CN112799122A - Three-dimensional seismic exploration interval arrangement construction method - Google Patents

Three-dimensional seismic exploration interval arrangement construction method Download PDF

Info

Publication number
CN112799122A
CN112799122A CN202110014344.8A CN202110014344A CN112799122A CN 112799122 A CN112799122 A CN 112799122A CN 202110014344 A CN202110014344 A CN 202110014344A CN 112799122 A CN112799122 A CN 112799122A
Authority
CN
China
Prior art keywords
shot
line
full coverage
boundary
work area
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110014344.8A
Other languages
Chinese (zh)
Inventor
李向阳
朱锐
高娟
刘奋勇
杨争发
冀东升
胡伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202110014344.8A priority Critical patent/CN112799122A/en
Publication of CN112799122A publication Critical patent/CN112799122A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01VGEOPHYSICS; GRAVITATIONAL MEASUREMENTS; DETECTING MASSES OR OBJECTS; TAGS
    • G01V1/00Seismology; Seismic or acoustic prospecting or detecting
    • G01V1/003Seismic data acquisition in general, e.g. survey design
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01VGEOPHYSICS; GRAVITATIONAL MEASUREMENTS; DETECTING MASSES OR OBJECTS; TAGS
    • G01V1/00Seismology; Seismic or acoustic prospecting or detecting
    • G01V1/02Generating seismic energy
    • G01V1/04Details
    • G01V1/09Transporting arrangements, e.g. on vehicles
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01VGEOPHYSICS; GRAVITATIONAL MEASUREMENTS; DETECTING MASSES OR OBJECTS; TAGS
    • G01V1/00Seismology; Seismic or acoustic prospecting or detecting
    • G01V1/02Generating seismic energy
    • G01V1/104Generating seismic energy using explosive charges
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01VGEOPHYSICS; GRAVITATIONAL MEASUREMENTS; DETECTING MASSES OR OBJECTS; TAGS
    • G01V1/00Seismology; Seismic or acoustic prospecting or detecting
    • G01V1/16Receiving elements for seismic signals; Arrangements or adaptations of receiving elements
    • G01V1/168Deployment of receiver elements
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01VGEOPHYSICS; GRAVITATIONAL MEASUREMENTS; DETECTING MASSES OR OBJECTS; TAGS
    • G01V1/00Seismology; Seismic or acoustic prospecting or detecting
    • G01V1/16Receiving elements for seismic signals; Arrangements or adaptations of receiving elements
    • G01V1/20Arrangements of receiving elements, e.g. geophone pattern

Landscapes

  • Physics & Mathematics (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Remote Sensing (AREA)
  • Acoustics & Sound (AREA)
  • Environmental & Geological Engineering (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • Geophysics (AREA)
  • Geophysics And Detection Of Objects (AREA)

Abstract

The invention discloses a three-dimensional seismic exploration interval arrangement construction method, in particular to the technical field of three-dimensional seismic exploration construction, which comprises the following steps: the method comprises the following steps: covering the collection line; step two: arrangement of the acquisition stations; step three: setting a receiving channel; step four: dividing the space; step five: covering the shot point; step six: and confirming the construction boundary. According to the invention, through the arrangement of the first step to the fourth step, the polarized wave with a certain direction can be excited and received during three-dimensional seismic exploration, and each time when the line is reversed, the vehicle only needs to walk one eighth of the original distance on the measuring line or move the collected objects on the measuring line arrangement, so that the line reversing task can be completed, a large number of vehicles are saved, the construction cost is reduced, and the construction efficiency is improved.

Description

Three-dimensional seismic exploration interval arrangement construction method
Technical Field
The embodiment of the invention relates to the technical field of three-dimensional seismic exploration construction, in particular to a three-dimensional seismic exploration interval arrangement construction method.
Background
Seismic exploration refers to a geophysical exploration method for deducing the properties and forms of underground rock formations by observing and analyzing the response of the earth to artificially-excited seismic waves by utilizing the difference between the elasticity and the density of a subsurface medium caused by artificial excitation. When the earth surface excites the earthquake wave artificially, the elastic wave caused by artificial excitation meets the rock layer interface with different medium properties, the earthquake wave is refracted and reflected, and the earthquake wave is received by a wave detector in the earth surface or well. The received seismic signals are related to the seismic source characteristics, the location of the geophone points, and the nature and structure of the subterranean strata through which the seismic waves pass. By processing and interpreting seismic wave recordings, the nature and morphology of the subterranean formation can be inferred. Seismic exploration is the most important method in geophysical exploration and the most effective method for solving the problem of oil and gas exploration, and seismic data play more and more important roles in mineral exploration and development.
At present, when three-dimensional seismic exploration is carried out by earthquake at home and abroad, a plurality of measuring lines are required to be arranged on the ground during acquisition, a plurality of detectors are arranged on each measuring line and used for receiving wave beams emitted from a seismic source and reflected by a stratum, the waves are sent into a seismograph through a lead for recording, finally, the received waveforms are arranged through a computer, and are drawn into a structural diagram to find out the underground structure with possible oil storage through intermediate product, so the arrangement and arrangement speed of the measuring lines during the seismic exploration is a key ring in the field seismic work. If eight measuring lines (collecting lines) are arranged, each line has 6-150 receiving channels, the distance between each receiving channel is 50 meters, namely the total length of one measuring line can reach 3 kilometers, and when the line is rewound, a worker places the receiving channels on each collecting station from top to bottom on a kilometer long road by using a special line rewinding vehicle. Eight survey lines need eight rewinders to move simultaneously, and the demodulator probe of laying is too much, and the construction boundary is great, and boundary portion demodulator probe does not contribute to the material in the full coverage, and this has increased construction cost undoubtedly, has lengthened the time limit for a project, has reduced the efficiency of construction, and is laborious again.
Disclosure of Invention
Therefore, the embodiment of the invention provides a three-dimensional seismic exploration interval arrangement construction method, which comprises the steps of determining a construction boundary under the condition of ensuring the completeness of a demodulator probe and a demodulator line of a shot-geophone correlation sheet through the arrangement of the step five and the step six, optimizing the demodulator probe and the demodulator line of a three-dimensional work area outside the construction boundary so as to carry out three-dimensional seismic exploration construction according to the construction boundary, aiming at the three-dimensional work area to be constructed, optimizing partial demodulator probes and demodulator lines of the three-dimensional work area under the condition of ensuring the completeness of the shot-geophone correlation sheet according to the shot-geophone correlation sheet and a full coverage range, namely ensuring that the demodulator probe and the demodulator line of the shot-geophone correlation sheet cannot be lost, meeting the requirement of pre-stack migration processing of data in the full coverage range, greatly reducing the demodulator probes used for construction, shortening the construction period and reducing the labor cost,
through the arrangement of the first step to the fourth step, when three-dimensional seismic exploration is carried out, polarized waves with a certain direction can be excited and received, and transverse waves can be polarized under certain conditions. Therefore, the transverse waves can be divided into two types, when the line is reversed every time, the vehicle only needs to walk on the measuring line for one eighth of the original distance or move the collected objects on the measuring line arrangement, the line reversing task can be completed, a large number of vehicles are saved, the construction cost is reduced, the construction efficiency is improved, and the problems that in the prior art, due to the fact that the line reversing vehicle is consumed in a large quantity, the number of arranged wave detection points is too large, the construction boundary is large, the detection points of the boundary part do not contribute to the materials in the full coverage range, the construction cost is increased, the construction period is prolonged, the construction efficiency is reduced, and labor is wasted are solved.
In order to achieve the above object, the embodiments of the present invention provide the following technical solutions: a three-dimensional seismic exploration interval arrangement construction method comprises the following specific steps:
the method comprises the following steps: covering the collection line: arranging 8-10 acquisition lines on the ground in the full coverage range of the three-dimensional work area;
step two: arrangement of the acquisition stations: arranging 8-10 collection lines in parallel at intervals of 120-150 meters, and then arranging 20-25 collection stations on each collection line at intervals of 210-250 meters;
step three: setting a receiving channel: 6-15 receiving channels are arranged on each acquisition station;
step four: dividing the space: dividing 8-10 collecting line sections into 7-12 sections according to the same size specification, and inserting section flags with different colors into each section;
step five: covering shot points: placing the shot points on the shot-checking relation sheet on the transverse boundary of the acquisition line, placing one shot point on the shot-checking relation sheet at the intersection of the acquisition line and preventing the shot points on the shot-checking relation sheet from being arranged outside the exploration interval range;
step six: confirming a construction boundary: the direction of a geophone correlation piece is parallel to the direction of a geophone line of a three-dimensional work area, and the transverse boundary and the longitudinal boundary are respectively acquisition line boundaries which are perpendicular to and parallel to the direction of the geophone line, so that the completeness of a geophone point and the geophone line of the geophone correlation piece is ensured, a construction boundary is determined, and three-dimensional seismic exploration construction is carried out.
Further, in step four, each interval is 700m 600m to 700m 900 m.
Further, the acquisition station in step two is a detector with directional sensitivity to particle motion in one direction.
Further, in the fifth step, the shot on the shot relation sheet has limitation on the particle motion direction.
Further, in the fifth step, the shot-checking relation pieces are rectangular, the full coverage range of the three-dimensional work area is also rectangular, the area of the shot-checking relation pieces is smaller than that of the three-dimensional work area, and the shot points in the shot-checking relation pieces are arranged in a row.
Further, in the fifth step, when the lateral boundary of the full coverage area of the three-dimensional work area is not located on the shot point of the three-dimensional work area and the shot point of the three-dimensional work area is located on the longitudinal boundary extension line of the full coverage area, the shot point on the shot detection relation piece is placed on the shot point which is outside the full coverage area and is closest to the lateral boundary of the full coverage area, one shot point on the shot point relation piece is placed on the longitudinal boundary extension line of the full coverage area, and no shot point on the shot detection relation piece is located outside the longitudinal boundary extension line of the full coverage area.
Further, in the sixth step, when the lateral boundary of the full coverage area of the three-dimensional work area is not located on the shot point of the three-dimensional work area and no shot point of the three-dimensional work area is located on the longitudinal boundary extension line of the full coverage area, the shot point on the shot detection relation sheet is placed on the shot point which is outside the full coverage area and is closest to the lateral boundary of the full coverage area, and only one shot point on the shot detection relation sheet is located outside the longitudinal boundary extension line of the full coverage area.
The embodiment of the invention has the following advantages:
1. compared with the prior art, the method has the advantages that through the arrangement of the first step to the fourth step, the polarized wave with a certain direction can be excited and received during the three-dimensional seismic exploration, the transverse wave can be polarized under a certain condition, and the polarization is that when the transverse wave passes through, if mass points move in one direction, the transverse wave is polarized in the direction. Therefore, the transverse waves can be divided into two types, and when the line is reversed every time, the vehicle only needs to walk on the measuring line for one eighth of the original distance or move the collected objects on the measuring line arrangement, so that the line reversing task can be completed, a large number of vehicles are saved, the construction cost is reduced, and the construction efficiency is improved;
2. through the arrangement of the fifth step and the sixth step, compared with the prior art, the construction boundary is determined under the condition that the integrity of the demodulator probe and the demodulator trace of the shot-geophone correlation sheet is ensured, the demodulator probe and the demodulator trace of the three-dimensional work area outside the construction boundary are optimized, three-dimensional seismic exploration construction is carried out according to the construction boundary, and partial demodulator probes and demodulator traces of the three-dimensional work area are optimized under the condition that the integrity of the shot-geophone correlation sheet is ensured, namely the demodulator probe and the demodulator trace of the shot-geophone correlation sheet cannot be lost, according to the shot-geophone correlation sheet and the full coverage range, so that the requirements of pre-stack migration processing can be met by data in the full coverage range, the demodulator probes used for construction are greatly reduced, the construction period is shortened, and the labor cost is reduced.
Detailed Description
The present invention is described in terms of particular embodiments, other advantages and features of the invention will become apparent to those skilled in the art from the following disclosure, and it is to be understood that the described embodiments are merely exemplary of the invention and that it is not intended to limit the invention to the particular embodiments disclosed. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example 1:
the invention provides a three-dimensional seismic exploration interval arrangement construction method, which comprises the following specific steps:
the method comprises the following steps: covering the collection line: arranging 8 acquisition lines on the ground in the full coverage range of the three-dimensional work area;
step two: arrangement of the acquisition stations: arranging 8 acquisition lines in parallel at intervals of 120 meters, and arranging 20 detectors with directional sensitivity to particle motion in one direction on each acquisition line at intervals of 210 meters;
step three: setting a receiving channel: each acquisition station is provided with 6 receiving channels;
step four: dividing the space: dividing 8 collection line segments into 7 intervals according to the same size specification, wherein the specification of each interval is 700m x 600m, and inserting interval flags of different colors into each interval;
step five: covering shot points: arranging the shot points on the shot-checking relation sheet on the transverse boundary of the acquisition line, arranging one shot point on the shot-checking relation sheet at the intersection of the acquisition line and preventing the shot points on the shot-checking relation sheet from being arranged outside the exploration interval range, wherein the shot points on the shot-checking relation sheet have limitation on the motion direction of particles, the shot-checking relation sheet is rectangular, the full coverage range of the three-dimensional work area is also rectangular, the area of the shot-checking relation sheet is smaller than that of the three-dimensional work area, the shot points in the shot-checking relation sheet are arranged in a row, when the transverse boundary of the full coverage area of the three-dimensional work area is not positioned on the shot point of the three-dimensional work area and the shot point of the three-dimensional work area is positioned on the extension line of the longitudinal boundary of the full coverage area, placing the shot points on the shot detection relation sheet on the shot points which are outside the full coverage range and are closest to the transverse boundary of the full coverage range, placing one shot point on the shot point relation sheet on the longitudinal boundary extension line of the full coverage range, and enabling no shot point on the shot detection relation sheet to be outside the longitudinal boundary extension line of the full coverage range;
step six: confirming a construction boundary: the method comprises the steps of enabling the direction of a wave detection line of a shot-inspection relational sheet to be parallel to the direction of a wave detection line of a three-dimensional work area, enabling a transverse boundary and a longitudinal boundary to be respectively acquisition line boundaries perpendicular to and parallel to the direction of the wave detection line, ensuring that a wave detection point and the wave detection line of the shot-inspection relational sheet are complete, determining a construction boundary, conducting three-dimensional seismic exploration construction, placing a shot point on the shot-inspection relational sheet on a shot point which is out of a full coverage range and is closest to the transverse boundary of the full coverage range when the transverse boundary of the full coverage range of the three-dimensional work area is not located on the shot point of the three-dimensional work area and no shot point of the three-dimensional work area is located on a longitudinal boundary extension line of the full coverage range, and enabling only one shot point on the shot-inspection relational sheet to be located.
Example 2:
the invention provides a three-dimensional seismic exploration interval arrangement construction method, which comprises the following specific steps:
the method comprises the following steps: covering the collection line: 9 acquisition lines are arranged on the ground within the full coverage range of the three-dimensional work area;
step two: arrangement of the acquisition stations: arranging 9 acquisition lines in parallel at intervals of 135 meters, and then arranging 23 detectors with directional sensitivity to particle motion in one direction on each acquisition line at intervals of 230 meters;
step three: setting a receiving channel: each acquisition station is provided with 10 receiving channels;
step four: dividing the space: dividing the 9 acquisition line segments into 9 intervals according to the equal size specification, wherein the specification of each interval is 700m x 700m, and inserting interval flags with different colors into each interval;
step five: covering shot points: arranging the shot points on the shot-checking relation sheet on the transverse boundary of the acquisition line, arranging one shot point on the shot-checking relation sheet at the intersection of the acquisition line and preventing the shot points on the shot-checking relation sheet from being arranged outside the exploration interval range, wherein the shot points on the shot-checking relation sheet have limitation on the motion direction of particles, the shot-checking relation sheet is rectangular, the full coverage range of the three-dimensional work area is also rectangular, the area of the shot-checking relation sheet is smaller than that of the three-dimensional work area, the shot points in the shot-checking relation sheet are arranged in a row, when the transverse boundary of the full coverage area of the three-dimensional work area is not positioned on the shot point of the three-dimensional work area and the shot point of the three-dimensional work area is positioned on the extension line of the longitudinal boundary of the full coverage area, placing the shot points on the shot detection relation sheet on the shot points which are outside the full coverage range and are closest to the transverse boundary of the full coverage range, placing one shot point on the shot point relation sheet on the longitudinal boundary extension line of the full coverage range, and enabling no shot point on the shot detection relation sheet to be outside the longitudinal boundary extension line of the full coverage range;
step six: confirming a construction boundary: the method comprises the steps of enabling the direction of a wave detection line of a shot-inspection relational sheet to be parallel to the direction of a wave detection line of a three-dimensional work area, enabling a transverse boundary and a longitudinal boundary to be respectively acquisition line boundaries perpendicular to and parallel to the direction of the wave detection line, ensuring that a wave detection point and the wave detection line of the shot-inspection relational sheet are complete, determining a construction boundary, conducting three-dimensional seismic exploration construction, placing a shot point on the shot-inspection relational sheet on a shot point which is out of a full coverage range and is closest to the transverse boundary of the full coverage range when the transverse boundary of the full coverage range of the three-dimensional work area is not located on the shot point of the three-dimensional work area and no shot point of the three-dimensional work area is located on a longitudinal boundary extension line of the full coverage range, and enabling only one shot point on the shot-inspection relational sheet to be located.
Example 3:
the invention provides a three-dimensional seismic exploration interval arrangement construction method, which comprises the following specific steps:
the method comprises the following steps: covering the collection line: arranging 10 acquisition lines on the ground in the full coverage range of the three-dimensional work area;
step two: arrangement of the acquisition stations: 10 acquisition lines are arranged in parallel at intervals of 150 meters, and then 25 detectors with directional sensitivity to particle motion in one direction are arranged on each acquisition line at intervals of 250 meters;
step three: setting a receiving channel: 15 receiving channels are arranged on each acquisition station;
step four: dividing the space: dividing 10 collecting line segments into 12 intervals according to the same size specification, wherein the specification of each interval is 700m x 900m, and inserting interval flags with different colors into each interval;
step five: covering shot points: arranging the shot points on the shot-checking relation sheet on the transverse boundary of the acquisition line, arranging one shot point on the shot-checking relation sheet at the intersection of the acquisition line and preventing the shot points on the shot-checking relation sheet from being arranged outside the exploration interval range, wherein the shot points on the shot-checking relation sheet have limitation on the motion direction of particles, the shot-checking relation sheet is rectangular, the full coverage range of the three-dimensional work area is also rectangular, the area of the shot-checking relation sheet is smaller than that of the three-dimensional work area, the shot points in the shot-checking relation sheet are arranged in a row, when the transverse boundary of the full coverage area of the three-dimensional work area is not positioned on the shot point of the three-dimensional work area and the shot point of the three-dimensional work area is positioned on the extension line of the longitudinal boundary of the full coverage area, placing the shot points on the shot detection relation sheet on the shot points which are outside the full coverage range and are closest to the transverse boundary of the full coverage range, placing one shot point on the shot point relation sheet on the longitudinal boundary extension line of the full coverage range, and enabling no shot point on the shot detection relation sheet to be outside the longitudinal boundary extension line of the full coverage range;
step six: confirming a construction boundary: the method comprises the steps of enabling the direction of a wave detection line of a shot-inspection relational sheet to be parallel to the direction of a wave detection line of a three-dimensional work area, enabling a transverse boundary and a longitudinal boundary to be respectively acquisition line boundaries perpendicular to and parallel to the direction of the wave detection line, ensuring that a wave detection point and the wave detection line of the shot-inspection relational sheet are complete, determining a construction boundary, conducting three-dimensional seismic exploration construction, placing a shot point on the shot-inspection relational sheet on a shot point which is out of a full coverage range and is closest to the transverse boundary of the full coverage range when the transverse boundary of the full coverage range of the three-dimensional work area is not located on the shot point of the three-dimensional work area and no shot point of the three-dimensional work area is located on a longitudinal boundary extension line of the full coverage range, and enabling only one shot point on the shot-inspection relational sheet to be located.
Example 4:
the following data were obtained from examples 1 to 3:
wave detection point Wave detection line Shot point Construction period Wire reversing vehicle
Example 1 35900 15 10 20 3
Example 2 43500 17 15 17 10
Example 3 46200 18 17 19 15
Control group 49700 20 20 30 20
As can be seen from the above table, the three-dimensional seismic exploration interval arrangement construction method of embodiments 1 to 3 can effectively optimize the elimination of the geophone points and the geophone lines, reduce the number of layout of the geophone points during seismic exploration, concentrate the devices in a reasonable interval, shorten the interval distance, and improve the completion efficiency of the rewinding task, but the optimization of embodiment 1 improves the degree to the maximum extent, so that the polarized waves with a certain direction can be excited and received during three-dimensional seismic exploration, the transverse waves can be polarized under certain conditions, the transverse waves can be divided into two types, and each time when rewinding, the vehicle only needs to walk the original 1/8 distance on the survey line or move the collected objects on the survey line arrangement to complete the rewinding task, thereby saving a large number of vehicles, reducing the construction cost, improving the construction efficiency, aiming at the three-dimensional work area to be constructed, according to the gun detection relationship sheets and the full coverage, under the condition that the shot-inspection relation piece is complete, namely the demodulator probe and the demodulator curve of the shot-inspection relation piece cannot be lost, part of the demodulator probe and the demodulator curve of the three-dimensional work area are optimized, the requirement that the data in the full coverage range can meet pre-stack migration processing can be met, the number of the demodulator probes used for construction is greatly reduced by 30%, the number of the demodulator curves is reduced by 5, the construction period is shortened by 10 days, and the labor cost is reduced.
Although the invention has been described in detail above with reference to a general description and specific examples, it will be apparent to one skilled in the art that modifications or improvements may be made thereto based on the invention. Accordingly, such modifications and improvements are intended to be within the scope of the invention as claimed.

Claims (7)

1. A three-dimensional seismic exploration interval arrangement construction method is characterized in that: the method comprises the following specific steps:
the method comprises the following steps: covering the collection line: arranging 8-10 acquisition lines on the ground in the full coverage range of the three-dimensional work area;
step two: arrangement of the acquisition stations: arranging 8-10 collection lines in parallel at intervals of 120-150 meters, and then arranging 20-25 collection stations on each collection line at intervals of 210-250 meters;
step three: setting a receiving channel: 6-15 receiving channels are arranged on each acquisition station;
step four: dividing the space: dividing 8-10 collecting line sections into 7-12 sections according to the same size specification, and inserting section flags with different colors into each section;
step five: covering shot points: placing the shot points on the shot-checking relation sheet on the transverse boundary of the acquisition line, placing one shot point on the shot-checking relation sheet at the intersection of the acquisition line and preventing the shot points on the shot-checking relation sheet from being arranged outside the exploration interval range;
step six: confirming a construction boundary: the direction of a geophone correlation piece is parallel to the direction of a geophone line of a three-dimensional work area, and the transverse boundary and the longitudinal boundary are respectively acquisition line boundaries which are perpendicular to and parallel to the direction of the geophone line, so that the completeness of a geophone point and the geophone line of the geophone correlation piece is ensured, a construction boundary is determined, and three-dimensional seismic exploration construction is carried out.
2. The method of claim 1, wherein the method comprises: in step four, the specification of each interval is 700m 600m-700m 900 m.
3. The method of claim 1, wherein the method comprises: the acquisition station in step two is a detector with directional sensitivity to particle motion in one direction.
4. The method of claim 1, wherein the method comprises: and in the fifth step, the shot point on the shot checking relation sheet has limit on the particle motion direction.
5. The method of claim 1, wherein the method comprises: in the fifth step, the shot-checking relation pieces are rectangular, the full coverage range of the three-dimensional work area is also rectangular, the area of the shot-checking relation pieces is smaller than that of the three-dimensional work area, and the shot points in the shot-checking relation pieces are arranged in a row.
6. The method of claim 1, wherein the method comprises: and fifthly, when the transverse boundary of the full coverage range of the three-dimensional work area is not positioned on the shot point of the three-dimensional work area and the longitudinal boundary extension line of the full coverage range has the shot point of the three-dimensional work area, placing the shot point on the shot detection relation sheet on the shot point which is out of the full coverage range and is closest to the transverse boundary of the full coverage range, placing one shot point on the shot point relation sheet on the longitudinal boundary extension line of the full coverage range and enabling no shot point on the shot detection relation sheet to be out of the longitudinal boundary extension line of the full coverage range.
7. The method of claim 1, wherein the method comprises: in the sixth step, when the transverse boundary of the full coverage area of the three-dimensional work area is not positioned on the shot point of the three-dimensional work area and the longitudinal boundary extension line of the full coverage area does not have the shot point of the three-dimensional work area, the shot point on the shot detection relation sheet is positioned on the shot point which is out of the full coverage area and is closest to the transverse boundary of the full coverage area, and only one shot point on the shot detection relation sheet is arranged out of the longitudinal boundary extension line of the full coverage area.
CN202110014344.8A 2021-01-06 2021-01-06 Three-dimensional seismic exploration interval arrangement construction method Pending CN112799122A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110014344.8A CN112799122A (en) 2021-01-06 2021-01-06 Three-dimensional seismic exploration interval arrangement construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110014344.8A CN112799122A (en) 2021-01-06 2021-01-06 Three-dimensional seismic exploration interval arrangement construction method

Publications (1)

Publication Number Publication Date
CN112799122A true CN112799122A (en) 2021-05-14

Family

ID=75808679

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110014344.8A Pending CN112799122A (en) 2021-01-06 2021-01-06 Three-dimensional seismic exploration interval arrangement construction method

Country Status (1)

Country Link
CN (1) CN112799122A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4001770A (en) * 1974-06-17 1977-01-04 Texas Instruments Incorporated Roll-a-long three-dimensional common depth point exploration
CN1120169A (en) * 1995-02-16 1996-04-10 辽河石油勘探局地球物理勘探公司 Construction method for three-dimensional seismic prospecting spacing arrangement
CN102062869A (en) * 2009-11-17 2011-05-18 中国石油化工股份有限公司 Method for designing seismic exploration and observation system
CN103995281A (en) * 2014-05-08 2014-08-20 中国石油化工股份有限公司 Method for rapid rolling laying of three-dimensional observation system
CN105319576A (en) * 2014-07-31 2016-02-10 中国石油化工股份有限公司 Concave polygon region observation system automatic full coverage quick layout method
CN106855635A (en) * 2016-12-09 2017-06-16 中国石油天然气集团公司 A kind of method and apparatus of the bin attributes information for determining orthogonal observation system
CN107678057A (en) * 2017-09-25 2018-02-09 中国石油集团川庆钻探工程有限公司地球物理勘探公司 Determined in 3-D seismics or optimize wave detector or equipment investment amount and the method for arrangement
CN111551983A (en) * 2020-06-02 2020-08-18 中国石油化工股份有限公司 Three-dimensional seismic exploration construction boundary optimization method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4001770A (en) * 1974-06-17 1977-01-04 Texas Instruments Incorporated Roll-a-long three-dimensional common depth point exploration
CN1120169A (en) * 1995-02-16 1996-04-10 辽河石油勘探局地球物理勘探公司 Construction method for three-dimensional seismic prospecting spacing arrangement
CN102062869A (en) * 2009-11-17 2011-05-18 中国石油化工股份有限公司 Method for designing seismic exploration and observation system
CN103995281A (en) * 2014-05-08 2014-08-20 中国石油化工股份有限公司 Method for rapid rolling laying of three-dimensional observation system
CN105319576A (en) * 2014-07-31 2016-02-10 中国石油化工股份有限公司 Concave polygon region observation system automatic full coverage quick layout method
CN106855635A (en) * 2016-12-09 2017-06-16 中国石油天然气集团公司 A kind of method and apparatus of the bin attributes information for determining orthogonal observation system
CN107678057A (en) * 2017-09-25 2018-02-09 中国石油集团川庆钻探工程有限公司地球物理勘探公司 Determined in 3-D seismics or optimize wave detector or equipment investment amount and the method for arrangement
CN111551983A (en) * 2020-06-02 2020-08-18 中国石油化工股份有限公司 Three-dimensional seismic exploration construction boundary optimization method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘万金等: "煤田三维地震采集设计中减少施工面积的方法", 《物探与化探》 *

Similar Documents

Publication Publication Date Title
CN102788991B (en) High-density rapid detection method based on z-component transmitting channel waves
CN102426384B (en) Method for detecting underground goaf and karst distribution
CN102262240B (en) Automatic layout method for full coverage area of three-dimensional observation system
CN107132571A (en) A kind of multi-source seismic interference method for tunnel geological forecast
CN110187390B (en) Coal mine tunnel parallel survey line three-dimensional earthquake observation and imaging method
CN110687602A (en) Shallow seismic multi-wave combined exploration method
CN103424769A (en) Combined multi-wave seismic exploration method in gob
CN111812707A (en) Method for detecting boulders in subway line site based on micro-motion and surface wave exploration
Huang et al. Source identification of microseismic events in underground mines with interferometric imaging and cross wavelet transform
CN102087367B (en) Method for dividing bed rock weathering zones by using longitudinal wave-surface wave speed ratio method
Dai et al. Focal mechanism determination for microseismic events and its application to the left bank slope of the Baihetan hydropower station in China
CN113376695B (en) Full waveform inversion method suitable for complex collapse column of coal seam floor
CN105866839A (en) Static correction method and static correction device on basis of common-attitude trace gathers
CN102914790B (en) Observing system method for primary collection of two-dimensional observing system and three-dimensional observing system
Spottiswoode et al. The use of waveform similarity to define planes of mining-induced seismic events
CN112799122A (en) Three-dimensional seismic exploration interval arrangement construction method
CN102798884B (en) Tunnel roof two-dimensional seismic exploration method and system
CN109085642A (en) A kind of anisotropic medium micro-seismic event localization method
CN102478663B (en) Three-dimensional seismological observation system migration noise obtaining method and device
CN103777246B (en) Common source receiving system of seismic prospecting instrument and VSP logging instrument
CN105607128A (en) Geological fault detection method under hard and soft interbedded geological condition
CN104155682A (en) Micro vibration seismic exploration method using moving vehicle as seismic source
CN111551983B (en) Three-dimensional seismic exploration construction boundary optimization method
CN110045414B (en) Method for detecting deep metal ore in mining area
Wang et al. A polarization migration velocity model building method for geological prediction ahead of the tunnel face

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210514