of the third curtain box backboard by gluing, and finishing edge finishing.
The beneficial effects of the invention are as follows:
1. According to the assembled drop-level suspended ceiling, the top hanging angle steel is fixed to the floor slab through the expansion bolts and combined with the other top hanging angle steel, and then the top hanging angle steel is locked through the locking bolts, so that the two top hanging angle steel can move up and down due to the strip-shaped holes in the middle of the top hanging angle steel, the leveling can be achieved, square pipes can be supported, the structure is simple, the service life is long, and the installation is convenient and quick.
2. The assembled drop-level suspended ceiling provided by the invention has the advantages that the keel hanging piece penetrates into the U-shaped keels, the U-shaped keels are installed in the keel base, the U-shaped keels and the panel are assembled into a whole, and the whole is lifted during installation, so that the keel hanging piece is hung on the square tube, the panel single-piece installation can be realized, the structure is simple, and the installation is rapid and convenient.
3. The assembled drop suspended ceiling provided by the invention has the advantages that the drop vertical plates and the curtain box backboard are all integrally extruded materials, the industrial production and transportation are easy, the structure is simple and easy to understand, the materials are few, the installation is convenient, the application range is wide, and the economic benefit is higher.
4. According to the assembled drop suspended ceiling, the gap between the drop vertical plate and the curtain box backboard is covered by the beautifying line, so that the whole suspended ceiling structure can be beautified, the beautifying line is simple in structure and convenient to install, and the suspended ceiling can be detached at any time.
5. The assembled drop suspended ceiling provided by the invention has the advantages of time saving, fast progress, clean construction site, easiness in management, no harm of gypsum powder and harmful flying dust to constructors, and no pollution.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments of the invention and together with the description, serve to explain the principles of the invention. In the drawings, like reference numerals are used to identify like elements. The drawings, which are included in the description, illustrate some, but not all embodiments of the invention. Other figures can be derived from these figures by one of ordinary skill in the art without undue effort.
FIG. 1 is a schematic side view of an assembled drop ceiling in different directions according to an embodiment of the present invention;
Fig. 2 is a schematic side structural view of an assembled drop ceiling in different directions of two top hanging angle steels;
FIG. 3 is a schematic perspective view of a high-level board of an assembled drop ceiling according to an embodiment of the present invention;
FIG. 4 is a schematic side view of a high-level board of an assembled drop ceiling according to an embodiment of the present invention;
FIG. 5 is a schematic side view of a ceiling curtain box of an assembled drop ceiling according to an embodiment of the present invention;
FIG. 6 is a schematic side view of a first drop ceiling drop structure of an assembled drop ceiling according to an embodiment of the present invention;
FIG. 7 is a schematic side view of a second drop ceiling structure of an assembled drop ceiling according to an embodiment of the present invention;
FIG. 8 is a schematic perspective view of a box curtain panel of an assembled drop ceiling according to an embodiment of the present invention;
FIG. 9 is a schematic side view of a high-level deck panel of an assembled drop ceiling according to an embodiment of the present invention;
Fig. 10 is a schematic perspective view of an assembled drop ceiling according to an embodiment of the present invention.
In the figure: 1. an original wall surface; 2. floor base layer; 3. a high-level plate; 4. suspended ceiling curtain box; 5. the first suspended ceiling is of a falling-level structure; 6. the second suspended ceiling is of a falling-level structure; 7. beautifying the line; 8. a clamping groove; 9. a clamping block; 101. a first wall surface; 102. a second wall surface; 103. a third wall surface; 301. hanging angle steel on the upper top; 302. hanging angle steel on the lower top; 303. a locking bolt; 304. an expansion bolt; 305. square tubes; 306. a keel hanger; 307. a U-shaped keel; 308. a high-level plate panel; 309. a keel base; 401. a first riser line; 402. a first falling stage riser; 403. a curtain box panel; 404. a first box back plate; 405. a first corner key; 501. a second riser line; 502. a second falling stage riser; 503. a second box back plate; 504. the second wood-plastic line; 601. a third riser line; 602. a third falling stage riser; 603. a third box back plate; 604. a third wood-plastic line; 4031. a fourth keel; 4032. a fourth keel base; 4033. a lower plate; 4034. edge collecting pieces; 4035. wood strips.
Detailed Description
In order to more clearly illustrate the embodiments of the present invention and the technical solutions in the prior art, the following description will explain the specific embodiments of the present invention with reference to the accompanying drawings. It is evident that the drawings in the following description are only examples of the invention, from which other drawings and other embodiments can be obtained by a person skilled in the art without inventive effort. The term "design azimuth" merely means a relative positional relationship between the respective members, not an absolute positional relationship.
Referring to fig. 1, in one aspect, an embodiment of the present invention provides an assembled drop ceiling, which includes four original wall surfaces 1 and a floor base layer 2 in a room, and is characterized in that the original wall surfaces 1 include a first wall surface 101 provided with a window, a second wall surface 102 opposite to the window, and a third wall surface 103 opposite to the other two sides, and further include a high-level plate 3 installed below the floor base layer 2, a ceiling curtain box 4 connecting the high-level plate 3 and the first wall surface 101, a first ceiling drop structure 5 connecting the high-level plate 3 and the second wall surface 102, and a second ceiling drop structure 6 connecting the high-level plate 3 and the third wall surface 103. Specifically, the high-level plate 3, the suspended ceiling curtain box 4, the first suspended ceiling falling-level structure 5 and the second suspended ceiling falling-level structure 6 jointly form an assembled suspended ceiling falling-level.
Referring to fig. 2, the upper plate 3 includes an upper top hanging angle 301, a lower top hanging angle 302, a locking bolt 303, an expansion bolt 304, a square tube 305, a keel hanger 306, a rectangular keel 307, an upper plate surface plate 308, and a keel base 309, wherein the top end of the upper top hanging angle 301 is fixedly mounted on the lower surface of the floor base 2 through the expansion bolt 304, the bottom end of the upper top hanging angle 301 and the top end of the lower top hanging angle 302 are locked and fixed through the locking bolt 303, the bottom end of the lower top hanging angle 302 is in a horizontal state, and the square tube 305 is horizontally arranged above the bottom end of the lower top hanging angle 302. Specifically, the upper top hanging angle steel 301 and the lower top hanging angle steel 302 are combined, then the locking bolt 303 is used for locking and fixing, the distance between the upper top hanging angle steel 301 and the lower top hanging angle steel 302 can be adjusted through a strip-shaped hole in the middle of the top hanging angle steel, so that the aim of leveling is achieved, the lower top hanging angle steel 302 can also support the square pipe 305, and the structure is simple and the installation is convenient.
Further, referring to fig. 3 and 4, the square tube 305 is hung with a plurality of keel hangers 306, the bottom of the keel hangers 306 is provided with a horizontal bracket 307, the bracket 307 is embedded into the bracket base 309 to form a stable structure, and the bracket base 309 is fixedly connected with the upper surface of the high-level panel 308. Specifically, the keel hanging piece 306 is threaded into the rectangular keel 307, then the rectangular keel 307 is installed in the keel base 309, and the rectangular keel is assembled with the high-level plate panel 308 to form a whole, and the whole is lifted during installation, so that the keel hanging piece 306 is hung on the square tube 305, and single panel installation can be realized, and the operation is convenient. In the embodiment of the present invention, two parallel-arranged brackets 307 are fixed above each upper panel 308, and 6 brackets bases 309 are embedded and fixed on each bracket 307, and according to the size of the actual panel, a plurality of brackets 307 may be optionally arranged above each upper panel 308. In the embodiment of the present invention, two square tubes 305 are provided, and a plurality of square tubes 305 may be optionally provided according to practical situations, so as to increase the bearing capacity of the square tubes 305.
Referring to fig. 5, the suspended ceiling curtain box 4 is disposed below a side of the high-level board 308, which is close to the first wall 101, the suspended ceiling curtain box 4 includes a first vertical board line 401, a first falling-level vertical board 402, a first curtain box back board 404, a first corner bracket 405, and a curtain box panel 403 for installing a curtain, the top end of the first vertical board line 401 is fixedly connected with the high-level board 308 through a screw, the first falling-level vertical board 402 is vertically hung at the bottom of the first vertical board line 401, two clamping grooves are disposed at the lower end of the first falling-level vertical board 402, the first curtain box back board 404 is fixedly connected with the first falling-level vertical board 402 through a clamping connection, the top end of the first curtain box back board 404 is in contact with the bottom surface of the curtain box panel 403, the first falling-level vertical board 402 is fixedly connected with the curtain box panel 403 through the first corner bracket 405, and two sides of the first corner bracket 405 are respectively fixedly connected with the first falling-level vertical board 402 and the curtain box panel 403 through a screw. Wherein, through the equipment first (window) curtain box backplate 404 with first level riser 402 falls the whole frame, installs high-order face board 308 lower surface, moreover first (window) curtain box backplate 404 with first level riser 402 falls the material of extruding as an organic whole, easily industrial production transportation, simple structure is understandable, and the material is few, simple to operate.
Referring to fig. 6, a first suspended ceiling stepped structure 5 is disposed below a side of the high-level board 308, which is close to the second wall surface 102, the first suspended ceiling stepped structure 5 includes a second vertical board line 501, a second stepped board 502, a second curtain box back board 503, and a second wood-plastic line 504, the top end of the second vertical board line 501 is fixedly connected with the high-level board 308 through a screw, the second stepped board 502 is vertically hung at the bottom of the second vertical board line 501, two clamping grooves are disposed on one side of the second stepped board 502, one end of the second curtain box back board 503 is fixedly clamped with the second stepped board 502, the other end of the second curtain box back board 503 is fixedly connected with the second wood-plastic line 504 through a screw, and the second wood-plastic line 504 is fixedly connected with the second wall surface 102 through a screw. Similarly, the second falling-stage vertical plate 502 and the second curtain box backboard 503 are assembled to form an integral frame, the integral frame is mounted on the lower surface of the high-level plate surface plate 308, and the second falling-stage vertical plate 502 and the second curtain box backboard 503 are all integrally extruded with materials, so that the integral curtain box is easy to industrially produce and transport, simple and easy to understand in structure, few in materials and convenient to mount.
Referring to fig. 7, a second suspended ceiling stepped structure 6 is disposed below a side of the upper plate 308, which is close to the third wall 103, where the second suspended ceiling stepped structure 6 includes a third vertical plate line 601, a third stepped vertical plate 602, a third curtain box back plate 603, and a third wood-plastic line 604, the top of the third vertical plate line 601 is fixedly connected with the upper plate 308 through a screw, the third stepped vertical plate 602 is vertically hung at the bottom of the third vertical plate line 601, two clamping grooves are disposed on one side of the third stepped vertical plate 602, one end of the third curtain box back plate 603 is fixedly clamped with the third stepped vertical plate 602, the other end of the third curtain box back plate 603 is fixedly connected with the third wood-plastic line 604 through a screw, and the third wood-plastic line 604 is fixedly connected with the third wall 103 through a screw. Similarly, the third falling-stage vertical plate 602 and the third curtain box backboard 603 are assembled to form an integral frame, the integral frame is mounted on the lower surface of the high-level plate surface plate 308, and the third falling-stage vertical plate 602 and the third curtain box backboard 603 are all integrally extruded with materials, so that the novel curtain box is easy to industrially produce and transport, simple and easy to understand in structure, few in materials and convenient to mount.
Further, referring to fig. 10, two ends of the first falling stage vertical plate 402 respectively collide with the third wall surface 103, two ends of the third falling stage vertical plate 602 respectively collide with the first falling stage vertical plate 402 and the second wall surface 102, and two ends of the second falling stage vertical plate 502 respectively collide with the third falling stage vertical plate 602 at two sides. Further, the length of the first curtain box backboard 404 is the same as that of the first falling stage vertical plate 402, the length of the second curtain box backboard 503 and the length of the second wood-plastic line 504 are the same as that of the second falling stage vertical plate 502, and the length of the third curtain box backboard 603 and the length of the third wood-plastic line 604 are the same as that of the third falling stage vertical plate 602. So set up, first level riser 402 second level riser 502 with third level riser 602 can be laid full of whole indoor furred ceiling for the furred ceiling structure is more complete pleasing to the eye.
Further, referring to fig. 8, the curtain box panel 403 includes a fourth runner 4031, a fourth runner base 4032, and a lower plate 4033, the fourth runner 4031 is embedded into the fourth runner base 4032 to form a stable structure, the fourth runner base 4032 is fixedly connected with the lower plate 4033, and one side of the lower plate 4033 is fixedly connected with the first corner bracket 405 through a screw. Furthermore, the lower plate 4033 is close to two ends of the third wall 103 and is provided with a horizontally arranged edge-folding member 4034, one side of the edge-folding member 4034 is fixedly connected with the third wall 103, a batten 4035 is arranged in the fourth h-shaped keel 4031 in a penetrating manner, the batten 4035 extends out of two ends of the fourth h-shaped keel 4031, and two ends of the batten 4035 are respectively fixedly overlapped with the edge-folding members 4034 of the third wall 103 at two sides. Specifically, in the embodiment of the present invention, two parallel fourth cross keels 4031 are disposed on the upper surface of the lower plate 4033, wood strips 4035 are threaded in the fourth cross keels 4031, and two ends of each wood strip 4035 are lapped on the edge collecting member 4034, so that the lower plate 4033 is lapped above the edge collecting member 4034.
Further, the edging 4034 is an aluminum edging. The aluminum edge collecting piece is light in weight and environment-friendly.
Further, the second wood plastic strand 504 and the third wood plastic strand 604 are porous hollow structures. The multi-hollow structure makes the second wood plastic strand 504 and the third wood plastic strand 604 lightweight, and is convenient to install and transport.
Further, the curtain box further comprises a beautifying line 7, and the beautifying line 7 is fixedly connected to the joint of the first falling-stage vertical plate 402 and the bottom end of the first curtain box backboard 404, the joint of the second falling-stage vertical plate 502 and the bottom end of the second curtain box backboard 503 and the joint of the third falling-stage vertical plate 602 and the bottom end of the third curtain box backboard 603. The beautifying line 7 can cover the gap at the connecting structure, and can effectively beautify the whole indoor suspended ceiling structure.
Further, in the embodiment of the present invention, referring to fig. 9, two sides of the upper board panels 308 are provided with clamping grooves 8, and clamping blocks 9 are clamped in the clamping grooves 8 between two adjacent upper board panels 308. In order to further stabilize the high-level board panels 308, the clamping blocks 9 are clamped in the clamping grooves 8 between two adjacent high-level board panels 308, so that the two adjacent high-level board panels 308 are integrated, and then the high-level board panels 308 are integrated.
On the other hand, the invention provides an installation method of the assembled drop-level suspended ceiling, which is characterized by comprising the following steps of:
S1, snapping wires on an original wall surface 1 and a floor base layer 2, fixedly mounting an upper top hanging angle steel 301 on the lower surface of the floor base layer 2 according to expansion bolts 304 for snapping wires, then fixing and leveling the upper top hanging angle steel 301 and a lower top hanging angle steel 302 by using locking bolts 303, and placing a square tube 305 on the lower top hanging angle steel 302;
S2, splicing high-level plate panels 308 on the ground, inserting the Chinese character 'ji' keels 307 into the keel hanging pieces 306, embedding the Chinese character 'ji' keels 307 into the keel bases 309, fixedly mounting the keel bases 309 on the upper surfaces of the high-level plate panels 308, sequentially assembling all the high-level plate panels 308 into a whole, and then lifting the high-level plate 3 integrally so that the keel hanging pieces 306 are hung on the square tubes 305;
s3, fixedly mounting a first riser line 401 on the lower surface of the high-level panel 308, hanging a first falling riser 402 on the first riser line 401, and then assembling a curtain box panel 403: embedding a fourth Chinese character 'ji' keel 4031 into a fourth keel base 4032, fixing the fourth keel base 4032 on the upper surface of a lower plate 4033, inserting battens 4035 into the fourth Chinese character 'ji' keels 4031, lifting the assembled curtain box panel 403 integrally so that two ends of the battens 4035 are lapped above edge collecting pieces 4034, fixing the lower plate 4033 and a first falling-stage vertical plate 402 through a first corner bracket 405, and finally inserting a first curtain box backboard 404 onto the first falling-stage vertical plate 402;
S4, installing a second wood plastic line 504 according to the elastic line position, fixedly installing a second vertical plate line 501 on the lower surface of the high-level plate surface plate 308, hanging a second falling-stage vertical plate 502 on the second vertical plate line 501, then inserting one end of a second curtain box backboard 503 on the second vertical plate line 501 for fixation, and fixing the other end of the second curtain box backboard 503 with the bottom end of the second wood plastic line 504 through screws;
S5, installing a third wood plastic line 604 according to the elastic line position, fixedly installing a third vertical plate line 601 on the lower surface of the high-level plate surface plate 308, hanging a third falling-stage vertical plate 602 on the third vertical plate line 601, then inserting one end of a third curtain box backboard 603 on the third vertical plate line 601 for fixation, and fixing the other end of the third curtain box backboard 603 with the bottom end of the third wood plastic line 604 through screws;
S6, installing the beautifying line 7 at the joint of the first falling-stage vertical plate 402 and the bottom end of the first curtain box backboard 404, the joint of the second falling-stage vertical plate 502 and the bottom end of the second curtain box backboard 503, and the joint of the third falling-stage vertical plate 602 and the bottom end of the third curtain box backboard 603, and finishing edge finishing.
The above description may be implemented alone or in various combinations and these modifications are within the scope of the present invention.
It is noted that relational terms such as first and second, and the like are used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Moreover, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising one …" does not exclude the presence of other like elements in a process, method, article, or apparatus that comprises an element.
The foregoing is a further detailed description of the invention in connection with the preferred embodiments, and it is not intended that the invention be limited to the specific examples described. It will be apparent to those skilled in the art that several simple deductions or substitutions may be made without departing from the spirit of the invention, and these should be considered to be within the scope of the invention.
Claims (10)
1. The assembled type drop ceiling comprises four original wall surfaces (1) and a floor base layer (2) in a room, and is characterized in that the original wall surfaces (1) comprise a first wall surface (101) provided with a window, a second wall surface (102) opposite to the window, a third wall surface (103) opposite to the other two sides, a high-level plate (3) arranged below the floor base layer (2), a ceiling curtain box (4) connected with the high-level plate (3) and the first wall surface (101), a first ceiling drop structure (5) connected with the high-level plate (3) and the second wall surface (102) and a second ceiling drop structure (6) connected with the high-level plate (3) and the third wall surface (103);
The high-level plate (3) comprises an upper top hanging angle steel (301), a lower top hanging angle steel (302), a locking bolt (303), an expansion bolt (304), a square tube (305), a keel hanging piece (306), a plurality of square-shaped keels (307), a high-level plate surface plate (308) and a keel base (309), wherein the top end of the upper top hanging angle steel (301) is fixedly arranged on the lower surface of a floor base layer (2) through the expansion bolt (304), the bottom end of the upper top hanging angle steel (301) and the top end of the lower top hanging angle steel (302) are fixedly locked through the locking bolt (303), the bottom end of the lower top hanging angle steel (302) is in a horizontal state, the square tube (305) is horizontally arranged above the bottom end of the lower top hanging angle steel (302), a plurality of the keel hanging pieces (306) are hung on the square-shaped keels (307) which are horizontally arranged are arranged on the bottom of the keel hanging pieces (306), the square-shaped keels (307) are embedded into the keel base (309) to form a stable structure, and the keel base (309) is fixedly connected with the upper surface of the high-level plate surface plate (308).
The suspended ceiling curtain box (4) is arranged below one side of the high-position plate surface plate (308) close to the first wall surface (101), the suspended ceiling curtain box (4) comprises a first vertical plate line (401), a first falling-level vertical plate (402), a first curtain box backboard (404), a first angle-setting code (405) and a curtain box panel (403) for installing a curtain, the top end of the first vertical plate line (401) is fixedly connected with the high-position plate surface plate (308) through screws, the first falling-level vertical plate (402) is vertically hung at the bottom of the first vertical plate line (401), two clamping grooves are formed in the lower end of the first falling-level vertical plate (402), the first curtain box backboard (404) is fixedly connected with the first falling-level vertical plate (402) through clamping, the top end of the first curtain box backboard (404) is in contact with the bottom surface of the curtain box panel (403), the first falling-level vertical plate (402) is fixedly connected with the curtain box panel (403) through the first angle-setting code (405) through the first angle-setting code (403), and the two sides of the curtain box panel (403) are fixedly connected with the curtain box (405) through the first angle-setting code (405) respectively;
The high-level panel (308) is close to the lower side of one side of the second wall surface (102) and is provided with a first suspended ceiling falling-level structure (5), the first suspended ceiling falling-level structure (5) comprises a second vertical plate line (501), a second falling-level vertical plate (502), a second curtain box backboard (503) and a second wood-plastic line (504), the top end of the second vertical plate line (501) is fixedly connected with the high-level panel (308) through screws, the second falling-level vertical plate (502) is vertically hung at the bottom of the second vertical plate line (501), one side of the second falling-level vertical plate (502) is provided with two clamping grooves, one end of the second curtain box backboard (503) is fixedly clamped with the second falling-level vertical plate (502), the other end of the second curtain box backboard (503) is fixedly connected with the second wood-plastic line (504) through screws, and the second wood-plastic line (504) is fixedly connected with the second wall surface (102) through screws;
The high-level board (308) is close to a second suspended ceiling falling structure (6) is arranged below one side of the third wall surface (103), the second suspended ceiling falling structure (6) comprises a third vertical board line (601), a third falling vertical board (602), a third curtain box backboard (603) and a third wood-plastic line (604), the top end of the third vertical board line (601) is fixedly connected with the high-level board (308) through screws, the third falling vertical board (602) is vertically hung at the bottom of the third vertical board line (601), two clamping grooves are formed in one side of the third falling vertical board (602), one end of the third curtain box backboard (603) is fixedly clamped with the third falling vertical board (602), the other end of the third curtain box backboard (603) is fixedly connected with the third wood-plastic line (604) through screws, and the third wood-plastic line (604) is fixedly connected with the third wall surface (103) through screws.
2. The assembled drop ceiling of claim 1, wherein two ends of the first drop floor (402) respectively collide with two sides of the third wall surface (103), two ends of the third drop floor (602) respectively collide with the first drop floor (402) and the second wall surface (102), and two ends of the second drop floor (502) respectively collide with two sides of the third drop floor (602).
3. The assembled drop ceiling of claim 2, wherein the first box back (404) is the same length as the first drop riser (402), the second box back (503) and the second wood-plastic strip (504) are the same length as the second drop riser (502), and the third box back (603) and the third wood-plastic strip (604) are the same length as the third drop riser (602).
4. The assembled drop ceiling according to claim 1, wherein the curtain box panel (403) comprises a fourth keel (4031), a fourth keel base (4032) and a low-level plate (4033), the fourth keel (4031) is embedded into the fourth keel base (4032) to form a stable structure, the fourth keel base (4032) is fixedly connected with the low-level plate (4033), and one side of the low-level plate (4033) is fixedly connected with the first corner bracket (405) through screws.
5. The assembled drop ceiling according to claim 4, wherein the lower plate (4033) is close to two ends of the third wall surface (103) and is provided with horizontally arranged edge collecting pieces (4034), one side of each edge collecting piece (4034) is fixedly connected with the third wall surface (103), wood strips (4035) are arranged in the fourth Chinese character 'ji' keels (4031) in a penetrating manner, the wood strips (4035) extend out of two ends of the fourth Chinese character 'ji' keels (4031), and two ends of each wood strip (4035) are respectively overlapped and fixed with the edge collecting pieces (4034) of the third wall surface (103) on two sides.
6. The fabricated drop ceiling of claim 5, wherein said trim piece (4034) is an aluminum trim piece.
7. The fabricated drop ceiling of claim 1, wherein the second wood-plastic strand (504) and the third wood-plastic strand (604) are each porous hollow structures.
8. The assembled drop ceiling according to claim 1, further comprising a beautifying line (7), wherein the beautifying line (7) is fixedly connected to the junction of the first drop floor (402) and the bottom end of the first curtain box back plate (404), the junction of the second drop floor (502) and the bottom end of the second curtain box back plate (503), and the junction of the third drop floor (602) and the bottom end of the third curtain box back plate (603).
9. The assembled drop ceiling according to claim 1, wherein two sides of the high-level board panels (308) are provided with clamping grooves (8), and clamping blocks (9) are clamped in the clamping grooves (8) between two adjacent high-level board panels (308).
10. The method for installing a fabricated drop ceiling according to any one of claims 1-9, comprising the steps of:
S1, snapping wires on an original wall surface (1) and a floor base layer (2), fixedly mounting an upper top hanging angle steel (301) on the lower surface of the floor base layer (2) according to expansion bolts (304) for snapping wires, then fixing the upper top hanging angle steel (301) and a lower top hanging angle steel (302) by locking bolts (303) and leveling, and placing a square tube (305) on the lower top hanging angle steel (302);
S2, splicing high-level plate panels (308) on the ground, inserting the Chinese character 'ji' shaped keels (307) into the keel hanging pieces (306), embedding the Chinese character 'ji' shaped keels (307) into the keel bases (309), fixedly mounting the keel bases (309) on the upper surfaces of the high-level plate panels (308), sequentially assembling all the high-level plate panels (308) into a whole, and then lifting the high-level plate (3) integrally, so that the keel hanging pieces (306) are hung on the square pipes (305);
s3, fixedly mounting a first riser line (401) on the lower surface of a high-level panel (308), hanging a first falling riser (402) on the first riser line (401), and then assembling a curtain box panel (403): embedding a fourth Chinese character 'ji' shaped keel (4031) into a fourth keel base (4032), fixing the fourth keel base (4032) on the upper surface of a low-level plate (4033), inserting a batten (4035) into the fourth Chinese character 'ji' shaped keel (4031), lifting the assembled curtain box panel (403) integrally so that two ends of the batten (4035) are lapped above a edging piece (4034), fixing the low-level plate (4033) and a first falling-level vertical plate (402) through a first corner bracket (405), and finally inserting a first curtain box backboard (404) onto the first falling-level vertical plate (402);
s4, installing a second wood plastic line (504) according to the elastic line position, fixedly installing a second vertical plate line (501) on the lower surface of the high-level plate surface plate (308), hanging a second falling-level vertical plate (502) on the second vertical plate line (501), then inserting one end of a second curtain box backboard (503) on the second vertical plate line (501) for fixation, and fixing the other end of the second curtain box backboard (503) with the bottom end of the second wood plastic line (504) through screws;
S5, installing a third wood plastic line (604) according to the elastic line position, fixedly installing a third vertical plate line (601) on the lower surface of a high-level plate surface plate (308), hanging a third falling-level vertical plate (602) on the third vertical plate line (601), then inserting one end of a third curtain box backboard (603) on the third vertical plate line (601) for fixation, and fixing the other end of the third curtain box backboard (603) with the bottom end of the third wood plastic line (604) through a screw;
S6, installing the beautifying lines (7) at the joint of the first falling-stage vertical plate (402) and the bottom end of the first curtain box backboard (404), at the joint of the second falling-stage vertical plate (502) and the bottom end of the second curtain box backboard (503), and at the joint of the third falling-stage vertical plate (602) and the bottom end of the third curtain box backboard (603) respectively, and finishing edge finishing.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202110070120.9A CN113323222B (en) | 2021-01-19 | 2021-01-19 | Assembled type drop suspended ceiling and installation method thereof |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202110070120.9A CN113323222B (en) | 2021-01-19 | 2021-01-19 | Assembled type drop suspended ceiling and installation method thereof |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN113323222A CN113323222A (en) | 2021-08-31 |
| CN113323222B true CN113323222B (en) | 2024-09-06 |
Family
ID=77413532
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202110070120.9A Active CN113323222B (en) | 2021-01-19 | 2021-01-19 | Assembled type drop suspended ceiling and installation method thereof |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN113323222B (en) |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113653256A (en) * | 2021-09-15 | 2021-11-16 | 浙江亚厦装饰股份有限公司 | A kind of prefabricated residential drop ceiling and installation method |
| CN113789903B (en) * | 2021-09-15 | 2024-09-06 | 浙江亚厦装饰股份有限公司 | Assembled drop-level suspended ceiling with curtain box hung downwards |
| CN113789902B (en) * | 2021-09-15 | 2024-09-06 | 浙江亚厦装饰股份有限公司 | Assembled suspended ceiling with curtain box hung downwards |
| CN116919138B (en) * | 2023-07-18 | 2025-12-12 | 湖北中建三局建筑工程技术有限责任公司 | A curtain box system for glass curtain walls |
Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN214614943U (en) * | 2021-01-19 | 2021-11-05 | 浙江亚厦装饰股份有限公司 | Assembled falls a grade furred ceiling |
Family Cites Families (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105569251B (en) * | 2016-02-04 | 2017-05-03 | 浙江亚厦装饰股份有限公司 | Device for split-level ceiling and installation method |
| CN106988470B (en) * | 2017-05-27 | 2024-02-06 | 上海聚通装饰集团有限公司 | Light steel keel small-step suspended ceiling and construction method |
| CN108049552B (en) * | 2017-12-30 | 2023-11-10 | 浙江亚厦装饰股份有限公司 | Top-mounted drop-grade ceiling and installation method |
| CN207974318U (en) * | 2017-12-30 | 2018-10-16 | 浙江亚厦装饰股份有限公司 | Wall hangs drop level furred ceiling |
-
2021
- 2021-01-19 CN CN202110070120.9A patent/CN113323222B/en active Active
Patent Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN214614943U (en) * | 2021-01-19 | 2021-11-05 | 浙江亚厦装饰股份有限公司 | Assembled falls a grade furred ceiling |
Also Published As
| Publication number | Publication date |
|---|---|
| CN113323222A (en) | 2021-08-31 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN113323261B (en) | Assembled suspension rod-free suspended ceiling structure and installation method thereof | |
| US7017317B2 (en) | Decorative ceiling panel and fastening system | |
| US4667450A (en) | Unitized partition system | |
| CN113323222A (en) | Assembled drop ceiling and installation method thereof | |
| CN110241951A (en) | A fast-assembled prefabricated partition wall installation structure | |
| US3417530A (en) | Suspended ceiling system | |
| CN112814308A (en) | Wall and floor integral decoration structure and installation method thereof | |
| US20030182894A1 (en) | Method of installing a set of ceiling panels | |
| AU2010249136B2 (en) | A mounting bracket for panels of a partition wall, and partition walls constructed using the mounting bracket | |
| CN113323250B (en) | Assembled double-layer keel structure and installation method thereof | |
| CN215368147U (en) | Assembled suspended ceiling without suspender | |
| CN215888920U (en) | Assembled does not have jib furred ceiling structure | |
| CN215759920U (en) | Extrusion material ceiling structure | |
| CN214614943U (en) | Assembled falls a grade furred ceiling | |
| CN215888793U (en) | Assembled furred ceiling suitable for level floor | |
| CN214614967U (en) | Assembled double-deck keel structure | |
| CN112922220B (en) | Ceiling structure with lamp groove and construction method thereof | |
| CN217399993U (en) | Energy-saving assembled building structure | |
| CN215889035U (en) | Wall ground integral decoration structure | |
| CN215583814U (en) | Assembled furred ceiling curtain box | |
| CN113323225B (en) | Assembled suspended ceiling without suspender and installation method thereof | |
| CN212427736U (en) | Suspended ceiling assembly | |
| CN116201310A (en) | A prefabricated suspended concave-convex modeling background wall system | |
| CN113317671B (en) | Assembled ceiling curtain box and installation method thereof | |
| CN215368146U (en) | Assembled type level-falling modeling structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |