Potential energy biological sewage purifier
Technical Field
The invention belongs to the technical field of sewage treatment, and particularly relates to a potential energy biological sewage purifier.
Background
At present, advanced biological treatment technology combining activated sludge and biological contact oxidation technology is mainly adopted for sewage at home and abroad, so that the treated water quality can reach the standard of reuse water, but in the sewage treatment technology, an aeration method of blast is mainly adopted in an aerobic process, so that reoxygenation efficiency is low, energy consumption is high, and running cost is high. The Chinese patent with the application number of CN20052056065. X discloses a potential energy oxygenation ecological bed, wherein an aerator is arranged at one end of an ecological riverbed or turf, the other end of the ecological riverbed or turf is a water tank for receiving a sewage water inlet pump pipe or a water tank for receiving water discharged by the upper layer of aerator, a siphon water suction port is arranged at the inlet of the lower part of the aerator, the effective water head of a water pump is fully utilized, potential energy is converted into kinetic energy through siphoning to carry out large oxygen reoxygenation and blowing-off, and the potential energy consumption of aeration can be reduced, but the problems of short residence time of sewage on each ecological bed, poor sewage treatment effect, higher energy consumption, easiness in breeding mosquitoes and flies around a biological turntable and the like exist.
For this reason, improvements to existing sewage treatment apparatuses are required in order to solve the above problems.
Disclosure of Invention
In order to solve the technical problem in the current sewage treatment, the invention provides a potential energy biological sewage purifier, which utilizes a plurality of layers of potential energy biological sewage purifying box bodies arranged up and down to intermittently pass sewage through a bacterial bed, reduce COD, BOD, N-NH 3 in the sewage, and accurately control the reoxygenation period by utilizing the buoyancy of water through adding a delay box assembly, so that the reoxygenation period can be accurately and rapidly regulated, and the denitrification and dephosphorization efficiency is further improved.
The invention adopts the following technical scheme:
the potential energy biological sewage purifier comprises a plurality of layers of potential energy biological sewage purifying box bodies which are arranged up and down;
the odd-layer potential energy biological sewage purifying box body and the even-layer potential energy biological sewage purifying box body are respectively separated by two water baffle assemblies which are arranged at two ends side by side to form a first purifier box body area, a second purifier box body area and a third purifier box body area;
The purifier box body area I, the purifier box body area II and the purifier box body area III in the odd-layer potential energy biological sewage purification box body are sequentially arranged from left to right;
the third area of the purifier box body of the odd-layer potential energy biological sewage purifying box body is communicated with the first area of the purifier box body of the even-layer potential energy biological sewage purifying box body through a purifier box body assembly;
The three areas of the purifier box body of the odd-layer potential energy biological sewage purifying box body and the three areas of the purifier box body of the even-layer potential energy biological sewage purifying box body are respectively provided with a floating box assembly;
The floating box assembly comprises a floating box body, floating capable of moving up and down is arranged in the floating box body, and the bottom end of the floating box body is fixedly arranged in a three-zone of the purifier box body through a floating box assembly bracket;
A floating box water outlet is formed in a bottom plate of the floating box body, a floating groove is formed in the position, opposite to the Ying Piao floating box water outlet, of the lower surface of the floating box body, a floating box water stop ball assembly is arranged in the floating groove, and the floating box water stop ball assembly can move up and down and can seal or open the floating box water outlet;
The purifier box assembly comprises a clamping groove arranged on the lower surface of the three areas of the purifier box and a purifier box water outlet groove arranged on the lower surface of the clamping groove, a purifier box water outlet is arranged at the position, corresponding to the floating box, of the bottom plate of the three areas of the purifier box, and a purifier box water outlet sealing plate is arranged at the position of the purifier box water outlet;
a bottom plate of the water outlet groove of the purifier box body is provided with a plurality of parallel purifier box body water-splitting long holes;
A fungus bed and a fungus bed fixing frame assembly are arranged in a second region of the purifier box body of the potential biological sewage purifying box body of each layer, and the fungus bed is fixed in the second region of the purifier box body through the fungus bed fixing frame assembly;
A delay box assembly is arranged in a first area of the purifier box body of the odd-layer potential energy biological sewage purifying box body;
The delay box assembly comprises a delay box fixedly arranged on the upper surface of the first area of the purifier box body, and a delay water leakage pipe, wherein a through hole is arranged at the position corresponding to the delay water leakage pipe on the first area of the purifier box body;
the top end of the delay box is open, a delay float is arranged in the delay box, one side of the delay float is hinged with the opening at the top end of the delay box, a delay box water outlet is arranged on the bottom plate of the delay box, a blocking float is arranged at the position of the delay box water outlet, a pull rod assembly is arranged at the top end of the delay float, and the delay float blocks or opens a delay water leakage pipe through the pull rod assembly.
