Disclosure of Invention
The invention aims to provide a scaffold pre-buried sliding groove type wall connecting piece to solve the problems that pre-buried steel pipes cannot be circulated, a hole reserved behind a masonry needs to be plugged and the like.
In order to achieve the purpose, the invention adopts the technical scheme that: a scaffold pre-buried sliding groove type wall connecting piece comprises a pre-buried piece and a wall connecting rod, wherein anchoring steel bars are arranged on the back surface of the pre-buried piece, and two sliding grooves which are oppositely arranged are vertically arranged on the front surface of the pre-buried piece; a connecting plate is fixed at one end of the wall connecting rod, through holes are respectively formed in the connecting bottom plate and positioned on two sides of the wall connecting rod, nuts are fixed on the connecting bottom plate and correspond to the through holes, and bolts are mounted on the nuts; when the connecting plate is used, two sides of the connecting plate are respectively arranged in the two sliding grooves, and the tail part of the bolt is abutted against the embedded part.
When the wall connecting piece is installed, the connecting bottom plate slides into the sliding groove of the embedded part, then the bolt is screwed down to enable the tail portion of the connecting bottom plate to be abutted against the embedded part, at the moment, the connecting bottom plate is abutted against the inner wall of the sliding groove, therefore, one end of the wall connecting rod is fixed on a building structure, and the other end of the wall connecting rod can be connected with a scaffold. The wall connecting piece adopts the wall connecting rod, the bolt and other recyclable materials, so that the engineering cost is saved, the purposes of cost reduction and efficiency improvement are achieved, and the phenomenon of leakage caused by untight plugging of the wall opening is avoided.
Preferably, the embedded part is a steel plate, two symmetrically arranged L-shaped steel plates are vertically welded on two sides of the front surface of the embedded part, and a sliding groove is formed between each L-shaped steel plate and the embedded part.
Preferably, the length of the embedded part is not less than twice of the length of the connecting bottom plate.
Preferably, the anchoring steel bar is L-shaped, and one end of the horizontal section of the anchoring steel bar is welded with the embedded part.
Preferably, the length of the horizontal section of the anchoring bar is 100mm, and the length of the vertical section is 50 mm.
Preferably, one end of the wall connecting rod is welded at the center of the connecting plate, and the other end of the wall connecting rod is connected with the scaffold in use.
Preferably, when the embedded part is used, the embedded part is embedded in the building structure, and the outer wall of the sliding groove is flush with the outer vertical surface of the building structure.
Based on the same invention concept, the invention also provides a construction method of the scaffold pre-buried sliding groove type wall connecting piece, which specifically comprises the following steps:
firstly, vertically embedding an embedded part into a building structure before an outer wall template is installed, and connecting an anchoring steel bar on the back of the embedded part with a main bar of the building structure;
after the external wall template is disassembled, the connecting bottom plate slides into a sliding groove in the front face of the embedded part, so that the wall connecting rod fixed on the connecting bottom plate is perpendicular to the external vertical face of the building structure;
screwing the bolt into the nut of the connecting bottom plate to enable the tail of the bolt to abut against the embedded part;
and step four, connecting the other end of the wall connecting rod to the scaffold through a fastener.
The invention has the beneficial effects that:
1. the construction method of the wall connecting piece is simple in process, strong in operability and small in construction difficulty. The wall connecting part is divided into an embedded part and a wall connecting rod, the embedded part is a part embedded in the construction process of a building structure, and the wall connecting rod is connected with the embedded part through a connecting bottom plate and is tightly propped through a bolt, so that the wall connecting rod is installed and fixed; when the wall connecting rod is dismantled, the wall connecting rod can slide out only by loosening the bolt, so that the engineering quality can be improved, and the engineering progress is accelerated;
2. compared with the traditional scaffold wall connecting piece, the scaffold wall connecting piece has the advantages that the wall connecting rod, the bolt and the like are adopted, materials can be used in a circulating mode, the engineering cost is saved, the purposes of cost reduction and efficiency improvement are achieved, the risk of leakage caused by untight plugging of the wall opening is avoided, good social benefits are achieved, and the scaffold wall connecting piece is suitable for popularization and use.
Detailed Description
The invention is further illustrated by the following figures and examples.
A scaffold pre-buried chute type wall connecting piece is shown in figures 1-4 and comprises an embedded part 1 and a wall connecting rod 3, wherein anchoring reinforcing steel bars 12 are arranged on the back face of the embedded part 1, and two chutes 11 which are arranged oppositely are vertically arranged on the front face of the embedded part 1. One end of the wall connecting rod 3 is fixed with a connecting plate 2, through holes are respectively arranged on the two sides of the wall connecting rod 3 on the connecting base plate 2, nuts 21 are fixed on the connecting base plate 2 corresponding to the through holes, and bolts 22 are installed on the nuts 21. When the wall connecting rod is used, two sides of the connecting plate 2 are respectively arranged in the two sliding grooves 11, the tail part of the bolt 22 abuts against the embedded part 1, and the free end of the wall connecting rod 3 is connected with the scaffold 5 through the fastener 6.
In this embodiment, the embedded part 1 is vertically embedded in the building structure 4, and the outer wall of the sliding groove 11 is flush with the outer surface of the building structure 4. The length of the embedded part is not less than 2 times of the length of the connecting bottom plate, and the width of the embedded part is not less than the width of the connecting bottom plate. The anchoring steel bar 12 is in an L shape, one end of the horizontal section of the anchoring steel bar is connected with the embedded part 1 in a welding mode, the length of the anchoring steel bar is 100mm, and the length of the vertical section of the anchoring steel bar is 50 mm. The sliding groove 11 is formed by welding and connecting an L-shaped steel plate and the embedded part 1, the length of the sliding groove 11 is not less than that of the connecting bottom plate 2, and the depth of the sliding groove 11 is slightly greater than the thickness of the connecting bottom plate 2. The connecting bottom plate 2 is a square steel plate, and the size of the steel plate is larger than the diameter of the wall connecting rod 3. The specification of the bolt 22 corresponds to that of the nut 21, and after the connecting bottom plate 2 slides into the sliding groove 11, the bolt 22 is screwed tightly and fixed with the embedded part 1.
The construction method of the scaffold pre-buried sliding groove type wall connecting piece in the embodiment specifically comprises the following steps:
the method comprises the following steps: before the outer wall template is installed, vertically embedding an embedded part 1 in a building structure 4, arranging a chute 11 at the lower end of the embedded part 1, and connecting an anchoring reinforcing steel bar 12 with a main bar 41 of the building structure;
step two: after the external wall template is dismantled, one end of the wall connecting rod 3 slides into the embedded part sliding groove 11 through the connecting bottom plate 2 and is vertical to an external vertical surface (a surface vertical to a horizontal plane or a surface with a certain inclination angle relative to the horizontal plane) of the building structure 4;
step three: and screwing two bolts 22 into two nuts 21 of the connecting base plate 2 respectively, so that the tail parts of the bolts 22 are tightly fixed with the embedded part 1.
Step four: the other end of the wall connecting rod 3 is connected with the vertical rod of the scaffold 5 through a fastener 6, so that the construction and installation of the wall connecting piece are realized.