CN111794167B CN202010714427.3A CN202010714427A CN111794167B CN 111794167 B CN111794167 B CN 111794167B CN 202010714427 A CN202010714427 A CN 202010714427A CN 111794167 B CN111794167 B CN 111794167B
Authority
CN
China
Prior art keywords
scaffold
connecting seat
joint
supporting rod
bottom plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010714427.3A
Other languages
Chinese (zh)
Other versions
CN111794167A (en
Inventor
金琰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjia Construction Group Co.,Ltd.
Original Assignee
Tianjia Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjia Construction Group Co ltd filed Critical Tianjia Construction Group Co ltd
Priority to CN202010714427.3A priority Critical patent/CN111794167B/en
Publication of CN111794167A publication Critical patent/CN111794167A/en
Application granted granted Critical
Publication of CN111794167B publication Critical patent/CN111794167B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01HSTREET CLEANING; CLEANING OF PERMANENT WAYS; CLEANING BEACHES; DISPERSING OR PREVENTING FOG IN GENERAL CLEANING STREET OR RAILWAY FURNITURE OR TUNNEL WALLS
    • E01H3/00Applying liquids to roads or like surfaces, e.g. for dust control; Stationary flushing devices
    • E01H3/04Fixed devices, e.g. permanently- installed flushing means
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D47/00Separating dispersed particles from gases, air or vapours by liquid as separating agent
    • B01D47/06Spray cleaning

Landscapes

  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Movable Scaffolding (AREA)

Abstract

The invention discloses a spraying dust-settling cooling device based on building construction, relates to the technical field of building engineering, and solves the problems that the existing cooling dust-settling device cannot be used in high-rise buildings and is poor in installation adaptability; the rear sides of the two-way joint and the three-way joint are fixedly connected with a joint connecting plate; the middle of each water spraying pipeline at the top and the bottom is fixedly connected with a water inlet pipe; the upper and lower adjacent support rods are fixedly connected through a group of support rod connecting bolts; two bottom plate connecting blocks are fixedly and symmetrically arranged at the top of the supporting bottom plate. The bracing piece can be through bottom plate connecting block fixed mounting at the supporting baseplate top, also can install in vertical scaffold frame and horizontal scaffold frame front side through a scaffold frame connecting seat and No. two scaffold frame connecting seats respectively, but also can adjust the erection space wantonly, so even scaffold frame width changes also can adjust the installation, installation adaptability strengthens greatly.

Description

Based on construction is with spraying dust fall heat sink
Technical Field
The invention relates to the technical field of building engineering, in particular to a spraying dust-settling and cooling device for building construction.
Background
When the main structure of the building engineering is constructed, the working face is mostly exposed to burning sun, and in hot summer, the temperature of the construction working face is very high and sometimes even exceeds 40 ℃, so that workers have to stagger high-temperature time periods when constructing on the building scaffold. Even in this case, a worker may be sunstroke and dizzy due to high temperature during the construction work. Therefore, reducing the temperature of the construction operation surface and improving the high-temperature environment of the construction operation surface become the key factors of people-oriented green construction and improvement of the construction efficiency of the building engineering. In addition, a lot of dust can also be produced in the construction process of the main structure of the building engineering, and the workers can cause adverse effects on the health of the workers when being in the environment for a long time, so that some spraying, cooling and dust settling equipment are provided.
For example, the patent with the application number of 201721422231.7 discloses a spraying dust-reducing and cooling device for a building construction working face, which comprises a water storage tank, a main pipeline, a water pump and a plurality of branch pipes, wherein a plurality of turbines and a plurality of rotating shafts are arranged in each branch pipe, each rotating shaft is provided with a turbine, one end of each rotating shaft is connected with a first spraying unit, each first spraying unit comprises a first spraying group and a second spraying group, and a first crankshaft, a first connecting rod and a first sliding plate in each first spraying group form a crankshaft connecting rod mechanism; the first disc, the first traction rod and the first slide block in the second spraying group form a crank slide block mechanism together. This scheme can carry out twice to the construction operation face and spray and once air-cooled, greatly reduced the temperature of construction operation face to can reduce the dust content in near the air of construction operation face, can also make spun water smoke more press close to the construction operation face, further strengthen the cooling effect, thereby improve workman operational environment's comfort level.
Based on the above, when being installed, the existing building construction cooling and dust falling device is fixedly placed on the ground through a base, but the whole device cannot be erected too high, otherwise, the situation that the gravity center is unstable and the device inclines and falls is generated, so that the device cannot be used when the high-rise building needs cooling and dust falling, some devices can be fixed on a scaffold, but the distance between the devices and a scaffold connecting structure is fixed, if the whole width of the scaffold is different or the width of a certain middle position is different, the device cannot be fixed, and the installation adaptability is poor; therefore, the existing requirements are not met, and a spraying dust-settling cooling device based on building construction is provided for the requirements.
Disclosure of Invention
The invention aims to provide a spraying dust-settling and cooling device for building construction, which aims to solve the problems that the existing building construction cooling and dust-settling devices proposed in the background technology are fixedly placed on the ground through a base during installation, but the whole device cannot be erected too high, otherwise the gravity center is unstable and the device inclines and falls, so the device cannot be used when high-rise buildings need to be cooled and dusted, some devices can be fixed on scaffolds, but the distance between the devices and a scaffold connecting structure is fixed, and the device cannot be fixed if the whole width of the scaffolds is different or the width of a certain position in the middle of the scaffolds is different, and the installation adaptability is poor.
In order to achieve the purpose, the invention provides the following technical scheme: a spraying dust-settling and cooling device for building construction comprises a two-way joint, a supporting bottom plate, a first scaffold connecting seat and a second scaffold connecting seat; the rear sides of the two-way joint and the three-way joint are fixedly connected with a joint connecting plate; the joint connecting plate is rotatably connected with the supporting rod through a rotating shaft respectively, and the joint connecting plate and the supporting rod are fixed through two screws; a water spraying pipeline is fixedly embedded between the two-way joint and the three-way joint which are adjacent in the transverse direction; a water supply pipeline is fixedly embedded between the two-way joint and the three-way joint which are longitudinally adjacent; the front side of the water spraying pipeline is fixedly connected with six spray heads which are arranged at equal intervals; the middle of each water spraying pipeline at the top and the bottom is fixedly connected with a water inlet pipe; the upper and lower adjacent support rods are fixedly connected through a group of support rod connecting bolts; the top of the supporting bottom plate is fixedly and symmetrically provided with two bottom plate connecting blocks; the supporting rod can be fixedly arranged at the top of the connecting block of the bottom plate through a connecting bolt of the supporting rod; the first scaffold connecting seat can be fixedly embedded into the inner side of the supporting rod through a connecting seat fixing bolt; no. two scaffold connecting seats also can be installed at the inboard of bracing piece through the fixed embedding of connecting seat fixing bolt.
Preferably, the bottom of bracing piece is all fixed and is provided with the cubic arch of a rectangle, and the top of bracing piece is all fixed and is provided with a rectangle recess that corresponds with the protruding size of bottom rectangle, and bottom plate connecting block top also is provided with a same rectangle recess, and the bellied intermediate position of bracing piece bottom rectangle and the intermediate position of top rectangle recess all fixed round hole that runs through around being provided with, and bracing piece connecting bolt embedding is installed in the round hole that runs through around this group.
Preferably, the support rod can rotate at the rear side of the joint connecting plate, the connecting position of the support rod and the joint connecting plate is fixedly provided with four threaded holes in an annular arrangement by taking the rotating shaft as a circle center, and the support rod and the joint connecting plate can be screwed into the two symmetrical threaded holes through two screws for fixing.
Preferably, after the support rods are fixedly connected with each other through the support rod connecting bolts, the water feeding pipeline can be fixedly installed between the upper and lower adjacent double-way joints or three-way joints just, the water feeding pipeline is installed in a plugging mode, and sealing strips are arranged on the inner sides of the interfaces of the double-way joints or the three-way joints.
Preferably, all be provided with the strip shape groove that runs through and control the running through around the twice on the bracing piece, and the strip shape groove thickness that runs through around and the thickness of the connecting plate of a scaffold connecting seat and No. two scaffold connecting seats front sides is the same, and the groove thickness that runs through about equals with connecting seat fixing bolt's diameter.
Preferably, all fixedly in the middle of the connecting plate of a scaffold connecting seat and No. two scaffold connecting seats front sides be provided with one with the same round hole of connecting seat fixing bolt diameter, during the installation with the bar groove of running through around on the connecting plate embedding bracing piece of a scaffold connecting seat and No. two scaffold connecting seats front sides and screw up fixedly through connecting seat fixing bolt and nut.
Preferably, the position of the connecting plate of a scaffold connecting seat and a second scaffold connecting seat front side can be adjusted in a sliding mode in a strip-shaped groove penetrating through the support rod from front to back, the first scaffold connecting seat can be adjusted left and right when being installed on a vertical scaffold, and the second scaffold connecting seat can be adjusted up and down when being installed on a horizontal scaffold.
Preferably, the bracing piece can pass through bottom plate connecting block fixed mounting at the supporting baseplate top, also can install at vertical scaffold frame and horizontal scaffold frame front side through a scaffold connecting seat and No. two scaffold connecting seats respectively.
Compared with the prior art, the invention has the beneficial effects that:
first, this device can install after the equipment connection and use on supporting baseplate, when needs use on high-rise building, can satisfy cooling dust fall demand when high-rise building construction through a scaffold frame connecting seat and No. two scaffold frame connecting seats fixed mounting again in the scaffold frame front side, but also can add three way connection wantonly, send water piping and spray pipe to increase the height, but also the dust removal area of cooling effectively increases, and it is more convenient to use.
Second, the bracing piece can be through bottom plate connecting block fixed mounting at the supporting baseplate top, also can install in vertical scaffold frame and horizontal scaffold frame front side through a scaffold frame connecting seat and No. two scaffold frame connecting seats respectively, and can change the interval between two adjacent scaffold frame connecting seats about through the position about adjusting a scaffold frame connecting seat when vertical scaffold frame installs, can change the interval between two adjacent scaffold frame connecting seats about through the upper and lower position of adjusting No. two scaffold frame connecting seats when horizontal scaffold frame installs, so even the scaffold frame width changes also can adjust the installation, installation adaptability strengthens greatly.
Drawings
FIG. 1 is a schematic side view of the shaft of the present invention after being fixed to a base;
FIG. 2 is a schematic side view of the axle of the present invention after being assembled with and disassembled from the base;
FIG. 3 is a schematic side view of the present invention in an axial configuration after it has been secured to a vertical scaffolding;
FIG. 4 is a schematic side view of the support rod of the present invention, shown disassembled with the first connecting base;
FIG. 5 is a schematic side view of the present invention in an axial configuration after it has been secured to a horizontal scaffolding;
FIG. 6 is a schematic side view of the support rod of the present invention, shown disassembled with the second connecting base;
FIG. 7 is an enlarged partial view of FIG. 1 at point A;
FIG. 8 is an enlarged partial view of FIG. 3 at point B;
in the figure: 1. a support bar; 2. a two-way joint; 3. a water supply pipeline; 4. a three-way joint; 5. a water spray pipe; 6. a joint connection plate; 7. a spray head; 8. a water inlet pipe; 9. the support rod is connected with a bolt; 10. a support base plate; 11. a bottom plate connecting block; 12. a first scaffold connecting seat; 13. a connecting seat fixing bolt; 14. no. two scaffold connecting seats.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
Referring to fig. 1 to 8, an embodiment of the present invention includes: a spraying dust-settling and cooling device for building construction comprises a two-way connector 2, a supporting base plate 10, a first scaffold connecting seat 12 and a second scaffold connecting seat 14; the rear sides of the two-way joint 2 and the three-way joint 4 are fixedly connected with a joint connecting plate 6; the joint connecting plate 6 is respectively connected with the supporting rod 1 in a rotating way through a rotating shaft, and the joint connecting plate 6 and the supporting rod 1 are fixed through two screws; the supporting rod 1 can rotate at the rear side of the joint connecting plate 6, four threaded holes are fixedly arranged at the connecting position of the supporting rod 1 and the joint connecting plate 6 in an annular arrangement mode by taking a rotating shaft as a circle center, the supporting rod 1 and the joint connecting plate 6 can be screwed into two symmetrical threaded holes through two screws for fixing, the supporting rod 1 can be suitable for being mounted on a vertical scaffold and a transverse scaffold through rotation, and the supporting rod 1 can be effectively prevented from rotating after being fixed through the screws; the support rod 1 can be fixedly installed at the top of a support base plate 10 through a base plate connecting block 11, and also can be installed at the front sides of a vertical scaffold and a horizontal scaffold through a first scaffold connecting seat 12 and a second scaffold connecting seat 14 respectively, and the distance between two adjacent first scaffold connecting seats 12 on the left and right can be changed by adjusting the left and right positions of the first scaffold connecting seat 12 when the vertical scaffold is installed, and the distance between two adjacent second scaffold connecting seats 14 on the upper and lower sides can be changed by adjusting the up and down positions of the second scaffold connecting seat 14 when the horizontal scaffold is installed, so that the adjustment and installation can be carried out even if the width of the scaffold is changed, and the installation adaptability is greatly enhanced; a water spraying pipeline 5 is fixedly embedded between the two-way joint 2 and the three-way joint 4 which are adjacent in the transverse direction; a water supply pipeline 3 is fixedly embedded between the two-way joint 2 and the three-way joint 4 which are longitudinally adjacent; the front side of the water spraying pipeline 5 is fixedly connected with six spray heads 7 which are arranged at equal intervals; the water inlet pipes 8 are fixedly connected between the water spraying pipes 5 at the top and the bottom; the upper and lower adjacent support rods 1 are fixedly connected through a group of support rod connecting bolts 9; two bottom plate connecting blocks 11 are fixedly and symmetrically arranged at the top of the supporting bottom plate 10; the supporting rod 1 can be fixedly arranged on the top of the bottom plate connecting block 11 through a supporting rod connecting bolt 9; the first scaffold connecting seat 12 can be fixedly embedded and installed on the inner side of the supporting rod 1 through a connecting seat fixing bolt 13; a round hole with the same diameter as the connecting seat fixing bolt 13 is fixedly arranged between the connecting plates at the front sides of the first scaffold connecting seat 12 and the second scaffold connecting seat 14, the connecting plates at the front sides of the first scaffold connecting seat 12 and the second scaffold connecting seat 14 are embedded into strip-shaped grooves penetrating through the support rod 1 in the front and back direction during installation and are screwed and fixed through the connecting seat fixing bolt 13 and a nut, and the connection and the fixation are very simple and convenient; and a second scaffold connecting seat 14 can also be fixedly embedded and installed on the inner side of the support rod 1 through a connecting seat fixing bolt 13.
Furthermore, the bottom of the supporting rod 1 is fixedly provided with a rectangular block-shaped bulge, the top of the supporting rod 1 is fixedly provided with a rectangular groove corresponding to the size of the rectangular bulge at the bottom, the top of the bottom plate connecting block 11 is also provided with a same rectangular groove, the middle position of the rectangular bulge at the bottom of the supporting rod 1 and the middle position of the rectangular groove at the top are respectively and fixedly provided with a round hole penetrating through the front and the back, the supporting rod connecting bolt 9 is embedded and installed in the round holes penetrating through the front and the back of the group, the supporting rod 1 is firstly connected with each other up and down and the water feeding pipeline 3 is inserted and installed between the two-way joints 2 or the three-way joints 4 adjacent up and down during assembly, the four two-way joints 2 are respectively placed at the topmost and bottommost, then the supporting rod 1 is screwed and fixed by the supporting rod connecting bolt 9 and a nut, so that the two-way joints 2, the three-way joints 4 and the water feeding pipeline 3 form an integrated body connected up and down, the disassembly and the assembly are very convenient.
Further, after the support rod 1 is fixedly connected with the upper part and the lower part through the support rod connecting bolt 9, the water feeding pipeline 3 can be fixedly installed between the upper and lower adjacent two-way joints 2 or three-way joints 4 just, the water feeding pipeline 3 is installed in an inserting mode, the inner sides of the interfaces of the two-way joints 2 or the three-way joints 4 are provided with sealing strips, therefore, the water feeding pipeline 3 is not required to be specially fixed in a complex structure, and the disassembly and assembly are more convenient.
Further, all be provided with the strip groove that runs through and control the through around the twice on the bracing piece 1, and the strip groove thickness that runs through around and the connecting plate thickness of a scaffold connecting seat 12 and No. two scaffold connecting seat 14 front sides is the same, the groove thickness that runs through about equals with the diameter of connecting seat fixing bolt 13, can not produce after the strip groove that runs through around in installing in the strip groove of first scaffold connecting seat 12 and No. two scaffold connecting seat 14 and rock, connecting seat fixing bolt 13 can not produce after installing in the groove that runs through about and rock yet, the installation back stability is higher.
Further, the connecting plate of a scaffold connecting seat 12 and No. two scaffold connecting seats 14 front sides can slide the adjustment position in the bar groove that runs through around on bracing piece 1, No. one scaffold connecting seat 12 can control the adjustment when vertical scaffold mounting, No. two scaffold connecting seats 14 can adjust from top to bottom when horizontal scaffold mounting, can change the interval between two adjacent No. one scaffold connecting seat 12 about the position through adjusting a scaffold connecting seat 12 when vertical scaffold mounting, can change the interval between two adjacent No. two scaffold connecting seats 14 from top to bottom through the upper and lower position of adjusting No. two scaffold connecting seats 14 when horizontal scaffold mounting, so even scaffold width changes also can adjust the installation.
The working principle is as follows: if the water spraying device is used on a low-rise building, firstly, the support rods 1 are mutually connected up and down, the water conveying pipeline 3 is inserted and installed between the two-way joints 2 or the three-way joints 4 which are adjacent up and down, the four two-way joints 2 are respectively placed at the topmost part and the bottommost part, then, the support rods 1 are screwed and fixed through the support rod connecting bolts 9 and the nuts, so that the two-way joints 2, the three-way joints 4 and the water conveying pipeline 3 form a whole which is connected up and down, finally, the support rod 1 at the bottommost part is inserted into the top part of the bottom plate connecting block 11, the water spraying pipeline 5 is inserted and installed between the two-way joints 2 or the three-way joints 4 which are adjacent transversely, then, the support rods 1 and the bottom plate connecting block 11 are screwed and fixed through the support rod connecting bolts 9 and the nuts, then, the two water inlet pipes 8 are communicated with an external water source, and water can enter the water spraying pipeline 5 and be sprayed out through the spray head 7, the device has the functions of cooling and dust settling, the two water inlet pipes 8 can prevent the water pressure of the bottom water inlet pipe 8 from influencing the normal spraying of the spray head 7 above the water pressure, when the device is required to be installed on a horizontal scaffold of a high-rise building, the support base plate 10 of the assembled device is firstly disassembled, then the second scaffold connecting seats 14 are respectively and fixedly installed on the outer sides of the horizontal scaffold, the distance between the front side connecting plates of the left and right adjacent second scaffold connecting seats 14 is equal to the distance between the front and rear penetrating strip-shaped grooves of the left and right adjacent support rods 1, after the fixing, the front side connecting plates of the second scaffold connecting seats 14 are embedded with the front and rear penetrating strip-shaped grooves of the support rods 1, even if the upper and lower distances of the second scaffold connecting seats 14 are different, the two can be connected and fixed by screwing the connecting seat fixing bolts 13 and nuts, when the device is required to be installed on the vertical scaffold, firstly, two screws on a joint connecting plate 6 are disassembled, then the supporting rods 1 are rotated outwards by 90 degrees and then are re-installed, then a scaffold connecting seat 12 is respectively and fixedly installed on the outer side of a vertical scaffold, the distance between the upper adjacent scaffold connecting seat 12 and the lower adjacent scaffold connecting seat is equal to the distance between the upper adjacent supporting rod 1 and the lower adjacent supporting rod 1, after the installation, the connecting plate on the front side of the scaffold connecting seat 12 is aligned with and embedded in a strip-shaped groove penetrating through the middle of the supporting rod 1 in the front and back direction, and then the connecting seat fixing bolt 13 and the nut are screwed up to fix the two Send water pipe 3 and spray pipe 5 to increase the height, but the cooling dust removal area also effectively increases, it is more convenient to use, and this device can change the interval between two adjacent scaffold connecting seats 12 about through the position about adjusting scaffold connecting seat 12 when vertical scaffold shelf location, can change the interval between two adjacent two scaffold connecting seats 14 about through the upper and lower position of adjusting No. two scaffold connecting seats 14 when horizontal scaffold shelf location, so even the scaffold width changes also can adjust the installation, installation adaptability strengthens greatly.
It will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, and that the present invention may be embodied in other specific forms without departing from the spirit or essential attributes thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (1)

1. The utility model provides a based on construction is with spraying dust fall heat sink which characterized in that: comprises a two-way connector (2), a support bottom plate (10), a first scaffold connecting seat (12) and a second scaffold connecting seat (14); the rear sides of the two-way joint (2) and the three-way joint (4) are fixedly connected with a joint connecting plate (6); the joint connecting plate (6) is respectively rotatably connected with the supporting rod (1) through a rotating shaft, and the joint connecting plate (6) and the supporting rod (1) are fixed through two screws; a water spraying pipeline (5) is fixedly embedded between the two-way joint (2) and the three-way joint (4) which are adjacent in the transverse direction; a water supply pipeline (3) is fixedly embedded between the two-way joint (2) and the three-way joint (4) which are longitudinally adjacent; the front sides of the water spraying pipelines (5) are fixedly connected with six spray heads (7) which are arranged at equal intervals; a water inlet pipe (8) is fixedly connected between the water spraying pipes (5) at the top and the bottom; the upper and lower adjacent support rods (1) are fixedly connected through a group of support rod connecting bolts (9); two bottom plate connecting blocks (11) are fixedly and symmetrically arranged at the top of the supporting bottom plate (10); the support rod (1) can be fixedly arranged at the top of the bottom plate connecting block (11) through a support rod connecting bolt (9); the first scaffold connecting seat (12) can be fixedly embedded into the inner side of the supporting rod (1) through a connecting seat fixing bolt (13); the second scaffold connecting seat (14) can also be fixedly embedded in the inner side of the supporting rod (1) through a connecting seat fixing bolt (13), a rectangular block-shaped bulge is fixedly arranged at the bottom of the supporting rod (1), a rectangular groove corresponding to the size of the rectangular bulge at the bottom is fixedly arranged at the top of the supporting rod (1), the same rectangular groove is also arranged at the top of the bottom plate connecting block (11), a round hole penetrating through the front and the back is fixedly arranged at the middle position of the rectangular bulge at the bottom of the supporting rod (1) and the middle position of the rectangular groove at the top, a supporting rod connecting bolt (9) is embedded in the set of round holes penetrating through the front and the back, the supporting rod (1) can rotate at the back side of the joint connecting plate (6), and four threaded holes are fixedly arranged in an annular mode by taking a rotating shaft as the center of a circle, bracing piece (1) can twist the screw hole of wherein two symmetries with joint connecting plate (6) through two screws and fix, bracing piece (1) is through bracing piece connecting bolt (9) fixed connection back from top to bottom, and send water pipeline (3) can fixed mounting just between adjacent bi-pass joint (2) or three way connection (4) from top to bottom, and send water pipeline (3) to install through the mode of pegging graft, and the interface inboard of bi-pass joint (2) or three way connection (4) all is provided with the sealing strip, all be provided with the strip groove that runs through and control around the twice on bracing piece (1), and the strip groove thickness that runs through around and the connecting plate thickness of a scaffold connecting seat (12) and No. two scaffold connecting seats (14) front sides is the same, and control the groove thickness that runs through and the diameter of connecting seat fixing bolt (13) and equal, all fixed establishing in the middle of the connecting plate of a scaffold connecting seat (12) and No. two scaffold connecting seats (14) front sides is established A round hole with the same diameter as the connecting seat fixing bolt (13) is arranged, a connecting plate at the front side of the first scaffold connecting seat (12) and the second scaffold connecting seat (14) is embedded into a strip-shaped groove penetrating through the support rod (1) from front to back during installation and is screwed and fixed through the connecting seat fixing bolt (13) and a nut, the connecting plates at the front sides of the first scaffold connecting seat (12) and the second scaffold connecting seat (14) can slide in strip-shaped grooves penetrating through the support rod (1) from front to back to adjust the positions, when the vertical scaffold is installed, the first scaffold connecting seat (12) can be adjusted left and right, when the horizontal scaffold is installed, the second scaffold connecting seat (14) can be adjusted up and down, bracing piece (1) can be through bottom plate connecting block (11) fixed mounting at supporting baseplate (10) top, also can install in vertical scaffold frame and level scaffold frame front side through a scaffold connecting seat (12) and No. two scaffold connecting seats (14) respectively.
CN202010714427.3A 2020-07-22 2020-07-22 Based on construction is with spraying dust fall heat sink Active CN111794167B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010714427.3A CN111794167B (en) 2020-07-22 2020-07-22 Based on construction is with spraying dust fall heat sink

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010714427.3A CN111794167B (en) 2020-07-22 2020-07-22 Based on construction is with spraying dust fall heat sink

Publications (2)

Publication Number Publication Date
CN111794167A CN111794167A (en) 2020-10-20
CN111794167B true CN111794167B (en) 2021-10-15

Family

ID=72827159

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010714427.3A Active CN111794167B (en) 2020-07-22 2020-07-22 Based on construction is with spraying dust fall heat sink

Country Status (1)

Country Link
CN (1) CN111794167B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112007456A (en) * 2020-09-14 2020-12-01 合肥建设装饰(集团)有限责任公司 Building construction distributed dust settling device and application method thereof
CN112576824B (en) * 2020-12-30 2022-09-20 烟台裕恒化工材料有限公司 Linear sealing tape and manufacturing method
CN115727900B (en) * 2022-11-09 2024-07-02 中邮通建设咨询有限公司 Portable computer lab temperature and humidity detection device

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205077438U (en) * 2015-09-09 2016-03-09 安吉县城西北开发有限公司 Dust removal heat sink for construction
CN206477298U (en) * 2016-12-30 2017-09-08 浙江工程建设监理公司 A kind of construction site scaffold spray system
CN206570739U (en) * 2017-03-03 2017-10-20 山东奥邦机械设备制造有限公司 A kind of kerbstone cleaning device
CN207003353U (en) * 2017-04-19 2018-02-13 佟冠亚 A kind of road and bridge construction atomizing de-dusting apparatus
CN209722847U (en) * 2018-11-30 2019-12-03 临沂会宝岭铁矿有限公司 A kind of plant area ground spray dust intelligent control system
KR102019789B1 (en) * 2019-05-31 2019-09-09 신한기술그룹 주식회사 Mist spray system
CN110327719B (en) * 2019-07-24 2021-11-09 济南二建集团工程有限公司 Attached lifting type scaffold dust-settling spraying device and construction method

Also Published As

Publication number Publication date
CN111794167A (en) 2020-10-20

Similar Documents

Publication Publication Date Title
CN111794167B (en) Based on construction is with spraying dust fall heat sink
CN109138444B (en) Light steel structure
CN204841404U (en) Wet flue gas desulfurization carries torrent pipe bars device and desulfurization absorption tower of effect
CN116169940A (en) Assembled building photovoltaic roof
CN111765587B (en) Air supply system and construction method thereof
CN215563534U (en) Modularized photovoltaic integrated block structure
CN211667296U (en) Two pipe synthesis pipeline side direction supports
CN212457278U (en) Modular raised floor air supply system
CN219639684U (en) Warm ventilation pipe hanger
CN221461532U (en) Building curtain wall with stable installation
CN220486729U (en) Fast-assembling formula building steel construction
CN205945605U (en) Distributing type photovoltaic module ground mounting structure
CN218438441U (en) Supporting device for constructional engineering construction
CN220870254U (en) Pipeline installation structure
CN221531434U (en) Intelligent cooling system for photovoltaic building
CN219953412U (en) Cooling device used in tunnel high-temperature environment
CN210532502U (en) Energy-concerving and environment-protective building heating equipment
CN221546041U (en) Curtain wall connecting piece convenient to install
CN212154215U (en) Take prefabricated wallboard bearing structure to one side of entrance to a cave
CN217871739U (en) Scaffold dust device
CN218323599U (en) Heat preservation decorative wall mounting structure
CN218990476U (en) Connection structure of steel column and enclosure wall
CN221553701U (en) Base mounting structure and fire control cabinet
CN215173631U (en) Anti-seismic bracket connecting piece with installation specification convenient to adjust
CN220416754U (en) Public building energy consumption supervision equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20210915

Address after: 518000 Room 201, block a, building 8, exhibition Bay South Bank Plaza, Heping community, Fuhai street, Bao'an District, Shenzhen, Guangdong Province

Applicant after: Tianjia Construction Group Co.,Ltd.

Address before: 450003 No. 1, floor 6, building 2, Jincheng golden center, No. 68, jingsan Road, Jinshui District, Zhengzhou City, Henan Province

Applicant before: Jin Yan