CN111945715A - Prefabricated pipe pile for construction of ultra-long stiff composite pile and construction method - Google Patents
Prefabricated pipe pile for construction of ultra-long stiff composite pile and construction method Download PDFInfo
- Publication number
- CN111945715A CN111945715A CN202010824898.XA CN202010824898A CN111945715A CN 111945715 A CN111945715 A CN 111945715A CN 202010824898 A CN202010824898 A CN 202010824898A CN 111945715 A CN111945715 A CN 111945715A
- Authority
- CN
- China
- Prior art keywords
- pile
- construction
- section
- sections
- super
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/52—Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
- E02D5/523—Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
- E02D5/526—Connection means between pile segments
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/24—Prefabricated piles
- E02D5/28—Prefabricated piles made of steel or other metals
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0026—Metals
- E02D2300/0029—Steel; Iron
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/20—Miscellaneous comprising details of connection between elements
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
本发明公开了一种用于超长劲性复合桩施工的预制管桩及施工方法,包括由下至上依次拼接的多个桩段,各桩段之间连接有连接装置;连接装置包括两个法兰盘和凸部,两个法兰盘分别布置于两个相邻桩段的对接处,两个桩段之间通过法兰盘连接,凸部与两个相邻桩段中的一个桩段一端连接,并插入另一个桩段一端的内圈。本发明操作简单方便,施工速度快,具有更好的承载性能,连接固定更加牢固。
The invention discloses a prefabricated pipe pile and a construction method for the construction of super-long composite piles. Flange plate and convex part, the two flange plates are respectively arranged at the butt joints of two adjacent pile sections, the two pile sections are connected by the flange plate, and the convex part is connected to one of the two adjacent pile sections. One end of the segment is connected and inserted into the inner ring at one end of the other pile segment. The invention has the advantages of simple and convenient operation, high construction speed, better bearing performance, and firmer connection and fixation.
Description
技术领域technical field
本发明涉及建筑施工技术领域,具体涉及一种用于超长劲性复合桩施工的预制管桩及施工方法。The invention relates to the technical field of building construction, in particular to a prefabricated pipe pile and a construction method for the construction of super-long composite piles.
背景技术Background technique
在软土地基上修建建(构)筑物时,天然地基持力层往往不能满足地基强度和结构变形的要求,因此需要对软土地基采取一定的增强措施,而劲性复合桩就是其中一种被广泛应用的桩基础形式。When constructing buildings (structures) on soft soil foundations, the natural foundation bearing layer often cannot meet the requirements of foundation strength and structural deformation, so it is necessary to take certain strengthening measures for soft soil foundations, and stiff composite piles are one of them. A widely used pile foundation form.
劲性复合桩是一种由散体桩(由碎石、砂、钢渣、矿渣或砖瓦碎块等散体材料形成的桩)、柔性桩(一般为水泥土搅拌桩)和刚性桩(一般为钢筋混凝土预制桩或钻孔灌注桩)中的两种或三种复合而成的新型桩。其综合了散体桩、柔性桩、刚性桩的优点,使桩芯的刚性桩承受全部竖向荷载,然后把荷载传递给周边的柔性桩,再由柔性桩利用较大摩阻面传递给桩周软土,因此其单桩极限承载力较高,同时具有造价低廉、施工方便、桩身质量稳定可靠和无污染等优点,是一种极具开发前景的新型桩。Stiff composite piles are a kind of piles composed of scattered piles (piles formed from scattered materials such as gravel, sand, steel slag, slag or brick and tile fragments), flexible piles (generally cement-soil mixing piles) and rigid piles (generally It is a new type of pile composed of two or three kinds of reinforced concrete precast piles or bored piles. It combines the advantages of scattered piles, flexible piles and rigid piles, so that the rigid piles of the pile core bear all the vertical loads, and then transfer the load to the surrounding flexible piles, and then the flexible piles use the larger friction surface to transfer the piles to the piles. Therefore, the single pile has high ultimate bearing capacity, and has the advantages of low cost, convenient construction, stable and reliable pile quality and no pollution. It is a new type of pile with great development prospects.
在劲性复合桩施工过程中,需要在散体桩或柔性桩中插入刚性桩。对于超长劲性复合桩,当其刚性桩采用钻孔灌注桩的形式时,其施工工艺已比较成熟,无较大技术难点;而采用预制桩的形式时,由于桩长的限制,就必须采取先分段制作、再现场连接的方法。目前国内连接分段预制桩的方法主要有:抱箍焊接、膨胀螺栓连接、销连接等。抱箍焊接方法比较费时费力,单纯的焊接其质量又难以控制,易造成桩体连接强度不足的问题。膨胀螺栓连接、销连接存在螺孔销孔不易对准、水平抗剪强度不足、安全性低等问题,因此需要一种更为简单、可靠的桩体分段连接方法,能够克服以上技术问题,保证预制桩能够达到预定的设计长度、发挥承载作用。During the construction of stiff composite piles, it is necessary to insert rigid piles into loose piles or flexible piles. For super-long composite piles, when the rigid piles are in the form of bored cast-in-place piles, the construction technology is relatively mature and there is no major technical difficulty; and when the prefabricated piles are used, due to the limitation of the pile length, it is necessary to Take the method of first section production, and then on-site connection. At present, the main methods of connecting segmented prefabricated piles in China are: hoop welding, expansion bolt connection, pin connection, etc. The hoop welding method is time-consuming and labor-intensive, and the quality of the simple welding is difficult to control, which is easy to cause the problem of insufficient connection strength of the pile body. Expansion bolt connection and pin connection have problems such as difficult alignment of screw holes and pin holes, insufficient horizontal shear strength, and low safety. Therefore, a simpler and more reliable pile section connection method is needed, which can overcome the above technical problems. Ensure that the prefabricated pile can reach the predetermined design length and play a bearing role.
发明内容SUMMARY OF THE INVENTION
本发明要解决的技术问题是,针对现有技术存在的上述缺陷,提供了一种用于超长劲性复合桩施工的预制管桩及施工方法,操作简单方便,施工速度快,具有更好的承载性能,连接固定更加牢固。The technical problem to be solved by the present invention is to provide a prefabricated pipe pile and a construction method for the construction of super-long composite piles in view of the above-mentioned defects in the prior art, which are simple and convenient to operate, fast in construction, and have better performance. The load-bearing performance is better, and the connection and fixation are more firm.
本发明为解决上述技术问题所采用的技术方案是:The technical scheme adopted by the present invention for solving the above-mentioned technical problems is:
一种用于超长劲性复合桩施工的预制管桩,包括由下至上依次拼接的多个桩段,各桩段之间连接有连接装置;通过连接装置实现各桩段之间的连接;A prefabricated tubular pile used for construction of super-long composite piles, comprising a plurality of pile sections spliced in sequence from bottom to top, connecting devices are connected between the pile sections; the connection between the pile sections is realized through the connecting device;
连接装置包括两个法兰盘和凸部,两个法兰盘分别布置于两个相邻桩段的对接处,两个桩段之间通过法兰盘连接,凸部与两个相邻桩段中的一个桩段一端连接,并插入另一个桩段一端的内圈。The connecting device includes two flanges and a convex part, the two flanges are respectively arranged at the butt joints of two adjacent pile sections, the two pile sections are connected by a flange, and the convex part is connected to the two adjacent piles. One of the segments is connected at one end and inserted into the inner ring at one end of the other.
按照上述技术方案,凸部为圆环钢筒。According to the above technical solution, the convex portion is a circular steel cylinder.
按照上述技术方案,圆环钢筒的壁厚为1.5cm~3cm,其中优先选择为2cm。According to the above technical solution, the wall thickness of the annular steel cylinder is 1.5 cm to 3 cm, of which 2 cm is preferred.
按照上述技术方案,凸部的插入长度为35~45cm。According to the above technical solution, the insertion length of the convex portion is 35-45 cm.
按照上述技术方案,法兰盘上沿周向分布有多个螺栓孔,两个对接的法兰盘之间通过螺栓连接,螺栓穿入相应的螺栓孔内。According to the above technical solution, a plurality of bolt holes are distributed on the flange along the circumferential direction, and the two butted flanges are connected by bolts, and the bolts penetrate into the corresponding bolt holes.
按照上述技术方案,两个对接的法兰盘分别为上部法兰盘和下部法兰盘。According to the above technical solution, the two butted flanges are an upper flange and a lower flange respectively.
按照上述技术方案,法兰盘与桩段之间连接有钢套箍,法兰盘与桩段的钢套箍预先焊接为一体。According to the above technical solution, a steel ferrule is connected between the flange and the pile section, and the flange and the steel ferrule of the pile section are pre-welded as a whole.
一种采用以上所述的用于超长劲性复合桩施工的预制管桩的施工方法,多个桩段分别为由下至上依次连接的底桩段、中间桩段和顶桩段;中间桩段为一个或多个;A construction method using the above-mentioned prefabricated tubular pile for construction of super-long composite piles, wherein the plurality of pile sections are respectively bottom pile sections, middle pile sections and top pile sections connected in sequence from bottom to top; segment is one or more;
所述的施工方法具体包括以下步骤:The construction method specifically includes the following steps:
1)将底桩段压入水泥土搅拌桩中;1) Press the bottom pile section into the cement-soil mixing pile;
2)将中间桩段吊起与底桩段通过连接装置连接,再继续将中间桩段也压入水泥土搅拌桩;2) Lift the middle pile section and connect the bottom pile section through the connecting device, and then continue to press the middle pile section into the cement-soil mixing pile;
3)将顶桩段吊起与中间桩段通过连接装置连接,再继续将顶桩段压入至水泥土搅拌桩中设计深度。3) Lift the top pile section and connect the middle pile section through the connecting device, and then continue to press the top pile section to the design depth in the cement-soil mixing pile.
按照上述技术方案,在所述的步骤2)和3)中,两个桩段之间通过连接装置连接之前,将高强树脂涂抹在相应的两个对接法兰盘和凸部上;之后再将凸部插入,并用螺栓紧密连接两个法兰盘。According to the above technical solution, in the steps 2) and 3), before the two pile sections are connected by the connecting device, high-strength resin is applied to the corresponding two butt flanges and the convex part; The protrusions are inserted and the two flanges are tightly connected with bolts.
按照上述技术方案,在水泥土搅拌桩施工完成后3小时内需要完成各桩段之间的连接及压入工作。According to the above technical scheme, the connection and pressing work between the pile sections need to be completed within 3 hours after the completion of the cement-soil mixing pile construction.
本发明具有以下有益效果:The present invention has the following beneficial effects:
本发明通过预制分段,现场连接,简化了管桩的连接方法,加快了施工速度。同时,通过凸部、法兰盘使得桩体的连接更加牢固,因而获得更好的水平和垂直承载性能。The invention simplifies the connection method of the pipe piles and accelerates the construction speed through prefabricated sections and on-site connection. At the same time, the connection of the pile body is made firmer through the convex part and the flange plate, so as to obtain better horizontal and vertical bearing performance.
附图说明Description of drawings
图1是本发明实施例中顶桩段的结构示意图;1 is a schematic structural diagram of a jacking section in an embodiment of the present invention;
图2是本发明实施例中中间桩段的结构示意图;Fig. 2 is the structural schematic diagram of the middle pile section in the embodiment of the present invention;
图3是本发明实施例中底桩段的结构示意图;Fig. 3 is the structural schematic diagram of the bottom pile section in the embodiment of the present invention;
图4是本发明实施例中上部法兰盘的结构示意图;Fig. 4 is the structural representation of the upper flange plate in the embodiment of the present invention;
图5是本发明实施例中下部法兰盘的结构示意图;Fig. 5 is the structural representation of the lower flange plate in the embodiment of the present invention;
图中,1-底桩段,2-中间桩段,3-顶桩段,4-钢套箍,5-上部法兰盘,6-凸部,7-下部法兰盘,8-螺栓孔。In the figure, 1-bottom pile section, 2-middle pile section, 3-top pile section, 4-steel ferrule, 5-upper flange, 6-convex, 7-lower flange, 8-bolt hole .
具体实施方式Detailed ways
下面结合附图和实施例对本发明进行详细说明。The present invention will be described in detail below with reference to the accompanying drawings and embodiments.
参照图1~图5所示,本发明提供的一个实施例中的用于超长劲性复合桩施工的预制管桩,包括由下至上依次拼接的多个桩段,各桩段之间连接有连接装置;通过连接装置实现各桩段之间的连接;Referring to Figures 1 to 5, a prefabricated tubular pile for construction of an ultra-long composite pile in an embodiment provided by the present invention includes a plurality of pile sections spliced sequentially from bottom to top, and each pile section is connected There is a connecting device; the connection between each pile section is realized through the connecting device;
连接装置包括两个法兰盘和凸部6,两个法兰盘分别布置于两个相邻桩段的对接处,两个桩段之间通过法兰盘连接,凸部6与两个相邻桩段中的一个桩段一端连接,并插入另一个桩段一端的内圈。The connecting device includes two flanges and a convex part 6, the two flanges are respectively arranged at the butt joints of two adjacent pile sections, the two pile sections are connected by the flange, and the convex part 6 is connected to the two adjacent pile sections. One of the adjacent pile segments is connected at one end and inserted into the inner ring at one end of the other pile segment.
进一步地,凸部6为圆环钢筒。Further, the convex portion 6 is a circular steel cylinder.
进一步地,圆环钢筒的壁厚为1.5cm~3cm,其中壁厚优先选择为2cm。Further, the wall thickness of the annular steel cylinder is 1.5cm-3cm, wherein the wall thickness is preferably 2cm.
进一步地,凸部6的插入长度为35~45cm,插入长度优先选择为40cm,可增强桩体连接处的水平抗剪能力。Further, the insertion length of the convex portion 6 is 35-45 cm, and the insertion length is preferably 40 cm, which can enhance the horizontal shear resistance of the pile body connection.
进一步地,法兰盘上沿周向分布有多个螺栓孔8,两个对接的法兰盘之间通过螺栓连接,螺栓穿入相应的螺栓孔8内。Further, a plurality of bolt holes 8 are distributed on the flange along the circumferential direction, and the two butted flanges are connected by bolts, and the bolts penetrate into the corresponding bolt holes 8 .
进一步地,两个对接的法兰盘分别为上部法兰盘5和下部法兰盘7。Further, the two butted flanges are the
进一步地,法兰盘与桩段之间连接有钢套箍,法兰盘与桩段上的钢套箍4预先焊接为一体。Further, a steel ferrule is connected between the flange and the pile section, and the flange and the
一种采用以上所述的用于超长劲性复合桩施工的预制管桩的施工方法,多个桩段分别为由下至上依次连接的底桩段1、中间桩段2和顶桩段3;中间桩段2为一个或多个;A construction method using the above-mentioned prefabricated tubular piles for the construction of super-long composite piles, the plurality of pile sections are respectively bottom pile section 1, middle pile section 2 and top pile section 3 connected sequentially from bottom to top ; One or more intermediate pile sections 2;
所述的施工方法具体包括以下步骤:The construction method specifically includes the following steps:
1)将底桩段1压入水泥土搅拌桩中;1) Press the bottom pile section 1 into the cement-soil mixing pile;
2)将中间桩段2吊起与底桩段1通过连接装置连接,再继续将中间桩段2也压入水泥土搅拌桩;2) Lift the middle pile section 2 and connect it with the bottom pile section 1 through the connecting device, and then continue to press the middle pile section 2 into the cement-soil mixing pile;
3)将顶桩段3吊起与中间桩段2通过连接装置连接,再继续将顶桩段3压入至水泥土搅拌桩中设计深度。3) Lift the top pile section 3 and connect it with the middle pile section 2 through the connecting device, and then continue to press the top pile section 3 to the design depth in the cement-soil mixing pile.
进一步地,在所述的步骤2)和3)中,两个桩段之间通过连接装置连接之前,将高强树脂涂抹在相应的两个对接法兰盘和凸部6上;之后再将凸部6插入,并用螺栓紧密连接两个法兰盘。Further, in the steps 2) and 3), before the two pile sections are connected by the connecting device, high-strength resin is smeared on the corresponding two butt flanges and the convex part 6; Section 6 is inserted, and the two flanges are tightly connected with bolts.
进一步地,法兰盘的螺栓孔8沿圆盘均匀分布,其直径、间距可根据施工实际需要预先定制。Further, the bolt holes 8 of the flange plate are evenly distributed along the disk, and their diameter and spacing can be customized in advance according to actual construction needs.
进一步地,在水泥土搅拌桩施工完成后3小时内需要完成各桩段之间的连接及压入工作。Further, it is necessary to complete the connection and pressing work between the various pile sections within 3 hours after the completion of the construction of the cement-soil mixing pile.
本发明的工作原理:连接装置包括上部法兰盘5、下部法兰盘7及螺栓,上部法兰盘5、下部法兰盘7均与其对应的钢套箍4预先焊接为一体。所述上部法兰盘5设置有螺栓孔8、凸部6,所述凸部6为圆环钢筒,与所述上部法兰盘5预先焊接为一体,可插入到下部法兰盘7中。所述下部法兰盘7设置有螺栓孔8,与上部法兰盘5螺栓孔8一一对应。所述螺栓将上部和下部法兰盘7连接。The working principle of the present invention: the connecting device includes an
凸部6插入下部法兰盘7,会使得桩体连接处的水平承载能力大大加强,而法兰盘会使得桩体的竖向承载性能获得极大提高。The insertion of the convex part 6 into the lower flange 7 will greatly enhance the horizontal bearing capacity of the connection of the pile body, and the flange plate will greatly improve the vertical bearing capacity of the pile body.
本发明还提供了一种用于超长劲性复合桩施工的预制管桩连接方法,所述上部法兰盘5位于上节桩段的底部,所述下部法兰盘7位于下节桩段的顶部。实际施工时,先将下节桩段压入水泥土搅拌桩中,当其顶部高于地面1米时停止压桩,此时吊起上节桩段至垂直状态,将高强树脂涂满上部法兰盘5、下部法兰盘7及凸部6,再缓慢降下,将上部法兰盘5的凸部6插入下节桩段,并将上部法兰盘5、下部法兰盘7的螺栓孔8一一对应,最后用螺栓紧密锁紧,此时即完成了桩段之间的连接。The present invention also provides a prefabricated pipe pile connection method for super-long composite pile construction, wherein the
但值得注意的是,法兰盘的外径大于圆筒形桩身外径,虽然其会提供更好的竖向承载性能,但其也会影响管桩的压入速度,因此应在水泥土搅拌桩施工完成后3小时内完成桩段的连接及压入,此时的水泥土仍有一定的流动性,在管桩压入后,水泥土仍可以与桩身紧密接触固结,桩体的侧摩阻力支承作用仍然可以得到很好地发挥。But it is worth noting that the outer diameter of the flange is larger than the outer diameter of the cylindrical pile body. Although it will provide better vertical bearing performance, it will also affect the pressing speed of the pipe pile. Therefore, it should be used in cement and soil. The connection and pressing of the pile sections are completed within 3 hours after the construction of the mixing pile is completed. At this time, the cement and soil still have a certain fluidity. The side friction resistance support function can still be well exerted.
采用劲性复合桩作为淤泥质粘土发育地区的建筑基础,柔性桩采用直径为900毫米的水泥土搅拌桩,设计长度为40米,刚性桩采用预制PHC管桩,设计长度39米,外径600毫米,壁厚130毫米。Stiff composite piles are used as the building foundation in the silty clay development area. The flexible piles are cement-soil mixing piles with a diameter of 900 mm and a design length of 40 meters. The rigid piles are prefabricated PHC pipe piles with a design length of 39 meters and an outer diameter of 600 meters. mm, wall thickness 130 mm.
参考图1~图5,施工顺序为先施作水泥土搅拌桩,施工完成后3小时内竖直压入底桩段1,在底桩段1顶部距离地面1米时,停止压入。再竖直吊起中间桩段2,将高强树脂均匀涂满上部法兰盘5、下部法兰盘7的接触位置,将中间桩段2的凸部6插入底桩段1的法兰盘7中,并使上部、下部法兰盘的螺栓孔8一一对应,再用螺栓将其紧密连接。Referring to Figures 1 to 5, the construction sequence is to first apply the cement-soil mixing pile, and press the bottom pile section 1 vertically within 3 hours after the construction is completed. When the top of the bottom pile section 1 is 1 meter from the ground, stop pressing. Then lift the middle pile section 2 vertically, apply high-strength resin evenly to the contact position of the
继续压入中间桩段2,当其顶部距离地面1米时,停止压入。竖直吊起顶桩段3,将高强树脂均匀涂满上部法兰盘5、下部法兰盘7的接触位置,将顶桩段3的凸部6插入中间桩段2的法兰盘7中,并使上部法兰盘、下部法兰盘的螺栓孔8一一对应,再用螺栓将其紧密连接,继续将顶桩段3压入至设计深度即可。Continue to press in the middle pile section 2, when its top is 1 meter from the ground, stop pressing in. Lift the top pile section 3 vertically, apply high-strength resin evenly to the contact position of the
本发明主要提供了一种用于劲性复合桩施工的预制管桩连接装置及连接方法,相比于传统的预制桩连接方法,施工更加方便、快捷,安全风险较小,同时由于凸部6圆环钢板的存在,使得桩体连接处可以承受一定的水平切向荷载,桩体整体更加牢固,且法兰盘会使得桩体侧面呈现凹凸形状,会增强桩体的竖向极限承载力,减小桩顶沉降。因此,本发明对提高劲性复合桩的承载性能具有一定的实际应用价值。The present invention mainly provides a prefabricated pipe pile connection device and connection method for stiff composite pile construction. Compared with the traditional prefabricated pile connection method, the construction is more convenient and faster, and the safety risk is smaller. The existence of the ring-shaped steel plate makes the joint of the pile body bear a certain horizontal tangential load, and the whole body of the pile body is firmer, and the flange plate will make the side of the pile body appear concave and convex shape, which will enhance the vertical ultimate bearing capacity of the pile body. Reduce pile top settlement. Therefore, the invention has certain practical application value for improving the bearing performance of the stiff composite pile.
以上的仅为本发明的较佳实施例而已,当然不能以此来限定本发明之权利范围,因此依本发明申请专利范围所作的等效变化,仍属本发明的保护范围。The above are only the preferred embodiments of the present invention, of course, the scope of the rights of the present invention cannot be limited by this, so the equivalent changes made according to the scope of the patent application of the present invention still belong to the protection scope of the present invention.
Claims (9)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010824898.XA CN111945715A (en) | 2020-08-17 | 2020-08-17 | Prefabricated pipe pile for construction of ultra-long stiff composite pile and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010824898.XA CN111945715A (en) | 2020-08-17 | 2020-08-17 | Prefabricated pipe pile for construction of ultra-long stiff composite pile and construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111945715A true CN111945715A (en) | 2020-11-17 |
Family
ID=73343242
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010824898.XA Pending CN111945715A (en) | 2020-08-17 | 2020-08-17 | Prefabricated pipe pile for construction of ultra-long stiff composite pile and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111945715A (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11140867A (en) * | 1997-11-06 | 1999-05-25 | Tenox Corp | Joint structure of prefabricated cylindrical pile |
CN104234047A (en) * | 2013-10-22 | 2014-12-24 | 王磊 | Composite pile made by jointly embedding nodular pile and tubular pile into cement-soil mixed soil-nailed pile |
KR20170130105A (en) * | 2016-05-18 | 2017-11-28 | 원병천 | Pile and the installing method thereof |
CN108442368A (en) * | 2018-05-18 | 2018-08-24 | 广西盛虎金属制品有限公司 | A kind of connector for steel-pipe pile |
KR20180135377A (en) * | 2017-06-12 | 2018-12-20 | 박명훈 | Boring casings pipe for micro-pile with connector |
CN110387877A (en) * | 2019-07-29 | 2019-10-29 | 中铁十二局集团建筑安装工程有限公司 | A kind of stiff composite pile construction technology |
CN110700274A (en) * | 2019-10-07 | 2020-01-17 | 王琪 | Mechanically-connected assembled stand column and stand column pile |
-
2020
- 2020-08-17 CN CN202010824898.XA patent/CN111945715A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11140867A (en) * | 1997-11-06 | 1999-05-25 | Tenox Corp | Joint structure of prefabricated cylindrical pile |
CN104234047A (en) * | 2013-10-22 | 2014-12-24 | 王磊 | Composite pile made by jointly embedding nodular pile and tubular pile into cement-soil mixed soil-nailed pile |
KR20170130105A (en) * | 2016-05-18 | 2017-11-28 | 원병천 | Pile and the installing method thereof |
KR20180135377A (en) * | 2017-06-12 | 2018-12-20 | 박명훈 | Boring casings pipe for micro-pile with connector |
CN108442368A (en) * | 2018-05-18 | 2018-08-24 | 广西盛虎金属制品有限公司 | A kind of connector for steel-pipe pile |
CN110387877A (en) * | 2019-07-29 | 2019-10-29 | 中铁十二局集团建筑安装工程有限公司 | A kind of stiff composite pile construction technology |
CN110700274A (en) * | 2019-10-07 | 2020-01-17 | 王琪 | Mechanically-connected assembled stand column and stand column pile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104018518B (en) | The method of prefabricated diaphragm wall and construction outer wall of basement and floor | |
CN103485334B (en) | Bi-layer plastic-bushing inverted-arch cambered hollow special-shaped pile and construction method | |
CN102605767A (en) | Precast pile reserved with grouting pipe and piling process of precast pile | |
CN107035159A (en) | A kind of method suitable for frame structure isolated footing building underground increasing layer | |
CN107642041A (en) | Super large diameter hollow pile group anchorage | |
CN110593303B (en) | Prefabricated reinforced concrete fixed buttress for thermal pipeline and construction method | |
CN102286982A (en) | Deep foundation pit precast building enclosure for constructing in low environment | |
CN204000925U (en) | Prefabricated diaphragm wall | |
CN107642040A (en) | Construction method of super large diameter hollow pile group anchorage | |
CN111945715A (en) | Prefabricated pipe pile for construction of ultra-long stiff composite pile and construction method | |
CN109137924B (en) | Structure for reducing pile length of deep soft soil layer by forming composite foundation and construction method | |
CN111101509A (en) | Prefabricated root type pile structure and construction method | |
CN112814016B (en) | A double-conical onshore wind turbine foundation | |
CN117488769A (en) | Static pressure pore-forming vibration impact solid sand pebble expanding grouting and static pressure pile technology | |
CN216041287U (en) | Assembled spiral anchor foundation | |
CN216893135U (en) | Assembled concrete connection structure through segmentation rebar connection | |
CN114232892B (en) | Fabricated concrete connection structure connected through segmented reinforcing steel bars and construction method thereof | |
CN215482904U (en) | Multi-section type prestressed hollow pile | |
CN213233417U (en) | Combined pile and combined foundation | |
CN201857608U (en) | Synthetic pile | |
CN214614035U (en) | High-strength prestressed concrete composite pile | |
CN213836719U (en) | Spliced prefabricated root key type digging foundation | |
CN205012327U (en) | Partially prefabricated friction pile | |
CN213173700U (en) | Precast pile for soft foundation treatment | |
CN113174967A (en) | Rotary-digging deep-stirring large-diameter stiff composite pile structure and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |