CN111910679A - Construction method of super-long and super-balanced retaining wall under complex terrain - Google Patents
Construction method of super-long and super-balanced retaining wall under complex terrain Download PDFInfo
- Publication number
- CN111910679A CN111910679A CN202010803900.5A CN202010803900A CN111910679A CN 111910679 A CN111910679 A CN 111910679A CN 202010803900 A CN202010803900 A CN 202010803900A CN 111910679 A CN111910679 A CN 111910679A
- Authority
- CN
- China
- Prior art keywords
- construction
- wall
- concrete
- retaining wall
- formwork
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0258—Retaining or protecting walls characterised by constructional features
- E02D29/0275—Retaining or protecting walls characterised by constructional features cast in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/18—Making embankments, e.g. dikes, dams
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0018—Cement used as binder
- E02D2300/002—Concrete
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- General Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Retaining Walls (AREA)
Abstract
Description
技术领域technical field
本发明涉及边坡支护施工技术领域,具体地说是复杂地形下超长超高衡重式挡土墙施工方法。The invention relates to the technical field of side slope support construction, in particular to a construction method for a super-long and super-balanced-weight retaining wall under complex terrain.
背景技术Background technique
随着我国基础设施建设步伐的不断加快,城市土地资源供应日趋紧张,通过对不良地形、地质实施技改,提高土地规划效益和利用率,对缓解城市土地供需压力具有极其重要的意义,尤其是像重庆、四川、云南和贵州这些山区城市,往往是通过采取边坡挡护的形式来实现土地资源从不可用到可用的目标转换。因此,随着优质土地资源的逐步匮乏,土地技改过程中对边坡挡护结构的设计和施工都提出了更高的挑战。With the accelerating pace of infrastructure construction in our country, the supply of urban land resources is becoming increasingly tight. It is of great significance to alleviate the pressure of urban land supply and demand by implementing technical transformation of unfavorable terrain and geology to improve the efficiency and utilization rate of land planning. Mountainous cities such as Chongqing, Sichuan, Yunnan and Guizhou often use the form of slope protection to achieve the goal of converting land resources from unavailable to usable. Therefore, with the gradual scarcity of high-quality land resources, the design and construction of slope retaining structures have posed higher challenges in the process of land technical transformation.
发明内容SUMMARY OF THE INVENTION
本发明的技术任务是针对以上不足之处,提供复杂地形下超长超高衡重式挡土墙施工方法,解决施工中基坑临时边坡失稳、墙身模板支设难度大以及大体积混凝土施工、挡土墙泄水及墙背回填质量不易控制等难题,具有显著地经济效益和社会效益。The technical task of the present invention is to provide a construction method for a super-long and super-balanced-weight retaining wall under complex terrain in view of the above deficiencies, so as to solve the problem of the temporary side slope instability of the foundation pit during the construction, the difficulty of supporting the wall formwork and the large volume. Concrete construction, retaining wall drainage and wall backfill quality are difficult to control, which have significant economic and social benefits.
本发明解决其技术问题所采用的技术方案是:The technical scheme adopted by the present invention to solve its technical problems is:
复杂地形下超长超高衡重式挡土墙施工方法,挡墙基础开挖过程中采用跳仓法施工,挡土墙结构采用水平跳仓竖向分层的方式组织施工,模板采用钢模板与木模板结合的方式,且采用模板斜拉自平衡固定;The construction method of the super-long and super-heavy retaining wall under complex terrain. During the excavation of the retaining wall foundation, the vaulting method is adopted. The retaining wall structure adopts the horizontal vaulting and vertical layering method to organize the construction, and the formwork adopts the steel formwork. It is combined with the wooden formwork, and the formwork is slanted and self-balancing fixed;
墙身混凝土分层浇筑,墙背反滤层分层施工;The wall concrete is poured in layers, and the back filter layer is constructed in layers;
挡墙基础开挖时将墙后地面挖成反坡台阶,挡土墙施工完毕后进行墙背回填。When the retaining wall foundation is excavated, the ground behind the wall is dug into a reverse slope step, and the back of the wall is backfilled after the construction of the retaining wall is completed.
该方法优化施工顺序,采用跳仓法施工和利用开挖台阶有效保证施工安全,同步解决山体陡坡便道施工难题;模板斜拉自平衡固定法代替传统对拉,有效解决大跨度长拉杆的拉伸变形、弹性变形问题,降低了施工成本,保证了施工安全和质量;墙背采用边浇筑混凝土边回填的方式,极大的减少了操作架体的搭设量,方便施工,有效降低安全风险。This method optimizes the construction sequence, adopts the skipping method for construction and uses excavation steps to effectively ensure construction safety, and simultaneously solves the construction problems of access roads on steep mountain slopes; the formwork cable-pulling self-balancing fixing method replaces the traditional pairing, effectively solving the stretching of long-span long tie rods The problems of deformation and elastic deformation reduce the construction cost and ensure the construction safety and quality; the backfill method is adopted while pouring concrete, which greatly reduces the erection amount of the operating frame, facilitates construction, and effectively reduces safety risks.
优选的,该方法的具体施工过程为:Preferably, the specific construction process of the method is:
1)、测量放线、基坑开挖,并进行基坑验槽以及锚杆施工;1) Measure the line, excavate the foundation pit, and carry out the inspection of the foundation pit and the construction of the bolt;
2)、基础混凝土浇筑;2), foundation concrete pouring;
3)、墙身模板安装,选择合适的模板及安装形式,进行断面尺寸设计、钢筋及泄水管的安装;3) Install the wall formwork, select the appropriate formwork and installation form, design the section size, install the steel bar and the drain pipe;
4)、进行墙身混凝土的浇筑,根据施工地区气候特点进行衡重式挡土墙大体积混凝土的施工,并进行挡土墙墙身监测;4) Carry out the concrete pouring of the wall body, carry out the construction of the mass concrete of the counterweight type retaining wall according to the climatic characteristics of the construction area, and carry out the monitoring of the retaining wall body;
5)、反滤层施工;5), the construction of the reverse filter layer;
6)、墙背回填。6), backfill the back of the wall.
进一步的,陡坡地貌在基坑开挖前先将挡墙基坑两侧边坡开挖成反坡台阶,并将墙背侧距基坑边3m范围内覆土翻运至墙面侧地势较低处,防止开挖过程中基坑顶部塌方及滑坡。Further, before the excavation of the foundation pit for steep slope landforms, the side slopes on both sides of the retaining wall foundation pit shall be excavated into reverse slope steps, and the covering soil within 3m from the side of the foundation pit on the back side of the wall shall be turned over to the lower terrain on the side of the wall. to prevent the top of the foundation pit from collapsing and landslides during the excavation process.
优选的,基槽开挖前将所有墙体结构逐一放样排布,按照由高到低的顺序分段分层流水作业;Preferably, all wall structures are set out one by one before the foundation trench is excavated, and the flow is carried out in sections and layers according to the order from high to low;
基坑开挖采用机械跳仓开挖,开挖至每层锚杆设计标高后,先行施工完成当层锚杆后继续下层开挖;The foundation pit excavation adopts mechanical jumping excavation. After the excavation reaches the design elevation of each layer of bolts, the construction of the bolts of the current layer is completed first, and then the lower layer is excavated;
基坑边坡、台阶及基底预留20cm采用人工开挖,人工开挖前重新进行测量放样,在确定开挖正确不偏位的情况下改用人工进行基底清理,确保基底符合设计及相关规范要求;The slope, steps and base of the foundation pit shall be reserved for 20cm by manual excavation. Before manual excavation, measure and stake out again. After confirming that the excavation is correct and not deviated, use manual cleaning of the base to ensure that the base meets the requirements of the design and relevant specifications. ;
基坑开挖完成后,及时进行地基验槽,然后进行混凝土挡墙的基础混凝土浇筑。After the excavation of the foundation pit is completed, the foundation trench shall be inspected in time, and then the foundation concrete pouring of the concrete retaining wall shall be carried out.
进一步的,采用永临结合方式确保临时边坡的稳定性;采用信息法施工,利用理正岩土6.5进行边坡稳定性分析,从而做好施工过程中临时边坡的巡视和监测,保证施工安全。Further, the combination of permanent and permanent is used to ensure the stability of the temporary slope; the information method is used for construction, and the stability analysis of the slope is carried out using Lizheng Geotechnical 6.5, so as to do a good job in the inspection and monitoring of the temporary slope during the construction process to ensure the construction. Safety.
优选的,墙面及墙背模板采用钢模板,墙身侧模采用胶合板,胶合板竖向背楞选用木方支撑,横向背楞选用双钢管和对拉螺栓拉结;Preferably, the wall and wall back formwork is made of steel formwork, the side formwork of the wall body is made of plywood, the vertical back corrugation of the plywood is supported by wooden squares, and the horizontal back corrugation is made of double steel pipes and tie bolts;
墙身模板的安装顺序为:搭设模板操作架,安装水平拉杆和剪力撑→立墙体两侧模板→用斜拉螺栓拉结侧模板横向背楞→紧固检查→调垂直度→验收;The installation sequence of the wall formwork is: erect the formwork operation frame, install the horizontal tie rods and shear braces → the formwork on both sides of the vertical wall → tie the lateral back corrugation of the side formwork with the oblique bolts → tighten the inspection → adjust the verticality → acceptance;
基础首层混凝土满灌浇筑,浇筑完成后预埋钢筋作为插筋,预埋混凝土长度不小于40cm,采用内外两排,根据挡墙坡率适当调整,确保每根插筋上顶层斜拉杆与混凝土面呈45度角;The first floor of the foundation shall be filled with concrete. After the pouring is completed, the pre-embedded steel bars shall be used as inserts. The length of the embedded concrete shall not be less than 40cm. Two rows of inner and outer rows shall be used. It shall be properly adjusted according to the slope rate of the retaining wall, so as to ensure that the top-level diagonal tie rods on each inserted bar are connected to the concrete surface. at a 45-degree angle;
模板斜拉杆采用螺纹钢,对拉采用同尺寸螺杆;The inclined rod of the formwork is made of threaded steel, and the screw of the same size is used for the pull;
对拉杆与插筋采用双面焊接,搭接长度不小于15cm,焊接质量满足规范要求;Double-sided welding is adopted for the tie rod and the insertion bar, and the lap length is not less than 15cm, and the welding quality meets the requirements of the specification;
钢模板采用1托2跳仓浇筑,每次浇筑高度1.94m,木模板每次支设两模,浇筑高度同钢模板;The steel formwork is poured with 1 support and 2 jumping warehouses, and the height of each pouring is 1.94m. The wooden formwork is supported with two forms each time, and the pouring height is the same as that of the steel formwork;
木模板加固方式同钢模板,每块模板横向设置三排拉杆;The reinforcement method of the wooden formwork is the same as that of the steel formwork, and three rows of tie rods are set horizontally for each formwork;
模板支设时采用上下定位的方式确定斜率,测量人员在垫层上弹出每段模板下口线,上口采用锤球吊点进行定位,为模板定位提供依据。When the template is set up, the slope is determined by the way of up and down positioning. The surveyor pops up the lower opening line of each template on the cushion layer, and the upper opening is positioned by the hammer ball hanging point, which provides the basis for the template positioning.
优选的,优化混凝土的配合比及原料选择,选用低水化热的矿渣水泥,并适当使用缓凝减水剂,在保证混凝土设计强度等级前提下,适当降低水灰比,减少水泥用量;Preferably, the mix ratio of concrete and the selection of raw materials are optimized, slag cement with low hydration heat is selected, setting retarding water reducing agent is used appropriately, and the water-cement ratio is appropriately reduced and the amount of cement is reduced on the premise of ensuring the design strength level of concrete;
水泥选用P.O42.5R级散装水泥,该水泥对混凝土的早期强度提高并不明显,前期产生的水化热符合规范要求;P.O42.5R grade bulk cement is used as the cement. The early strength of the concrete is not significantly improved, and the hydration heat generated in the early stage meets the requirements of the specification;
粗骨料选用5~20mm卵碎石,其压碎指标值不大于8%,最大粒径为20mm,含泥量小于1.0%,针片状颗粒含量小于5.0%;Coarse aggregates are selected from 5-20mm pebble gravel, the crushing index value is not more than 8%, the maximum particle size is 20mm, the mud content is less than 1.0%, and the acicular particle content is less than 5.0%;
细骨料天然砂选用特细砂,细度模数MX≥0.8,含泥量≤2.0%,无潜在碱活性;卵石机制砂(中砂),含泥量≤1.0%;细度模数控制范围为2.6~2.9;含粉量≤5.0%,母岩强度大于80MPa,压碎指标值小于25%,无潜在碱活性;Fine aggregate natural sand is made of extra-fine sand, with fineness modulus MX≥0.8, mud content≤2.0%, and no potential alkali activity; pebble machine-made sand (medium sand), mud content≤1.0%; fineness modulus control The range is 2.6 to 2.9; the powder content is ≤5.0%, the strength of the parent rock is greater than 80MPa, the crushing index value is less than 25%, and there is no potential alkali activity;
粉煤灰选用F类Ⅱ级粉煤灰,粉煤灰对降低水化热、改善混凝土和易性有利,但掺加粉煤灰的混凝土早期极限抗拉值均有所降低,对混凝土抗渗抗裂不利,因此粉煤灰的掺量严格按混凝土配合比报告进行控制,采用外掺法,即不减少配合比中的水泥用量,按配合比要求计算出每立方米混凝土所掺加粉煤灰量;The fly ash is F-class II grade fly ash. Fly ash is beneficial to reduce the heat of hydration and improve the workability of concrete. The crack resistance is not good, so the amount of fly ash is strictly controlled according to the concrete mix ratio report, and the external mixing method is adopted, that is, the cement amount in the mix ratio is not reduced, and the fly ash added per cubic meter of concrete is calculated according to the mix ratio requirements. Ash volume;
外加剂选用PCA-R聚羟酸型缓凝高性能减水剂,该外加剂能显著增大混凝土的流动性,改善操作性,可延缓水泥水化放热峰值,避免施工结合层冷缝现象,有效提高其抗裂防水性能,各项检测指标符合以下之规定:与生产用P.O42.5R级水泥、矿渣粉、混凝土膨胀剂、纤维等材料具有良好的适应性。每次材料进厂必须取样检测,检验合格后方可使用。每次进场取样检测其净浆流动度、减水率、混凝土坍落度经时损失、凝结时间;The admixture is PCA-R polyhydroxy acid type retarding high-performance water-reducing agent, which can significantly increase the fluidity of concrete, improve operability, delay the peak of cement hydration and exotherm, and avoid the phenomenon of cold joints in the construction joint layer. , effectively improve its anti-cracking and waterproof performance, and each test index meets the following requirements: It has good adaptability with P.O42.5R grade cement, slag powder, concrete expansion agent, fiber and other materials used in production. Every time the material enters the factory, it must be sampled and tested, and it can be used after passing the inspection. Each time the site is sampled, the fluidity of the slurry, the water reduction rate, the loss of concrete slump over time, and the setting time are tested;
控制混凝土入模温度在10℃至20℃之间,混凝土的浇筑温度(振捣后50~100mm深处的温度)不得高于28℃;为减少每次浇筑的蓄热量,减少水化热的积聚,减小温度应力,采取分层浇筑,每层厚度控制在300mm~500mm,以伸缩缝为分界线,每次混凝土分三至四层自左向右连续进行浇筑,每层浇筑完成后,上一层混凝土浇筑之前,应清除浇筑表面的浮浆、软弱混凝土层及松动的石子,并均匀的露出粗骨料,用压力水冲洗混凝土表面的污物,充分润湿,但不得有积水;Control the temperature of the concrete into the mold between 10 °C and 20 °C, and the pouring temperature of the concrete (the temperature at a depth of 50 to 100 mm after vibrating) shall not be higher than 28 °C; Accumulation, reducing temperature stress, adopting layered pouring, the thickness of each layer is controlled at 300mm ~ 500mm, with expansion joints as the dividing line, each time the concrete is poured continuously from left to right in three to four layers. Before the last layer of concrete is poured, the laitance, weak concrete layer and loose stones on the pouring surface should be removed, and the coarse aggregate should be exposed evenly. The dirt on the concrete surface should be washed with pressure water, and it should be fully wetted, but there should be no standing water. ;
进行墙身混凝土的浇筑时,采用定型化操作平台辅助施工,定型化操作平台包括操作平台、主梁、次梁、斜撑、支腿以及钢爬梯。When the wall concrete is poured, a stereotyped operation platform is used to assist the construction. The stereotyped operation platform includes the operation platform, the main beam, the secondary beam, the diagonal brace, the outrigger and the steel ladder.
衡重式挡土墙墙身截面较大时,在浇筑混凝土时,墙身中心混凝土无法有效振捣,而传统的脚手架操作平台搭设复杂,稳定性差,操作难度大,不利于混凝土浇筑振捣及整体工期进度。定型化操作平台能够解决这些难题,采用轻型钢骨架制作而成,操作简单、快速,能够有效提升施工进度和施工质量。When the section of the counterweight retaining wall is large, the concrete in the center of the wall cannot be vibrated effectively when the concrete is poured. However, the traditional scaffolding operation platform is complicated to set up, has poor stability, and is difficult to operate, which is not conducive to concrete pouring and vibration. Overall construction progress. The stereotyped operation platform can solve these problems. It is made of light steel skeleton, which is simple and fast to operate, and can effectively improve the construction progress and construction quality.
优选的,由于衡重式挡墙高度较大,偏心距较大,若待全部浇筑完成后施工滤水层并回填台背存在较多安全隐患,如填筑质量不易保证和墙身及地基容易损坏等问题,因此反滤层施工过程中每浇筑三层或浇筑高度不超过6m进行一次滤水层施工,并在混凝土强度达到100%时进行基础及台背的回填工作;Preferably, due to the large height of the counterweight retaining wall and the large eccentric distance, if the water filter layer is constructed and the back of the platform is backfilled after all the pouring is completed, there will be many hidden dangers in safety, such as the difficulty in ensuring the filling quality and the difficulty in the wall and foundation. Therefore, during the construction of the anti-filter layer, the construction of the water filter layer is carried out every three layers or the pouring height does not exceed 6m, and the backfill of the foundation and the back of the platform is carried out when the concrete strength reaches 100%;
滤水层分为三层,第一层为20mm粗砺或碎石,第二层为1-4mm砂砾或石屑,第三层为300-400g/m2土工布,滤水层施工过程中控制泄水孔5%的流水坡度,并保证泄水孔向外排水顺畅,确保墙背积水可及时通过泄水孔排出,减少墙背压力,确保挡墙安全;采用透水性编织袋将滤水材料分包码放,即避免了挂网施工工艺对墙身结构破坏的影响,克服了挡板工艺施工难题,同时解决了隐蔽验收难题,该工艺施工操作简单,成本低,可大大提高工程施工质量,保证滤水效果。The water filter layer is divided into three layers, the first layer is 20mm rough or crushed stone, the second layer is 1-4mm gravel or stone chips, and the third layer is 300-400g/m2 geotextile. The sloping hole has a 5% flow gradient, and the drainage hole is ensured to drain smoothly to the outside, ensuring that the water on the back of the wall can be discharged through the scuppering hole in time, reducing the pressure on the back of the wall and ensuring the safety of the retaining wall; the permeable woven bag is used to filter the water The material is subcontracted and stacked, which avoids the impact of the hanging net construction process on the damage to the wall structure, overcomes the construction problem of the baffle process, and solves the problem of concealed acceptance. , to ensure the water filtration effect.
优选的,对于山坡状的施工地貌,所述墙背回填,在挡墙基础开挖时,将墙后地面挖成反坡台阶,台阶宽度不小于3m,高宽比不大于1:2,台阶面呈5%反坡,当基岩面上的覆盖层较薄时,须先清除覆盖层再开挖台阶,当覆盖层较厚且稳定时,可予以保留,在原地面挖台阶后填筑填料。Preferably, for hillside-shaped construction landforms, the back of the wall is backfilled, and when the retaining wall foundation is excavated, the ground behind the wall is excavated into reverse slope steps, the width of the steps is not less than 3m, the height-width ratio is not more than 1:2, and the steps are not less than 3m wide. The surface is 5% reverse slope. When the covering layer on the bedrock surface is thin, the covering layer must be removed first and then the steps are excavated. When the covering layer is thick and stable, it can be retained, and the filling is filled after excavating the steps on the original ground. .
进一步的,墙背25m范围内地基处理采用40cm/层振动碾压+2m/冲击碾压,碾压盲区采用人工夯实。Further, the foundation treatment within 25m of the back of the wall adopts 40cm/layer vibration rolling + 2m/impact rolling, and the blind area of rolling is manually compacted.
为降低地基处理对墙身产生挤压影响变形,挡土墙25m范围内不采用强夯,改为40cm/层振动碾压+2m/层冲击碾压,其中碾压盲区采用人工夯实,每层松散摊铺厚度不大于40cm,采用振动压路机逐层碾压,每2m再进行冲击碾压,每层振动碾压完成后进行压实度检测,确保压实度不小于94%,每层冲击碾压完成后进行地基承载力、有效加固深度及弹性模量检测。In order to reduce the extrusion and deformation of the wall caused by the foundation treatment, dynamic compaction is not used within 25m of the retaining wall, but instead is 40cm/layer vibration compaction + 2m/layer impact compaction. The thickness of loose paving shall not be greater than 40cm, and vibratory rollers shall be used to roll layer by layer, and impact rolling shall be carried out every 2m. After the compression is completed, the bearing capacity of the foundation, the effective reinforcement depth and the elastic modulus are tested.
本发明的复杂地形下超长超高衡重式挡土墙施工方法与现有技术相比,具有以下有益效果:Compared with the prior art, the construction method for an ultra-long and ultra-high counterweight retaining wall under complex terrain of the present invention has the following beneficial effects:
该方法通过优化施工顺序,采用跳仓法施工和利用开挖台阶有效保证施工安全,同步解决山体陡坡便道施工难题;采用模板斜拉自平衡固定法代替传统对拉,有效解决大跨度长拉杆的拉伸变形、弹性变形问题,降低了施工成本,保证了施工安全和质量;墙背采用边浇筑混凝土边回填的方式,极大的减少了操作架体的搭设量,方便施工,有效降低安全风险。This method optimizes the construction sequence, adopts the warehouse jumping method and uses excavation steps to effectively ensure the construction safety, and simultaneously solves the construction problem of the access road on the steep slope of the mountain. The problems of tensile deformation and elastic deformation reduce the construction cost and ensure the construction safety and quality; the backfill method is adopted while pouring concrete on the back of the wall, which greatly reduces the erection amount of the operating frame, facilitates construction, and effectively reduces safety risks. .
通过采用定型化浇筑振捣平台施工,安全美观,与传统脚手架搭设操作平台相比较,具有操作简单、安全稳固、外观效果好的特点;墙背反滤层施工利用反滤包形成反滤层,解决了墙体挂网难度大、回填破坏、隐蔽验收及墙体静水压力等一系列难题,保证了滤水效果及挡土墙结构安全。Compared with the traditional scaffolding operation platform, it has the characteristics of simple operation, safety and stability, and good appearance effect; the construction of the reverse filter layer on the back of the wall uses the reverse filter bag to form the reverse filter layer, which solves the problem. It solves a series of problems such as the difficulty of hanging nets on the wall, backfill damage, concealed acceptance and wall hydrostatic pressure, and ensures the water filtering effect and the safety of the retaining wall structure.
本方法工期快、成本低,经济效益和社会效益显著,解决了施工中基坑临时边坡失稳、墙身模板支设难度大以及大体积混凝施工、挡土墙泄水及墙背回填质量不易控制等一系列难题,为同类项目的施工提供了技术参考,具有显著的经济效益和社会效益,适用于复杂地形地貌条件下的超长、超大、单阶超高衡重式挡土墙边坡支护施工。The method has fast construction period, low cost, significant economic and social benefits, and solves the problems of temporary slope instability of foundation pit, difficulty in setting up wall formwork, large-volume concrete construction, retaining wall drainage and wall backfilling during construction. A series of problems such as difficult quality control provide a technical reference for the construction of similar projects, with significant economic and social benefits, suitable for ultra-long, ultra-large, single-stage ultra-high counterweight retaining walls under complex terrain conditions Slope support construction.
附图说明Description of drawings
图1是本发明实施例提供的复杂地形下超长超高衡重式挡土墙施工方法工艺流程图;1 is a process flow diagram of a construction method for an ultra-long and ultra-high counterweight type retaining wall under complex terrain provided by the embodiment of the present invention;
图2是本发明实施例中的典型原地貌断面示意图;Fig. 2 is the typical in-situ topography sectional schematic diagram in the embodiment of the present invention;
图3是本发明实施例中的边坡修整示意图;Fig. 3 is the side slope trimming schematic diagram in the embodiment of the present invention;
图4是本发明实施例中的基坑开挖工序示意图;4 is a schematic diagram of a foundation pit excavation process in an embodiment of the present invention;
图5是本发明实施例中的钢模板设计图;Fig. 5 is the steel formwork design drawing in the embodiment of the present invention;
图6是本发明实施例中的木模板设计图;Fig. 6 is the wooden formwork design drawing in the embodiment of the present invention;
图7是本发明实施例中的钢模板安装加固示意图;7 is a schematic diagram of the installation and reinforcement of the steel formwork in the embodiment of the present invention;
图8是本发明实施例中的温度监测点平面布置图;8 is a plan view of a temperature monitoring point in an embodiment of the present invention;
图9是本发明实施例中的温度监测点剖面图;9 is a sectional view of a temperature monitoring point in an embodiment of the present invention;
图10是本发明实施例中的定型化操作平台的俯视图;10 is a top view of the stereotyped operation platform in the embodiment of the present invention;
图11是本发明实施例中的定型化操作平台的正视图;Fig. 11 is the front view of the stereotyped operation platform in the embodiment of the present invention;
图12是本发明实施例中的定型化操作平台的侧视图;12 is a side view of the stereotyped operation platform in the embodiment of the present invention;
图13是本发明实施例提供的墙背台阶开挖示意图。FIG. 13 is a schematic diagram of excavation of steps on the back of a wall provided by an embodiment of the present invention.
图9中,a、混凝土,b、传感器。图10-11中,1、操作平台,2、钢爬梯,3、操作平台护栏,4、主梁,5、次梁,6、斜撑,7、旋转轴,8、钢丝网片,9、定位片,10、操作平台前支腿,11、操作平台中支腿,12、操作平台后支腿。图12中,13、衡重式挡墙,14、破裂线。In Figure 9, a, concrete, b, sensor. In Figure 10-11, 1. Operating platform, 2. Steel ladder, 3. Operating platform guardrail, 4. Main beam, 5. Secondary beam, 6. Diagonal brace, 7. Rotating shaft, 8. Steel mesh, 9. Positioning piece, 10. Front outrigger of operating platform, 11. Middle outrigger of operating platform, 12. Rear outrigger of operating platform. In Figure 12, 13, counterweight retaining wall, 14, rupture line.
具体实施方式Detailed ways
下面结合附图和具体实施例对本发明作进一步说明。The present invention will be further described below with reference to the accompanying drawings and specific embodiments.
下面以我公司承接的重庆市轨道交通四号线一期为例对本方法进行详细说明,重庆市轨道交通四号线一期唐家沱车辆段工程场平过程中在场地东侧及南侧形成高约30m的高填方边坡,设计采用衡重式挡土墙进行边坡支护。In the following, this method will be described in detail by taking the first phase of Chongqing
本工程施工环境复杂,安全风险较大,为确保安全快捷的施工,我公司组织技术骨干,从施工组织顺序、工艺历程和施工顺序等方面,通过理论计算和大胆创新总结,形成了先进的超长超高超大衡重式挡土墙施工工法,完全解决了施工中基坑临时边坡失稳、墙身模板支设难度大以及大体积混凝施工、挡土墙泄水及墙背回填质量不易控制等一系列难题,为同类项目的施工提供了技术参考,具有显著的经济效益和社会效益。The construction environment of this project is complex and the safety risk is relatively high. In order to ensure safe and fast construction, our company has organized technical backbones to form an advanced ultra-high The construction method of long, ultra-high, and super-balanced-weight retaining wall completely solves the problem of temporary slope instability of foundation pit during construction, difficulty in setting up wall formwork, and difficulty in large-volume concrete construction, retaining wall drainage and wall backfill quality. A series of difficult problems such as control provides a technical reference for the construction of similar projects, and has significant economic and social benefits.
复杂地形下超长超高衡重式挡土墙施工方法,挡墙基础开挖过程中采用跳仓法施工,挡土墙结构采用水平跳仓竖向分层的方式组织施工,模板采用钢模板与木模板结合的方式,且采用模板斜拉自平衡固定;墙身混凝土分层浇筑,墙背反滤层分层施工;挡墙基础开挖时将墙后地面挖成反坡台阶,挡土墙施工完毕后进行墙背回填。主要包括:The construction method of the super-long and super-heavy retaining wall under complex terrain. During the excavation of the retaining wall foundation, the vaulting method is adopted. The retaining wall structure adopts the horizontal vaulting and vertical layering method to organize the construction, and the formwork adopts the steel formwork. It is combined with wooden formwork, and the formwork is inclined to be self-balancing and fixed; the wall concrete is poured in layers, and the back filter layer is constructed in layers; when the retaining wall foundation is excavated, the ground behind the wall is dug into reverse slope steps, and the retaining wall Backfill the back of the wall after construction is completed. mainly include:
基坑开挖:根据现场施工条件,合理优化施工顺序,施工前将所有墙体结构逐一放样排布,按照由高到低的顺序分段分层流水作业。挡墙基础开挖过程中,采用跳仓法开挖,开挖至每层锚杆设计标高后,锚杆施工完成后继续下层开挖,采用永临结合方式,并利用理正岩土6.5进行边坡稳定性分析,进一步确保临时边坡的稳定性,保证施工安全。Foundation pit excavation: According to the construction conditions on site, rationally optimize the construction sequence. Before construction, all wall structures shall be staked out one by one, and the water flow shall be carried out in sections and layers according to the order from high to low. During the excavation process of the retaining wall foundation, the excavation method is adopted. After the excavation reaches the design elevation of the bolts of each layer, the lower layer excavation is continued after the construction of the bolts is completed. Slope stability analysis to further ensure the stability of the temporary slope and ensure construction safety.
模板安装:挡土墙结构采取水平跳仓竖向分层的方式组织施工,模板采用钢模板与木模板结合方式;创新采用模板斜拉自平衡固定法,有效解决大跨度长拉杆的拉伸变形及弹性变形,保证施工质量及施工安全。Formwork installation: The retaining wall structure is constructed by horizontal jumping and vertical layering, and the formwork adopts the combination of steel formwork and wood formwork; innovatively adopts the formwork inclined-pulling self-balancing fixation method, which effectively solves the tensile deformation of long-span long tie rods And elastic deformation, to ensure construction quality and construction safety.
混凝土浇筑:根据重庆地区气候特点,结合总体施工工期要求,合理部署土石方等交叉工序作业范围,将衡重式挡土墙施工时间安排在自然气温在10℃-20℃之间的季节组织大体积混凝土施工,同时,优化大体积混凝土配合,采用定型化操作平台保证浇筑操作条件,保证施工质量。Concrete pouring: According to the climatic characteristics of Chongqing area, combined with the requirements of the overall construction period, the cross-process operation scope such as earthwork and stonework should be reasonably deployed, and the construction time of the counterweight retaining wall will be arranged in the season when the natural temperature is between 10°C and 20°C. Concrete construction, at the same time, optimize the coordination of large-volume concrete, and use a stereotyped operation platform to ensure the pouring operation conditions and the construction quality.
反滤层施工:将反滤层材料采用包体码放,切实解决墙体挂网难度大、回填破坏及隐蔽验收等一系列难题,保证滤水效果,有效避免墙后积水现象的发生。The construction of the reverse filter layer: the materials of the reverse filter layer are stacked in the package to effectively solve a series of problems such as the difficulty of hanging the wall on the wall, backfill damage and concealed acceptance, ensure the water filtering effect, and effectively avoid the occurrence of water accumulation behind the wall.
墙背回填:将墙后地面挖成反坡台阶,台阶宽度不小于3m,高宽比不大于1:2,台阶面成5%反坡,提高基底原状土体抗滑移能力,并在后期回填施工中方便施工机械作业。优化墙背25m范围内地基处理设计做法,将重锤夯击调整为40cm/层分层碾压+2m/层冲击碾压+盲区人工夯实,通过工艺性试验指导施工,保证墙背回填地基处理施工质量的同时,避免重锤夯击对墙体稳定性的影响。Backfilling at the back of the wall: Dig the ground behind the wall into a reverse slope step, the width of the step is not less than 3m, the height-width ratio is not more than 1:2, and the step surface is a 5% reverse slope, so as to improve the anti-slip ability of the original soil of the base, and in the later stage It is convenient for construction machinery to operate during backfill construction. Optimize the design practice of foundation treatment within 25m of the back of the wall, adjust the heavy hammer ramming to 40cm/layer layered rolling + 2m/layer impact rolling + manual compaction in the blind area, and guide the construction through technological tests to ensure the backfill foundation treatment on the back of the wall While improving the construction quality, avoid the impact of heavy hammer ramming on the stability of the wall.
该方法优化施工顺序,采用跳仓法施工和利用开挖台阶有效保证施工安全,同步解决山体陡坡便道施工难题;模板斜拉自平衡固定法代替传统对拉,有效解决大跨度长拉杆的拉伸变形、弹性变形问题,降低了施工成本,保证了施工安全和质量;墙背采用边浇筑混凝土边回填的方式,极大的减少了操作架体的搭设量,方便施工,有效降低安全风险;采用定型化浇筑振捣平台施工,安全美观,与传统脚手架搭设操作平台相比较,具有操作简单、安全稳固、外观效果好的特点;墙背反滤层施工利用反滤包形成反滤层,解决了墙体挂网难度大、回填破坏、隐蔽验收及墙体静水压力等一系列难题,保证了滤水效果及挡土墙结构安全。This method optimizes the construction sequence, adopts the skipping method for construction and uses excavation steps to effectively ensure construction safety, and simultaneously solves the construction problems of access roads on steep mountain slopes; the formwork cable-pulling self-balancing fixing method replaces the traditional pairing, effectively solving the stretching of long-span long tie rods The problem of deformation and elastic deformation reduces the construction cost and ensures the construction safety and quality; the backfill method is adopted while pouring concrete, which greatly reduces the erection amount of the operating frame, facilitates construction, and effectively reduces safety risks; The construction of the stereotyped pouring and vibrating platform is safe and beautiful. Compared with the traditional scaffolding operation platform, it has the characteristics of simple operation, safety and stability, and good appearance; A series of problems such as the difficulty of hanging the net, backfill damage, concealed acceptance and wall hydrostatic pressure ensure the water filtering effect and the safety of the retaining wall structure.
如图1所示,该方法的具体施工过程为:As shown in Figure 1, the specific construction process of the method is as follows:
1)、测量放线、基坑开挖,并进行基坑验槽以及锚杆施工;1) Measure the line, excavate the foundation pit, and carry out the inspection of the foundation pit and the construction of the bolt;
2)、基础混凝土浇筑;2), foundation concrete pouring;
3)、墙身模板安装,选择合适的模板及安装形式,强身混凝土分层浇注,一次进行每一节墙身混凝土的浇注以及进行断面尺寸设计、钢筋及泄水管的安装;3), wall body formwork installation, select the appropriate formwork and installation form, strengthen the concrete layered pouring, carry out the pouring of each section of the wall body concrete at one time, and carry out the section size design, the installation of steel bars and drainage pipes;
进行墙身混凝土的浇筑,根据施工地区气候特点进行衡重式挡土墙大体积混凝土的施工,并进行挡土墙墙身监测;Carry out the concrete pouring of the wall body, carry out the construction of mass concrete of the counterweight retaining wall according to the climatic characteristics of the construction area, and carry out the monitoring of the retaining wall body;
4)、反滤层施工;4), the construction of the reverse filter layer;
5)、墙背回填;5), backfill the wall;
6)、分部工程验收。6), branch project acceptance.
具体的施工方法和操作要点如下:The specific construction methods and operation points are as follows:
1、基坑开挖:1. Excavation of foundation pit:
场地原地貌主要为陡坡,基础开挖前先采用挖掘机将挡墙基坑两侧边坡开挖成反坡台阶,并将墙背侧距基坑边3m范围内覆土翻运至墙面侧地势较低处,防止开挖过程中基坑顶部塌方及滑坡。开挖边坡严格按照设计及规范要求进行放坡,不允许偏陡,防止塌方或滑坡,保证施工边坡稳定。The original landform of the site is mainly steep slopes. Before foundation excavation, excavators are used to excavate the slopes on both sides of the retaining wall foundation pit into reverse slope steps, and the overlying soil within 3m from the back side of the wall to the side of the foundation pit is turned over to the side of the wall. In the lower part of the terrain, to prevent the top of the foundation pit from collapsing and landslides during the excavation process. The excavation slope shall be graded in strict accordance with the design and specification requirements, and steepness is not allowed to prevent landslides or landslides and ensure the stability of the construction slope.
基槽开挖前将所有墙体结构逐一放样排布,按照由高到低的顺序分段分层流水作业。基坑开挖采用机械跳仓开挖,开挖至每层锚杆设计标高后,先行施工完成当层锚杆后继续下层开挖,采用永临结合方式,进一步确保临时边坡的稳定性,采用信息法施工,利用理正岩土6.5进行边坡稳定性分析,做好施工过程中临时边坡的巡视和监测,保证施工安全。基坑边坡、台阶及基底预留20cm采用人工开挖。人工开挖前重新进行测量放样,在确定开挖正确不偏位的情况下改用人工进行基底清理,确保基底符合设计及相关规范要求。基坑开挖完成后,及时进行地基验槽,然后进行混凝土挡墙的基础混凝土浇筑。Before the excavation of the foundation trench, all the wall structures shall be staked out one by one, and the flow shall be carried out in sections and layers according to the order from high to low. The foundation pit excavation adopts mechanical jumping excavation. After the excavation reaches the design elevation of the anchor rods of each layer, the construction of the anchor rods of the current layer is completed first, and then the lower layer excavation is continued. Use the information method for construction, use Lizheng Geotechnical 6.5 to analyze the stability of the slope, and do a good job in the inspection and monitoring of the temporary slope during the construction process to ensure the safety of the construction. The slope, steps and base of the foundation pit shall be reserved for 20cm by manual excavation. Re-measure and stake out before manual excavation, and switch to manual cleaning of the base under the condition that the excavation is correct and not deviated to ensure that the base meets the design and relevant specifications. After the excavation of the foundation pit is completed, the foundation trench inspection shall be carried out in time, and then the foundation concrete pouring of the concrete retaining wall shall be carried out.
参考图2-图4所示,进一步说明基坑开挖过程。Referring to Figures 2-4, the excavation process of the foundation pit is further described.
2、墙身模板安装:2. Wall formwork installation:
1)、模板选择,1), template selection,
挡墙基础放坡、未嵌入中风化岩层部分及墙身混凝土浇筑必须安装模板。Formwork must be installed for the grading of the retaining wall foundation, the part not embedded in the weathered rock layer and the concrete pouring of the wall body.
本工程因挡土墙高度不同,导致基础尺寸及墙背坡率不一致,综合考虑工期及经济性,墙面及墙背模板采用钢模板,墙身侧模因两侧放坡且坡率不同,采用1.5cm厚胶合板。胶合板竖向背楞选用50×100mm的木枋支撑,间距300mm;横向背楞采用选用双钢管间距410mm,采用M18的对拉螺栓(两头焊接对拉片)间距600×640mm进行拉结;钢模板采用组合小钢模,每块模板截面尺寸为1.5m×1.0m,模板支设采用1托2形式,模板设计参考图5、图6所示。Due to the different heights of the retaining walls in this project, the foundation size and the slope rate of the wall back are inconsistent. Considering the construction period and economy, the wall and wall back formwork are made of steel formwork. Use 1.5cm thick plywood. The vertical back corrugation of plywood is supported by 50×100mm wooden slats with a spacing of 300mm; the horizontal back corrugation is The distance between the double steel pipes is 410mm, and the distance between the M18 pull bolts (two ends welded to the pull tabs) is 600×640mm for tie; 1 to 2 forms, the template design is shown in Figure 5 and Figure 6.
2)、自平衡斜拉杆设计与模板安拆,2) The design of self-balancing inclined rods and the installation and dismantling of formwork,
待基础混凝土浇筑完成后,将基础上立模位置用水泥砂浆找平,将第一节模板的每块小钢模人工拼装,After the foundation concrete is poured, the vertical formwork position on the foundation is leveled with cement mortar, and each small steel formwork of the first section formwork is assembled manually.
校准其垂直度和平面位置、模内尺寸,用对拉螺杆将模板与预埋钢筋连接并紧固。所有模板的轴线位置、截面尺寸、平整度、垂直度通过自检、互检、交接检严格检查,确认无误后,进入下一道工序施工。每次模板安装高度为2.0m,并根据挡墙的断面尺寸进行调整。Calibrate its verticality, plane position, and dimensions in the mold, and connect and fasten the template with the embedded steel bar with a pair of pull screws. The axis position, section size, flatness and verticality of all formwork are strictly checked through self-inspection, mutual inspection and handover inspection. The installation height of each formwork is 2.0m, and it is adjusted according to the section size of the retaining wall.
安装顺序为:搭设模板操作架(包括安装水平拉杆和剪力撑)→立墙体两侧模板→用斜拉螺栓拉结横向背楞→紧固检查→调垂直度→验收。The installation sequence is: erecting the formwork operation frame (including installing horizontal tie rods and shear braces) → formwork on both sides of the vertical wall → tie the horizontal back corrugation with diagonal-stayed bolts → tightening inspection → vertical adjustment → acceptance.
a、基础首层混凝土满灌浇筑,浇筑完成后预埋Φ25HRB335钢筋作为插筋,每根长度60cm,预埋混凝土长度不小于40cm,采用内外两排,内排间距局模板内边80cm,外排间距距模板内边175cm,并根据挡墙坡率适当调整,确保每根插筋上顶层斜拉杆与混凝土面呈45度角;a. The first layer of the foundation is filled with concrete. After the pouring is completed, the Φ25HRB335 steel bars are pre-buried as inserts, each length is 60cm, and the length of the pre-embedded concrete is not less than 40cm. The inner and outer rows are used. The spacing is 175cm away from the inner edge of the formwork, and is appropriately adjusted according to the slope rate of the retaining wall to ensure that the top-layer diagonal tie rods on each rib are at a 45-degree angle to the concrete surface;
b、模板斜拉杆采用Φ18螺纹钢,对拉采用M18螺杆;b. The inclined rod of the template adopts Φ18 threaded steel, and the pair of pulls adopts M18 screw;
c、对拉杆与插筋采用双面焊接,搭接长度不小于15cm,焊接质量满足规范要求;c. Double-sided welding is used for the tie rod and the inserting bar, and the lap length is not less than 15cm, and the welding quality meets the requirements of the specification;
d、钢模板采用1托2跳仓浇筑,每次浇筑高度1.94m,木模板每次支设两模,浇筑高度同钢模板。d. The steel formwork is poured with 1 support and 2 vaults, and the height of each pouring is 1.94m. The wooden formwork is supported with two forms each time, and the pouring height is the same as that of the steel formwork.
e、木模板加固方式同钢模板,每块模板横向设置三排拉杆。e. The reinforcement method of the wooden formwork is the same as that of the steel formwork, and three rows of tie rods are set horizontally for each formwork.
3)、斜率控制方法,3), slope control method,
模板支设时采用上下定位的方式确定斜率,测量人员在垫层上弹出每段模板下口线,上口采用锤球吊点进行定位,为模板定位提供依据。When the template is set up, the slope is determined by the way of up and down positioning. The surveyor pops up the lower opening line of each template on the cushion layer, and the upper opening is positioned by the hammer ball hanging point, which provides the basis for the template positioning.
3、混凝土浇筑:3. Concrete pouring:
1)、配合比优化及原材料选择,1), mix ratio optimization and raw material selection,
进行混凝土配比时,应优先选用低水化热的矿渣水泥,并适当使用缓凝减水剂;在保证混凝土设计强度等级前提下,适当降低水灰比,减少水泥用量。When carrying out concrete proportioning, slag cement with low hydration heat should be preferred, and setting retarding water reducing agent should be used appropriately; under the premise of ensuring the design strength grade of concrete, the water-cement ratio should be appropriately reduced and the amount of cement should be reduced.
表3-1木模板材料规格参数Table 3-1 Specifications and parameters of wood formwork materials
水泥,选用P.O42.5R级散装水泥。该水泥对混凝土的早期强度提高并不明显,前期产生的水化热符合规范要求。Cement, use P.O42.5R grade bulk cement. The cement does not improve the early strength of concrete obviously, and the hydration heat generated in the early stage meets the requirements of the specification.
粗骨料,选用5~20mm卵碎石。其压碎指标值不大于8%,最大粒径为20mm,含泥量小于1.0%,针片状颗粒含量小于5.0%。Coarse aggregate, choose 5-20mm gravel. The crushing index value is not more than 8%, the maximum particle size is 20mm, the mud content is less than 1.0%, and the needle flake particle content is less than 5.0%.
细骨料,天然砂选用特细砂,细度模数MX≥0.8,含泥量≤2.0%,无潜在碱活性;卵石机制砂(中砂),含泥量≤1.0%;细度模数控制范围为2.6~2.9;含粉量≤5.0%,母岩强度大于80MPa,压碎指标值小于25%。无潜在碱活性。Fine aggregate, natural sand is superfine sand, fineness modulus MX≥0.8, mud content≤2.0%, no potential alkali activity; pebble machine-made sand (medium sand), mud content≤1.0%; fineness modulus The control range is 2.6 to 2.9; the powder content is less than or equal to 5.0%, the strength of the parent rock is greater than 80MPa, and the crushing index value is less than 25%. No potential base activity.
粉煤灰,选用F类Ⅱ级粉煤灰。粉煤灰对降低水化热、改善混凝土和易性有利,但掺加粉煤灰的混凝土早期极限抗拉值均有所降低,对混凝土抗渗抗裂不利,因此粉煤灰的掺量严格按混凝土配合比报告进行控制,采用外掺法,即不减少配合比中的水泥用量。按配合比要求计算出每立方米混凝土所掺加粉煤灰量。Fly ash, choose F class II fly ash. Fly ash is beneficial to reduce the heat of hydration and improve the workability of concrete, but the early ultimate tensile value of concrete mixed with fly ash is reduced, which is unfavorable for concrete impermeability and crack resistance, so the amount of fly ash is strict. Control according to the concrete mix ratio report, adopt the external admixture method, that is, do not reduce the amount of cement in the mix ratio. Calculate the amount of fly ash added per cubic meter of concrete according to the mix ratio requirements.
外加剂,选用PCA-R聚羟酸型缓凝高性能减水剂。该外加剂能显著增大混凝土的流动性,改善操作性,可延缓水泥水化放热峰值,避免施工结合层冷缝现象,有效提高其抗裂防水性能。各项检测指标符合以下之规定:与生产用P.O42.5R级水泥、矿渣粉、混凝土膨胀剂、纤维等材料具有良好的适应性。每次材料进厂必须取样检测,检验合格后方可使用。每次进场取样检测其净浆流动度、减水率、混凝土坍落度经时损失、凝结时间。The admixture is PCA-R polyhydroxy acid type retarding high-performance water reducing agent. The admixture can significantly increase the fluidity of concrete, improve the operability, delay the peak of cement hydration heat release, avoid the phenomenon of cold joints in the construction bonding layer, and effectively improve its crack resistance and waterproof performance. Each test index conforms to the following requirements: It has good adaptability with P.O42.5R grade cement, slag powder, concrete expansion agent, fiber and other materials used in production. Every time the material enters the factory, it must be sampled and tested, and it can be used after passing the inspection. Each time the site is sampled, the fluidity of the slurry, the water reduction rate, the loss of concrete slump over time, and the setting time are checked.
2)、混凝土浇筑时间的选择,2), the choice of concrete pouring time,
考虑到重庆地区夏季昼夜温差较大,雨季时间较长,为避免气温升到最高时加剧混凝土内部温升及混凝土表面温度与大气温度差值过大,同时有效控制混凝土入模温度,保证衡重式挡土墙及护脚墙大体积混凝土施工质量。通过合理部署土石方施工,结合挡土墙施工工期要求,在充分调查重庆地区历年气候,并与参建各方协商同意后,本工程衡重式挡土墙施工时间全部安排在自然气温在10℃-20℃之间的2015年10月1日至2016年4月30日。Considering that the temperature difference between day and night in Chongqing is large in summer and the rainy season is long, in order to avoid the temperature rise inside the concrete and the temperature difference between the concrete surface and the atmosphere being too large when the temperature rises to the highest Construction quality of mass concrete for retaining wall and foot wall. Through reasonable deployment of earth and stone construction, combined with the construction period requirements of the retaining wall, after fully investigating the climate in Chongqing over the years, and after negotiating and agreeing with all parties involved in the construction, the construction time of the counterweight retaining wall for this project is all arranged at a natural temperature of 10 ℃ -20°C between October 1, 2015 and April 30, 2016.
3)、混凝土浇筑,3), concrete pouring,
a、加强混凝土入模温度监测,严格控制混凝土入模温度在10℃至20℃之间,混凝土的浇筑温度(振捣后50~100mm深处的温度)不得高于28℃。a. Strengthen the temperature monitoring of the concrete entering the mold, strictly control the temperature of the concrete entering the mold between 10 °C and 20 °C, and the pouring temperature of the concrete (the temperature at a depth of 50 to 100 mm after vibration) shall not be higher than 28 °C.
b、为减少每次浇筑的蓄热量,减少水化热的积聚,减小温度应力,混凝土采取分层浇筑,每层厚度控制在300mm~500mm。本工程明确以伸缩缝为分界线,每次混凝土分三至四层自左向右连续进行浇筑。每层浇筑完成后,上一层混凝土浇筑之前,应清除浇筑表面的浮浆、软弱混凝土层及松动的石子,并均匀的露出粗骨料,用压力水冲洗混凝土表面的污物,充分润湿,但不得有积水。b. In order to reduce the heat storage of each pouring, reduce the accumulation of hydration heat, and reduce the temperature stress, the concrete is poured in layers, and the thickness of each layer is controlled at 300mm to 500mm. This project clearly takes the expansion joint as the dividing line, and each time the concrete is poured continuously from left to right in three to four layers. After each layer is poured and before the last layer of concrete is poured, the laitance, weak concrete layer and loose stones on the pouring surface should be removed, and the coarse aggregate should be exposed evenly, and the dirt on the concrete surface should be washed with pressure water to fully wet , but there must be no standing water.
c、严格控制振捣时间,采用插入式振动器振实。混凝土施工中充分振捣可使骨料和水泥浆在模板中得到致密排列,有助于混凝土的密实性和抗裂性的提高,但过分振捣将使粗骨科沉落并使表层混凝土有较大收缩性,水分蒸发后易集聚形成凝缩缝。因此要求振捣手控制在20秒一30秒,或观察混凝土表面不冒气泡且已有部分泛浆即可。c. Strictly control the vibrating time, and use a plug-in vibrator to vibrate. Sufficient vibration in concrete construction can make the aggregate and cement slurry densely arranged in the formwork, which helps to improve the compactness and crack resistance of concrete. Great shrinkage, easy to agglomerate to form condensation joints after water evaporation. Therefore, the vibrator is required to be controlled within 20 seconds to 30 seconds, or it is sufficient to observe that the concrete surface is free of air bubbles and has been partially flooded.
4)、混凝土测温,4), concrete temperature measurement,
由于大体积砼浇筑量大,浇筑后在砼硬化过程中释放大量水化热。砼内外温差增大,容易产生较高温度应力和收缩应力,处理不好会导致产生温度裂缝,危害结构使用性能。因此,对于墙体大体积砼的测温监控成为难点之一,必须予以足够重视。Due to the large amount of large-volume concrete poured, a large amount of hydration heat is released during the concrete hardening process after pouring. The temperature difference between the inside and outside of the concrete increases, and it is easy to generate high temperature stress and shrinkage stress. If the treatment is not good, it will cause temperature cracks and endanger the performance of the structure. Therefore, the temperature measurement and monitoring of large-volume concrete walls has become one of the difficulties and must be paid enough attention.
a、混凝土温度测算:砼浇筑体的里表温差(不含砼收缩的当量温度)不宜大于25℃;砼浇筑体的降温速率不宜大于2.00C/d;砼浇筑体表面与大气温差不大于20℃。a. Calculation of concrete temperature: the temperature difference between the inside and outside of the concrete pouring body (excluding the equivalent temperature of concrete shrinkage) should not be greater than 25°C; the cooling rate of the concrete pouring body should not be greater than 2.00C/d; the temperature difference between the surface of the concrete pouring body and the atmosphere should not be greater than 20°C °C.
b、浇筑后的测温及温控:温度指标要求:b. Temperature measurement and temperature control after pouring: temperature index requirements:
①砼入模板基础上温升值≤50℃;①The temperature rise value is ≤50℃ on the basis of the concrete entering the formwork;
②里表温差≤25℃;②The temperature difference between the inside and outside is ≤25℃;
③降温速率≤2℃/d;③ Cooling rate≤2℃/d;
④砼表面与大气温差≤20℃④The temperature difference between the concrete surface and the atmosphere is less than or equal to 20℃
混凝土测温在混凝土不同部位进行,从浇筑到养护期全部过程进行跟踪和监测,随时了解内部的温度状况。有的放矢地采取相应技术措施,确保施工质量。在混凝土部设测温点,平面纵横向间距不大于4m,并均匀布置,用Φ8钢筋固定测温线,详见图8所示测温点平面布置图。Concrete temperature measurement is carried out in different parts of the concrete, and the whole process from pouring to curing period is tracked and monitored, so as to know the internal temperature status at any time. Corresponding technical measures are taken in a targeted manner to ensure the construction quality. Set up temperature measurement points in the concrete part, the vertical and horizontal distance between the planes is not more than 4m, and they are evenly arranged, and the temperature measurement line is fixed with Φ8 steel bars.
由于在养护开始阶段,混凝土温升比较快,在第1~3天,测温每2个小时进行一次;第4~28天,测温每4个小时进行一次。内外温差小于25℃时停止测温;如发现温差超过25℃,及时增加覆盖保温。Since the concrete temperature rises relatively quickly in the initial stage of curing, the temperature measurement is carried out every 2 hours on the 1st to 3rd day; the temperature measurement is carried out every 4 hours on the 4th to 28th day. Stop the temperature measurement when the temperature difference between the inside and outside is less than 25℃; if the temperature difference exceeds 25℃, increase the covering and insulation in time.
5)、混凝土养护,5), concrete curing,
加强混凝土的养护,严格控制混凝土内部温度不超过60℃。每次混凝土浇筑完成后,表面实行保温潮湿养护,降低混凝土表面散热速度,使其表面温度与内部温度差控制在25℃以内。采用带模板养护,在模板外挂草帘,混凝土侧面及表面喷涂保水率在90%以上的无机砼保护剂并覆盖毛毡。当实测温差过大时必要时加盖草帘进行保温养护。养护在混凝土浇筑完成后12h内开始,养护时间不少于7d。且在任意养护时间,若淋注于混凝土表面的养护水温度低于混凝土表面温度,二者间温差不得大于15℃,最大不得超过65℃。Strengthen the maintenance of concrete, and strictly control the internal temperature of concrete not to exceed 60 ℃. After each concrete pouring is completed, the surface is subjected to heat preservation and moisture conservation to reduce the heat dissipation rate of the concrete surface, so that the difference between the surface temperature and the internal temperature is controlled within 25 °C. Adopt template maintenance, hang straw curtains outside the template, spray the inorganic concrete protective agent with a water retention rate of more than 90% on the side and surface of the concrete and cover it with felt. When the measured temperature difference is too large, cover the straw curtain for thermal insulation and maintenance if necessary. The curing starts within 12h after the concrete pouring is completed, and the curing time is not less than 7d. And at any curing time, if the temperature of the curing water poured on the concrete surface is lower than the temperature of the concrete surface, the temperature difference between the two shall not exceed 15°C, and the maximum shall not exceed 65°C.
6)、定型化操作平台,6), stereotyped operating platform,
本工程衡重式挡土墙墙身截面最大为30米×18米,在浇筑混凝土时,墙身中心混凝土无法有效振捣,而传统的脚手架操作平台搭设复杂,稳定性差,操作难度大,不利于混凝土浇筑振捣及整体工期进度。定型化操作平台能够解决这些难题,采用轻型钢骨架制作而成,操作简单、快速,得到了业主及监理的认可。定型化操作平台参考图10-图12所示。The maximum section of the counterweight retaining wall in this project is 30m x 18m. When the concrete is poured, the concrete in the center of the wall cannot be vibrated effectively. However, the traditional scaffolding operation platform is complicated to set up, has poor stability, and is difficult to operate. Conducive to concrete pouring and vibrating and the overall progress of the construction period. The stereotyped operation platform can solve these problems. It is made of light-weight steel skeleton, and the operation is simple and fast. It has been recognized by the owner and the supervisor. The stereotyped operation platform is shown in Figure 10-12.
4、墙背反滤层施工:4. Construction of anti-filter layer on the back of the wall:
本工程衡重式挡墙由于高度较大,偏心距较大,若待全部浇筑完成后施工滤水层并回填台背存在较多安全隐患,如填筑质量不易保证和墙身及地基容易损坏等问题。因此施工过程中每浇筑3层,即浇筑高度不超过6m进行一次滤水层施工,并在混凝土强度达到100%时进行基础及台背的回填工作。Due to the large height and large eccentric distance of the counterweight retaining wall in this project, if the water filter layer is constructed and the backfill is completed after all the pouring is completed, there will be many hidden dangers in safety, such as the quality of filling is difficult to guarantee and the wall body and foundation are easily damaged. And other issues. Therefore, in the construction process, every 3 layers is poured, that is, the pouring height is not more than 6m, and the construction of the water filter layer is carried out, and when the concrete strength reaches 100%, the backfill work of the foundation and the back of the table is carried out.
本工程滤水层共分为三层,第一层为20mm粗砾或碎石,厚300mm,第二层为1~4mm砂砾或石屑,厚200mm,第三层为300~400g/㎡土工布。滤水层施工过程中严格控制泄水孔5%的流水坡度,并保证泄水孔向外排水顺畅,确保墙背积水可及时通过泄水孔排出,减少墙背压力,确保挡墙安全。The water filter layer of this project is divided into three layers, the first layer is 20mm coarse gravel or gravel, 300mm thick, the second layer is 1-4mm gravel or stone chips, 200mm thick, and the third layer is 300-400g/㎡ geotechnical cloth. During the construction of the water filter layer, strictly control the 5% flow gradient of the scupper hole, and ensure that the scupper hole drains smoothly to the outside, to ensure that the water accumulated on the back of the wall can be discharged through the scupper hole in time, reduce the pressure on the back of the wall, and ensure the safety of the retaining wall.
常规采用的挂网分层和挡板临时分层方式难以保证施工质量,常因回填破坏导致虑水效果不佳,对结构使用造成较大安全隐患。因此,反滤层第一层材料选用20mm粒径成品碎石,采用40*63*35cm透水性编织袋分装扎孔后码放,每层码放高度50cm,第二层材料选用1~4mm粒径机制砂,采用40*63*28cm透水性编织袋分装扎孔后码放,每层码放高度同第一层,包裹土工布后进行分层回填,回填碾压过程中做好土工布的保护。The conventionally used method of hanging net layering and temporary layering of baffles is difficult to ensure the construction quality, often due to backfill damage, resulting in poor water filtering effect, causing great safety hazards to the use of the structure. Therefore, the first layer of the reverse filter layer is made of 20mm particle size finished crushed stone, and the 40*63*35cm water-permeable woven bag is used to pack the holes and then stack them. The height of each layer is 50cm. The second layer is made of 1-4mm particle size The machine-made sand is packed in 40*63*28cm permeable woven bags and stacked after piercing. The height of each layer is the same as the first layer. After wrapping the geotextile, it is backfilled in layers, and the geotextile is protected during the backfilling and rolling process.
采用透水性编织袋将滤水材料分包码放的做法,即避免了挂网施工工艺对墙身结构破坏的影响,克服了挡板工艺施工难题,同时解决了隐蔽验收难题,该工艺施工操作简单,成本低,可大大提高工程施工质量,保证滤水效果。The use of permeable woven bags to package and stack the water filtering materials avoids the impact of the hanging net construction process on the damage to the wall structure, overcomes the construction problem of the baffle process, and solves the problem of concealed acceptance. This process is simple and easy to operate. , low cost, can greatly improve the quality of engineering construction, ensure the effect of water filtration.
5、墙背高填方施工:5. High backfill construction:
本工程现场地貌呈山坡状,挡墙基础开挖时,将墙后地面挖成反坡台阶,台阶宽度不小于3m,高宽比不大于1:2,台阶面成5%反坡,当基岩面上的覆盖层较薄时,须先清除覆盖层再开挖台阶。当覆盖层较厚且稳定时,可予以保留,在原地面挖台阶后填筑填料。The topography of the project site is in the shape of a hillside. When the retaining wall foundation is excavated, the ground behind the wall shall be dug into a reverse slope step. When the overburden on the rock surface is thin, the overburden must be removed before excavation of the steps. When the covering layer is thick and stable, it can be retained, and the filling can be filled after excavating the steps on the original ground.
1)、基础施工完成后,将墙趾坡体采用M7.5水泥砂浆砌筑片石回填。砌筑前清除片石表面泥垢、水锈等杂质,并用水清洗干净。1) After the foundation construction is completed, the toe slope of the wall shall be backfilled with M7.5 cement mortar masonry rubble. Before masonry, remove dirt, rust and other impurities on the surface of the rubble, and wash it with water.
2)、施工中回填填料选择级配良好(Cu≥5,且Cc=1~3)的砂土或碎石类土作填料,不得将淤泥、耕土以及有机质含量大于5%的土进行回填。以砾石、卵石或块石作填料时,其最大粒径不大于200mm,且粒径大于60mm颗粒含量超过总质量的50%,细粒含量5%~15%。液限大于32%、塑性指数大于26的细粒土,不得作为填料填筑,且满足墙背填料计算内摩擦角不小于35°。并结合现场实际情况优化填料,就地取材形成级配碎石土填料。2) During the construction, sandy soil or gravel soil with good gradation (Cu≥5, and Cc=1~3) shall be selected as the backfill filler, and silt, cultivated soil and soil with organic matter content greater than 5% shall not be backfilled. When gravel, pebbles or boulders are used as fillers, the maximum particle size is not more than 200mm, and the particle content is more than 50% of the total mass and the fine particle content is 5% to 15%. Fine-grained soil with a liquid limit greater than 32% and a plasticity index greater than 26 shall not be filled as filler, and the internal friction angle of the wall backfill shall not be less than 35°. Combined with the actual situation on site, the packing is optimized, and the graded gravel soil packing is formed by taking local materials.
表5.2.5-1级配碎石土填料配比表Table 5.2.5-1 Graded gravel soil filler ratio table
3)、墙背前检测回填填料含水量,确保控制在最优含水量ωop±2范围。3) Detect the water content of the backfill in front of the back of the wall to ensure that it is controlled within the optimal water content ωop±2 range.
4)、为降低地基处理对墙身产生挤压影响变形,挡土墙25m范围内不采用强夯,改为40cm/层振动碾压+2m/层冲击碾压,其中碾压盲区采用人工夯实,每层松散摊铺厚度不大于40cm,采用振动压路机逐层碾压,每2m再进行冲击碾压,每层振动碾压完成后进行压实度检测,确保压实度不小于94%,每层冲击碾压完成后进行地基承载力、有效加固深度及弹性模量检测。4) In order to reduce the extrusion and deformation of the wall body caused by the foundation treatment, dynamic compaction is not used within 25m of the retaining wall, but is changed to 40cm/layer vibration rolling + 2m/layer impact rolling, and manual compaction is used in the blind area of rolling. , the thickness of each layer of loose paving is not more than 40cm, and the vibratory roller is used to roll layer by layer, and the impact rolling is carried out every 2m. After the layer impact rolling is completed, the bearing capacity of the foundation, the effective reinforcement depth and the elastic modulus are tested.
5)、碾压时,振动压路机从低到高,从边到中,适当重叠碾压。为保证碾压的均匀性,碾压速度不能太快,先快后慢,行驶速度控制在2km/h以内。冲击碾压施工时自边坡坡脚一侧开始,顺(逆)时针行驶,以冲压面中心线为轴转圈,而后按纵向错轮冲压,全路幅排压后,再自行向内冲压,压实机的行进速度应控制在10~12km/h左右。为防止漏压,碾压时横向接头的轮迹重叠宽度为15cm~25cm,每块连接处的重叠碾压宽度为lm~1.5m,碾压遍数根据现场试验以施工时冲击轮轮迹高差小于15mm控制,并确保检测结果满足设计相关参数要求。5) When rolling, the vibrating roller should overlap and roll properly from low to high, from side to middle. In order to ensure the uniformity of rolling, the rolling speed should not be too fast, first fast then slow, and the driving speed should be controlled within 2km/h. During the impact rolling construction, start from the side of the slope foot, drive clockwise (counterclockwise), turn around the center line of the stamping surface, and then press the longitudinal staggered wheels. The traveling speed of the compactor should be controlled at about 10-12km/h. In order to prevent leakage, the overlapping width of the wheel track of the transverse joint during rolling is 15cm~25cm, and the overlapping rolling width of each joint is 1m~1.5m. The difference is less than 15mm control, and ensure that the test results meet the design-related parameter requirements.
墙背回填施工完成后,为切实保证回填质量,在过程检测全部合格的基础上,采用单孔剪切波速法试验、地表面波测试、超重型动力触探和浅层平板载荷试验等手段进行成品检测。After the backfilling of the wall is completed, in order to ensure the quality of the backfill, on the basis of all qualified process tests, the single-hole shear wave velocity test, the surface wave test, the super-heavy dynamic penetration and the shallow plate load test are used to carry out the test. Finished product inspection.
6、监控量测:6. Monitoring measurement:
1)、衡重式挡土墙采用分层分仓浇筑混凝土,根据墙面及墙背坡率计算每层模板的斜率,确定模板上下角点的坐标,为保证整个墙身的线型和坡率,模板支设过程中,采用全站仪进行精准定位,模板定位偏差为±1cm。1) The counterweight retaining wall adopts layered and sub-siloed concrete, calculates the slope of each layer of formwork according to the wall and wall back slope ratio, and determines the coordinates of the upper and lower corners of the formwork, in order to ensure the line and slope of the entire wall. During the template setting process, the total station was used for precise positioning, and the template positioning deviation was ±1cm.
2)、高边坡施工前编制系统的开挖监控方案,监控方案应包括监控目的、监控项目、监控报警值、监测方法及精度要求、监测点的布置、监测周期、工序管理和记录制度以及信息反馈系统等。2) Prepare a systematic excavation monitoring plan before high slope construction. The monitoring plan should include monitoring purposes, monitoring items, monitoring alarm values, monitoring methods and accuracy requirements, monitoring point layout, monitoring cycle, process management and recording system and information feedback system, etc.
表5.2.6-1场内监测点布置情况统计表Table 5.2.6-1 Statistical table of the layout of monitoring points in the field
3)、基准点的布设及标识:3), the layout and identification of reference points:
平面基准网按《规程》中二级导线相关技术要求和作业方法布设。根据场地实际情况,在支挡工程影响区域外的稳定地区埋设基准点4点组成导线网。基准点采用混凝土现场浇灌,嵌入铜质预制标心,以标心顶部十字丝为测量标识。基准点按一般标志埋设。The plane reference network is laid out in accordance with the relevant technical requirements and operation methods of the secondary conductors in the "Regulations". According to the actual situation of the site, 4 reference points are buried in the stable area outside the influence area of the support project to form a wire network. The reference point is poured with concrete on site, embedded in the copper prefabricated marking core, and the crosshair on the top of the marking core is used as the measurement mark. The datum point is buried according to the general mark.
重庆市轨道交通四号线一期工程唐家沱车辆段场地内自然地势北高南低,场地自然高差大,衡重式挡墙最大高度约为31米,总长度约801m,混凝土浇筑量达17万方。项目部最先投入部分木模板施工,但受到其工效差、耗时长、混凝土外观粗糙等多项缺点的制约。因此,综合考虑工期及现场情况,决定采用钢模板及墙背侧随浇筑混凝土随回填的方法施工,有效的提高了挡土墙混凝土成型外观效果,加快了工程进度,同时降低了施工成本。该工法赢得业主及监理的一致认可,为企业带来良好的社会效益。The natural terrain of the Tangjiatuo Depot of Chongqing
将本工法应用在该项目产生的效益主要表现在以下几个方面:The benefits of applying this method to this project are mainly reflected in the following aspects:
1、工期效益1. Construction period benefits
钢模板施工方便,安装简单牢固,按照挡土墙同一浇筑高度计算,钢模板安装工期为1天/节,而木模板由于加固时间长,耗时1.5天/节。缩短工期30%,加快了挡土墙施工进度,为整个平基工程的提前完工奠定了基础。The steel formwork is easy to construct, and the installation is simple and firm. According to the same pouring height of the retaining wall, the steel formwork installation period is 1 day/section, while the wood formwork takes 1.5 days/section due to the long reinforcement time. The construction period was shortened by 30%, the construction progress of the retaining wall was accelerated, and the foundation was laid for the early completion of the entire flat foundation project.
2、经济效益2. Economic benefits
模板产生效益:钢模板成本高,但周转使用率高,按照浇筑一仓衡重式挡土墙施工来计算,每仓墙身长20米,高度平均20米,每节浇筑混凝土高度2米,均采用翻模法施工:Formwork benefits: The cost of steel formwork is high, but the turnover rate is high. It is calculated according to the construction of one warehouse weighing type retaining wall. The length of each warehouse wall is 20 meters, the height is 20 meters on average, and the concrete height of each section is 2 meters. Construction by overturning method:
a、使用钢模板施工投入(每节钢模板重35kg,规格尺寸为:1m×1.5m,):(20m/1.5m×2×2节)×0.035t/节×4850元/t=9053元a. Construction investment using steel formwork (each section of steel formwork weighs 35kg, size: 1m×1.5m,): (20m/1.5m×2×2 sections)×0.035t/section×4850 yuan/t=9053 yuan
b、使用木模板施工投入(每块模板规格尺寸:1.22m×2.44m,模板按照周转3次考虑,且损耗率考虑17%):b. Construction investment using wooden formwork (the size of each formwork: 1.22m×2.44m, the formwork is considered according to the turnover of 3 times, and the loss rate is considered to be 17%):
(20m×2×2×2×2节)/(1.22m×2.44m)×(1+17%)×105元/张=13206元(20m×2×2×2×2 sections)/(1.22m×2.44m)×(1+17%)×105 yuan/piece=13206 yuan
根据工期要求,综合考虑现场情况,由于挡土墙采用跳仓开挖的形式,故周转材料投入墙身全长的一半,本工程共计43仓,故需配置22套模板。由此可得,According to the requirements of the construction period and comprehensive consideration of the site conditions, since the retaining wall adopts the form of skipping excavation, the turnover material is invested in half of the total length of the wall. The project has a total of 43 warehouses, so 22 sets of formwork need to be configured. Therefore,
共节省投入:(13206元-9053元)×22套=91366元。Total investment savings: (13,206 yuan - 9,053 yuan) × 22 sets = 91,366 yuan.
操作平台产生效益:定型化混凝土振捣操作平台因操作简单,较传统脚手架搭设工序,每次浇筑混凝土节省人力投入2个工日,架子工人工费按照180元/工日计。故节省人工费:10次/仓×43仓×180元/工日×2=154800元。Benefit from the operation platform: The stereotyped concrete vibrating operation platform is easier to operate than the traditional scaffolding process, saving 2 man-days for each pouring of concrete, and the labor cost of the scaffolding workers is calculated at 180 yuan/man-day. Therefore, the labor cost is saved: 10 times / warehouse × 43 warehouses × 180 yuan / working days × 2 = 154,800 yuan.
斜拉自平衡锚固产生效益:The benefits of the cable-stayed self-balancing anchoring:
节省钢筋拉杆:若按照平均每根斜拉杆3m计算,两根拉杆共用1根预埋钢筋,则每孔位拉杆所需投入钢筋用量为18钢筋6m,25插筋0.6m;若采用对拉杆,经计算平均每根拉杆长度为13.7m,且必须采用25钢筋,本工程累计使用拉杆数量为18200根,因此节省钢筋用量如下:Reinforcement bar saving: If calculated according to the average 3m of each diagonal stay bar, and two tie bars share 1 embedded steel bar, the required amount of steel bar for each tie bar is 6m for 18 bars and 0.6m for 25 bars; if paired bars are used, After calculation, the average length of each tie rod is 13.7m, and 25 steel bars must be used. The cumulative number of tie rods used in this project is 18,200, so the amount of steel bars saved is as follows:
【3.86kg/m×(13.7m/根-0.6m/根)-2kg/m×6m/根】×18200根=701901.2kg【3.86kg/m×(13.7m/piece-0.6m/piece)-2kg/m×6m/piece】×18200 pieces=701901.2kg
节省费用:重庆市场钢材价格为3700元/t,则节省费用为:Cost savings: The price of steel in Chongqing market is 3700 yuan/t, then the cost savings are:
701.9t×3700元/t=2597034.44元701.9t×3700 yuan/t=2597034.44 yuan
累计产生经济效益=284.3万元。Accumulated economic benefits = 2.843 million yuan.
3、社会效益3. Social benefits
该工法采用钢模板施工,混凝土外观质量好,线型流畅。墙背采用随浇筑随回填的施工方法,规避了脚手架高空作业的安全风险,赢得了良好的社会口碑。The construction method adopts steel formwork construction, the concrete appearance quality is good, and the line is smooth. The back of the wall adopts the construction method of pouring and backfilling, which avoids the safety risk of scaffolding high-altitude operation and has won a good social reputation.
通过上面具体实施方式,所述技术领域的技术人员可容易的实现本发明。但是应当理解,本发明并不限于上述的具体实施方式。在公开的实施方式的基础上,所述技术领域的技术人员可任意组合不同的技术特征,从而实现不同的技术方案。Through the above specific embodiments, those skilled in the art can easily implement the present invention. However, it should be understood that the present invention is not limited to the specific embodiments described above. On the basis of the disclosed embodiments, those skilled in the technical field can arbitrarily combine different technical features to realize different technical solutions.
除说明书所述的技术特征外,均为本专业技术人员的已知技术。Except for the technical features described in the specification, they are all known technologies by those skilled in the art.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010803900.5A CN111910679B (en) | 2020-08-12 | 2020-08-12 | Construction method of super-long and super-balanced retaining wall under complex terrain |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010803900.5A CN111910679B (en) | 2020-08-12 | 2020-08-12 | Construction method of super-long and super-balanced retaining wall under complex terrain |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN111910679A true CN111910679A (en) | 2020-11-10 |
| CN111910679B CN111910679B (en) | 2022-02-18 |
Family
ID=73283956
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202010803900.5A Active CN111910679B (en) | 2020-08-12 | 2020-08-12 | Construction method of super-long and super-balanced retaining wall under complex terrain |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN111910679B (en) |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113651571A (en) * | 2021-07-06 | 2021-11-16 | 浙江华东工程建设管理有限公司 | A kind of ultra-lean consolidation backfill suitable for backfill of retaining wall and its construction technology |
| CN114657940A (en) * | 2022-05-07 | 2022-06-24 | 四川路航建设工程有限责任公司 | Formwork system and construction method of plywood formwork cast-in-situ gravity type dike retaining wall concrete |
| CN115142465A (en) * | 2022-06-18 | 2022-10-04 | 中国水利水电第十六工程局有限公司 | Construction method of inclined gravity retaining wall |
| CN115383530A (en) * | 2021-05-24 | 2022-11-25 | 山东艺兴明远新材料有限公司 | Extruded sheet all-in-one of making level |
| CN115492136A (en) * | 2022-11-01 | 2022-12-20 | 中国建筑第五工程局有限公司 | Reinforcing device and reinforcing method for side wall of irregular rock stratum |
| CN117926652A (en) * | 2022-10-17 | 2024-04-26 | 中建二局第二建筑工程有限公司 | Overhead road protection device and construction method thereof |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103469815A (en) * | 2013-09-23 | 2013-12-25 | 江苏省交通科学研究院股份有限公司 | Construction method for protecting slope of reinforced-concrete retaining wall |
| CN206205452U (en) * | 2016-10-13 | 2017-05-31 | 中建八局第二建设有限公司 | A kind of telescopic bulk concrete pours regularization operating platform |
| CN109736346A (en) * | 2018-12-13 | 2019-05-10 | 中交一公局桥隧工程有限公司 | Structure and construction method of reinforced balance-weight retaining wall reinforced by steel anchor pipe in weathered rock formation |
| CN110056000A (en) * | 2019-05-24 | 2019-07-26 | 中国电建集团贵阳勘测设计研究院有限公司 | Construction method and structure of balance weight type retaining wall |
| CN110344439A (en) * | 2019-07-30 | 2019-10-18 | 中建五局第三建设有限公司 | Construction method of rear retaining wall drain hole |
-
2020
- 2020-08-12 CN CN202010803900.5A patent/CN111910679B/en active Active
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103469815A (en) * | 2013-09-23 | 2013-12-25 | 江苏省交通科学研究院股份有限公司 | Construction method for protecting slope of reinforced-concrete retaining wall |
| CN206205452U (en) * | 2016-10-13 | 2017-05-31 | 中建八局第二建设有限公司 | A kind of telescopic bulk concrete pours regularization operating platform |
| CN109736346A (en) * | 2018-12-13 | 2019-05-10 | 中交一公局桥隧工程有限公司 | Structure and construction method of reinforced balance-weight retaining wall reinforced by steel anchor pipe in weathered rock formation |
| CN110056000A (en) * | 2019-05-24 | 2019-07-26 | 中国电建集团贵阳勘测设计研究院有限公司 | Construction method and structure of balance weight type retaining wall |
| CN110344439A (en) * | 2019-07-30 | 2019-10-18 | 中建五局第三建设有限公司 | Construction method of rear retaining wall drain hole |
Cited By (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115383530A (en) * | 2021-05-24 | 2022-11-25 | 山东艺兴明远新材料有限公司 | Extruded sheet all-in-one of making level |
| CN115383530B (en) * | 2021-05-24 | 2024-01-26 | 山东艺兴明远新材料有限公司 | Extruded sheet leveling all-in-one |
| CN113651571A (en) * | 2021-07-06 | 2021-11-16 | 浙江华东工程建设管理有限公司 | A kind of ultra-lean consolidation backfill suitable for backfill of retaining wall and its construction technology |
| CN114657940A (en) * | 2022-05-07 | 2022-06-24 | 四川路航建设工程有限责任公司 | Formwork system and construction method of plywood formwork cast-in-situ gravity type dike retaining wall concrete |
| CN114657940B (en) * | 2022-05-07 | 2024-05-14 | 四川路航建设工程有限责任公司 | Formwork supporting system for cement slab formwork cast-in-situ gravity type embankment retaining wall concrete and construction method |
| CN115142465A (en) * | 2022-06-18 | 2022-10-04 | 中国水利水电第十六工程局有限公司 | Construction method of inclined gravity retaining wall |
| CN115142465B (en) * | 2022-06-18 | 2024-05-14 | 中国水利水电第十六工程局有限公司 | Construction method of upward inclined gravity retaining wall |
| CN117926652A (en) * | 2022-10-17 | 2024-04-26 | 中建二局第二建筑工程有限公司 | Overhead road protection device and construction method thereof |
| CN115492136A (en) * | 2022-11-01 | 2022-12-20 | 中国建筑第五工程局有限公司 | Reinforcing device and reinforcing method for side wall of irregular rock stratum |
Also Published As
| Publication number | Publication date |
|---|---|
| CN111910679B (en) | 2022-02-18 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN111910679B (en) | Construction method of super-long and super-balanced retaining wall under complex terrain | |
| CN111576454B (en) | Combined protective structure for slope retaining wall plus steel pipe piles and construction method thereof | |
| CN107558480B (en) | Construction method of subgrade three-dimensional drainage reinforced ecological slope protection structure | |
| CN109736346B (en) | Steel anchor pipe reinforced weathered rock stratum reinforced weighing type retaining wall structure and construction method | |
| CN104790428B (en) | Ultrahigh integral steel-plastic grid reinforced earth abutment retaining wall structure and construction method thereof | |
| CN106192907B (en) | Add the construction method of 150m~300m grade high concrete panel rock-fill dams of cement sand and gravel structure sheaf | |
| CN104264680B (en) | The method for processing foundation of Tian Wa joint portion, a kind of collapsible loess slope | |
| CN105155558A (en) | Combined retaining structure and construction method thereof | |
| CN103334450B (en) | Construction method of pile precast slab retaining wall with drainage ditch | |
| CN106930319A (en) | A kind of high slope framed revetment and its construction method | |
| CN109914161B (en) | Construction method of high-speed railway filling roadbed in soft soil area | |
| CN116377780A (en) | Construction Method of High Fill Subgrade in Mountainous Highway | |
| CN106836238A (en) | A kind of construction method and its structure for falling the vertical floor support replacement of grade formula deep basal pit | |
| CN111894641A (en) | Treatment and construction process for tunnel to penetrate through super-huge water-containing cavity karst cave | |
| CN114991165A (en) | Construction method for subway deep foundation pit adjacent to railway business line | |
| CN109706952A (en) | Large-scale well-sinking construction method | |
| CN110905529B (en) | Construction method of loess tunnel penetrating through landslide mass | |
| CN115679993A (en) | Construction method of shallow-buried bias ultra-small clear distance tunnel portal section structure | |
| CN103572777B (en) | A kind of geotechnical grid retaining wall and construction method thereof | |
| CN116446915A (en) | Shallow tunnel portal supporting structure and construction method | |
| CN116575475A (en) | Construction method of ultra-large foundation pit supporting structure of fully-buried sewage plant | |
| CN204676593U (en) | A super-high integral steel-plastic grid reinforced earth abutment retaining wall structure | |
| CN221589652U (en) | Hundred-meter-level high-filling structure | |
| CN109098203A (en) | Plateau Permafrost Regions reinforced earth retaining wall and its construction method | |
| CN116517206A (en) | Construction method of integrated basement ramp combining forever |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |