CN112012790A - Groundwater seepage control method for water-rich soft plastic loess tunnel based on drainage of dewatering well - Google Patents

Groundwater seepage control method for water-rich soft plastic loess tunnel based on drainage of dewatering well Download PDF

Info

Publication number
CN112012790A
CN112012790A CN202010911266.7A CN202010911266A CN112012790A CN 112012790 A CN112012790 A CN 112012790A CN 202010911266 A CN202010911266 A CN 202010911266A CN 112012790 A CN112012790 A CN 112012790A
Authority
CN
China
Prior art keywords
water
well
dewatering
soft plastic
dewatering well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010911266.7A
Other languages
Chinese (zh)
Inventor
夏万云
张晓宇
毕焕军
曹峰
周泉
梁树文
王栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Survey and Design Institute Group Ltd
Original Assignee
China Railway First Survey and Design Institute Group Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Survey and Design Institute Group Ltd filed Critical China Railway First Survey and Design Institute Group Ltd
Priority to CN202010911266.7A priority Critical patent/CN112012790A/en
Publication of CN112012790A publication Critical patent/CN112012790A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D24/00Filters comprising loose filtering material, i.e. filtering material without any binder between the individual particles or fibres thereof
    • B01D24/02Filters comprising loose filtering material, i.e. filtering material without any binder between the individual particles or fibres thereof with the filter bed stationary during the filtration
    • B01D24/10Filters comprising loose filtering material, i.e. filtering material without any binder between the individual particles or fibres thereof with the filter bed stationary during the filtration the filtering material being held in a closed container
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明涉及基于降水井抽排的富水软塑黄土隧道地下水渗流控制方法,方法为:于富水软塑黄土隧道两侧地表成列布置降水井;降水井施做完成后进行洗井;通过降水井定期抽水作业,降低土层含水率,达到控制富水软塑黄土隧道地下水渗流的目的。本方法解决了地下水渗流严重影响富水黄土隧道施工的难题,确定了地表降水井布置过程的关键参数,通过地表降水,减少了富水软塑黄土隧道的洞内地下水渗流量,降低了黄土含水率,确保了黄土隧道正常施工,达到了安全高效施工的目的。

Figure 202010911266

The invention relates to a method for controlling groundwater seepage in a water-rich soft-plastic loess tunnel based on the pumping and draining of a water-rich soft-plastic loess tunnel. The dewatering well is regularly pumped to reduce the moisture content of the soil layer and achieve the purpose of controlling the groundwater seepage in the water-rich soft plastic loess tunnel. This method solves the problem that groundwater seepage seriously affects the construction of water-rich loess tunnels, and determines the key parameters of the surface dewatering well layout process. It ensures the normal construction of the loess tunnel and achieves the purpose of safe and efficient construction.

Figure 202010911266

Description

基于降水井抽排的富水软塑黄土隧道地下水渗流控制方法Groundwater seepage control method for water-rich soft plastic loess tunnel based on drainage well

技术领域technical field

本发明涉及隧道地下水渗流控制技术领域,具体涉及一种基于降水井抽排的富水软塑黄土隧道地下水渗流控制方法。The invention relates to the technical field of groundwater seepage control in tunnels, in particular to a water-rich soft plastic loess tunnel groundwater seepage control method based on pumping and draining of dewatering wells.

背景技术Background technique

目前,富水软塑黄土隧道施工存在以下问题:At present, the following problems exist in the construction of water-rich soft plastic loess tunnels:

1、隧道长大段落位于地下水位以下的工况中,受软塑黄土及地下水的影响,隧道在施工中会出现渗涌水、隧底软化、掌子面滑塌失稳等问题,严重影响施工安全与进度。1. In the working conditions where the long section of the tunnel is below the groundwater level, due to the influence of soft plastic loess and groundwater, problems such as seepage of water, softening of the tunnel bottom, and collapse and instability of the tunnel face will occur during the construction of the tunnel, which will seriously affect the construction. Safety and progress.

2、洞内措施施工干扰大,难以确保施工进度及安全。2. The measures in the cave have great construction interference, and it is difficult to ensure the construction progress and safety.

3、地表降水具有黄土含水层厚度大、渗透性相对较差、预降水时间长、降深大的特点。3. Surface precipitation has the characteristics of thick loess aquifer, relatively poor permeability, long pre-precipitation time and large drawdown.

发明内容SUMMARY OF THE INVENTION

本发明的目的是提供一种基于降水井抽排的富水软塑黄土隧道地下水渗流控制方法,解决了地下水渗流严重影响富水黄土隧道施工的难题,确定了地表降水井布置过程的关键参数,通过地表降水,减少了富水软塑黄土隧道的洞内地下水渗流量,降低了黄土含水率,确保了黄土隧道正常施工,达到了安全高效施工的目的。The purpose of the present invention is to provide a water-rich soft plastic loess tunnel groundwater seepage control method based on dewatering well pumping and drainage, which solves the problem that groundwater seepage seriously affects the water-rich loess tunnel construction, and determines the key parameters of the surface dewatering well arrangement process, Through surface precipitation, the groundwater seepage flow in the water-rich soft plastic loess tunnel is reduced, the moisture content of the loess is reduced, the normal construction of the loess tunnel is ensured, and the purpose of safe and efficient construction is achieved.

本发明所采用的技术方案为:The technical scheme adopted in the present invention is:

基于降水井抽排的富水软塑黄土隧道地下水渗流控制方法,其特征在于:A method for controlling groundwater seepage in a water-rich soft plastic loess tunnel based on pumping and draining of a dewatering well, which is characterized by:

所述方法包括以下步骤:The method includes the following steps:

S1:于富水软塑黄土隧道两侧地表成列布置降水井;S1: Dewatering wells are arranged in rows on both sides of the water-rich soft plastic loess tunnel;

S2:降水井施做完成后进行洗井;S2: Clean the well after the dewatering well is completed;

S3:通过降水井定期抽水作业,降低土层含水率,达到控制富水软塑黄土隧道地下水渗流的目的。S3: Through the regular pumping operation of the dewatering well, the moisture content of the soil layer is reduced, and the purpose of controlling the groundwater seepage of the water-rich soft-plastic loess tunnel is achieved.

降水井施做过程为:The process of dewatering well construction is as follows:

钻孔采用大孔径无岩芯全面钻进,钻孔孔径600mm,钻成井直径325mm,孔深达到设计深度后,依次下入根据排水方案确定的井管;地下水位以上采用粘性土回填固井;井管采用Ф325*6钢卷管,井管连接方式为焊接。The borehole is fully drilled with large aperture without core, the borehole diameter is 600mm, and the diameter of the drilled well is 325mm. After the hole depth reaches the design depth, the well pipe determined according to the drainage plan is run in sequence; above the groundwater level, backfill cementing with clay; The well pipe adopts Ф325*6 steel coiled pipe, and the well pipe connection method is welding.

井管内设置滤水管,为Ф325*6桥式滤水管,滤水管按照预定位置投入准备好的规格砾料,直径2~5mm,在井孔与滤水管之间填砾,填砾厚度200~300mm,投砾方法采用静水投砾法,在滤水管外包100目尼龙网一层。A water filter pipe is installed in the well pipe, which is a Ф325*6 bridge type water filter pipe. The water filter pipe is put into the prepared specification gravel according to the predetermined position, with a diameter of 2-5mm, and the gravel is filled between the well hole and the water filter pipe, and the thickness of the gravel is 200-300mm. , The method of throwing gravel is the method of throwing gravel in still water, and a layer of 100-mesh nylon mesh is wrapped around the water filter pipe.

降水井内设置有用于抽排降水的潜水泵:配置流量10~20m3/h;孔深≤100m,扬程大于150m;孔深>100m,扬程大于200m。The precipitation well is equipped with a submersible pump for pumping and draining precipitation: the flow rate is 10-20m3/h; the hole depth is ≤100m, and the lift is greater than 150m; the hole depth is greater than 100m, and the lift is greater than 200m.

降水井纵向间距为20~25m,布置于正洞轮廓线外侧边缘左右侧4m处。The longitudinal spacing of the dewatering wells is 20-25m, and they are arranged at 4m on the left and right sides of the outer edge of the outline of the main hole.

降水井直径325mm,降水井深进入软塑层高程以下15~25m。The diameter of the dewatering well is 325mm, and the depth of the dewatering well is 15-25m below the elevation of the soft plastic layer.

降水井内底部为沉砂管,长度为5m。The bottom of the dewatering well is a sand tube with a length of 5m.

下管、填料完成后立即进行洗井,采用水泵抽吸联合洗井方法洗井。The well is cleaned immediately after the pipe down and packing are completed.

采用分段分时抽水,降水井最终水位降深为距离孔底5m或采取疏干降水。Staged time-sharing pumping is adopted, and the final water level of the dewatering well is drawn to a depth of 5m from the bottom of the hole, or drainage and precipitation are adopted.

本发明具有以下优点:The present invention has the following advantages:

1、首次将地表深井降水应用于山岭富水黄土隧道。1. The first application of surface deep well dewatering in mountain loess tunnels with rich water.

2、通过地表降水,大大减小了洞内的出水量,解决了隧道洞内股状出水及涌水的问题,施工范围内的黄土基本无渗水,改善了隧道施工及掌子面掘进条件,降低了施工安全风险。2. Through the surface precipitation, the water output in the tunnel is greatly reduced, and the problems of strand-shaped water output and water gushing in the tunnel are solved. The loess in the construction area is basically free of water seepage, which improves the tunnel construction and tunnel face driving conditions and reduces the cost of water flow. construction safety risks.

3、地表降水改变了隧道洞身黄土的含水特性和物理性质,黄土的含水率、液性指数都出现了较大的下降,提高了隧道洞身黄土围岩稳定性,降水井实施后拱顶沉降累积量和变形速率明显降低,为隧道施工工法调整提供了依据。3. Surface precipitation has changed the water content and physical properties of the loess in the tunnel body, and the water content and liquid index of the loess have decreased significantly, which has improved the stability of the loess surrounding rock in the tunnel body. The accumulated settlement and deformation rate were significantly reduced, which provided the basis for the adjustment of the tunnel construction method.

附图说明Description of drawings

图1:降水井结构示意图。Figure 1: Schematic diagram of the dewatering well structure.

图中,1-实管,2-滤水管,3-沉淀管。In the figure, 1-solid pipe, 2-filter pipe, 3-precipitation pipe.

图2:降水井布置示意图。Figure 2: Schematic diagram of the layout of the dewatering wells.

图3:地表抽排水量-隧道洞内出水量与时间关系图。Figure 3: The relationship between the surface pumping water volume and the water output volume in the tunnel cavity and time.

图4:斜井掌子面黄土含水率日变化图。Figure 4: Diurnal variation of loess moisture content on the face of the inclined shaft.

具体实施方式Detailed ways

下面结合具体实施方式对本发明进行详细的说明。The present invention will be described in detail below with reference to specific embodiments.

本发明涉及一种基于降水井抽排的富水软塑黄土隧道地下水渗流控制方法,所述方法包括以下步骤:The invention relates to a method for controlling groundwater seepage in a water-rich soft plastic loess tunnel based on pumping and draining of a dewatering well. The method comprises the following steps:

S1:于富水软塑黄土隧道两侧地表成列布置降水井;S1: Dewatering wells are arranged in rows on both sides of the water-rich soft plastic loess tunnel;

S2:降水井施做完成后进行洗井;S2: Clean the well after the dewatering well is completed;

S3:通过降水井定期抽水作业,降低土层含水率,达到控制富水软塑黄土隧道地下水渗流的目的。S3: Through the regular pumping operation of the dewatering well, the moisture content of the soil layer is reduced, and the purpose of controlling the groundwater seepage of the water-rich soft-plastic loess tunnel is achieved.

降水井施做过程为:The process of dewatering well construction is as follows:

钻孔采用大孔径无岩芯全面钻进,钻孔孔径600mm,钻成井直径325mm,孔深达到设计深度后,依次下入根据排水方案确定的井管;地下水位以上采用粘性土回填固井;井管采用Ф325*6钢卷管,井管连接方式为焊接。The borehole is fully drilled with large aperture without core, the borehole diameter is 600mm, and the diameter of the drilled well is 325mm. After the hole depth reaches the design depth, the well pipe determined according to the drainage plan is run in sequence; above the groundwater level, backfill cementing with clay; The well pipe adopts Ф325*6 steel coiled pipe, and the well pipe connection method is welding.

井管内设置滤水管(即过滤器),为Ф325*6桥式滤水管,滤水管按照预定位置投入准备好的规格砾料,直径2~5mm,在井孔与滤水管之间填砾,填砾厚度200~300mm,投砾方法采用静水投砾法,在滤水管外包100目尼龙网一层。A water filter pipe (ie filter) is set in the well pipe, which is a Ф325*6 bridge water filter pipe. The water filter pipe is put into the prepared specification gravel according to the predetermined position, with a diameter of 2-5mm, and the gravel is filled between the well hole and the water filter pipe. The thickness of the gravel is 200-300mm, and the method of throwing the gravel is the static water throwing method, and the water filter pipe is covered with a layer of 100-mesh nylon mesh.

降水井内设置有用于抽排降水的潜水泵:配置流量10~20m3/h;孔深≤100m,扬程大于150m;孔深>100m,扬程大于200m。The precipitation well is equipped with a submersible pump for pumping and draining precipitation: the flow rate is 10-20m3/h; the hole depth is ≤100m, and the lift is greater than 150m; the hole depth is greater than 100m, and the lift is greater than 200m.

根据水文地质条件,分析富水软塑黄土隧道含水层分布情况,确定隧道洞身所处软塑层段落及含水层厚度,从而确定降水井的布置方案和关键参数。降水井纵向间距为20~25m,布置于正洞轮廓线外侧边缘左右侧4m处。降水井直径325mm,降水井深进入软塑层高程以下15~25m,填砾厚度200~300mm。降水井内底部为沉砂管,长度为5m。According to the hydrogeological conditions, the distribution of the aquifer in the water-rich soft plastic loess tunnel is analyzed, and the section of the soft plastic layer where the tunnel body is located and the thickness of the aquifer are determined, so as to determine the layout plan and key parameters of the dewatering well. The longitudinal spacing of the dewatering wells is 20-25m, and they are arranged at 4m on the left and right sides of the outer edge of the outline of the main hole. The diameter of the dewatering well is 325mm, the depth of the dewatering well is 15-25m below the elevation of the soft plastic layer, and the thickness of the gravel is 200-300mm. The bottom of the dewatering well is a sand tube with a length of 5m.

下面结合实施例对本发明的方法进行进一步详细说明:Below in conjunction with embodiment, the method of the present invention is described in further detail:

实施例:银西高铁驿马一号隧道Example: Yinxi High-speed Railway Yima No. 1 Tunnel

S1步骤:地表降水设计参数Step S1: Design parameters of surface precipitation

1、含水层类型:以黏质黄土为主的潜水含水层。1. Types of aquifers: submerged aquifers dominated by clayey loess.

2、根据分析计算结果,降水井间距分别按20~25m考虑,隧道两侧左右对称布置,地形起伏及冲沟位置间距略有调整。2. According to the analysis and calculation results, the spacing of the dewatering wells is considered as 20-25m, the left and right sides of the tunnel are symmetrically arranged, and the terrain fluctuations and the distance between the gully positions are slightly adjusted.

3、地表降水井布置于正洞轮廓线外侧边缘左右侧4m处(图2)。3. Surface dewatering wells are arranged at 4m from the left and right sides of the outer edge of the outline of the main hole (Figure 2).

4、降水井直径325mm,降水井深进入软塑层高程以下15~25m,填砾厚度200~300mm;4. The diameter of the dewatering well is 325mm, the depth of the dewatering well is 15-25m below the elevation of the soft plastic layer, and the thickness of the gravel is 200-300mm;

5、过滤器位置:自静水位至距离孔底5m之间范围内,根据成井揭示黄土含水层确定。5. The location of the filter: within the range from the static water level to 5m from the bottom of the hole, determined according to the loess aquifer revealed by the completion of the well.

6、地下水位以勘测期间地下水位为依据,变化幅度按1~2m考虑。6. The groundwater level is based on the groundwater level during the survey period, and the variation range is considered as 1-2m.

7、潜水泵:配置流量10~20m3/h,孔深≤100m,扬程大于150m,孔深>100m,扬程大于200m的潜水泵。7. Submersible pump: equipped with a submersible pump with a flow rate of 10-20m 3 /h, a hole depth ≤ 100m, a lift greater than 150m, a hole depth greater than 100m, and a lift greater than 200m.

降水井的结构为:钻孔采用大孔径无岩芯全面钻进,钻孔孔径600mm,钻成井直径325mm,孔深达到设计深度后,依次下入根据排水方案确定的井管。地下水位以上采用粘性土回填固井。井管采用Ф325*6钢卷管,滤水管为Ф325*6桥式滤水管,井管连接方式为焊接。The structure of the dewatering well is as follows: the borehole is fully drilled with large aperture without core, the borehole diameter is 600mm, the diameter of the drilled well is 325mm, and after the hole depth reaches the design depth, the well pipe determined according to the drainage plan is run in sequence. Above the groundwater level, backfill and cement with clayey soil. The well pipe adopts Ф325*6 steel coil pipe, the water filter pipe is Ф325*6 bridge-type water filter pipe, and the well pipe connection method is welding.

S2步骤:降水井实施及效果分析Step S2: Implementation and effect analysis of dewatering wells

1. 成井工艺及方法要求1. Well completion process and method requirements

(1)为确保成井质量,施工前应根据降水井成主要技术参数进行降水井结构、工艺、洗井、试验等设计;(1) In order to ensure the quality of the well completed, the design of the structure, process, well cleaning, and testing of the dewatering well should be carried out according to the main technical parameters of the dewatering well before construction;

(2)降水井尽量保持垂直,当孔斜倾向斜井左右两侧时需及时纠偏,确保降水井对斜井施工无影响或偏离斜井较远时影响降水效果;(2) The dewatering well should be kept as vertical as possible. When the hole deviation is inclined to the left and right sides of the inclined well, the deviation should be corrected in time to ensure that the dewatering well has no influence on the construction of the inclined well or the dewatering effect will be affected when it deviates far from the inclined well;

(3)建议采用反循环及正循环相结合工艺成井;(3) It is recommended to use a combination of reverse circulation and positive circulation to complete the well;

(4)设计沉砂管长度5m;(4) The length of the designed sand chamber is 5m;

(5)施钻过程中准确量测初见水位和静止水位。(5) Accurately measure the initial water level and static water level during the drilling process.

(6)含水层段砾料应具有一定的磨圆度,砾料含泥量(含石粉)≤3%,粒径2~5mm;(6) The gravel in the aquifer section should have a certain degree of roundness, the mud content (including stone powder) of the gravel should be ≤3%, and the particle size should be 2-5mm;

(7)要避免填料速度过快或不均造成滤管偏移及滤料在孔内架桥现象,洗井后滤料下沉应及时补充滤料,要求实际填料量不小于95%理论计算量。(7) To avoid the phenomenon of filter tube offset and filter material bridging in the hole caused by excessively fast or uneven filling speed, the filter material should be replenished in time after the well is washed, and the actual amount of filler should not be less than 95% of the theoretical calculation. quantity.

2. 洗井要求2. Well cleaning requirements

(1)洗井要求达到“水清砂净”;(1) The requirement of well cleaning to achieve "clean water and sand";

(2)下管、填料完成后应立即进行洗井,成井-洗井最大时间间隔不能超过8小时;(2) Well flushing should be carried out immediately after the completion of pipe laying and packing, and the maximum time interval between well completion and well flushing should not exceed 8 hours;

(3)采用泥浆钻进时,采用机械、化学、空压机等联合洗井方式,以达到破除井孔泥壁,清除孔内泥砂,疏通水路之目的;(3) When using mud drilling, the combined well washing methods of mechanical, chemical and air compressors are used to achieve the purpose of breaking the mud wall of the well hole, removing the mud and sand in the hole, and dredging the waterway;

(4)洗井、抽水试验水量水位观测等严格按《铁路工程水文地质勘察规范》(TB10049-2014)及《供水水文地质勘察规范》(GB5007-2016)的要求进行。(4) Well washing, water pumping test, water level observation, etc. shall be carried out in strict accordance with the requirements of "Code for Hydrogeological Investigation of Railway Engineering" (TB10049-2014) and "Code for Hydrogeological Investigation of Water Supply" (GB5007-2016).

(5)验收标准(5) Acceptance criteria

1)洗井结束前的含砂量不大于1/20000(体积比);1) The sand content before the well flushing is not more than 1/20000 (volume ratio);

2)降水井稳定出水量或1周连续出水量达到5m3/h,不断流。2) The steady water output of the dewatering well or the continuous water output for one week reaches 5m 3 /h, and the flow is continuous.

(6)维护降水期地下水观测(6) Maintain groundwater observation during precipitation period

1)维护降水期应对地下水动态进行观测,并对地下水动态变化进行及时分析;1) During the maintenance precipitation period, the dynamics of groundwater should be observed, and the dynamic changes of groundwater should be analyzed in time;

2)当地下水位急剧变化应及时分析原因(如水泵损坏或区域地下水位上升等),采取相应的处理措施;2) When the groundwater level changes sharply, the reasons should be analyzed in time (such as water pump damage or regional groundwater level rise, etc.), and corresponding measures should be taken;

3)降水井施工结束后,在正式抽水前应先测静止水位,降水范围内水位下降未达到设计降深之前,观测频率应为每天观测不少于3次,当水位达到设计降深后,且水位变化不大时,可每天观测1次;3) After the construction of the dewatering well, the static water level should be measured before the formal pumping. Before the water level within the precipitation range drops to the design drawdown, the observation frequency should be no less than 3 times a day. When the water level reaches the design drawdown, And when the water level does not change much, it can be observed once a day;

4)降水井最终水位降深为距离孔底5m或采取疏干降水。4) The final water level of the dewatering well shall be drawn down to 5m from the bottom of the hole, or the dewatering shall be taken.

3、试验段效果分析3. Analysis of the effect of the test section

(1)隧道地下水位下降(1) Tunnel groundwater level drops

一号斜井与正洞相交里程为DK256+520,结合斜井挑顶施工进展情况,降水井于2017年9月15日陆续开始一号斜井附近试验降水井的施工,并进行了试抽水。正式抽水开始后,10眼群井抽水稳定后的平均涌水量为31~91m3/d,各井内动水位与试抽水的基本一致,达到了86~92m,孔内降深为42.2~45.2m,比正式抽水略有降低,低于隧底深度。根据一号斜井及正洞DK256+510~DK256+680降水试验井的抽水情况,地下水静水位在47m~54m之间,经过长时间的抽水,动水位达到了86~92m,孔内降深为42.2~45.2m,平均40.5m。The intersection mileage of the No. 1 inclined shaft and the main hole is DK256+520. Combined with the progress of the construction of the inclined shaft roof, the dewatering well started the construction of the test dewatering well near the No. 1 inclined shaft on September 15, 2017, and the test pumping was carried out. . After the official water pumping started, the average water inflow of the 10 group wells after pumping stabilized was 31-91m3/d, the dynamic water level in each well was basically the same as that of the test pumping, reaching 86-92m, and the drawdown in the hole was 42.2-45.2m. Slightly lower than the formal pumping, lower than the depth of the tunnel bottom. According to the pumping conditions of the No. 1 inclined well and the DK256+510~DK256+680 precipitation test wells in the main hole, the static water level of the groundwater is between 47m and 54m. It is 42.2 to 45.2m, with an average of 40.5m.

(2)隧道洞内出水量减少(2) The water output in the tunnel is reduced

2017年3月至9月,驿马隧道一号斜井在X0+235~+385洞身进入软塑土层后,含水率逐渐增加,并由渗水发展成局部股状出水,集中最大水量可以达到400~600m3/d,之后逐渐衰减,衰减期半个月左右,稳定水量一般在200~300m3/d之间。施工过程中,局部地段出现股状涌水。一般情况下,洞身两侧6眼降水井同时工作,地表降水量达到400m3/d以上,降水40天左右,隧道洞内出水量减少至70m3/d左右,掌子面基本无渗水,洞内出水主要为后方初期支护渗水及二衬盲管排水。From March to September 2017, after the inclined shaft of Yima Tunnel No. 1 entered the soft plastic soil layer in the body of X0+235~+385, the water content gradually increased, and the water seepage developed into a local strand-shaped water outlet. The maximum concentration of water can be It reaches 400~600m 3 /d, and then gradually decays. The decay period is about half a month, and the stable water volume is generally between 200~300m 3 /d. During the construction process, water gushing appeared in some areas. Under normal circumstances, 6 dewatering wells on both sides of the tunnel body work at the same time, the surface precipitation reaches more than 400m 3 /d, the precipitation is about 40 days, the water output in the tunnel is reduced to about 70m 3 /d, and the tunnel face is basically free of water seepage. The effluent in the tunnel is mainly the seepage of the rear initial support and the drainage of the secondary lining blind pipe.

(4)掌子面黄土物理性质变化(4) Changes in physical properties of loess on the palm face

Figure 306637DEST_PATH_IMAGE002
Figure 306637DEST_PATH_IMAGE002

从表1反应了驿马一号隧道地表降水试验试验过程中黄土围岩物理性质测试结果,可以看出,驿马一号隧道在未进行地表降水前,黄土含水率平均为31.2%,液限平均为33%,塑限平均为18.75,液性指数平均为0.84,塑性指数平均为14.28。经过长时间的地表降水,隧道掌子面黄土的物理性质有一定的改善,含水率、液性指数以及塑性指数都出现了一定的下降,在降水初期,掌子面的黄土含水率和液性指数下降明显,大约40天以后,黄土含水率和液性指数均变化幅度减小,数值趋于稳定。总体上含水率平均值由34.4%降到27.3%,最小达到了23.6%;液性指数平均值也从0.84降到了0.6,最小达到了0.3,部分测试结果显示出黄土为硬塑状态;塑性指数平均值从14.28降低到了10.6,最小为10.2。同时黄土的液限与塑限未发生明显改变,平均值较为接近,这说明地表降水未改变黄土的基本特性,主要改变了黄土的含水特征,黄土的塑性状态也发生一定的变化,围岩自稳能力明显加强,改善了隧道洞身黄土围岩的性质,地表降水效果明显。Table 1 reflects the test results of the physical properties of the loess surrounding rock during the surface precipitation test of the Yima No. 1 tunnel. It can be seen that before the surface precipitation of the Yima No. 1 tunnel, the average moisture content of the loess is 31.2%, and the liquid limit is 31.2%. The average is 33%, the average plastic limit is 18.75, the average liquid index is 0.84, and the average plastic index is 14.28. After a long period of surface precipitation, the physical properties of the loess on the tunnel face have been improved to a certain extent, and the moisture content, liquidity index and plasticity index have all declined to a certain extent. The index decreased obviously. After about 40 days, the changes of water content and liquid index of loess decreased, and the values tended to be stable. In general, the average water content decreased from 34.4% to 27.3%, and the minimum reached 23.6%; the average liquid index also decreased from 0.84 to 0.6, and the minimum reached 0.3. Some test results showed that the loess was in a hard plastic state; the plasticity index The average dropped from 14.28 to 10.6, with a minimum of 10.2. At the same time, the liquid limit and plastic limit of loess have not changed significantly, and the average value is relatively close, which indicates that surface precipitation has not changed the basic characteristics of loess, but mainly changed the water content of loess, and the plastic state of loess has also changed to a certain extent. The stability is obviously enhanced, the properties of the loess surrounding rock in the tunnel body are improved, and the effect of surface precipitation is obvious.

驿马一号隧道按照提前降水的原则实施,抽水时间开始为2017年10月22日(试验井),至2019年7月10日截止,2019年7月18日驿马一号隧道全线贯通。DK255+880~DK257+596段总计布井135眼,实际工作的降水井数量为14920m/135眼。地表降水的主要原则如下:The Yima No. 1 tunnel was implemented in accordance with the principle of early precipitation. The pumping time began on October 22, 2017 (experimental well), and ended on July 10, 2019. On July 18, 2019, the Yima No. 1 tunnel was fully completed. DK255+880~DK257+596 section has a total of 135 wells, and the actual number of dewatering wells is 14920m/135. The main principles of surface precipitation are as follows:

1、需要降水的施工段落需提前施作,成井后随即开始间断性抽水,保证降水井正常工作。1. The construction sections that need dewatering should be carried out in advance, and the water will be pumped intermittently immediately after the well is completed to ensure the normal operation of the dewatering well.

2、根据施工进度,采用分段分时抽水。2. According to the construction progress, the water is pumped in sections and time-sharing.

3、各掌子面附近保证有6~8眼降水井同时降水。降水井预降水时间为 1~2个月。3. There are 6 to 8 precipitation wells near each face to ensure simultaneous precipitation. The pre-precipitation time of the precipitation well is 1-2 months.

4、原则上单井的工作时间为120~150天,如遇挑顶、组装台车、工作面贯通、塌方处理等特殊情况时,根据工作需要实时降水,并延长降水井工作时间。4. In principle, the working time of a single well is 120 to 150 days. In case of special circumstances such as roofing, assembling trolleys, working face penetration, landslide treatment, etc., real-time dewatering is required according to work needs, and the working time of dewatering wells is extended.

单井平均抽水251d。The average pumping of a single well is 251d.

单井抽水量34~127m³/d,平均单井抽水量84m³/d,抽水总量2691141m³。具体抽水时间、抽水量、抽水降深详见附件:驿马一号隧道DK255+880~DK257+596段已施工地表井情况核查表。The single well pumping capacity is 34-127m³/d, the average single well pumping capacity is 84m³/d, and the total pumping volume is 2,691,141m³. For specific pumping time, pumping amount, and pumping drawdown, please refer to the appendix: Checklist for Surface Wells Constructed in Sections DK255+880~DK257+596 of Yima No. 1 Tunnel.

开展地表降水后,洞内围岩改良效果明显,股状水、渗涌水等情况基本杜绝,进、出口正洞、斜井工区西安、银川方向掌子面基本无水,围岩以硬塑为主,含水率23%左右。横洞西安、银川方向掌子面少量渗水,无股状、线状出水,围岩以硬塑为主,局部夹软塑,含水率27%左右。降水效果明显,含水率由31%(平均值)下降至25%(平均值),裂隙水基本疏干,掘进环境改善明显,详见下表。After the surface precipitation was carried out, the improvement effect of the surrounding rock in the cave was obvious, and the situation of strand water and seepage water was basically eliminated. Mainly, the moisture content is about 23%. There is a small amount of water seepage on the face of the tunnel in the direction of Xi'an and Yinchuan, and there is no strand or linear water outlet. The surrounding rock is mainly hard plastic, with soft plastic in some parts, and the moisture content is about 27%. The effect of precipitation is obvious, the moisture content is reduced from 31% (average) to 25% (average), the fissure water is basically drained, and the tunneling environment is improved significantly, as shown in the table below.

Figure 895881DEST_PATH_IMAGE004
Figure 895881DEST_PATH_IMAGE004

本发明的内容不限于实施例所列举,本领域普通技术人员通过阅读本发明说明书而对本发明技术方案采取的任何等效的变换,均为本发明的权利要求所涵盖。The content of the present invention is not limited to those listed in the embodiments, and any equivalent transformations taken by those of ordinary skill in the art to the technical solutions of the present invention by reading the description of the present invention are covered by the claims of the present invention.

Claims (9)

1. The groundwater seepage control method of the water-rich soft plastic loess tunnel based on drainage of the dewatering well is characterized by comprising the following steps of:
the method comprises the following steps:
s1: arranging precipitation wells on the ground surfaces on two sides of the water-rich soft plastic loess tunnel in rows;
s2: washing the well after the dewatering well is constructed;
s3: the water content of the soil layer is reduced through the regular pumping operation of the dewatering well, and the purpose of controlling the groundwater seepage of the water-rich soft plastic loess tunnel is achieved.
2. The groundwater seepage control method of the water-rich soft plastic loess tunnel based on dewatering well drainage of claim 1, wherein:
the construction process of the dewatering well comprises the following steps:
drilling holes by adopting large-aperture core-free comprehensive drilling, wherein the hole diameter of each drilled hole is 600mm, the diameter of each drilled hole is 325mm, and well pipes determined according to a drainage scheme are sequentially put into the drilled holes after the hole depth reaches the design depth; backfilling and cementing the well by using cohesive soil above the underground water level; the well pipe adopts a phi 325 and 6 steel coiled pipe, and the connection mode of the well pipe is welding.
3. The groundwater seepage control method of the water-rich soft plastic loess tunnel based on dewatering well drainage of claim 2, wherein:
and arranging filter pipes in the well pipe, wherein the filter pipes are phi 325 & 6 bridge type filter pipes, the filter pipes are filled with prepared gravel materials with the specification according to preset positions, the diameter of the gravel materials is 2-5 mm, gravel is filled between the well hole and the filter pipes, the thickness of the filled gravel is 200-300 mm, a still water gravel filling method is adopted in the gravel filling method, and a nylon net layer with 100 meshes is coated outside the filter pipes.
4. The groundwater seepage control method of the water-rich soft plastic loess tunnel based on dewatering well drainage of claim 3, wherein:
be provided with the immersible pump that is used for pump drainage precipitation in the precipitation well: configuring the flow rate to be 10-20 m 3/h; the hole depth is less than or equal to 100m, and the lift is more than 150 m; the hole depth is more than 100m, and the head is more than 200 m.
5. The groundwater seepage control method of the water-rich soft plastic loess tunnel based on dewatering well drainage of claim 4, wherein:
the longitudinal distance of the dewatering wells is 20-25 m, and the dewatering wells are arranged at the positions 4m on the left side and the right side of the outer edge of the main tunnel contour line.
6. The groundwater seepage control method of the water-rich soft plastic loess tunnel based on dewatering well drainage of claim 5, wherein:
the diameter of the dewatering well is 325mm, and the depth of the dewatering well is 15-25 m below the elevation of the soft plastic layer.
7. The groundwater seepage control method of the water-rich soft plastic loess tunnel based on dewatering well drainage of claim 6, wherein:
the bottom in the dewatering well is a sand setting pipe with the length of 5 m.
8. The groundwater seepage control method of the water-rich soft plastic loess tunnel based on dewatering well drainage of claim 7, wherein:
and (5) immediately washing the well after the pipe lowering and the filling are finished, and washing the well by adopting a water pump suction combined well washing method.
9. The groundwater seepage control method of the water-rich soft plastic loess tunnel based on dewatering well drainage of claim 8, wherein:
and (3) pumping water in a segmented and time-sharing manner, and finally lowering the water level of the dewatering well to 5m from the bottom of the hole or dewatering.
CN202010911266.7A 2020-09-02 2020-09-02 Groundwater seepage control method for water-rich soft plastic loess tunnel based on drainage of dewatering well Pending CN112012790A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010911266.7A CN112012790A (en) 2020-09-02 2020-09-02 Groundwater seepage control method for water-rich soft plastic loess tunnel based on drainage of dewatering well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010911266.7A CN112012790A (en) 2020-09-02 2020-09-02 Groundwater seepage control method for water-rich soft plastic loess tunnel based on drainage of dewatering well

Publications (1)

Publication Number Publication Date
CN112012790A true CN112012790A (en) 2020-12-01

Family

ID=73515684

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010911266.7A Pending CN112012790A (en) 2020-09-02 2020-09-02 Groundwater seepage control method for water-rich soft plastic loess tunnel based on drainage of dewatering well

Country Status (1)

Country Link
CN (1) CN112012790A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114059569A (en) * 2021-10-29 2022-02-18 上海长凯岩土工程有限公司 Positive and negative circulation gravel pack control system of dewatering well

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101070704A (en) * 2007-06-04 2007-11-14 上海地矿工程勘察有限公司 Controllable one-well lamina precipitation construction method
CN101787702A (en) * 2010-02-08 2010-07-28 上海广联建设发展有限公司 Strong vacuum dewatering method
CN102535489A (en) * 2012-02-17 2012-07-04 河北建设勘察研究院有限公司 Method for dewatering large-area foundation pit on silt stratum
CN104514502A (en) * 2014-12-11 2015-04-15 中铁十九局集团有限公司 Surface dewatering deep well washing device
CN107165181A (en) * 2017-07-11 2017-09-15 中交隧道工程局有限公司 It is a kind of that there is the subway foundation pit dewatering well for monitoring depressurization
CN107476322A (en) * 2017-08-10 2017-12-15 魏玉建 Well-points dewatering automatic servo compensation technique
CN107489159A (en) * 2017-08-03 2017-12-19 中国电建集团铁路建设有限公司 Deep & thick silt matter Soft Soil Layer vacuum tube well dewatering construction structure and its construction
CN108867673A (en) * 2018-06-12 2018-11-23 武汉丰达地质工程有限公司 A kind of underwater prevention method in the foundation pit based on the curtain that draws water
CN111254962A (en) * 2020-01-21 2020-06-09 上海勘察设计研究院(集团)有限公司 A rapid precipitation structure and precipitation method for confined water
CN111335344A (en) * 2020-03-19 2020-06-26 中铁六局集团有限公司 Super pressure suction combined well point dewatering construction method for subway deep foundation pit
CN211144529U (en) * 2019-11-15 2020-07-31 中铁二十局集团有限公司 Rich water loess tunnel precipitation construction structures

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101070704A (en) * 2007-06-04 2007-11-14 上海地矿工程勘察有限公司 Controllable one-well lamina precipitation construction method
CN101787702A (en) * 2010-02-08 2010-07-28 上海广联建设发展有限公司 Strong vacuum dewatering method
CN102535489A (en) * 2012-02-17 2012-07-04 河北建设勘察研究院有限公司 Method for dewatering large-area foundation pit on silt stratum
CN104514502A (en) * 2014-12-11 2015-04-15 中铁十九局集团有限公司 Surface dewatering deep well washing device
CN107165181A (en) * 2017-07-11 2017-09-15 中交隧道工程局有限公司 It is a kind of that there is the subway foundation pit dewatering well for monitoring depressurization
CN107489159A (en) * 2017-08-03 2017-12-19 中国电建集团铁路建设有限公司 Deep & thick silt matter Soft Soil Layer vacuum tube well dewatering construction structure and its construction
CN107476322A (en) * 2017-08-10 2017-12-15 魏玉建 Well-points dewatering automatic servo compensation technique
CN108867673A (en) * 2018-06-12 2018-11-23 武汉丰达地质工程有限公司 A kind of underwater prevention method in the foundation pit based on the curtain that draws water
CN211144529U (en) * 2019-11-15 2020-07-31 中铁二十局集团有限公司 Rich water loess tunnel precipitation construction structures
CN111254962A (en) * 2020-01-21 2020-06-09 上海勘察设计研究院(集团)有限公司 A rapid precipitation structure and precipitation method for confined water
CN111335344A (en) * 2020-03-19 2020-06-26 中铁六局集团有限公司 Super pressure suction combined well point dewatering construction method for subway deep foundation pit

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114059569A (en) * 2021-10-29 2022-02-18 上海长凯岩土工程有限公司 Positive and negative circulation gravel pack control system of dewatering well

Similar Documents

Publication Publication Date Title
CN113309565B (en) A curtain grouting method for goaf with large space and large inclination angle
CN103967507B (en) A kind of curtain-grouting technique being suitable for rich water mine down-hole exploitation water blockoff
CN209636826U (en) Rich water sand and gravel stratum foundation pit water sealing structure
CN103088836A (en) Sedimentation control method for pumping water and performing reinjection in well casing simultaneously
CN114412550A (en) Goaf grouting treatment method for extra-thick coal seam old goaf re-mining
CN110646329A (en) Slow-dip-angle weak structural surface penetration deformation field test method after grouting and sample device thereof
CN114233338A (en) A construction technology for grouting reconstruction of loose aquifers in coal mines
CN115126441A (en) Grouting and Stopping Technology of Vertical Deep Drilling
CN110656642A (en) A method for controllable pre-soaking water treatment of collapsible loess foundation
CN116290047B (en) Automatic-monitoring deep foundation pit transverse connection type net-shaped precipitation construction method
CN112012790A (en) Groundwater seepage control method for water-rich soft plastic loess tunnel based on drainage of dewatering well
CN108867673A (en) A kind of underwater prevention method in the foundation pit based on the curtain that draws water
CN104975610B (en) A kind of expansion end step-down well, deep foundation pit structure and its construction method
CN116517539A (en) Method for marine hydrogeology pumping test
CN110748379A (en) Mine plugging method and structure thereof
CN211144529U (en) Rich water loess tunnel precipitation construction structures
CN109868833B (en) Control Method of Precipitation in Deep Foundation Pit with Binary Structure
CN203066092U (en) Pumping and recharging dual-purpose well casing
CN211477996U (en) Specimen device for field test of seepage deformation after grouting of soft inclination angle
CN211477997U (en) Sump structure of sample device for field test of seepage deformation after grouting of soft inclination angle
CN203475411U (en) Structure for reinforcing dredger fill soil foundations by drainage wells combined with air pressure splitting
CN116044495A (en) A kind of mine wastewater treatment method
CN108625374A (en) A kind of homogeneous earth dam and wear dam culvert pipe contact scour antiseepage grouting construction method and detection of grouting effects method
CN107313438B (en) Well formation construction method for dewatering well in area with complex geological conditions
CN117780354B (en) Method for reinforcing bottom of shaft of coal mine vertical shaft to be built by thick loose layer thin bedrock by sparse-filling

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20201201