CN113148060A - Gas transport ship block strength test and insulation installation method - Google Patents

Gas transport ship block strength test and insulation installation method Download PDF

Info

Publication number
CN113148060A
CN113148060A CN202110394938.6A CN202110394938A CN113148060A CN 113148060 A CN113148060 A CN 113148060A CN 202110394938 A CN202110394938 A CN 202110394938A CN 113148060 A CN113148060 A CN 113148060A
Authority
CN
China
Prior art keywords
block
broadside
strength test
section
finished
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110394938.6A
Other languages
Chinese (zh)
Inventor
张启鹏
徐占勇
李宁
朱宇峰
李芝忠
那铁锁
王杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Waigaoqiao Shipbuilding Co Ltd
Original Assignee
Shanghai Waigaoqiao Shipbuilding Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Waigaoqiao Shipbuilding Co Ltd filed Critical Shanghai Waigaoqiao Shipbuilding Co Ltd
Priority to CN202110394938.6A priority Critical patent/CN113148060A/en
Publication of CN113148060A publication Critical patent/CN113148060A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B73/00Building or assembling vessels or marine structures, e.g. hulls or offshore platforms
    • B63B73/10Building or assembling vessels from prefabricated hull blocks, i.e. complete hull cross-sections
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B71/00Designing vessels; Predicting their performance

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Abstract

The invention discloses a method for testing the strength of a gas carrier block and insulating installation, which comprises the following steps: dividing the total section of the cargo compartment ring section into a left broadside total section, a right broadside total section, a bottom double-bottom total section and a deck total section; the cargo compartment ring section is provided with a left ballast compartment and a right ballast compartment, and the two ballast compartments are separated at the bottom by a pipe ballast compartment; normally placing the broadside block structure after the broadside block structure is finished, and plugging an opening on a bottom longitudinal girder of the broadside block; placing the port and starboard side sections face to face, and placing the port and starboard side sections on a strength test service rack for a first strength test; after the first strength test is finished, installing a heat-insulating layer on the side state broadside block; plugging an opening on a bottom longitudinal girder of the double-bottom-layer block; after the preparation work is finished, water injection is started, and a second strength test is finished; and a heat-insulating layer is arranged on the double-bottom-layer main section. The dock cycle can be greatly shortened.

Description

Gas transport ship block strength test and insulation installation method
Technical Field
The invention relates to the field of gas carrier construction, in particular to a strength test and insulation installation method for a gas carrier block.
Background
The heat-insulating layer of the gas transport ship is arranged on the main hull structure outside the liquid tank. According to the construction process, the insulation needs to be installed after the strength test of the ballast tank is finished. It is now common practice to conduct a ballast tank strength test at the dock stage after the ballast tank structure is completed, by flooding the ballast tank at the dock stage to complete the strength test. This results in the gas carrier insulation needing to be installed at the dock stage. Because the construction period of the heat insulation layer of the gas carrier is long, if the insulation is installed in the dock stage, a large number of dock periods are occupied. It is known that dock efficiency is a key factor affecting shipbuilding efficiency in shipyards, and dock resources are bottleneck resources of a shipyard. In order to shorten the dock period and realize quick construction, the strength test and insulation installation stages need to be moved forward to the total stage.
Disclosure of Invention
The invention aims to provide a strength test and insulation installation method for a gas carrier block, which can greatly shorten the dock period.
The technical scheme for realizing the purpose is as follows:
a method for testing strength of a gas transport ship block and insulating installation comprises the following steps:
dividing the total section of the cargo compartment ring section into a left broadside total section, a right broadside total section, a bottom double-bottom total section and a deck total section; the cargo compartment ring section is provided with a left ballast compartment and a right ballast compartment, and the two ballast compartments are separated at the bottom by a pipe ballast compartment;
normally placing the broadside block structure after the broadside block structure is finished, and plugging an opening on a bottom longitudinal girder of the broadside block;
placing the port and starboard side sections face to face, and placing the port and starboard side sections on a strength test service rack for a first strength test;
after the first strength test is finished, installing a heat-insulating layer on the side state broadside block;
plugging an opening on a bottom longitudinal girder of the double-bottom-layer block;
after the preparation work is finished, water injection is started, and a second strength test is finished;
and a heat-insulating layer is arranged on the double-bottom-layer main section.
Preferably, the first strength test refers to: and arranging a vent pipe at the highest point of the top of the broadside block, and starting water injection after the preparation work is finished to finish the strength test.
Preferably, after the first strength test is qualified, draining the water in the ballast tank, and dismantling the corresponding tool; placing the broadside block in a wind and rain shed in a lateral state by taking the outer plate as a base surface; and after the installation and the inspection of the heat preservation layer are finished, hoisting the main section to a dock for carrying.
Preferably, after the second strength test is qualified, draining the water in the ballast tank, and dismantling the corresponding tool; placing the double-bottom-layer general section in a wind and rain shed; and after the installation and the inspection of the heat preservation layer are finished, hoisting the double-bottom-layer block section to a dock for carrying.
The invention has the beneficial effects that: according to the invention, the total section of the cargo compartment ring section is divided into the left and right side total sections, the double-bottom total section at the bottom and the deck total section, so that the strength test of the ballast compartment of the gas transport ship and the insulating installation of the ballast compartment in the total section are realized, the dock period is greatly shortened, and the efficient construction is realized. In addition, in the process, the open holes are plugged, so that the ballast tank is watertight.
Drawings
FIG. 1 is a front view of the total segmentation in the present invention;
FIG. 2 is a cross-sectional view of the overall segmentation of the present invention;
FIG. 3 is a front view of the arrangement of ballast tanks in the present invention;
FIG. 4 is a cross-sectional view of a ballast tank arrangement of the present invention;
FIG. 5 is a front view of a broadside bus section strength test in accordance with the present invention;
FIG. 6 is a side view of a broadside block strength test of the present invention;
FIG. 7 is a front view of a dual bottom layer total section strength test in accordance with the present invention.
Detailed Description
The invention will be further explained with reference to the drawings.
The invention relates to a method for testing the strength of a gas carrier block and insulating installation, which comprises the following steps:
dividing a total section of a cargo compartment ring section into a left shipboard total section, a right shipboard total section, a double-bottom total section at the bottom and a deck total section; the cargo compartment ring section is provided with a left ballast compartment and a right ballast compartment, and the two ballast compartments are separated at the bottom by a pipe. As shown in fig. 1-4.
And secondly, normally placing the side block structure after the completion for simulating the on-board state of the ballast tank, and plugging the open hole on the bottom longitudinal girder of the side block to ensure the watertightness of the side ballast tank. As shown in fig. 5 and 6.
And thirdly, the port and starboard side sections are placed face to face, so that the structure is ensured not to overturn. And placing the test piece on a strength test service rack for carrying out a first strength test. As shown in fig. 5 and 6. The stability of the total section in the strength test is ensured.
The first strength test refers to: and arranging a vent pipe at the highest point of the top of the broadside block, and starting water injection after the preparation work is finished to finish the strength test.
Fourthly, after the first strength test is qualified, draining the water in the ballast tank, and dismantling the corresponding tool; the side block is arranged in a wind and rain shed in a side state by taking an outer plate as a base surface, and an insulating layer is arranged on the side block; and after the installation and the inspection of the heat preservation layer are finished, hoisting the main section to a dock for carrying.
Fifthly, plugging the open holes on the bottom longitudinal girders of the double-bottom-layer block section to ensure the watertight bottom ballast tank; as shown in fig. 7.
And sixthly, starting water injection after the preparation work is finished, and finishing the second strength test. Draining water in the ballast tank after the second strength test is qualified, and dismantling a corresponding tool; and placing the double-bottom-layer block in a wind and rain shed, and installing a heat-insulating layer on the double-bottom-layer block. And after the installation and the inspection of the heat preservation layer are finished, hoisting the double-bottom-layer block section to a dock for carrying.
In conclusion, the strength test and the insulation installation of the ballast tank of the gas transport ship can be carried out at the total section stage, the dock period is greatly shortened, and the efficient construction is realized.
The above embodiments are provided only for illustrating the present invention and not for limiting the present invention, and those skilled in the art can make various changes and modifications without departing from the spirit and scope of the present invention, and therefore all equivalent technical solutions should also fall within the scope of the present invention, and should be defined by the claims.

Claims (4)

1. A method for testing strength of a gas transport ship block and insulating installation is characterized by comprising the following steps:
dividing the total section of the cargo compartment ring section into a left broadside total section, a right broadside total section, a bottom double-bottom total section and a deck total section; the cargo compartment ring section is provided with a left ballast compartment and a right ballast compartment, and the two ballast compartments are separated at the bottom by a pipe ballast compartment;
normally placing the broadside block structure after the broadside block structure is finished, and plugging an opening on a bottom longitudinal girder of the broadside block;
placing the port and starboard side sections face to face, and placing the port and starboard side sections on a strength test service rack for a first strength test;
after the first strength test is finished, installing a heat-insulating layer on the side state broadside block;
plugging an opening on a bottom longitudinal girder of the double-bottom-layer block;
after the preparation work is finished, water injection is started, and a second strength test is finished;
and a heat-insulating layer is arranged on the double-bottom-layer main section.
2. The method for testing the strength and installing insulation of a gas carrier block according to claim 1, wherein the first strength test is: and arranging a vent pipe at the highest point of the top of the broadside block, and starting water injection after the preparation work is finished to finish the strength test.
3. The method for testing the strength of the gas carrier block and installing the gas carrier block in an insulating manner according to claim 1, wherein after the first strength test is qualified, water in the ballast tank is drained, and a corresponding tool is removed; placing the broadside block in a wind and rain shed in a lateral state by taking the outer plate as a base surface; and after the installation and the inspection of the heat preservation layer are finished, hoisting the main section to a dock for carrying.
4. The method for testing the strength of the gas carrier block and installing the gas carrier block in an insulating manner according to claim 1, wherein after the second strength test is qualified, water in the ballast tank is drained, and a corresponding tool is removed; placing the double-bottom-layer general section in a wind and rain shed; and after the installation and the inspection of the heat preservation layer are finished, hoisting the double-bottom-layer block section to a dock for carrying.
CN202110394938.6A 2021-04-13 2021-04-13 Gas transport ship block strength test and insulation installation method Pending CN113148060A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110394938.6A CN113148060A (en) 2021-04-13 2021-04-13 Gas transport ship block strength test and insulation installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110394938.6A CN113148060A (en) 2021-04-13 2021-04-13 Gas transport ship block strength test and insulation installation method

Publications (1)

Publication Number Publication Date
CN113148060A true CN113148060A (en) 2021-07-23

Family

ID=76890401

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110394938.6A Pending CN113148060A (en) 2021-04-13 2021-04-13 Gas transport ship block strength test and insulation installation method

Country Status (1)

Country Link
CN (1) CN113148060A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090020825A (en) * 2007-08-24 2009-02-27 대우조선해양 주식회사 Tank hydro test method a period of dock stage using buoyancy of half diving state
CN107444567A (en) * 2017-07-28 2017-12-08 广船国际有限公司 A kind of Strength Testing Methods of ultra large crude carrier
CN108407968A (en) * 2018-04-27 2018-08-17 广船国际有限公司 A kind of side ballast tank segmentation division methods
CN111634368A (en) * 2020-06-29 2020-09-08 芜湖造船厂有限公司 Ship ballast tank structure and processing method thereof
CN112078746A (en) * 2020-08-11 2020-12-15 沪东中华造船(集团)有限公司 Method for carrying out strength test on ballast tank in dock
CN112078745A (en) * 2020-08-11 2020-12-15 沪东中华造船(集团)有限公司 LNG ship ballast tank strength test system
CN112098222A (en) * 2020-08-11 2020-12-18 沪东中华造船(集团)有限公司 LNG ship ballast tank strength test method
CN112550626A (en) * 2020-12-07 2021-03-26 沪东中华造船(集团)有限公司 Construction method of deep oil tank area of container ship

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090020825A (en) * 2007-08-24 2009-02-27 대우조선해양 주식회사 Tank hydro test method a period of dock stage using buoyancy of half diving state
CN107444567A (en) * 2017-07-28 2017-12-08 广船国际有限公司 A kind of Strength Testing Methods of ultra large crude carrier
CN108407968A (en) * 2018-04-27 2018-08-17 广船国际有限公司 A kind of side ballast tank segmentation division methods
CN111634368A (en) * 2020-06-29 2020-09-08 芜湖造船厂有限公司 Ship ballast tank structure and processing method thereof
CN112078746A (en) * 2020-08-11 2020-12-15 沪东中华造船(集团)有限公司 Method for carrying out strength test on ballast tank in dock
CN112078745A (en) * 2020-08-11 2020-12-15 沪东中华造船(集团)有限公司 LNG ship ballast tank strength test system
CN112098222A (en) * 2020-08-11 2020-12-18 沪东中华造船(集团)有限公司 LNG ship ballast tank strength test method
CN112550626A (en) * 2020-12-07 2021-03-26 沪东中华造船(集团)有限公司 Construction method of deep oil tank area of container ship

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
梁有祥: "散货船货舱区分段工艺划分的几种型式", 《造船技术》 *
魏莉洁等: "《船舶建造工艺》", 28 February 2010, 哈尔滨工程大学出版社 *

Similar Documents

Publication Publication Date Title
CN113772042A (en) Cargo compartment segmentation design method for 8-million-cubic-level thin-film LNG ship and cargo compartment segmentation
CN104743060A (en) Ship main engine installation method
CN113955044B (en) Method for carrying container ship LNG tank block, LNG tank block and container ship
KR101895286B1 (en) Method for conversion of a vessel for use as floating liquefied natural gas facility
SG171756A1 (en) Device for floating production of lng and method for converting a lng-carrier to such a device
KR102157346B1 (en) Method for shipbuilding by adapting non-floating tandem in dry dock
KR20180048610A (en) Offshore structure
US4491081A (en) Method for assembling a complete module of multideck ship hull
CN113200126A (en) 438TEU high-energy-efficiency container ship for direct transportation from river to sea
KR100914350B1 (en) Tank hydro test method a period of dock stage using buoyancy of half diving state
CN113148060A (en) Gas transport ship block strength test and insulation installation method
CN104590486A (en) Pre-outfitting technology for finished product oil and chemical ship engine room
CN205770042U (en) A kind of ocean work platforms
CN104691704B (en) A kind of method of construction of inland navigation craft
CN113148059A (en) General section strength test and insulation installation method of gas transport ship
CN102632965A (en) Combined type module ship and module connecting way thereof
JP2009517290A (en) Inundation method applied to tandem construction method
CN202703846U (en) Fixation compound plate
CN203581334U (en) Wood chip transport ship
CN204939027U (en) Water pre-treatment means at the bottom of a kind of gravity type boat davit ship cabin
CN221571240U (en) Multi-model compatible diversion adaptation device of carrier rocket marine launch ship
JP2005104187A (en) Duct device of tanker
CN212423373U (en) Composite board containing expanded rubber and anti-sinking ship
CN215599941U (en) Integrated model of marine ship for middle school students
CN216878754U (en) Naked tower of desulfurization repacking

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210723