CN113308952B - Construction method of fabricated retaining wall bridgehead foam concrete light embankment - Google Patents
Construction method of fabricated retaining wall bridgehead foam concrete light embankment Download PDFInfo
- Publication number
- CN113308952B CN113308952B CN202110527804.7A CN202110527804A CN113308952B CN 113308952 B CN113308952 B CN 113308952B CN 202110527804 A CN202110527804 A CN 202110527804A CN 113308952 B CN113308952 B CN 113308952B
- Authority
- CN
- China
- Prior art keywords
- retaining wall
- concrete
- construction
- prefabricated
- strip
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 73
- 239000011381 foam concrete Substances 0.000 title claims abstract description 45
- 239000004567 concrete Substances 0.000 claims abstract description 70
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 46
- 239000010959 steel Substances 0.000 claims abstract description 46
- 238000009415 formwork Methods 0.000 claims abstract description 45
- 238000009434 installation Methods 0.000 claims abstract description 9
- 239000006260 foam Substances 0.000 claims description 11
- 230000001360 synchronised effect Effects 0.000 claims description 8
- 239000003795 chemical substances by application Substances 0.000 claims description 3
- 239000011505 plaster Substances 0.000 claims description 3
- 238000009417 prefabrication Methods 0.000 claims description 3
- 239000004575 stone Substances 0.000 claims description 3
- 238000005516 engineering process Methods 0.000 abstract description 6
- 230000009286 beneficial effect Effects 0.000 abstract description 2
- 230000002787 reinforcement Effects 0.000 abstract description 2
- 230000010485 coping Effects 0.000 abstract 1
- 230000001681 protective effect Effects 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 6
- 238000004513 sizing Methods 0.000 description 4
- 238000000034 method Methods 0.000 description 3
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 239000011449 brick Substances 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000009191 jumping Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000003973 paint Substances 0.000 description 1
- 238000007493 shaping process Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C3/00—Foundations for pavings
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C3/00—Foundations for pavings
- E01C3/04—Foundations produced by soil stabilisation
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/02—Piers; Abutments ; Protecting same against drifting ice
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/18—Making embankments, e.g. dikes, dams
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0258—Retaining or protecting walls characterised by constructional features
- E02D29/0266—Retaining or protecting walls characterised by constructional features made up of preformed elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G1/00—Scaffolds primarily resting on the ground
- E04G1/15—Scaffolds primarily resting on the ground essentially comprising special means for supporting or forming platforms; Platforms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G1/00—Scaffolds primarily resting on the ground
- E04G1/18—Scaffolds primarily resting on the ground adjustable in height
- E04G1/22—Scaffolds having a platform on an extensible substructure, e.g. of telescopic type or with lazy-tongs mechanism
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G1/00—Scaffolds primarily resting on the ground
- E04G1/24—Scaffolds primarily resting on the ground comprising essentially special base constructions; comprising essentially special ground-engaging parts, e.g. inclined struts, wheels
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G1/00—Scaffolds primarily resting on the ground
- E04G1/36—Scaffolds for particular parts of buildings or buildings of particular shape, e.g. for stairs, cupolas, domes
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0018—Cement used as binder
- E02D2300/002—Concrete
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/20—Miscellaneous comprising details of connection between elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Mechanical Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域technical field
本发明涉及一种装配式护壁桥头泡沫混凝土轻质路堤的施工方法,主要适用于桥头段轻质路堤施工。The invention relates to a construction method of a foam concrete lightweight embankment at a bridgehead with an assembled wall protection, which is mainly suitable for the construction of a lightweight embankment at a bridgehead section.
背景技术Background technique
随着我国各地公路桥梁建设迅猛发展,路桥建设过程中桥梁、涵洞等公路构造物的数量也在不断增加,此类构造物在投入运营后,桥台与台背回填路段易出现差异沉降、路堤失稳等工程问题,严重影响公路工程建设中的经济效益。轻质泡沫混凝土是近年来应用到公路工程领域的一项新型轻质填筑材料,具有质量轻、强度高、流动性强、自立性好、施工方便等特性,在公路路堤填筑中的应用也越来越广泛。With the rapid development of road and bridge construction in various parts of my country, the number of road structures such as bridges and culverts in the process of road and bridge construction is also increasing. Instability and other engineering problems have seriously affected the economic benefits of highway construction. Lightweight foam concrete is a new type of lightweight filling material that has been applied to the field of highway engineering in recent years. It has the characteristics of light weight, high strength, strong fluidity, good self-support, and convenient construction. is also becoming more widespread.
采用轻质泡沫混凝土不仅能很好地解决地基沉降和结构物的不均匀沉降,还能有效地避免桥头跳车的发生,轻质泡沫混凝土作为桥台台背填筑的新型绿色材料,为桥台台背填筑提供了一种新的技术,但该技术施工时,桥台护壁一般采用砖砌或者现浇混凝土的形式,待养护达到一定强度后才能进行后续施工,由于目前装配式技术在工程施工中越来越广泛,通过装配式技术可大幅加快施工质量及施工效率。The use of lightweight foam concrete can not only solve the foundation settlement and the uneven settlement of structures, but also effectively avoid the occurrence of vehicle jumping at the bridge head. The abutment back filling provides a new technology, but when this technology is constructed, the abutment retaining wall is generally in the form of brick or cast-in-place concrete, and subsequent construction can only be carried out after the maintenance reaches a certain strength. Engineering construction is becoming more and more widespread, and the construction quality and construction efficiency can be greatly accelerated through assembly technology.
鉴于此,为了提高桥头泡沫混凝土轻质路堤的施工质量及施工效率,充分发挥泡沫混凝土的优点并配合最新的装配式技术,亟待发明一种简单有效的装配式护壁桥头泡沫混凝土轻质路堤的施工方法。In view of this, in order to improve the construction quality and construction efficiency of the foam concrete light embankment at the bridge head, give full play to the advantages of foam concrete and cooperate with the latest assembly technology, it is urgent to invent a simple and effective construction of the foam concrete light embankment at the bridge head with retaining walls method.
发明内容Contents of the invention
本发明的目的是克服现有技术中的不足,提供一种装配式护壁桥头泡沫混凝土轻质路堤的施工方法,提高桥头泡沫混凝土轻质路堤的施工质量及施工效率,具有较好的技术经济效益。The purpose of the present invention is to overcome the deficiencies in the prior art, provide a construction method of the foam concrete lightweight embankment at the head of the bridge retaining wall, improve the construction quality and construction efficiency of the foam concrete light embankment at the bridge head, and have better technical and economic benefits .
这种装配式护壁桥头泡沫混凝土轻质路堤,包括桩柱式桥台、条基垫层、装配式条形混凝土基础、装配式护壁、护壁预埋抱箍、泡沫混凝土、混凝土压顶、钢管立柱、泡沫塑料板和填土路基,所述桩柱式桥台一侧设置装配式条形混凝土基础,所述装配式条形混凝土基础下部设置条基垫层,条基垫层上设置预埋铆钉用于固定装配式条形混凝土基础,装配式条形混凝土基础上部的预留槽口设置装配式护壁,该槽口一侧设置的预埋套筒内置入钢管立柱,所述钢管立柱间设置系杆,钢管立柱与系杆通过限位卡扣固定,所述装配式护壁上部设置混凝土压顶,装配式护壁一侧设置与钢管立柱相对应的护壁预留槽口,装配式护壁上部设置护壁预埋抱箍钢筋用以与桩柱式桥台固定,变形缝内设置单侧支模体系,装配式护壁与填土路基之间浇筑泡沫混凝土。This prefabricated retaining wall bridge head foam concrete lightweight embankment includes pile-column abutment, strip foundation cushion, fabricated strip concrete foundation, fabricated retaining wall, pre-embedded hoop for retaining wall, foam concrete, concrete capping, steel pipe column, Foam plastic board and filled soil subgrade, one side of the pile-type abutment is provided with a prefabricated strip concrete foundation, the lower part of the prefabricated strip concrete foundation is provided with a strip base cushion, and the strip base cushion is provided with pre-embedded rivets. On the fixed assembled strip concrete foundation, the reserved slot on the upper part of the assembled strip concrete foundation is provided with an assembled retaining wall, and the pre-embedded sleeve set on one side of the slot is inserted into the steel pipe column, and the steel pipe column is provided with a tie rod , the steel pipe column and the tie rod are fixed by limit buckles, the upper part of the assembled retaining wall is provided with a concrete top, one side of the assembled retaining wall is provided with a reserved notch corresponding to the steel pipe column, and the upper part of the assembled retaining wall is provided with a pre-buried retaining wall The hoop steel bars are used to fix the pile-type abutment, the single-side formwork system is set in the deformation joint, and the foam concrete is poured between the prefabricated retaining wall and the filled subgrade.
作为优选:所述装配式条形混凝土基础两端设置企口,企口处设置预埋钢筋或预留孔,预留孔上设置注浆孔,装配式条形混凝土基础底部设置条基预留铆钉孔并与条基垫层的预埋铆钉配合连接。As a preference: the two ends of the prefabricated strip concrete foundation are provided with rebates, pre-embedded steel bars or reserved holes are provided at the rebates, grouting holes are provided on the reserved holes, and strip foundations are provided at the bottom of the prefabricated strip concrete foundation. The rivet holes are connected with the pre-embedded rivets of the strip base cushion.
作为优选:所述钢管立柱内嵌于装配式护壁上的护壁预留槽口内,系杆外侧设置临时剪刀撑,所述临时剪刀撑一侧设置临时斜撑,临时斜撑底部设置锚板,锚板通过固定钉与原地面固定。As a preference: the steel pipe column is embedded in the reserved notch on the prefabricated retaining wall, a temporary scissors brace is arranged on the outside of the tie bar, a temporary diagonal brace is arranged on one side of the temporary scissors brace, and an anchor plate is arranged at the bottom of the temporary diagonal brace. The board is fixed to the original ground by fixing nails.
作为优选:所述单侧支模体系包括泡沫塑料板、单侧模板和旋转式斜撑,变形缝处设置泡沫塑料板,泡沫塑料板外侧设置单侧模板,单侧模板上设置斜撑垫板,原地面与单侧模板上的斜撑垫板间设置旋转式斜撑,单侧模板底部设置临时固定螺栓。As a preference: the single-side formwork system includes a foam plastic board, a single-side formwork and a rotary diagonal brace, a foam plastic board is arranged at the deformation joint, a single-side formwork is arranged on the outside of the foam plastic board, and a diagonal brace backing plate is arranged on the single-side formwork , Rotary diagonal braces are set between the original ground and the diagonal brace plate on the one-side formwork, and temporary fixing bolts are set at the bottom of the one-side formwork.
作为优选:还包括泡沫混凝土多管同步浇筑整体式提升移动架,所述泡沫混凝土多管同步浇筑整体式提升移动架由可锁式滚轮、支撑杆、伸缩式装置、可拆卸爬梯、立柱、对撑、施工平台、栏板和可开启式栏杆组成,立柱底部设置可锁式滚轮,立柱中部设置伸缩式装置,立柱之间设置对撑,伸缩式装置之间设置支撑杆,立柱上部设置施工平台,施工平台上部设置栏板,施工平台上方的立柱之间设置固定围栏,施工平台上方开口处设置可开启式栏杆,可开启式栏杆下方对应设置可拆卸爬梯。As a preference: it also includes a foam concrete multi-pipe synchronous pouring integral lifting mobile frame, the foam concrete multi-pipe synchronous pouring integral lifting mobile frame is composed of lockable rollers, support rods, telescopic devices, detachable ladders, columns, It is composed of support, construction platform, railing and openable railing. The bottom of the column is equipped with lockable rollers, the middle of the column is equipped with a telescopic device, the columns are provided with braces, the support rods are installed between the telescopic devices, and the upper part of the column is provided with a construction platform. , The upper part of the construction platform is provided with railings, fixed fences are provided between the columns above the construction platform, openable railings are provided at the opening above the construction platform, and detachable ladders are correspondingly provided below the openable railings.
作为优选:所述混凝土压顶两侧设置压顶定型化模具,所述定型化模具上设置对拉螺栓,压顶定型化模具的内侧模板置于泡沫混凝土上,其外侧模板通过对拉螺栓与内侧模板固定。As a preference: the two sides of the concrete topping are provided with topping sizing molds, the sizing molds are provided with pull bolts, the inner formwork of the topping sizing mold is placed on the foam concrete, and the outer formwork is fixed to the inner formwork by the pull bolts .
这种装配式护壁桥头泡沫混凝土轻质路堤的施工方法,包括以下步骤:The construction method of the foam concrete lightweight embankment of the prefabricated retaining bridge head comprises the following steps:
1)构件预制:预制装配式条形混凝土基础及装配式护壁,装配式条形混凝土基础预制时上部均匀设置预埋套筒,并在装配式条形混凝土基础一端设置预埋钢筋,另一端设置预留孔及注浆孔,装配式护壁上对应于预埋套筒设置护壁预留槽口,装配式护壁上根据桩柱式桥台位置预留护壁预埋抱箍钢筋;1) Component prefabrication: prefabricated prefabricated strip concrete foundation and prefabricated retaining wall. When the prefabricated strip concrete foundation is prefabricated, pre-embedded sleeves are evenly arranged on the upper part, and pre-embedded steel bars are set at one end of the prefabricated strip concrete foundation, and the other end is set Reserved holes and grouting holes, on the prefabricated retaining wall corresponding to the pre-embedded sleeve set the reserved notch for the retaining wall, and on the prefabricated retaining wall according to the position of the pile abutment, reserve the pre-embedded hoop reinforcement for the retaining wall;
2)条基垫层施工:桩柱式桥台施工完成后施工条基垫层,混凝土浇筑前在条基垫层内根据装配式条形混凝土基础的条基预留铆钉孔位置设置预埋铆钉;2) Construction of the strip foundation cushion: After the construction of the pile-column abutment is completed, the strip foundation cushion is constructed. Before concrete pouring, pre-embedded rivets are set in the strip foundation cushion according to the positions of the rivet holes reserved for the strip foundation of the fabricated strip concrete foundation. ;
3)装配式条形混凝土基础拼装施工:根据企口拼装装配式条形混凝土基础,装配式条形混凝土基础底部的条基预留铆钉孔准确插入预埋铆钉,并在条基预留铆钉孔内灌入混凝土,预埋套筒内安装钢管立柱;3) Assembled construction of prefabricated strip concrete foundation: According to the tongue-and-groove assembled prefabricated strip concrete foundation, the rivet holes reserved at the bottom of the prefabricated strip concrete foundation are accurately inserted into the pre-embedded rivets, and the rivet holes are reserved in the strip foundation Concrete is poured inside, and steel pipe columns are installed in the pre-embedded sleeve;
4)立柱竖向框架体系施工:钢管立柱间安装水平系杆,并用限位卡扣固定,在系杆外侧安装临时剪刀撑,临时剪刀撑外侧再设置临时斜撑,临时斜撑底部通过固定钉固定于原地面上;4) Construction of the vertical frame system of columns: install horizontal tie rods between steel pipe columns and fix them with limit buckles, install temporary scissors braces on the outside of the tie rods, set temporary diagonal braces outside the temporary scissor braces, and pass the fixing nails at the bottom of the temporary braces fixed on the original ground;
5)装配式护壁拼装:根据钢管立柱及护壁预留槽口位置分块拼装装配式护壁,钢管立柱与护壁预留槽口配合相接,待一块装配式护壁安装完成将其上部预埋的护壁预埋抱箍钢筋绕桩柱式桥台弯折形成抱箍形式,将装配式护壁与桩柱式桥台固定;5) Assembling the prefabricated retaining wall: Assemble the prefabricated retaining wall in pieces according to the position of the steel pipe column and the reserved notch of the retaining wall. The steel pipe column and the reserved notch of the retaining wall are matched and connected. The pre-embedded hoop steel bar is bent around the pile-type abutment to form a hoop, and the assembled retaining wall and the pile-type abutment are fixed;
6)变形缝单侧支模:在需设变形缝位置搭设单侧模板,单侧模板底部用临时固定螺栓固定于原地面上,并在单侧模板内侧沿模板布置一层泡沫塑料板;6) Single-side formwork support for deformation joints: set up a single-side formwork at the position where the deformation joint is required, fix the bottom of the one-side formwork to the original ground with temporary fixing bolts, and arrange a layer of foam plastic board along the formwork inside the single-side formwork;
7)泡沫混凝土浇筑:通过多管同步浇筑整体式提升移动架浇筑泡沫混凝土,首先安装可拆卸爬梯,待工人及浇筑导管就位后卸下爬梯,随浇筑移动或抬高施工平台,完成浇筑;7) Foam concrete pouring: Foam concrete is poured by multi-pipe synchronous pouring integral lifting mobile frame. First, a detachable ladder is installed. After the workers and pouring conduits are in place, the ladder is removed, and the construction platform is moved or raised with the pouring to complete the pouring;
8)混凝土压顶施工:待泡沫混凝土浇筑完成后进行压顶施工,压顶定型化模具的内侧模板置于泡沫混凝土上,其外侧模板通过对拉螺栓与内侧模板固定,安装完成后在对拉螺栓上涂刷脱模剂,并浇筑混凝土形成混凝土压顶;8) Concrete topping construction: After the foam concrete pouring is completed, the topping construction is carried out. The inner formwork of the topping finalized mold is placed on the foam concrete, and the outer formwork is fixed with the inner formwork by the tension bolts. After the installation is completed, paint on the tension bolts. Brush release agent, and pour concrete to form concrete capping;
9)护壁预留槽口抹面:清除护壁预留槽口内松散混凝土并在槽口内用高一强度等级细石混凝土抹面。9) Plastering of the reserved notch of the retaining wall: clear the loose concrete in the reserved notch of the retaining wall and plaster the surface with fine stone concrete of a higher strength grade in the notch.
本发明的有益效果是:The beneficial effects of the present invention are:
1.预制装配式条形混凝土基础采用企口搭接锚地技术,两端基础拼装时注浆加固,大大提高基础施工效率。1. The prefabricated strip concrete foundation adopts the groove-and-groove lap joint anchorage technology, and the two ends of the foundation are assembled and reinforced by grouting, which greatly improves the efficiency of foundation construction.
2.条形基础预埋套筒后续安装钢管立柱行形成竖向框架体系,并通过该体系快速镶嵌安装装配式护壁,钢管立柱与护壁预留槽口精准定位,提高了施工效率和施工质量。2. The pre-embedded sleeve of the strip foundation is followed by the installation of steel pipe columns to form a vertical frame system, and the prefabricated retaining wall is quickly inlaid and installed through this system. The steel pipe pillars and the reserved notches of the retaining wall are precisely positioned, which improves construction efficiency and construction quality.
3.在装配式护壁上预埋抱箍钢筋,待护壁安装完成后将钢筋向桩柱两侧弯折形成抱箍体系,可提高后续混凝土浇筑时结构的整体稳定性。3. Pre-embed hoop steel bars on the prefabricated retaining wall. After the retaining wall is installed, bend the steel bars to both sides of the pile to form a hoop system, which can improve the overall stability of the structure during subsequent concrete pouring.
4.泡沫混凝土分段施工,在变形缝处与模板同时安装泡沫塑料板,加快施工进度。4. Foam concrete is constructed in sections, and foam plastic boards are installed at the deformation joints together with the formwork to speed up the construction progress.
5.泡沫混凝土采用同步浇筑整体式提升移动架多人多管同时浇筑,加快施工进度。5. Foam concrete is poured simultaneously by multiple people and multiple pipes on the integrated lifting mobile frame to speed up the construction progress.
6.装配式护壁顶部混凝土压顶采用快速浇筑定型化模具施工,保证施工质量及施工效率。6. Concrete topping on the top of the prefabricated retaining wall is constructed using rapid pouring stereotyped molds to ensure construction quality and construction efficiency.
附图说明Description of drawings
图1是本发明装配式护壁桥头泡沫混凝土轻质路堤整体结构三维示意图;Fig. 1 is a three-dimensional schematic diagram of the overall structure of the foamed concrete lightweight embankment of the assembled type retaining wall bridge head of the present invention;
图2是本发明装配式护壁桥头泡沫混凝土轻质路堤剖面图;Fig. 2 is a sectional view of the foamed concrete lightweight embankment of the assembled type retaining wall bridge head of the present invention;
图3是装配式条形混凝土基础结构示意图;Fig. 3 is a schematic diagram of the prefabricated strip concrete foundation structure;
图4是装配式条形混凝土基础与垫层连接示意图;Figure 4 is a schematic diagram of the connection between the prefabricated strip concrete foundation and the cushion;
图5是钢管立柱安装三维结构图;Fig. 5 is a three-dimensional structural diagram of steel pipe column installation;
图6是竖向框架体系及护壁抱箍立面图;Figure 6 is an elevation view of the vertical frame system and the retaining hoop;
图7是变形缝单侧支模体系结构示意图;Fig. 7 is a schematic diagram of the single-side support formwork system of the deformation joint;
图8是泡沫混凝土多管同步浇筑整体式提升移动架结构示意图。Fig. 8 is a structural schematic diagram of an integral lifting mobile frame for simultaneous pouring of multiple pipes of foam concrete.
附图标记说明:1.桩柱式桥台、2.条基垫层、3.装配式条形混凝土基础、4.装配式护壁、5.护壁预埋抱箍、6.泡沫混凝土、7.混凝土压顶、8.路床、9.压顶定型化模具、10.对拉螺栓、11.临时剪刀撑、12.系杆、13.临时斜撑、14.护壁预留槽口、15.钢管立柱、16.预埋铆钉、17.路面、18、旋转式斜撑、19.单侧模板、20.临时固定螺栓、21.泡沫塑料板、22.填土路基、23.斜撑垫板、24.预埋套筒、25.企口、26.可锁式滚轮、27.支撑杆、28.伸缩式装置、29、可拆卸爬梯、30.立柱、31.对撑、32.施工平台、33、栏板、34可开启式栏杆、35、固定围栏、36.预埋钢筋、37.预留孔、38.限位卡扣、39.原地面、40.注浆孔、41.锚板、42.固定钉、43.条基预留铆钉孔。Explanation of reference signs: 1. Pile-type abutment, 2. Strip foundation cushion, 3. Prefabricated strip concrete foundation, 4. Prefabricated retaining wall, 5. Pre-embedded hoop for retaining wall, 6. Foam concrete, 7. Concrete topping, 8. Road bed, 9. Topping finalization mold, 10. Pull bolts, 11. Temporary scissors bracing, 12. Tie rods, 13. Temporary diagonal bracing, 14. Reservation notch for retaining wall, 15. Steel pipe column , 16. Embedded rivets, 17. Pavement, 18. Rotary diagonal brace, 19. One-sided formwork, 20. Temporary fixing bolts, 21. Foam plastic board, 22. Filled roadbed, 23. Slant brace plate, 24 .Embedded sleeve, 25. Groove, 26. Lockable roller, 27. Support rod, 28. Telescopic device, 29. Detachable ladder, 30. Column, 31. Support, 32. Construction platform, 33 , fence, 34 openable railing, 35, fixed fence, 36. embedded steel bar, 37. reserved hole, 38. limit buckle, 39. original ground, 40. grouting hole, 41. anchor plate, 42. Fixing nails, 43. Reserve rivet holes for strip base.
具体实施方式Detailed ways
下面结合实施例对本发明做进一步描述。下述实施例的说明只是用于帮助理解本发明。应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以对本发明进行若干改进和修饰,这些改进和修饰也落入本发明权利要求的保护范围内。The present invention will be further described below in conjunction with the examples. The description of the following examples is provided only to aid the understanding of the present invention. It should be pointed out that for those skilled in the art, without departing from the principle of the present invention, some improvements and modifications can be made to the present invention, and these improvements and modifications also fall within the protection scope of the claims of the present invention.
实施例一Embodiment one
如图1-2所示装配式护壁桥头泡沫混凝土轻质路堤,包括桩柱式桥台1、条基垫层2、装配式条形混凝土基础3、装配式护壁4、护壁预埋抱箍5、泡沫混凝土6、混凝土压顶7、压顶定型化模具9、钢管立柱15、旋转式斜撑18、单侧模板19、泡沫塑料板21、填土路基22等,所述桩柱式桥台1一侧设置装配式条形混凝土基础3,所述装配式条形混凝土基础3下部设置条基垫层2,条基垫层2上设置预埋铆钉16用于固定装配式条形混凝土基础3,装配式条形混凝土基础3上部的预留槽口设置装配式护壁4,该槽口一侧设置的预埋套筒24内置入钢管立柱15,钢管立柱15间设置系杆12,两者采用限位卡扣38固定。装配式护壁4上部设置混凝土压顶7,装配式护壁4一侧设置与钢管立柱15相对应的护壁预留槽口14,装配式护壁4上部设置护壁预埋抱箍5钢筋用以与桩柱式桥台1固定,混凝土压顶7施工时两侧设置压顶定型化模具9,定型化模具9上设置对拉螺栓10。As shown in Figure 1-2, the foam concrete lightweight embankment of the prefabricated retaining wall bridge head includes
如图3-4所示,装配式条形混凝土基础3两端设置企口25用于拼装,企口25处设置预埋钢筋36或预留孔37,预留孔37上设置注浆孔40,装配式条形混凝土基础3底部设置条基预留铆钉孔43与条基垫层2拼装。As shown in Figure 3-4,
如图5所示,装配式条形混凝土基础3上的预埋套筒24用于安装钢管立柱15,钢管立柱15间设置系杆12,两者通过限位卡扣38固定。As shown in FIG. 5 , the embedded
如图6所示,钢管立柱15内嵌于装配式护壁4上的护壁预留槽口14内,钢管立柱15上设置系杆12,系杆12外侧设置临时剪刀撑11,临时剪刀撑11一侧设置临时斜撑13,临时斜撑13底部设置锚板41,设置固定钉42将锚板41与原地面39固定。As shown in Figure 6, the
如图7所示,变形缝内设置单侧支模体系,单侧支模体系包括泡沫塑料板21、单侧模板19和旋转式斜撑18,变形缝处设置泡沫塑料板21,泡沫塑料板21外侧设置单侧模板19,单侧模板19上设置斜撑垫板23,原地面39与单侧模板19的斜撑垫板23间设置旋转式斜撑18,单侧模板19底部设置临时固定螺栓20。As shown in Figure 7, a unilateral formwork system is set in the deformation joint, and the unilateral formwork system includes a foamed
如图8所示,泡沫混凝土浇筑时采用泡沫混凝土多管同步浇筑整体式提升移动架,所述泡沫混凝土多管同步浇筑整体式提升移动架由可锁式滚轮26、支撑杆27、伸缩式装置28、可拆卸爬梯29、立柱30、对撑31、施工平台32、栏板33、可开启式栏杆34等组成,立柱30底部设置可锁式滚轮26,立柱30中部设置伸缩式装置28,立柱30之间设置对撑31,伸缩式装置28之间设置支撑杆27,立柱30上部设置施工平台32,施工平台32上部设置栏板33,施工平台32上方的立柱30之间设置固定围栏35,施工平台32上方开口处设置可开启式栏杆34,可开启式栏杆34下方对应设置可拆卸爬梯29,待工人就位后爬梯可拆卸,便于施工平台32移动,伸缩式装置可使施工平台32上下移动,可锁式滚轮26可使施工平台32左右移动,可由多个工人四周同步浇筑施工。As shown in Figure 8, the foam concrete multi-pipe synchronous pouring integral lifting mobile frame is adopted when the foam concrete is poured, and the foam concrete multi-pipe synchronous pouring integral lifting mobile frame is composed of
实施例二Embodiment two
本发明还提供一种装配式护壁桥头泡沫混凝土轻质路堤的施工方法,装配式护壁基础采用预制装配式施工,条形基础预埋套筒后安装钢管立柱形成护壁竖向框架支撑体系,装配式护壁配合竖向框架体系快速镶嵌安装,装配式护壁预埋抱箍钢筋与桩柱形成抱箍临时支撑体系,变形缝处设置泡沫塑料板同步单侧支模浇筑泡沫混凝土,泡沫混凝土浇筑时采用多管同步浇筑整体式移动架施工,混凝土压顶采用快速浇筑定型化模具施工。具体包括以下步骤:The present invention also provides a construction method for a lightweight foam concrete embankment at the head of a prefabricated retaining wall. The foundation of the prefabricated retaining wall adopts a prefabricated construction. After the strip foundation is pre-embedded with a sleeve, steel pipe columns are installed to form a vertical frame support system for the retaining wall. The retaining wall is quickly embedded and installed with the vertical frame system. The pre-embedded hoop steel bars and piles in the prefabricated retaining wall form a temporary hoop support system. The integral mobile frame is constructed by simultaneous pouring of pipes, and the concrete topping is constructed by rapid pouring and stereotyped molds. Specifically include the following steps:
(1)构件预制:装配式条形混凝土基础3及装配式护壁4根据图纸精确预制,条基预制时上部均匀设置预埋套筒24,并在条基一端设置预埋钢筋36,另一端设置预留孔37及注浆孔40,装配式护壁4上对应于预埋套筒24设置护壁预留槽口14,装配式护壁4上根据桩柱式桥台柱位置预留护壁预埋抱箍5钢筋。(1) Component prefabrication: Prefabricated strip
(2)条基垫层施工:桥台柱施工完成后施工条基垫层2,混凝土浇筑前在垫层内根据条基预留孔位置设置预埋铆钉16。(2) Construction of the foundation cushion: After the construction of the abutment columns is completed, construct the
(3)装配式条形混凝土基础拼装施工:根据企口25拼装装配式条形混凝土基础3,装配式条形混凝土基础3底部的条基预留铆钉孔43准确插入预埋铆钉16,在预留孔内灌入混凝土,预埋套筒24内安装钢管立柱15。(3) Assembled construction of the prefabricated strip concrete foundation: Assemble the prefabricated strip
(4)立柱竖向框架体系施工:钢管立柱15间安装水平系杆12,并用限位卡扣38固定,在系杆12外侧安装临时剪刀撑11,剪刀撑外侧再设置临时斜撑13,临时斜撑13底部通过固定钉42固定于原地面39上。(4) Construction of the vertical frame system of columns: install
(5)装配式护壁拼装:根据钢管立柱15及护壁预留槽口14位置分块拼装装配式护壁4,钢管立柱15与护壁预留槽口14配合相接,待一块装配式护壁4安装完成将其上部预埋的护壁预埋抱箍5钢筋绕桩柱式桥台1弯折形成抱箍形式,用于将装配式护壁4与桩柱式桥台1固定。(5) Assembling the prefabricated retaining wall: according to the position of the
(6)变形缝单侧支模:在需设变形缝位置搭设单侧模板19,模板底部用临时固定螺栓20固定于原地面39上,并在模板内侧沿模板布置一层泡沫塑料板21。(6) Single-side formwork support for deformation joints: Set up a single-
(7)泡沫混凝土浇筑:通过多管同步浇筑整体式提升移动架浇筑泡沫混凝土,首先安装可拆卸爬梯29,待工人及浇筑导管就位后卸下爬梯,随浇筑移动或抬高施工平台32,快速完成浇筑。(7) Foamed concrete pouring: pouring foamed concrete through multi-pipe synchronous pouring integral lifting mobile frame, first install
(8)混凝土压顶施工:待泡沫混凝土浇筑完成后进行压顶施工,压顶定型化模具9的内侧模板置于泡沫混凝土6上,其外侧模板通过对拉螺栓10与内侧模板固定,安装完成后在对拉螺栓10上涂刷脱模剂,并浇筑混凝土形成混凝土压顶7。(8) Concrete topping construction: After the foam concrete pouring is completed, the topping construction is carried out. The inner formwork of the
(9)护壁预留槽口抹面:清除护壁预留槽口14内松散混凝土并在槽口内用高一强度等级细石混凝土抹面。(9) Plastering of the reserved notch for the retaining wall: clear the loose concrete in the
护壁与其基础工厂预制,运至施工现场快速镶嵌拼装施工,并设置多道临时支撑,提高施工安全性;施工段单侧支模并置入泡沫塑料板,泡沫混凝土浇筑时采用多管同步浇筑整体式提升移动架,提高泡沫混凝土浇筑施工效率。The retaining wall and its foundation are prefabricated in the factory, transported to the construction site for quick mosaic assembly construction, and multiple temporary supports are set up to improve construction safety; the construction section supports formwork on one side and puts foam plastic boards, and multi-pipe synchronous pouring is used when pouring foam concrete as a whole The lifting mobile frame can improve the construction efficiency of foam concrete pouring.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202110527804.7A CN113308952B (en) | 2021-05-14 | 2021-05-14 | Construction method of fabricated retaining wall bridgehead foam concrete light embankment |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202110527804.7A CN113308952B (en) | 2021-05-14 | 2021-05-14 | Construction method of fabricated retaining wall bridgehead foam concrete light embankment |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN113308952A CN113308952A (en) | 2021-08-27 |
| CN113308952B true CN113308952B (en) | 2023-03-31 |
Family
ID=77373217
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202110527804.7A Active CN113308952B (en) | 2021-05-14 | 2021-05-14 | Construction method of fabricated retaining wall bridgehead foam concrete light embankment |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN113308952B (en) |
Family Cites Families (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP3645229B2 (en) * | 2002-04-22 | 2005-05-11 | ケイコン株式会社 | Speed prefab greening method and its retaining wall block |
| CN104652470B (en) * | 2014-12-24 | 2016-08-10 | 中交第二公路勘察设计研究院有限公司 | Light-duty self-anchored type prefabricated reinforced concrete retaining wall and construction method |
| CN106013200B (en) * | 2016-06-29 | 2018-06-05 | 山东远博建筑科技有限公司 | A kind of prefabricated assembled strip footing and construction technology |
| CN107805987A (en) * | 2017-09-14 | 2018-03-16 | 中交第公路勘察设计研究院有限公司 | The hassock layer Foam lightweight soil road structure and construction method in deep soft foundation section |
| CN108708239B (en) * | 2018-07-28 | 2025-02-14 | 新疆维吾尔自治区交通规划勘察设计研究院 | A geogrid steep slope embankment structure and construction method |
| CN210439090U (en) * | 2019-03-19 | 2020-05-01 | 贵州智华建设工程有限责任公司 | A structure for building or widening a high embankment |
-
2021
- 2021-05-14 CN CN202110527804.7A patent/CN113308952B/en active Active
Also Published As
| Publication number | Publication date |
|---|---|
| CN113308952A (en) | 2021-08-27 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR102321338B1 (en) | Segmental precast concrete ventilating slabs of structure and construction way in tunnel for rapid installation | |
| CN108824220A (en) | A kind of cast-in-place support and construction method of the rigid structure of cantilever T-type | |
| CN108265885B (en) | Construction method of high-large non-orthogonal large-inclination-angle special-shaped concrete inclined column | |
| CN107905114A (en) | A kind of construction method of large span Successive interference cancellation | |
| CN107354953B (en) | Concrete rib band and the reinforced Retaining wall structure of intensive aspect and construction method | |
| CN104060629A (en) | Covered top-down excavation subway station overlapped wall construction method and movable side wall formwork jumbo | |
| CN111155385B (en) | Treatment structure and construction method of newly added retaining wall for large deformation subgrade in active service | |
| CN106835992B (en) | Construction method of arc-shaped structure bare concrete cast-in-place box girder | |
| CN112211113A (en) | Cast-in-place construction method for large-span diamond-shaped bent cap of high pier | |
| CN105200925A (en) | Construction method of ultra-wide main arch ring of large span open-spandrel type arch bridge in extremely-cold regions | |
| CN114059585A (en) | Construction method of unilateral aluminum mould of subway side wall tripod | |
| CN112832079A (en) | Construction method of highway embankment with foam lightweight soil combined with width and height | |
| CN112554077A (en) | Steel pipe concrete assembled truss composite beam construction system and construction method | |
| CN203924116U (en) | Portable side wall formwork jumbo | |
| CN113279334B (en) | Construction method of one-step pouring molding system of double-column type vase pier steel template | |
| CN105952140B (en) | Tool-type steel framework Wood-plastic formwork system and its construction technology for cast-in-place concrete | |
| CN114790690A (en) | Synchronous construction method for tie beam and pier body in hydraulic creeping formwork high pier | |
| CN113308952B (en) | Construction method of fabricated retaining wall bridgehead foam concrete light embankment | |
| CN215051681U (en) | Assembled dado bridgehead foam concrete light embankment | |
| CN104164882B (en) | Side slope builds construction method and the structure on supporting and protection structure beam basis | |
| CN115538316A (en) | A kind of pier construction method | |
| CN102828506A (en) | Ultra-deep large-section square support pile and construction method thereof | |
| CN214168790U (en) | Concrete-filled steel tube assembled truss composite beam construction system | |
| CN115492371A (en) | Installation method of multi-curved-surface combined high and large template | |
| CN216689105U (en) | Cast-in-place box culvert and template support system thereof |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |