CN111749244A - Construction device and construction method for safe construction of underground structure - Google Patents
Construction device and construction method for safe construction of underground structure Download PDFInfo
- Publication number
- CN111749244A CN111749244A CN202010764638.8A CN202010764638A CN111749244A CN 111749244 A CN111749244 A CN 111749244A CN 202010764638 A CN202010764638 A CN 202010764638A CN 111749244 A CN111749244 A CN 111749244A
- Authority
- CN
- China
- Prior art keywords
- plate
- construction
- foundation pit
- enclosure
- grouting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Sewage (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
本发明公开了一种用于地下结构安全施工的施工装置及施工方法,所述施工装置包括基坑支护组件,所述基坑支护组件包括多块支护板,所述支护板包括多块围板及多块挡土板;所述围板为中空的板状结构;所述围板包括用于与基坑相接的外侧板及靠近基坑中心的内侧板,所述外侧板上开设有多个连通孔;所述内侧板上开设有的排水口;任意两相邻挡土板之间的间隙内均设置有注浆管,所述注浆孔的出口端朝向注浆管远离围板的一侧。所述施工方法基于所述施工装置。采用本方案提供的装置及方法,不仅可通过为基坑施工提供支护以利于施工安全,同时在完成基坑施工后,可部分或全部填补因为基坑施工对基坑边缘土层所造成的空洞,利于基坑周围地层的稳定性。
The invention discloses a construction device and a construction method for safe construction of an underground structure. The construction device includes a foundation pit support assembly, the foundation pit support assembly includes a plurality of support plates, and the support plates include A plurality of enclosure plates and a plurality of earth retaining plates; the enclosure plates are hollow plate-like structures; the enclosure plates include an outer plate for connecting with the foundation pit and an inner plate close to the center of the foundation pit, the outer plate A plurality of communication holes are opened on the upper part; a drainage port is opened on the inner side plate; a grouting pipe is arranged in the gap between any two adjacent soil retaining plates, and the outlet end of the grouting hole faces the grouting pipe The side away from the hoarding. The construction method is based on the construction device. By using the device and method provided by this scheme, not only can the construction safety be facilitated by providing support for the foundation pit construction, but at the same time, after the foundation pit construction is completed, it can partially or fully fill the soil layer at the edge of the foundation pit caused by the foundation pit construction. The cavity is conducive to the stability of the formation around the foundation pit.
Description
技术领域technical field
本发明涉及地下工程施工技术领域,特别是涉及一种用于地下结构安全施工的施工装置及施工方法。The invention relates to the technical field of underground engineering construction, in particular to a construction device and a construction method for the safe construction of underground structures.
背景技术Background technique
基坑一般是指在建筑物基础设计位置按建筑物基底标高和基础平面尺寸,所开挖的土坑。针对基坑施工,基坑支护装置作为临时结构且为安全防护结构,用于防止基坑施工过程中出现坍塌现象。同时在基坑开挖和施工过程中,需要考虑基坑的降水问题。The foundation pit generally refers to the soil pit excavated at the base design position of the building according to the base elevation of the building and the size of the base plane. For foundation pit construction, the foundation pit support device is used as a temporary structure and a safety protection structure to prevent collapse during the construction of the foundation pit. At the same time, during the excavation and construction of the foundation pit, the problem of precipitation of the foundation pit needs to be considered.
砂卵地质一般地层松散、富水,对富水砂卵石地层近接重要建筑物的基坑施工中,尤其需要注意地层降水对周围环境的影响。故在现有施工中,针对砂卵地层深基坑(开挖深度超过5米(含5米),或深度虽未超过5米,但地质条件和周围环境及地下管线特别复杂的基坑工程)施工过程中存在的施工难度大、对周边环境影响大等一系列问题。Sand pebble geology is generally loose and water-rich. In the construction of foundation pits with water-rich sand and pebble strata close to important buildings, special attention should be paid to the impact of stratum precipitation on the surrounding environment. Therefore, in the existing construction, for the deep foundation pit in the sand egg stratum (excavation depth is more than 5 meters (including 5 meters), or the depth is not more than 5 meters, but the geological conditions and surrounding environment and underground pipelines are particularly complex foundation pit engineering. ) There are a series of problems in the construction process, such as difficult construction and great impact on the surrounding environment.
现有技术中,软土地区常采用的支护方式有钻孔咬合桩和地下连续墙。开展富水砂卵地层深基坑降水优化及风险控制研究,对地下建筑施工具有重要意义。In the prior art, the commonly used support methods in soft soil areas include drilled occlusal piles and underground diaphragm walls. It is of great significance to the construction of underground buildings to carry out research on the optimization of precipitation and risk control of deep foundation pits in water-rich sand egg strata.
发明内容SUMMARY OF THE INVENTION
针对上述提出的开展富水砂卵地层深基坑降水优化及风险控制研究,对地下建筑施工具有重要意义的技术问题,本发明提供了一种用于地下结构安全施工的施工装置及施工方法,采用本方案提供的装置和方法,不仅可通过为基坑施工提供支护以利于施工安全,同时在完成基坑施工后,可部分或全部填补因为基坑施工对基坑边缘土层所造成的空洞,利于基坑周围地层的稳定性。In view of the above-mentioned technical problem of great significance for underground building construction by carrying out research on dewatering optimization and risk control of deep foundation pits in water-rich sand egg strata, the present invention provides a construction device and a construction method for safe construction of underground structures. By using the device and method provided by this scheme, not only can the construction safety be facilitated by providing support for the foundation pit construction, but at the same time, after the foundation pit construction is completed, it is possible to partially or fully fill the soil layer at the edge of the foundation pit caused by the foundation pit construction. The cavity is conducive to the stability of the formation around the foundation pit.
本发明提供的用于地下结构安全施工的施工装置及施工方法通过以下技术要点来解决问题,用于地下结构安全施工的施工装置,包括基坑支护组件,所述基坑支护组件包括多块沿着基坑周向方向依次排布的支护板,所述支护板包括多块围板及多块挡土板;The construction device and construction method for the safe construction of the underground structure provided by the present invention solve the problem through the following technical points. The construction device for the safe construction of the underground structure includes a foundation pit support assembly, and the foundation pit support assembly includes multiple a supporting plate arranged in sequence along the circumferential direction of the foundation pit, the supporting plate includes a plurality of surrounding plates and a plurality of retaining plates;
所述挡土板沿着基坑的周向方向间隔排布,任意两相邻挡土板之间均设置有一块围板,各围板的外侧均挤压于对应两挡土板的内侧上;The earth retaining plates are arranged at intervals along the circumferential direction of the foundation pit, a surrounding plate is arranged between any two adjacent earth retaining plates, and the outer side of each surrounding plate is extruded on the inner side of the corresponding two earth retaining plates ;
所述围板为中空的板状结构;The enclosure plate is a hollow plate-like structure;
所述围板包括用于与基坑相接的外侧板及靠近基坑中心的内侧板,所述外侧板上开设有多个贯通外侧板内、外侧的连通孔;所述内侧板上开设有贯通内侧板内、外侧的排水口;The enclosure plate includes an outer plate for connecting with the foundation pit and an inner plate close to the center of the foundation pit, the outer plate is provided with a plurality of communication holes penetrating the inner and outer sides of the outer plate; the inner plate is provided with Through the inner and outer drains of the inner panel;
任意两相邻挡土板之间的间隙内均设置有竖向设置的注浆管,所述注浆管上设置有多个沿着注浆管轴线方向排布的注浆孔,所述注浆孔的出口端朝向注浆管远离围板的一侧。A vertically arranged grouting pipe is arranged in the gap between any two adjacent earth retaining plates, and a plurality of grouting holes arranged along the axis of the grouting pipe are arranged on the grouting pipe. The outlet end of the grout hole faces the side of the grout pipe away from the coaming plate.
本方案针对在砂卵地层基坑施工过程中,特别是深基坑施工过程中存在的施工难度大、容易对周边环境造成较大影响的问题,以砂卵地层通常伴有的富水特点且极容易发生坍塌的特点,提供以上方案。本方案在具体运用时,按照如下操作方法达到为几下结构施工提供安全防护用支护、提供基坑降水条件和提升基坑施工后,基坑周围底层稳定性的目的:This scheme is aimed at the problems of difficult construction and easy to have a great impact on the surrounding environment during the construction of the foundation pit in the sand egg stratum, especially in the construction of the deep foundation pit. It is extremely prone to collapse, and the above solutions are provided. In the specific application of this scheme, the following operation methods are used to achieve the purpose of providing safety protection support for the construction of several structures, providing foundation pit dewatering conditions and improving the stability of the bottom layer around the foundation pit after the foundation pit construction:
S1、完成所述围板、挡土板及注浆管在基坑边缘上的安装,利用所述装置,为基坑的壁面提供支护,本步骤中,所述围板、挡土板均作为支护上的挡土墙,通过贴合于基坑的内壁上,达到如避免以开挖基坑发生垮塌事故的目的,在具体运用时,由于在基坑的周向方向上,各挡土板的两端均支撑于对应位置的围板上,故采用支撑架,为围板在基坑的径向方向上提供支撑约束即可。S1. Complete the installation of the enclosure plate, the retaining plate and the grouting pipe on the edge of the foundation pit, and use the device to provide support for the wall of the foundation pit. In this step, the enclosure plate and the earth retaining plate are both As the retaining wall on the support, it can be attached to the inner wall of the foundation pit to achieve the purpose of avoiding collapse accidents when excavating the foundation pit. Both ends of the soil slab are supported on the coaming plate at the corresponding position, so a support frame is used to provide support and restraint for the coaming plate in the radial direction of the foundation pit.
S2、在基坑施工过程中,利用围板上的连通孔和排水口,实现基坑降水,本步骤中,针对如地下结构施工中,砂卵地质不便于设置井点降水的问题,采用在作为挡土墙组成部分的围板上开设连通孔和排水口,实现基坑降水,具体结构设计中,将围板设置为中空结构,旨在考虑:连通孔实际上为围板上的进水孔,排水口实际上为围板上的出水孔,而以上进水孔的设计实际上应该考虑为设置为尽可能多且覆盖面积尽可能大,这样,即可在一定程度上解决来自地层的水体由围板的局部集中引入围板,造成地层局部因为水体冲刷而形成大面积孔洞的问题,在水体进入围板以后在围板的内部汇聚,而后由排水口排出,可达到便于收集和抽取来自围板的出水,故在具体运用时,设置为连通孔覆盖外侧板的整个表面。S2. During the construction of the foundation pit, use the connecting holes and the drainage port on the hoarding to realize the dewatering of the foundation pit. In this step, for example, in the construction of the underground structure, the sand egg geology is not convenient for setting well point precipitation. As part of the retaining wall, there are communicating holes and drainage ports on the hoarding to realize the dewatering of the foundation pit. In the specific structural design, the hoarding is set as a hollow structure, in order to consider that the communicating holes are actually the water inlet on the hoarding. The water outlet is actually the water outlet on the hoarding, and the design of the above inlet holes should actually be considered to be set as many as possible and cover the area as large as possible, so that the problem from the formation can be solved to a certain extent. The water body is introduced into the hoarding plate from a local part of the hoarding plate, which causes the problem that large-area holes are formed in the stratum due to the scouring of the water body. The water comes from the enclosure plate, so in the specific application, the communication hole is set to cover the entire surface of the outer plate.
S3、完成基坑施工后,利用所述注浆管,向注浆管外侧注入灌浆料,且在灌浆料固化过程中,利用围板作为注浆管支撑用模板,采用本方案,针对基坑降水不可避免的形成位于基坑壁面的空洞,利用所述注浆管,受压的灌浆料可填补所述空洞,通过增加基坑壁面的密实度,达到利于基坑周围地层的稳定性的目的。S3. After the foundation pit construction is completed, the grouting pipe is used to inject grouting material to the outside of the grouting pipe, and during the solidification process of the grouting material, the coaming plate is used as a template for supporting the grouting pipe. This scheme is adopted for the foundation pit. Precipitation inevitably forms a cavity on the wall of the foundation pit. Using the grouting pipe, the pressurized grouting material can fill the cavity. By increasing the density of the wall of the foundation pit, the stability of the stratum around the foundation pit can be achieved. .
本方案在具体运用时,围板可采用多块板材拼接而成,如根据内部设计,针对不采用过滤网的方案,可采用6块平板焊接,针对包括过滤网且需要对过滤网进行维护的方案,设置为其中一块平板与其相接平板螺栓连接等。In the specific application of this scheme, the hoarding plate can be spliced by multiple plates. For example, according to the internal design, for the scheme without filter screen, 6 flat plates can be used for welding. The scheme is set as one of the plates is bolted to the connecting plate, etc.
更进一步的技术方案为:Further technical solutions are:
为利用本装置形成对基坑壁面的全部防护,设置为:所述围板与挡土板围成筒状结构,各围板与与之接触的挡土板之间均设置有竖向设置的密封条。采用本方案,利用所述密封条,使得基坑降水的流通路径仅限于穿过围板,这样,如井点降水和控制井点降水的流量上,便于本领域技术人员获得平衡点:即满足降水需要,亦满足对周围底层安全的考虑,如通过控制排水口的出水流量,达到以上目的。In order to use this device to form all the protection for the wall of the foundation pit, it is set as follows: the enclosure plate and the retaining plate form a cylindrical structure, and there are vertically arranged between each enclosure plate and the earth retaining plate in contact with it. sealing strip. With this solution, using the sealing strip, the circulation path of the foundation pit precipitation is limited to passing through the hoarding plate, so that, for example, in the well point precipitation and the control of the flow rate of the well point precipitation, it is convenient for those skilled in the art to obtain a balance point: that is, satisfying Precipitation needs, but also meet the consideration of the safety of the surrounding ground floor, such as by controlling the water flow of the drainage outlet to achieve the above purpose.
为便于实现围板出水收集和实现以上平衡点掌握,设置为:各围板底部内侧均设置有固定于内侧板上的水槽,所述排水口的出口端位于水槽内;In order to facilitate the collection of water from the coaming plate and to realize the above balance point control, it is set as follows: the inner side of the bottom of each coaming plate is provided with a water tank fixed on the inner side plate, and the outlet end of the water outlet is located in the water tank;
各围板上排水口的流体导通能力均可调。The fluid conduction capacity of the drain outlet on each coaming plate can be adjusted.
作为一种排水口的流体导通能力可调的具体方案,设置为:各围板上排水口的数量均为多个,且在各围板上,部分或全部排水口的封堵状态可调。本方案通过多个排水口形成围板出水流量调节,具体调节方式采用封堵部分排水口的方式。在具体运用时,如基坑排水不满足安全需要,可采用如上排水口全部封堵的状态。As a specific solution for the adjustable fluid conduction capacity of the drainage outlet, it is set as follows: the number of drainage outlets on each coaming plate is multiple, and the blocking state of some or all of the drainage outlets on each coaming plate can be adjusted. . In this scheme, a plurality of drainage ports are used to form the water outlet flow adjustment of the coaming plate, and the specific adjustment method adopts the method of blocking part of the drainage ports. In the specific application, if the drainage of the foundation pit does not meet the safety requirements, the state of all the drainage outlets as above can be adopted.
如上所述,本方案在具体实施时,为实现围板通过排水口排水流量多梯度可调,优选设置为排水口数量尽可能多,同时,考虑到围板外侧板上对基坑边缘的导水能力,避免集中导水导致基坑局部孔洞过大扩大基坑开挖对底层造成的影响,优选采用连通孔均匀分布在外侧板整个面上的方式,作为一种排水口防堵方案,设置为:还包括设置在各围板中空空间内的过滤网,在围板的板厚方向上,所述过滤网将所述中空空间分割为外侧腔体和内侧腔体,所述外侧腔体为过滤网与外侧板之间的腔体,所述内侧腔体为过滤网与内侧板之间的腔体;As mentioned above, in the specific implementation of this scheme, in order to realize the multi-gradient adjustable drainage flow of the coaming plate through the drainage outlet, it is preferable to set the number of drainage outlets as much as possible. Water capacity, avoid concentrated water diversion leading to oversized local holes in the foundation pit and expand the influence of foundation pit excavation on the bottom layer. It also includes a filter screen arranged in the hollow space of each enclosure plate, in the thickness direction of the enclosure plate, the filter screen divides the hollow space into an outer cavity and an inner cavity, and the outer cavity is a cavity between the filter screen and the outer plate, the inner cavity is the cavity between the filter screen and the inner plate;
还包括连接在围板底侧、入口端与内侧腔体相接的排泥口;It also includes a mud discharge port connected to the bottom side of the coaming plate, and the inlet end is connected with the inner cavity;
还包括连接在围板上,出口端与内侧腔体相接的注水口;It also includes a water injection port connected to the enclosure, and the outlet end is connected to the inner cavity;
所述排泥口、注水口均设置有用于控制各自通断状态的截断装置。本方案中,利用所述过滤网作为连通孔与排水口之间的过滤组件,避免如因为由于连通孔较多,短期内向围板内引入沙、泥等造成排水口被堵塞;设置为包括所述排泥口、注水口,旨在实现:定期或在需要的情况下,通过所述注水口注入清洗水清洗外侧腔体,再由排泥口排出;设置为还包括截断装置,旨在实现在非必要情况下排泥口截断,流体仅富集在水槽中由一般的泵体抽出;以上排泥口、注水口的位置限定,旨在尽可能的通过以上清洗水覆盖过滤网的整个过滤面;以上截断装置的设置不仅旨在实现以上限流目的,同时亦可通过外侧腔体作为进入围板砂、泥的暂存空间,如利用一定时间间隔外侧腔体内积累的砂、泥,判断此时降水流量对地层安全性的影响。Both the mud discharge port and the water injection port are provided with cut-off devices for controlling their respective on-off states. In this solution, the filter screen is used as the filter element between the communication hole and the drain port to avoid blockage of the drain port due to the introduction of sand, mud, etc. into the enclosure in a short time due to the large number of communication holes; The mud discharge port and the water injection port are designed to realize: regularly or when necessary, inject cleaning water through the water injection port to clean the outer cavity, and then discharge from the mud discharge port; it is arranged to further include a cut-off device, which aims to realize The mud discharge port is cut off when it is not necessary, and the fluid is only concentrated in the water tank and pumped out by the general pump body; the positions of the above mud discharge port and water injection port are limited, and the purpose is to cover the entire filter screen with the above cleaning water as much as possible. The above cut-off device is not only designed to achieve the above purpose of limiting the flow, but also can be used as a temporary storage space for sand and mud entering the coaming plate through the outer cavity. The influence of precipitation flow on formation safety at this time.
作为一种在封闭各排水口、关断所述截断装置情况下,通过向围板中空空间内引入压力气体,解决连通孔堵塞情况的技术方案,设置为:各排水口均匹配有堵头,还包括连接在围板上,出口端与所述中空空间相通的连通管。As a technical solution to solve the blockage of the communication holes by introducing pressure gas into the hollow space of the enclosure under the condition of closing the drains and shutting off the cut-off device, it is set as follows: each drain is matched with a plug, It also includes a communication pipe connected to the enclosure plate, and the outlet end communicates with the hollow space.
作为一种便于过滤网安装和使用过程中清洁维护的技术方案:所述过滤网与围板的连接通过如下方式实现:所述过滤网与围板的连接通过如下方式实现:围板的其余四个面分别为上端面、下端面、左端面和右端面,其余四个面中,任意一者螺栓连接于围板上;As a technical solution to facilitate cleaning and maintenance during the installation and use of the filter screen: the connection between the filter screen and the enclosure is achieved in the following manner: the connection between the filter screen and the enclosure is achieved in the following manner: the remaining four of the enclosure are connected. Each surface is the upper end surface, the lower end surface, the left end surface and the right end surface, and any one of the remaining four surfaces is bolted to the hoarding plate;
在围板中空空间的壁面上设置有两条呈正对关系的滑槽,所述过滤网通过所述滑槽夹持在所述中空空间内;Two chutes in a facing relationship are provided on the wall surface of the hollow space of the enclosure plate, and the filter screen is clamped in the hollow space through the chutes;
所述滑槽的起始端正对螺栓连接在围板上的面。采用本方案,在拆离螺栓连接在围板上的面后,即可通过抽、插操作,完成过滤网的拆卸或安装。The starting end of the chute is opposite to the surface of the shroud that is bolted to. With this solution, the removal or installation of the filter screen can be completed by pulling and inserting operations after the bolts are disconnected from the surface of the enclosure.
还包括设置在内侧腔体内的支撑板,所述过滤网作为内侧腔体边界的表面支撑于所述支撑板上。It also includes a support plate arranged in the inner cavity, and the filter screen is supported on the support plate as the surface of the inner cavity boundary.
作为一种便于完成围板在基坑边缘约束的技术方案,设置为:还包括用于支撑围板的支撑架,所述支撑架包括立杆及沿着立杆轴线方向排布的多根横杆,所述横杆作为立杆与各围板内侧之间的支撑件,所述横杆的长度可调;作为一种横杆长度可调且便于调整的具体方案,所述横杆包括相串联的螺纹筒及螺纹杆,所述螺纹筒与螺纹杆螺纹连接且同轴,所述螺纹筒与立杆相连,所述螺纹杆的端部与围板内侧之间均设置有垫板;As a technical solution to facilitate the confinement of the enclosure plate at the edge of the foundation pit, it is provided as follows: a support frame for supporting the enclosure plate is further included, the support frame includes a vertical pole and a plurality of horizontal bars arranged along the axis direction of the vertical pole. The horizontal bar is used as a support between the vertical bar and the inner side of each enclosure, and the length of the horizontal bar is adjustable; as a specific solution for the adjustable length of the horizontal bar and easy adjustment, the horizontal bar includes A threaded barrel and a threaded rod are connected in series, the threaded barrel and the threaded rod are threadedly connected and coaxial, the threaded barrel is connected with the vertical rod, and a backing plate is provided between the end of the threaded rod and the inner side of the enclosure;
所述垫板包括:为钢板的第一板体、为塑料板或石墨板的第二板体、为钢板的第三板体,所述第一板体与螺纹杆固定连接,所述第二板体夹持在第一板体与第三板体之间,所述底板板体的外侧与围板内侧接触,本方案结构简单,第二板体作为第一板体与第三板体之间的减磨板材,以便于实现第一板体与第三板体相对转动;The backing plate includes: a first plate body that is a steel plate, a second plate body that is a plastic plate or a graphite plate, and a third plate body that is a steel plate, the first plate body is fixedly connected with the threaded rod, the second plate body is The plate body is clamped between the first plate body and the third plate body, and the outer side of the bottom plate body is in contact with the inner side of the enclosure plate. between the wear-reducing plates, so as to realize the relative rotation of the first plate body and the third plate body;
作为一种通过均衡立杆两侧受力,便于稳定立杆在空间中的位置,使得支撑架为分体式结构,便于支撑架位置转移和存储,使得可根据具体支撑需要方便的调整横杆位置的技术方案,设置为:还包括套设在立杆上,能够沿着立杆轴线滑动的套筒,各套筒上均固定有两根横杆,且各套筒上的横杆均相对于套筒的轴线呈线对称;As a method of balancing the force on both sides of the pole, it is convenient to stabilize the position of the pole in the space, so that the support frame is a split structure, which is convenient for the position transfer and storage of the support frame, so that the position of the cross bar can be easily adjusted according to the specific support needs. The technical scheme is set as follows: it also includes a sleeve sleeved on the vertical rod and capable of sliding along the axis of the vertical rod, two cross bars are fixed on each sleeve, and the cross bars on each sleeve are opposite to The axis of the sleeve is line-symmetric;
围板的数量为偶数个且围板相对于立杆的轴线环形均布,各套筒上横杆的端部均作用在立杆对应侧的围板上;The number of the coaming plates is an even number, and the coaming plates are evenly distributed relative to the axis of the vertical rod.
还包括用于实现套筒在横杆轴线上位置锁定的锁定装置。以上具体结构设计中,设置为:围板为的数量为偶数个且环形均布在立杆的周向方向上,针对立杆的受力,由于来自不同侧横杆的推力方向相反,故由套筒、横杆组成的装配体可有效优化立杆的受力,提高支撑架的稳定性。Also included is a locking device for achieving positional locking of the sleeve on the axis of the crossbar. In the above specific structural design, it is set as follows: the number of enclosures is an even number and the rings are evenly distributed in the circumferential direction of the vertical rod. For the force on the vertical rod, since the thrust directions from different side cross rods are opposite, the The assembly composed of the sleeve and the cross rod can effectively optimize the force of the vertical rod and improve the stability of the support frame.
设置为套筒可沿着立杆的轴线滑动,如配合在立杆的上端设置可拆卸的吊环,针对支撑架的设置以及本装置的装配,方便通过如下操作,在经济合理、易于操作的情况下,获得安全可靠的施工方案:It is set so that the sleeve can slide along the axis of the vertical pole. For example, a detachable lifting ring is arranged on the upper end of the vertical pole. For the setting of the support frame and the assembly of the device, the following operations are convenient. In the case of economical, reasonable and easy operation Next, get a safe and reliable construction plan:
D1、完成全部套筒在立杆上的套设,且套筒层叠于立杆的底部;D1. Complete the sleeves of all the sleeves on the poles, and the sleeves are stacked on the bottom of the poles;
完成围板在支撑架侧面的安装,且使得围板与挡土板的内侧面相贴;Complete the installation of the hoarding plate on the side of the support frame, and make the hoarding plate abut the inner side of the retaining plate;
完成吊环在立杆顶部的安装;Complete the installation of the lifting ring on the top of the pole;
D2、调整最下方套筒两侧横杆的长度,使得横杆的两端均形成与对应侧围板的支撑关系,利用以上支撑关系,可约束立杆在空间的位置以及维持立杆的力气状态;D2. Adjust the length of the crossbars on both sides of the lowermost sleeve, so that both ends of the crossbar form a support relationship with the corresponding side wall. Using the above support relationship, the position of the vertical bar in space can be restricted and the strength of the vertical bar can be maintained state;
D3、利用挂设在吊环上的吊装工具,依次起吊最下方套筒上侧套筒上的横杆,使得对应套筒随其上的横杆移动至所需的立杆轴线位置;D3. Use the hoisting tool hung on the hoisting ring to hoist the crossbar on the upper sleeve of the lowermost sleeve in turn, so that the corresponding sleeve moves to the required vertical rod axis position with the crossbar on it;
具体起吊为:最上层的套筒为最先起吊并在轴线位置确定后,通过调整横杆长度以约束对应侧围板后,通过对应的锁定装置完成固定于立杆上的一者,而后,在套筒的排列顺序上,依次由上至下完成各套筒在立杆上的位置调节、调整横杆长度以约束围板和在立杆上的位置固定。The specific lifting is as follows: the uppermost sleeve is the first to be lifted and the position of the axis is determined. After adjusting the length of the crossbar to constrain the corresponding side wall, the corresponding locking device is used to complete the one that is fixed on the vertical rod, and then, In terms of the arrangement sequence of the sleeves, the position adjustment of each sleeve on the vertical rod, the adjustment of the length of the cross rod to constrain the enclosure plate and the fixed position on the vertical rod are completed sequentially from top to bottom.
所述吊环可拆卸,使得立杆可以光杆的形式先完成在安装位置的立起,而后如由立杆的上端,完成各套筒的套设,而后再安装好吊环,为各套筒提供位于立杆顶端的吊点。The lifting ring is detachable, so that the vertical rod can be erected at the installation position first in the form of a polished rod, and then the sleeves are set up by the upper end of the vertical rod, and then the lifting ring is installed to provide each sleeve with The hanging point at the top of the pole.
具体结构限定以及操作方式中,利用最下方套筒上的横杆,即可实现利用围板,为立杆的支撑状态形成防倒约束,这样,在进行后续套筒吊起时,可使得立杆处于相对稳定的状态,直至完成所有套筒位置调整,如利用手拉葫芦、电动葫芦的方式完成包括套筒和横杆组合体吊起,实现立杆的防倒约束和完成后续吊装均具有操作方便,经济性好的特点。针对套筒的位置固定,可在立杆的轴线方向上设置数量对于套筒数量的插销孔,根据具体套筒的安装需要,选择对应位置的插销孔,使得套筒与立杆形成销连接关系即可达到固定目的。In the specific structure limitation and operation mode, the use of the horizontal bar on the lowermost sleeve can realize the use of the enclosure plate to form an anti-fall constraint for the support state of the vertical bar. In this way, when the subsequent sleeve is hoisted, the vertical The rod is in a relatively stable state until all sleeve position adjustments are completed, such as the use of chain hoists and electric hoists to complete the lifting of the combination of the sleeve and the cross bar, to achieve the anti-fall restraint of the vertical pole and complete the subsequent hoisting. Easy to operate and economical. For the fixed position of the sleeve, the number of bolt holes corresponding to the number of sleeves can be set in the axial direction of the vertical rod. According to the installation requirements of the specific sleeve, the corresponding position of the bolt hole can be selected, so that the sleeve and the vertical rod form a pin connection relationship to achieve a fixed purpose.
本方案还提供了一种具体的施工方法,该方法基于如上任意一项所述的装置,该方法通过如下步骤实现:This solution also provides a specific construction method, the method is based on the device described in any one of the above, and the method is realized by the following steps:
S1、完成所述围板、挡土板及注浆管在基坑边缘上的安装,利用所述装置,为基坑的壁面提供支护;S1. Complete the installation of the enclosure plate, the earth retaining plate and the grouting pipe on the edge of the foundation pit, and use the device to provide support for the wall of the foundation pit;
S2、在基坑施工过程中,利用围板上的连通孔和排水口,实现基坑降水;S2. During the construction of the foundation pit, use the connecting holes and drainage ports on the hoarding to realize the dewatering of the foundation pit;
S3、完成基坑施工后,利用所述注浆管,向注浆管外侧注入灌浆料,且在灌浆料固化过程中,利用围板作为注浆管支撑用模板。S3. After the foundation pit construction is completed, the grouting pipe is used to inject grouting material to the outside of the grouting pipe, and during the curing process of the grouting material, the coaming plate is used as a template for supporting the grouting pipe.
在具体运用时,优选设置为各挡土板之间均设置有多根注浆管,针对同样的注浆面积,多根注浆管可减小单根注浆管的内径,以提升注浆管的抗压能力,以获得更好的注浆效果,同时,针对利用围板实现降水的目的,多根注浆管亦可覆盖尽可能大的用于实现降水的基坑壁面排水面积。In specific application, it is preferable to set multiple grouting pipes between each retaining plate. For the same grouting area, multiple grouting pipes can reduce the inner diameter of a single grouting pipe to improve grouting. The compressive capacity of the pipe can be used to obtain better grouting effect. At the same time, for the purpose of using the coaming plate to achieve dewatering, multiple grouting pipes can also cover the largest possible drainage area of the foundation pit wall for dewatering.
进一步的,各挡土板之间的注浆管形成注浆区域,为利于灌浆区域的结构稳定性,优选设置为各灌浆区域内均设置有作为灌浆料钢筋骨架的钢筋网,如通过灌浆的形式最终形成包括钢筋骨架的混凝土挡土墙。Further, the grouting pipes between each retaining plate form a grouting area. In order to facilitate the structural stability of the grouting area, it is preferable to set each grouting area with a steel mesh serving as a reinforced skeleton of the grouting material, such as through grouting. The form culminates in a concrete retaining wall comprising a reinforced skeleton.
本发明具有以下有益效果:The present invention has the following beneficial effects:
本方案针对在砂卵地层基坑施工过程中,特别是深基坑施工过程中存在的施工难度大、容易对周边环境造成较大影响的问题,以砂卵地层通常伴有的富水特点且极容易发生坍塌的特点,提供以上方案。本方案在具体运用时,按照如下操作方法达到为几下结构施工提供安全防护用支护、提供基坑降水条件和提升基坑施工后,基坑周围底层稳定性的目的:This scheme is aimed at the problems of difficult construction and easy to have a great impact on the surrounding environment during the construction of the foundation pit in the sand egg stratum, especially in the construction of the deep foundation pit. It is extremely prone to collapse, and the above solutions are provided. In the specific application of this scheme, the following operation methods are used to achieve the purpose of providing safety protection support for the construction of several structures, providing foundation pit dewatering conditions and improving the stability of the bottom layer around the foundation pit after the foundation pit construction:
S1、完成所述围板、挡土板及注浆管在基坑边缘上的安装,利用所述装置,为基坑的壁面提供支护,本步骤中,所述围板、挡土板均作为支护上的挡土墙,通过贴合于基坑的内壁上,达到如避免以开挖基坑发生垮塌事故的目的,在具体运用时,由于在基坑的周向方向上,各挡土板的两端均支撑于对应位置的围板上,故采用支撑架,为围板在基坑的径向方向上提供支撑约束即可。S1. Complete the installation of the enclosure plate, the retaining plate and the grouting pipe on the edge of the foundation pit, and use the device to provide support for the wall of the foundation pit. In this step, the enclosure plate and the earth retaining plate are both As the retaining wall on the support, it can be attached to the inner wall of the foundation pit to achieve the purpose of avoiding collapse accidents when excavating the foundation pit. Both ends of the soil slab are supported on the coaming plate at the corresponding position, so a support frame is used to provide support and restraint for the coaming plate in the radial direction of the foundation pit.
S2、在基坑施工过程中,利用围板上的连通孔和排水口,实现基坑降水,本步骤中,针对如地下结构施工中,砂卵地质不便于设置井点降水的问题,采用在作为挡土墙组成部分的围板上开设连通孔和排水口,实现基坑降水,具体结构设计中,将围板设置为中空结构,旨在考虑:连通孔实际上为围板上的进水孔,排水口实际上为围板上的出水孔,而以上进水孔的设计实际上应该考虑为设置为尽可能多且覆盖面积尽可能大,这样,即可在一定程度上解决来自地层的水体由围板的局部集中引入围板,造成地层局部因为水体冲刷而形成大面积孔洞的问题,在水体进入围板以后在围板的内部汇聚,而后由排水口排出,可达到便于收集和抽取来自围板的出水,故在具体运用时,设置为连通孔覆盖外侧板的整个表面。S2. During the construction of the foundation pit, use the connecting holes and the drainage port on the hoarding to realize the dewatering of the foundation pit. In this step, for example, in the construction of the underground structure, the sand egg geology is not convenient for setting well point precipitation. As part of the retaining wall, there are communicating holes and drainage ports on the hoarding to realize the dewatering of the foundation pit. In the specific structural design, the hoarding is set as a hollow structure, in order to consider that the communicating holes are actually the water inlet on the hoarding. The water outlet is actually the water outlet on the hoarding, and the design of the above inlet holes should actually be considered to be set as many as possible and cover the area as large as possible, so that the problem from the formation can be solved to a certain extent. The water body is introduced into the hoarding plate from a local part of the hoarding plate, which causes the problem that large-area holes are formed in the stratum due to the scouring of the water body. The water comes from the enclosure plate, so in the specific application, the communication hole is set to cover the entire surface of the outer plate.
S3、完成基坑施工后,利用所述注浆管,向注浆管外侧注入灌浆料,且在灌浆料固化过程中,利用围板作为注浆管支撑用模板,采用本方案,针对基坑降水不可避免的形成位于基坑壁面的空洞,利用所述注浆管,受压的灌浆料可填补所述空洞,通过增加基坑壁面的密实度,达到利于基坑周围地层的稳定性的目的。S3. After the foundation pit construction is completed, the grouting pipe is used to inject grouting material to the outside of the grouting pipe, and during the solidification process of the grouting material, the coaming plate is used as a template for supporting the grouting pipe. This scheme is adopted for the foundation pit. Precipitation inevitably forms a cavity on the wall of the foundation pit. Using the grouting pipe, the pressurized grouting material can fill the cavity. By increasing the density of the wall of the foundation pit, the stability of the stratum around the foundation pit can be achieved. .
附图说明Description of drawings
图1是本发明所述的用于地下结构安全施工的施工装置一个具体实施例的主视图且为局部结构示意图,用于反映支撑架与围板的配合关系;1 is a front view of a specific embodiment of the construction device for the safe construction of underground structures according to the present invention and is a schematic diagram of a partial structure, used to reflect the matching relationship between the support frame and the enclosure;
图2是本发明所述的用于地下结构安全施工的施工装置一个具体实施例的局部示意图,该示意图用于反映围板部分的结构组成;2 is a partial schematic diagram of a specific embodiment of the construction device for the safe construction of underground structures according to the present invention, and the schematic diagram is used to reflect the structural composition of the coaming plate part;
图3是本发明所述的用于地下结构安全施工的施工装置一个具体实施例的俯视图;3 is a top view of a specific embodiment of the construction device for the safe construction of underground structures according to the present invention;
图4是本发明所述的用于地下结构安全施工的施工装置一个具体实施例中,注浆管的结构示意图。4 is a schematic structural diagram of a grouting pipe in a specific embodiment of the construction device for safe construction of an underground structure according to the present invention.
图中的附图标记依次为:1、围板,2、横杆,3、立杆,4、螺纹筒,5、螺纹杆,6、垫板,7、排泥口,8、连通管,9、注水口,10、注浆管,101、注浆孔,11、钢筋网,12、水槽,13、排水口,14、堵头,15、连通孔,16、过滤网,17、支撑板,18、吊环,19、插销孔,20、套筒,21、挡土板。The reference signs in the figure are: 1, enclosure plate, 2, cross bar, 3, vertical rod, 4, threaded barrel, 5, threaded rod, 6, backing plate, 7, mud discharge port, 8, connecting pipe, 9, water injection port, 10, grouting pipe, 101, grouting hole, 11, steel mesh, 12, water tank, 13, drain outlet, 14, plug, 15, connecting hole, 16, filter screen, 17, support plate , 18, lifting ring, 19, bolt hole, 20, sleeve, 21, retaining plate.
具体实施方式Detailed ways
下面结合实施例对本发明作进一步的详细说明,但是本发明的结构不仅限于以下实施例。The present invention will be further described in detail below in conjunction with the examples, but the structure of the present invention is not limited to the following examples.
实施例1:Example 1:
如图1至图4所示,用于地下结构安全施工的施工装置,包括基坑支护组件,所述基坑支护组件包括多块沿着基坑周向方向依次排布的支护板,所述支护板包括多块围板1及多块挡土板21;As shown in Figures 1 to 4, the construction device for the safe construction of underground structures includes a foundation pit support assembly, and the foundation pit support assembly includes a plurality of support plates arranged in sequence along the circumferential direction of the foundation pit , the support plate includes a plurality of
所述挡土板21沿着基坑的周向方向间隔排布,任意两相邻挡土板21之间均设置有一块围板1,各围板1的外侧均挤压于对应两挡土板21的内侧上;The
所述围板1为中空的板状结构;The
所述围板1包括用于与基坑相接的外侧板及靠近基坑中心的内侧板,所述外侧板上开设有多个贯通外侧板内、外侧的连通孔15;所述内侧板上开设有贯通内侧板内、外侧的排水口13;The
任意两相邻挡土板21之间的间隙内均设置有竖向设置的注浆管10,所述注浆管10上设置有多个沿着注浆管10轴线方向排布的注浆孔101,所述注浆孔101的出口端朝向注浆管10远离围板1的一侧。A vertically arranged
本方案针对在砂卵地层基坑施工过程中,特别是深基坑施工过程中存在的施工难度大、容易对周边环境造成较大影响的问题,以砂卵地层通常伴有的富水特点且极容易发生坍塌的特点,提供以上方案。本方案在具体运用时,按照如下操作方法达到为几下结构施工提供安全防护用支护、提供基坑降水条件和提升基坑施工后,基坑周围底层稳定性的目的:This scheme is aimed at the problems of difficult construction and easy to have a great impact on the surrounding environment during the construction of the foundation pit in the sand egg stratum, especially in the construction of the deep foundation pit. It is extremely prone to collapse, and the above solutions are provided. In the specific application of this scheme, the following operation methods are used to achieve the purpose of providing safety protection support for the construction of several structures, providing foundation pit dewatering conditions and improving the stability of the bottom layer around the foundation pit after the foundation pit construction:
S1、完成所述围板1、挡土板21及注浆管10在基坑边缘上的安装,利用所述装置,为基坑的壁面提供支护,本步骤中,所述围板1、挡土板21均作为支护上的挡土墙,通过贴合于基坑的内壁上,达到如避免以开挖基坑发生垮塌事故的目的,在具体运用时,由于在基坑的周向方向上,各挡土板21的两端均支撑于对应位置的围板1上,故采用支撑架,为围板1在基坑的径向方向上提供支撑约束即可。S1. Complete the installation of the
S2、在基坑施工过程中,利用围板1上的连通孔15和排水口13,实现基坑降水,本步骤中,针对如地下结构施工中,砂卵地质不便于设置井点降水的问题,采用在作为挡土墙组成部分的围板1上开设连通孔15和排水口13,实现基坑降水,具体结构设计中,将围板1设置为中空结构,旨在考虑:连通孔15实际上为围板1上的进水孔,排水口13实际上为围板1上的出水孔,而以上进水孔的设计实际上应该考虑为设置为尽可能多且覆盖面积尽可能大,这样,即可在一定程度上解决来自地层的水体由围板1的局部集中引入围板1,造成地层局部因为水体冲刷而形成大面积孔洞的问题,在水体进入围板1以后在围板1的内部汇聚,而后由排水口13排出,可达到便于收集和抽取来自围板1的出水,故在具体运用时,设置为连通孔15覆盖外侧板的整个表面。S2. During the construction of the foundation pit, use the communication holes 15 and the
S3、完成基坑施工后,利用所述注浆管10,向注浆管10外侧注入灌浆料,且在灌浆料固化过程中,利用围板1作为注浆管10支撑用模板,采用本方案,针对基坑降水不可避免的形成位于基坑壁面的空洞,利用所述注浆管10,受压的灌浆料可填补所述空洞,通过增加基坑壁面的密实度,达到利于基坑周围地层的稳定性的目的。S3. After the foundation pit construction is completed, the
本方案在具体运用时,围板1可采用多块板材拼接而成,如根据内部设计,针对不采用过滤网16的方案,可采用6块平板焊接,针对包括过滤网16且需要对过滤网16进行维护的方案,设置为其中一块平板与其相接平板螺栓连接等。In the specific application of this scheme, the
实施例2:Example 2:
如图1至图4所示,本实施例在实施例1的基础上作进一步限定:为利用本装置形成对基坑壁面的全部防护,设置为:所述围板1与挡土板21围成筒状结构,各围板1与与之接触的挡土板21之间均设置有竖向设置的密封条。采用本方案,利用所述密封条,使得基坑降水的流通路径仅限于穿过围板1,这样,如井点降水和控制井点降水的流量上,便于本领域技术人员获得平衡点:即满足降水需要,亦满足对周围底层安全的考虑,如通过控制排水口13的出水流量,达到以上目的。As shown in Figures 1 to 4, this embodiment is further limited on the basis of Embodiment 1: in order to use this device to form all protection for the walls of the foundation pit, it is set as follows: the
为便于实现围板1出水收集和实现以上平衡点掌握,设置为:各围板1底部内侧均设置有固定于内侧板上的水槽12,所述排水口13的出口端位于水槽12内;In order to facilitate the collection of water from the
各围板1上排水口13的流体导通能力均可调。The fluid conducting capacity of the
作为一种排水口13的流体导通能力可调的具体方案,设置为:各围板1上排水口13的数量均为多个,且在各围板1上,部分或全部排水口13的封堵状态可调。本方案通过多个排水口13形成围板1出水流量调节,具体调节方式采用封堵部分排水口13的方式。在具体运用时,如基坑排水不满足安全需要,可采用如上排水口13全部封堵的状态。As a specific solution for the adjustable fluid conduction capacity of the
如上所述,本方案在具体实施时,为实现围板1通过排水口13排水流量多梯度可调,优选设置为排水口13数量尽可能多,同时,考虑到围板1外侧板上对基坑边缘的导水能力,避免集中导水导致基坑局部孔洞过大扩大基坑开挖对底层造成的影响,优选采用连通孔15均匀分布在外侧板整个面上的方式,作为一种排水口13防堵方案,设置为:还包括设置在各围板1中空空间内的过滤网16,在围板1的板厚方向上,所述过滤网16将所述中空空间分割为外侧腔体和内侧腔体,所述外侧腔体为过滤网16与外侧板之间的腔体,所述内侧腔体为过滤网16与内侧板之间的腔体;As mentioned above, in the specific implementation of this solution, in order to realize the multi-gradient adjustable drainage flow of the
还包括连接在围板1底侧、入口端与内侧腔体相接的排泥口7;It also includes a
还包括连接在围板1上,出口端与内侧腔体相接的注水口9;It also includes a water injection port 9 connected to the
所述排泥口7、注水口9均设置有用于控制各自通断状态的截断装置。本方案中,利用所述过滤网16作为连通孔15与排水口13之间的过滤组件,避免如因为由于连通孔15较多,短期内向围板1内引入沙、泥等造成排水口13被堵塞;设置为包括所述排泥口7、注水口9,旨在实现:定期或在需要的情况下,通过所述注水口9注入清洗水清洗外侧腔体,再由排泥口7排出;设置为还包括截断装置,旨在实现在非必要情况下排泥口7截断,流体仅富集在水槽12中由一般的泵体抽出;以上排泥口7、注水口9的位置限定,旨在尽可能的通过以上清洗水覆盖过滤网16的整个过滤面;以上截断装置的设置不仅旨在实现以上限流目的,同时亦可通过外侧腔体作为进入围板1砂、泥的暂存空间,如利用一定时间间隔外侧腔体内积累的砂、泥,判断此时降水流量对地层安全性的影响。Both the
作为一种在封闭各排水口13、关断所述截断装置情况下,通过向围板1中空空间内引入压力气体,解决连通孔15堵塞情况的技术方案,设置为:各排水口13均匹配有堵头14,还包括连接在围板1上,出口端与所述中空空间相通的连通管8。As a technical solution for solving the blockage of the communication holes 15 by introducing pressure gas into the hollow space of the
作为一种便于过滤网16安装和使用过程中清洁维护的技术方案:所述过滤网16与围板1的连接通过如下方式实现:所述过滤网16与围板1的连接通过如下方式实现:围板1的其余四个面分别为上端面、下端面、左端面和右端面,其余四个面中,任意一者螺栓连接于围板1上;As a technical solution to facilitate the cleaning and maintenance of the
在围板1中空空间的壁面上设置有两条呈正对关系的滑槽,所述过滤网16通过所述滑槽夹持在所述中空空间内;On the wall surface of the hollow space of the
所述滑槽的起始端正对螺栓连接在围板1上的面。采用本方案,在拆离螺栓连接在围板1上的面后,即可通过抽、插操作,完成过滤网16的拆卸或安装。The starting end of the chute is facing the surface where the bolts are connected to the
还包括设置在内侧腔体内的支撑板17,所述过滤网16作为内侧腔体边界的表面支撑于所述支撑板17上。It also includes a
在具体运用时,优选设置为各挡土板21之间均设置有多根注浆管10,针对同样的注浆面积,多根注浆管10可减小单根注浆管10的内径,以提升注浆管10的抗压能力,以获得更好的注浆效果,同时,针对利用围板1实现降水的目的,多根注浆管10亦可覆盖尽可能大的用于实现降水的基坑壁面排水面积。In specific application, it is preferable to set
进一步的,各挡土板21之间的注浆管10形成注浆区域,为利于灌浆区域的结构稳定性,优选设置为各灌浆区域内均设置有作为灌浆料钢筋骨架的钢筋网11,如通过灌浆的形式最终形成包括钢筋骨架的混凝土挡土墙。Further, the
实施例3:Example 3:
如图1至图4所示,本实施例在实施例1的基础上作进一步限定,As shown in FIG. 1 to FIG. 4 , this embodiment is further limited on the basis of
作为一种便于完成围板1在基坑边缘约束的技术方案,设置为:还包括用于支撑围板1的支撑架,所述支撑架包括立杆3及沿着立杆3轴线方向排布的多根横杆2,所述横杆2作为立杆3与各围板1内侧之间的支撑件,所述横杆2的长度可调;作为一种横杆2长度可调且便于调整的具体方案,所述横杆2包括相串联的螺纹筒4及螺纹杆5,所述螺纹筒4与螺纹杆5螺纹连接且同轴,所述螺纹筒4与立杆3相连,所述螺纹杆5的端部与围板1内侧之间均设置有垫板6;As a technical solution to facilitate the confinement of the
所述垫板6包括:为钢板的第一板体、为塑料板或石墨板的第二板体、为钢板的第三板体,所述第一板体与螺纹杆5固定连接,所述第二板体夹持在第一板体与第三板体之间,所述底板板体的外侧与围板1内侧接触,本方案结构简单,第二板体作为第一板体与第三板体之间的减磨板材,以便于实现第一板体与第三板体相对转动;The
作为一种通过均衡立杆3两侧受力,便于稳定立杆3在空间中的位置,使得支撑架为分体式结构,便于支撑架位置转移和存储,使得可根据具体支撑需要方便的调整横杆2位置的技术方案,设置为:还包括套设在立杆3上,能够沿着立杆3轴线滑动的套筒20,各套筒20上均固定有两根横杆2,且各套筒20上的横杆2均相对于套筒20的轴线呈线对称;As a way of balancing the force on both sides of the
围板1的数量为偶数个且围板1相对于立杆3的轴线环形均布,各套筒20上横杆2的端部均作用在立杆3对应侧的围板1上;The number of the
还包括用于实现套筒20在横杆2轴线上位置锁定的锁定装置。以上具体结构设计中,设置为:围板1为的数量为偶数个且环形均布在立杆3的周向方向上,针对立杆3的受力,由于来自不同侧横杆2的推力方向相反,故由套筒20、横杆2组成的装配体可有效优化立杆3的受力,提高支撑架的稳定性。Also included is a locking device for locking the position of the
设置为套筒20可沿着立杆3的轴线滑动,如配合在立杆3的上端设置可拆卸的吊环18,针对支撑架的设置以及本装置的装配,方便通过如下操作,在经济合理、易于操作的情况下,获得安全可靠的施工方案:It is arranged that the
D1、完成全部套筒20在立杆3上的套设,且套筒20层叠于立杆3的底部;D1. Complete the sleeve setting of all the
完成围板1在支撑架侧面的安装,且使得围板1与挡土板21的内侧面相贴;Complete the installation of the
完成吊环18在立杆3顶部的安装;Complete the installation of the lifting
D2、调整最下方套筒20两侧横杆2的长度,使得横杆2的两端均形成与对应侧围板1的支撑关系,利用以上支撑关系,可约束立杆3在空间的位置以及维持立杆3的力气状态;D2. Adjust the lengths of the cross bars 2 on both sides of the
D3、利用挂设在吊环18上的吊装工具,依次起吊最下方套筒20上侧套筒20上的横杆2,使得对应套筒20随其上的横杆2移动至所需的立杆3轴线位置;D3. Using the hoisting tool hung on the hoisting
具体起吊为:最上层的套筒20为最先起吊并在轴线位置确定后,通过调整横杆2长度以约束对应侧围板1后,通过对应的锁定装置完成固定于立杆3上的一者,而后,在套筒20的排列顺序上,依次由上至下完成各套筒20在立杆3上的位置调节、调整横杆2长度以约束围板1和在立杆3上的位置固定。The specific lifting is as follows: after the
所述吊环18可拆卸,使得立杆3可以光杆的形式先完成在安装位置的立起,而后如由立杆3的上端,完成各套筒20的套设,而后再安装好吊环18,为各套筒20提供位于立杆3顶端的吊点。The lifting
具体结构限定以及操作方式中,利用最下方套筒20上的横杆2,即可实现利用围板1,为立杆3的支撑状态形成防倒约束,这样,在进行后续套筒20吊起时,可使得立杆3处于相对稳定的状态,直至完成所有套筒20位置调整,如利用手拉葫芦、电动葫芦的方式完成包括套筒20和横杆2组合体吊起,实现立杆3的防倒约束和完成后续吊装均具有操作方便,经济性好的特点。针对套筒20的位置固定,可在立杆3的轴线方向上设置数量对于套筒20数量的插销孔19,根据具体套筒20的安装需要,选择对应位置的插销孔19,使得套筒20与立杆3形成销连接关系即可达到固定目的。In the specific structure limitation and operation mode, the use of the
以上内容是结合具体的优选实施方式对本发明作的进一步详细说明,不能认定本发明的具体实施方式只局限于这些说明。对于本发明所属技术领域的普通技术人员来说,在不脱离本发明的技术方案下得出的其他实施方式,均应包含在本发明的保护范围内。The above content is a further detailed description of the present invention in conjunction with specific preferred embodiments, and it cannot be considered that the specific embodiments of the present invention are limited to these descriptions. For those of ordinary skill in the technical field to which the present invention pertains, other embodiments obtained without departing from the technical solutions of the present invention shall be included within the protection scope of the present invention.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010764638.8A CN111749244B (en) | 2020-07-31 | 2020-07-31 | Construction device and construction method for safe construction of underground structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010764638.8A CN111749244B (en) | 2020-07-31 | 2020-07-31 | Construction device and construction method for safe construction of underground structure |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN111749244A true CN111749244A (en) | 2020-10-09 |
| CN111749244B CN111749244B (en) | 2024-12-17 |
Family
ID=72712717
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202010764638.8A Active CN111749244B (en) | 2020-07-31 | 2020-07-31 | Construction device and construction method for safe construction of underground structure |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN111749244B (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113216208A (en) * | 2021-05-18 | 2021-08-06 | 新乡学院 | Foundation pit supporting structure and foundation pit supporting assembly |
| CN113235630A (en) * | 2021-05-11 | 2021-08-10 | 中交第三公路工程局有限公司 | Pneumatic dewatering method and dewatering device thereof |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102912797A (en) * | 2012-10-19 | 2013-02-06 | 中国建筑第六工程局有限公司 | Foundation pit supporting method with precipitation function |
| CN207582475U (en) * | 2017-12-12 | 2018-07-06 | 黑龙江科技大学 | A kind of deep pit support protection unit |
| CN209066465U (en) * | 2018-10-18 | 2019-07-05 | 苏州市三联建设工程勘测有限公司 | A kind of deep basal pit structure with ejectment side wall water burst |
| CN110093931A (en) * | 2019-04-28 | 2019-08-06 | 四川航天建筑工程有限公司 | A kind of civil construction drainage of foundation pit structure and its construction method |
| CN210288407U (en) * | 2019-03-25 | 2020-04-10 | 西京学院 | Civil engineering earthwork excavation is with foundation ditch protection machanism |
| CN212742546U (en) * | 2020-07-31 | 2021-03-19 | 中信国安建工集团有限公司 | Support for safety construction of underground structure |
-
2020
- 2020-07-31 CN CN202010764638.8A patent/CN111749244B/en active Active
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102912797A (en) * | 2012-10-19 | 2013-02-06 | 中国建筑第六工程局有限公司 | Foundation pit supporting method with precipitation function |
| CN207582475U (en) * | 2017-12-12 | 2018-07-06 | 黑龙江科技大学 | A kind of deep pit support protection unit |
| CN209066465U (en) * | 2018-10-18 | 2019-07-05 | 苏州市三联建设工程勘测有限公司 | A kind of deep basal pit structure with ejectment side wall water burst |
| CN210288407U (en) * | 2019-03-25 | 2020-04-10 | 西京学院 | Civil engineering earthwork excavation is with foundation ditch protection machanism |
| CN110093931A (en) * | 2019-04-28 | 2019-08-06 | 四川航天建筑工程有限公司 | A kind of civil construction drainage of foundation pit structure and its construction method |
| CN212742546U (en) * | 2020-07-31 | 2021-03-19 | 中信国安建工集团有限公司 | Support for safety construction of underground structure |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113235630A (en) * | 2021-05-11 | 2021-08-10 | 中交第三公路工程局有限公司 | Pneumatic dewatering method and dewatering device thereof |
| CN113216208A (en) * | 2021-05-18 | 2021-08-06 | 新乡学院 | Foundation pit supporting structure and foundation pit supporting assembly |
Also Published As
| Publication number | Publication date |
|---|---|
| CN111749244B (en) | 2024-12-17 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105569095B (en) | One kind cuts row's decompression anti-floating system | |
| CN205975626U (en) | Strut integrated configuration with stagnant water unification in soft soil layer foundation ditch | |
| CN111576431A (en) | Excavation method for foundation pit of four-layer subway station | |
| CN105804089B (en) | Locally increase deep support system and its construction method after a kind of former deep foundation pit construction | |
| CN108755706B (en) | Movable foundation pit inner support system and foundation pit construction method | |
| CN103469817A (en) | Existing subway station main structure broadening construction method | |
| CN112376589A (en) | Landslide belt pile plate type comprehensive protection construction system and construction method | |
| CN111749244A (en) | Construction device and construction method for safe construction of underground structure | |
| CN106193047A (en) | Big width base pit stand construction | |
| CN105484277A (en) | Component for tubular well precipitation construction in elevator foundation pit or sump and construction method | |
| CN205205844U (en) | Member is used in construction of tubular well precipitation in elevator foundation ditch or sump pit | |
| CN212742546U (en) | Support for safety construction of underground structure | |
| CN105421498B (en) | A kind of foundation ditch water-impervious and subsidence control method based on three-dimensional curtain gang of wells system | |
| CN119877578B (en) | Multilayer pressure-bearing water suspension type waterproof curtain decompression precipitation structure of high-permeability water-rich stratum and construction method thereof | |
| CN104264679B (en) | Construction method of large-caliber underwater cast-in-place pile for power transmission tower foundation | |
| CN214832726U (en) | Supporting structure for pipe-jacking working well in deep soft soil area | |
| CN207048004U (en) | A kind of coarse rack open caisson for sewage disposal system | |
| CN111827305A (en) | Mechanism and method for anti-destruction reinforcement of geotechnical engineering | |
| CN201686965U (en) | Cast-in-situ reinforced concrete gate of diversion tunnel | |
| CN111827297A (en) | System and method for dewatering and excavation of sand egg stratum foundation pit | |
| CN212270964U (en) | Side slope, foundation ditch anti-damage reinforcing apparatus | |
| CN212742548U (en) | Equipment for foundation pit construction of water-rich sand-gravel stratum | |
| CN205591261U (en) | Anti system of floating of row's of cutting decompression | |
| CN213836693U (en) | Comprehensive protection construction system of landslide with piles and plates | |
| CN205296177U (en) | Dado bearing structure suitable for hole friction pile stake hole is dug in manual work |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |
