CN113153384A - Construction method for deep-buried subway station under rock geology - Google Patents
Construction method for deep-buried subway station under rock geology Download PDFInfo
- Publication number
- CN113153384A CN113153384A CN202110314801.5A CN202110314801A CN113153384A CN 113153384 A CN113153384 A CN 113153384A CN 202110314801 A CN202110314801 A CN 202110314801A CN 113153384 A CN113153384 A CN 113153384A
- Authority
- CN
- China
- Prior art keywords
- station
- layer
- construction
- excavating
- rock soil
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000011435 rock Substances 0.000 title claims abstract description 52
- 238000010276 construction Methods 0.000 title claims abstract description 51
- 239000002689 soil Substances 0.000 claims abstract description 39
- 238000009412 basement excavation Methods 0.000 claims abstract description 26
- 239000002893 slag Substances 0.000 claims abstract description 13
- 238000005553 drilling Methods 0.000 claims abstract description 9
- 210000003660 Reticulum Anatomy 0.000 claims abstract description 8
- 238000005192 partition Methods 0.000 claims description 10
- 230000002787 reinforcement Effects 0.000 claims description 5
- 230000000694 effects Effects 0.000 abstract 1
- 230000002093 peripheral Effects 0.000 abstract 1
- 238000000034 method Methods 0.000 description 5
- 238000005422 blasting Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D13/00—Large underground chambers; Methods or apparatus for making them
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/105—Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
Abstract
The invention relates to a construction method of a deep-buried subway station under rock geology, which comprises the steps of firstly constructing fender posts on the ground by adopting a rotary drilling rig according to the peripheral contour line of the station, and taking the fender posts as primary supports of the station; constructing a row of latticed columns along the longitudinal center line of the station, and reducing the span of the station by half; adopting rotary drilling to drill a plurality of slag taking holes in a honeycomb shape on the ground within the plane range of the subway station, and taking out most rock soil within the excavation range of the station; and then carrying out underground excavation construction on the station rock soil by adopting a reverse construction method. The invention can avoid the problems of low efficiency and large risk of the lower small-section independent closed loop excavation, has high construction safety and construction efficiency, good effects of controlling the deformation of the surrounding soil body and the surface settlement, can reduce the supporting amount of the supporting structure and reduce the construction cost.
Description
Technical Field
The invention belongs to the technical field of subway tunnel construction, and relates to an excavation construction method of a deep-buried large-section subway station under rock geology.
Background
The excavation section of the subway station is large, the open excavation method can be adopted for construction of a shallow station, the open excavation method is too large for a deep station or a station with a complex surrounding environment, and the underground excavation construction such as a double-side-wall pit guiding method and a CRD method is generally adopted. The principle of the method is that a large section is divided into a plurality of small sections, each small section is independently closed into a ring for excavation and supporting, the construction process is complicated, the efficiency is low, a supporting system is easy to damage in the construction process to cause primary support instability, especially in rock geology, blasting construction needs to be adopted in the excavation process, the blasting operation greatly disturbs surrounding rock masses, and the double-side-wall pit guiding method and the CRD method are difficult to ensure the integrity of the rock masses at the arch foot of the supporting structure, so that great construction risks and potential safety hazards are caused.
Disclosure of Invention
The invention aims to solve the problems and provides a construction method suitable for a deep-buried subway station under rock geology, which simplifies the process, improves the construction efficiency and reduces the construction risk.
The technical scheme of the invention is as follows:
a construction method for a deep-buried subway station under rock geology is characterized by comprising the following steps:
(1) constructing a circle of fender piles on the ground along the periphery of the plane outline of the subway station, and constructing a row of lattice columns along the longitudinal center line of the station; the lower ends of the enclosure piles and the lattice columns are at least 2m below the elevation of the bottom of the station, a reinforcement cage is arranged below the interior of the enclosure piles, concrete is poured to the top of the pile, the reinforcement cage is placed below the interior of the lattice columns, and the concrete is poured to the elevation of the top of the station;
(2) in the plane range of the subway station, a plurality of slag taking holes are drilled on the ground in a honeycomb shape by adopting rotary drilling, and the depth of each slag taking hole reaches the bottom elevation of the subway station;
(3) according to station layering, adopting a reverse construction method to carry out station underground excavation construction:
(31) constructing the upper layer of the station: firstly, excavating rock soil on two sides of an upper layer, and pouring two side walls of the upper layer; excavating part of rock soil of the vault, pouring the vault, and backfilling a slag taking hole above the closed vault after the vault is poured; excavating upper-layer cavern rock soil, arranging temporary supports between two side walls after the excavation of the upper-layer cavern rock soil is finished, pouring an upper-layer partition plate of a construction station, and removing the temporary supports;
(32) construction of a middle layer of a station: excavating rock soil on two sides of the middle layer, and pouring two side walls of the middle layer; then excavating middle-layer cavern rock soil; after the rock soil excavation of the middle-layer cavern is finished, arranging a temporary support between the two middle-layer side walls, then pouring a construction station middle-layer partition plate, and dismantling the temporary support;
(33) and (3) constructing the lower layer of the station: excavating rock soil on two sides of the lower layer, and pouring two side walls of the lower layer; then excavating the rock soil of the lower-layer cavern; after the excavation of the rock soil of the lower-layer cavern is finished, a temporary support is arranged between the two lower-layer side walls, then a construction station bottom plate is poured, and the temporary support is detached.
Compared with the existing underground excavation construction methods such as a double-side-wall pit guiding method, a CRD method and the like, the invention has the following advantages:
(1) most rock masses in the main body position of the station are taken out through rotary drilling and drilling on the ground, so that the underground excavation workload of the rock masses is greatly reduced. The ground construction speed is fast, and is efficient.
(2) The rotary drilling rig is in a honeycomb shape for slag taking, the honeycomb shape has good mechanical property in the horizontal direction, and the honeycomb rock-soil structure and the outer contour fender post in the station main body are stressed together, so that the stability of the surrounding rock-soil body in the construction process can be ensured.
(3) After most of the rock mass of the main body of the station is drilled into a honeycomb structure, the difficulty of rock mass excavation is greatly reduced, and the disturbance of blasting to surrounding rock mass and environment can be effectively reduced when blasting construction is adopted.
(4) The lattice column halves the station span, and when the cavern is excavated, the construction degree of difficulty and safety risk can be reduced.
(5) The station main part adopts reverse construction, and the permanent structure of station is as the inside support of work progress, reducible supporting construction's support volume, and control surrounding soil body deformation and earth's surface subside are effectual.
Drawings
FIG. 1 is a flow chart of the construction of the present invention;
FIG. 2 is a plan view of the arrangement of fender posts and lattice columns and earth boring holes;
FIG. 3 is an elevation view of the arrangement of fender posts and lattice columns and earth-borrowing boreholes;
fig. 4 is a cross-sectional structural view of a station;
FIG. 5 is a schematic view of a station upper side wall after pouring is completed;
FIG. 6 is a schematic diagram of a state after the pouring of the station vault is completed;
FIG. 7 is a schematic view of a temporary support structure between upper sidewalls;
FIG. 8 is a schematic view of the upper layer partition after pouring is completed;
FIG. 9 is a schematic view of the middle side wall and the temporary support after the construction is completed;
FIG. 10 is a schematic view of the middle layer of the partition after pouring;
FIG. 11 is a schematic view of the lower sidewall and the temporary support after the construction is completed;
fig. 12 is a schematic view of a state after pouring of the station floor is completed.
Detailed Description
The construction method of the present invention is explained below by a specific embodiment, in which a subway station is a transfer station and is divided into upper, middle and lower 3 floors.
FIG. 1 is a construction flow chart of the present invention, and the specific construction steps are as follows:
(1) as shown in fig. 2 and 3, firstly, a circle of fender posts 2 are constructed on the ground along the periphery of a plane contour 1 of a subway station, and a row of lattice columns 3 are constructed along the longitudinal center line of the station; and (3) excavating the fender post and the lattice column by adopting a rotary drilling rig, excavating the lower ends of the fender post 2 and the lattice column 3 to at least 2m below the elevation of the bottom of the station, lowering a reinforcement cage after pore-forming, and pouring concrete. The fender post is used as the primary support of the station main body, and concrete is poured to the top of the post; pouring concrete in the lattice column to the elevation of the top of the station; the lattice column divides the station into two areas longitudinally, so that the span of the station is halved.
(2) In the plane range of the subway station, a plurality of slag taking holes 4 are drilled in a honeycomb mode on the ground by adopting a rotary drilling rig, the depth of each slag taking hole 4 reaches the elevation of the bottom of the subway station, and most rock soil in the station excavation range is taken out through the slag taking holes.
The spacing of the fender post 2 is generally set to be 2-2.5m, the spacing of the lattice column 3 is 5-6m, and the spacing of the slag taking holes 4 is 0.8-1 times of the hole pitch.
As shown in fig. 4, the station is divided into 3 layers, and the main structure includes a vault 5, an upper layer side wall 6, an upper layer partition 7, a middle layer side wall 8, a middle layer partition 9, a lower layer side wall 10, and a bottom plate 11. The fender post 2 is used as a primary support of the station, and the latticed column 3 divides the station into a left area and a right area.
(3) According to station layering, adopting a reverse construction method to carry out station underground excavation construction from top to bottom, and the concrete flow is as follows:
(31) firstly, carrying out upper layer construction of a station: as shown in fig. 5, firstly excavating rock soil on two sides of the upper layer, and pouring an upper layer side wall 6;
as shown in fig. 6, after the upper layer side wall 6 is poured, excavating part of rock soil of the vault and pouring the vault 5; after the vault 5 is poured, backfilling and sealing a slag taking hole above the vault;
as shown in fig. 7, after the vault 5 is poured, excavating upper-layer cavern rock soil; after the excavation of upper strata cavern ground is accomplished, set up interim support 12 between both sides wall, prevent that the side wall from inwards warping after the excavation of cavern ground.
As shown in fig. 8, the upper-layer partition 7 of the station is cast and then the temporary support is removed.
(32) Carrying out middle layer construction of the station: as shown in fig. 9, excavating rock soil on two sides of the middle layer, and pouring the side wall 8 of the middle layer; then excavating middle-layer cavern rock soil, and arranging a temporary support 12 between two middle-layer side walls after the excavation of the upper-layer cavern rock soil is finished; then, as shown in fig. 10, the middle layer partition 9 of the station is poured and constructed, and the temporary support is removed.
(33) And finally, constructing the lower layer of the station: as shown in fig. 11, excavating rock soil on two sides of the lower layer, and pouring the lower layer side wall 10; secondly, excavating lower-layer cavern rock soil, and arranging a temporary support 12 between two lower-layer side walls after the lower-layer cavern rock soil is excavated; then, as shown in fig. 12, the station floor 11 is cast and the temporary support is removed.
The lattice column longitudinally divides a station into two areas, when each layer of cavern rock soil is excavated, one side of the lattice column is excavated firstly, the other side of the lattice column is excavated, and the transverse span is halved when the cavern is excavated, so that the construction safety can be ensured; and excavating the rock soil by adopting a step method and circularly excavating.
Claims (3)
1. A construction method for a deep-buried subway station under rock geology is characterized by comprising the following steps:
(1) constructing a circle of fender piles on the ground along the periphery of the plane outline of the subway station, and constructing a row of lattice columns along the longitudinal center line of the station; the lower ends of the enclosure piles and the lattice columns are at least 2m below the elevation of the bottom of the station, a reinforcement cage is arranged below the interior of the enclosure piles, concrete is poured to the top of the pile, the reinforcement cage is placed below the interior of the lattice columns, and the concrete is poured to the elevation of the top of the station;
(2) in the plane range of the subway station, a plurality of slag taking holes are drilled on the ground in a honeycomb shape by adopting rotary drilling, and the depth of each slag taking hole reaches the bottom elevation of the subway station;
(3) according to station layering, adopting a reverse construction method to carry out station underground excavation construction:
(31) constructing the upper layer of the station: firstly, excavating rock soil on two sides of an upper layer, and pouring two side walls of the upper layer; excavating part of rock soil of the vault, pouring the vault, and backfilling a slag taking hole above the closed vault after the vault is poured; excavating upper-layer cavern rock soil, arranging temporary supports between two side walls after the excavation of the upper-layer cavern rock soil is finished, pouring an upper-layer partition plate of a construction station, and removing the temporary supports;
(32) construction of a middle layer of a station: excavating rock soil on two sides of the middle layer, and pouring two side walls of the middle layer; then excavating middle-layer cavern rock soil; after the rock soil excavation of the middle-layer cavern is finished, arranging a temporary support between the two middle-layer side walls, then pouring a construction station middle-layer partition plate, and dismantling the temporary support;
(33) and (3) constructing the lower layer of the station: excavating rock soil on two sides of the lower layer, and pouring two side walls of the lower layer; then excavating the rock soil of the lower-layer cavern; after the excavation of the rock soil of the lower-layer cavern is finished, a temporary support is arranged between the two lower-layer side walls, then a construction station bottom plate is poured, and the temporary support is detached.
2. The method for constructing a deep buried subway station under rock geology according to claim 1, characterized in that: the spacing of the guard piles is 2-2.5m, the spacing of the lattice columns is 5-6m, and the spacing of the drilled holes is 0.8-1 time of the aperture.
3. The method for constructing a deep buried subway station under rock geology according to claim 1, characterized in that: in the step (2), when excavating each layer of cavern rock soil, firstly excavating one side of the lattice column, and then excavating the other side of the lattice column, wherein each side is excavated by a step method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110314801.5A CN113153384A (en) | 2021-03-24 | 2021-03-24 | Construction method for deep-buried subway station under rock geology |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110314801.5A CN113153384A (en) | 2021-03-24 | 2021-03-24 | Construction method for deep-buried subway station under rock geology |
Publications (1)
Publication Number | Publication Date |
---|---|
CN113153384A true CN113153384A (en) | 2021-07-23 |
Family
ID=76884589
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110314801.5A Pending CN113153384A (en) | 2021-03-24 | 2021-03-24 | Construction method for deep-buried subway station under rock geology |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113153384A (en) |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08253946A (en) * | 1995-03-17 | 1996-10-01 | Fujita Corp | Reverse placing method for concrete of underground structure under road |
JP2006132219A (en) * | 2004-11-08 | 2006-05-25 | Toda Constr Co Ltd | Underground structure construction method, underground structure, and precast concrete side wall or intermediate wall/pole for use in the same |
WO2013147652A2 (en) * | 2012-03-30 | 2013-10-03 | Общество с ограниченной ответственностью "Инженерное бюро Юркевича" | Metro station and method for constructing same |
CN105544607A (en) * | 2016-02-02 | 2016-05-04 | 中铁十一局集团城市轨道工程有限公司 | Exterior-covered waterproof construction method for subway station side walls with hanging plate girders |
CN205776347U (en) * | 2016-06-22 | 2016-12-07 | 中铁第四勘察设计院集团有限公司 | Novel cover for subway station digs against making structural system |
CN110130393A (en) * | 2019-05-22 | 2019-08-16 | 中铁四局集团有限公司 | A kind of underwater foundation pit drilling of soft rock and punching point arrangement method |
CN110306593A (en) * | 2019-07-03 | 2019-10-08 | 中铁二十五局集团第五工程有限公司 | A kind of station construction method |
CN111576431A (en) * | 2020-05-25 | 2020-08-25 | 中铁隧道局集团有限公司 | Excavation method for foundation pit of four-layer subway station |
CN111779027A (en) * | 2020-08-18 | 2020-10-16 | 北京中岩智泊科技有限公司 | Construction method for constructing underground garage through cover-excavation top-down construction |
-
2021
- 2021-03-24 CN CN202110314801.5A patent/CN113153384A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08253946A (en) * | 1995-03-17 | 1996-10-01 | Fujita Corp | Reverse placing method for concrete of underground structure under road |
JP2006132219A (en) * | 2004-11-08 | 2006-05-25 | Toda Constr Co Ltd | Underground structure construction method, underground structure, and precast concrete side wall or intermediate wall/pole for use in the same |
WO2013147652A2 (en) * | 2012-03-30 | 2013-10-03 | Общество с ограниченной ответственностью "Инженерное бюро Юркевича" | Metro station and method for constructing same |
CN105544607A (en) * | 2016-02-02 | 2016-05-04 | 中铁十一局集团城市轨道工程有限公司 | Exterior-covered waterproof construction method for subway station side walls with hanging plate girders |
CN205776347U (en) * | 2016-06-22 | 2016-12-07 | 中铁第四勘察设计院集团有限公司 | Novel cover for subway station digs against making structural system |
CN110130393A (en) * | 2019-05-22 | 2019-08-16 | 中铁四局集团有限公司 | A kind of underwater foundation pit drilling of soft rock and punching point arrangement method |
CN110306593A (en) * | 2019-07-03 | 2019-10-08 | 中铁二十五局集团第五工程有限公司 | A kind of station construction method |
CN111576431A (en) * | 2020-05-25 | 2020-08-25 | 中铁隧道局集团有限公司 | Excavation method for foundation pit of four-layer subway station |
CN111779027A (en) * | 2020-08-18 | 2020-10-16 | 北京中岩智泊科技有限公司 | Construction method for constructing underground garage through cover-excavation top-down construction |
Non-Patent Citations (1)
Title |
---|
汪思满: "轨道交通地下车站逆作法施工技术研究与实例", 《建筑施工》 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105089061B (en) | Ultra-deep foundation pit supporting method | |
CN102758632A (en) | Rock stratum double initial support layering method for establishing large-scale underground structure | |
CN106088154B (en) | Prefabricated assembled underground silo compound shaft construction method and silo structure | |
CN103775110A (en) | Underground excavation construction method for multilayer underground space of soft soil area | |
CN106567717A (en) | Construction oblique channel structure utilizing subway exit and entrance and construction method | |
CN108532586A (en) | A kind of construction method of garage parking diaphram wall | |
CN107514262A (en) | The construction method of shield piping lane | |
CN107218046A (en) | Mechanical assistance sealing Station structure and construction method in a kind of pilot tunnel | |
CN210530860U (en) | Deep-buried blocking barrier for controlling deformation of tunnel outside foundation pit | |
CN112240207B (en) | Jumbo-span cave depot lattice jumping excavation and rapid bottom turning method | |
CN113417294B (en) | Synchronous excavation construction method suitable for subway transfer hub foundation pit group | |
CN106567391A (en) | Segmented profile-steel horizontal retaining structure of subway exits and entrances of rock strata and construction method | |
CN113153384A (en) | Construction method for deep-buried subway station under rock geology | |
CN111851515B (en) | Adjacent foundation pit cooperative construction enclosure structure and construction method thereof | |
CN111236310B (en) | Construction method of connecting channel of existing underground structure in weak water-rich stratum | |
CN212316933U (en) | Excavation protection structure for foundation pit above existing tunnel | |
CN111101540B (en) | Construction method for passing existing electric power tunnel on open cut tunnel | |
CN113153383A (en) | Construction method for deep-buried large-section subway station | |
CN105840216B (en) | A kind of tunneling construction method of underground space development | |
JP2604210B2 (en) | Construction method of underground large-scale spatial structure | |
CN111441794B (en) | Underground excavation construction method and structure for rebuilding existing tunnel into double-layer tunnel | |
CN113847062B (en) | Subway station construction method combining small-diameter jacking pipes with double-layer six-hole piles | |
CN212175793U (en) | Underground protective structure based on underground diaphragm wall and steel open caisson combination formula | |
CN111472389B (en) | Open excavation construction method for rebuilding existing tunnel into double-layer tunnel | |
CN111677515B (en) | Construction method for breaking open cut foundation pit wall into hole from pile support supporting system by adopting shallow-buried underground excavation method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |