- Publication number
- CN111962401A CN111962401A CN202011005289.8A CN202011005289A CN111962401A CN 111962401 A CN111962401 A CN 111962401A CN 202011005289 A CN202011005289 A CN 202011005289A CN 111962401 A CN111962401 A CN 111962401A
- Authority
- CN
- China
- Prior art keywords
- box
- climbing
- ratchet block
- limiting plate
- box body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 230000009194 climbing Effects 0.000 title claims abstract description 98
- 238000009415 formwork Methods 0.000 title claims description 9
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 51
- 239000010959 steel Substances 0.000 claims abstract description 51
- 241000219098 Parthenocissus Species 0.000 claims 6
- 230000037431 insertion Effects 0.000 claims 1
- 238000003780 insertion Methods 0.000 claims 1
- 230000000149 penetrating effect Effects 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 2
- 238000010586 diagram Methods 0.000 description 6
- 238000009434 installation Methods 0.000 description 4
- 238000000034 method Methods 0.000 description 3
- 230000008569 process Effects 0.000 description 2
- 230000003014 reinforcing effect Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Jib Cranes (AREA)
Abstract
本发明涉及桥梁施工设备领域,具体公开了一种爬箱,包括箱体、第一棘块和至少两个导向板,至少两个导向板上下排列固定在箱体上,所述第一棘块上通过轴设在箱体上,第一棘块可绕该轴的轴心线转动,所述箱体上设有上限位板、下限位板和用于钢吊带贯穿的插口,第一棘块择一端抵触在上限位板或下限位板,且第一棘块箱体上设有与液压油缸连接点,轴与箱体的连接点位于插口和液压油缸连接点之间。本发明的目的在于提供爬箱,以解决转换受力时操作不便的技术问题。
The invention relates to the field of bridge construction equipment, and specifically discloses a climbing box, comprising a box body, a first ratchet block and at least two guide plates, wherein the at least two guide plates are arranged up and down and fixed on the box body, the first ratchet block The upper pass shaft is arranged on the box body, and the first ratchet block can rotate around the axis line of the shaft. The box body is provided with an upper limit plate, a lower limit plate and a socket for the steel sling to pass through. The first ratchet block The selected end is against the upper limit plate or the lower limit plate, and the box body of the first ratchet block is provided with a connection point with the hydraulic cylinder, and the connection point between the shaft and the box body is located between the socket and the connection point of the hydraulic cylinder. The purpose of the present invention is to provide a climbing box to solve the technical problem of inconvenient operation when converting force.
Description
技术领域technical field
本发明涉及桥梁施工设备领域,具体公开了爬箱及用于爬模的驱动装置。The invention relates to the field of bridge construction equipment, and specifically discloses a climbing box and a driving device for a climbing formwork.
背景技术Background technique
现有的爬箱一般包括爬架、附墙装置、爬箱和滑轨。附墙装置用于附着在建筑结构上,如桥梁桥墩等;爬架一般包括上横梁、下横梁、立柱和斜撑杆,上横梁和下横梁上下并行排布,立柱竖直设置且用于连接上横梁和下横梁,斜撑杆倾斜设置且其上下两端分别与上横梁和下横梁连接,爬架的作用是用于安装模板;爬箱滑动设在滑轨上并沿滑轨移动,爬箱带动爬架向上移动以实现模板向上爬升的功能,滑轨不仅为爬箱导向且还承受爬架在水平方向的分力。此种结构形式的爬箱,均为单面爬升,当某一面的爬模出现下坠时,易出现安全隐患。目前,已出现有将多个面的爬模连接形成一个整体,进行爬升的,但采用是吊杆和穿心式千斤顶,此种结构因吊杆强度不足,只能承载相对较小的重量爬箱。Existing climbing boxes generally include climbing frames, wall-attaching devices, climbing boxes and slide rails. The wall-attaching device is used to attach to the building structure, such as bridge piers, etc.; the climbing frame generally includes upper beams, lower beams, columns and diagonal struts. The upper beam and the lower beam, the diagonal struts are inclined and the upper and lower ends are connected with the upper beam and the lower beam respectively. The function of the climbing frame is to install the template; the climbing box slides on the slide rail and moves along the slide rail, climbing The box drives the climbing frame to move upward to realize the function of the template climbing upwards. The slide rail not only guides the climbing box but also bears the component force of the climbing frame in the horizontal direction. Climbing boxes of this type of structure all climb on one side. When the climbing form on one side falls, it is easy to cause potential safety hazards. At present, there have been climbing forms that connect multiple surfaces to form a whole for climbing, but they use booms and through-core jacks. Due to the insufficient strength of booms, this structure can only carry a relatively small weight for climbing. box.
发明内容SUMMARY OF THE INVENTION
有鉴于此,本发明的目的在于提供一种能够适用于钢吊带的爬箱,以及提供一种整体爬升承载量的驱动装置。In view of this, the purpose of the present invention is to provide a climbing box that can be applied to a steel sling, and to provide a driving device with an overall climbing capacity.
为达到上述目的,本发明提供如下技术方案:To achieve the above object, the present invention provides the following technical solutions:
一种爬箱,包括箱体、第一棘块和至少两个导向板,至少两个导向板上下排列固定在箱体上,所述第一棘块上通过轴设在箱体上,第一棘块可绕该轴的轴心线转动,所述箱体上设有上限位板、下限位板和用于钢吊带贯穿插设的插口,第一棘块择一端抵触在上限位板或下限位板,且第一棘块箱体上设有与液压油缸连接点,轴与箱体的连接点位于插口和液压油缸连接点之间。A climbing box includes a box body, a first ratchet block and at least two guide plates, the at least two guide plates are arranged up and down on the box body, the first ratchet block is arranged on the box body through a shaft, and the first ratchet block is arranged on the box body. The ratchet block can be rotated around the axis line of the shaft. The box body is provided with an upper limit plate, a lower limit plate and a socket for the penetration of the steel sling. One end of the first ratchet block is against the upper limit plate or the lower limit. The first ratchet block box is provided with a connection point with the hydraulic cylinder, and the connection point between the shaft and the box is located between the socket and the connection point of the hydraulic cylinder.
可选地,所述插口竖直贯穿所有导向板。Optionally, the socket vertically penetrates all guide plates.
可选地,所述第一棘块上下两端的外侧均设有限位平面,所述限位平面能够抵触在上限位板或下限位板上。Optionally, the outer sides of the upper and lower ends of the first ratchet block are provided with limit planes, and the limit planes can abut against the upper limit plate or the lower limit plate.
可选地,所述第一棘块上端的顶部和下端的底部均设有受力平面,所述受力平面能够抵触在钢吊带上。Optionally, the top of the upper end of the first ratchet block and the bottom of the lower end are both provided with a force-bearing plane, and the force-bearing plane can abut against the steel strap.
可选地,所述上限位板和下限位板与箱体组合形成插口。Optionally, the upper limit plate and the lower limit plate are combined with the box to form a socket.
可选地,还包括换向器,所述换向器包括换向杆和两个换向弹簧,所述换向杆转动设置在两个箱体之间,两个所述换向弹簧的一端与换向杆转动连接,两个所述换向弹簧的另一端分别与第一棘块的上下两侧转动连接。Optionally, it also includes a reversing device, the reversing device includes a reversing rod and two reversing springs, the reversing rod is rotatably arranged between the two boxes, and one end of the two reversing springs is The other ends of the two reversing springs are rotatably connected with the upper and lower sides of the first ratchet block respectively.
本发明还提供一种用于爬模的驱动装置,所述用于爬模的驱动装置包括顶升器、上爬箱和下爬箱,上爬箱和下爬箱之间通过顶升器连接,还包括钢吊带,所述钢吊带上设有若干受力槽,若干受力槽沿钢吊带高度方向均匀排布,所述钢吊带穿设在上爬箱和下爬箱内,下爬箱为如权利要求1-7所述的爬箱。The present invention also provides a driving device for a climbing form, the driving device for a climbing form includes a jack, an upper climbing box and a lower climbing box, and the upper and lower climbing boxes are connected by a jack , and also includes a steel sling, the steel sling is provided with a number of stress grooves, and the several stress grooves are evenly arranged along the height direction of the steel sling, and the steel sling is worn in the upper and lower climbing boxes, and the lower climbing box It is a climbing box as claimed in claims 1-7.
可选地,所述上爬箱包括第二箱体、第二棘块、第二换向器和第二上限位板,所述第二棘块转动设在第二箱体上,所述第二换向器设在第二箱体上并与第二棘块连接,所述第二换向器用于驱动第二棘块转动,所述第二上限位板用于限定第二棘块转动的角度,所述第二棘块用于与钢吊带配合,所述第二上限位板与第二箱体之间形成第三插口,所述第三插口用于插设钢吊带。Optionally, the climbing box includes a second box body, a second ratchet block, a second commutator and a second upper limit plate, the second ratchet block is rotatably arranged on the second box body, and the first The second commutator is arranged on the second box body and is connected with the second ratchet block. The second commutator is used to drive the second ratchet block to rotate, and the second upper limit plate is used to limit the rotation of the second ratchet block. Angle, the second ratchet block is used to cooperate with the steel sling, a third socket is formed between the second upper limit plate and the second box, and the third socket is used to insert the steel sling.
本方案的工作原理及有益效果在于:The working principle and beneficial effects of this scheme are as follows:
1、本方案中设置有第一棘块和钢吊带,同时将钢吊带穿设在爬箱内,采用第一棘块与钢吊带配合进行支撑,钢吊带相比现有的吊杆在受力过程中受力面积大,故而能承载更大的载重量。第一棘块可以转动,当第一棘块转动到钢吊带的受力槽时,第一棘块与受力槽上下相抵即可使爬箱挂在钢吊带上。第一棘块的操作方式十分简单,仅仅需要将其转动到受力槽中、转动到受力槽外即可实现支撑与脱离两种状态的更换,与现有技术相比更省时省力。1. In this scheme, a first ratchet block and a steel sling are provided. At the same time, the steel sling is placed in the climbing box, and the first ratchet block and the steel sling are used for support. Compared with the existing suspender, the steel sling is under stress. During the process, the force area is large, so it can carry a larger load. The first ratchet block can be rotated, and when the first ratchet block rotates to the force receiving groove of the steel sling, the first ratchet block and the force receiving groove are abutted up and down, so that the climbing box can be hung on the steel sling. The operation mode of the first ratchet block is very simple. It only needs to be rotated into the force receiving groove and out of the force receiving groove to realize the replacement of the two states of support and separation, which is more time-saving and labor-saving compared with the prior art.
2、本方案中导向板上设置有滑槽,箱体上设置有上导向板和下导向板;其中滑槽与钢吊带滑动接触,能够起到限位作用,避免爬箱在上下滑动时脱离钢吊带;上导向板和下导向板一方面能够起到限制第一棘块转动角度的作用,另一方面也能够起到限制爬箱水平移动的作用,进一步避免爬箱脱离钢吊带。2. In this scheme, the guide plate is provided with a chute, and the box body is provided with an upper guide plate and a lower guide plate; wherein the chute is in sliding contact with the steel sling, which can play a limiting role and prevent the climbing box from disengaging when sliding up and down. Steel sling; the upper guide plate and the lower guide plate can limit the rotation angle of the first ratchet block on the one hand, and limit the horizontal movement of the climbing box on the other hand, further preventing the climbing box from being separated from the steel sling.
3、本方案中的附墙装置采用连接方销的方式与钢吊带连接,安装和拆卸都十分简单,省时省力。3. The wall-attaching device in this scheme is connected with the steel sling by means of connecting square pins. The installation and disassembly are very simple, saving time and effort.
4、由于爬箱中轴与箱体的连接点位于插口和液压油缸连接点之间而不在同一竖直直线上,所以当液压油缸运作时,箱体不仅会受到竖直向上的推力,还会受到旋转的施力,导致箱体与钢吊带发生相对转动而卡死、损坏;本方案中设置有导向板,导向板能够对箱体的移动轨迹进行限位,使其只能向上移动,同时,上限位板和下限位板也能够起到相应的限位作用,保证液压油缸运作时,箱体能够顺利竖直向上移动。4. Since the connection point between the shaft of the climbing box and the box body is located between the socket and the connection point of the hydraulic cylinder and not on the same vertical line, when the hydraulic cylinder is operating, the box body will not only receive a vertical upward thrust, but also Due to the force of rotation, the box body and the steel sling will rotate relative to each other and become stuck and damaged; in this scheme, a guide plate is provided, which can limit the movement track of the box body, so that it can only move upward, and at the same time , the upper limit plate and the lower limit plate can also play a corresponding limiting role to ensure that the box body can move vertically upward smoothly when the hydraulic cylinder is operating.
本发明的其他优点、目标和特征在某种程度上将在随后的说明书中进行阐述,并且在某种程度上,基于对下文的考察研究对本领域技术人员而言将是显而易见的,或者可以从本发明的实践中得到教导。本发明的目标和其他优点可以通过下面的说明书来实现和获得。Other advantages, objects, and features of the present invention will be set forth in the description that follows, and will be apparent to those skilled in the art based on a study of the following, to the extent that is taught in the practice of the present invention. The objectives and other advantages of the present invention may be realized and attained by the following description.
附图说明Description of drawings
图1为实施例的结构示意图;Fig. 1 is the structural representation of embodiment;
图2为下方的爬箱的侧面结构示意图;Fig. 2 is the side structure schematic diagram of the lower climbing box;
图3为立柱、钢吊带、爬箱、附墙装置和顶升器的结构示意图;Figure 3 is a schematic structural diagram of a column, a steel sling, a climbing box, a wall-attaching device and a jacking device;
图4为下方的爬箱和顶升器的结构示意图;Fig. 4 is the structural schematic diagram of the lower climbing box and the jack;
图5为下方的爬箱和钢吊带后侧的结构示意图;Figure 5 is a schematic structural diagram of the lower climbing box and the rear side of the steel sling;
图6为附墙装置的结构示意图;FIG. 6 is a schematic structural diagram of a wall-attaching device;
图7为下方的爬箱内部设置有换向器时的结构示意图。FIG. 7 is a schematic structural diagram when a commutator is provided inside the lower climbing box.
附图中标记如下:上横梁1、下横梁2、立柱3、斜撑杆4、附墙装置5、钢吊带6、受力槽7、顶升器8、爬箱9、棘块10、上导向板11、下导向板12、箱体13、油缸销孔14、上限位板15、换向销轴16、第一转动销17、第二转动销18、滑槽19、受力平面20、限位平面21、安装通槽22、油缸销孔23、支撑座24、限位座25、换向杆26、第一换向架27、第二换向架28、第一换向弹簧29、第二换向弹簧30。The symbols in the drawings are as follows: upper beam 1,
具体实施方式Detailed ways
下面通过具体实施方式进一步详细说明:The following is further described in detail by specific embodiments:
实施例Example
一种爬模系统,包括四个爬模单元,爬模单元通过围圈连接形成一个整体,围圈用于承载爬架在水平方向上的分力。围圈为现有技术,故在此不再赘述。如图1所示,每一爬模单元包括爬架、附墙装置5、顶升器8、两个爬箱9、钢吊带6、上导向板11和下导向板12。两个爬箱9通过顶升器8连接,钢吊带6还穿过插口设置在两个爬箱9内,且位于上方的爬箱9与爬架固定,爬架与附墙装置可拆卸连接。上导向板11和下导向板12设在位于下方的爬箱9上,上导向板11和下导向板12的两侧均设置有滑槽19,滑槽19卡住两侧的立柱3并与立柱3滑动接触,下导向板12和上导向板11均设有安装通槽22,爬箱9和钢吊带6均位于安装通槽22内。顶升器8为液压油缸。A climbing formwork system includes four climbing formwork units, the climbing formwork units are connected to form a whole through a surrounding ring, and the surrounding ring is used to carry the component force of the climbing frame in the horizontal direction. The enclosure is the prior art, so it is not repeated here. As shown in FIG. 1 , each climbing formwork unit includes a climbing frame, a
爬架包括两个竖直并排设置的立柱3、上横梁1、下横梁2和斜撑杆4,上横梁1和下横梁2上下并行排布,立柱3竖直设置且用于固定连接上横梁1和下横梁2,斜撑杆4倾斜设置且其上下两端分别与上横梁1和下横梁2固定连接。爬架的顶部再用于安装模板。每一立柱3对应设置有附墙装置5、顶升器8、爬箱9和钢吊带6。每一立柱3包括两个立柱3和连接在立柱3之间的加强板。The climbing frame includes two
钢吊带6呈扁平的长方体状,钢吊带6上水平设有若干受力槽7,若干受力槽7沿钢吊带6高度方向均匀排布,受力槽7呈长方体状。The
结合图6,附墙装置5包括本体、支撑座24和限位座25,支撑座24转动设置在本体上,限位座25设置在支撑座24的下方,且限位座25的顶壁与支撑座24的底部相抵并用于撑起支撑座24以及限位支撑座24的转动角度。受力槽7的内顶壁与支撑座24相抵并支撑钢吊带6,实现附墙装置5与钢吊带6可拆卸连接。爬架与附墙装置5可拆卸连接的方式为:本体的底部水平设置有第一方销孔,爬架上水平设有第二方销孔,第一方销孔和第二方销孔中插入有连接方销。Referring to FIG. 6 , the
结合图2、图3、图5,爬箱9设置在两个立柱3之间。爬箱9包括箱体13、换向器和棘块10;箱体13的上端与上导向板11的底部固定连接,箱体13的下端与下导向板12的顶部固定连接;棘块10通过换向销轴16转动设置在箱体13上;换向器用于驱动棘块10转动换向。位于下方爬箱9的箱体13上固定设有两块用于限制棘块10转动角度的上限位板15和下限位板,上限位板15和下导向板设置在箱体13远离爬架的一侧,上限位板15和下限位板套设在钢吊带6上且与钢吊带6滑动接触;位于上方爬箱9与位于下方的爬箱9的不同之处在于:上方的爬箱9未设置上导向板11和下导向板12、箱体上固定设有两块用于限制棘块10转动角度的上限位板15,但其中一块上限位板15为立柱的加强板。棘块10与受力槽7接触的一侧设有受力平面20,棘块10与上限位板15接触的一侧设有限位平面21。棘块10朝受力槽7的方向转动后与受力槽7上下相抵并用于支撑爬箱9。2 , 3 and 5 , the
结合图4,顶升器8设置在两个爬箱9之间,顶升器8的两端分别与两个爬箱9转动连接,转动连接的方式为:顶升器8的上端固定设有第一转动销17,顶升器8的下端固定设有第二转动销18,箱体13上均设有油缸销孔14,第一转动销17和第二转动销18分别对准上方和下方的油缸销孔14并插入油缸销轴完成转动连接。4, the
图1-图6中未示出换向器,如图7中所示,换向器包括换向杆26、第一换向弹簧29、第二换向弹簧30、第一换向架27和第二换向架28;换向杆26呈U形,且两端水平弯折并转动设置在两侧的箱体13上;第一换向架27和第二换向架28分别固定设置在棘块10的上侧和下侧,第一换向弹簧29的两端分别与第一换向架27和换向杆26转动连接,第二换向弹簧30的两端分别与第二换向架28和换向杆26转动连接。转动换向杆26可驱动棘块10转动,改变棘块10与钢吊带6之间的配合关系。The commutator is not shown in FIGS. 1-6 , as shown in FIG. 7 , the commutator includes a reversing
位于上方的爬箱9中设有插口,该插口由上方的爬箱9上的上限位板15、下限位板与箱体13组合形成。下方的爬箱9中设有第三插口,第三插口由该爬箱9上的上限位板15和箱体13组合形成。The
具体实施时:When implementing:
需要向上爬升时,先向上移动钢吊带6使其与上方的建筑体的附墙装置5连接,其后,将上方爬箱9的换向器驱动棘块10的下端向建筑体一侧转动,下方爬箱9的换向器驱动棘块10的下端向建筑体一侧转动,此时,下方爬箱9支撑钢吊带6上,上方爬箱9可在钢吊带6上滑动,此时顶升器8工作带动上方爬箱9向上移动,从而带动爬模向上移动;待顶升器8处于最大行程时,顶升器8停止工作,同时将两个爬箱9的棘块10方向转动,即利用换向器驱动棘块10的上端向建筑体一侧转动,此时上方爬箱9支撑在钢吊带6上,下方爬箱9可在钢吊带6上滑动;再次让顶升器8工作至最小行程,从而爬升了下方爬箱9的位置,再次反向翻转棘块10,重复前面的步骤,直至爬架爬升至预设位置,此时将爬架再次固定到附墙装置5上。When it is necessary to climb upward, first move the
本方案中设置有棘块10和钢吊带6,同时将钢吊带6穿设在爬箱9内,采用棘块10与钢吊带配合进行支撑,钢吊带6相比现有的吊杆在受力过程中受力面积大,故而能承载更大的载重量。In this solution, a
以上所述的仅是本发明的实施例,方案中公知的具体结构及特性等常识在此未作过多描述。应当指出,对于本领域的技术人员来说,在不脱离本发明结构的前提下,还可以作出若干变形和改进,这些也应该视为本发明的保护范围,这些都不会影响本发明实施的效果和本发明的实用性。The above descriptions are only examples of the present invention, and common knowledge such as well-known specific structures and characteristics in the solution are not described too much here. It should be pointed out that for those skilled in the art, on the premise of not departing from the structure of the present invention, several modifications and improvements can also be made, which should also be regarded as the protection scope of the present invention, and these will not affect the implementation of the present invention. Effects and applicability of the present invention.
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202011005289.8A CN111962401B (en) | 2020-09-23 | 2020-09-23 | Drive device for climbing formwork |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202011005289.8A CN111962401B (en) | 2020-09-23 | 2020-09-23 | Drive device for climbing formwork |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN111962401A true CN111962401A (en) | 2020-11-20 |
| CN111962401B CN111962401B (en) | 2024-12-20 |
Family
ID=73387520
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202011005289.8A Active CN111962401B (en) | 2020-09-23 | 2020-09-23 | Drive device for climbing formwork |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN111962401B (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN118029659A (en) * | 2023-11-22 | 2024-05-14 | 中国建筑第八工程局有限公司 | A sleeve type climbing device |
Citations (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE3842094A1 (en) * | 1988-12-14 | 1990-06-21 | Peri Werk Schwoerer Kg Artur | SECTIONAL MOVABLE SLIDING STAGE ON A WALL |
| CN101343928A (en) * | 2008-08-14 | 2009-01-14 | 江都揽月机械有限公司 | Hydraulic pole climbing device |
| CN204139590U (en) * | 2014-08-05 | 2015-02-04 | 广州市达蒙建筑技术有限公司 | Hydraulic self-creeping formwork climbing device |
| CN204299175U (en) * | 2014-09-30 | 2015-04-29 | 广州达蒙安防科技有限公司 | Hydraulic climbing die block system |
| KR20160045654A (en) * | 2016-04-08 | 2016-04-27 | 이옥순 | Construction noise reduction devices for windows and doors of the formwork system |
| CN106672821A (en) * | 2017-01-04 | 2017-05-17 | 沈阳建筑大学 | Tower crane climbing system with automatic climbing belt lifting function |
| CN110937528A (en) * | 2019-12-04 | 2020-03-31 | 沈阳建筑大学 | Tower Crane Climbing Belt Climbing Safety Facilities |
| CN210508407U (en) * | 2019-08-30 | 2020-05-12 | 厦门安科科技有限公司 | Anti-falling climbing device for climbing form |
| CN212452320U (en) * | 2020-09-23 | 2021-02-02 | 重庆广路模板制造有限公司 | Climb case and be used for drive arrangement of creeping formwork |
-
2020
- 2020-09-23 CN CN202011005289.8A patent/CN111962401B/en active Active
Patent Citations (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE3842094A1 (en) * | 1988-12-14 | 1990-06-21 | Peri Werk Schwoerer Kg Artur | SECTIONAL MOVABLE SLIDING STAGE ON A WALL |
| CN101343928A (en) * | 2008-08-14 | 2009-01-14 | 江都揽月机械有限公司 | Hydraulic pole climbing device |
| CN204139590U (en) * | 2014-08-05 | 2015-02-04 | 广州市达蒙建筑技术有限公司 | Hydraulic self-creeping formwork climbing device |
| CN204299175U (en) * | 2014-09-30 | 2015-04-29 | 广州达蒙安防科技有限公司 | Hydraulic climbing die block system |
| KR20160045654A (en) * | 2016-04-08 | 2016-04-27 | 이옥순 | Construction noise reduction devices for windows and doors of the formwork system |
| CN106672821A (en) * | 2017-01-04 | 2017-05-17 | 沈阳建筑大学 | Tower crane climbing system with automatic climbing belt lifting function |
| CN210508407U (en) * | 2019-08-30 | 2020-05-12 | 厦门安科科技有限公司 | Anti-falling climbing device for climbing form |
| CN110937528A (en) * | 2019-12-04 | 2020-03-31 | 沈阳建筑大学 | Tower Crane Climbing Belt Climbing Safety Facilities |
| CN212452320U (en) * | 2020-09-23 | 2021-02-02 | 重庆广路模板制造有限公司 | Climb case and be used for drive arrangement of creeping formwork |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN118029659A (en) * | 2023-11-22 | 2024-05-14 | 中国建筑第八工程局有限公司 | A sleeve type climbing device |
Also Published As
| Publication number | Publication date |
|---|---|
| CN111962401B (en) | 2024-12-20 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105000482B (en) | Tower crane with traveling mechanism | |
| CN211173046U (en) | Wall-attached support for attached lifting scaffold | |
| CN114704096A (en) | Climbing formula quick detach concrete spreader in pit shaft | |
| CN114991482A (en) | Roof steel truss sliding track and dismounting method | |
| CN213626572U (en) | Tool type external cantilever operation platform | |
| CN111962401A (en) | Climbing box and drive for climbing formwork | |
| CN211114737U (en) | A construction operation platform in elevator well for tower crane promotes | |
| CN212452320U (en) | Climb case and be used for drive arrangement of creeping formwork | |
| CN119287969A (en) | Cup mouth base socket type inner mold | |
| CN216732451U (en) | Building roof drilling rig support | |
| CN113175201B (en) | A sliding operating platform for elevator shaft construction | |
| CN111645202B (en) | Mobile automatic lifting bench of drilling rig for reinforcement of railway retaining wall | |
| CN212002156U (en) | A kind of convenient moving scaffolding for building construction | |
| CN209651835U (en) | A hydraulic lift for steel structure installation | |
| CN213509528U (en) | High lift platform for construction of security | |
| CN220565730U (en) | Guide rail type discharging device | |
| CN223293348U (en) | A safe construction frame | |
| CN220432220U (en) | An engineering equipment maintenance device | |
| CN223781124U (en) | Anti-toppling scaffold | |
| CN216360881U (en) | Supporting platform for mounting steel structure industrial factory building | |
| CN116770728B (en) | A rapid positioning device for high-altitude installation of main tower steel reinforcement frame | |
| CN220100568U (en) | Building construction frame | |
| CN219411733U (en) | Building construction platform convenient to move | |
| CN214734103U (en) | Controllable over-and-under type operation platform for building | |
| CN213038810U (en) | Telescopic reinforcing bar installation operation panel |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |