CN111910923A - Integral hoisting type hoisting platform - Google Patents

Integral hoisting type hoisting platform Download PDF

Info

Publication number
CN111910923A
CN111910923A CN202010796382.9A CN202010796382A CN111910923A CN 111910923 A CN111910923 A CN 111910923A CN 202010796382 A CN202010796382 A CN 202010796382A CN 111910923 A CN111910923 A CN 111910923A
Authority
CN
China
Prior art keywords
guide plate
plate
inner template
connecting rod
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010796382.9A
Other languages
Chinese (zh)
Inventor
高渭泉
祝文飞
彭辉
梁凯辉
姚木平
谢延义
徐�明
李越
童超
谭宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGMEN ZHITE NEW MATERIAL TECHNOLOGY Co.,Ltd.
Original Assignee
Jiangxi Zhite New Material Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangxi Zhite New Material Co ltd filed Critical Jiangxi Zhite New Material Co ltd
Priority to CN202010796382.9A priority Critical patent/CN111910923A/en
Publication of CN111910923A publication Critical patent/CN111910923A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/28Climbing forms, i.e. forms which are not in contact with the poured concrete during lifting from layer to layer and which are anchored in the hardened concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Moulds, Cores, Or Mandrels (AREA)

Abstract

本发明涉及建筑领域,特别涉及到一种整体吊升式吊装平台。包括本体,所述本体上设有支撑板和与支撑板侧边数量相等的内模板组,两两相邻的内模板组之间设有方向引导柱,所述方向引导柱上设有调节装置,所述调节装置分别与两两相邻的内模板组相连,当所述调节装置被执行时,所述内模板组沿方向引导柱引导的方向向支撑板中心靠近或远离。通过内模板组、方向引导柱和调节装置实现了对不同截面尺寸的筒子型现浇剪力墙的装模和脱模,通过内模板组可根据现场需要可任意调节平台大小,调节方便,且可以重复使用,适应不同截面尺寸筒子型现浇剪力墙模板施工。

Figure 202010796382

The invention relates to the field of construction, in particular to an integral hoisting type hoisting platform. Including a body, the body is provided with a support plate and an inner template group equal in number to the side of the support plate, a direction guide column is arranged between two adjacent inner template groups, and an adjustment device is arranged on the direction guide column , the adjustment devices are respectively connected with two adjacent inner template groups, when the adjustment devices are executed, the inner template groups approach or move away from the center of the support plate along the direction guided by the directional guide columns. Through the inner formwork group, the direction guide column and the adjusting device, the moulding and demoulding of the cast-in-situ shear walls of different section sizes are realized. It can be reused to adapt to the construction of cast-in-place shear wall formwork of different section sizes.

Figure 202010796382

Description

一种整体吊升式吊装平台An integral hoisting hoisting platform

【技术领域】【Technical field】

本发明涉及建筑领域,特别涉及到一种整体吊升式吊装平台。The invention relates to the field of construction, in particular to an integral hoisting type hoisting platform.

【背景技术】【Background technique】

建筑施工中,经常遇到各种形状和不同截面尺寸的筒子型现浇剪力墙,通常会搭设筒形的内模板平台以便混凝土浇注成型。然而,由于施工空间较小,电梯井模/筒形的内模板平台无论是安装或者拆除都比较复杂。在传统的高层建筑的施工中,常规上采用落地式脚手架进行施工,这种施工方法在装模和拆模的施工过程相当繁杂,劳动强度大,工作效率低,且随着楼层的增高,落地脚手架的搭设、使用和拆除存在较大的安全隐患。In construction, we often encounter tube-shaped cast-in-situ shear walls of various shapes and different cross-sectional dimensions, and a cylindrical inner formwork platform is usually set up for concrete casting. However, due to the small construction space, the elevator shaft formwork/tubular inner formwork platform is more complicated to install or remove. In the construction of traditional high-rise buildings, floor-standing scaffolding is conventionally used for construction. This construction method is quite complicated in the construction process of formwork and formwork removal, with high labor intensity and low work efficiency. The erection, use and dismantling of scaffolding have great potential safety hazards.

【发明内容】[Content of the invention]

本发明的目的在于针对现有技术的缺陷和不足,提供一种提高工程质量、加快施工速度、提高劳动生产率、降低工程成本的整体吊升式吊装平台。The purpose of the present invention is to provide an integral hoisting hoisting platform that improves the quality of the project, accelerates the construction speed, improves the labor productivity and reduces the cost of the project, aiming at the defects and deficiencies of the prior art.

针对上述的问题,本发明采用以下技术方案:For the above-mentioned problems, the present invention adopts the following technical solutions:

一种整体吊升式吊装平台,包括本体,所述本体上设有支撑板和与支撑板侧边数量相等的内模板组,两两相邻的内模板组之间设有方向引导柱,所述方向引导柱顶部设有吊环,所述方向引导柱上设有调节装置,所述调节装置分别与两两相邻的内模板组相连,当所述调节装置被执行时,所述内模板组沿方向引导柱引导的方向向支撑板中心靠近或远离,所述支撑板上设有多根加强杆组,所述加强杆组上设有多个与墙体内部预设的定位小盒配合连接的摆腿,所述加强杆组上设有若干个使支撑板活动安装在内模板组上的悬挂装置。An integral hoisting type hoisting platform includes a main body on which a support plate and inner formwork groups equal in number to the side of the support plate are arranged, and a direction guide column is arranged between two adjacent inner formwork groups, so that the The top of the direction guide column is provided with a lifting ring, and the direction guide column is provided with an adjustment device, and the adjustment device is respectively connected with two adjacent inner template groups. When the adjustment device is executed, the inner template group The center of the support plate is approached or away from the center of the support plate in the direction guided by the directional guide column. The support plate is provided with a plurality of reinforcing rod groups, and the reinforcing rod groups are provided with a plurality of positioning small boxes that are matched and connected to the interior of the wall. The swing legs of the reinforced rod group are provided with a number of suspension devices that enable the support plate to be movably installed on the inner template group.

优选地,所述方向引导柱包括立柱和封头板,所述封头板设置在立柱的两端,所述吊环设置在封头板上,所述立柱的一侧面上开设有上下两端开口的凹槽,所述凹槽上开设有多条紧固件容纳槽,所述容纳槽内放置有若干个T型螺栓。Preferably, the direction guide column includes a column and a head plate, the end plate is arranged on both ends of the column, the suspension ring is arranged on the end plate, and one side of the column is provided with upper and lower ends openings The groove is provided with a plurality of fastener accommodating grooves, and several T-bolts are placed in the accommodating grooves.

优选地,所述立柱为等腰直角三棱柱,所述立柱的横截面为等腰直角三角形,所述凹槽与等腰直角三角形的斜边平行。Preferably, the column is an isosceles right triangle, the cross section of the column is an isosceles right triangle, and the groove is parallel to the hypotenuse of the isosceles right triangle.

优选地,所述内模板组包括第一导向板、内模板、补偿板和第二导向板,所述第一导向板与内模板、内模板与补偿板、补偿板与第二导向板均通过螺栓活动连接,所述第一导向板和第二导向板均与调节装置滑动连接并沿对应的斜边方向在对应的凹槽上实现来回滑动。Preferably, the inner template group includes a first guide plate, an inner template, a compensation plate and a second guide plate, and the first guide plate and the inner template, the inner template and the compensation plate, and the compensation plate and the second guide plate all pass through The bolts are movably connected, and the first guide plate and the second guide plate are both slidably connected with the adjusting device and slide back and forth on the corresponding groove along the corresponding hypotenuse direction.

优选地,所述第一导向板和第二导向板均包括滑动件、角码、稳固件、延伸件和连接件,所述滑动件与稳固件的夹角为45°,所述角码设置在滑动件与稳固件之间,所述稳固件与连接件相互平行,所述稳固件和连接件均与延伸件连接并垂直,所述连接件与内模板连接。Preferably, both the first guide plate and the second guide plate include a sliding member, an angle code, a fixing member, an extending member and a connecting member, the included angle between the sliding member and the fixing member is 45°, and the angle code is provided with Between the slider and the stabilizer, the stabilizer and the connection are parallel to each other, the stabilizer and the connection are both connected and perpendicular to the extension, and the connection is connected to the inner template.

优选地,所述调节装置包括丝杆构件、定位滑动构件和铰接构件,所述螺杆构件分别与定位滑动构件和铰接构件螺纹连接,所述定位滑动构件与分别与第一导向板和第二导向板滑动连接,所述铰接构件分别与第一导向板和第二导向板铰接连接,当所述丝杆构件执行正转时,铰接构件带动第一导向板和第二导向板沿定位滑动构件向丝杆构件方向靠近,当所述丝杆构件执行反转时,铰接构件带动第一导向板和第二导向板沿定位滑动构件向丝杆构件方向远离。Preferably, the adjusting device includes a screw member, a positioning sliding member and a hinge member, the screw member is screwed with the positioning sliding member and the hinge member, respectively, and the positioning sliding member is respectively connected with the first guide plate and the second guide plate. Plate sliding connection, the hinge member is hingedly connected with the first guide plate and the second guide plate respectively, when the screw member performs forward rotation, the hinge member drives the first guide plate and the second guide plate along the positioning sliding member. The direction of the screw member approaches, and when the screw member performs inversion, the hinge member drives the first guide plate and the second guide plate to move away from the direction of the screw member along the positioning sliding member.

优选地,所述定位滑动构件包括滑座、设置在滑座内来回滑动的滑块和滑座支撑块,滑座与滑座支撑块通过T型螺栓固定在立柱上,所述滑块分别与第一导向板和第二导向板连接。Preferably, the positioning sliding member includes a sliding seat, a sliding block arranged in the sliding seat to slide back and forth, and a sliding seat supporting block, the sliding seat and the sliding seat supporting block are fixed on the upright column by T-bolts, and the sliding block and The first guide plate and the second guide plate are connected.

优选地,所述铰接构件包括正丝铰接块、反丝铰接块、第一连架杆、第二连架杆和连杆,所述第一连架杆和第二连架杆分别与各自的正丝铰接块和反丝铰接块枢接,所述连杆分别与第一连架杆和第二连架杆枢接。Preferably, the hinge member includes a positive wire hinge block, a reverse wire hinge block, a first connecting rod, a second connecting rod and a connecting rod, and the first connecting rod and the second connecting rod are respectively connected with their respective The positive wire hinge block and the reverse wire hinge block are pivotally connected, and the connecting rods are respectively pivoted with the first connecting rod and the second connecting rod.

优选地,所述丝杆构件包括双向丝杆、花键套和花键轴,所述双向丝杆的两端设有花键,所述正丝铰接块和反丝铰接块与双向丝杆螺纹连接,所述双向丝杆的一端穿过滑座支撑块,另一端与花键轴通过花键套实现花键联接。Preferably, the screw member includes a bidirectional screw, a spline sleeve and a spline shaft, the two ends of the bidirectional screw are provided with splines, and the positive and reverse screw joint blocks are threaded with the two-way screw. One end of the two-way screw rod passes through the sliding seat support block, and the other end is connected with the spline shaft through the spline sleeve to realize the spline connection.

优选地,所述悬挂装置包括挂杆和挂板,所述挂杆的一端与加强杆组螺栓连接,所述挂杆的另一端穿出支撑板并与挂板螺丝连接,所述挂板上设有环扣,所述环扣与内模板(32)之间设有钢索。Preferably, the suspension device includes a hanging rod and a hanging plate, one end of the hanging rod is bolted to the reinforcing rod group, and the other end of the hanging rod passes through the support plate and is screwed to the hanging plate, and the hanging plate A ring buckle is provided, and a steel cable is arranged between the ring buckle and the inner template (32).

本发明一种整体吊升式吊装平台的有益效果如下:The beneficial effects of an integral hoisting hoisting platform of the present invention are as follows:

本发明一种整体吊升式吊装平台,通过内模板组、方向引导柱和调节装置实现了对不同截面尺寸的筒子型现浇剪力墙的装模和脱模,通过内模板组可根据现场需要可任意调节平台大小,调节方便,且可以重复使用,适应不同截面尺寸筒子型现浇剪力墙模板施工。同时在施工完之后,通过吊机可将整体平台向上吊起直接进行下一层的建造,提升了设备的技术性能,极大提高建筑施工效率,并可重复使用,安全可靠。The present invention is an integral hoisting type hoisting platform, which realizes the installation and demoulding of the cast-in-situ shear walls of different section sizes through the inner template group, the direction guide column and the adjusting device. The size of the platform can be adjusted arbitrarily, the adjustment is convenient, and it can be reused to adapt to the construction of the cast-in-place shear wall formwork of different section sizes. At the same time, after the construction is completed, the whole platform can be lifted up by the crane to directly carry out the construction of the next floor, which improves the technical performance of the equipment, greatly improves the construction efficiency, and can be reused, safe and reliable.

以下将结合附图对本发明的构思、具体结构及产生的效果作进一步说明,以充分地理解本发明的目的、特征和效果。The concept, specific structure and effects of the present invention will be further described below with reference to the accompanying drawings, so as to fully understand the purpose, features and effects of the present invention.

【说明书附图】【Attachments in the Instruction Manual】

图1为本发明的结构示意图;Fig. 1 is the structural representation of the present invention;

图2为本发明的剖视图;Fig. 2 is a sectional view of the present invention;

图3为方向引导柱示意图;3 is a schematic diagram of a direction guide column;

图4为方向引导柱剖视图;4 is a sectional view of a direction guide column;

图5为内模板组示意图;Fig. 5 is the schematic diagram of inner template group;

图6为图5-A局部放大图;Fig. 6 is a partial enlarged view of Fig. 5-A;

图7为本发明的仰视图;Fig. 7 is the bottom view of the present invention;

图8为第一导向板、第二导向板和调节装置配合示意图;Figure 8 is a schematic diagram of the cooperation of the first guide plate, the second guide plate and the adjusting device;

图9为悬挂装置示意图;9 is a schematic diagram of a suspension device;

本体1;支撑板11;环扣111;摆腿12;立柱21;封头板22;凹槽23;紧固件容纳槽24;斜边25;第一导向板31;内模板32;支撑梁321;补偿板33;第二导向板34;滑动件351;角码352;稳固件353;延伸件354;连接件355;滑座41;滑块42;滑座支撑块43;正丝铰接块51;反丝铰接块52;第一连架杆53;第二连架杆54;连杆55;双向丝杆61;花键套62;花键轴63;挂杆71;挂板72;横向加强杆81;纵向加强杆82。main body 1; support plate 11; buckle 111; swing leg 12; upright column 21; head plate 22; groove 23; fastener accommodating groove 24; 321; Compensation plate 33; Second guide plate 34; Slider 351; Corner code 352; Stabilizer 353; Extension 354; 51; anti-wire hinge block 52; first connecting rod 53; second connecting rod 54; connecting rod 55; two-way screw 61; spline sleeve 62; spline shaft 63; Reinforcing rod 81; longitudinal reinforcement rod 82.

【具体实施方式】【Detailed ways】

在本发明的描述中,需要理解的是,术语中“中心”、“上”、“下”、“前”、“后”、“左”、“右”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。此外,术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性。In the description of the present invention, it should be understood that the orientation or positional relationship indicated by "center", "upper", "lower", "front", "rear", "left", "right", etc. in the terms is based on The orientation or positional relationship shown in the drawings is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the indicated device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be construed as Limitations of the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and should not be construed to indicate or imply relative importance.

在本发明的描述中,需要说明的是,除非另有明确的规定和限定,术语“安装”、“连接”、“相连”应做广义理解,例如,可以是固定连接,也可以是拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以是通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本发明的具体含义。此外,在本发明的描述中,除非另有说明,“多个”、“若干”的含义是两个或两个以上。In the description of the present invention, it should be noted that, unless otherwise expressly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it may be a fixed connection or a detachable connection , or integrally connected; it can be a mechanical connection or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or the internal communication between the two components. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood in specific situations. In addition, in the description of the present invention, unless otherwise specified, "plurality" and "several" mean two or more.

请参见图1-9,图1-9揭示的是一种整体吊升式吊装平台的最佳实施方式:Please refer to Fig. 1-9, Fig. 1-9 discloses the best embodiment of an integral hoisting hoisting platform:

一种整体吊升式吊装平台,包括本体1,所述本体1上设有支撑板11和与支撑板11侧边数量相等的内模板组;本实施例中,该支撑板11为4边形,所以内模板组也为4组。该支撑板11按现场实际需求,如三边形、五边形不等,在此不一一举例。An integral hoisting type hoisting platform includes a body 1 on which a support plate 11 and an inner formwork group equal in number to the side of the support plate 11 are arranged; in this embodiment, the support plate 11 is quadrilateral , so the inner template group is also 4 groups. The support plate 11 varies according to the actual needs of the site, such as a triangle and a pentagon, which are not listed here.

更具体地,两两相邻的内模板组之间设有方向引导柱;本实施例的最佳实施方式是:所述方向引导柱包括立柱21和封头板22,所述封头板22设置在立柱21的两端,所述吊环设置在封头板22上,所述吊环用于吊机把本体1吊至高空进行作业。所述立柱21的一侧面上开设有上下两端开口的凹槽23,所述凹槽23上开设了6条紧固件容纳槽24,所述容纳槽内放置有若干个T型螺栓。本实施例例中,T型螺栓的头部嵌入在紧固件容纳槽24内,使用时,与T型螺母配合使用即可夹紧。More specifically, a direction guide column is provided between two adjacent inner template groups; the best implementation of this embodiment is: the direction guide column includes a column 21 and a head plate 22, and the head plate 22 The lifting rings are arranged on both ends of the upright column 21, and the lifting rings are arranged on the head plate 22, and the lifting rings are used for the crane to lift the main body 1 to a high altitude for operation. A groove 23 with open upper and lower ends is formed on one side of the upright column 21 , and six fastener accommodating grooves 24 are formed on the groove 23 , and several T-bolts are placed in the accommodating grooves. In this embodiment, the head of the T-bolt is embedded in the fastener accommodating groove 24, and can be clamped when used in conjunction with the T-nut.

更加具体地,所述立柱21为等腰直角三棱柱,所述立柱21的横截面为等腰直角三角形,所述凹槽23与等腰直角三角形的斜边25平行,由于等腰直角三角形具有较强的稳固、坚定、耐压的特点。More specifically, the column 21 is an isosceles right triangle, the cross section of the column 21 is an isosceles right triangle, and the groove 23 is parallel to the hypotenuse 25 of the isosceles right triangle, because the isosceles right triangle has Strong stability, firmness and pressure resistance.

更加具体地,所述内模板组包括第一导向板31、内模板32、补偿板33和第二导向板34,所述第一导向板31与内模板32、内模板32与补偿板33、补偿板33与第二导向板34均通过螺栓活动连接,所述第一导向板31和第二导向板34均与调节装置滑动连接并沿对应的斜边25方向在对应的凹槽23上实现来回滑动。通过设置第一导向板31和第二导向板34,可确保内模板组的滑动方向,避免出现方向偏移的问题。本实施例中,内模板32共使用了3块,可根据平台的大小而定内模板32的使用量,而且通过补偿板33,可兼容更多尺寸大小,通用性极强。More specifically, the inner template group includes a first guide plate 31, an inner template 32, a compensation plate 33 and a second guide plate 34, the first guide plate 31 and the inner template 32, the inner template 32 and the compensation plate 33, The compensation plate 33 and the second guide plate 34 are movably connected by bolts, and the first guide plate 31 and the second guide plate 34 are both slidably connected with the adjusting device and are realized on the corresponding groove 23 along the direction of the corresponding hypotenuse 25 Swipe back and forth. By arranging the first guide plate 31 and the second guide plate 34, the sliding direction of the inner template group can be ensured, and the problem of direction deviation can be avoided. In this embodiment, a total of three inner templates 32 are used, and the usage amount of the inner templates 32 can be determined according to the size of the platform, and the compensation plate 33 can be compatible with more sizes, and has strong versatility.

更加具体地,所述第一导向板31和第二导向板34均包括滑动件351、角码352、稳固件353、延伸件354和连接件355,所述滑动件351与稳固件353的夹角为45°,所述角码352设置在滑动件351与稳固件353之间,所述稳固件353与连接件355相互平行,所述稳固件353和连接件355均与延伸件354连接并垂直,所述连接件355与内模板32连接。角码352对滑动件351与稳固件353起到加固作用,增加承受压力;本实施例中,滑动件351与稳固件353的夹角为45°,夹角可根据现场需求进行调整,在此不一一举例。More specifically, the first guide plate 31 and the second guide plate 34 each include a sliding piece 351 , a corner code 352 , a fixing piece 353 , an extension piece 354 and a connecting piece 355 , and the sliding piece 351 and the fixing piece 353 are clamped The angle is 45°, the angle code 352 is arranged between the sliding piece 351 and the fixing piece 353, the fixing piece 353 and the connecting piece 355 are parallel to each other, and both the fixing piece 353 and the connecting piece 355 are connected with the extension piece 354 and are connected to each other. Vertically, the connecting piece 355 is connected to the inner formwork 32 . The angle code 352 reinforces the sliding member 351 and the fixing member 353, increasing the bearing pressure; in this embodiment, the included angle between the sliding member 351 and the fixing member 353 is 45°, and the included angle can be adjusted according to on-site requirements, here Not one by one example.

更加具体地,所述方向引导柱上设有调节装置,所述调节装置分别与两两相邻的内模板组相连,当所述调节装置被执行时,所述内模板组沿方向引导柱引导的方向向支撑板11中心靠近或远离。本实施例的最佳实施反式是:所述调节装置包括丝杆构件、定位滑动构件和铰接构件,所述螺杆构件分别与定位滑动构件和铰接构件螺纹连接,所述定位滑动构件与分别与第一导向板31和第二导向板34滑动连接,所述铰接构件分别与第一导向板31和第二导向板34铰接连接,当所述丝杆构件执行正转时,铰接构件带动第一导向板31和第二导向板34沿定位滑动构件向丝杆构件方向靠近,当所述丝杆构件执行反转时,铰接构件带动第一导向板31和第二导向板34沿定位滑动构件向丝杆构件方向远离。为了提高工程质量,该调节装置共采用了三组定位滑动构件,三组铰接构件和三组丝杆构件,分别设置在立柱21的上、中、下的相对位置,从而使两两相邻的内模板组结构更紧密,紧固性更强。More specifically, an adjustment device is provided on the direction guide column, and the adjustment device is respectively connected with two adjacent inner template groups. When the adjustment device is executed, the inner template group is guided along the direction guide column. The direction is closer to or away from the center of the support plate 11 . The best implementation of this embodiment is: the adjusting device includes a screw member, a positioning sliding member and a hinge member, the screw member is screwed with the positioning sliding member and the hinge member, respectively, and the positioning sliding member is respectively connected with the hinge member. The first guide plate 31 and the second guide plate 34 are slidably connected, and the hinge member is hingedly connected with the first guide plate 31 and the second guide plate 34 respectively. When the screw member performs a forward rotation, the hinge member drives the first guide plate 31 and the second guide plate 34. The guide plate 31 and the second guide plate 34 approach the screw member along the positioning sliding member. When the screw member is reversed, the hinge member drives the first guide plate 31 and the second guide plate 34 along the positioning sliding member. The direction of the screw member is far away. In order to improve the quality of the project, the adjusting device adopts three sets of positioning sliding members, three sets of hinge members and three sets of screw members, which are respectively arranged at the relative positions of the upper, middle and lower parts of the column 21, so that the adjacent two The inner formwork group has a tighter structure and stronger fastening.

更加具体地,所述定位滑动构件包括滑座41、设置在滑座41内来回滑动的滑块42和滑座支撑块43,滑座41与滑座支撑块43通过T型螺栓固定在立柱21上,所述滑块42分别与第一导向板31和第二导向板34连接。通过此设计,第一导向板31和第二导向板34可以带动自身的内模板组实现精确的移动,提高浇筑效率,更方便操作工人实现装模和脱模。More specifically, the positioning sliding member includes a sliding seat 41, a sliding block 42 and a sliding seat supporting block 43 arranged in the sliding seat 41 to slide back and forth, and the sliding seat 41 and the sliding seat supporting block 43 are fixed on the upright column 21 by T-bolts Above, the sliders 42 are respectively connected with the first guide plate 31 and the second guide plate 34 . Through this design, the first guide plate 31 and the second guide plate 34 can drive their own inner formwork group to achieve precise movement, improve pouring efficiency, and make it more convenient for operators to install and demold.

更加具体地,所述铰接构件包括正丝铰接块51、反丝铰接块52、第一连架杆53、第二连架杆54和连杆55,所述第一连架杆53和第二连架杆54分别与各自的正丝铰接块51和反丝铰接块52枢接,所述连杆55分别与第一连架杆53和第二连架杆54枢接。采用枢接和铰接方式一起使用,大幅度增加了内模板组的移动范围,从而跟好的施工。More specifically, the hinge member includes a positive wire hinge block 51, a reverse wire hinge block 52, a first connecting rod 53, a second connecting rod 54 and a connecting rod 55, the first connecting rod 53 and the second connecting rod 55 The connecting rods 54 are pivotally connected to the respective positive wire hinge blocks 51 and the reverse wire hinge blocks 52 respectively, and the connecting rods 55 are pivotally connected to the first connecting rod 53 and the second connecting rod 54 respectively. The use of pivoting and hinged joints greatly increases the moving range of the inner formwork group, so as to keep up with the construction.

更加具体地,所述丝杆构件包括双向丝杆61、花键套62和花键轴63,所述双向丝杆61的两端设有花键,所述正丝铰接块51和反丝铰接块52与双向丝杆61螺纹连接,所述双向丝杆61的一端穿过滑座支撑块43,另一端与花键轴63通过花键套62实现花键联接。通过采用双向丝杆61、花键套62和花键轴63组合安装,可以兼容不同高度的内模板组,实用性强,采用花键套62,拆装方便快捷,加快施工速度、提高劳动生产率。More specifically, the screw member includes a two-way screw 61, a spline sleeve 62 and a spline shaft 63, the two ends of the two-way screw 61 are provided with splines, and the positive wire hinge block 51 and the reverse wire are hinged. The block 52 is threadedly connected with the two-way screw 61 , one end of the two-way screw 61 passes through the sliding seat support block 43 , and the other end is splined with the spline shaft 63 through the spline sleeve 62 . By adopting the combined installation of the bidirectional screw 61, the spline sleeve 62 and the spline shaft 63, it can be compatible with different heights of inner formwork sets, and has strong practicability. The spline sleeve 62 is used, which is convenient and quick to disassemble and assemble, speed up the construction speed and improve labor productivity. .

更加具体地,所述支撑板11上设有多根加强杆组,所述加强杆组上设有多个与墙体内部预设的定位小盒配合连接的摆腿12,所述加强杆组上设有若干个使支撑板11活动安装在内模板组上的悬挂装置。本实施例中,所述加强杆组为设置在支撑板11下的5根横向加强杆81和7根纵向加强杆82。通过设置加强杆组,可大大提高支撑板11的承受压力,提高安全性。More specifically, the support plate 11 is provided with a plurality of reinforcing rod groups, and the reinforcing rod groups are provided with a plurality of swing legs 12 that are connected with a preset positioning box inside the wall. A number of suspension devices are arranged on the support plate 11 to movably install on the inner formwork group. In this embodiment, the reinforcing rod group is five transverse reinforcing rods 81 and seven longitudinal reinforcing rods 82 arranged under the support plate 11 . By arranging the reinforcing rod group, the bearing pressure of the support plate 11 can be greatly improved, and the safety can be improved.

本实施例中,所述悬挂装置包括挂杆71和挂板72,所述挂杆71的一端与加强杆组螺栓连接,所述挂杆71的另一端穿出支撑板11并与挂板72螺丝连接,述挂板72上设有环扣111,所述环扣111与内模板32之间设有钢索(112)。In this embodiment, the suspension device includes a hanging rod 71 and a hanging plate 72 , one end of the hanging rod 71 is bolted to the reinforcing rod group, and the other end of the hanging rod 71 passes through the support plate 11 and is connected to the hanging plate 72 For screw connection, the hanging plate 72 is provided with a ring buckle 111 , and a steel cable ( 112 ) is arranged between the ring buckle 111 and the inner template 32 .

所述内模板32与支撑板11相抵触的侧边上设有支撑梁321,所述支撑梁321与支撑板11抵触,所述支撑梁321在内模板组移动时起到支撑作用,解决了内模板组在支撑板11上移动的问题。操作时,支撑板11面积比电梯井横截面积略小,在吊升的过程中,能顺便通过电梯井。当完成前一层浇筑后,吊机通过吊环把吊装平台向上吊起,此时,摆腿12脱出前一层的定位小盒,沿浇筑好的混泥土墙墙向上移动至上方预留的定位小盒附近,当摆腿12插入后预留的定位小盒后,吊机停止停止工作,然后进行下一层的建造。A support beam 321 is provided on the side where the inner template 32 and the support plate 11 are in conflict, and the support beam 321 is in conflict with the support plate 11. The support beam 321 plays a supporting role when the inner template group moves, solving the problem of The problem of the movement of the inner formwork group on the support plate 11 . During operation, the area of the support plate 11 is slightly smaller than the cross-sectional area of the elevator shaft, and can pass through the elevator shaft by the way during the hoisting process. After the pouring of the previous layer is completed, the crane lifts the hoisting platform upward through the lifting ring. At this time, the swing leg 12 comes out of the positioning box of the previous layer, and moves up along the poured concrete wall to the reserved positioning above. Near the small box, when the swing leg 12 is inserted into the reserved positioning small box, the crane stops and stops working, and then the construction of the next floor is carried out.

本发明的工作步骤如下:The working steps of the present invention are as follows:

本发明实施时,将吊装平台放入预制基座的内部,并预先建造最下方的定位小盒,然后通过反转丝杆构件,正丝铰接块51和反丝铰接块52相互靠近,第一连架杆53和第二连架杆54推动第一导向板31和第二导向板34沿滑座41向丝杆构件方向远离,从而使内模板组向支撑板11中心远离,当距离调整达到设计要求后,外部设置外模板,然后进行墙体浇筑,建造第一层电梯井,浇筑建造时,在本层电梯井的上部预置定位小盒,最下方的一层电梯井完成并达到预定强度后,通过正转丝杆构件,正丝铰接块51和反丝铰接块52相互远离,第一连架杆53和第二连架杆54拉动第一导向板31和第二导向板34沿滑座41向丝杆构件方向靠近,从而使内模板组向支撑板11中心靠近,实现脱模;然后吊机通过吊环将吊装平台向上吊起,此时支撑板11通过环扣111和钢索112与内模板组连接,支撑板11通过钢索112随内模板组向上移动至上方的定位小盒附近,摆腿12进入定位小盒进行固定,然后将吊装平台调整水平,重新反转丝杆构件将内模板组扩张成设计尺寸,进行下一层的建造。When the present invention is implemented, the hoisting platform is put into the interior of the prefabricated base, and the lowermost positioning small box is pre-built, and then the positive-wire hinge block 51 and the reverse-wire hinge block 52 are approached by reversing the screw member. The connecting rod 53 and the second connecting rod 54 push the first guide plate 31 and the second guide plate 34 away from the direction of the screw member along the sliding seat 41, so that the inner template group is moved away from the center of the support plate 11. When the distance adjustment reaches After the design requirements, the external formwork is set up, and then the wall is poured to build the first elevator shaft. During the pouring and construction, the positioning small box is preset on the upper part of the elevator shaft on this floor, and the bottom elevator shaft is completed and reaches the predetermined level. After the strength, through the forward rotation of the screw member, the forward screw hinge block 51 and the reverse screw hinge block 52 are separated from each other, and the first connecting rod 53 and the second connecting rod 54 pull the first guide plate 31 and the second guide plate 34 along the The sliding seat 41 approaches the direction of the screw member, so that the inner formwork group approaches the center of the support plate 11 to realize demoulding; then the crane lifts the hoisting platform upward through the lifting ring, and the support plate 11 passes through the ring buckle 111 and the steel cable. 112 is connected with the inner template group, the support plate 11 moves upward with the inner template group through the steel cable 112 to the vicinity of the positioning small box above, the swing leg 12 enters the positioning small box for fixing, then adjusts the level of the hoisting platform, and reverses the screw rod again. The component expands the inner formwork group to the design size, and the construction of the next floor is carried out.

最后应说明的是:以上所述仅为本发明的优选实施例而已,并不用于限制本发明,尽管参照前述实施例对本发明进行了详细的说明,对于本领域的技术人员来说,其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。Finally, it should be noted that the above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Although the present invention has been described in detail with reference to the foregoing embodiments, for those skilled in the art, the The technical solutions described in the foregoing embodiments may be modified, or some technical features thereof may be equivalently replaced. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.

Claims (10)

1.一种整体吊升式吊装平台,其特征在于:包括本体(1),所述本体(1)上设有支撑板(11)和与支撑板(11)侧边数量相等的内模板组,两两相邻的内模板组之间设有方向引导柱,所述方向引导柱顶部设有吊环,所述方向引导柱上设有调节装置,所述调节装置分别与两两相邻的内模板组相连,当所述调节装置被执行时,所述内模板组沿方向引导柱引导的方向向支撑板(11)中心靠近或远离,所述支撑板(11)上设有多根加强杆组,所述加强杆组上设有多个与墙体内部预设的定位小盒配合连接的摆腿(12),所述加强杆组上设有若干个使支撑板(11)活动安装在内模板组上的悬挂装置。1. An integral hoisting type hoisting platform, characterized in that: it comprises a main body (1), and the main body (1) is provided with a support plate (11) and an inner template group equal in number to the side of the support plate (11). , a direction guide column is arranged between two adjacent inner template groups, the top of the direction guide column is provided with a lifting ring, and an adjustment device is arranged on the direction guide column, and the adjustment device is respectively connected with the two adjacent inner template groups. The formwork sets are connected, and when the adjusting device is executed, the inner formwork set approaches or moves away from the center of the support plate (11) along the direction guided by the directional guide columns, and the support plate (11) is provided with a plurality of reinforcing rods The reinforcing rod group is provided with a plurality of swing legs (12) that cooperate with the positioning small boxes preset inside the wall, and the reinforcing rod group is provided with a plurality of supporting plates (11) movably installed on the Suspension on inner formwork set. 2.根据权利要求1所述的一种整体吊升式吊装平台,其特征在于:所述方向引导柱包括立柱(21)和封头板(22),所述封头板(22)设置在立柱(21)的两端,所述吊环设置在封头板(22)上,所述立柱(21)的一侧面上开设有上下两端开口的凹槽(23),所述凹槽(23)上开设有多条紧固件容纳槽(24),所述紧固件容纳槽(24)内放置有若干个T型螺栓。2. An integral hoisting type hoisting platform according to claim 1, characterized in that: the direction guide column comprises a vertical column (21) and a head plate (22), and the head plate (22) is arranged on the Both ends of the upright column (21), the rings are arranged on the head plate (22), and a groove (23) with openings at the upper and lower ends is provided on one side of the upright column (21), and the groove (23) ) is provided with a plurality of fastener accommodating grooves (24), and several T-bolts are placed in the fastener accommodating grooves (24). 3.根据权利要求2所述的一种整体吊升式吊装平台,其特征在于:所述立柱(21)为等腰直角三棱柱,所述立柱(21)的横截面为等腰直角三角形,所述凹槽(23)与等腰直角三角形的斜边(25)平行。3. A kind of integral hoisting type hoisting platform according to claim 2, is characterized in that: described upright column (21) is an isosceles right-angled triangular prism, and the cross section of described upright column (21) is an isosceles right-angled triangle, The groove (23) is parallel to the hypotenuse (25) of the isosceles right triangle. 4.根据权利要求3所述的一种整体吊升式吊装平台,其特征在于:所述内模板组包括第一导向板(31)、内模板(32)、补偿板(33)和第二导向板(34),所述第一导向板(31)与内模板(32)、内模板(32)与补偿板(33)、补偿板(33)与第二导向板(34)均通过螺栓活动连接,所述第一导向板(31)和第二导向板(34)均与调节装置滑动连接并沿对应的斜边(25)方向在对应的凹槽(23)上实现来回滑动,所述内模板(32)与支撑板(11)相抵触的侧边上设有支撑梁(321)。4. An integral hoisting type hoisting platform according to claim 3, characterized in that: the inner template group comprises a first guide plate (31), an inner template (32), a compensation plate (33) and a second A guide plate (34), the first guide plate (31) and the inner template (32), the inner template (32) and the compensation plate (33), the compensation plate (33) and the second guide plate (34) all pass through bolts Actively connected, the first guide plate (31) and the second guide plate (34) are both slidably connected with the adjusting device and slide back and forth on the corresponding groove (23) along the direction of the corresponding hypotenuse (25), so A support beam (321) is provided on the side edge of the inner formwork (32) in contact with the support plate (11). 5.根据权利要求4所述的一种整体吊升式吊装平台,其特征在于:所述第一导向板(31)和第二导向板(34)均包括滑动件(351)、角码(352)、稳固件(353)、延伸件(354)和连接件(355),所述滑动件(351)与稳固件(353)的夹角为45°,所述角码(352)设置在滑动件(351)与稳固件(353)之间,所述稳固件(353)与连接件(355)相互平行,所述稳固件(353)和连接件(355)均与延伸件(354)连接并垂直,所述连接件(355)与内模板(32)连接。5. An integral hoisting type hoisting platform according to claim 4, characterized in that: the first guide plate (31) and the second guide plate (34) both comprise a sliding member (351), an angle code ( 352), the stabilizer (353), the extension (354) and the connecting element (355), the angle between the sliding element (351) and the stabilizer (353) is 45°, and the angle code (352) is set at Between the sliding piece (351) and the fixing piece (353), the fixing piece (353) and the connecting piece (355) are parallel to each other, and the fixing piece (353) and the connecting piece (355) are both parallel to the extension piece (354) Connected and vertical, the connecting piece (355) is connected with the inner formwork (32). 6.根据权利要求4所述的一种整体吊升式吊装平台,其特征在于:所述调节装置包括丝杆构件、定位滑动构件和铰接构件,所述螺杆构件分别与定位滑动构件和铰接构件螺纹连接,所述定位滑动构件与分别与第一导向板(31)和第二导向板(34)滑动连接,所述铰接构件分别与第一导向板(31)和第二导向板(34)铰接连接,当所述丝杆构件执行正转时,铰接构件带动第一导向板(31)和第二导向板(34)沿定位滑动构件向丝杆构件方向靠近,当所述丝杆构件执行反转时,铰接构件带动第一导向板(31)和第二导向丝杆构件方向远离。6 . An integral hoisting type hoisting platform according to claim 4 , wherein the adjusting device comprises a screw member, a positioning sliding member and a hinged member, and the screw member is respectively connected with the positioning sliding member and the hinged member. 7 . screw connection, the positioning sliding member is slidably connected with the first guide plate (31) and the second guide plate (34) respectively, and the hinge member is respectively connected with the first guide plate (31) and the second guide plate (34) Hinged connection, when the screw member performs forward rotation, the hinge member drives the first guide plate (31) and the second guide plate (34) to approach the direction of the screw member along the positioning sliding member, when the screw member performs When reversed, the hinge member drives the first guide plate (31) and the second guide screw member to move away in the direction. 7.根据权利要求4所述的一种整体吊升式吊装平台,其特征在于:所述定位滑动构件包括滑座(41)、设置在滑座(41)内来回滑动的滑块(42)和滑座支撑块(43),滑座(41)与滑座支撑块(43)通过T型螺栓固定在立柱(21)上,所述滑块(42)分别与第一导向板(31)和第二导向板(34)连接。7. An integral hoisting type hoisting platform according to claim 4, characterized in that: the positioning sliding member comprises a sliding seat (41), a sliding block (42) arranged in the sliding seat (41) to slide back and forth and the sliding seat supporting block (43), the sliding seat (41) and the sliding seat supporting block (43) are fixed on the column (21) by T-bolts, and the sliding block (42) is respectively connected to the first guide plate (31) connected with the second guide plate (34). 8.根据权利要求7所述的一种整体吊升式吊装平台,其特征在于:所述铰接构件包括正丝铰接块(51)、反丝铰接块(52)、第一连架杆(53)、第二连架杆(54)和连杆(55),所述第一连架杆(53)和第二连架杆(54)分别与各自的正丝铰接块(51)和反丝铰接块(52)枢接,所述连杆(55)分别与第一连架杆(53)和第二连架杆(54)枢接。8. An integral hoisting type hoisting platform according to claim 7, characterized in that: the hinge member comprises a positive wire hinge block (51), a reverse wire hinge block (52), a first connecting rod (53) ), the second connecting rod (54) and the connecting rod (55), the first connecting rod (53) and the second connecting rod (54) are respectively connected with the respective positive wire hinge block (51) and reverse wire The hinge block (52) is pivotally connected, and the connecting rod (55) is pivotally connected with the first connecting rod (53) and the second connecting rod (54) respectively. 9.根据权利要求8所述的一种整体吊升式吊装平台,其特征在于:所述丝杆构件包括双向丝杆(61)、花键套(62)和花键轴(63),所述双向丝杆(61)的两端设有花键,所述正丝铰接块(51)和反丝铰接块(52)与双向丝杆(61)螺纹连接,所述双向丝杆(61)的一端穿过滑座支撑块(43),另一端与花键轴(63)通过花键套(62)实现花键联接。9. An integral hoisting type hoisting platform according to claim 8, wherein the screw member comprises a bidirectional screw (61), a spline sleeve (62) and a spline shaft (63), Both ends of the two-way screw (61) are provided with splines, and the positive-thread hinge block (51) and the reverse-thread hinge block (52) are threadedly connected with the two-way screw (61), and the two-way screw (61) One end passes through the sliding seat support block (43), and the other end realizes spline connection with the spline shaft (63) through the spline sleeve (62). 10.根据权利要求4所述的一种整体吊升式吊装平台,其特征在于:所述悬挂装置包括挂杆(71)和挂板(72),所述挂杆(71)的一端与加强杆组螺栓连接,所述挂杆(71)的另一端穿出支撑板(11)并与挂板(72)螺丝连接,所述挂板(72)上设有环扣(111),所述环扣(111)与内模板(32)之间设有钢索(112)。10. An integral hoisting type hoisting platform according to claim 4, characterized in that: the suspension device comprises a hanging rod (71) and a hanging plate (72), and one end of the hanging rod (71) is connected to the reinforcement The rod group is connected by bolts, and the other end of the hanging rod (71) passes through the support plate (11) and is screwed to the hanging board (72), and the hanging board (72) is provided with a ring buckle (111). A steel cable (112) is arranged between the ring buckle (111) and the inner template (32).
CN202010796382.9A 2020-08-10 2020-08-10 Integral hoisting type hoisting platform Pending CN111910923A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010796382.9A CN111910923A (en) 2020-08-10 2020-08-10 Integral hoisting type hoisting platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010796382.9A CN111910923A (en) 2020-08-10 2020-08-10 Integral hoisting type hoisting platform

Publications (1)

Publication Number Publication Date
CN111910923A true CN111910923A (en) 2020-11-10

Family

ID=73283539

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010796382.9A Pending CN111910923A (en) 2020-08-10 2020-08-10 Integral hoisting type hoisting platform

Country Status (1)

Country Link
CN (1) CN111910923A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113006470A (en) * 2021-03-12 2021-06-22 胡华 Lifting and collecting type elevator shaft inner mold system
CN114382284A (en) * 2021-12-31 2022-04-22 江西志特新材料股份有限公司 An elevator shaft formwork system and its operation method
CN115095139A (en) * 2022-06-30 2022-09-23 山东众泰建筑科技股份有限公司 Elevator shaft integral lifting template device

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050088767A (en) * 2004-03-03 2005-09-07 박정진 Hanging type formwork for non-supporting formwork system for top down construction and concrete structure construction method using the same
CN204983636U (en) * 2015-09-01 2016-01-20 中民筑友有限公司 Revenue and expenditure mould mechanism, interior tube formwork and lift well formwork device
CN105507580A (en) * 2016-01-27 2016-04-20 山东方圆建筑材料有限公司 Integral lifting type formwork device for an elevator shaft
CN206189846U (en) * 2016-09-12 2017-05-24 张铁强 Elevator shaft mould with adjustable
CN108385967A (en) * 2017-08-25 2018-08-10 中建二局第建筑工程有限公司 The construction method of elevator shaft integral mold plate system and elevator shaft
CN109763627A (en) * 2019-03-13 2019-05-17 中国五冶集团有限公司 A kind of high-rise building elevator shaft construction structure and construction method
CN210636438U (en) * 2019-08-09 2020-05-29 中国水利水电第六工程局有限公司 Underwater gate well template pouring system
CN212802515U (en) * 2020-08-10 2021-03-26 江门志特新材料科技有限公司 Integral hoisting type hoisting platform

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050088767A (en) * 2004-03-03 2005-09-07 박정진 Hanging type formwork for non-supporting formwork system for top down construction and concrete structure construction method using the same
CN204983636U (en) * 2015-09-01 2016-01-20 中民筑友有限公司 Revenue and expenditure mould mechanism, interior tube formwork and lift well formwork device
CN105507580A (en) * 2016-01-27 2016-04-20 山东方圆建筑材料有限公司 Integral lifting type formwork device for an elevator shaft
CN206189846U (en) * 2016-09-12 2017-05-24 张铁强 Elevator shaft mould with adjustable
CN108385967A (en) * 2017-08-25 2018-08-10 中建二局第建筑工程有限公司 The construction method of elevator shaft integral mold plate system and elevator shaft
CN109763627A (en) * 2019-03-13 2019-05-17 中国五冶集团有限公司 A kind of high-rise building elevator shaft construction structure and construction method
CN210636438U (en) * 2019-08-09 2020-05-29 中国水利水电第六工程局有限公司 Underwater gate well template pouring system
CN212802515U (en) * 2020-08-10 2021-03-26 江门志特新材料科技有限公司 Integral hoisting type hoisting platform

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113006470A (en) * 2021-03-12 2021-06-22 胡华 Lifting and collecting type elevator shaft inner mold system
CN114382284A (en) * 2021-12-31 2022-04-22 江西志特新材料股份有限公司 An elevator shaft formwork system and its operation method
CN115095139A (en) * 2022-06-30 2022-09-23 山东众泰建筑科技股份有限公司 Elevator shaft integral lifting template device

Similar Documents

Publication Publication Date Title
WO2023082776A1 (en) Box-type prefabricated member system and operating method
CN111910923A (en) Integral hoisting type hoisting platform
CN110616640A (en) Positioning and lowering device for reinforcement cage and construction method of positioning and lowering device
CN219672108U (en) Combined type elevator shaft climbing barrel mold device
CN114407191A (en) Mould for manufacturing steel reinforcement framework of prefabricated box girder
CN115162713A (en) Construction method of self-climbing type shaft template system
CN108691277A (en) Three-dimensional adjustment tool for positioning of segmental prefabricated assembled beams during erection
CN209775027U (en) prefabricated box girder integral contraction type hydraulic internal mold dismounting trolley combined structure
CN215969285U (en) Mould for manufacturing concrete fence plate
CN212802515U (en) Integral hoisting type hoisting platform
CN114382284A (en) An elevator shaft formwork system and its operation method
CN215618848U (en) Walking integral hydraulic prefabricated small box girder template structure
CN215107202U (en) A operation platform that rises that slides for elevartor shaft construction
CN213418468U (en) Device for pouring concrete into high-rise building supporting and hanging formwork
CN115321338A (en) Hoisting and positioning structure for PC laminated slab and construction method
CN115897417A (en) A formwork construction method and device in the process of cantilever pouring continuous beams
CN115787514A (en) Be suitable for continuous variable cross section hydraulic pressure and adjust centre form
CN113175201A (en) A operation platform that rises that slides for elevartor shaft construction
CN223548969U (en) Base guiding positioning type concrete precast column assembly structure
CN209686242U (en) Suspension bridge high mound steel framework demolishs device
CN112523172A (en) Gate chamber corridor moving and supporting device and method
CN120906346B (en) A formwork support device for cantilevered staggered-level balconies
CN223753680U (en) Cast-in-situ shear wall casting construction template structure of elevator shaft
CN216515160U (en) Suspension bridge king-tower entablature lower chamfer hangs mould construction template system
CN116905362B (en) An integrated device for prefabricated pier column butt jointing and wet joint casting and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20210129

Address after: 529300 8 Huancui East Road, cuishanhu New District, Kaiping City, Jiangmen City, Guangdong Province

Applicant after: JIANGMEN ZHITE NEW MATERIAL TECHNOLOGY Co.,Ltd.

Address before: 344900 Guangchang Industrial Park, Guangchang county, Fuzhou City, Jiangxi Province

Applicant before: JIANGXI ZHITE NEW MATERIAL Co.,Ltd.

TA01 Transfer of patent application right
RJ01 Rejection of invention patent application after publication

Application publication date: 20201110

RJ01 Rejection of invention patent application after publication