CN111851318A - Side span formwork system of cantilever bridge and its construction method - Google Patents

Side span formwork system of cantilever bridge and its construction method Download PDF

Info

Publication number
CN111851318A
CN111851318A CN202010920835.4A CN202010920835A CN111851318A CN 111851318 A CN111851318 A CN 111851318A CN 202010920835 A CN202010920835 A CN 202010920835A CN 111851318 A CN111851318 A CN 111851318A
Authority
CN
China
Prior art keywords
support
side span
mold
construction method
formwork system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010920835.4A
Other languages
Chinese (zh)
Other versions
CN111851318B (en
Inventor
豆德存
崔芳胜
王勇
弓永涛
权龙�
黄玉娟
汪传福
钱江
郜超群
张敏
章焕
马正峰
关珊
鲁劲松
苏陈明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Gourgen Traffic Construction Co Ltd
Original Assignee
Anhui Gourgen Traffic Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Gourgen Traffic Construction Co Ltd filed Critical Anhui Gourgen Traffic Construction Co Ltd
Priority to CN202010920835.4A priority Critical patent/CN111851318B/en
Publication of CN111851318A publication Critical patent/CN111851318A/en
Application granted granted Critical
Publication of CN111851318B publication Critical patent/CN111851318B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了悬臂桥边跨支模体系及其施工方法,属于桥梁建筑技术领域,预埋钢板设置在边跨支墩顶部,在预埋钢板上焊接安装支撑架,相邻支撑架之间设置加强撑,在支撑架和已浇筑桥段间安装临时固定墩、顶部纵梁、支架纵梁、后上横梁、后下横梁和前横梁,在底部纵梁上设置横向分配梁;底模主要铺设在横向分配梁上,另一部分铺设在支撑架和永久支座之间,由内临时支座支撑,外模支架设在支架纵梁上,翼缘底模和外侧模设置在外模支架上,分别通过对拉拉杆固定,底模上安装有内模,利用边跨支墩顶部支撑架和已浇筑桥段作为悬臂桥边跨合拢段施工的重力支撑结构,减少吊装工作量,从而减少了施工工期和成本。

Figure 202010920835

The invention discloses a side span formwork system of a cantilever bridge and a construction method thereof, and belongs to the technical field of bridge construction. Pre-embedded steel plates are arranged on the top of side span buttresses, support frames are welded and installed on the embedded steel plates, and adjacent support frames are arranged between adjacent support frames. Strengthen the bracing, install temporary fixed piers, top longitudinal beams, support longitudinal beams, rear upper beams, rear lower beams and front beams between the support frame and the poured bridge section, and set up a horizontal distribution beam on the bottom longitudinal beam; the bottom formwork is mainly laid On the horizontal distribution beam, the other part is laid between the support frame and the permanent support, supported by the inner temporary support, the outer mold support is set on the support longitudinal beam, and the flange bottom mold and the outer mold are set on the outer mold support, respectively. By fixing the tie rods, the bottom mold is installed with an inner mold, and the top support frame of the side span pier and the poured bridge section are used as the gravity support structure for the construction of the side span closing section of the cantilever bridge, which reduces the hoisting workload and thus reduces the construction period. and cost.

Figure 202010920835

Description

悬臂桥边跨支模体系及其施工方法Side span formwork system of cantilever bridge and its construction method

技术领域technical field

本发明属于桥梁建造技术领域,特别是涉及悬臂桥边跨支模体系及其施工方法。The invention belongs to the technical field of bridge construction, in particular to a side span formwork system of a cantilever bridge and a construction method thereof.

背景技术Background technique

随着我国社会经济的不断发展,桥梁建设进入高速发展时期,当今的道路和桥梁的建设投资规模越来越大,相关施工技术水平要求越来越高,结构复杂程度逐渐加深。其中悬臂梁桥指的是以一端或两端向外自由悬出的简支梁作为上部结构主要承重构件的梁桥。悬臂梁桥一般为静定结构,结构内力不受地基变形影响,对基础要求较低。在多孔桥中,在墩上只需要设置一个支座,从而相应地减小了桥墩的尺寸,也节省了基础工程的材料用量,因此在桥梁建设中得到广泛应用。With the continuous development of my country's social economy, bridge construction has entered a period of rapid development. Today's road and bridge construction investment scale is increasing, the relevant construction technology level is getting higher and higher, and the structural complexity is gradually deepening. The cantilever girder bridge refers to a girder bridge in which a simply supported beam with one or both ends freely suspended outwards is used as the main load-bearing member of the upper structure. Cantilever girder bridges are generally statically indeterminate structures, and the internal force of the structure is not affected by the deformation of the foundation, and the requirements for the foundation are low. In a porous bridge, only one support needs to be set on the pier, which reduces the size of the pier accordingly and saves the material consumption of the foundation engineering, so it is widely used in bridge construction.

悬臂梁桥不易采用装配式施工,我们在浇筑大跨径的悬臂桥梁的时候通常采用吊篮的方法,就地分段悬臂作业。比如在边跨合拢段施工中,现有专利CN103556578B利用了边跨墩顶与挂篮作为悬臂浇筑连续梁直线段与边跨合拢段浇筑的重力支撑结构,代替了在地面上搭设边跨现浇支架作为其混凝土工程的重力支撑结构。但是此专利只写明如何支立外模,未写明如何支立内模,对于内模的支立常见的需要架立复杂的吊篮体系,在费用昂贵、搭建繁琐且速度缓慢的支架模板上现浇。Cantilever girder bridges are not easy to adopt prefabricated construction. When pouring large-span cantilever bridges, we usually use the method of hanging baskets to perform segmented cantilever operations on site. For example, in the construction of the side span closed section, the existing patent CN103556578B uses the side span pier top and the hanging basket as the gravity support structure for the cantilever pouring of the continuous beam straight line section and the side span closed section, instead of erecting the side span cast-in-place on the ground. The bracket acts as the gravity support structure for its concrete works. However, this patent only states how to support the outer mold, but does not specify how to support the inner mold. For the support of the inner mold, it is common to erect a complex hanging basket system, which is expensive, cumbersome and slow. Pouring on top.

因此,目前亟需寻求一种施工效率高,经济效益好且结构简单稳固的悬臂桥边跨支模体系及其施工方法显得十分重要。Therefore, it is very important to find a cantilever bridge side span formwork system and its construction method with high construction efficiency, good economic benefits and simple and stable structure.

发明内容SUMMARY OF THE INVENTION

本发明的目的就是克服上述缺陷,提供一种悬臂桥边跨支模体系及其施工方法。The purpose of the present invention is to overcome the above-mentioned defects and provide a cantilever bridge side span formwork system and its construction method.

为解决上述技术问题,本发明是通过以下技术方案实现的:In order to solve the above-mentioned technical problems, the present invention is achieved through the following technical solutions:

本发明为悬臂桥边跨支模体系施工方法,包括以下步骤:The present invention provides a construction method for a side span formwork system of a cantilever bridge, comprising the following steps:

步骤一、在浇筑边跨支墩顶部预埋预埋钢板,在预埋钢板上安装具有上、中、下三道支撑横梁的支撑架,浇筑边跨支墩顶部安装设置外临时支座;Step 1. Pre-embedded steel plates are pre-embedded at the top of the pouring side-span buttresses, a support frame with upper, middle and lower support beams is installed on the pre-embedded steel plates, and external temporary supports are installed on the top of the pouring side-span buttresses;

步骤二、在已浇筑桥段的顶板上方安装临时固定墩,通过后吊带将后上横梁固定在已浇筑桥段的顶板下方、将后下横梁锚固在已浇筑桥段的底板下方,顶部纵梁的两端分别连接于临时固定墩和支撑架上道的支撑横梁,支架纵梁的两端分别连接于支撑架中道的支撑横梁以及顶板设置的吊带,底部纵梁的两端分别连接于外临时支座和底板上所设的后吊带,底部纵梁上铺满横向分配梁;Step 2: Install a temporary fixed pier above the top plate of the poured bridge section, fix the rear upper beam under the top plate of the poured bridge section through the rear sling, anchor the rear lower beam under the bottom plate of the poured bridge section, and the top longitudinal beam The two ends of the pier are respectively connected to the temporary fixed pier and the supporting beam on the upper road of the support frame. Temporary supports and rear slings on the bottom plate, and the bottom longitudinal beams are covered with horizontal distribution beams;

步骤三、顶部纵梁和支架纵梁中部区域安装前吊带,前吊带上吊挂前横梁;Step 3. Install the front sling in the middle area of the top longitudinal beam and the bracket longitudinal beam, and hang the front beam on the front sling;

步骤四、在横向分配梁上安装底模,同时在支撑架和永久支座之间铺设底模,由内临时支座支撑;Step 4. Install the bottom mold on the horizontal distribution beam, and at the same time lay the bottom mold between the support frame and the permanent support, which is supported by the inner temporary support;

步骤五、在支架纵梁上安装外模支架,并通过对拉拉杆将翼缘底模和外侧模固定在外模支架上;Step 5. Install the outer mold bracket on the longitudinal beam of the bracket, and fix the flange bottom mold and the outer mold on the outer mold bracket by pulling the tie rods;

步骤六、在边跨段底板上绑扎钢筋,将内模安装在底膜上。Step 6: Bind steel bars on the bottom plate of the side span, and install the inner mold on the bottom film.

进一步地,内模通过支撑角钢悬空设置在底模上方,支撑角钢一端设置在支撑架的下道的支撑横梁上,另一端通过锚固杆固定在已浇筑桥段底板上方。Further, the inner mold is suspended above the bottom mold through the support angle steel, one end of the support angle steel is arranged on the support beam of the lower channel of the support frame, and the other end is fixed above the bottom plate of the poured bridge section through the anchor rod.

进一步地,内模包括支撑角钢、下内模、内侧模、上内模、连接角钢和内支撑,下内模、上内模和两内侧模构成一矩形筒,其转角处通过连接角钢固定,支撑角钢连接于下内模上,支撑角钢设有两条,支撑角钢和上内模边缘处的连接角钢之间通过内支撑连接。Further, the inner mold includes a support angle steel, a lower inner mold, an inner mold, an upper inner mold, a connecting angle steel and an inner support, and the lower inner mold, the upper inner mold and the two inner molds form a rectangular tube, and the corner is fixed by connecting the angle steel, The supporting angle steel is connected to the lower inner mold, and there are two supporting angle steels, and the supporting angle steel and the connecting angle steel at the edge of the upper inner mold are connected by an inner support.

边跨支墩顶部设置有两个预埋钢板,支撑架由两支撑纵梁以及设置在支撑纵梁间的上、中、下三道支撑横梁构成,支撑纵梁的底部设于预埋钢板上,支撑架设有两个,两支撑架之间通过加强撑连接。Two pre-embedded steel plates are arranged at the top of the side span buttresses. The support frame is composed of two supporting longitudinal beams and three upper, middle and lower supporting beams arranged between the supporting longitudinal beams. The bottom of the supporting longitudinal beams is set on the pre-embedded steel plate. There are two supporting frames, and the two supporting frames are connected by reinforcing braces.

进一步地,边跨支墩的顶部被支撑架分割为两安装位,每一安装位上自撑架至边跨支墩顶面的边缘处依次设有内临时支座、永久支座、外临时支座。Further, the top of the side span buttress is divided into two installation positions by the support frame, and each installation position is provided with an inner temporary support, a permanent support and an outer temporary support in sequence from the support frame to the edge of the top surface of the side span support pier. stand.

进一步地,底模和永久支座的顶部等高。Further, the bottom mold and the top of the permanent support are of equal height.

进一步地,前横梁和后下横梁处于同一水平高度处。Further, the front cross member and the rear lower cross member are at the same level.

进一步地,在支撑架的侧面安装端模。Further, an end form is installed on the side of the support frame.

悬臂桥边跨支模体系,是通过以上步骤进行搭建的。The cantilever bridge side span formwork system is built through the above steps.

本发明具有以下有益效果:The present invention has the following beneficial effects:

采用无吊篮进行边跨合拢段施工,利用边跨支墩顶部支撑架和已浇筑桥段作为悬臂桥边跨合拢段施工的重力支撑结构,减少吊装工作量,从而减少了施工工期和成本。The side span closed section construction is carried out without a hanging basket, and the top support frame of the side span pier and the poured bridge section are used as the gravity support structure for the construction of the side span closed section of the cantilever bridge, which reduces the hoisting workload, thereby reducing the construction period and cost.

通过支撑纵梁和支撑横梁之间焊接构成支撑架,结构简单,同时方便边跨支墩两侧的边跨段现浇梁同步施工,减小了施工周期,其通过加强撑进行加固,进一步提高支撑结构的稳定性。The support frame is formed by welding between the support longitudinal beam and the support cross beam, which has a simple structure and facilitates the simultaneous construction of the cast-in-place beams of the side spans on both sides of the side span buttresses, which reduces the construction period. The stability of the support structure.

内模安装时无需内支撑架,结构稳固简单,安装方便,减少钢材使用量同时能高效快速施工。There is no need for an inner support frame when the inner mold is installed, the structure is stable and simple, the installation is convenient, the consumption of steel is reduced, and the construction is efficient and fast.

当然,实施本发明的任一产品并不一定需要同时达到以上所述的所有优点。Of course, it is not necessary for any product embodying the present invention to achieve all of the above-described advantages simultaneously.

附图说明Description of drawings

为了更清楚地说明本发明实施例的技术方案,下面将对实施例描述所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to illustrate the technical solutions of the embodiments of the present invention more clearly, the following briefly introduces the accompanying drawings used in the description of the embodiments. Obviously, the drawings in the following description are only some embodiments of the present invention. For those of ordinary skill in the art, other drawings can also be obtained from these drawings without any creative effort.

图1是悬臂桥边跨支模体系的示意图;Figure 1 is a schematic diagram of the side span formwork system of a cantilever bridge;

图2是墩顶支撑架的示意图;Fig. 2 is the schematic diagram of pier top support frame;

图3是边跨支墩墩顶支撑体系的示意图;Figure 3 is a schematic diagram of the pier top support system for side span buttresses;

图4是模板托架体系的示意图;Figure 4 is a schematic view of a formwork carrier system;

图5是底模布置的示意图;Fig. 5 is the schematic diagram of bottom mold arrangement;

图6是翼缘底模和外侧模布置的示意图;Fig. 6 is the schematic diagram of flange bottom mould and outboard mould arrangement;

图7是内模的断面示意图;Figure 7 is a schematic cross-sectional view of the inner mold;

图8是悬臂桥边跨支模体系的断面示意图;Figure 8 is a schematic cross-sectional view of the side span formwork system of a cantilever bridge;

附图中,各标号所代表的部件列表如下:In the accompanying drawings, the list of components represented by each number is as follows:

1-加强撑;2-支撑横梁;3-端模;4-支撑纵梁;5-预埋钢板;6-内临时支座;7-永久支座;8-外临时支座;9-顶部纵梁;10-底模;11-底部纵梁;12-横向分配梁;13-前吊带;14-支撑角钢;15-支架纵梁;16-下内模;17-前横梁;18-临时固定墩;19-后上横梁;20-锚固杆;21-后吊带;22-后下横梁;23-边跨支墩;24-内模;25-外模支架;26-内侧模;27-上内模;28-连接角钢;29-内支撑;30-已浇筑桥段;31-翼缘底模;32-外侧模。1- Reinforcing support; 2- Support beam; 3- End form; 4- Support longitudinal beam; 5- Pre-embedded steel plate; 6- Inner temporary support; 7- Permanent support; 8- Outer temporary support; 9- Top Longitudinal beam; 10-bottom formwork; 11-bottom longitudinal beam; 12-transverse distribution beam; 13-front sling; 14-support angle steel; 15-support longitudinal beam; 16-lower inner formwork; 17-front beam; 18-temporary Fixed pier; 19-rear upper beam; 20-anchor rod; 21-rear sling; 22-rear lower beam; 23-side span buttress; 24-inner mold; 25-outer mold bracket; 26-inner mold; Upper inner mold; 28-connecting angle steel; 29-inner support; 30-cast bridge section; 31-flange bottom mold; 32-outside mold.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其它实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

在本发明的描述中,需要理解的是,术语“开孔”、“上”、“下”、“厚度”、“顶”、“中”、“长度”、“内”、“四周”等指示方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的组件或元件必须具有特定的方位,以特定的方位构造和操作,因此不能理解为对本发明的限制。In the description of the present invention, it is to be understood that the terms "opening", "upper", "lower", "thickness", "top", "middle", "length", "inside", "around", etc. Indicates the orientation or positional relationship, only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the components or elements referred to must have a specific orientation, are constructed and operated in a specific orientation, and therefore should not be construed as a limitation of the present invention .

钢筋之间焊接技术要求,混凝土浇筑要点、素土夯实、桩基施工质量标准等,本发明不再累述,重点阐述本发明结构的实施方式。The technical requirements for welding between steel bars, the key points of concrete pouring, the compaction of plain soil, and the construction quality standards of pile foundations, etc., are not repeated in the present invention, and the embodiments of the structure of the present invention are focused on.

请参阅图1-8所示,本发明为悬臂桥边跨支模体系:Please refer to Figures 1-8, the present invention is a cantilever bridge side span formwork system:

边跨支墩23顶部设置有两个预埋钢板5,并在两预埋钢板5上焊接支撑纵梁4,两预埋钢板5上对应位置上的两支撑纵梁4之间在通过横向设置的三条道支撑横梁2连接在一起,由支撑纵梁4和支撑横梁2构成支撑架,之后在形成的支撑架之间通过加强撑1连接在一起,并将边跨支墩23的顶部分割为两部分,每一部分上由支撑架至边跨支墩23边缘处依次设置有内临时支座6、永久支座7、外临时支座8。Two pre-embedded steel plates 5 are arranged on the top of the side span buttresses 23 , and support longitudinal beams 4 are welded on the two pre-embedded steel plates 5 . The three supporting beams 2 are connected together, and the supporting frame is formed by the supporting longitudinal beam 4 and the supporting beam 2, and then the formed supporting frames are connected together by the reinforcing brace 1, and the top of the side span support pier 23 is divided into Two parts, each part is provided with an inner temporary support 6, a permanent support 7, and an outer temporary support 8 in sequence from the support frame to the edge of the side span buttress 23.

已浇筑桥段30的端部具有顶板和底板,其中后上横梁19通过后吊带21固定在顶板的下,后下横梁22均通过后吊带21固定在底板的下,其中在后下横梁22和外临时支座8上架设底部纵梁11,其中底部纵梁11设有一排,在支撑架上中间的一个支撑横梁2和后上横梁19之间架设支架纵梁15,另外的在顶板的上表面还设置有临时固定墩18,临时固定墩18和位于支撑架顶部的支撑横梁2上搭设有顶部纵梁9,相应的顶部纵梁9和支架纵梁15中部区域安装前吊带13,在前吊带13上固定有前横梁17,其中前横梁17后下横梁22同一水平高度处,并在底部纵梁11架设一排横向分配梁12,底模10则铺设在横向分配梁12上,其中在支撑架和永久支座7之间也铺设有底模10,该部分底模10由内临时支座6支撑,支架纵梁15上架设有外模支架25上,外模支架25安装有翼缘底模31和外侧模32,具体的外模支架25的截面呈阶梯状,其外表面安装有外侧模,台阶面上设置有翼缘底模31,具体的通过对拉拉杆进行拉紧固定,支架纵梁15抵触于翼缘底模31的下表面。The end of the poured bridge section 30 has a top plate and a bottom plate, wherein the rear upper beam 19 is fixed under the top plate by the rear strap 21, and the rear lower beam 22 is fixed under the bottom plate by the rear strap 21, wherein the rear lower beam 22 and A bottom longitudinal beam 11 is erected on the outer temporary support 8, wherein the bottom longitudinal beam 11 is provided with a row, and a bracket longitudinal beam 15 is erected between a supporting beam 2 in the middle of the support frame and the rear upper beam 19, and the other is on the top plate. The surface is also provided with a temporarily fixed pier 18. The temporary fixed pier 18 and the support beam 2 at the top of the support frame are provided with a top longitudinal beam 9. The corresponding top longitudinal beam 9 and the middle area of the support longitudinal beam 15 are installed with front slings 13. A front beam 17 is fixed on the sling 13, wherein the front beam 17 and the rear lower beam 22 are at the same level, and a row of transverse distribution beams 12 is erected on the bottom longitudinal beam 11, and the bottom mold 10 is laid on the transverse distribution beam 12. A bottom mold 10 is also laid between the support frame and the permanent support 7, and this part of the bottom mold 10 is supported by the inner temporary support 6, the support longitudinal beam 15 is framed with an outer mold support 25, and the outer mold support 25 is installed with flanges The bottom mold 31 and the outer mold 32, the specific outer mold support 25 has a stepped cross-section, an outer mold is installed on its outer surface, and a flange bottom mold 31 is provided on the stepped surface. Specifically, the tension rod is tightened and fixed. The bracket longitudinal beam 15 abuts against the lower surface of the flange bottom mold 31 .

内模24通过支撑角钢14悬空设置在底模10上方,支撑角钢14一端设置在支撑架的最下方的支撑横梁2上,另一端通过锚固杆20固定在已浇筑桥段30底板上方,支撑架的侧面安装有端模3。The inner mold 24 is suspended above the bottom mold 10 through the supporting angle steel 14, one end of the supporting angle steel 14 is arranged on the lowermost supporting beam 2 of the support frame, and the other end is fixed on the bottom plate of the poured bridge section 30 through the anchor rod 20. An end die 3 is installed on the side of the .

内模24包括支撑角钢14、下内模16、内侧模26、上内模27、连接角钢28和内支撑29,其整体焊接成型。The inner mold 24 includes a supporting angle steel 14, a lower inner mold 16, an inner mold 26, an upper inner mold 27, a connecting angle steel 28 and an inner support 29, which are integrally welded and formed.

下内模16、上内模27和两内侧模26构成一矩形筒,其转角处通过连接角钢28固定。The lower inner mold 16 , the upper inner mold 27 and the two inner molds 26 form a rectangular tube, the corners of which are fixed by connecting angle steels 28 .

支撑角钢14连接于下内模16上,且支撑角钢14设有两条并分别和上内模27两边缘处的两连接角钢28之间通过内支撑29连接。The supporting angle steel 14 is connected to the lower inner mold 16 , and two supporting angle steels 14 are provided and are respectively connected with the two connecting angle steels 28 at the two edges of the upper inner mold 27 through inner supports 29 .

悬臂桥边跨支模体系施工方法:Construction method of side span formwork system of cantilever bridge:

步骤一、在浇筑边跨支墩23顶部预埋预埋钢板5,在预埋钢板5上安装具有上、中、下三道支撑横梁2的支撑架,其中,可将由两支撑纵梁4以及设置在支撑纵梁4间的上、中、下三道支撑横梁2预先组装完成,之后再吊装至边跨支墩23的顶面安装在预埋预埋钢板5上,另外的再次通过加强撑1对两支撑架进行连接加固,其中在后续的搭建过程完工后,在支撑架一侧安装端模3;Step 1. Pre-embedding the pre-embedded steel plate 5 at the top of the pouring side span buttresses 23, and installing the support frame with the upper, middle and lower supporting beams 2 on the pre-embedded steel plate 5, wherein the two supporting longitudinal beams 4 and The upper, middle and lower support beams 2 arranged between the support longitudinal beams 4 are pre-assembled, and then hoisted to the top surface of the side span buttresses 23 to be installed on the embedded steel plate 5. 1. Connect and reinforce the two support frames. After the subsequent construction process is completed, install the end form 3 on one side of the support frame;

其中,浇筑边跨支墩23顶部安装设置外临时支座8,外临时支座8靠内处的边跨支墩23顶部还依次设置有永久支座7和内临时支座6。Among them, the outer temporary support 8 is installed on the top of the pouring side span support pier 23, and the top of the side span support 23 at the inner side of the outer temporary support 8 is also provided with a permanent support 7 and an inner temporary support 6 in sequence.

步骤二、在已浇筑桥段30的顶板上方安装临时固定墩18,通过后吊带21将后上横梁19固定在已浇筑桥段30的顶板下方、将后下横梁22锚固在已浇筑桥段30的底板下方,之后架设底部纵梁11、支架纵梁15和部纵梁9;Step 2: Install the temporary fixed pier 18 above the top plate of the poured bridge section 30, fix the rear upper cross beam 19 under the top plate of the poured bridge section 30 through the rear sling 21, and anchor the rear lower cross beam 22 on the poured bridge section 30. Below the bottom plate, the bottom longitudinal beam 11, the bracket longitudinal beam 15 and the upper longitudinal beam 9 are erected;

具体的顶部纵梁9的两端分别连接于临时固定墩18和支撑架上道的支撑横梁2,支架纵梁15的两端分别连接于支撑架中道的支撑横梁2以及顶板设置的吊带21,底部纵梁11的两端分别连接于外临时支座8和底板上所设的后吊带21,底部纵梁11上铺满横向分配梁12。Specifically, the two ends of the top longitudinal beam 9 are respectively connected to the temporary fixed pier 18 and the supporting beam 2 on the upper road of the support frame, and the two ends of the supporting longitudinal beam 15 are respectively connected to the supporting beam 2 of the middle road of the supporting frame and the suspenders 21 provided on the top plate. , the two ends of the bottom longitudinal beam 11 are respectively connected to the outer temporary support 8 and the rear strap 21 provided on the bottom plate, and the bottom longitudinal beam 11 is covered with horizontal distribution beams 12 .

步骤三、顶部纵梁9和支架纵梁15中部区域安装前吊带13,前吊带13上吊挂前横梁17。Step 3: Install the front sling 13 in the middle area of the top longitudinal beam 9 and the support longitudinal beam 15 , and hang the front cross beam 17 on the front sling 13 .

步骤四、在横向分配梁12上安装底模10,同时在支撑架和永久支座7之间铺设底模10,由内临时支座支撑6。Step 4: Install the bottom mold 10 on the lateral distribution beam 12, and at the same time lay the bottom mold 10 between the support frame and the permanent support 7, and support 6 by the inner temporary support.

步骤五、在支架纵梁15上安装外模支架25,并通过对拉拉杆将翼缘底模31和外侧模32固定在外模支架25上。Step 5: Install the outer mold support 25 on the support longitudinal beam 15 , and fix the flange bottom mold 31 and the outer mold 32 on the outer mold support 25 by pulling and pulling rods.

步骤六、在边跨段底板上绑扎钢筋,将内模24安装在底膜10上,其中内模24为预制的或在底膜10上现场制作的,具体的通过支撑角钢14将内膜10悬空设置在底模10上方,支撑角钢14一端设置在支撑架的最下方的支撑横梁2上,另一端通过锚固杆20固定在已浇筑桥段30底板上方。Step 6: Bind the steel bars on the bottom plate of the side span, and install the inner mold 24 on the bottom film 10, wherein the inner mold 24 is prefabricated or made on site on the bottom film 10. It is suspended above the bottom mold 10 , one end of the supporting angle steel 14 is set on the lowermost supporting beam 2 of the support frame, and the other end is fixed above the bottom plate of the poured bridge section 30 through the anchor rod 20 .

在本说明书的描述中,参考术语“一个实施例”、“示例”、“具体示例”等的描述意指结合该实施例或示例描述的具体特征、结构、材料或者特点包含于本发明的至少一个实施例或示例中。在本说明书中,对上述术语的示意性表述不一定指的是相同的实施例或示例。而且,描述的具体特征、结构、材料或者特点可以在任何的一个或多个实施例或示例中以合适的方式结合。In the description of this specification, description with reference to the terms "one embodiment," "example," "specific example," etc. means that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one aspect of the present invention. in one embodiment or example. In this specification, schematic representations of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.

以上公开的本发明优选实施例只是用于帮助阐述本发明。优选实施例并没有详尽叙述所有的细节,也不限制该发明仅为所述的具体实施方式。显然,根据本说明书的内容,可作很多的修改和变化。本说明书选取并具体描述这些实施例,是为了更好地解释本发明的原理和实际应用,从而使所属技术领域技术人员能很好地理解和利用本发明。本发明仅受权利要求书及其全部范围和等效物的限制。The above-disclosed preferred embodiments of the present invention are provided only to help illustrate the present invention. The preferred embodiments do not exhaust all the details, nor do they limit the invention to only the described embodiments. Obviously, many modifications and variations are possible in light of the content of this specification. The present specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can well understand and utilize the present invention. The present invention is to be limited only by the claims and their full scope and equivalents.

Claims (9)

1. The construction method of the cantilever bridge side span formwork system is characterized by comprising the following steps:
firstly, pre-burying a steel plate (5) at the top of a pouring side span buttress (23), mounting a support frame with an upper support beam, a middle support beam and a lower support beam (2) on the pre-buried steel plate (5), and mounting and arranging an outer temporary support (8) at the top of the pouring side span buttress (23);
step two, installing a temporary fixing pier (18) above a top plate of a poured bridge section (30), fixing a rear upper cross beam (19) below the top plate of the poured bridge section (30) through a rear hanging strip (21), anchoring a rear lower cross beam (22) below a bottom plate of the poured bridge section (30), respectively connecting two ends of a top longitudinal beam (9) to the temporary fixing pier (18) and a supporting cross beam (2) of an upper way of a supporting frame, respectively connecting two ends of a support longitudinal beam (15) to the supporting cross beam (2) of a middle way of the supporting frame and the hanging strip (21) arranged on the top plate, respectively connecting two ends of a bottom longitudinal beam (11) to an outer temporary support (8) and the rear hanging strip (21) arranged on the bottom plate, and fully paving a transverse distribution beam (12) on the bottom longitudinal beam (11);
thirdly, mounting a front hanging strip (13) in the middle area of the top longitudinal beam (9) and the support longitudinal beam (15), and hanging a front cross beam (17) on the front hanging strip (13);
fourthly, mounting a bottom die (10) on the transverse distribution beam (12), laying the bottom die (10) between the support frame and the permanent support (7), and supporting the bottom die (10) by the inner temporary support (6);
fifthly, an outer mold support (25) is installed on the support longitudinal beam (15), and the flange bottom die (31) and the outer mold (32) are fixed on the outer mold support (25) through a counter-pulling pull rod;
and sixthly, binding steel bars on the bottom plate of the side span section, and installing the inner mold (24) on the bottom film (10).
2. The cantilever bridge side span formwork system construction method according to claim 1, wherein the inner formwork (24) is suspended above the bottom formwork (10) through a support angle steel (14), one end of the support angle steel (14) is arranged on a support cross beam (2) of a lower course of the support frame, and the other end is fixed above a bottom plate of a poured bridge section (30) through an anchoring rod (20).
3. The cantilever bridge side span formwork system construction method according to claim 2, wherein the inner mold (24) comprises support angle steel (14), a lower inner mold (16), inner side molds (26), an upper inner mold (27), connecting angle steel (28) and inner supports (29), the lower inner mold (16), the upper inner mold (27) and the two inner side molds (26) form a rectangular cylinder, the corners of the rectangular cylinder are fixed through the connecting angle steel (28), the support angle steel (14) is connected to the lower inner mold (16), two support angle steel (14) are arranged, and the support angle steel (14) and the connecting angle steel (28) at the edges of the upper inner mold (27) are connected through the inner supports (29).
4. The cantilever bridge side span formwork system construction method according to claim 1, wherein two embedded steel plates (5) are arranged at the top of the side span buttress (23), the support frame is composed of two support longitudinal beams (4) and three upper, middle and lower support cross beams (2) arranged between the support longitudinal beams (4), the bottom of each support longitudinal beam (4) is arranged on the embedded steel plates (5), two support frames are arranged, and the two support frames are connected through the reinforcing support (1).
5. The cantilever bridge side span formwork system construction method according to claim 1, wherein the top of the side span buttress (23) is divided into two installation positions by a support frame, and an inner temporary support (6), a permanent support (7) and an outer temporary support (8) are sequentially arranged from the support frame to the edge of the top surface of the side span buttress (23) on each installation position.
6. The cantilever bridge side-span formwork system construction method according to claim 1, wherein the top of the bottom formwork (10) and the top of the permanent support (7) are equal in height.
7. The cantilever bridge side-span formwork system construction method according to claim 1, wherein the front cross beam (17) and the rear lower cross beam (22) are at the same level.
8. The cantilever bridge side-span formwork system construction method according to claim 1, characterized in that an end formwork (3) is installed on the side surface of the supporting frame.
9. A cantilever bridge side span formwork system is characterized by being built through the steps.
CN202010920835.4A 2020-09-04 2020-09-04 Side span formwork system of cantilever bridge and its construction method Active CN111851318B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010920835.4A CN111851318B (en) 2020-09-04 2020-09-04 Side span formwork system of cantilever bridge and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010920835.4A CN111851318B (en) 2020-09-04 2020-09-04 Side span formwork system of cantilever bridge and its construction method

Publications (2)

Publication Number Publication Date
CN111851318A true CN111851318A (en) 2020-10-30
CN111851318B CN111851318B (en) 2021-09-07

Family

ID=72967819

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010920835.4A Active CN111851318B (en) 2020-09-04 2020-09-04 Side span formwork system of cantilever bridge and its construction method

Country Status (1)

Country Link
CN (1) CN111851318B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112627060A (en) * 2020-12-30 2021-04-09 中国建筑土木建设有限公司 Side-span cast-in-place section cantilever bearing system and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009108635A (en) * 2007-10-31 2009-05-21 Sumitomo Mitsui Construction Co Ltd Bridge erection method
CN202658536U (en) * 2012-04-11 2013-01-09 中铁三局集团有限公司 Device for synchronous construction of continuous girder bridge cantilever side span cast-in-situ section and folding section
CN103556578A (en) * 2013-10-14 2014-02-05 中铁十九局集团有限公司 Casting mold system for straight line section and side span closure section of continuous beam and building method thereof
CN106522102A (en) * 2016-11-22 2017-03-22 中交公局海威工程建设有限公司 Side span construction support, rigid frame bridge side span and rigid frame bridge
CN107724244A (en) * 2017-10-26 2018-02-23 中铁第四勘察设计院集团有限公司 Temporary T structure and its construction method without bearing continuous rigid frame end bay beam section composition
CN111395181A (en) * 2020-03-27 2020-07-10 中交二公局东萌工程有限公司 Self-anchored construction method for side span cast-in-place section and closed section of continuous rigid frame bridge
CN211171632U (en) * 2019-08-14 2020-08-04 中交二公局东萌工程有限公司 Continuous rigid frame bridge side-span cast-in-place section and closure section are pour and are used gallows

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009108635A (en) * 2007-10-31 2009-05-21 Sumitomo Mitsui Construction Co Ltd Bridge erection method
CN202658536U (en) * 2012-04-11 2013-01-09 中铁三局集团有限公司 Device for synchronous construction of continuous girder bridge cantilever side span cast-in-situ section and folding section
CN103556578A (en) * 2013-10-14 2014-02-05 中铁十九局集团有限公司 Casting mold system for straight line section and side span closure section of continuous beam and building method thereof
CN106522102A (en) * 2016-11-22 2017-03-22 中交公局海威工程建设有限公司 Side span construction support, rigid frame bridge side span and rigid frame bridge
CN107724244A (en) * 2017-10-26 2018-02-23 中铁第四勘察设计院集团有限公司 Temporary T structure and its construction method without bearing continuous rigid frame end bay beam section composition
CN211171632U (en) * 2019-08-14 2020-08-04 中交二公局东萌工程有限公司 Continuous rigid frame bridge side-span cast-in-place section and closure section are pour and are used gallows
CN111395181A (en) * 2020-03-27 2020-07-10 中交二公局东萌工程有限公司 Self-anchored construction method for side span cast-in-place section and closed section of continuous rigid frame bridge

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112627060A (en) * 2020-12-30 2021-04-09 中国建筑土木建设有限公司 Side-span cast-in-place section cantilever bearing system and construction method thereof

Also Published As

Publication number Publication date
CN111851318B (en) 2021-09-07

Similar Documents

Publication Publication Date Title
JP7429940B2 (en) Construction method of steel concrete main girder of cable-stayed bridge
CN102888815B (en) The pouring construction method of a kind of wide-angle V-type pier and 0# block case beam
CN111663449A (en) Combined cast-in-place box girder support system and construction method
CN110761402B (en) Concrete pouring construction method for lag and synchronous construction on the same floor of house building
WO2022156255A1 (en) Double-deck multi-span bridge construction method
CN105568854A (en) Construction method of overwater curved fish-bellied cast-in-place reinforced concrete box girder
CN110607738A (en) Small box girder structure suitable for medium and small span simply supported girder bridges and its construction method
CN110552502A (en) Construction method of C-shaped stock yard intermediate retaining wall overhanging platform
CN113265959A (en) Construction method for side-span cast-in-place section of hanging basket combined bracket of high-pier steel web bridge
CN217734853U (en) Overload small clear distance beam adjustable disc buckle formwork support frame
CN207017483U (en) The full precast shear wall structural system of regenerative steel skeleton
CN103469735A (en) Method for mounting curve ultrahigh hollow column plate type pier top solid section template
CN110847039A (en) Full cantilever installation method of segmental precast concrete box girder
CN112227216B (en) Triangular area cable buckling and sling combined construction method for steel diagonal bracing continuous rigid frame bridge
CN213204915U (en) Overweight overhanging suspended component supporting system of super high-rise residential conversion layer
CN111851318A (en) Side span formwork system of cantilever bridge and its construction method
CN116201351A (en) Assembled reinforced concrete post-pouring strip template supporting system
CN113846746A (en) Basement structure beneficial to efficient construction and construction method
CN209584813U (en) Frame bridge system
CN209816632U (en) Arch foot structure for special-shaped space arch bridge
CN209873811U (en) Subway major structure medium plate also serves as temporary supporting structure
CN117432239A (en) Construction method of new ground ring beams in old buildings
CN111593874A (en) Supporting system for overweight overhung suspended member of super high-rise residential conversion layer and construction method
CN112323647B (en) Rigid frame bridge hanging basket suspension casting system and construction method thereof
CN214271749U (en) Reinforced concrete arch culvert reinforced structure formwork system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20201030

Assignee: Anhui Xingtai Financial Leasing Co.,Ltd.

Assignor: ANHUI GOURGEN TRAFFIC CONSTRUCTION CO.,LTD.

Contract record no.: X2023980034901

Denomination of invention: Side span formwork system of cantilever bridge and its construction method

Granted publication date: 20210907

License type: Exclusive License

Record date: 20230423

EE01 Entry into force of recordation of patent licensing contract
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Side span formwork system of cantilever bridge and its construction method

Effective date of registration: 20230426

Granted publication date: 20210907

Pledgee: Anhui Xingtai Financial Leasing Co.,Ltd.

Pledgor: ANHUI GOURGEN TRAFFIC CONSTRUCTION CO.,LTD.

Registration number: Y2023980039310

EC01 Cancellation of recordation of patent licensing contract
EC01 Cancellation of recordation of patent licensing contract

Assignee: Anhui Xingtai Financial Leasing Co.,Ltd.

Assignor: ANHUI GOURGEN TRAFFIC CONSTRUCTION CO.,LTD.

Contract record no.: X2023980034901

Date of cancellation: 20241204

PC01 Cancellation of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Granted publication date: 20210907

Pledgee: Anhui Xingtai Financial Leasing Co.,Ltd.

Pledgor: ANHUI GOURGEN TRAFFIC CONSTRUCTION CO.,LTD.

Registration number: Y2023980039310