CN111564810A - Laying process of marine interlocking row - Google Patents

Laying process of marine interlocking row Download PDF

Info

Publication number
CN111564810A
CN111564810A CN202010255160.6A CN202010255160A CN111564810A CN 111564810 A CN111564810 A CN 111564810A CN 202010255160 A CN202010255160 A CN 202010255160A CN 111564810 A CN111564810 A CN 111564810A
Authority
CN
China
Prior art keywords
laying
interlocking
positioning
row
interlocking row
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010255160.6A
Other languages
Chinese (zh)
Inventor
丛军
王守成
李民强
王磊
方东园
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Haisheng Ocean Engineering Group Co ltd
Original Assignee
Shandong Haisheng Ocean Engineering Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Haisheng Ocean Engineering Group Co ltd filed Critical Shandong Haisheng Ocean Engineering Group Co ltd
Priority to CN202010255160.6A priority Critical patent/CN111564810A/en
Publication of CN111564810A publication Critical patent/CN111564810A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G9/00Installations of electric cables or lines in or on the ground or water
    • H02G9/02Installations of electric cables or lines in or on the ground or water laid directly in or on the ground, river-bed or sea-bottom; Coverings therefor, e.g. tile
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/06Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
    • H02G1/08Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle through tubing or conduit, e.g. rod or draw wire for pushing or pulling
    • H02G1/081Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle through tubing or conduit, e.g. rod or draw wire for pushing or pulling using pulling means at cable ends, e.g. pulling eyes or anchors

Abstract

The invention provides a laying process of an offshore interlocking row, wherein positioning personnel determine an interlocking row laying initial point tug to assist a laying vessel in moving the vessel to a proper position and assist in anchoring; accurately positioning the pipeline treatment position by using an USBL (ultra short base line) underwater positioning system, monitoring the laying process in real time, lifting and releasing an interlocking row, simultaneously starting a main winch and an auxiliary winch to release an interlocking row block, and using various detection means such as a 3D (three-dimensional) real-time detection and scanning sonar and multi-beam scanning; has the advantages that: the invention has high working efficiency and low construction cost; the investment on equipment is less, and the maintenance is convenient; the underwater workload is reduced, and the diving risk is reduced; the influence of ocean current is small, and the construction time is not limited.

Description

Laying process of marine interlocking row
Technical Field
The invention relates to the field of submarine pipeline suspension protection, in particular to a laying process of an offshore interlocking row.
Background
The traditional marine laying mode is that a large-scale floating crane ship is used for directly hoisting a row body to a position to be treated, and a diver is launched to centralize and release a lifting hook. The paving mode has the following defects or shortcomings: the intervention use of a large floating crane ship increases the construction cost; secondly, more diving personnel are needed, and the construction cost is increased; thirdly, the underwater operation of the diving operation receives the influence of ocean current, so the construction period is longer; the diver has difficulty and potential danger in righting the raft body underwater; fifthly, the row body needs to be lapped for at least 2 meters each time, which causes material waste to a certain extent.
Disclosure of Invention
The invention aims to solve the defects of the prior art and provide a laying process of an offshore interlocking row.
The new technical scheme of the invention is as follows: a laying process of an offshore interlocking row is as follows:
1) according to design requirements and coordinates provided by an owner, positioning personnel determine an interlocking row laying starting point;
2) the tugboat assists the spread ship to move to a proper position, so that the tugboat is perpendicular to the submarine cable to be spread, and the anchor throwing boat is arranged to assist the sea vessel 6 to throw the anchor; after the positioning is finished, the 3D real-time side-scan sonar is used for monitoring the seabed surface in a laying range in real time, and divers are arranged to clear large stones, obstacles and the like at fixed points;
3) the laying ship adjusts the ship position through the hinged anchor, ensures that the center of the laying device is flush with the pipeline to be treated, and completes the pipe riding positioning of the ship;
4) the USBL ultra-short baseline underwater positioning system is used for accurately positioning the treatment position of the pipeline:
carrying the USBL (ultra short base line) underwater positioning system by a diver, comparing design requirements with the coordinates of positioning personnel, dotting the treatment initial coordinate of the submarine cable, and accurately dotting the treatment initial coordinate at intervals of 5 meters along the direction of the submarine cable treatment route, wherein the positioning precision requirement error is less than 15 cm;
5) real-time monitoring of the laying process:
after the interlocking row is in place, using K60 satellite station differential positioning equipment to monitor that the interlocking row laying route is consistent with the ultra-short baseline underwater positioning coordinate in real time, and performing positioning and rechecking once every 5 m to ensure that the interlocking row does not deviate in the laying process and improve the laying precision; meanwhile, in the laying process, 3D real-time detection and scanning sonar is used for monitoring the underwater laying state of the interlocking row in real time, so that the interlocking row is prevented from being overlapped on the seabed;
6) hoisting the interlocking row:
arranging the interlocking arrangement on a release interlocking row movable inclined plate by adopting a marine crane, and binding two rows of cement blocks and between the cement blocks and geotextile by using a polyester rope with the diameter of 12mm, wherein the specific binding part is between a cement block connecting rope and a reinforced belt;
7) a professional simultaneously starts the main winch and the auxiliary winch to release the interlocking blocks, the interlocking blocks on the movable inclined plate slide downwards under the action of self weight, the main winch needs to run at a low speed, the impulse generated by the sliding downwards is reduced, the braking and the parking are convenient, and the 2 auxiliary winches stop running after the inclined plate reaches a working position;
8) the laying ship realizes the purpose of ship laying by simultaneously collecting and releasing a plurality of positioning anchor machines;
9) in normal laying operation, the speed of the main winch of the geotextile and the anchor mooring speed of the working ship are synchronously released, so that the interlocking rows are prevented from being overlapped on the seabed;
10) if wind shielding is needed or materials need to be prepared again as much as possible, the last row of interlocking rows are released to the sea bottom, after the geotextile is loosened, a diver cuts the geotextile at the laying end underwater and records the coordinates of the laying position by using differential positioning, and the length of the geotextile lapped at the butt joint position is not less than 2 meters during the next construction;
11) after the whole laying construction is finished, the interlocking row laying is subjected to quality inspection by using various detection means such as a 3D real-time detection and scanning sonar and a multi-beam scanning.
The invention has the beneficial effects that: the invention has high working efficiency and low construction cost; the investment on equipment is less, and the maintenance is convenient; the underwater workload is reduced, and the diving risk is reduced; the influence of ocean current is small, and the construction time is not limited.
Drawings
FIG. 1 is a schematic view of the USBL underwater positioning and arranging ship of the present invention in place.
Detailed Description
The invention will be further described with reference to the accompanying drawings.
A laying process of an offshore interlocking row is as follows:
1) according to design requirements and coordinates provided by an owner, positioning personnel determine an interlocking row laying starting point;
2) the tugboat assists the spread ship to move to a proper position, so that the tugboat is perpendicular to the submarine cable to be spread, and the anchor throwing boat is arranged to assist the sea vessel 6 to throw the anchor; after the positioning is finished, the 3D real-time side-scan sonar is used for monitoring the seabed surface in a laying range in real time, and divers are arranged to clear large stones, obstacles and the like at fixed points;
3) the laying ship adjusts the ship position through the hinged anchor, ensures that the center of the laying device is flush with the pipeline to be treated, and completes the pipe riding positioning of the ship;
4) the USBL ultra-short baseline underwater positioning system is used for accurately positioning the treatment position of the pipeline:
carrying the USBL (ultra short base line) underwater positioning system by a diver, comparing design requirements with the coordinates of positioning personnel, dotting the treatment initial coordinate of the submarine cable, and accurately dotting the treatment initial coordinate at intervals of 5 meters along the direction of the submarine cable treatment route, wherein the positioning precision requirement error is less than 15 cm;
5) real-time monitoring of the laying process:
after the interlocking row is in place, using K60 satellite station differential positioning equipment to monitor that the interlocking row laying route is consistent with the ultra-short baseline underwater positioning coordinate in real time, and performing positioning and rechecking once every 5 m to ensure that the interlocking row does not deviate in the laying process and improve the laying precision; meanwhile, in the laying process, 3D real-time detection and scanning sonar is used for monitoring the underwater laying state of the interlocking row in real time, so that the interlocking row is prevented from being overlapped on the seabed;
6) hoisting the interlocking row:
arranging the interlocking arrangement on a release interlocking row movable inclined plate by adopting a marine crane, and binding two rows of cement blocks and between the cement blocks and geotextile by using a polyester rope with the diameter of 12mm, wherein the specific binding part is between a cement block connecting rope and a reinforced belt;
7) a professional simultaneously starts the main winch and the auxiliary winch to release the interlocking blocks, the interlocking blocks on the movable inclined plate slide downwards under the action of self weight, the main winch needs to run at a low speed, the impulse generated by the sliding downwards is reduced, the braking and the parking are convenient, and the 2 auxiliary winches stop running after the inclined plate reaches a working position;
8) the laying ship realizes the purpose of ship laying by simultaneously collecting and releasing a plurality of positioning anchor machines;
9) in normal laying operation, the speed of the main winch of the geotextile and the anchor mooring speed of the working ship are synchronously released, so that the interlocking rows are prevented from being overlapped on the seabed;
10) if wind shielding is needed or materials need to be prepared again as much as possible, the last row of interlocking rows are released to the sea bottom, after the geotextile is loosened, a diver cuts the geotextile at the laying end underwater and records the coordinates of the laying position by using differential positioning, and the length of the geotextile lapped at the butt joint position is not less than 2 meters during the next construction;
11) after the whole laying construction is finished, the interlocking row laying is subjected to quality inspection by using various detection means such as a 3D real-time detection and scanning sonar and a multi-beam scanning.
Before construction: accurately positioning the pipeline treatment position by using the USBL (ultra short base line) underwater positioning system, accurately positioning every five meters underwater, checking the submarine cable routing track, and ensuring the laying accuracy of the chain rows;
during construction: using K60 satellite station differential positioning equipment to monitor that the laid route of the chain row is consistent with the underwater positioning coordinate of the ultra-short baseline in real time, and ensuring that the route of the chain row does not deviate in the laying process;
after construction: using a plurality of detection means such as a 3D real-time scan sonar and a multi-beam scan to carry out quality inspection on the linkage row laying;
discontinuous construction: if the offshore construction is influenced by factors such as adverse weather, the last row of chain rows are released to the seabed, the geotextile is cut off and the coordinates of the laying position are recorded after the geotextile is loosened, and the length of the geotextile lapped at the butt joint position is not less than 2 meters during the next construction.

Claims (1)

1. The laying process of the marine interlocking row is characterized by comprising the following steps:
the interlocking row laying process comprises the following steps:
1) according to design requirements and coordinates provided by an owner, positioning personnel determine an interlocking row laying starting point;
2) the tugboat assists the spread ship to move to a proper position, so that the tugboat is perpendicular to the submarine cable to be spread, and the anchor throwing boat is arranged to assist the sea vessel 6 to throw the anchor; after the positioning is finished, the 3D real-time side-scan sonar is used for monitoring the seabed surface in a laying range in real time, and divers are arranged to clear large stones, obstacles and the like at fixed points;
3) the laying ship adjusts the ship position through the hinged anchor, ensures that the center of the laying device is flush with the pipeline to be treated, and completes the pipe riding positioning of the ship;
4) the USBL ultra-short baseline underwater positioning system is used for accurately positioning the treatment position of the pipeline:
carrying the USBL (ultra short base line) underwater positioning system by a diver, comparing design requirements with the coordinates of positioning personnel, dotting the treatment initial coordinate of the submarine cable, and accurately dotting the treatment initial coordinate at intervals of 5 meters along the direction of the submarine cable treatment route, wherein the positioning precision requirement error is less than 15 cm;
5) real-time monitoring of the laying process:
after the interlocking row is in place, using K60 satellite station differential positioning equipment to monitor that the interlocking row laying route is consistent with the ultra-short baseline underwater positioning coordinate in real time, and performing positioning and rechecking once every 5 m to ensure that the interlocking row does not deviate in the laying process and improve the laying precision; meanwhile, in the laying process, 3D real-time detection and scanning sonar is used for monitoring the underwater laying state of the interlocking row in real time, so that the interlocking row is prevented from being overlapped on the seabed;
hoisting the interlocking row:
arranging the interlocking arrangement on a release interlocking row movable inclined plate by adopting a marine crane, and binding two rows of cement blocks and between the cement blocks and geotextile by using a polyester rope with the diameter of 12mm, wherein the specific binding part is between a cement block connecting rope and a reinforced belt;
7) a professional simultaneously starts the main winch and the auxiliary winch to release the interlocking blocks, the interlocking blocks on the movable inclined plate slide downwards under the action of self weight, the main winch needs to run at a low speed, the impulse generated by the sliding downwards is reduced, the braking and the parking are convenient, and the 2 auxiliary winches stop running after the inclined plate reaches a working position;
8) the laying ship realizes the purpose of ship laying by simultaneously collecting and releasing a plurality of positioning anchor machines;
9) in normal laying operation, the speed of the main winch of the geotextile and the anchor mooring speed of the working ship are synchronously released, so that the interlocking rows are prevented from being overlapped on the seabed;
10) if wind shielding is needed or materials need to be prepared again as much as possible, the last row of interlocking rows are released to the sea bottom, after the geotextile is loosened, a diver cuts the geotextile at the laying end underwater and records the coordinates of the laying position by using differential positioning, and the length of the geotextile lapped at the butt joint position is not less than 2 meters during the next construction;
11) after the whole laying construction is finished, the interlocking row laying is subjected to quality inspection by using various detection means such as a 3D real-time detection and scanning sonar and a multi-beam scanning.
CN202010255160.6A 2020-04-02 2020-04-02 Laying process of marine interlocking row Pending CN111564810A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010255160.6A CN111564810A (en) 2020-04-02 2020-04-02 Laying process of marine interlocking row

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010255160.6A CN111564810A (en) 2020-04-02 2020-04-02 Laying process of marine interlocking row

Publications (1)

Publication Number Publication Date
CN111564810A true CN111564810A (en) 2020-08-21

Family

ID=72070401

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010255160.6A Pending CN111564810A (en) 2020-04-02 2020-04-02 Laying process of marine interlocking row

Country Status (1)

Country Link
CN (1) CN111564810A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112018665A (en) * 2020-09-10 2020-12-01 中英海底系统有限公司 Ultra-shallow water multi-ship combined submarine cable construction positioning method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB883149A (en) * 1959-10-23 1961-11-22 Melvin Rudolph Greiser Prevention of beach erosion and encouragement of land restoration
CN101881014A (en) * 2010-07-02 2010-11-10 长江重庆航道工程局 Construction method of sinking mattress along water current for river waterway regulation
CN102277853A (en) * 2011-04-26 2011-12-14 中交四航工程研究院有限公司 Novel quick and reliable underwater arrangement technology
CN102758419A (en) * 2012-07-31 2012-10-31 长江南京航道工程局 Method for deep-water interlocking row laying construction based on movable reinforced bars
CN103590366A (en) * 2013-10-16 2014-02-19 长江南京航道工程局 Contraction preventing system for interlocking blocks
JP2015071940A (en) * 2014-12-10 2015-04-16 株式会社大宇宙産業 Footed reinforcement plate, paving structure, and paving method
CN205257848U (en) * 2016-01-08 2016-05-25 山东海盛海洋工程集团有限公司 Laying device is arranged to marine interlocking
CN106049357A (en) * 2016-05-26 2016-10-26 中交第航务工程局有限公司 Sand pillow soft mattress and manufacturing process and construction process thereof
JP2018115475A (en) * 2017-01-18 2018-07-26 株式会社トッコン Concrete block and laying structure using the same

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB883149A (en) * 1959-10-23 1961-11-22 Melvin Rudolph Greiser Prevention of beach erosion and encouragement of land restoration
CN101881014A (en) * 2010-07-02 2010-11-10 长江重庆航道工程局 Construction method of sinking mattress along water current for river waterway regulation
CN102277853A (en) * 2011-04-26 2011-12-14 中交四航工程研究院有限公司 Novel quick and reliable underwater arrangement technology
CN102758419A (en) * 2012-07-31 2012-10-31 长江南京航道工程局 Method for deep-water interlocking row laying construction based on movable reinforced bars
CN103590366A (en) * 2013-10-16 2014-02-19 长江南京航道工程局 Contraction preventing system for interlocking blocks
JP2015071940A (en) * 2014-12-10 2015-04-16 株式会社大宇宙産業 Footed reinforcement plate, paving structure, and paving method
CN205257848U (en) * 2016-01-08 2016-05-25 山东海盛海洋工程集团有限公司 Laying device is arranged to marine interlocking
CN106049357A (en) * 2016-05-26 2016-10-26 中交第航务工程局有限公司 Sand pillow soft mattress and manufacturing process and construction process thereof
JP2018115475A (en) * 2017-01-18 2018-07-26 株式会社トッコン Concrete block and laying structure using the same

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
冯海暴: "超短基线软体排深水水下定位检测系统设计与实现", 《中国优秀硕士学位论文全文数据库 信息科技辑》 *
孙卫平等: "长江下游感潮河段超长护底软体排铺设关键技术", 《水运工程》 *
焦永强: "超短基线测量技术在铺排施工中的应用", 《中国港湾建设》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112018665A (en) * 2020-09-10 2020-12-01 中英海底系统有限公司 Ultra-shallow water multi-ship combined submarine cable construction positioning method

Similar Documents

Publication Publication Date Title
CN109338883B (en) Working method of bridge underwater structure detection platform
CN109460061B (en) Parallel operation method for autonomous underwater robot and geological sampling equipment
CN201245235Y (en) Deep water jackstone leveling ship
CN103247977B (en) Multiphase submarine cable transverse arrangement of turbo circulation laying and construction method
CN109506044A (en) A kind of pipeline under the ocean construction technology
WO2018074977A1 (en) System and method for reconfiguring a mobile docking apparatus for transporting, removal, installation, housing and transferring assets
CN104631602A (en) Construction method of pipeline in sea area for sewage deep sea disposal engineering
CN109024525B (en) Artificial island structure considering underground space development and utilization and construction method thereof
CN111564810A (en) Laying process of marine interlocking row
JP2005121077A (en) Submarine pipe laying method
CN106704705B (en) overwater pipeline assembling operation method and system
CN101786496A (en) Deep-water directional drilling and steel-cable back-dragging device
CN114368456B (en) Process for separating upper floating body and lower floating body of offshore platform
US3690111A (en) Offshore pipeline installation method
CN2589773Y (en) Off-shore connecting device for shallow seabed pipeline laying
US3841106A (en) Pipeline anchoring systems
JPH0213684B2 (en)
RU2324100C2 (en) Method of underwater pipe laying, realization system and complexes of joining pipes used
JPS62122898A (en) Underwater working device
CN203528773U (en) Multi-function ship for shallow water pipeline construction
CN107658794A (en) Laying method for submarine cable
CN108330977A (en) SA sand bedding course throwing constructions
JP4219226B2 (en) Submarine pipe laying method using long pipe
CN110525600B (en) Simple anchor stone transportation and delivery device and application method
CN217272346U (en) Cross river canal and lift by crane launching gear

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200821