Furthermore, the potential energy biological sewage purifying box bodies of each layer are arranged in a staggered mode, so that the fungus beds can be conveniently taken out, filled and cleaned.
Further, a vertical upward guide pipe is arranged in the middle of the bottom of the floating box body, the floating box body is I-shaped, a through hole penetrating through the floating box body from top to bottom is formed in the middle of the floating box body, the guide pipe penetrates into the floating through hole from bottom to top, a floating box fixing frame in the shape of a Chinese character 'ji' is arranged at the floating top end, a screw rod is arranged on the floating box fixing frame, the screw rod penetrates into the guide pipe from top to bottom, the floating box fixing frame and the screw rod can move up and down along the guide pipe, the floating box fixing frame and the screw rod are used for limiting the floating moving position, and the floating box fixing frame and the screw rod are prevented from shifting leftwards and rightwards in the moving process.
Further, the floating box water stop ball assembly comprises a floating box water stop ball, a connecting rod is arranged at the bottom end of the floating box water stop ball, the bottom end of the connecting rod penetrates through the bottom of the floating tank, and a floating box water stop floating body is arranged at the tail end of the connecting rod.
Further, a purifier box water outlet shaft which can penetrate through the guide pipe is arranged at the top end of the purifier box water outlet sealing plate.
Further, the clamping groove is arranged right below the floating box body.
Further, the bottom plate lower surface of purifier box play basin is equipped with the purifier box play water bottom plate strengthening rib of perpendicular to purifier box play water slot hole extending direction, and purifier box play water bottom plate strengthening rib is used for strengthening the intensity of purifier box play bottom plate of basin, prevents to use the deformation that leads to the bottom plate of purifier box play basin for a long time.
Furthermore, the fungus beds are in a plurality of rectangular plates which are arranged side by side, the fungus beds extend along the front-back direction, gaps are formed between the fungus beds, the fungus beds have pore structures, the specific surface area of the fungus beds ranges from 1000 to 6000, and the fungus beds are carriers of biological bacteria and are used for reducing COD, BOD, N-NH 3 in sewage and further improving the denitrification and dephosphorization efficiency.
Further, the fungus bed fixing frame assembly comprises a fungus bed hook fixing frame, a fungus bed straight hook blocking frame and a fungus bed fixing frame plate, wherein the fungus bed hook fixing frame is connected with the bottom end of a fungus bed in a clamping mode, the fungus bed straight hook blocking frame is arranged on one side of the fungus bed hook fixing frame, the fungus bed fixing frame plate is arranged at the bottom end of the fungus bed hook fixing frame and is detachably connected with the second area of the purifier box body, threaded holes are formed in the bottom end of the fungus bed fixing frame plate and the second area of the purifier box body, detachable connection is achieved through penetrating bolts, and the fungus bed is fixed on the upper surface of the second area of the purifier box body through the fungus bed fixing frame assembly.
Furthermore, the bacterial bed can be fixed on the upper surface of the second area of the purifier box body of the potential biological sewage purifying box body by utilizing the bacterial bed fixing frame assembly, and can be hung on the lower bottom surface of the potential biological sewage purifying box body of the upper layer or hung on the side end of the potential biological sewage purifying box body of the upper layer.
Further, the time delay box assembly is positioned above the floating box assembly of the lower potential energy biological sewage purifying box body.
Further, the tail end of the pull rod assembly is provided with a delay ball, the delay ball is positioned above the delay water leakage pipe, and the delay ball periodically opens and closes the delay water leakage pipe under the action of floating force.
Further, the bottom of the first area of the purifier box body of the odd-layer potential energy biological sewage purifying box body is also provided with a lower water control mechanism corresponding to the third area of the purifier box body of the even-layer potential energy biological sewage purifying box body;
The lower water control mechanism comprises a plugging ball water leakage pipe arranged at the bottom of a first area of the odd-layer potential energy biological sewage purification box body purifier, a three-way pipe fitting communicated with the plugging ball water leakage pipe is arranged at the bottom end of the plugging ball water leakage pipe, a three-way water outlet pipe is connected to a branch port of the three-way pipe fitting, a plugging ball connecting rod is arranged in the plugging ball water leakage pipe in a penetrating manner, the top end of the plugging ball connecting rod penetrates out of the plugging ball water leakage pipe upwards, a plugging ball is arranged at the top end of the plugging ball connecting rod, the bottom end of the plugging ball connecting rod penetrates through the plugging ball water leakage pipe and the three-way pipe fitting downwards in sequence and penetrates out of a bottom end outlet of the three-way pipe fitting, and a plugging ball control float is arranged at the bottom end of the plugging ball connecting rod.
Further, the plugging ball is positioned in the first area of the purifier box body of the odd-layer potential energy biological sewage purifying box body, the plugging ball is controlled to float in the third area of the purifier box body of the even-layer potential energy biological sewage purifying box body, and the water outlet end of the three-way water outlet pipe extends into the third area of the purifier box body of the even-layer potential energy biological sewage purifying box body.
The beneficial effects of the invention are as follows:
1. the potential energy biological sewage purifier utilizes a plurality of layers of potential energy biological sewage purifying box bodies arranged up and down, enables sewage to intermittently pass through a fungus bed, reduces COD, BOD, N-NH 3 in the sewage, precisely controls the reoxygenation period by utilizing the buoyancy of water through additionally arranging the delay box assembly, can accurately and quickly adjust the reoxygenation period, and has the advantages of high denitrification and dephosphorization efficiency, strong impact load resistance, stable operation and the like.
2. In the running process, the potential energy is utilized to lead sewage to intermittently pass through the potential energy biological sewage purifier and then carry out the reoxygenation and the blowing-off of the large oxygen.
3. When the potential energy biological sewage purifier adopts the 6-layer potential energy biological sewage purifying box body, the potential energy biological sewage purifier can reach the first-level A standard of pollutant emission standard of urban sewage treatment plants (GB 18918-2002). When the 8-10-layer potential energy biological sewage purifying box body is adopted, the main standard of class III water on the surface of the earth can be achieved in the quality standard of urban surface water environment (GB 3838-2002). The potential energy bioenergy biological sewage purifier disclosed by the invention not only can be suitable for treating urban domestic sewage, but also is suitable for treating and recycling high-concentration sewage, has wide adaptability to sewage treatment and resource utilization, can be fully automatically controlled without special management, and has good economic benefit and environmental benefit.
Drawings
FIG. 1 is a front cross-sectional view of the present invention;
FIG. 2 is a top view of the present invention;
FIG. 3 is a cross-sectional view of section A-A of FIG. 2;
FIG. 4 is a section B-B of FIG. 2;
FIG. 5 is a cross-sectional view of FIG. 1 taken along line C-C;
FIG. 6 is a sectional view of the D-D view of FIG. 1
The device is characterized by comprising a first-layer potential biological sewage purification box body 1, a second-layer potential biological sewage purification box body 2, a floating box assembly 3, a screw rod 3-1, a floating box fixing frame 3-2, a floating 3-3, a floating box assembly support 3-5, a floating box water stop ball 3-6, a floating box water stop floating body 3-7, a floating box water outlet 3-8, a purifier box body one area 4-1, a purifier box body two area 4-2, a purifier box body three area 4-3, a water baffle assembly 5, a fungus bed 6, a fungus bed fixing frame assembly 7, a fungus bed hook fixing frame 7-1, a fungus bed straight hook blocking frame 7-2, a fungus bed fixing frame plate 7-3, a purifier box body assembly 8, a purifier box body water outlet shaft 8-1, a purifier box body water outlet 8-2, a purifier box body water outlet groove bottom plate 8-4, a purifier box body water outlet bottom plate reinforcing rib 8-5, a purifier box body 8-6, a filter box body long hole 8-6, a water delay ball 9-10, a three-way pipe assembly 9, a three-way pipe 10, a three-way pipe assembly 9, a three-way pipe assembly 9, a delay ball 9 and a three-way pipe assembly 9, a sealing plug, and a three-way pipe assembly 9-10, and a sealing plug.
Detailed Description
The present invention is described in detail below by way of examples for better understanding of the present invention, and therefore the examples are not to be construed as limiting the present invention.
In the description of the present invention, it should be noted that, for the azimuth words such as "center", "lateral", "longitudinal", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", etc., the azimuth and positional relationships are based on the azimuth or positional relationships shown in the drawings, it is merely for convenience of describing the present invention and simplifying the description, and it is not to be construed as limiting the specific scope of protection of the present invention that the device or element referred to must have a specific azimuth configuration and operation.
It should be noted that the terms "first," "second," and the like in the description and in the claims are used for distinguishing between similar objects and not necessarily for describing a particular sequential or chronological order. It is to be understood that the data so used may be interchanged where appropriate in order to describe the embodiments of the application herein.
Example 1
As shown in fig. 1-6, a potential biological sewage purifier comprises a plurality of potential biological sewage purifying tanks arranged up and down (each potential biological sewage purifying tank is a standard layer), specifically, even potential biological sewage purifying tanks are arranged at the front position below the odd potential biological sewage purifying tanks, namely, each potential biological sewage purifying tank is arranged in a staggered manner;
for convenience of explanation, the drawings of the present invention only show the first-layer potential biological sewage purifying tank 1 (odd-layer potential biological sewage purifying tank) and the second-layer potential biological sewage purifying tank 2 (even-layer potential biological sewage purifying tank), and the connection relationship of the components and the operation principle between the upper and lower adjacent potential biological sewage purifying tanks are described below;
the first-layer potential biological sewage purifying box 1 and the second-layer potential biological sewage purifying box 2 are respectively separated by two water baffle assemblies 5 which are arranged at two ends side by side to form a first purifier box region 4-1, a second purifier box region 4-2 and a third purifier box region 4-3, and the difference is that the first purifier box region 4-1, the second purifier box region 4-2 and the third purifier box region 4-3 in the first-layer potential biological sewage purifying box 1 are sequentially arranged from left to right, the first purifier box region 4-1, the second purifier box region 4-2 and the third purifier box region 4-3 in the second-layer potential biological sewage purifying box 2 are sequentially arranged from right to left, and the third purifier box region 4-3 of the first-layer potential biological sewage purifying box 1 is communicated with the first purifier box region 4-1 of the second-layer potential biological sewage purifying box 2 by the purifier box assemblies 8;
As shown in fig. 2, a three-zone 4-3 of the purifier box body of the first-layer potential biological sewage purifying box body 1 and a three-zone of the purifier box body of the second-layer potential biological sewage purifying box body 2 are respectively provided with a floating box assembly 3;
As shown in fig. 1-2, the floating box assembly 3 comprises a floating box body 3-4 with an open top, a vertical upward guide pipe is arranged in the middle of the bottom of the floating box body 3-4, an I-shaped floating 3-3 is arranged in the floating box body 3-4, a through hole penetrating through the floating 3-3 from top to bottom is arranged in the middle of the floating 3-3, the guide pipe penetrates into the through hole of the floating 3-3 from bottom to top, a floating box fixing frame 3-2 in a shape of a Chinese character 'ji' is arranged at the top of the floating 3-3, a screw rod 3-1 is arranged on the floating box fixing frame 3-2, and the screw rod 3-1 penetrates into the guide pipe from top to bottom;
As shown in fig. 1 and 4, a bottom plate of a floating box body 3-4 is provided with a floating box water outlet 3-8, a floating groove is arranged on the lower surface of the floating box body 3-4 at the position corresponding to Ying Piao floating box water outlet 3-8, a floating box water stop ball 3-6 is arranged in the floating groove, a connecting rod is arranged at the bottom end of the floating box water stop ball 3-6, the bottom end of the connecting rod penetrates through the bottom of the floating groove, and a floating box water stop floating body 3-7 is arranged at the tail end of the connecting rod;
As shown in fig. 1-4, the purifier box assembly 8 comprises a clamping groove arranged on the lower surface of the three-zone 4-3 of the purifier box and a purifier box water outlet groove arranged on the lower surface of the clamping groove, wherein the clamping groove is arranged right below the floating box 3-4, a purifier box water outlet 8-3 is arranged at the position, corresponding to the floating box 3-4, of the bottom plate of the three-zone 4-3 of the purifier box, a purifier box water outlet sealing plate 8-2 is arranged at the position of the purifier box water outlet 8-3, and a purifier box water outlet shaft 8-1 capable of penetrating through a guide pipe is arranged at the top end of the purifier box water outlet sealing plate 8-2;
The bottom plate 8-4 of the purifier box body water outlet groove is provided with a plurality of purifier box body water outlet long holes 8-6 which are arranged in parallel, the lower surface of the bottom plate 8-4 of the purifier box body water outlet groove is provided with a purifier box body water outlet bottom plate reinforcing rib 8-5 which is perpendicular to the extending direction of the purifier box body water outlet long holes 8-6, and the purifier box body water outlet bottom plate reinforcing rib 8-5 is used for reinforcing the strength of the bottom plate 8-4 of the purifier box body water outlet groove and preventing the bottom plate 8-4 of the purifier box body water outlet groove from deforming after long-term use;
as shown in fig. 2-3, a fungus bed 6 and a fungus bed fixing frame assembly 7 are arranged in a purifier box body two-zone 4-2 of the potential biological sewage purifying box body of each layer;
The bacterial beds 6 are in a plurality of rectangular plates which are arranged side by side, the bacterial beds 6 extend along the front and rear directions, gaps are formed among the bacterial beds 6, the bacterial beds 6 are in pore structures, the specific surface area of the bacterial beds 6 is 1000-6000, and the bacterial beds 6 are carriers of biological bacteria and are used for reducing COD, BOD, N-NH 3 in sewage, so that the nitrogen and phosphorus removal efficiency is further improved;
The fungus bed fixing frame assembly 7 comprises a fungus bed hook fixing frame 7-1, a fungus bed straight hook blocking frame 7-2 and a fungus bed fixing frame plate 7-3, wherein the fungus bed hook fixing frame 7-1 is clamped with the bottom end of the fungus bed 6, the fungus bed straight hook blocking frame 7-2 is arranged on one side of the fungus bed hook fixing frame 7-1, the fungus bed fixing frame plate 7-3 is arranged at the bottom end of the fungus bed hook fixing frame 7-1, the bottom end of the fungus bed fixing frame plate 7-3 is detachably connected with the two areas 4-2 of the purifier box body, and the fungus bed 6 is fixed on the upper surface of the two areas 4-2 of the purifier box body through the fungus bed fixing frame assembly 7.
As shown in fig. 2-3, a delay box assembly 9 is arranged in a first zone 4-1 of the purifier box body of the first-layer potential biological sewage purifying box body 1 (odd-layer potential biological sewage purifying box body), and the delay box assembly 9 is positioned above a floating box assembly 3 of the lower-layer potential biological sewage purifying box body;
The delay box assembly 9 comprises a delay box 9-2 and a delay water leakage pipe 9-7 arranged on one side of the delay box 9-2, wherein the bottom end of the delay box 9-2 is fixed on the upper surface of the first area 4-1 of the purifier box body through a bracket, the delay water leakage pipe 9-7 is fixed on the upper surface of the first area 4-1 of the purifier box body, and a through hole is arranged on the first area 4-1 of the purifier box body corresponding to the position of the delay water leakage pipe 9-7;
The top end of the delay box 9-2 is open, a delay float 9-1 is arranged in the delay box 9-2, one side of the delay float 9-1 is hinged to the opening of the top end of the delay box 9-2, a pull rod assembly 9-5 is arranged at the top end of the delay float 9-1, a delay ball 9-6 is arranged at the tail end of the pull rod assembly 9-5, the delay ball 9-6 is positioned above the delay water leakage pipe 9-7, a delay box water outlet 9-3 is arranged on the bottom plate of the delay box 9-2, a blocking float 9-4 is arranged at the delay box water outlet 9-3, and the delay water leakage pipe 9-7 is periodically opened and closed through the effect of the delay ball 9-6 due to water float.
When sewage flows into the first-layer potential energy biological sewage purifying box body 1 (odd-layer potential energy biological sewage purifying box body), the blocking float 9-4 rises to block the delay box water outlet 9-3 along with the rising of the water level, and then the sewage flows into the buoyancy box assembly 3 of the next layer through the delay water leakage pipe 9-7, and flows into the delay box 9-2 along with the rising of the water level. The delay float 9-1 moves upwards under the action of water buoyancy, the delay float 9-1 rotates to enable the delay ball 9-6 on the pull rod assembly 9-5 to move downwards, and the delay water leakage pipe 9-7 is plugged. When the first-layer potential energy biological sewage purifying box body 1 (odd-layer potential energy biological sewage purifying box body) is used for discharging sewage from a full state, the delay float 9-1 seals the water leakage pipe 9-7 under the action of the buoyancy of the sewage in the delay box 9-2 along with the descending of the water level, the blocking float 9-4 moves downwards along with the descending of the water level to open the water outlet 9-3 of the delay box, the sewage in the delay box is discharged, the delay float 9-1 moves downwards, the delay float 9-1 rotates to enable the delay ball 9-6 on the pull rod assembly 9-5 to move upwards, and the delay water leakage pipe 9-7 is opened.
Each layer of potential energy biological sewage purifying box body can be designed to be 3-30 minutes delayed according to the needs.
The water inlet between adjacent layers of potential biological sewage purifying tanks is controlled by the buoyancy tank assembly 3 of the adjacent layers, and the water outlet of the purifier tank assembly 8 is controlled by the time delay tank assembly 9 of the adjacent layers acting on the buoyancy tank assembly 3 of the layer.
The potential energy biological sewage purifying box bodies of all layers are arranged in a staggered mode, so that the bacterial bed 6 can be conveniently taken out, filled and cleaned. The bacterial bed 6 can be fixed by fixing the bacterial bed 6 on the upper surface of the second section 4-2 of the purifier of the potential biological sewage purifying box by using the bacterial bed fixing frame assembly 7, or by hanging the bacterial bed 6 on the lower bottom surface of the upper potential biological sewage purifying box or on the side end of the potential biological sewage purifying box.
As shown in fig. 6, the lower water control mechanism is further arranged at the bottom of the first-layer potential biological sewage purifying box 1 (odd-layer potential biological sewage purifying box) at the position corresponding to the third-layer potential biological sewage purifying box 2 (even-layer potential biological sewage purifying box);
The lower water control mechanism comprises a plugging ball water leakage pipe 10-3 arranged at the bottom of a first-layer potential energy biological sewage purification box body 1 in a first area 4-1, a three-way pipe fitting 10-4 communicated with the plugging ball water leakage pipe 10-3 is arranged at the bottom end of the plugging ball water leakage pipe 10-3, a three-way water outlet pipe 10-5 is connected to a branch port of the three-way pipe fitting 10-4, a plugging ball connecting rod 10-2 is penetrated into the plugging ball water leakage pipe 10-3, the top end of the plugging ball connecting rod 10-2 penetrates out of the plugging ball water leakage pipe 10-3 upwards, the top end of the plugging ball connecting rod 10-2 is provided with a plugging ball 10-1, the bottom end of the plugging ball connecting rod 10-2 penetrates through the plugging ball water leakage pipe 10-3 and the three-way pipe fitting 10-4 in sequence, a ball control float 10-6 is arranged at the bottom end outlet of the three-way pipe fitting 10-4 in the first-layer biological sewage purification box body 1, the plugging ball control float 10-6 is positioned in the second-layer biological sewage purification box body in the first area 4-1, the plugging ball control float 10-6 is positioned at the bottom end of the third-layer biological sewage purification box body in the second-2 in the potential energy biological sewage purification box body, and the three-layer of the water outlet pipe extends out of the third-layer biological sewage purification box body 2.
The plugging ball connecting rod 10-2 can move downwards in the three-way pipe fitting 10-4 along with the buoyancy force born by the plugging ball control float 10-6, and the plugging ball 10-1 plugs the plugging ball water leakage pipe 10-3 downwards under the action of gravity in the state that no water exists in the first area 4-1 of the purifier box body of the first-layer potential biological sewage purifying box body 1. The lower water control mechanism is arranged at the bottom of the first zone 4-1 of the purifier box body of the first-layer potential biological sewage purification box body 1, so that the mode that the lower potential biological sewage purification box body controls water inlet and water outlet of the upper potential biological sewage purification box body between the potential biological sewage purification box bodies of two adjacent layers can be realized.
The operation principle is that sewage flows into a first purifier box body area 4-1 (shown in figure 1) at the left side of a first layer of potential biological sewage purifying box body 1 (odd layer potential biological sewage purifying box body) through a water feeding device of the potential biological sewage purifier, and the sewage sequentially flows through the first purifier box body area 4-1, a water baffle assembly 5, a second purifier box body area 4-2, a plurality of groups of bacterial beds 6, the water baffle assembly 5 and a third purifier box body area 4-3 in the second purifier box body area 4-2.
Along with the continuous inflow of water flow into the first-layer potential energy biological sewage purification box body 1 in the first-layer potential energy biological sewage purification box body 4-1, the water level in the first-layer potential energy biological sewage purification box body 1 rises, the plugging float 9-4 of the delay box assembly 9 rises to plug the delay box water outlet 9-3, sewage enters the delay box 9-2, and the delay float 9-1 seals the water leakage pipe 9-7 under the action of sewage buoyancy in the delay box 9-2.
The water level in the first-layer potential energy biological sewage purifying box body 1 continuously rises, and the floating box water stop ball 3-6 of the floating box assembly 3 floats along with the floating box water stop floating body 3-7 to block the water outlet 3-8 of the floating box.
The water level in the first-layer potential energy biological sewage purifying box body 1 continuously rises, sewage enters the floating box body 3-4 of the floating box assembly 3, along with the rising of the water level in the floating box body 3-4, the floating 3-3 rises along the guide pipe, meanwhile, the purifier box body water outlet sealing plate 8-2 is driven to rise, the purifier box body water outlet 8-3 is opened, the sewage in the first-layer potential energy biological sewage purifying box body 1 (odd-layer potential energy biological sewage purifying box body) flows through the purifier box body water outlet 8-3 through the purifier box body long hole 8-6, dissolved oxygen is increased in a water splitting mode, DO reaches 6mg/L, and the sewage flows into the purifier box body one zone 4-1 on the right side of the second-layer potential energy biological sewage purifying box body 2 (even-layer potential energy biological sewage purifying box body).
The water level in the first-layer potential energy biological sewage purifying box body 1 is lowered, the plugging float 9-4 is moved downwards to open the water outlet 9-3 of the delay box, sewage in the delay box 9-2 is discharged, the delay float 9-1 is rotated to enable the delay ball 9-6 on the pull rod assembly 9-5 to move upwards, the sewage flows into the floating box assembly 3 in the second-layer potential energy biological sewage purifying box body 2, the floating 3-3 is lifted along the guide pipe along with the rising of the water level of the floating box body 3-4, the purifier box body water outlet sealing plate 8-2 is driven to rise at the same time, the purifier box body water outlet 8-3 is opened, the sewage in the first-layer potential energy biological sewage purifying box body 1 flows through the purifier box body water outlet 8-3 to be discharged through the purifier box body water long hole 8-6, and accordingly the purifier box body water outlet 8-3 of the second-layer potential energy biological sewage purifying box body is controlled to discharge water.
The water level in the first-layer potential energy biological sewage purifying box body 1 continuously descends, the floating box water stop floating body 3-7 descends with the floating box water stop ball 3-6 to open the sealed floating box water outlet 3-8, so that sewage in the floating box body 3-4 in the floating box assembly 3 is discharged into the purifier box body three region 4-3 of the first-layer potential energy biological sewage purifying box body 1 from the floating box water outlet 3-8 and flows into the purifier box body one region 4-1 of the second-layer potential energy biological sewage purifying box body 2 through the purifier box body water outlet 8-3 and the purifier box body long hole 8-6. And sewage enters the third-layer potential energy biological sewage purifying box body through the second-layer potential energy biological sewage purifying box body in the same mode, and finally flows through the potential energy biological sewage purifying box bodies in each layer in sequence.
Further, between the potential energy biological sewage purifying box bodies of two adjacent layers, the potential energy biological sewage purifying box bodies of the lower layer can control the water inlet and the water outlet of the potential energy biological sewage purifying box bodies of the upper layer, and the potential energy biological sewage purifying box bodies of the lower layer are specifically:
When the upper potential energy biological sewage purification box body starts to inject water into the lower potential energy biological sewage purification box body in a large quantity through the long hole 8-6 of the purifier box body, the blocking ball 10-1 closes the blocking ball water leakage pipe 10-3 by means of self weight, the blocking ball control float 10-6 is subjected to buoyancy along with the rising of the water level of the lower potential energy biological sewage purification box body, so that the blocking ball 10-1 is driven to open the blocking ball water leakage pipe 10-3, and the upper potential energy biological sewage purification box body starts to inject water into the floating box body 3-4 of the floating box assembly of the lower potential energy biological sewage purification box body slowly through the blocking ball water leakage pipe 10-3. At this time, the upper potential energy biological sewage purifying box body is injected with a large amount of water to the lower upper potential energy biological sewage purifying box body through the long hole 8-6 of the water, and simultaneously, the upper potential energy biological sewage purifying box body is slowly injected into the floating box body 3-4 of the floating box assembly in the lower upper potential energy biological sewage purifying box body through the plugging ball water leakage pipe 10-3, and the two water injection modes have the time difference required to control the stay on the process design requirement, and the time difference can be adjusted by changing the relative position of the plugging ball control float 10-6 fixed at the lower end of the plugging ball connecting rod 10-2.
After the water level of the floating box body 3-4 of the lower potential energy biological sewage purifying box body floating box assembly rises to a set height, the floating box body 3-3 rises along the guide pipe and drives the purifier box body water outlet sealing plate 8-2 to rise, the purifier box body water outlet 8-3 is opened, sewage in the potential energy biological sewage purifying box body 1 passes through the purifier box body water outlet 8-3, and flows into the lower potential energy biological sewage purifier from the purifier box body water splitting slot 8-6.
The foregoing is merely a preferred embodiment of the present application, and what is not described in detail in the present specification belongs to the technology known to those skilled in the art. Various changes and modifications to the present application may be made by one skilled in the art after reading the description herein, and such equivalents are intended to fall within the scope of the application as defined in the appended claims. Therefore, the protection scope of the present application should be subject to the protection scope of the claims.