CN112510466B - A kind of cable quick connection construction method - Google Patents
A kind of cable quick connection construction method Download PDFInfo
- Publication number
- CN112510466B CN112510466B CN202011321584.4A CN202011321584A CN112510466B CN 112510466 B CN112510466 B CN 112510466B CN 202011321584 A CN202011321584 A CN 202011321584A CN 112510466 B CN112510466 B CN 112510466B
- Authority
- CN
- China
- Prior art keywords
- ring
- waterproof
- cable body
- rubber
- annular groove
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- H—ELECTRICITY
- H01—ELECTRIC ELEMENTS
- H01R—ELECTRICALLY-CONDUCTIVE CONNECTIONS; STRUCTURAL ASSOCIATIONS OF A PLURALITY OF MUTUALLY-INSULATED ELECTRICAL CONNECTING ELEMENTS; COUPLING DEVICES; CURRENT COLLECTORS
- H01R43/00—Apparatus or processes specially adapted for manufacturing, assembling, maintaining, or repairing of line connectors or current collectors or for joining electric conductors
- H01R43/26—Apparatus or processes specially adapted for manufacturing, assembling, maintaining, or repairing of line connectors or current collectors or for joining electric conductors for engaging or disengaging the two parts of a coupling device
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/14—Extreme weather resilient electric power supply systems, e.g. strengthening power lines or underground power cables
Landscapes
- Engineering & Computer Science (AREA)
- Manufacturing & Machinery (AREA)
- Cable Accessories (AREA)
Abstract
Description
技术领域technical field
本申请涉及电缆维护的领域,尤其是涉及一种电缆快速驳接施工方法。The present application relates to the field of cable maintenance, and in particular, to a construction method for quick connection of cables.
背景技术Background technique
电缆是由一根或多根相互绝缘的导体和外包绝缘保护层制成,将电力或信息从一处传输到另一处的导线,当一个电缆盘的电缆长度不满足线路的设计要求时,需将两段电缆通过电缆中间接头连接起来使用。A cable is made of one or more mutually insulated conductors and an outer insulating protective layer, which transmits power or information from one place to another. When the cable length of a cable reel does not meet the design requirements of the line, It is necessary to connect the two sections of cable through the middle connector of the cable.
在相关的电缆快速驳接工艺中,一般先用斜口钳或者美工刀对两条线缆端部进行开线处理,使得线缆两端的线芯暴露,并将两个线缆的线芯分别压接固定在过连接头的两端,并用绝缘带将两根线缆端部缠绕固定,绝缘带起到绝缘和防水的作用。In the related rapid cable connection process, generally, the ends of the two cables are opened with diagonal pliers or a utility knife, so that the cores at both ends of the cable are exposed, and the cores of the two cables are separated. The crimp is fixed on both ends of the over-connector, and the ends of the two cables are wrapped and fixed with insulating tape, which plays the role of insulation and waterproofing.
针对上述中的相关技术,发明人认为:当线缆使用时间较长,长时间经受风吹日晒,绝缘带容易老化,从而使得防水性能变差,容易出现因渗水而出现电路短路的情况,因此仍有改进空间。In view of the above-mentioned related technologies, the inventor believes that when the cable is used for a long time and is exposed to the wind and the sun for a long time, the insulating tape is easy to age, so that the waterproof performance is deteriorated, and the circuit short circuit due to water seepage is prone to occur. So there is still room for improvement.
发明内容SUMMARY OF THE INVENTION
为了提高线缆的防水性能,本申请提供一种电缆快速驳接施工方法。In order to improve the waterproof performance of cables, the present application provides a construction method for rapid connection of cables.
本申请提供的一种电缆快速驳接施工方法采用如下的技术方案:A cable quick connection construction method provided by the application adopts the following technical solutions:
一种电缆快速驳接施工方法,包括以下步骤:A construction method for quick connection of cables, comprising the following steps:
步骤一:预制防水套件和铜线连接件;Step 1: Prefabricated waterproof kits and copper wire connectors;
步骤二:安装防水套件:准备两个相互配合的防水套件,将两个防水套件分别套在两条电缆本体端部;Step 2: Install the waterproof kit: Prepare two waterproof kits that cooperate with each other, and put the two waterproof kits on the ends of the two cable bodies respectively;
步骤三:线缆开线处理:切除两根线缆本体端部的绝缘层,使线缆本体的线芯暴露;Step 3: Cable opening processing: cut off the insulating layers at the ends of the two cable bodies to expose the cores of the cable bodies;
步骤四:压接线缆本体:将线缆本体的线芯分别压接固定在铜线连接件的两端;Step 4: Crimp the cable body: crimp the cores of the cable body to the two ends of the copper wire connector respectively;
步骤五:线缆绝缘处理:用绝缘带缠绑固定在两根线芯裸露处以及铜线连接件裸露处;Step 5: Cable insulation treatment: use insulating tape to bind and fix the exposed parts of the two cores and the exposed copper wire connectors;
步骤六:拼接防水套件;Step 6: Splicing waterproof kit;
步骤七:防水套件密封防水处理;Step 7: The waterproof kit is sealed and waterproof;
所述防水套件呈筒状且一端开口设置,所述防水套件底壁贯穿有供线缆本体穿过的通孔,两个所述防水套件开口相互正对,且其中一个防水套件内周面与另一个防水套件外周面螺纹连接,所述防水套件外底壁设置有锁紧线缆本体的锁紧件。The waterproof sleeve is cylindrical and has an opening at one end, the bottom wall of the waterproof sleeve has a through hole for the cable body to pass through, the two waterproof sleeve openings are facing each other, and the inner peripheral surface of one of the waterproof sleeves is the same as the one. The outer peripheral surface of the other waterproof kit is threadedly connected, and the outer bottom wall of the waterproof kit is provided with a locking member for locking the cable body.
通过采用上述技术方案,通过将防水套件套设在线缆本体外周面,并在两个防水套件拼接之前,完成两条电缆本体线芯的压接以及绝缘处理,并通过两个防水套件的螺纹连接,从形成包裹电缆本体连接处的外壳,从而减少了连接处暴露在外的情况,延缓了绝缘带的老化速度,进而提高了电缆本体连接处的防水性能,通过锁紧件将防水套件与线缆本体锁紧,有利于降低线缆本体出现滑动的概率,同时在通孔处将线缆本体锁紧,有利于降低水从通孔处进入防水套件空腔内的情况,有利于提高该防水套件的防水性能。By using the above technical solution, the waterproof kit is sleeved on the outer peripheral surface of the cable body, and before the two waterproof kits are spliced, the crimping and insulation treatment of the cores of the two cable bodies are completed, and the threads of the two waterproof kits are completed. The connection forms a shell that wraps the connection of the cable body, thereby reducing the exposure of the connection, delaying the aging speed of the insulating tape, and improving the waterproof performance of the connection of the cable body. The cable body is locked, which is beneficial to reduce the probability of sliding of the cable body. At the same time, the cable body is locked at the through hole, which is beneficial to reduce the situation that water enters the cavity of the waterproof kit from the through hole, and is beneficial to improve the waterproofness. Water resistance of the kit.
优选的,所述通孔内侧壁开有第一环形槽,所述第一环形槽内设置有橡胶环,当所述线缆本体穿过通孔时,所述橡胶环套设于线缆本体外周面。Preferably, a first annular groove is formed on the inner side wall of the through hole, and a rubber ring is arranged in the first annular groove. When the cable body passes through the through hole, the rubber ring is sleeved on the cable body peripheral surface.
通过采用上述技术方案,将第一环形槽内的橡胶环套设在线缆本体的外周面,进行填补了水从通孔和线缆本体之间的间隙,并阻断水渗入防水套件空腔内的路径,有利于提高防水套件的防水性能。By adopting the above technical solution, the rubber ring in the first annular groove is sleeved on the outer peripheral surface of the cable body, so as to fill the gap between the water from the through hole and the cable body, and prevent water from infiltrating into the cavity of the waterproof kit The inner path is beneficial to improve the waterproof performance of the waterproof kit.
优选的,所述第一环形槽内设置驱动环,所述驱动环套设于橡胶环外侧,所述驱动环内侧设置有若干个周向分布的驱动齿,所述橡胶环外侧设置有若干个周向分布的橡胶块,若干所述驱动齿与若干所述橡胶块相错设置,所述橡胶环的两个端面分别开有若干个导向槽,若干所述导向槽长度方向的延长线交汇于通孔轴线的一点,所述第一环形槽两个内侧壁设置有若干个分别位于若干导向槽内的限位块;所述防水套件外周面开有与第一环形槽相通的操作槽,所述驱动环外侧设置有位于操作槽内的操作杆,当若干所述驱动齿的齿顶部与若干橡胶块朝向驱动环的一端一一抵紧时,所述橡胶环内侧抵紧线缆本体外周面。Preferably, a drive ring is arranged in the first annular groove, the drive ring is sleeved on the outer side of the rubber ring, the inner side of the drive ring is provided with a number of driving teeth distributed in the circumferential direction, and the outer side of the rubber ring is provided with a number of driving teeth Circumferentially distributed rubber blocks, a plurality of the driving teeth and a plurality of the rubber blocks are arranged in a staggered manner, the two end faces of the rubber ring are respectively provided with a plurality of guide grooves, and the extension lines in the length direction of the guide grooves meet at the At one point of the axis of the through hole, the two inner side walls of the first annular groove are provided with a number of limit blocks respectively located in the guide grooves; the outer peripheral surface of the waterproof sleeve is provided with an operation groove that communicates with the first annular groove, so The outer side of the drive ring is provided with an operating rod located in the operating groove. When the tooth tops of the driving teeth and the rubber blocks are pressed against one end of the driving ring one by one, the inner side of the rubber ring is pressed against the outer peripheral surface of the cable body. .
通过采用上述技术方案,从而可通过摆动操作杆来驱使驱动环转动,并使驱动环内侧的驱动齿朝驱动环内环的切线方向挤压橡胶环外侧的橡胶块,在限位块的限制作用下,橡胶环不跟随驱动环一起转动,并在导向槽的导向作用下,使得驱动齿与橡胶块从相错状态转变为相互抵紧的状态,并迫使橡胶环收缩并抵紧电缆本体外周面,进一步提高了橡胶环的密封性,有利于提高防水套件的防水性能。By adopting the above technical solution, the driving ring can be driven to rotate by swinging the operating rod, and the driving teeth on the inner side of the driving ring can press the rubber block on the outer side of the rubber ring in the tangential direction of the inner ring of the driving ring, so that the limiting effect of the limit block is Under the guidance of the guide groove, the rubber ring does not rotate with the driving ring, and the driving teeth and the rubber block are changed from the staggered state to the mutually tight state, and the rubber ring is forced to shrink and press against the outer peripheral surface of the cable body. , which further improves the sealing performance of the rubber ring, which is beneficial to improve the waterproof performance of the waterproof kit.
优选的,所述防水套件外周面开有第二环形槽,所述第二环形槽转动连接有封闭所述操作槽开口的外环,所述外环内侧与操作杆远离驱动环的一端固定连接。Preferably, a second annular groove is formed on the outer peripheral surface of the waterproof sleeve, the second annular groove is rotatably connected with an outer ring that closes the opening of the operating groove, and the inner side of the outer ring is fixedly connected to the end of the operating rod away from the drive ring .
通过采用上述技术方案,在操作杆的联动下。可通过转动外环来驱使驱动环转动,便于安装人员操作,同时,外环封闭操作槽的开口,从而减少水从操作槽内进入防水套件空腔内部,有利于提高防水套件的防水性能。By adopting the above technical solution, under the linkage of the operating lever. The drive ring can be driven to rotate by rotating the outer ring, which is convenient for the installation personnel to operate. At the same time, the outer ring closes the opening of the operation slot, thereby reducing the water entering the cavity of the waterproof kit from the operation slot, which is beneficial to improve the waterproof performance of the waterproof kit.
优选的,所述外环、操作杆以及驱动环共同贯穿有注料孔,所述注料孔两端分别连通外环的外侧和驱动环的内侧。Preferably, the outer ring, the operating rod and the driving ring are jointly provided with injection holes, and both ends of the injection holes are respectively connected to the outer side of the outer ring and the inner side of the driving ring.
通过采用上述技术方案,使得注料孔连通防水套件外部和第一环形槽内部,从而可通过往注料孔注入树脂,使树脂填满防水套件内部的空隙,待树脂固化后,有利于进一步提高防水套件的防水性能。By adopting the above technical solution, the injection hole is connected to the outside of the waterproof kit and the inside of the first annular groove, so that the resin can be injected into the injection hole to fill the gap inside the waterproof kit. After the resin is cured, it is beneficial to further improve the The waterproof performance of the waterproof kit.
优选的,所述橡胶环开设有若干连接孔,所述连接孔连通橡胶环内侧和橡胶环外侧。Preferably, the rubber ring is provided with a plurality of connecting holes, and the connecting holes communicate with the inner side of the rubber ring and the outer side of the rubber ring.
通过采用上述技术方案,使得树脂可通过连接孔与线缆本体外周面,待树脂固化后,有利于提高线缆本体在通孔处的稳固性。By adopting the above technical solution, the resin can pass through the connecting hole and the outer peripheral surface of the cable body, and after the resin is cured, it is beneficial to improve the stability of the cable body at the through hole.
优选的,所述橡胶环内侧开设有第三环形槽,所述第三环形槽底壁与若干所述连接孔连通。Preferably, a third annular groove is formed on the inner side of the rubber ring, and the bottom wall of the third annular groove communicates with a plurality of the connecting holes.
通过采用上述技术方案,使得树脂经过连接孔进入第三环形槽,待树脂固化后,会在线缆本体外周面形成防水圈,从而进一步提高了防水套件的防水性能。By adopting the above technical solution, the resin enters the third annular groove through the connecting hole, and after the resin is cured, a waterproof ring is formed on the outer peripheral surface of the cable body, thereby further improving the waterproof performance of the waterproof kit.
优选的,所述防水套件外周面开有与第一环形槽相通的连接槽,驱动环外侧设置有位于连接槽内且与驱动环外侧固定连接的连接杆,所述外环、连接杆以及驱动环共同贯穿有气孔,所述气孔两端分别连通外环的外侧和驱动环的内侧,所述外环设置有封闭所述气孔的橡胶塞。Preferably, the outer peripheral surface of the waterproof sleeve is provided with a connecting groove which communicates with the first annular groove, and the outer side of the driving ring is provided with a connecting rod which is located in the connecting groove and is fixedly connected with the outer side of the driving ring. The rings pass through together with air holes, the two ends of the air holes are respectively connected to the outer side of the outer ring and the inner side of the driving ring, and the outer ring is provided with a rubber plug that closes the air holes.
通过采用上述技术方案,使得防水套件内部空隙通过气孔和注料孔而与外界连通,有利于在往注料孔注入树脂时,防水套件内的压强与大气压强保持平衡,有利于提高树脂的注料速率,通过橡胶塞的设置,可在树脂填满防水套件内部空隙后进行封堵,便于树脂固化成型。By adopting the above technical solution, the voids inside the waterproof kit are communicated with the outside through the air holes and the injection holes, which is beneficial to maintain a balance between the pressure in the waterproof kit and the atmospheric pressure when the resin is injected into the injection holes, which is beneficial to improve the injection rate of the resin. Through the setting of the rubber stopper, the resin can be sealed after filling the internal void of the waterproof kit, which is convenient for resin curing and molding.
综上所述,本申请包括以下至少一种有益技术效果:To sum up, the present application includes at least one of the following beneficial technical effects:
1.通过在线缆本体外周面套设防水套件,并通过两个防水套件的螺纹连接,从而在电缆本体连接处的四周形成保护屏障,从而减少了连接处暴露在外的情况,延缓了绝缘带的老化速度,进而提高了电缆本体连接处的防水性能;1. By covering the outer circumference of the cable body with a waterproof kit and connecting the two waterproof kits with threads, a protective barrier is formed around the connection of the cable body, thereby reducing the exposure of the connection and delaying the insulation tape. The aging speed of the cable body is improved, and the waterproof performance of the connection of the cable body is improved;
2.通过注料孔的开设,使注料孔与防水套件的内部空隙与外界连通,通过往注料孔注入防水套件的内部空隙内,有利于提高防水套件的防水性能。2. Through the opening of the injection hole, the injection hole and the inner gap of the waterproof kit are connected to the outside world, and by injecting the injection hole into the inner gap of the waterproof kit, it is beneficial to improve the waterproof performance of the waterproof kit.
附图说明Description of drawings
图1是本申请实施例的整体结构示意图。FIG. 1 is a schematic diagram of the overall structure of an embodiment of the present application.
图2是本申请实施例中防水套件的内部结构示意图。FIG. 2 is a schematic diagram of the internal structure of the waterproof kit in the embodiment of the present application.
图3是图2中A处的放大示意图。FIG. 3 is an enlarged schematic view of A in FIG. 2 .
图4是本实施实施例中外环以及防水套件径向剖视图。FIG. 4 is a radial cross-sectional view of the outer ring and the waterproof sleeve in this embodiment.
图5是图4中B处的放大示意图。FIG. 5 is an enlarged schematic view of B in FIG. 4 .
附图标记说明:1、线缆本体;11、线芯;2、防水套件;21、第一环形槽;211、限位块;22、操作槽;23、第二环形槽;24、连接槽;3、铜线连接件;31、套管;32、软铜线;4、锁紧件;41、抱箍;42、橡胶圈;5、绝缘带;6、橡胶环;61、橡胶块;62、连接孔;63、导向槽;64、第三环形槽;7、橡胶塞;8、外环;81、操作杆;811、注料孔;82、连接杆;821、气孔;83、驱动环;831、驱动齿。Description of reference numerals: 1. cable body; 11. wire core; 2. waterproof kit; 21, first annular groove; 211, limit block; 22, operating groove; 23, second annular groove; 24, connecting groove ;3, copper wire connector; 31, casing; 32, soft copper wire; 4, locking piece; 41, hoop; 42, rubber ring; 5, insulating tape; 6, rubber ring; 61, rubber block; 62, connecting hole; 63, guide groove; 64, third annular groove; 7, rubber plug; 8, outer ring; 81, operating rod; 811, injection hole; 82, connecting rod; 821, air hole; 83, drive ring; 831, drive teeth.
具体实施方式Detailed ways
以下结合附图1-5对本申请作进一步详细说明。The present application will be further described in detail below in conjunction with accompanying drawings 1-5.
本申请实施例公开一种电缆快速驳接施工方法。参照图1和图2,一种电缆快速驳接施工方法包括以下步骤:The embodiment of the present application discloses a construction method for rapid connection of cables. 1 and 2, a construction method for quick connection of cables includes the following steps:
步骤一:预制防水套件和铜线连接件;Step 1: Prefabricated waterproof kits and copper wire connectors;
步骤二:安装防水套件:准备两个相互配合的防水套件2,将两个防水套件2分别套在两条电缆本体端部;Step 2: Install the waterproof kit: Prepare two
步骤三:线缆本体开线处理:用斜口钳切除两根线缆本体1端部的绝缘层,使线缆本体1的线芯11裸露预定长度;Step 3: Cable body opening processing: use diagonal pliers to cut off the insulating layers at the ends of the two
步骤四:压接线缆本体:将两根线缆本体1的线芯11分别与铜线连接件3的两端连接并用于压接钳压接固定;Step 4: Crimp the cable body: connect the
步骤五:线缆本体绝缘处理:用绝缘带5缠绑固定在两根线芯11裸露处以及铜线连接件3裸露处;Step 5: Insulation treatment of the cable body: use insulating tape 5 to wrap and fix it on the exposed parts of the two
步骤六:拼接防水套件;Step 6: Splicing waterproof kit;
步骤七:防水套件密封防水处理;Step 7: The waterproof kit is sealed and waterproof;
防水套件2呈圆筒状且一端开口设置,防水套件2底壁沿自身轴线方向贯穿有供线缆本体1穿过的通孔,两个防水套件2开口正对设置,其中一个防水套件2的外径为10cm,且该防水套件2的外周面开有外螺纹。另一个防水套件2的内径为10cm,且该防水套件2内周面开有内螺纹,两个防水套件2通过螺纹连接完成拼接操作。防水套件2外底壁安装有锁紧件4,锁紧件4包括固定在防水套件2外底壁的橡胶圈42以及锁紧橡胶圈42外侧的抱箍41,橡胶圈42抵紧线缆本体1外周面,橡胶圈42轴线与通孔重合,抱箍41通过螺栓锁紧,从而在达到固定线缆本体1和线缆本体1固定目的的同时,也在通孔开口处形成密封层,有利于提高该防水套件2的防水性能。铜线连接件3包括两个套管31和若干根连接两个套管31的软铜线32,将两个套管31套住线缆本体1的线芯11并压接固定。从而实现了两条线缆本体1的可靠连接的目的。The
参照图3和图4,通孔内侧壁开有第一环形槽21,第一环形槽21环绕于通孔内侧壁。第一环形槽21内放置有橡胶环6,橡胶环6的两个端面分别与第一环形槽21的两个内侧壁抵接。当线缆本体1穿过通孔时,橡胶环6套设在线缆本体1外周面,橡胶环6的设置,在通孔内侧壁处形成了第二道密封层,有利于进一步提高防水套件2的防水性能。Referring to FIGS. 3 and 4 , a first
参照图3和图5,第一环形槽21内安装有驱动环83,驱动环83套设于橡胶环6外侧,驱动环83的轴线与橡胶环6的轴线重合,驱动环83外侧与第一环形槽21的底壁抵接。驱动环83内侧固定有若干个驱动齿831,若干驱动齿831绕驱动环83轴线周向等间隔分布。橡胶环6外侧固定有若干个橡胶块61,若干橡胶块61绕橡胶环6轴线周向等间隔分布。若干驱动齿831与若干橡胶块61间隔相错设置,橡胶环6两个端面开有若干个导向槽63,若干导向槽63与若干橡胶块61一一对应。若干导向槽63长度方向的延长线交汇于通孔轴线的一点,第一环形槽21两个内侧壁固定有若干个分别位于若干导向槽63内的限位块211。限位块211呈圆柱状。防水套件2外周面开有与第一环形槽21相通的操作槽22,驱动环83外侧固定有伸入操作槽22内的操作杆81,操作槽22往防水套件2外周面的切线方向延展,从而为操作杆81绕防水套件2轴线摆动时提供移动空间。当若干驱动齿831的齿顶部与若干橡胶块61朝向驱动环83的一端一一抵紧时,橡胶环6内侧抵紧线缆本体1外周面,从而进一步提高了橡胶环6的密封性,有利于提高防水套件2的防水性能。3 and 5, a
参照图4和图5,防水套件2外周面开有第二环形槽23,第二环形槽23环绕防水套件2外周面。第二环形槽23转动连接有封闭操作槽22开口的外环8,外环8轴线与驱动环83轴线重合,外环8内侧与操作杆81远离驱动环83的一端固定连接。外环8、操作杆81以及驱动环83共同贯穿有注料孔811,注料孔811两端分别连通外环8的外侧和驱动环83的内侧。注料孔811在驱动环83内侧处的开口位于两个驱动齿831之间,橡胶环6开设有若干连接孔62,连接孔62连通橡胶环6内侧和橡胶环6外侧。若干连接孔62与若干橡胶块61间隔设置。橡胶环6内侧壁开有第三环形槽64,第三环形槽64环绕橡胶环6内侧壁,且与若干连接孔62连通。当若干驱动齿831的齿顶部与若干橡胶块61朝向驱动环83的一端一一抵紧时,注料孔811与其中一个连接孔62正对。在步骤七中,对防水套件2进行防水密封处理时,安装人员通过往注料孔811内注入树脂,树脂通过连接孔62进入第三环形槽64内,待树脂固化后,树脂在第三环形槽64内形成第三重密封层,进一步提高了该防水套件2的防水性能。橡胶块61的宽度小于橡胶环6的宽度,从而利于在驱动齿831抵紧橡胶块61时,树脂可从橡胶块61两侧流动,从而便于树脂填满整个防水套件2的内部空隙,进而提高该防水套件2的防水性能。4 and 5 , a second annular groove 23 is formed on the outer peripheral surface of the
参照图4和图5,防水套件2外周面开有与第一环形槽21相通的连接槽24,连接槽24沿防水套件2外周面切线方向延展,连接槽24与操作槽22正对设置。驱动环83外侧固定有伸入连接槽24内且与驱动环83外侧固定连接的连接杆82,连接杆82长度方向延长线与操作杆81的长度方向延长线重合且交汇于驱动环83轴线一点,外环8、连接杆82以及驱动环83共同贯穿有气孔821,气孔821两端分别连通外环8的外侧和驱动环83的内侧。有利于在往注料孔811注入树脂时,防水套件2内的压强与大气压强保持平衡,有利于提高树脂的注料速率。外环8安装有两个橡胶塞7。两个橡胶塞7分别用于堵住注料孔811和气孔821的开口,待注料完毕后,通过橡胶塞7堵住注料孔811和气孔821,降低了树脂外泄的概率,有利于树脂的固化成型。4 and 5, the outer peripheral surface of the
以上均为本申请的较佳实施例,并非依此限制本申请的保护范围,故:凡依本申请的结构、形状、原理所做的等效变化,均应涵盖于本申请的保护范围之内。The above are all preferred embodiments of the present application, and are not intended to limit the protection scope of the present application. Therefore: all equivalent changes made according to the structure, shape and principle of the present application should be covered within the scope of the present application. Inside.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202011321584.4A CN112510466B (en) | 2020-11-23 | 2020-11-23 | A kind of cable quick connection construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202011321584.4A CN112510466B (en) | 2020-11-23 | 2020-11-23 | A kind of cable quick connection construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN112510466A CN112510466A (en) | 2021-03-16 |
| CN112510466B true CN112510466B (en) | 2022-05-17 |
Family
ID=74959520
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202011321584.4A Active CN112510466B (en) | 2020-11-23 | 2020-11-23 | A kind of cable quick connection construction method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN112510466B (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN114512850B (en) * | 2022-03-22 | 2025-04-25 | 广东坚宝电缆有限公司 | A quick-install cable connector |
| CN115548717A (en) * | 2022-10-08 | 2022-12-30 | 国家电网有限公司 | A new type of integrated cable terminal transfer clamp |
| CN118137213B (en) * | 2024-05-08 | 2024-07-05 | 常州市薛巷电讯股份有限公司 | Waterproof cable connector |
Family Cites Families (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US5281761A (en) * | 1992-02-25 | 1994-01-25 | Burndy Corporation | Grounding pipe/water pipe with compression connectors |
| CN201725966U (en) * | 2010-07-05 | 2011-01-26 | 深圳市联益电子有限公司 | Waterproof connector |
| CN108879119B (en) * | 2018-08-03 | 2024-03-26 | 广东电网有限责任公司广州供电局 | Cable connection assembly and cable connection method |
| CN209488151U (en) * | 2019-03-18 | 2019-10-11 | 青岛缆海工业科技集团股份有限公司 | A kind of novel cable with defencive function |
-
2020
- 2020-11-23 CN CN202011321584.4A patent/CN112510466B/en active Active
Also Published As
| Publication number | Publication date |
|---|---|
| CN112510466A (en) | 2021-03-16 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN112510466B (en) | A kind of cable quick connection construction method | |
| US5382756A (en) | Encapsulation closure for cables | |
| CN105185482B (en) | A kind of preparation method with the outer cable by structure of waterproof | |
| CN111029050A (en) | Preparation method of water-blocking cable | |
| ES2924360T3 (en) | Thread joint and manufacturing procedure thereof | |
| CN114824984A (en) | High-temperature-resistant cable joint sealing process | |
| CN210927059U (en) | Core wire sealing structure for submersible motor | |
| AU2020334655B2 (en) | Cable | |
| CN205828708U (en) | A kind of fast cable connector | |
| CN212411647U (en) | Special power supply cable for underwater weak current equipment | |
| CN206331809U (en) | A kind of anti-shark formula submarine cable | |
| CN221708433U (en) | An underground cable | |
| CN106158115A (en) | One is pressed crosslinked polyethylene water repellent electric cable | |
| CN216016421U (en) | Quick plumbous big envelope of marine wind power main sea cable | |
| CN204614491U (en) | Fully dry high resistance water communication cable | |
| CN219041368U (en) | Water pump cable inner end prevents sealing structure that intakes | |
| CN217427656U (en) | Water-blocking intermediate joint | |
| CN215451011U (en) | Waterproofing type power cable | |
| CN112071488A (en) | A waterproof cable of environmental protection for scrubbing equipment under water | |
| CN106877557A (en) | The waterproof seal of diving generator cable | |
| CN220122604U (en) | Sealing device for cable and cable prepared by same | |
| CN203351271U (en) | A waterproof ethylene propylene rubber insulating power cable | |
| CN223401413U (en) | Marine cable with good water-blocking and tensile effects | |
| CN203085243U (en) | A waterproof anti-ultraviolet environment-friendly cable | |
| CN220340955U (en) | Water-blocking type low-voltage power cable |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| CB02 | Change of applicant information |
Address after: 510032 room 206, No. 551-1, Qingnian Road, Guangzhou Economic and Technological Development Zone, Guangzhou City, Guangdong Province Applicant after: Guangdong Yili Jian'an Engineering Co.,Ltd. Address before: 510032 room 206, No. 551-1, Qingnian Road, Guangzhou Economic and Technological Development Zone, Guangzhou City, Guangdong Province Applicant before: Guangzhou Yili construction Electromechanical Engineering Co.,Ltd. |
|
| CB02 | Change of applicant information | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of invention: A rapid cable splicing construction method Granted publication date: 20220517 Pledgee: Agricultural Bank of China Limited Guangzhou Development Zone Branch Pledgor: Guangdong Yili Jian'an Engineering Co.,Ltd. Registration number: Y2025980020294 |
|
| PE01 | Entry into force of the registration of the contract for pledge of patent right |