CN112444480B - Freeze-thaw and dry-wet alternation test device and use method thereof - Google Patents

Freeze-thaw and dry-wet alternation test device and use method thereof Download PDF

Info

Publication number
CN112444480B
CN112444480B CN202011101151.8A CN202011101151A CN112444480B CN 112444480 B CN112444480 B CN 112444480B CN 202011101151 A CN202011101151 A CN 202011101151A CN 112444480 B CN112444480 B CN 112444480B
Authority
CN
China
Prior art keywords
water
test
box
shell
electric
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202011101151.8A
Other languages
Chinese (zh)
Other versions
CN112444480A (en
Inventor
周军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Jinhuan Experimental Equipment Co ltd
Original Assignee
Jiangsu Jinhuan Experimental Equipment Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Jinhuan Experimental Equipment Co ltd filed Critical Jiangsu Jinhuan Experimental Equipment Co ltd
Priority to CN202011101151.8A priority Critical patent/CN112444480B/en
Publication of CN112444480A publication Critical patent/CN112444480A/en
Application granted granted Critical
Publication of CN112444480B publication Critical patent/CN112444480B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N17/00Investigating resistance of materials to the weather, to corrosion, or to light
    • G01N17/002Test chambers

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Ecology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Environmental Sciences (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Analytical Chemistry (AREA)
  • Biochemistry (AREA)
  • General Health & Medical Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • Immunology (AREA)
  • Pathology (AREA)
  • Testing Resistance To Weather, Investigating Materials By Mechanical Methods (AREA)

Abstract

The invention discloses a freeze-thaw and dry-wet alternation test device and a using method thereof, relates to the technical field of freeze-thaw and dry-wet alternation tests, and aims to solve the problem that the volume of the existing freeze-thaw and dry-wet alternation test device is overlarge due to the fact that an internal heat exchange device of the existing freeze-thaw and dry-wet alternation test device occupies a large space. The air exchange device comprises a shell, and is characterized in that a ventilation box is arranged at the front end of the shell, a test box is arranged at the upper end of the ventilation box, bases are arranged at four corners of the lower end of the shell, a control panel is arranged on one side of the test box, a transparent observation window is arranged at the front end of the test box, a door plate handle is arranged on one side of the transparent observation window, a ventilation panel is arranged at the front end of the ventilation box, exhaust grooves are arranged on two sides of the ventilation panel, a water outlet is arranged on one side of the shell, an object stage is arranged between the ventilation box and the test box, a test table rotating motor is arranged inside the object stage, and a test table is arranged at the upper end of the test table rotating motor.

Description

Freeze-thaw and dry-wet alternation test device and use method thereof
Technical Field
The invention relates to the technical field of freeze thawing and dry-wet alternation tests, in particular to a freeze thawing and dry-wet alternation test device and a using method thereof.
Background
The freeze-thaw test is a scientific experiment performed by a scientific research institution on a new drug or a new material and aims to test the stability and effectiveness of various indexes of an experimental object. When designing a stability investigation experiment scheme of a medicine, a new medicine research unit usually pays attention to selecting the packaging and storage conditions of the medicine through a series of influence factor experiments, and determines the validity period of the product through a long-term sample retention experiment under standard conditions. But often neglects the adverse effect that some special medicines may have on the quality of the product due to temperature changes during transportation or use. The test box is a general term of products in the environmental test industry, and is used for simulating a natural climate environment in an effective space range, and the test types are as follows: the system comprises a high-low temperature test chamber, a xenon lamp aging test chamber, an ultraviolet aging test chamber, a box-type rain box, antirust grease, a dripping device, a purifying and cleaning storage cabinet, a nitrogen storage cabinet, non-standard products and the like.
However, the existing freeze-thaw and dry-wet alternative test device has the problem of overlarge volume of the device due to large occupied space of an internal heat exchange device; therefore, the existing requirements are not met, and a freeze-thaw and dry-wet alternation test device and a using method thereof are provided.
Disclosure of Invention
The invention aims to provide a freeze-thaw and dry-wet alternation test device and a using method thereof, and aims to solve the problem that the volume of the existing freeze-thaw and dry-wet alternation test device in the background art is too large due to large occupied space of an internal heat exchange device.
In order to achieve the purpose, the invention provides the following technical scheme: a freeze-thaw and dry-wet alternation test device comprises a housing, an air-exchange box is arranged at the front end of the housing and is welded to the housing, a test box is arranged at the upper end of the air-exchange box and is welded to the housing, bases are arranged at the four corners of the lower end of the housing and are welded to the housing, a control panel is arranged at one side of the test box and is welded to the front end of the housing, a transparent viewing window is arranged at the front end of the test box and is welded to the test box, and the test box is welded to the transparent viewing window, a door panel handle is arranged at one side of the transparent viewing window and is welded to the door panel, and is welded to the test box, an air inlet net is arranged at the inner part of the air inlet net and is welded to the air inlet net, an air outlet net is arranged at the two sides of the air inlet net and is welded to the air inlet net, an air outlet groove is arranged at the two sides of the air inlet net and is welded to the air inlet net, an air outlet net is arranged at the inner side of the air-exchange box and is connected to the air-exchange box, a rotating test box is arranged at the inner wall of the test box and is connected to the rotating test box, a spraying motor is arranged at the upper end of the rotating test box and is arranged at the inner wall of the rotating test box, and the rotary spraying device is welded with the scavenging box, an electric heating scavenging pump is arranged in the scavenging box, an air inlet of the electric heating scavenging pump is connected with an air inlet pipe network, scavenging pump fixing frames are arranged at the upper end and the lower end of the electric heating scavenging pump and are in bolted connection with the electric heating scavenging pump, the scavenging pump fixing frames are welded with the scavenging box, an exhaust port of the electric heating scavenging pump is provided with an exhaust pipe, and the exhaust pipe is welded with an exhaust groove.
Preferably, the inside of rotatory sprinkler is provided with the rotation and sprays the casing, the upper end of rotatory casing that sprays is provided with leads to water outer tube, and leads to water outer tube and rotatory casing welded connection that sprays, the inside that leads to water outer tube is provided with automatically controlled inner tube, and automatically controlled inner tube and rotatory casing welded connection that sprays, the lower extreme that the rotatory casing that sprays is provided with leads to water bearing shell, and leads to water bearing shell and rotatory casing welded connection that sprays, the lower extreme that leads to water bearing shell is provided with rotatable shower nozzle, and rotatable shower nozzle and lead to water bearing shell pivot and be connected, the rear end of casing is provided with the electric cabinet, and electric cabinet and automatically controlled inner tube welded connection.
Preferably, a built-in rotating shaft is arranged inside the water passing bearing shell and is connected with the rotatable spray head in a welding mode, a built-in rotating motor is arranged at the upper end of the built-in rotating shaft, and the output end of the built-in rotating motor is in transmission connection with the built-in rotating shaft.
Preferably, a cold and hot pipe is arranged at the upper end of the rotary spraying device, the cold and hot pipe is arranged in the shell, and the cold and hot pipe is connected with the rotary spraying device through a pipeline.
Preferably, the inner wall of the test box is provided with two air exchange pipes, and the two air exchange pipes are respectively connected with the air inlet end flange and the air outlet end flange of the electric heating air exchange pump.
Preferably, one side in the object stage is provided with a drainage floor drain, the drainage floor drain is connected with the object stage in a welding mode and is connected with a drainage outlet pipeline, and the upper end of the drainage floor drain is provided with a floor drain filter screen, and the floor drain filter screen is connected with the drainage floor drain in a welding mode.
Preferably, an electric water tank is arranged on one side inside the shell and is welded to the inner wall of the shell, an electric cold water tank is arranged at the upper end of the electric water tank and is welded to the electric water tank, a three-way water pump is arranged on one side of the electric water tank and is respectively connected with the electric water tank, the electric cold water tank and a cold and hot pipe pipeline.
A use method of a freeze-thaw and alternate dry-wet test device comprises the following steps:
the method comprises the following steps: pulling a door plate handle to open a test box, placing an experimental material in an experimental vessel, closing the test box to start a machine, sucking air from an air inlet net on an air exchange panel by an electric heating scavenging pump, heating the air according to the experimental requirement, finally enabling the air to enter the test box from one scavenging pipe, drying the material, pumping redundant air into an exhaust pipe from another scavenging pipe, and finally exhausting the air from an exhaust groove to balance the air pressure in the test box, simultaneously driving the experimental vessel on the test table to rotate by a test table rotating motor, fully treating the material to the maximum extent, irradiating the tested material by a heating lamp to heat and raise the temperature, completing a melting and drying experiment, and enabling sewage to flow into a drainage floor drain and be exhausted from a drainage outlet;
step two: when the experiment needs to be frozen or humidified, the electric water tank and the electric cold water tank respectively heat and cool an external water source, finally, the cold-hot proportion of water is controlled by the three-way water pump to achieve temperature control, the water meeting the experiment temperature requirement is pumped into the cold-hot pipe and then enters the rotary spraying device, the rotary spraying device sprays water to freeze or humidify the tested material, the water in the cold-hot pipe flows in from the outer water pipe, the electric control inner pipe isolates the water in the outer water pipe, a circuit in the electric control inner pipe is electrically connected with a built-in rotary motor below the electric control inner pipe to prevent the built-in rotary motor from contacting with the water, the water in the outer water pipe passes through the rotary spraying shell and is finally sprayed out from the rotary spray head through the water bearing shell, the built-in rotary motor in the water bearing shell drives the built-in rotary shaft to rotate, the rotary spray head is driven by the rotary built-in rotary shaft to rotate at the lower end of the water bearing shell, so that the rotary spraying function is realized, the freezing or humidifying experiment treatment can be completed, and the sewage can flow in the drain and be discharged from the water outlet.
Compared with the prior art, the invention has the beneficial effects that:
1. according to the invention, through the arrangement of the electric heating air exchange pump, the electric heating air exchange pump sucks air from an air inlet net on the air exchange panel, the air is heated according to the experiment requirement, finally, the air can enter the test box from one air exchange pipe to dry the material, the redundant air can be pumped into the exhaust pipe from the other air exchange pipe and finally exhausted from the exhaust groove, so that the air pressure in the test box is balanced, the air exchange box is overlapped to optimize the pipeline, the occupied volume of the air exchange device is reduced while the maximization of the air exchange port of the device is ensured, and the problem of overlarge volume of the device caused by the large occupied space of an internal heat exchange device of the existing freeze thawing and dry-wet alternation test device is solved.
2. Through the setting of electric water tank and electric cold water tank, electric water tank and electric cold water tank heat respectively and cool down the processing to external water source, and the cold and hot proportion of controlling water reaches the processing of accuse temperature by the tee bend water pump at last, reaches the required temperature of experimental temperature.
3. Through the setting of the rotary spraying device, the rotary spraying device sprays water to freeze or humidify a tested material, water in the cold and hot pipes flows in from the water-through outer pipe, the electric control inner pipe isolates the water of the water-through outer pipe, a circuit in the electric control inner pipe is electrically connected with a built-in rotating motor below the electric control inner pipe, the built-in rotating motor is prevented from contacting with the water, the water in the water-through outer pipe is sprayed out of the rotatable spray head through rotation, the water-through bearing shell is sprayed out of the rotatable spray head finally, the built-in rotating motor inside the water-through bearing shell drives the built-in rotating shaft to rotate, the rotating built-in rotating shaft drives the rotatable spray head to rotate at the lower end of the water-through bearing shell, so that the rotary spraying function is realized, freezing or humidifying experimental treatment can be completed, and sewage can flow into the drainage floor drain and is discharged from the drainage outlet.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic diagram of the internal side view structure of the present invention;
FIG. 3 is a schematic view of a rotary spraying apparatus according to the present invention;
FIG. 4 is a schematic view of the structure of the drainage floor drain of the present invention;
FIG. 5 is an enlarged view of a portion of the invention at A;
in the figure: 1. a housing; 2. a ventilation box; 3. a test chamber; 4. a base; 5. a control panel; 6. a transparent viewing window; 7. a door panel handle; 8. a ventilation panel; 9. an air intake network; 10. an exhaust duct; 11. a water outlet; 12. an object stage; 13. a test bed rotating motor; 14. a test bed; 15. a laboratory vessel; 16. a heating lamp; 17. rotating the spraying device; 18. a cold and hot pipe; 19. a floor drain for draining water; 20. an electric heat scavenging pump; 21. a scavenging pump fixing frame; 22. a ventilation tube; 23. an electric cabinet; 24. rotating the spray housing; 25. a water-through outer pipe; 26. an electric control inner pipe; 27. a water bearing shell; 28. a rotating shaft is arranged inside; 29. a rotatable spray head; 30. a built-in rotating electrical machine; 31. a floor drain filter screen; 32. an electric water tank; 33. an electric cooling water tank; 34. a three-way water pump; 35. and (4) exhausting the gas.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
Referring to fig. 1-5, an embodiment of the present invention is shown: a freeze-thaw and dry-wet alternation test device comprises a shell 1, an air exchange box 2 is arranged at the front end of the shell 1, the air exchange box 2 is connected with the shell 1 in a welding mode, a test box 3 is arranged at the upper end of the air exchange box 2, the test box 3 is connected with the shell 1 in a welding mode, bases 4 are arranged at four corners of the lower end of the shell 1, the bases 4 are connected with the shell 1 in a welding mode, a control panel 5 is arranged at one side of the test box 3, the control panel 5 is connected with the front end of the shell 1 in a welding mode, a transparent observation window 6 is arranged at the front end of the test box 3, the transparent observation window 6 is connected with the test box 3 in a welding mode, an air inlet net 9 is arranged inside the air exchange panel 8, the air inlet net 9 is connected with the air exchange panel 8 in a welding mode, two sides of the air inlet net 8 are provided with air exchange grooves 10, the air exchange grooves 10 are connected with the air exchange box 2, a rotating test table 12 is arranged at the upper end of the shell 2, a rotating test table 12 is arranged at the upper end of the rotating test box 2, a rotating test table 13, a rotating test table 12 is arranged above the rotating test box 12, and a rotating test table 12 is arranged on the shell 2, and a rotating test table 12 is arranged on the rotating test table 12, the heating lamp 16 is welded with the inner wall of the test box 3, the four corners of the inner wall of the upper end of the test box 3 are provided with rotary spraying devices 17, the rotary spraying devices 17 are welded with the air exchange box 2, the electric heating air exchange pump 20 is arranged inside the air exchange box 2, the air inlet of the electric heating air exchange pump 20 is connected with the air inlet net 9 through a pipeline, air exchange pump fixing frames 21 are arranged at the upper end and the lower end of the electric heating air exchange pump 20, the air exchange pump fixing frames 21 are connected with the electric heating air exchange pump 20 through bolts, the air exchange pump fixing frames 21 are welded with the air exchange box 2, the air outlet of the electric heating air exchange pump 20 is provided with an exhaust pipe 35, the exhaust pipe 35 is welded with the exhaust groove 10, the overlapped air exchange box 2 and the electric heating air exchange pump 20 optimize the pipeline, the occupied volume of the air exchange device is reduced while the maximization of the air exchange port is guaranteed, and the problem that the occupied space of the existing freeze thawing and dry-wet alternation test device is large in size is solved.
Further, the inside of rotatory sprinkler 17 is provided with rotatory casing 24 that sprays, the upper end of rotatory casing 24 that sprays is provided with water outer tube 25, and water outer tube 25 and rotatory casing 24 welded connection that sprays, the inside of water outer tube 25 is provided with automatically controlled inner tube 26, and automatically controlled inner tube 26 and rotatory casing 24 welded connection that sprays, the lower extreme of rotatory casing 24 that sprays is provided with water bearing shell 27, and water bearing shell 27 and rotatory casing 24 welded connection that sprays, the lower extreme of water bearing shell 27 is provided with rotatable shower nozzle 29, and rotatable shower nozzle 29 is connected with water bearing shell 27 pivot, the rear end of casing 1 is provided with electric cabinet 23, and electric cabinet 23 and automatically controlled inner tube 26 welded connection, rotatory sprinkler 17 makes the direct rotatory measured material that sprays of water after the regulation, make the temperature obvious to material control.
Further, a built-in rotating shaft 28 is arranged inside the water passing bearing shell 27, the built-in rotating shaft 28 is connected with the rotatable spray head 29 in a welding mode, a built-in rotating motor 30 is arranged at the upper end of the built-in rotating shaft 28, the output end of the built-in rotating motor 30 is connected with the built-in rotating shaft 28 in a transmission mode, the built-in rotating shaft 28 is connected with the rotatable spray head 29, the built-in rotating shaft 28 drives the rotatable spray head 29 to rotate, the function of rotating and uniformly spraying is achieved, and materials are heated uniformly.
Further, the upper end of the rotary spraying device 17 is provided with a cold and hot pipe 18, the cold and hot pipe 18 is arranged inside the shell 1, the cold and hot pipe 18 is connected with the rotary spraying device 17 through a pipeline, and the cold and hot pipe 18 is separated from the electric control inner pipe 26, so that water and electricity are separated, and the volume occupation of the device is reduced.
Further, the inner wall of the test box 3 is provided with two air exchanging pipes 22, the two air exchanging pipes 22 are respectively connected with the air inlet end and the air outlet end of the electric heating air exchanging pump 20 through flanges, and the air exchanging pipes 22 are used for heating, drying and air exchanging ports.
Further, a drainage floor drain 19 is arranged on one side inside the objective table 12, the drainage floor drain 19 is connected with the objective table 12 in a welded mode, the drainage floor drain 19 is connected with the water outlet 11 through a pipeline, a floor drain filter screen 31 is arranged at the upper end of the drainage floor drain 19, the floor drain filter screen 31 is connected with the drainage floor drain 19 in a welded mode, the drainage floor drain 19 effectively removes accumulated water and sewage, and the drying experiment is accelerated.
Furthermore, an electric water tank 32 is arranged on one side inside the shell 1, the electric water tank 32 is welded with the inner wall of the shell 1, an electric cold water tank 33 is arranged at the upper end of the electric water tank 32, the electric cold water tank 33 is welded with the electric water tank 32, a three-way water pump 34 is arranged on one side of the electric water tank 32, the three-way water pump 34 is respectively connected with the electric water tank 32, the electric cold water tank 33 and the cold and hot pipes 18 through pipelines, and the electric water tank 32 and the electric cold water tank 33 are matched with the three-way water pump 34 to achieve the function of adjusting the water temperature.
The use method of the freeze-thaw alternating with dry-wet test device based on the claim comprises the following steps:
the method comprises the following steps: firstly, pulling a door plate handle 7 to open a test box 3, placing experimental materials in an experimental vessel 15, closing the test box 3 to start a machine, then sucking air from an air inlet net 9 on a ventilation panel 8 by an electric heating scavenging pump 20, heating the air according to the experimental requirements, finally enabling the air to enter the test box 3 from one scavenging pipe 22, drying the materials, pumping the redundant air into an exhaust pipe 35 from the other scavenging pipe 22, and finally exhausting the air from an exhaust groove 10, so as to balance the air pressure in the test box 3, meanwhile, driving the experimental vessel 15 on a test bed 14 to rotate by a test bed rotating motor 13, fully treating the materials to the maximum extent, irradiating the tested materials by a heating lamp 16 to heat and raise the temperature, completing a melting and drying experiment, and enabling sewage to flow into a drainage floor drain 19 and be exhausted from a drainage outlet 11;
step two: when the experiment needs to be performed with freezing or humidifying treatment, the electric water tank 32 and the electric cold water tank 33 respectively perform heating and cooling treatment on an external water source, finally, the three-way water pump 34 controls the cold-hot proportion of water to achieve temperature control treatment, water meeting the experiment temperature requirement is pumped into the cold-hot pipe 18 and then enters the rotary spraying device 17, the rotary spraying device 17 sprays water to perform freezing or humidifying treatment on the measured material, the water in the cold-hot pipe 18 flows in from the water through outer pipe 25, the electric control inner pipe 26 isolates the water in the water through outer pipe 25, a circuit in the electric control inner pipe 26 is electrically connected with the built-in rotary motor 30 below the electric control inner pipe to prevent the built-in rotary motor 30 from contacting with the water, the water in the water through outer pipe 25 passes through the rotary spraying shell 24 and the water through bearing shell 27 and finally is sprayed out from the rotary spray nozzle 29, the built-in rotary motor 30 in the water through bearing shell 27 drives the built-in the rotary shaft 28 to rotate, the rotary nozzle 29 is driven by the rotary built-in the rotary shaft 28 to rotate at the lower end of the water through bearing shell 27, thereby realizing the rotary spraying function, the rotary spraying function can be performed with freezing or humidifying treatment, and the sewage can flow into the drainage outlet 19 from the humidifying drainage outlet 11.
It will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, and that the present invention may be embodied in other specific forms without departing from the spirit or essential attributes thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (8)

1. A freeze-thaw and dry-wet alternation test device comprises a shell (1), and is characterized in that: the front end of the shell (1) is provided with a ventilation box (2), the ventilation box (2) is connected with the shell (1) in a welding mode, the upper end of the ventilation box (2) is provided with a test box (3), the test box (3) is connected with the shell (1) in a welding mode, four corners of the lower end of the shell (1) are provided with bases (4), the bases (4) are connected with the shell (1) in a welding mode, one side of the test box (3) is provided with a control panel (5), the control panel (5) is connected with the front end of the shell (1) in a welding mode, the front end of the test box (3) is provided with a transparent observation window (6), the transparent observation window (6) is connected with the test box (3) in a welding mode, the test box (3) is connected with the transparent observation window (6) in a welding mode, one side of the transparent observation window (6) is provided with a door plate handle (7), the door plate handle (7) is connected with the test box (3) in a welding mode, the front end of the ventilation box (2) is provided with a ventilation panel (8), the ventilation panel (8) is connected with the ventilation box (2), an air intake net (9) is arranged on two sides of the ventilation net (9), and three air intake net (9) are provided with an air intake net (8), the exhaust groove (10) is connected with the ventilation box (2) in a welding mode, a water outlet (11) is arranged on one side of the shell (1), the water outlet (11) is connected with the shell (1) in a flange mode, an object stage (12) is arranged between the ventilation box (2) and the test box (3), the object stage (12) is connected with the ventilation box (2) and the test box (3) in a welding mode, a test table rotating motor (13) is arranged inside the object stage (12), the test table rotating motor (13) is connected with the object stage (12) in a welding mode, a test table (14) is arranged at the upper end of the test table rotating motor (13), the test table (14) is connected with the object stage (12) in a welding mode, an experimental vessel (15) is arranged at the upper end of the test table (14), the experimental vessel (15) is connected with the output end of the test table rotating motor (13) in a transmission mode, a heating lamp (16) is arranged above the experimental vessel (15), the heating lamp (16) is connected with the inner wall of the ventilation box (3) in a welding mode, four corners of the upper end of the experimental vessel (3) are provided with a spraying device (17), a spraying device (17) is connected with the ventilation box (2), and a spraying device (20) is connected with the ventilation box (2), the upper end and the lower end of the electric heating scavenging pump (20) are provided with scavenging pump fixing frames (21), the scavenging pump fixing frames (21) are in bolt connection with the electric heating scavenging pump (20), the scavenging pump fixing frames (21) are in welded connection with the scavenging box (2), an exhaust port of the electric heating scavenging pump (20) is provided with an exhaust pipe (35), and the exhaust pipe (35) is in welded connection with the exhaust groove (10).
2. A freeze-thaw alternating with dry-wet test apparatus according to claim 1, wherein: the inside of rotatory sprinkler (17) is provided with rotatory casing (24) that sprays, the upper end that rotatory casing (24) sprayed is provided with logical water outer tube (25), and leads to water outer tube (25) and rotatory casing (24) welded connection that sprays, the inside that leads to water outer tube (25) is provided with automatically controlled inner tube (26), and automatically controlled inner tube (26) and rotatory casing (24) welded connection that sprays, the lower extreme that rotatory casing (24) sprayed is provided with leads to water bearing housing (27), and leads to water bearing housing (27) and rotatory casing (24) welded connection that sprays, the lower extreme that leads to water bearing housing (27) is provided with rotatable sprinkler (29), and rotatable sprinkler (29) and lead to water bearing housing (27) pivot connection, the rear end of casing (1) is provided with electric cabinet (23), and electric cabinet (23) and automatically controlled inner tube (26) welded connection.
3. A freeze-thaw alternating with dry-wet test apparatus according to claim 2, wherein: the water-through bearing comprises a water-through bearing shell (27), wherein a built-in rotating shaft (28) is arranged in the water-through bearing shell (27), the built-in rotating shaft (28) is connected with a rotatable spray head (29) in a welding mode, a built-in rotating motor (30) is arranged at the upper end of the built-in rotating shaft (28), and the output end of the built-in rotating motor (30) is in transmission connection with the built-in rotating shaft (28).
4. A freeze-thaw alternating with dry-wet test apparatus according to claim 1, wherein: the upper end of the rotary spraying device (17) is provided with a cold and hot pipe (18), the cold and hot pipe (18) is arranged in the shell (1), and the cold and hot pipe (18) is connected with the rotary spraying device (17) through a pipeline.
5. A freeze-thaw alternating with dry-wet test apparatus according to claim 1, wherein: the inner wall of the test box (3) is provided with two air exchange pipes (22), and the two air exchange pipes (22) are connected with the air inlet end and the air outlet end of the electric heating scavenging pump (20) through flanges respectively.
6. The alternate freeze-thaw and dry-wet test apparatus according to claim 1, wherein: one side in the object stage (12) is provided with a drainage floor drain (19), the drainage floor drain (19) is connected with the object stage (12) in a welding mode, the drainage floor drain (19) is connected with the water outlet (11) through a pipeline, a floor drain filter screen (31) is arranged at the upper end of the drainage floor drain (19), and the floor drain filter screen (31) is connected with the drainage floor drain (19) in a welding mode.
7. The alternate freeze-thaw and dry-wet test apparatus according to claim 1, wherein: the utility model discloses a solar water heater, including casing (1), inside one side of casing (1) is provided with electric water tank (32), and electric water tank (32) and casing (1) inner wall welded connection, the upper end of electric water tank (32) is provided with electric cold water tank (33), and electric cold water tank (33) and electric water tank (32) welded connection, one side of electric water tank (32) is provided with three-way water pump (34), and three-way water pump (34) respectively with electric water tank (32), electric cold water tank (33), cold and hot pipe (18) pipe connection.
8. The use method of the freeze-thaw alternating with dry-wet test device according to any one of claims 1 to 7, comprising the steps of:
the method comprises the following steps: firstly pulling a door plate handle (7) to open a test box (3), placing a test material in a test vessel (15), closing the test box (3) to start a machine, then sucking air from an air inlet net (9) on a ventilation panel (8) by an electric heating ventilation pump (20), heating the air according to the test requirement, finally, allowing the air to enter the test box (3) from one ventilation pipe (22), drying the material, pumping the redundant air into an exhaust pipe (35) from the other ventilation pipe (22), and finally discharging the redundant air from an exhaust groove (10) so as to balance the internal air pressure of the test box (3), simultaneously driving the test vessel (15) on a test table (14) to rotate by a test table rotating motor (13), fully treating the material to the maximum extent, irradiating the tested material by a heating lamp (16) to heat and raise the temperature, completing a melting and drying test, and allowing sewage to flow into a drain (19) and be discharged from a water outlet (11);
step two: when the experiment needs to be performed with freezing or humidifying treatment, the electric water tank (32) and the electric cold water tank (33) respectively perform heating and cooling treatment on an external water source, finally, the three-way water pump (34) is used for controlling the cold-hot proportion of water to achieve temperature control treatment, the water meeting the experiment temperature requirement is pumped into the cold-hot pipe (18) and then enters the rotary spraying device (17), the rotary spraying device (17) sprays water to perform freezing or humidifying treatment on the material to be detected, the water in the cold-hot pipe (18) flows in from the water through outer pipe (25), the electric control inner pipe (26) isolates the water in the water through outer pipe (25), a circuit in the electric control inner pipe (26) is electrically connected with the built-in rotary motor (30) below, the built-in rotary motor (30) is prevented from being in contact with the water, the water in the water through outer pipe (25) passes through the rotary spraying shell (24), the water through bearing shell (27) is finally sprayed out from the rotary spray nozzle (29), the built-in rotary motor (28) in the water through bearing shell (27) drives the built-in rotary spraying shell (28) to rotate, the rotary spray nozzle (29) to discharge the rotary bearing shell (29), and the rotary spraying function of discharging and the rotary bearing (29) is realized, the rotary spraying of the experiment, the rotary bearing, the sewage discharge outlet (19) to discharge function of the rotary spraying and the rotary bearing (11) can be discharged, so that the sewage can be discharged from the rotary bearing, the experiment can be discharged, and the sewage can be discharged, and the experiment can be discharged from the rotary bearing, so that the sewage can be discharged.
CN202011101151.8A 2020-10-15 2020-10-15 Freeze-thaw and dry-wet alternation test device and use method thereof Active CN112444480B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011101151.8A CN112444480B (en) 2020-10-15 2020-10-15 Freeze-thaw and dry-wet alternation test device and use method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011101151.8A CN112444480B (en) 2020-10-15 2020-10-15 Freeze-thaw and dry-wet alternation test device and use method thereof

Publications (2)

Publication Number Publication Date
CN112444480A CN112444480A (en) 2021-03-05
CN112444480B true CN112444480B (en) 2022-11-22

Family

ID=74735997

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011101151.8A Active CN112444480B (en) 2020-10-15 2020-10-15 Freeze-thaw and dry-wet alternation test device and use method thereof

Country Status (1)

Country Link
CN (1) CN112444480B (en)

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203869997U (en) * 2014-05-15 2014-10-08 上海林频仪器股份有限公司 High and low temperature wet and hot compound salt haze box
CN203899617U (en) * 2014-05-29 2014-10-29 上海秦沛环保科技有限公司 VOC and formaldehyde release amount environment simulation test box
CN205049457U (en) * 2015-08-03 2016-02-24 广州市汉迪环境试验设备有限公司 Xenon -lamp weather resistance test chamber
CN206897416U (en) * 2017-04-28 2018-01-19 武汉东湖学院 A kind of Multifunctional laboratory chamber
CN207894855U (en) * 2018-01-12 2018-09-21 上海和晟仪器科技有限公司 A kind of weather-proof cold and hot adjusting chamber of new energy battery
CN110542643B (en) * 2018-06-06 2021-11-30 中昊清远(北京)科技有限公司 Corrosion and aging test equipment for simulating marine multi-zone environment

Also Published As

Publication number Publication date
CN112444480A (en) 2021-03-05

Similar Documents

Publication Publication Date Title
CN106839135A (en) Air conditioner room unit, air-conditioner outdoor unit and air-conditioner
CN112444480B (en) Freeze-thaw and dry-wet alternation test device and use method thereof
CN217777849U (en) Nylon humidifying and toughening treatment equipment
CN209689336U (en) A kind of large-scale vertical vacuum oven
CN106287996B (en) Mobile air conditioner with air purification device
CN210070384U (en) Square vacuum drying machine
CN110711144B (en) Fermentation and drying integrated equipment for traditional Chinese medicine processing and use method thereof
CN113230441A (en) Disinfecting equipment based on fuzzy control
CN209623189U (en) A kind of freezer Parallel sets with Waste Heat Recovery
CN215124039U (en) Quick thawing device for food freezing
CN208475639U (en) A kind of intelligent air energy heat pump
CN207922444U (en) A kind of energy-saving all-fresh air air-conditioning device
CN214690792U (en) Jar is deposited to konjaku convenient to inside drying
CN206531356U (en) A kind of low temperature and high/low temperature catalyst drying unit
CN213119914U (en) Anticorrosive mould proof woodwork constant temperature drying equipment
CN215637086U (en) Novel low-pressure mixed superconducting gas heat pump steam unit
CN220779052U (en) Temperature detection control device for rotary evaporator
CN216114317U (en) Heating and ventilation energy-saving equipment for building
CN213766651U (en) Water-cooling circulation equipment for plastic particle production
CN216114378U (en) Heat energy recovery device for energy-saving reconstruction project of central air conditioner
CN114440596B (en) Drying method and equipment suitable for citrus grandis
CN221147013U (en) Baking and aroma-improving equipment for uniformly heating tribute eyebrow white tea
CN221279817U (en) Air conditioner filter screen slope drying equipment
CN209991684U (en) Heated air circulation oven for medicine production
CN215694113U (en) Test box wind circulating device for corrosive gas

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant