CN111817203A - Distribution network high voltage emergency interface and its working method - Google Patents
Distribution network high voltage emergency interface and its working method Download PDFInfo
- Publication number
- CN111817203A CN111817203A CN202010649590.6A CN202010649590A CN111817203A CN 111817203 A CN111817203 A CN 111817203A CN 202010649590 A CN202010649590 A CN 202010649590A CN 111817203 A CN111817203 A CN 111817203A
- Authority
- CN
- China
- Prior art keywords
- interface
- voltage
- distribution network
- medium
- switch
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/02—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
Landscapes
- Stand-By Power Supply Arrangements (AREA)
Abstract
本发明提出一种配网高压应急接口及其工作方法,其特征在于:绝缘固定在电杆上,包括:分别通过绝缘导线与每一架空电线构成电气连接的引出部、带有与引出部相同数量的绝缘导线的接口部、以及连接引出部和接口部的开关部;所述引出部和接口部的每一绝缘导线经开关部构成一一对应的开断式电气连接;所述接口部的绝缘导线的另一端设置有裸露端作为接口端,并电气连接有接地环。通过高压应急接口取代原本带电拆接火流程,优化流程,降低保电成本,解决带电作业受天气、地形制约问题,加大了中压车在检修、故障中的应用。能够满足与10kV中压发电车、旁路电缆等设备的快速连接需求。
The present invention provides a distribution network high-voltage emergency interface and a working method thereof, which are characterized in that: insulation is fixed on the pole, and includes: a lead-out part which is electrically connected to each overhead wire through an insulated wire; The interface part of a number of insulated wires, and the switch part connecting the lead-out part and the interface part; each insulated wire of the lead-out part and the interface part forms a one-to-one corresponding disconnected electrical connection through the switch part; The other end of the insulated wire is provided with a bare end as an interface end, and is electrically connected with a grounding ring. The high-voltage emergency interface replaces the original live disconnection and fire process, optimizes the process, reduces the cost of maintaining electricity, solves the problem that live work is restricted by weather and terrain, and increases the application of medium-voltage vehicles in maintenance and faults. It can meet the needs of quick connection with 10kV medium voltage generator vehicles, bypass cables and other equipment.
Description
技术领域technical field
本发明属于配网运维检修技术领域,尤其涉及一种配网高压应急接口及其工作方法。The invention belongs to the technical field of distribution network operation, maintenance and repair, in particular to a distribution network high-voltage emergency interface and a working method thereof.
背景技术Background technique
随着供电可靠性要求的提升,配网检修故障中应用发电车保供电的工作越来越频繁,其中10kV中压发电车保供电的技术方案是:一部10kV中压发电车、一部绝缘斗臂车,通过绝缘斗臂车将中压发电车的高压电缆接入线路进行发电。With the improvement of power supply reliability requirements, the use of generator vehicles to ensure power supply in distribution network maintenance and faults is becoming more and more frequent. Among them, the technical solution for 10kV medium voltage generator vehicles to ensure power supply is: one 10kV medium voltage generator vehicle, one insulation The bucket arm truck is used to connect the high voltage cable of the medium voltage generator car to the line through the insulated bucket arm truck to generate electricity.
现有中压发电车与绝缘斗臂车配合保供电存在问题:一是占用空间大,现场选点难度大。现有中压发电车接入架空线路需要能容纳绝缘斗臂车及中压发电车的大场地,往往很难找到合适的位置。二是需要带电作业配合,受天气制约。现有中压发电车接入线路需要带电配合将高压电缆接入和退出线路,作业成本大且带电作业需要良好的天气,受天气影响较大。同时,该种作业方式保电费用高,每次中压发电车保供电任务,其中紧带电接入和退出线路作业,需要数万施工费。The existing medium-voltage generator car and the insulated bucket arm car have problems to maintain power supply: First, it takes up a lot of space and it is difficult to select a site. The existing medium-voltage generators need to be connected to the overhead line, which requires a large space that can accommodate the insulated boom trucks and the medium-voltage generators, and it is often difficult to find a suitable location. The second is the need to cooperate with live work, which is restricted by the weather. The existing access line of medium-voltage generators needs to be connected to and withdrawn from the high-voltage cable with live co-ordination. The operation cost is high, and live work requires good weather, which is greatly affected by the weather. At the same time, this kind of operation method has high cost of maintaining electricity. Every time the medium-voltage generator vehicle ensures the power supply task, in which the operation of connecting and exiting the line with tight electricity requires tens of thousands of construction costs.
发明内容SUMMARY OF THE INVENTION
针对现有方案存在的缺陷和不足,本发明一种配网高压应急接口及其工作方法,通过预先建设的应急结构,直接替代了绝缘斗臂车的作用,使发电车保电的工作只需要中压发电车就能独立完成,大大节约了占用的产地和操作的复杂度及成本。Aiming at the defects and deficiencies of the existing solutions, the present invention provides a high-voltage emergency interface for a distribution network and a working method thereof. The pre-built emergency structure directly replaces the role of the insulating bucket truck, so that the work of the generator vehicle to ensure electricity only needs to be The medium voltage generator car can be completed independently, which greatly saves the occupied production area and the complexity and cost of operation.
其具体采用以下技术方案:Specifically, the following technical solutions are adopted:
一种配网高压应急接口,其特征在于:绝缘固定在电杆上,包括:分别通过绝缘导线与每一架空电线构成电气连接的引出部、带有与引出部相同数量的绝缘导线的接口部、以及连接引出部和接口部的开关部;所述引出部和接口部的每一绝缘导线经开关部构成一一对应的开断式电气连接;所述接口部的绝缘导线的另一端设置有裸露端作为接口端,并电气连接有接地环。A high-voltage emergency interface for distribution network is characterized in that: insulation is fixed on the pole, including: a lead-out part which is electrically connected to each overhead wire through insulated wires, and an interface part with the same number of insulated wires as the lead-out part. , and a switch part connecting the lead-out part and the interface part; each insulated wire of the lead-out part and the interface part forms a one-to-one corresponding disconnected electrical connection through the switch part; the other end of the insulated wire of the interface part is provided with The exposed end serves as the interface end, and is electrically connected with a grounding ring.
优选地,所述引出部的绝缘导线通过并沟线夹与架空电线固定并构成电气连接。Preferably, the insulated wire of the lead-out portion is fixed to the overhead wire through a parallel groove wire clip to form an electrical connection.
优选地,所述开关部为隔离刀闸或全封闭跌落开关,且通过横担固定在电杆上。Preferably, the switch part is an isolation knife switch or a fully enclosed drop switch, and is fixed on the pole through a cross arm.
优选地,所述接口端通过横担和柱式瓷瓶固定在电杆上。Preferably, the interface end is fixed on the pole through a cross arm and a column-type porcelain bottle.
优选地,所述裸露端固定连接有金具作为接口端。Preferably, the bare end is fixedly connected with a metal fitting as the interface end.
优选地,所述引出部、开关部和接口部从上至下依次设置。Preferably, the lead-out portion, the switch portion and the interface portion are arranged in sequence from top to bottom.
优选地,每2000kVA配置一个。Preferably, one is configured every 2000kVA.
以及根据以上配网高压应急接口的工作方法,其特征在于,包括以下步骤:And according to the working method of the above distribution network high-voltage emergency interface, it is characterized in that it comprises the following steps:
步骤S1:将中压发电车移动至配网高压应急接口下方;Step S1: Move the medium-voltage generator car to below the high-voltage emergency interface of the distribution network;
步骤S2:将中压发电车的电源输出线与所述接口端和接地环连接;Step S2: connecting the power output line of the medium-voltage generator car with the interface terminal and the grounding ring;
步骤S3:将所述开关部合闸接通;Step S3: closing and turning on the switch part;
步骤S4:中压发电车的中压发电机组启动并进行送电;Step S4: the medium-voltage generator set of the medium-voltage generator vehicle starts and transmits electricity;
步骤S5:送电结束之后,先将所述开关部关闸断开,再将中压发电车的电源输出线从所述接口端和接地环上拆除。Step S5: After the power transmission is completed, the switch part is first turned off and disconnected, and then the power output wire of the medium-voltage generator car is removed from the interface terminal and the grounding ring.
本发明及其优选方案通过高压应急接口取代原本带电拆接火流程,优化流程,降低保电成本,解决带电作业受天气、地形制约问题,加大了中压车在检修、故障中的应用。能够满足与10kV中压发电车、旁路电缆等设备的快速连接需求。当线路因检修、故障等需要紧急复电时,由发电车随车人员及属地施工人员在接地线保护下,将高压电缆快速锁进快速接入点裸露部位,减少带电配合环节,减员增效,不受天气制约。The present invention and its preferred solution replace the original live disassembly and connection fire process through the high-voltage emergency interface, optimize the process, reduce the cost of maintaining electricity, solve the problem that live work is restricted by weather and terrain, and increase the application of medium voltage vehicles in maintenance and faults. It can meet the needs of quick connection with 10kV medium voltage generator vehicles, bypass cables and other equipment. When the line needs to be re-energized urgently due to maintenance, fault, etc., under the protection of the grounding wire, the crew of the generator car and the local construction personnel will quickly lock the high-voltage cable into the exposed part of the quick access point, reduce the live coordination link, reduce staff and increase efficiency , not subject to weather restrictions.
附图说明Description of drawings
下面结合附图和具体实施方式对本发明进一步详细的说明:The present invention will be described in further detail below in conjunction with the accompanying drawings and specific embodiments:
图1是本发明实施例结构示意图;1 is a schematic structural diagram of an embodiment of the present invention;
图2是本发明实施例使用方法示意图;Fig. 2 is a schematic diagram of a method of use according to an embodiment of the present invention;
图3是本发明实施例立体示意图;Fig. 3 is the three-dimensional schematic diagram of the embodiment of the present invention;
图中:1-并沟线夹;2-绝缘导线;3-隔离刀闸;4-接地环;5-金具;6-柱式瓷瓶。In the picture: 1- Parallel groove clamp; 2- Insulated wire; 3- Isolation knife gate; 4- Grounding ring; 5- Hardware;
具体实施方式Detailed ways
为让本专利的特征和优点能更明显易懂,下文特举实施例,作详细说明如下:In order to make the features and advantages of this patent more obvious and easy to understand, the following specific examples are given and described in detail as follows:
如图1、图3所示,本实施例方案围绕现有的10kv线路的电杆节点进行改造,通过成本低廉的方式形成了可靠的配网高压应急接口。As shown in Figures 1 and 3, the solution of this embodiment is reconstructed around the pole nodes of the existing 10kv line, and a reliable high-voltage emergency interface of the distribution network is formed in a low-cost way.
其首先通过并沟线夹1,将绝缘导线2与每一架空电线(一般为三根)构成电气连接并完成固定,该引出的绝缘导线2连接至固定在电杆上的隔离刀闸3的一侧(也可采用全封闭跌落开关),而隔离刀闸3的另一侧则连接接口侧的绝缘导线2。该接口侧的绝缘导线2的下端通过柱式瓷瓶6固定在电杆上,设置有接地环4,同时末端设置有连接金具5的裸露端,作为接口使用。First, the insulated
如图2所示,在电网正常输电工作的状态下,隔离刀闸3处于断开的状态,将接口端与电路进行隔离,由于接口端的位置相对较低,因此可以防止意外触电的情况发生。而当输电线路无法正常保证电力供应时,需要发电车接入实现外部供电,当发电车通过接口将电路快速连接完成后,将隔离刀闸3进行合闸操作,从而接通备用的供电电路。As shown in Figure 2, when the power grid is working normally, the
接口端固定连接的金具5则起到了方便发电车接、拆线的作用,进一步提高了效率。The
如图3所示,在本实施例中,各个固定件通过在电杆上竖向排列固定的若干横担完成固定,同时使得各组绝缘导线2在空间上相对分离,而不至于发生交叉的情况。As shown in FIG. 3 , in this embodiment, each fixing member is fixed by a plurality of cross arms vertically arranged and fixed on the pole, and at the same time, each group of
在本实施例的方案的实施当中,在负荷密集区且可容纳中压发电车位置的架空线路上安装,每2000kVA配置1台,满足与10kV中压发电车、旁路电缆等设备的快速连接需求。当线路因检修、故障等需要紧急复电时,由发电车随车人员及属地施工人员在接地线保护下,将高压电缆快速锁进快速接入点裸露部位,减少带电配合环节,减员增效,不受天气制约。In the implementation of the solution of this embodiment, it is installed on the overhead line in the load-intensive area and can accommodate the location of medium-voltage generators, and one set per 2000kVA is configured to meet the fast connection with 10kV medium-voltage generators, bypass cables and other equipment. need. When the line needs to be re-energized urgently due to maintenance, failure, etc., under the protection of the grounding wire, the crew of the generator car and the local construction personnel will quickly lock the high-voltage cable into the exposed part of the quick access point, reduce the live coordination link, reduce staff and increase efficiency , not subject to weather restrictions.
基于本实施例提供的结构设计,其工作方法可以包括以下步骤:Based on the structural design provided by this embodiment, its working method may include the following steps:
步骤S1:将中压发电车移动至配网高压应急接口下方;Step S1: Move the medium-voltage generator car to below the high-voltage emergency interface of the distribution network;
步骤S2:将中压发电车的电源输出线与接口端和接地环4连接;Step S2: connect the power output line of the medium-voltage generator car to the interface terminal and the
步骤S3:将开关部合闸接通;Step S3: turn on the switch part;
步骤S4:中压发电车的中压发电机组启动并进行送电;Step S4: the medium-voltage generator set of the medium-voltage generator vehicle starts and transmits electricity;
步骤S5:送电结束之后,先将开关部关闸断开,再将中压发电车的电源输出线从接口端和接地环4上拆除。Step S5 : after the power transmission is completed, the switch part is turned off first, and then the power output wire of the medium-voltage generator car is removed from the interface terminal and the
本专利不局限于上述最佳实施方式,任何人在本专利的启示下都可以得出其它各种形式的配网高压应急接口及其工作方法,凡依本发明申请专利范围所做的均等变化与修饰,皆应属本专利的涵盖范围。This patent is not limited to the above-mentioned best embodiment, anyone can come up with other various forms of distribution network high-voltage emergency interface and its working method under the inspiration of this patent. and modifications, shall fall within the scope of this patent.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010649590.6A CN111817203A (en) | 2020-07-08 | 2020-07-08 | Distribution network high voltage emergency interface and its working method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010649590.6A CN111817203A (en) | 2020-07-08 | 2020-07-08 | Distribution network high voltage emergency interface and its working method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN111817203A true CN111817203A (en) | 2020-10-23 |
Family
ID=72842707
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202010649590.6A Pending CN111817203A (en) | 2020-07-08 | 2020-07-08 | Distribution network high voltage emergency interface and its working method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN111817203A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113991362A (en) * | 2021-11-01 | 2022-01-28 | 国网江苏省电力有限公司南通供电分公司 | 10kV medium voltage power generation car overhead line quick interface device |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102445592A (en) * | 2010-10-09 | 2012-05-09 | 林良伟 | Vacuum switch and cable connection electricity testing device |
| CN106300104A (en) * | 2016-10-26 | 2017-01-04 | 国网上海市电力公司 | The universal attachment means of power supply vehicle of meet an emergency and low pressure aerial condutor and application thereof |
| CN108963875A (en) * | 2018-07-19 | 2018-12-07 | 吉林师范大学 | The method of on-load migration 10KV overhead transmission line |
| CN109066469A (en) * | 2018-09-17 | 2018-12-21 | 广东电网有限责任公司 | A kind of generator car Quick access device for distribution network overhead line |
| CN110957658A (en) * | 2019-12-31 | 2020-04-03 | 贵州电网有限责任公司 | Rack transformer for 10kV distribution network overhead line and installation method thereof |
-
2020
- 2020-07-08 CN CN202010649590.6A patent/CN111817203A/en active Pending
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102445592A (en) * | 2010-10-09 | 2012-05-09 | 林良伟 | Vacuum switch and cable connection electricity testing device |
| CN106300104A (en) * | 2016-10-26 | 2017-01-04 | 国网上海市电力公司 | The universal attachment means of power supply vehicle of meet an emergency and low pressure aerial condutor and application thereof |
| CN108963875A (en) * | 2018-07-19 | 2018-12-07 | 吉林师范大学 | The method of on-load migration 10KV overhead transmission line |
| CN109066469A (en) * | 2018-09-17 | 2018-12-21 | 广东电网有限责任公司 | A kind of generator car Quick access device for distribution network overhead line |
| CN110957658A (en) * | 2019-12-31 | 2020-04-03 | 贵州电网有限责任公司 | Rack transformer for 10kV distribution network overhead line and installation method thereof |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113991362A (en) * | 2021-11-01 | 2022-01-28 | 国网江苏省电力有限公司南通供电分公司 | 10kV medium voltage power generation car overhead line quick interface device |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US8872377B2 (en) | Autotransformer traction power supply system equipped with 2×27.5kV outdoor modularized electric apparatus in electrified railway | |
| JP2019526144A (en) | Uninterruptible power function module with cable extension in GIS | |
| CN207541193U (en) | A distribution network multi-state complex fault simulation test platform | |
| CN102403780A (en) | Power supply device for bypass to operate without power failure | |
| CN104898018A (en) | Automatic pull trial detection and control device for single-phase earth fault of power distribution network | |
| CN110208630A (en) | A kind of power distribution network real model experiment platform | |
| CN110676739A (en) | A mobile substation | |
| CN103904564B (en) | High-voltage distribution device with double breakers used for single bus segmentation and application thereof | |
| CN111817203A (en) | Distribution network high voltage emergency interface and its working method | |
| CN204067884U (en) | A kind of distribution line based on double bus scheme | |
| CN107329050A (en) | A kind of circuitry fault detection method, detection means and detecting system | |
| CN215340152U (en) | Withstand voltage test device that GIS transformer substation cable compartment was arranged outdoors | |
| CN112838510A (en) | An integrated node switch TV unit cabinet | |
| CN109066320B (en) | HGIS equipment applied to double-bus outgoing line | |
| CN107503526B (en) | 500kV Substation Incomplete String Expansion to Complete String Blackout Construction Method | |
| CN203660363U (en) | Portable cable load quick transfer device in emergency condition | |
| CN210443803U (en) | A 220kV HGIS power distribution device applied to substation single bus segment wiring | |
| CN201252380Y (en) | Transmission line de-icing device of bundled multi-split conductor | |
| CN204258112U (en) | A kind of combined transformer | |
| CN101572493A (en) | Method and device for configuring high-voltage conversion device of test transformer substation | |
| CN205882398U (en) | Female wire sleeve cross arrangement structure of HGIS | |
| CN209948370U (en) | Bypass node type PT cabinet | |
| CN222563371U (en) | Gas-insulated switchgear with parallel bus system | |
| CN113922265B (en) | 500KV HGIS power distribution device | |
| CN105914591A (en) | Crossed configuration structure of HGIS bus sleeve |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20201023 |
|
| RJ01 | Rejection of invention patent application after publication |
