CN111720138A - Tunnel and underground engineering formwork lining supporting structure and supporting method thereof - Google Patents

Tunnel and underground engineering formwork lining supporting structure and supporting method thereof Download PDF

Info

Publication number
CN111720138A
CN111720138A CN202010504433.6A CN202010504433A CN111720138A CN 111720138 A CN111720138 A CN 111720138A CN 202010504433 A CN202010504433 A CN 202010504433A CN 111720138 A CN111720138 A CN 111720138A
Authority
CN
China
Prior art keywords
top plate
jacking
movable
pipe
upper top
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010504433.6A
Other languages
Chinese (zh)
Inventor
刘建友
陈学峰
蒋小锐
谭富圣
王杨
王婷
彭斌
魏盼
宋月光
岳岭
陈志广
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Engineering Consulting Group Co Ltd
Original Assignee
China Railway Engineering Consulting Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Engineering Consulting Group Co Ltd filed Critical China Railway Engineering Consulting Group Co Ltd
Priority to CN202010504433.6A priority Critical patent/CN111720138A/en
Publication of CN111720138A publication Critical patent/CN111720138A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries

Abstract

The invention is suitable for the technical field of engineering, and provides a tunnel and underground engineering mould-built lining supporting structure which comprises a plurality of jacking pipes, wherein each jacking pipe is butted with each other, each jacking pipe consists of an upper top plate, a lower top plate, a movable plate and a protective brim, the movable plate is positioned between the upper top plate and the lower top plate, the movable plate is detachably connected with the upper top plate and the lower top plate, the protective brim is fixedly connected with the upper top plate, and the protective brim is matched with the movable plate; constitute the push pipe support in using and in the entrance to a cave department of excavation to form interim supporting structure main part, take out the fly leaf thereupon, and after carrying out concrete placement thereupon, alright carry out the earthwork excavation in the main part of structure, have the characteristics of security height under the supporting role of a plurality of push pipes, and be used for rich water and sandy soil layer, combine the all grouting of pipe, can form better waterproof closed loop, avoid precipitation on a large scale, and can effectively ensure construction safety.

Description

Tunnel and underground engineering formwork lining supporting structure and supporting method thereof
Technical Field
The invention belongs to the technical field of engineering, and particularly relates to a molded lining supporting structure for tunnels and underground engineering and a supporting method thereof.
Background
With the rapid development of urbanization construction and underground engineering in China, large underground structures in special environments such as busy sections of cities and complex geological conditions are increasing day by day. The deformation control requirements of excavation of underground spaces of partial sections on existing building structures and ground surface traffic infrastructures at the periphery of the underground spaces are high, the traditional shallow-buried underground excavation construction method is difficult to meet the actual engineering requirements, and the research and the adoption of a large-span shallow-buried urban underground engineering construction method which is more scientific, safe, efficient and controllable in deformation are urgently needed.
Since the last 80 th century, the rapid development of the economy of China has expanded the scale of cities, the level of urbanization has been continuously improved, and particularly, the traveling mode of residents in large and medium-sized cities has been greatly changed, and the environment-friendly and efficient passenger transport system of urban rail transit is fully developed in large and medium-sized cities and urban groups, such as Yangtze river delta, Zhujiang delta, Jingjin pond and other areas. At present, more than 70 subway lines are constructed nationwide, and the urban rail transit investment reaches 1.23 trillion yuan. In the next decade, the development direction of urban traffic in China is as follows: on the premise of sustainable development, the economic development is taken as a main line, and a multi-level and three-dimensional modern urban traffic system is initially established by combining with homeland planning; the demand management is implemented, and the growing traffic demand is scientifically and reasonably controlled and guided; the urban rail transit construction is enhanced, the transition from the conventional public transit on the ground to the urban traffic system taking the urban rail transit as a main part is realized in a large city, the service quality of the urban traffic is improved while the scale of the traffic infrastructure is improved, and the conversion to the international standard is further realized.
Meanwhile, the central area of the city in China is developing towards the direction of comprehensively utilizing underground space, and the initial civil air defense engineering is developing to underground commercial streets, transportation hubs, underground entertainment facilities and the like. The underground street in the center of the city is the extension of the ground space and is also the important supplement of the city function, and the synchronous and coordinated development with the ground can be finally realized. It is easy to find that the underground space of the city is continuously developed and matured, the development and utilization degree of the underground space is increased year by year, and complex projects with multiple functions are gradually formed in large and medium-sized cities.
The current subway design specification puts the design principle of 'safe and reliable, energy-saving and environment-friendly and advanced technology' into the general outline of subway design in China. The wide application of the formwork lining support method can fundamentally improve the safety and reliability of shallow-buried large-span urban rail transit underground excavation construction, and plays an important technical support role in the development of urban rail transit.
When the formwork lining support method is used for construction, the construction operation space is relatively narrow when concrete is poured in a formwork, the concrete is not easy to vibrate, and although self-compacting concrete is usually adopted in the design, the pouring still has quality hidden trouble, and measures such as targeted management, monitoring, inspection, maintenance and the like need to be adopted in the future construction so as to ensure the pouring quality of the large-volume self-compacting concrete.
Disclosure of Invention
The invention provides a formwork lining supporting structure for tunnels and underground engineering and a supporting method thereof, aiming at solving the problems that when the formwork lining supporting method is used for construction, the construction operation space is relatively narrow when concrete is poured in a formwork, the concrete is not easy to vibrate, and the pouring still has hidden quality troubles although self-compacting concrete is usually adopted in the design.
The invention is realized in such a way that a tunnel and underground engineering mold building lining supporting structure comprises a plurality of jacking pipes, wherein each jacking pipe is butted with each other, each jacking pipe is composed of an upper top plate, a lower top plate, a movable plate and a protective cap peak, the movable plate is positioned between the upper top plate and the lower top plate and is detachably connected with the upper top plate and the lower top plate, the protective cap peak is fixedly connected with the upper top plate, and the protective cap peak is matched with the movable plate.
Preferably, the top pipe further comprises a movable lock catch, and the movable plate is detachably connected to the upper top plate and the lower top plate through the movable lock catch.
Preferably, each of the top tubes is provided with two movable plates, the protection brim corresponds to a gap formed between two adjacent movable plates, and the protection brim is arc-shaped.
Preferably, the top pipe further comprises a support upright, and the support upright is supported between the upper top plate and the lower top plate.
Preferably, the support columns are arranged in a plurality and are sequentially arranged along the length direction of the movable plate, and each support column is spaced from three meters to five meters.
Preferably, the upper top plate and the lower top plate are both provided with a plurality of parts, and the upper top plate and the lower top plate are spliced with each other to form an arc shape.
Preferably, a cavity is formed inside each top pipe, and each cavity is separated by a movable plate.
A method for supporting a modular lining of a tunnel and underground engineering comprises the following steps:
step S10: setting the thickness of a structural layer according to structural load and stress requirements;
step S20: dividing the structural layer into a plurality of jacking pipes;
step S30: constructing a jacking pipe and completely jacking all the jacking pipes;
step S40: the movable side plate is pulled away, and all the jacking pipes are annularly communicated together;
step S50: arranging circumferential and longitudinal steel bars and pouring concrete;
step S60: and excavating earthwork in the tunnel.
Preferably, in step S10, the thickness of the structural layer needs to be greater than one and a half meters.
Compared with the prior art, the invention has the beneficial effects that: according to the tunnel and underground engineering mold-built lining supporting structure and the supporting method thereof, the upper top plate, the lower top plate and the movable plate are arranged, the jacking pipes are formed during use and supported at the excavated hole, the temporary supporting structure main body is formed, the movable plate is pulled out along with the jacking pipes, concrete pouring is carried out along with the jacking pipes, earthwork excavation in the structure main body can be carried out, the structure has the characteristic of high safety under the supporting action of a plurality of jacking pipes, and the structure is used for water-rich and sandy soil layers, can form a good waterproof closed ring by combining with grouting around the pipes, avoids large-range precipitation and can effectively guarantee construction safety.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the structure of the jacking pipe in the present invention;
FIG. 3 is a schematic view of a movable plate structure in the present invention;
FIG. 4 is a schematic flow diagram of a method of the present invention;
in the figure: 1. jacking pipes; 11. an upper top plate; 12. a lower top plate; 13. a movable plate; 14. a movable lock catch; 15. protecting the brim; 16. and supporting the upright post.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
Referring to fig. 1-3, the present invention provides a technical solution: the utility model provides a tunnel and underground works mould build lining supporting construction, includes a plurality of push pipes 1, docks each other between every push pipe 1, and push pipe 1 comprises last roof 11, roof 12 down, fly leaf 13 and protection brim of a hat 15, and fly leaf 13 is located between roof 11 and the roof 12 down, and fly leaf 13 can dismantle to be connected in last roof 11 and roof 12 down, protection brim of a hat 15 fixed connection in last roof 11, and protection brim of a hat 15 and fly leaf 13 looks adaptation.
In the embodiment, before excavation is needed, a lining template needs to be built along the contour line of the excavation, firstly, the thickness of a structural layer needs to be set according to the structural load and stress requirements and the space requirements of personnel operation in the jacking pipe 1, the thickness of the structural layer generally needs to be more than one point and two meters, then, the structural layer is divided into a plurality of jacking pipes 1, each jacking pipe 1 is relatively independent, when each jacking pipe 1 is installed, firstly, two movable plates 13 need to be installed between an upper top plate 11 and a lower top plate 12, the movable plates 13 are fixed between the upper top plate 11 and the lower top plate 12 through movable latches 14, in addition, one supporting upright post 16 is arranged at intervals of 3-5 m on each movable plate 13, the support between the upper top plate 11 and the lower top plate 12 is realized through the supporting upright posts 16, secondly, one end of each upper top plate 11 is provided with an arc-shaped protective cap 15, after the plurality of jacking pipes 1 are spliced, the protection brim 15 corresponds to the joint between the two jacking pipes 1, a certain gap is formed between two adjacent movable plates 13 inside the jacking pipes 1 due to the splicing of the jacking pipes 1, the gap is covered by the protection brim 15, the stability of surrounding rocks at the joint of the two jacking pipes 1 can be further protected, the sand soil is prevented from being extruded to the gap and being deformed and leaked, then, after the jacking pipes 1 are completely butted and constructed, the movable lock 14 can be opened, the movable lock 14 is pulled out from between the upper top plate 11 and the lower top plate 12 through the opening of the movable lock 14, the cavity inside each jacking pipe 1 is communicated through the pulling out of the movable lock 13, circumferential and longitudinal steel bars are arranged in the jacking pipes 1, concrete is poured, and after the steel concrete in the jacking pipes 1 reaches the designed strength, the earth in the tunnel is excavated.
Further, the top tube 1 further comprises a movable lock 14, and the movable plate 13 is detachably connected to the upper top plate 11 and the lower top plate 12 through the movable lock 14.
In the present embodiment, the movable lock 14 is fixed to the movable plate 13, and hooks (not shown) are provided on both the upper top plate 11 and the lower top plate 12, and when the movable plate 13 is fixed, it is necessary to hang the lock of the movable lock 14 on the hooks of the upper top plate 11 and the lower top plate 12, and the movable plate 13 is fixed to the upper top plate 11 and the lower top plate 12 by using both of them.
Furthermore, each top pipe 1 is provided with two movable plates 13, the protection brim 15 corresponds to a gap formed between two adjacent movable plates 13, and the protection brim 15 is arc-shaped.
In the embodiment, in the using process, after the plurality of jacking pipes 1 are spliced, the protective cap peak 15 corresponds to the joint between the two jacking pipes 1, a certain gap is formed between two adjacent movable plates 13 inside the jacking pipes 1 due to the splicing of the jacking pipes 1, and the gap is covered by the protective cap peak 15, so that the stability of surrounding rocks at the joint of the two jacking pipes 1 can be protected, and the sand soil is prevented from extruding, deforming and leaking to the gap.
Further, the jacking pipe 1 further comprises a support upright 16, and the support upright 16 is supported between the upper top plate 11 and the lower top plate 12; the plurality of support columns 16 are arranged in sequence along the length direction of the movable plate 13, and each support column 16 is spaced three meters to five meters apart.
In the present embodiment, in the using process, the plurality of support columns 16 are provided to stably support the space between the upper top plate 11 and the lower top plate 12, so that the phenomenon of subsequent collapse can be avoided.
Further, the upper top plate 11 and the lower top plate 12 are provided in plurality, and the plurality of upper top plates 11 and the plurality of lower top plates 12 are mutually spliced to form an arc shape.
In the present embodiment, during the use process, the plurality of upper and lower top plates 11 and 12 are provided, so that the top pipe 1 can be smoothly formed, has the same contour as the excavated part, and can smoothly build the lining form with respect to the contour line of the excavated part.
Further, a cavity is formed inside each top pipe 1, and each cavity is separated by a movable plate 13.
In the present embodiment, during use, the movable plate 13 is extracted from between the upper top plate 11 and the lower top plate 12, the cavity inside each top pipe 1 is communicated by the extraction of the movable plate 13, and then the circumferential and longitudinal steel bars are arranged in the cavity, and concrete is poured.
Referring to fig. 4, a lining support method for tunnel and underground engineering molding includes the following steps:
step S10: setting the thickness of a structural layer according to structural load and stress requirements;
step S20: dividing the structural layer into a plurality of jacking pipes;
step S30: constructing a jacking pipe and completely jacking all the jacking pipes;
step S40: the movable side plate is pulled away, and all the jacking pipes are annularly communicated together;
step S50: arranging circumferential and longitudinal steel bars and pouring concrete;
step S60: and excavating earthwork in the tunnel.
In the embodiment, before excavation is needed, a lining template needs to be built along the contour line of the excavation, firstly, the thickness of a structural layer needs to be set according to the structural load and stress requirements and the space requirements of personnel operation in the jacking pipe 1, the thickness of the structural layer generally needs to be more than one point and two meters, then, the structural layer is divided into a plurality of jacking pipes 1, each jacking pipe 1 is relatively independent, when each jacking pipe 1 is installed, firstly, two movable plates 13 need to be installed between an upper top plate 11 and a lower top plate 12, the movable plates 13 are fixed between the upper top plate 11 and the lower top plate 12 through movable latches 14, in addition, one supporting upright post 16 is arranged at intervals of 3-5 m on each movable plate 13, the support between the upper top plate 11 and the lower top plate 12 is realized through the supporting upright posts 16, secondly, one end of each upper top plate 11 is provided with an arc-shaped protective cap 15, after the plurality of jacking pipes 1 are spliced, the protection brim 15 corresponds to the joint between the two jacking pipes 1, a certain gap is formed between two adjacent movable plates 13 inside the jacking pipes 1 due to the splicing of the jacking pipes 1, the gap is covered by the protection brim 15, the stability of surrounding rocks at the joint of the two jacking pipes 1 can be further protected, the sand soil is prevented from being extruded to the gap and being deformed and leaked, then, after the jacking pipes 1 are completely butted and constructed, the movable lock 14 can be opened, the movable lock 14 is pulled out from between the upper top plate 11 and the lower top plate 12 through the opening of the movable lock 14, the cavity inside each jacking pipe 1 is communicated through the pulling out of the movable lock 13, circumferential and longitudinal steel bars are arranged in the jacking pipes 1, concrete is poured, and after the steel concrete in the jacking pipes 1 reaches the designed strength, the earth in the tunnel is excavated.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents and improvements made within the spirit and principle of the present invention are intended to be included within the scope of the present invention.

Claims (9)

1. The utility model provides a tunnel and underground works mould lining support structure which characterized in that: the novel pipe jacking device comprises a plurality of pipe jacking pipes (1), each pipe jacking pipe (1) is in butt joint with each other, the pipe jacking pipes (1) are composed of an upper top plate (11), a lower top plate (12), a movable plate (13) and a protection brim (15), the movable plate (13) is located between the upper top plate (11) and the lower top plate (12), the movable plate (13) is detachably connected with the upper top plate (11) and the lower top plate (12), the protection brim (15) is fixedly connected with the upper top plate (11), and the protection brim (15) is matched with the movable plate (13).
2. The modular lining support structure for tunnels and underground works according to claim 1, wherein: the jacking pipe (1) further comprises a movable lock catch (14), and the movable plate (13) is detachably connected to the upper top plate (11) and the lower top plate (12) through the movable lock catch (14).
3. The modular lining support structure for tunnels and underground works according to claim 1, wherein: each jacking pipe (1) is provided with two movable plates (13), the protection brim (15) corresponds to a gap formed between two adjacent movable plates (13), and the protection brim (15) is arc-shaped.
4. The modular lining support structure for tunnels and underground works according to claim 1, wherein: the jacking pipe (1) further comprises a supporting upright post (16), and the supporting upright post (16) is supported between the upper top plate (11) and the lower top plate (12).
5. The modular lining support structure for tunnels and underground works according to claim 4, wherein: the supporting columns (16) are arranged in a plurality and are sequentially arranged along the length direction of the movable plate (13), and each supporting column (16) is spaced from three meters to five meters.
6. The modular lining support structure for tunnels and underground works according to claim 1, wherein: go up roof (11) and roof (12) down and all be provided with a plurality ofly, and a plurality of go up roof (11) and roof (12) splice each other and be circular-arc.
7. The modular lining support structure for tunnels and underground works according to claim 1, wherein: cavities are formed in the top pipes (1), and the cavities are separated by movable plates (13).
8. A tunnel and underground engineering mould building lining supporting method is characterized in that: the method comprises the following steps:
step S10: setting the thickness of a structural layer according to structural load and stress requirements;
step S20: dividing the structural layer into a plurality of jacking pipes;
step S30: constructing a jacking pipe and completely jacking all the jacking pipes;
step S40: the movable side plate is pulled away, and all the jacking pipes are annularly communicated together;
step S50: arranging circumferential and longitudinal steel bars and pouring concrete;
step S60: and excavating earthwork in the tunnel.
9. The modular lining support method for tunnels and underground works according to claim 8, wherein: in step S10, the thickness of the structural layer needs to be greater than one point and two meters.
CN202010504433.6A 2020-06-05 2020-06-05 Tunnel and underground engineering formwork lining supporting structure and supporting method thereof Pending CN111720138A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010504433.6A CN111720138A (en) 2020-06-05 2020-06-05 Tunnel and underground engineering formwork lining supporting structure and supporting method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010504433.6A CN111720138A (en) 2020-06-05 2020-06-05 Tunnel and underground engineering formwork lining supporting structure and supporting method thereof

Publications (1)

Publication Number Publication Date
CN111720138A true CN111720138A (en) 2020-09-29

Family

ID=72566000

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010504433.6A Pending CN111720138A (en) 2020-06-05 2020-06-05 Tunnel and underground engineering formwork lining supporting structure and supporting method thereof

Country Status (1)

Country Link
CN (1) CN111720138A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0681590A (en) * 1992-09-04 1994-03-22 Sumitomo Metal Ind Ltd Tunnel lining segment
JPH10159491A (en) * 1996-11-27 1998-06-16 Kajima Corp Hinge structure of tunnel timbering material and expansion structure
CN1594833A (en) * 2004-06-25 2005-03-16 清华大学 Steel plate-concrete composite lining
CN103321658A (en) * 2013-06-26 2013-09-25 中铁工程设计咨询集团有限公司 Molded lining support structure and construction method for soft soil ground layer
CN204126653U (en) * 2014-08-27 2015-01-28 中国电建集团华东勘测设计研究院有限公司 A kind of integrated ground shield lining circular ring structure
CN105484765A (en) * 2016-01-11 2016-04-13 北京市轨道交通设计研究院有限公司 Fabricated secondary lining structure of bored tunnel and construction method of fabricated secondary lining structure
CN207420587U (en) * 2017-11-23 2018-05-29 中国铁路总公司 One kind is suitable for TBM tunnel-liner rings
CN109404008A (en) * 2018-11-28 2019-03-01 中国水利水电科学研究院 Intelligent prestressed concrete liner tunnel
CN209369834U (en) * 2019-01-08 2019-09-10 四川公路桥梁建设集团有限公司 A kind of prefabricated assembled secondary liner structure in tunnel

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0681590A (en) * 1992-09-04 1994-03-22 Sumitomo Metal Ind Ltd Tunnel lining segment
JPH10159491A (en) * 1996-11-27 1998-06-16 Kajima Corp Hinge structure of tunnel timbering material and expansion structure
CN1594833A (en) * 2004-06-25 2005-03-16 清华大学 Steel plate-concrete composite lining
CN103321658A (en) * 2013-06-26 2013-09-25 中铁工程设计咨询集团有限公司 Molded lining support structure and construction method for soft soil ground layer
CN204126653U (en) * 2014-08-27 2015-01-28 中国电建集团华东勘测设计研究院有限公司 A kind of integrated ground shield lining circular ring structure
CN105484765A (en) * 2016-01-11 2016-04-13 北京市轨道交通设计研究院有限公司 Fabricated secondary lining structure of bored tunnel and construction method of fabricated secondary lining structure
CN207420587U (en) * 2017-11-23 2018-05-29 中国铁路总公司 One kind is suitable for TBM tunnel-liner rings
CN109404008A (en) * 2018-11-28 2019-03-01 中国水利水电科学研究院 Intelligent prestressed concrete liner tunnel
CN209369834U (en) * 2019-01-08 2019-09-10 四川公路桥梁建设集团有限公司 A kind of prefabricated assembled secondary liner structure in tunnel

Similar Documents

Publication Publication Date Title
CN108678775B (en) Transverse oval deformation resistant shield tunnel reinforcing structure of embedded steel plate and construction method
CN111188629B (en) Construction method for sudden change of tunnel bifurcation section and expanding excavation
CN102979531B (en) Reinforce construction method and the structure of large-scale rock slope deep weak structural plane
CN105256812B (en) Foundation ditch prefabricated assembled concrete supporting construction and its construction method
CN105909268B (en) Prestressing combination formula well tunnel modular structure construction method and modular structure
CN111365017B (en) Construction method of underground intercommunication tunnel
CN106351258A (en) All-prefabricated split steel concrete combined utility tunnel
CN105781595A (en) Method for mechanical branch underground excavation construction of rectangular and quasi-rectangular cross-section underground engineering
CN112160755A (en) Subway line construction method for expanding excavation station after shield tunnel construction in advance
CN206752667U (en) A kind of basement barrier wall structure
CN111270616A (en) Off-line construction and capping beam jacking system and construction method for lower structure of temporary bridge of railway
CN108979663B (en) Subway station main body structure construction method adopting temporary middle column support
CN205990921U (en) Double-deck lining cutting special defects circular cross section Tunneling by mining method structure
CN206428588U (en) A kind of road bridge construction prestressed anchor
CN110117959B (en) Construction method for foundation pit support near river
CN111720138A (en) Tunnel and underground engineering formwork lining supporting structure and supporting method thereof
CN219261111U (en) Structure system of temporary track panel well of subway station
CN112575789A (en) Diagonal space truss foundation pit inner support system
CN208734343U (en) A kind of station tunnel excavation structure with interim middle spacer post support
CN210315654U (en) Urban tunnel, rail transit interval tunnel and utility tunnel co-construction structure
Huang et al. China Highway Canyon Bridges
CN207619987U (en) A kind of prefabricated foundation pit enclosure structure of environment-friendly type underground garage
CN107419743A (en) A kind of new city pipe gallery mobile formwork
CN110939139A (en) Pile slab wall structure based on rigid contact of post-pile special-shaped retaining wall and construction method thereof
CN212003200U (en) A expand and dig structure for shield tunnel foundation is last

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200929