CN111980249A - Waterproof mounting structure of assembled curtain - Google Patents
Waterproof mounting structure of assembled curtain Download PDFInfo
- Publication number
- CN111980249A CN111980249A CN202010976698.6A CN202010976698A CN111980249A CN 111980249 A CN111980249 A CN 111980249A CN 202010976698 A CN202010976698 A CN 202010976698A CN 111980249 A CN111980249 A CN 111980249A
- Authority
- CN
- China
- Prior art keywords
- waterproof
- curtain wall
- plate
- connecting rod
- groove
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/88—Curtain walls
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
- E04B1/68—Sealings of joints, e.g. expansion joints
- E04B1/6806—Waterstops
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
- E04B1/68—Sealings of joints, e.g. expansion joints
- E04B1/6812—Compressable seals of solid form
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Building Environments (AREA)
Abstract
Description
技术领域technical field
本发明涉及室内装修领域,具体而言,涉及一种装配式幕墙的防水安装结构。The invention relates to the field of interior decoration, in particular to a waterproof installation structure of an assembled curtain wall.
背景技术Background technique
装配式装饰是近年新兴的一种装饰施工形式。装配式装饰顾名思义,即是将装饰所需要使用的各个部品部件在工厂内实现生产完成,然后运输到装饰现场进行组合安装,免去了传统的装饰现场对各部品部件的测量、切割等作业,施工更为简单方便,可以极大地提高装饰现场的施工效率,并且施工现场更为整洁和美观,不会产生过多的装饰材料垃圾,是一种更为绿色环保的装饰施工形式。Prefabricated decoration is an emerging form of decoration construction in recent years. As the name implies, prefabricated decoration is to complete the production of various parts and components required for decoration in the factory, and then transport them to the decoration site for combined installation, eliminating the need for the traditional decoration site to measure and cut each part. The construction is simpler and more convenient, which can greatly improve the construction efficiency of the decoration site, and the construction site is more tidy and beautiful, and will not generate too much decoration material waste, which is a more green and environmentally friendly decoration construction form.
在装配式装饰中,幕墙是其中一项比较重要的装修形式,目前,对于幕墙的底口部分,基本上都是采用密封条来进行防水,但是密封条在经过风吹日晒之后,容易产生脱落等问题,造成防水的失效,并且密封条的拆装都不方便。In the prefabricated decoration, the curtain wall is one of the more important decoration forms. At present, for the bottom part of the curtain wall, the sealing strip is basically used for waterproofing, but the sealing strip is easy to produce after being exposed to wind and sun Falling off and other problems cause waterproof failure, and the disassembly and assembly of the sealing strip is inconvenient.
发明内容SUMMARY OF THE INVENTION
鉴于此,本发明提供了一种装配式幕墙的防水安装结构,其可以有效地解决密封条脱落造成防水失效的问题,从而可以达到提高幕墙防水效果的目的。In view of this, the present invention provides a waterproof installation structure of an assembled curtain wall, which can effectively solve the problem of waterproof failure caused by the falling off of the sealing strip, so as to achieve the purpose of improving the waterproof effect of the curtain wall.
为此,本发明提供了一种装配式幕墙的防水安装结构,其包括幕墙板和基层,基层上设置有安装槽,幕墙板安装在安装槽内,安装槽与幕墙板的两侧分别设置有第一防水部件和第二防水部件,第一防水部件和第二防水部件均包括底板、连接杆、第一防水板和第二防水板,连接杆的一端连接底板,连接杆的另一端连接第一防水板,第二防水板的一端连接在底板上,第二防水板的另一端连接在第一防水板上。To this end, the present invention provides a waterproof installation structure for an assembled curtain wall, which includes a curtain wall board and a base layer, an installation groove is arranged on the base layer, the curtain wall board is installed in the installation groove, and two sides of the installation groove and the curtain wall board are respectively provided with The first waterproof component and the second waterproof component, the first waterproof component and the second waterproof component each include a bottom plate, a connecting rod, a first waterproof board and a second waterproof board, one end of the connecting rod is connected to the bottom plate, and the other end of the connecting rod is connected to the first waterproof board. A waterproof plate, one end of the second waterproof plate is connected to the bottom plate, and the other end of the second waterproof plate is connected to the first waterproof plate.
进一步地,上述安装槽上设置有台阶面,台阶面上设置有防水槽。Further, the installation groove is provided with a stepped surface, and the stepped surface is provided with a waterproof groove.
进一步地,上述第一防水板底部设置有凸起部,凸起部卡接在防水槽内。Further, the bottom of the first waterproof plate is provided with a protruding portion, and the protruding portion is clamped in the waterproof groove.
进一步地,上述底板上设置有螺纹槽,连接杆螺接在螺纹槽内。Further, the base plate is provided with a threaded groove, and the connecting rod is screwed into the threaded groove.
进一步地,上述连接杆为螺杆,连接杆上套接有弹簧。Further, the connecting rod is a screw rod, and a spring is sleeved on the connecting rod.
进一步地,上述第一防水板上设置有橡胶层,橡胶层延伸至基层上。Further, a rubber layer is provided on the first waterproof plate, and the rubber layer extends to the base layer.
进一步地,上述底板上设置有第一卡槽,第一卡槽沿底板的长度方向设置,第二防水板底部卡接在第一卡槽内。Further, the bottom plate is provided with a first card slot, the first card slot is arranged along the length direction of the bottom plate, and the bottom of the second waterproof plate is clipped in the first card slot.
进一步地,上述第一防水板设置有第二卡槽,第二卡槽平行第一卡槽,第二防水板顶部卡接在第二卡槽内。Further, the first waterproof plate is provided with a second slot, the second slot is parallel to the first slot, and the top of the second waterproof plate is clipped in the second slot.
进一步地,上述连接杆和第一防水板为一体结构。Further, the above-mentioned connecting rod and the first waterproof plate have an integral structure.
本发明所提供的一种装配式幕墙的防水安装结构中,主要设置了幕墙板和基层,基层上设置有安装槽,幕墙板安装在安装槽内,安装槽与幕墙板的两侧分别设置有第一防水部件和第二防水部件,第一防水部件和第二防水部件均包括底板、连接杆、第一防水板和第二防水板,连接杆的一端连接底板,连接杆的另一端连接第一防水板,第二防水板的一端连接在底板上,第二防水板的另一端连接在第一防水板上,具体安装时,将第二防水板卡接在底板上,再将连接杆螺接在底板的螺纹槽内,使底板、连接杆、第一防水板和第二防水板组成一个整体,即第一防水部件,幕墙板安装在安装槽后,将第一防水部件和第二防水部件插入安装槽与幕墙板之间,即可以固定幕墙板,又可以替代密封条起到防水的作用。In the waterproof installation structure of the prefabricated curtain wall provided by the present invention, a curtain wall board and a base layer are mainly provided, an installation groove is arranged on the base layer, the curtain wall board is installed in the installation groove, and two sides of the installation groove and the curtain wall board are respectively provided with The first waterproof component and the second waterproof component, the first waterproof component and the second waterproof component each include a bottom plate, a connecting rod, a first waterproof board and a second waterproof board, one end of the connecting rod is connected to the bottom plate, and the other end of the connecting rod is connected to the first waterproof board. A waterproof plate, one end of the second waterproof plate is connected to the bottom plate, and the other end of the second waterproof plate is connected to the first waterproof plate. When installing, the second waterproof plate is clamped on the bottom plate, and then the connecting rod is screwed. It is connected to the threaded groove of the bottom plate, so that the bottom plate, connecting rod, first waterproof plate and second waterproof plate form a whole, that is, the first waterproof part. After the curtain wall plate is installed in the installation groove, the first waterproof part and the second waterproof plate The component is inserted between the installation slot and the curtain wall panel, which can fix the curtain wall panel and replace the sealing strip to play a waterproof role.
因此,本发明提供了一种装配式幕墙的防水安装结构,其通过橡胶层、第一防水板和第二防水板可以多次起到防水的作用,且本结构安装方便,可以缩短幕墙板的施工周期。Therefore, the present invention provides a waterproof installation structure of a prefabricated curtain wall, which can play a waterproof role for many times through the rubber layer, the first waterproof board and the second waterproof board, and the structure is easy to install, and can shorten the length of the curtain wall board. Construction period.
附图说明Description of drawings
通过阅读下文优选实施方式的详细描述,各种其他的优点和益处对于本领域普通技术人员将变得清楚明了。附图仅用于示出优选实施方式的目的,而并不认为是对本发明的限制。而且在整个附图中,用相同的参考符号表示相同的部件。在附图中:Various other advantages and benefits will become apparent to those of ordinary skill in the art upon reading the following detailed description of the preferred embodiments. The drawings are for the purpose of illustrating preferred embodiments only and are not to be considered limiting of the invention. Also, the same components are denoted by the same reference numerals throughout the drawings. In the attached image:
图1为本发明实施例提供的一种装配式幕墙的防水安装结构的结构示意图;1 is a schematic structural diagram of a waterproof installation structure of a prefabricated curtain wall according to an embodiment of the present invention;
图2为图1中A部的放大图;Fig. 2 is the enlarged view of A part in Fig. 1;
图3为本发明实施例四提供的一种装配式幕墙的防水安装结构中第一防水部件的结构示意图;3 is a schematic structural diagram of a first waterproof component in a waterproof installation structure of an assembled curtain wall according to
图4为本发明实施例四提供的一种装配式幕墙的防水安装结构中底板的结构示意图。4 is a schematic structural diagram of a bottom plate in a waterproof installation structure of an assembled curtain wall according to
其中,1-幕墙板;2-基层;21-安装槽;211-台阶面;2111-防水槽;3-第一防水部件;31-底板;311-螺纹槽;312-第一卡槽;32-连接杆;33-第一防水板;331-凸起部;332-第二卡槽;34-第二防水板;4-第二防水部件;5-橡胶层。Among them, 1-curtain wall panel; 2-base layer; 21-installation groove; 211-step surface; 2111-waterproof groove; 3-first waterproof part; 31-base plate; 311-thread groove; 312-first card groove; - connecting rod; 33 - first waterproof plate; 331 - raised part; 332 - second slot; 34 - second waterproof plate; 4 - second waterproof part; 5 - rubber layer.
具体实施方式Detailed ways
下面将参照附图更详细地描述本公开的示例性实施例。虽然附图中显示了本公开的示例性实施例,然而应当理解,可以以各种形式实现本公开而不应被这里阐述的实施例所限制。相反,提供这些实施例是为了能够更透彻地理解本公开,并且能够将本公开的范围完整的传达给本领域的技术人员。Exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. While exemplary embodiments of the present disclosure are shown in the drawings, it should be understood that the present disclosure may be embodied in various forms and should not be limited by the embodiments set forth herein. Rather, these embodiments are provided so that the present disclosure will be more thoroughly understood, and will fully convey the scope of the present disclosure to those skilled in the art.
实施例一:Example 1:
参见图1至图4,图中示出了本发明实施例一提供的一种装配式幕墙的防水安装结构,包括幕墙板1和基层2,基层2上设置有安装槽21,幕墙板1安装在安装槽21内,安装槽21与幕墙板1的两侧分别设置有第一防水部件3和第二防水部件4,第一防水部件3和第二防水部件4均包括底板31、连接杆32、第一防水板33和第二防水板34,连接杆的一端连接底板31,连接杆32的另一端连接第一防水板33,第二防水板34的一端连接在底板31上,第二防水板34的另一端连接在第一防水板33上。Referring to FIGS. 1 to 4 , a waterproof installation structure of a prefabricated curtain wall provided in the first embodiment of the present invention is shown, including a curtain wall panel 1 and a
继续参见图1至图4,底板31上设置有第一卡槽312,第一卡槽312沿底板31的长度方向设置,第二防水板34底部卡接在第一卡槽312内。Continuing to refer to FIGS. 1 to 4 , the
继续参见图1至图4,第一防水板33设置有第二卡槽332,第二卡槽332平行第一卡槽312,第二防水板34顶部卡接在第二卡槽332内。Continuing to refer to FIGS. 1 to 4 , the first
继续参见图1至图4,连接杆32和第一防水板33为一体结构。Continuing to refer to FIGS. 1 to 4 , the connecting
本发明所提供的一种装配式幕墙的防水安装结构中,主要设置了幕墙板和基层,基层上设置有安装槽,幕墙板安装在安装槽内,安装槽与幕墙板的两侧分别设置有第一防水部件和第二防水部件,第一防水部件和第二防水部件均包括底板、连接杆、第一防水板和第二防水板,连接杆的一端连接底板,连接杆的另一端连接第一防水板,第二防水板的一端连接在底板上,第二防水板的另一端连接在第一防水板上,具体安装时,将第二防水板卡接在底板上,再将连接杆螺接在底板的螺纹槽内,使底板、连接杆、第一防水板和第二防水板组成一个整体,即第一防水部件,幕墙板安装在安装槽后,将第一防水部件和第二防水部件插入安装槽与幕墙板之间,即可以固定幕墙板,又可以替代密封条起到防水的作用。In the waterproof installation structure of the prefabricated curtain wall provided by the present invention, a curtain wall board and a base layer are mainly provided, an installation groove is arranged on the base layer, the curtain wall board is installed in the installation groove, and two sides of the installation groove and the curtain wall board are respectively provided with The first waterproof component and the second waterproof component, the first waterproof component and the second waterproof component each include a bottom plate, a connecting rod, a first waterproof board and a second waterproof board, one end of the connecting rod is connected to the bottom plate, and the other end of the connecting rod is connected to the first waterproof board. A waterproof plate, one end of the second waterproof plate is connected to the bottom plate, and the other end of the second waterproof plate is connected to the first waterproof plate. When installing, the second waterproof plate is clamped on the bottom plate, and then the connecting rod is screwed. It is connected to the threaded groove of the bottom plate, so that the bottom plate, connecting rod, first waterproof plate and second waterproof plate form a whole, that is, the first waterproof part. After the curtain wall plate is installed in the installation groove, the first waterproof part and the second waterproof plate The component is inserted between the installation slot and the curtain wall panel, which can fix the curtain wall panel and replace the sealing strip to play a waterproof role.
因此,本发明提供了一种装配式幕墙的防水安装结构,其通过橡胶层、第一防水板和第二防水板可以多次起到防水的作用,且本结构安装方便,可以缩短幕墙板的施工周期。Therefore, the present invention provides a waterproof installation structure of a prefabricated curtain wall, which can play a waterproof role for many times through the rubber layer, the first waterproof board and the second waterproof board, and the structure is easy to install, and can shorten the length of the curtain wall board. Construction period.
实施例二:Embodiment 2:
参见图1至图4,图中示出了本发明实施例二提供的一种装配式幕墙的防水安装结构,本实施例在上述各实施例的基础上还进一步地做出了以下作为改进的技术方案:安装槽21上设置有台阶面211,台阶面211上设置有防水槽2111,第一防水板33底部设置有凸起部331,凸起部331卡接在防水槽2111内。通过上述结构的设置,可以使第一防水板连接的更加牢固,凸起部配合防水槽即可以起到限位的作用,还可以防止水从缝隙中流入,达到提高防水效果的目的。Referring to FIGS. 1 to 4, the drawings show a waterproof installation structure of a prefabricated curtain wall provided by the second embodiment of the present invention. This embodiment further makes the following improvements on the basis of the above-mentioned embodiments. Technical solution: the installation groove 21 is provided with a
实施例三:Embodiment three:
参见图1至图4,图中示出了本发明实施例三提供的一种装配式幕墙的防水安装结构,本实施例在上述各实施例的基础上还进一步地做出了以下作为改进的技术方案:底板31上设置有螺纹槽311,连接杆32螺接在螺纹槽311内,连接杆32为螺杆,连接杆32上套接有弹簧321。通过上述结构的设置,螺接连接可以降低安装难度,提高安装速率,同时螺接可以使底板与连接杆连接的更加紧密,提高密封效果,弹簧可以起到缓冲保护防水板的作用。Referring to FIGS. 1 to 4, the drawings show a waterproof installation structure of a prefabricated curtain wall provided by the third embodiment of the present invention. This embodiment further makes the following improvements on the basis of the above-mentioned embodiments. Technical solution: the
实施例四:Embodiment 4:
参见图1至图4,图中示出了本发明实施例四提供的一种装配式幕墙的防水安装结构,本实施例在上述各实施例的基础上还进一步地做出了以下作为改进的技术方案:第一防水板33上设置有橡胶层5,橡胶层5延伸至基层2上。通过上述结构的设置,可以进一步地提高密封效果。Referring to FIGS. 1 to 4, the drawings show a waterproof installation structure of a prefabricated curtain wall provided by
显然,本领域的技术人员可以对本发明进行各种改动和变型而不脱离本发明的精神和范围。这样,倘若本发明的这些修改和变型属于本发明权利要求及其等同技术的范围之内,则本发明也意图包含这些改动和变型在内。It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the spirit and scope of the invention. Thus, provided that these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010976698.6A CN111980249A (en) | 2020-09-16 | 2020-09-16 | Waterproof mounting structure of assembled curtain |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010976698.6A CN111980249A (en) | 2020-09-16 | 2020-09-16 | Waterproof mounting structure of assembled curtain |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN111980249A true CN111980249A (en) | 2020-11-24 |
Family
ID=73449825
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202010976698.6A Pending CN111980249A (en) | 2020-09-16 | 2020-09-16 | Waterproof mounting structure of assembled curtain |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN111980249A (en) |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR20160056748A (en) * | 2014-11-12 | 2016-05-20 | 주식회사 리니트 코리아 | U-Profiled Glass Aluminum Curtain wall for improvement adiabatic efficiency |
| CN110118009A (en) * | 2019-05-30 | 2019-08-13 | 苏州柯利达装饰股份有限公司 | A kind of outer with light chooses decorative thread system |
| CN209244034U (en) * | 2018-11-20 | 2019-08-13 | 深圳东海建设集团有限公司 | A kind of curtain wall damp-proof device |
| CN210713409U (en) * | 2019-08-15 | 2020-06-09 | 南通奥华幕墙装饰工程有限公司 | A waterproof and easy-drying glass curtain wall |
| CN212405634U (en) * | 2020-09-16 | 2021-01-26 | 金螳螂精装科技(苏州)有限公司 | Waterproof mounting structure of assembled curtain |
-
2020
- 2020-09-16 CN CN202010976698.6A patent/CN111980249A/en active Pending
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR20160056748A (en) * | 2014-11-12 | 2016-05-20 | 주식회사 리니트 코리아 | U-Profiled Glass Aluminum Curtain wall for improvement adiabatic efficiency |
| CN209244034U (en) * | 2018-11-20 | 2019-08-13 | 深圳东海建设集团有限公司 | A kind of curtain wall damp-proof device |
| CN110118009A (en) * | 2019-05-30 | 2019-08-13 | 苏州柯利达装饰股份有限公司 | A kind of outer with light chooses decorative thread system |
| CN210713409U (en) * | 2019-08-15 | 2020-06-09 | 南通奥华幕墙装饰工程有限公司 | A waterproof and easy-drying glass curtain wall |
| CN212405634U (en) * | 2020-09-16 | 2021-01-26 | 金螳螂精装科技(苏州)有限公司 | Waterproof mounting structure of assembled curtain |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN202401634U (en) | Adjustable connection structure of photovoltaic glass curtain wall and photovoltaic glass | |
| CN111980249A (en) | Waterproof mounting structure of assembled curtain | |
| CN210105078U (en) | A glass curtain wall with improved water resistance | |
| CN212405634U (en) | Waterproof mounting structure of assembled curtain | |
| CN217841141U (en) | Novel energy-saving assembled sound insulation board | |
| CN212224984U (en) | Unilateral mounting structure of assembled window wrap | |
| CN202300130U (en) | Solar sun-shading louver with flexible assembling | |
| CN217054104U (en) | Assembled revetment veneer dry-type installing the system | |
| CN204804248U (en) | Stone material honeycomb panel and mounting structure | |
| CN208088609U (en) | A kind of soundproof construction decorative curtain wall | |
| CN201740283U (en) | Novel solar collector heatproof frame | |
| CN208105585U (en) | Wall connecting component | |
| CN219509035U (en) | Heat preservation wallboard with waterproof function for decoration and fitment | |
| CN212156910U (en) | Wall washer structure | |
| CN207714579U (en) | A kind of assembled curtain wall | |
| CN208190549U (en) | The solar double-glass assemblies fixing piece that family is installed guide rail with BIPV photovoltaic and cooperated with the guide rail | |
| CN223805724U (en) | A corner wall panel installation structure | |
| CN219100557U (en) | A new type of anti-deformation thermal insulation decorative exterior wall | |
| CN222083935U (en) | Anti-loosening assembled decorative wall panel | |
| CN210485630U (en) | Light trough profiles | |
| CN219343854U (en) | Building surface template | |
| CN111395702A (en) | Ceiling keel structure for architectural decoration | |
| CN217923173U (en) | Bridge sound insulation structure that municipal works were used | |
| CN206207332U (en) | A kind of LED road lamp shade | |
| CN205857547U (en) | Femerell |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| AD01 | Patent right deemed abandoned |
Effective date of abandoning: 20251118 |
|
| AD01 | Patent right deemed abandoned |