CN111622272A - Post-construction process of anti-floating anchor rod - Google Patents

Post-construction process of anti-floating anchor rod Download PDF

Info

Publication number
CN111622272A
CN111622272A CN202010494527.XA CN202010494527A CN111622272A CN 111622272 A CN111622272 A CN 111622272A CN 202010494527 A CN202010494527 A CN 202010494527A CN 111622272 A CN111622272 A CN 111622272A
Authority
CN
China
Prior art keywords
anchor rod
floating anchor
floating
construction
grouting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202010494527.XA
Other languages
Chinese (zh)
Inventor
江涛
李万旺
王鑫茹
郝吉光
宋贺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Jiaoling Construction Engineering Group Co Ltd
Original Assignee
Guangdong Jiaoling Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Jiaoling Construction Engineering Group Co Ltd filed Critical Guangdong Jiaoling Construction Engineering Group Co Ltd
Priority to CN202010494527.XA priority Critical patent/CN111622272A/en
Publication of CN111622272A publication Critical patent/CN111622272A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/10Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure
    • E02D31/12Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure against upward hydraulic pressure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/0023Slurry

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses an anti-floating anchor post-construction process, which comprises the following steps: pouring a cushion layer in the foundation pit, drilling an anti-floating anchor rod hole, placing an anti-floating anchor rod in the anti-floating anchor rod hole, pouring the anti-floating anchor rod hole, performing anti-floating anchor rod hole waterproof engineering construction, bending the anti-floating anchor rod, binding anti-floating plate reinforcing steel bars, and enabling the anti-floating anchor rod reinforcing steel bars to be located in a space formed by binding the anti-floating plate reinforcing steel bars. The invention has the advantages that: the method is suitable for all soil bodies and rock masses; the method is suitable for residential basement garage foundations, commercial complex underground garages, underground shopping malls, basement equipment house foundations, subway tunnels, subway stations, underwater structures and underwater tunnels; the bottom is picked up before the anti-floating anchor rod construction, so that the slurry cleaning is reduced, the soaking and the damage of water and slurry brought by the anti-floating anchor rod construction to a foundation bearing layer are reduced, the construction period is shortened, and the concrete replacement amount is reduced by 50%; the concrete pouring and forming effects of the cushion layer are facilitated; is favorable for the forming of the anti-floating anchor rod reinforcing steel bar.

Description

Post-construction process of anti-floating anchor rod
Technical Field
The invention relates to the technical field of construction of foundations and foundations of building construction engineering, in particular to a construction technology of an anti-floating anchor rod.
Background
In recent years, urban construction is more crowded, and in order to better solve the problem of utilization of longitudinal space of a building and save floor space of the building, underground space of the building is more and more widely applied. Large underground structures such as underground large basements, large underground structures, large equipment foundations and the like with shallow underground water levels occur in underground engineering, and underground burial is deep. Because the underground structures have large building area and deeper foundation burial, the number of building layers is increased day by day. Under the condition of the historical highest underground water level, the self weight of the structure is not enough to resist the buoyancy of underground water, and the anti-floating problem of underground structures is increasingly prominent.
The anti-floating anchor rod is one of the anti-floating measures for underground structure in building engineering. In the anti-floating design, the underground structures are mostly in the form of anti-floating anchor rods or anti-floating piles (uplift piles). The upward displacement of the building on the pressure pile is resisted, and the pressure pile is opposite to the stress direction related to the height and the change of the underground water level. The rock mass anti-floating anchor rod has high uplift resistance, simple and convenient construction, high speed, economy, environmental protection and no space occupation, and has extremely high economic benefit and social benefit. The construction of traditional anti-floating anchor rod is before the bed course is pour, and anti-floating anchor rod is under construction earlier, then pours the bed course, and the anti-floating plate reinforcing bar of ligature again pours anti-floating plate, nevertheless if under the circumstances that groundwater is abundant or has rock stratum fracture water, the construction anti-floating anchor rod very easily causes disturbance, soaking to the foundation soil layer, can form the secondary simultaneously and pick up the end.
Disclosure of Invention
The invention aims to provide an anti-floating anchor post-construction process to solve the problems of disturbance, soaking and secondary bottom picking of a foundation soil layer.
In order to achieve the purpose, the anti-floating anchor rods are adopted for construction, the foundation pit is excavated and then the foundation bed is constructed to seal the substrate, when the strength of the bed reaches the designed strength, the anti-floating anchor rods are constructed, and then the anti-floating plate reinforcing steel bars are bound.
The specific technical scheme is as follows:
a post-construction process of an anti-floating anchor rod,
the method comprises the following steps:
(1) manually matching with a mechanical foundation to pick up the foundation to the foundation pit cushion foundation elevation;
(2) pouring a cushion layer;
(3) positioning and paying off are carried out according to the construction position of the design point diagram of the anti-floating anchor rod, and the position of the anti-floating anchor rod is marked;
(4) after drilling and hole cleaning are finished, an anti-floating anchor rod and a grouting pipe which are made of steel bars are put into an anti-floating anchor rod hole, the part of the anti-floating anchor rod, which is positioned in the anti-floating anchor rod hole, is an anchoring section, and the part, which is exposed out of the anti-floating anchor rod hole, is an exposed section;
(5) grouting into the anti-floating anchor rod hole;
(6) after grouting, performing waterproof construction;
(7) and after the strength of the anti-floating anchor rod hole meets the requirement, bending the exposed section of the anti-floating anchor rod to enable the exposed section of the anti-floating anchor rod to be located in a space formed by binding the anti-floating plate steel bars.
Further, the specific process of the step (1) is as follows: specifically, positioning and paying off a foundation and measuring the elevation of the foundation; the mechanical breaking and the foundation excavation form a foundation pit, the foundation is picked up by manually matching with a mechanical foundation, the foundation pit is directly constructed to the foundation elevation of the foundation pit cushion layer, the foundation pit is provided with a water collecting pit, and open water in the foundation pit is drained and collected to remove the foundation pit.
Further, the specific process of the step (2) is as follows: installing a foundation template, pouring a concrete cushion, and well performing elevation measurement and surface press polishing in the cushion pouring process to prepare for subsequent waterproof engineering construction.
Further, the specific process of the step (3) is as follows:
a. making a mechanical inlet and outlet route of the anti-floating anchor rod;
b. the strength of the cushion layer meets the design requirement, the anti-floating anchor rod is positioned and paid off according to the construction position of the anti-floating anchor rod design point diagram, the anti-floating anchor rod is positioned and marked at the position, and the anti-floating anchor rod is uniformly arranged in a planar mode and is uniformly arranged under the basement bottom plate;
c. then, the anti-floating anchor rod drilling machine enters the field for construction: and the anti-floating anchor rod drilling machine walks on the cushion layer and performs drilling construction of the anti-floating anchor rod according to the positioning position of the anti-floating anchor rod.
Furthermore, the grouting in the step (5) is implemented by adding M30 cement slurry mixed with the pea stones, and performing reverse grouting by using hole bottom pressure, wherein the full-hole grouting is completed at one time, and the grouting pressure is 1.0 MPa.
Further, the descending depth of the anti-floating anchor rod in the step (4) and the design error are not more than 10cm, the anti-floating anchor rod completed in the same day is required to complete grouting in the operation of the step (5), and a grouting pipe is reserved in the hole.
Further, in the step (5), when the slurry overflows from the orifice and the color and the water-cement ratio of the overflowed slurry and the poured slurry are basically consistent, feeding is stopped, the filling degree of the grouting is checked for 24 hours, and if shrinkage or settlement exists, the slurry is supplemented.
Further, quantitative grouting and hole forming conditions in the drilling process are adopted in the grouting process in the step (5) for control;
and (4) if grouting is stopped for more than 30 minutes in the grouting process, repeating the step (4) at the position close to the anti-floating anchor rod, and performing drilling, hole cleaning, anti-floating anchor rod and grouting pipe releasing and grouting again.
Further, the step (6) specifically comprises the following operations:
a. washing the slurry and the cement slurry on the surface of the cushion layer;
b. and (3) waterproof engineering construction: the grouting end socket of the anti-floating anchor rod is processed to be flat or recessed by 10mm, the head-out position of the anti-floating anchor rod is filled with factice for sealing, a cement-based permeable crystalline coating waterproof layer is coated, and a cushion layer self-adhesive waterproof coiled material is constructed; constructing a waterproof protective layer;
c. and (4) carrying out a drawing test after the anti-floating anchor rod reaches the design strength, and carrying out drilling, hole cleaning, grouting, anti-floating anchor rod foundation waterproof engineering and waterproof protection engineering construction on the unqualified anti-floating anchor rod at the adjacent position again.
Further, the specific operation of the step (7) is: bending the anti-floating anchor rod reinforcing steel bars by adopting a hydraulic machine; and then carrying out foundation construction: and (3) binding the reinforcing steel bars of the anti-floating plate, installing the template, and anchoring the anti-floating anchor steel bars to the anti-floating plate reinforcing steel bars after the anti-floating plate is poured, wherein the exposed sections of the anti-floating anchor steel bars are positioned in the space formed by binding the anti-floating plate reinforcing steel bars.
The invention has the following advantages:
the method is suitable for all soil bodies and rock masses; the method is suitable for residential basement garage foundations, commercial complex underground garages, underground shopping malls, basement equipment house foundations, subway tunnels, subway stations, underwater structures and underwater tunnels; the bottom is picked up before the anti-floating anchor rod construction, so that the slurry cleaning is reduced, the soaking and the damage of water and slurry brought by the anti-floating anchor rod construction to a foundation bearing layer are reduced, the construction period is shortened, and the concrete replacement amount is reduced by 50%; the concrete pouring and forming effects of the cushion layer are facilitated; is favorable for the forming of the anti-floating anchor rod reinforcing steel bar.
Drawings
The accompanying drawings, which are included to provide a further understanding of the invention and are incorporated in and constitute a part of this application, illustrate embodiment(s) of the invention and together with the description serve to explain the principles of the invention:
FIG. 1 is a schematic diagram of a poured bedding construction;
FIG. 2 is a schematic structural diagram of the anti-floating anchor rod after cement slurry is poured;
FIG. 3 is a schematic structural diagram of the cement-based capillary crystalline coating after waterproof layer construction;
FIG. 4 is a schematic structural view of a cushion layer self-adhesive waterproof roll after construction;
FIG. 5 is a schematic structural view of the waterproof protective layer after construction;
FIG. 6 is an enlarged view of the structure of part A;
FIG. 7 is a field diagram of hole forming of an anti-floating anchor rod hole after the cushion layer is poured;
FIG. 8 is a field view after the construction of a waterproof project;
FIG. 9 is a field view after the construction of the waterproof protection project;
FIG. 10 is a field view after the construction of the waterproof protection project;
FIG. 11 is a construction site view of the anti-floating plate reinforcement bar binding;
fig. 12 is a field view after the anti-floating plate reinforcing steel bar binding construction.
The self-adhesive waterproof coating comprises a cushion layer 1, an anti-floating anchor rod 2, an anchoring section 21, an exposed section 22, cement paste 3, factice 4, a cement-based permeable crystalline coating waterproof layer 5, a cushion layer self-adhesive waterproof coiled material 6 and a waterproof protective layer 7.
Detailed Description
The present invention will be described in detail with reference to the drawings and specific embodiments, which are illustrative of the present invention and are not to be construed as limiting the present invention.
The construction process comprises the following steps: pouring a cushion layer 1 in a foundation pit, drilling an anti-floating anchor rod hole, placing an anti-floating anchor rod 2 in the anti-floating anchor rod hole, pouring the anti-floating anchor rod hole, constructing anti-floating anchor rod hole waterproof engineering, bending the anti-floating anchor rod 2, binding anti-floating plate reinforcing steel bars, and placing the anti-floating anchor rod 2 reinforcing steel bars in a space formed by binding the anti-floating plate reinforcing steel bars.
The detailed construction process is as follows:
first, basement excavation
(1) Measurement: specifically, positioning and paying off a foundation and measuring the elevation of the foundation;
(2) mechanically breaking and excavating a base to form a foundation pit, manually matching with a mechanical base to pick up the base, and directly constructing to the base elevation of the foundation pit cushion layer;
(3) the foundation pit is provided with a water collecting pit, and open water in the base is drained, collected and discharged out of the foundation pit;
second, cushion layer (replacement and filling) construction
(1) The foundation is a differentiated mud rock layer, the mud rock is blocky, disturbance exists in the excavation and bottom picking processes, and the excavation amount is larger than the basic budget amount; because the size and the thickness of the independent foundation are different, a foundation template needs to be installed, then a concrete cushion layer 1 is poured, elevation reading and measuring and surface press polishing are carried out in the pouring process of the cushion layer 1, and preparation is made for subsequent waterproof engineering construction;
thirdly, manufacturing and processing the anti-floating anchor rod 2
(1) A mechanical inlet and outlet route of the anti-floating anchor rod 2 is made;
(2) the strength of the cushion layer 1 meets the design requirement, the anti-floating anchor rod 2 is positioned and set off according to the construction position of the design point diagram of the anti-floating anchor rod 2, the position of the anti-floating anchor rod 2 is positioned and marked, the anti-floating anchor rod is uniformly arranged in a planar manner and is uniformly arranged under the bottom plate of the basement,
(3) then, the anti-floating anchor rod drilling machine enters the field for construction: the anti-floating anchor rod drilling machine walks on the cushion layer 1, carries out anti-floating anchor rod hole drilling construction according to the positioning position of the anti-floating anchor rod 2, reduces disturbance to the basement mudstone,
(4) after drilling and hole cleaning are finished, an anti-floating anchor rod 2 and a grouting pipe which are manufactured by using steel bars are put into an anti-floating anchor rod hole and are put to a designed depth, the error is not more than 10cm, the part of the anti-floating anchor rod 2 in the anti-floating anchor rod hole is an anchoring section 21, and the part exposed out of the anti-floating anchor rod hole is an exposed section 22;
(5) grouting, namely grouting the anti-floating anchor rod 2 completed in the same day, performing reverse grouting by adopting hole bottom pressure, and completing full-hole grouting at one time, wherein the grouting pressure is 1.0 MPa.
Mixing the M30 cement paste 3 with a stirrer, adding pea stone into the M30 cement paste 3 for mixing, filling the anti-floating anchor rod hole, increasing the friction force of the anti-floating anchor rod 2, pressing and injecting the mixed cement paste 3 into the anti-floating anchor rod hole through a grouting machine, and keeping the grouting pipe in the hole. And when the grout overflows from the orifice and the color and the water cement ratio of the overflowed grout 3 and the poured grout 3 are basically consistent, stopping feeding, checking the grouting fullness within 24 hours, and if shrinkage or settlement exists, supplementing the grout. In order to ensure the grouting length of the anchoring section and avoid over-grouting or under-grouting, quantitative grouting is adopted in the grouting process to be combined with the hole forming condition in the drilling process for control. Before the slurry is not completely cured, the anti-floating anchor 2 must not be pulled and moved. In the grouting process, stopping grouting for more than 30 minutes in the midway, and if stopping grouting for more than 30 minutes, drilling, cleaning holes, placing the anti-floating anchor rod and a grouting pipe and grouting again at the position close to the anti-floating anchor rod 2;
fourth, anti-floating anchor rod foundation waterproof engineering and waterproof protection engineering construction
(1) The surface mud and the cement slurry 3 of the cushion layer 1 are washed clean;
(2) and (3) waterproof engineering construction: grouting and sealing heads of the anti-floating anchor rods 2 to be flat or concave (10mm), pouring factice 4 into the head positions of the anti-floating anchor rods 2 for sealing, painting cement-based permeable crystalline coating waterproof layers 5, and constructing self-adhesive waterproof coiled materials 6 of cushion layers;
(3) constructing a waterproof protective layer 7;
(4) and (3) carrying out a drawing test after the anti-floating anchor rod 2 reaches the design strength, and carrying out drilling, hole cleaning, anti-floating anchor rod and grouting pipe placing, grouting, anti-floating anchor rod foundation waterproof engineering and waterproof protection engineering construction on the unqualified anti-floating anchor rod 2 at the adjacent position again.
Fifthly, bending treatment of 2 reinforcing steel bars of anti-floating anchor rod
(1) Bending the exposed section of the reinforcing steel bar of the anti-floating anchor rod 2 by adopting a hydraulic machine;
(2) foundation construction: and (3) binding the reinforcing steel bars of the anti-floating plate, installing the template, and anchoring the 2 reinforcing steel bars of the anti-floating anchor rod to the anti-floating plate after the anti-floating plate is poured, wherein the exposed part of the 2 reinforcing steel bars of the anti-floating anchor rod is positioned in a space formed by binding the reinforcing steel bars of the anti-floating plate.
The process of the invention has the advantages that:
1. the method is suitable for all soil bodies and rock masses; the method is suitable for residential basement garage foundations, commercial complex underground garages, underground shopping malls, basement equipment house foundations, subway tunnels, subway stations, underwater structures and underwater tunnels;
2. the foundation bottom picking mode is generally that manual work is mainly used as auxiliary machinery, the foundation bottom picking is carried out before the anti-floating anchor rod construction, the operation is simple, the speed is high, and the mechanical labor cost is reduced by 50%;
3. the bottom picking before the anti-floating anchor rod construction reduces the cleaning of slurry, reduces the soaking and damage of water and slurry to a foundation bearing layer caused by the anti-floating anchor rod construction, reduces the secondary bottom picking, saves the construction period and reduces the concrete replacement amount by 50 percent;
4. the post-construction of the anti-floating anchor rod is beneficial to the concrete pouring and forming effects of the cushion layer;
5. after the cushion layer construction is finished, the anti-floating anchor rod construction is carried out, so that organized cleaning of anti-floating anchor rod construction slurry is facilitated, and the difficulty in site cleaning is greatly reduced;
6. after the cushion layer construction is finished, the anti-floating anchor rod construction is carried out, the hole forming effect of the anti-floating anchor rod is good, and the back flow of slurry backflow is reduced;
7. after the cushion layer construction is finished, the anti-floating anchor rod construction is carried out, the anti-floating anchor rod reinforcing steel bar forming effect is good, and the damage of mechanical construction to the anti-floating anchor rod reinforcing steel bar is reduced;
8. pouring a cushion layer, wherein the grouting end socket of the anti-floating anchor rod is processed to be flat or concave (10mm), the waterproof treatment of the base coiled material in the range of the anti-floating anchor rod is relatively flat, and the waterproof is easy to be fixed by being turned over on the surface of the steel bar;
9. the anti-floating anchor rod steel bar anchor goes into the curved anchor shaping of foundation inner steel bar effectual, reduces the artifical 30% of reinforcing bar restoration.
The technical solutions provided by the embodiments of the present invention are described in detail above, and the principles and embodiments of the present invention are explained herein by using specific examples, and the descriptions of the embodiments are only used to help understanding the principles of the embodiments of the present invention; meanwhile, for a person skilled in the art, according to the embodiments of the present invention, there may be variations in the specific implementation manners and application ranges, and in summary, the content of the present description should not be construed as a limitation to the present invention.

Claims (10)

1. The post-construction process of the anti-floating anchor rod is characterized by comprising the following steps:
the method comprises the following steps:
(1) manually matching with a mechanical foundation to pick up the foundation to the foundation pit cushion foundation elevation;
(2) pouring a cushion layer;
(3) positioning and paying off are carried out according to the construction position of the design point diagram of the anti-floating anchor rod, and the position of the anti-floating anchor rod is marked;
(4) after drilling and hole cleaning are finished, an anti-floating anchor rod and a grouting pipe which are made of steel bars are put into an anti-floating anchor rod hole, the part of the anti-floating anchor rod, which is positioned in the anti-floating anchor rod hole, is an anchoring section, and the part, which is exposed out of the anti-floating anchor rod hole, is an exposed section;
(5) grouting into the anti-floating anchor rod hole;
(6) after grouting, performing waterproof construction;
(7) and after the strength of the anti-floating anchor rod hole meets the requirement, bending the exposed section of the anti-floating anchor rod to enable the exposed section of the anti-floating anchor rod to be located in a space formed by binding the anti-floating plate steel bars.
2. The post-construction process of the anti-floating anchor rod according to claim 1, characterized in that:
the specific process of the step (1) is as follows: specifically, positioning and paying off a foundation and measuring the elevation of the foundation; the mechanical breaking and the foundation excavation form a foundation pit, the foundation is picked up by manually matching with a mechanical foundation, the foundation pit is directly constructed to the foundation elevation of the foundation pit cushion layer, the foundation pit is provided with a water collecting pit, and open water in the foundation pit is drained and collected to remove the foundation pit.
3. The post-construction process of the anti-floating anchor rod according to claim 1, characterized in that:
the specific process of the step (2) is as follows: installing a foundation template, pouring a concrete cushion, and well performing elevation measurement and surface press polishing in the cushion pouring process to prepare for subsequent waterproof engineering construction.
4. The post-construction process of the anti-floating anchor rod according to claim 1, characterized in that:
the specific process of the step (3) is as follows:
a. making a mechanical inlet and outlet route of the anti-floating anchor rod;
b. the strength of the cushion layer meets the design requirement, the anti-floating anchor rod is positioned and paid off according to the construction position of the anti-floating anchor rod design point diagram, the anti-floating anchor rod is positioned and marked at the position, and the anti-floating anchor rod is uniformly arranged in a planar mode and is uniformly arranged under the basement bottom plate;
c. then, the anti-floating anchor rod drilling machine enters the field for construction: and the anti-floating anchor rod drilling machine walks on the cushion layer and performs drilling construction of the anti-floating anchor rod according to the positioning position of the anti-floating anchor rod.
5. The post-construction process of the anti-floating anchor rod according to claim 1, characterized in that:
and (5) grouting in the step (5) is performed by adding M30 cement slurry mixed with the pea stones, and performing reverse grouting by adopting the bottom pressure of the hole, wherein the full-hole grouting is completed at one time, and the grouting pressure is 1.0 MPa.
6. The post-construction process of the anti-floating anchor rod according to claim 1, characterized in that:
and (3) the lowering depth of the anti-floating anchor rod in the step (4) is not more than 10cm from the design error, the anti-floating anchor rod completed in the same day is required to complete grouting in the operation of the step (5), and a grouting pipe is reserved in the hole.
7. The post-construction process of the anti-floating anchor rod according to claim 1, characterized in that:
and (5) stopping feeding when the slurry overflows from the orifice and the color and the water-cement ratio of the overflowed slurry and the poured slurry are basically consistent, checking the fullness degree of grouting for 24 hours, and supplementing slurry if shrinkage or settlement exists.
8. The post-construction process of the anti-floating anchor rod according to claim 1, characterized in that:
in the grouting process of the step (5), quantitative grouting is adopted to be combined with the hole forming condition in the drilling process for control;
and (4) if grouting is stopped for more than 30 minutes in the grouting process, repeating the step (4) at the position close to the anti-floating anchor rod, and performing drilling, hole cleaning, anti-floating anchor rod and grouting pipe releasing and grouting again.
9. The post-construction process of the anti-floating anchor rod according to claim 1, characterized in that:
the step (6) comprises the following specific operations:
a. washing the slurry and the cement slurry on the surface of the cushion layer;
b. and (3) waterproof engineering construction: the grouting end socket of the anti-floating anchor rod is processed to be flat or recessed by 10mm, the head-out position of the anti-floating anchor rod is filled with factice for sealing, a cement-based permeable crystalline coating waterproof layer is coated, and a cushion layer self-adhesive waterproof coiled material is constructed; constructing a waterproof protective layer;
c. and (4) carrying out a drawing test after the anti-floating anchor rod reaches the design strength, and carrying out drilling, hole cleaning, grouting, anti-floating anchor rod foundation waterproof engineering and waterproof protection engineering construction on the unqualified anti-floating anchor rod at the adjacent position again.
10. The post-construction process of the anti-floating anchor rod according to claim 1, characterized in that:
the specific operation of the step (7) is as follows: bending the anti-floating anchor rod reinforcing steel bars by adopting a hydraulic machine; and then carrying out foundation construction: and (3) binding the reinforcing steel bars of the anti-floating plate, installing the template, and anchoring the anti-floating anchor steel bars to the anti-floating plate reinforcing steel bars after the anti-floating plate is poured, wherein the exposed sections of the anti-floating anchor steel bars are positioned in the space formed by binding the anti-floating plate reinforcing steel bars.
CN202010494527.XA 2020-06-03 2020-06-03 Post-construction process of anti-floating anchor rod Withdrawn CN111622272A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010494527.XA CN111622272A (en) 2020-06-03 2020-06-03 Post-construction process of anti-floating anchor rod

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010494527.XA CN111622272A (en) 2020-06-03 2020-06-03 Post-construction process of anti-floating anchor rod

Publications (1)

Publication Number Publication Date
CN111622272A true CN111622272A (en) 2020-09-04

Family

ID=72270080

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010494527.XA Withdrawn CN111622272A (en) 2020-06-03 2020-06-03 Post-construction process of anti-floating anchor rod

Country Status (1)

Country Link
CN (1) CN111622272A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112252376A (en) * 2020-10-14 2021-01-22 中积兴业建设集团有限公司 Self-locking anti-floating anchor rod construction method in complex geological environment
CN113529765A (en) * 2021-07-16 2021-10-22 中国建筑第二工程局有限公司 Rapid precipitation construction method of anti-floating anchor rod
CN114892657A (en) * 2022-05-18 2022-08-12 中建二局第四建筑工程有限公司 Construction method of foundation slab with anti-floating anchor rod
CN115126015A (en) * 2022-06-23 2022-09-30 河南省诚建检验检测技术股份有限公司 Construction method of underground garage foundation anti-floating reinforcement comprehensive treatment system
CN115142482A (en) * 2022-07-04 2022-10-04 中国十九冶集团有限公司 Later-stage anti-floating reinforcement treatment method for basement
CN115163149A (en) * 2022-06-22 2022-10-11 保利长大工程有限公司 Anti-floating anchor rod construction process based on tunnel engineering
CN115182339A (en) * 2022-08-19 2022-10-14 中国建筑第八工程局有限公司 Construction method for anti-floating anchor rod by grouting first and then bending
CN116815830A (en) * 2023-07-12 2023-09-29 安阳市高新建筑有限责任公司 Underground engineering foundation anti-floating method and system based on two-way force system construction
CN116905483A (en) * 2023-06-25 2023-10-20 中建八局第二建设有限公司 Construction method for increasing anti-floating anchors behind basement bottom plate

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112252376A (en) * 2020-10-14 2021-01-22 中积兴业建设集团有限公司 Self-locking anti-floating anchor rod construction method in complex geological environment
CN113529765A (en) * 2021-07-16 2021-10-22 中国建筑第二工程局有限公司 Rapid precipitation construction method of anti-floating anchor rod
CN113529765B (en) * 2021-07-16 2024-04-26 中国建筑第二工程局有限公司 Rapid water-lowering construction method for anti-floating anchor rod
CN114892657A (en) * 2022-05-18 2022-08-12 中建二局第四建筑工程有限公司 Construction method of foundation slab with anti-floating anchor rod
CN115163149A (en) * 2022-06-22 2022-10-11 保利长大工程有限公司 Anti-floating anchor rod construction process based on tunnel engineering
CN115163149B (en) * 2022-06-22 2023-04-21 保利长大工程有限公司 Anti-floating anchor construction process based on tunnel engineering
CN115126015A (en) * 2022-06-23 2022-09-30 河南省诚建检验检测技术股份有限公司 Construction method of underground garage foundation anti-floating reinforcement comprehensive treatment system
CN115126015B (en) * 2022-06-23 2024-06-04 河南省诚建检验检测技术股份有限公司 Construction method of anti-floating reinforcement comprehensive treatment system for underground garage foundation
CN115142482B (en) * 2022-07-04 2024-02-13 中国十九冶集团有限公司 Later-stage anti-floating reinforcement treatment method for basement
CN115142482A (en) * 2022-07-04 2022-10-04 中国十九冶集团有限公司 Later-stage anti-floating reinforcement treatment method for basement
CN115182339A (en) * 2022-08-19 2022-10-14 中国建筑第八工程局有限公司 Construction method for anti-floating anchor rod by grouting first and then bending
CN116905483A (en) * 2023-06-25 2023-10-20 中建八局第二建设有限公司 Construction method for increasing anti-floating anchors behind basement bottom plate
CN116815830B (en) * 2023-07-12 2024-03-08 安阳市高新建筑有限责任公司 Underground engineering foundation anti-floating method and system based on two-way force system construction
CN116815830A (en) * 2023-07-12 2023-09-29 安阳市高新建筑有限责任公司 Underground engineering foundation anti-floating method and system based on two-way force system construction

Similar Documents

Publication Publication Date Title
CN111622272A (en) Post-construction process of anti-floating anchor rod
CN100462507C (en) Construction method for pulling-resistant and pressure-resistant slip casting pipe pile
CN101435198A (en) Deep pit support reinforcing anti-seepage water stop composite structure
CN110004991B (en) Anti-floating system and construction method of underground structure based on convex wing foot plate
CN104532957B (en) Existing building sets up basement reversed construction method
CN111119195A (en) Foundation pit soil nail shotcrete support construction method
CN110700248A (en) A kind of small and medium-sized span bridge grouting miniature steel pipe pile and pile foundation and construction method
CN107700474A (en) A kind of existing construction foundation reinforcement means and campshed formula diaphram wall
CN102011591A (en) Grouting process for working surface of deep well
CN113338356A (en) Anti-floating anchor rod construction structure and construction method thereof
CN108677956A (en) Covered karst development area rock and soil layer contact surface grouting method
CN114541408A (en) Air-contained shaft structure at front upper part of end well of underground station and underpass construction method thereof
CN110847167A (en) Combined enhanced uplift anchor rod device and construction method
CN110144918A (en) Construction method of anti-seepage and plugging of underground building dewatering well
CN117026958A (en) A fully bonded prestressed anti-floating anchor and its construction method
CN105386610A (en) Protective construction method for natural-foundation ancient architectures at top of asymmetric deep foundation pit
CN109723055B (en) Underground diaphragm wall bottom reinforcing structure and construction method thereof
CN103015430A (en) Long auger pressure filling steel reinforced cement-soil pile foundation pit water-resisting and supporting method
CN115288181A (en) Tower crane foundation waterproof and drainage structure embedded in basement and construction method thereof
CN112982395A (en) Stiff composite pile body anchor rod device and construction process
CN108571330A (en) Method for treating leakage water of post-cast strip of subway bottom plate
CN112392042A (en) Construction method of anti-floating anchor rod pile of large underground structure
CN109183800B (en) Construction process of preliminary grouting system
CN207419441U (en) A kind of campshed formula diaphram wall
CN203361138U (en) Rear implantation pile of expanded-base pier pit underpinning

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20200904

WW01 Invention patent application withdrawn after publication