CN111519847A CN202010373613.5A CN202010373613A CN111519847A CN 111519847 A CN111519847 A CN 111519847A CN 202010373613 A CN202010373613 A CN 202010373613A CN 111519847 A CN111519847 A CN 111519847A
Authority
CN
China
Prior art keywords
stainless steel
close
steel structure
piece
double
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010373613.5A
Other languages
Chinese (zh)
Inventor
张世超
徐练
杨云鹏
肖长庚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Broad Sustainable Building Technology Co ltd
Original Assignee
Henan Broad Sustainable Building Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Broad Sustainable Building Technology Co ltd filed Critical Henan Broad Sustainable Building Technology Co ltd
Priority to CN202010373613.5A priority Critical patent/CN111519847A/en
Publication of CN111519847A publication Critical patent/CN111519847A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F10/00—Sunshades, e.g. Florentine blinds or jalousies; Outside screens; Awnings or baldachins
    • E04F10/08—Sunshades, e.g. Florentine blinds or jalousies; Outside screens; Awnings or baldachins of a plurality of similar rigid parts, e.g. slabs, lamellae

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Building Awnings And Sunshades (AREA)

Abstract

The invention provides an assembled inserted steel structure awning and a process method, wherein the assembled inserted steel structure awning comprises an inserting piece, double-layer glass is clamped at a position, close to the middle, of the outer surface of one side of the inserting piece, stainless steel refuels are movably connected at positions, close to the two sides and the middle, of the outer surface of the front end of the double-layer glass, the three stainless steel refuels are three in number, the position, close to the middle, of the outer surface of one side of each stainless steel refuel is clamped with the double-layer glass, the lower end of each stainless steel refuel is movably connected with a connecting beam, round holes are formed in positions, close to the two sides and the middle, of the outer surface of the upper end of each connecting beam, the outer surface of the lower end of each stainless steel refuel is inserted. The invention promotes the overall assembly rate of the assembly type steel structure, reduces pollution, supplements and expands the assembly type steel structure, and reduces fussy assembly procedures and construction period.

Description

一种装配式插入钢结构雨篷及工艺方法A kind of prefabricated insert steel structure awning and process method

技术领域technical field

本发明涉及钢结构雨篷技术领域,尤其是涉及一种装配式插入钢结构雨篷及工艺方法。The invention relates to the technical field of steel structure awnings, in particular to an assembled insert steel structure awning and a process method.

背景技术Background technique

雨篷是安装在门洞或者窗口上方的建筑部件,用于遮挡雨水。为了方便人员进出,建筑物的主要出入口往往会设置大型钢结构雨篷,即在墙体上固定多根钢质外悬挑,与横向的连系梁配合搭建平台,然后在平台上铺设安全玻璃、铝板、PC板。现有的雨棚施工不能满足装配式钢结构建筑施工的需要,建筑装配率效率低,污染性大,工期长、工序繁琐。An awning is a building component installed above a door opening or window to block rainwater. In order to facilitate the entry and exit of people, large-scale steel structure awnings are often set at the main entrances and exits of buildings, that is, a plurality of steel outer cantilevers are fixed on the wall, and a platform is constructed in cooperation with the horizontal connecting beams, and then safety glass is laid on the platform. , aluminum plate, PC board. The existing canopy construction cannot meet the needs of the prefabricated steel structure construction, the construction efficiency is low, the pollution is large, the construction period is long, and the procedures are cumbersome.

为此,提出一种装配式插入钢结构雨篷及工艺方法。To this end, a prefabricated insert steel structure awning and a process method are proposed.

发明内容SUMMARY OF THE INVENTION

本发明的第一目的在于提供一种装配式插入钢结构雨篷及工艺方法,该装配式插入钢结构雨篷及工艺方法能够推动装配式钢结构的整体装配率,减少污染,对装配式钢结构进行补充扩展,减少了繁琐的装配工序和工期,以解决上述背景技术中提出的问题。The first object of the present invention is to provide an assembled insert steel structure awning and a process method, the assembled insert steel structure awning and the process method can promote the overall assembly rate of the fabricated steel structure, reduce pollution, and reduce the pollution of the fabricated steel structure. The structure is supplemented and expanded to reduce the tedious assembly process and construction period, so as to solve the problems raised in the above-mentioned background art.

本发明提供一种装配式插入钢结构雨篷及工艺方法,包括安插件,所述安插件的一侧外表面靠近中间的位置卡接有双层玻璃,且双层玻璃的前端外表面靠近两侧和中间的位置均活动连接有不锈钢驳接件,所述不锈钢驳件的数量有三个,且不锈钢驳接件的一侧外表面靠近中间的位置与双层玻璃相卡接,所述不锈钢驳接件的下端活动连接有连接梁,所述连接梁的上端外表面靠近两侧和中间的位置均设有圆孔,且不锈钢驳接件的下端外表面安插在圆孔的内部,所述连接梁的一侧外表面活动连接有固定件,所述固定件与连接梁之间活动连接有连接螺母,且连接螺母的数量为若干。The invention provides a prefabricated-inserted steel structure awning and a process method, including an insert, one outer surface of the insert is clamped with double-layer glass at a position close to the middle, and the front outer surface of the double-glass is close to the two sides. Both the side and middle positions are movably connected with stainless steel connecting pieces, the number of the stainless steel connecting pieces is three, and the outer surface of one side of the stainless steel connecting piece is clamped with the double-layer glass near the middle position, and the stainless steel connecting pieces are connected with the double-layer glass. The lower end of the connecting piece is movably connected with a connecting beam, the outer surface of the upper end of the connecting beam is provided with circular holes near both sides and the middle, and the outer surface of the lower end of the stainless steel connecting piece is inserted inside the circular hole. An outer surface of one side of the beam is movably connected with a fixing piece, and a connecting nut is movably connected between the fixing piece and the connecting beam, and the number of the connecting nut is several.

推动装配式钢结构的整体装配率,减少污染,对装配式钢结构进行补充扩展,减少了繁琐的装配工序和工期。Promote the overall assembly rate of the prefabricated steel structure, reduce pollution, supplement and expand the prefabricated steel structure, and reduce the tedious assembly process and construction period.

优选的,所述安插件一侧外表面与墙体为胶接。Preferably, the outer surface of one side of the plug-in is glued to the wall.

通过采用上述技术方案,该结构便于安插件的固定,从而便于双层玻璃的限定。By adopting the above technical solution, the structure facilitates the fixing of the insert, thereby facilitating the definition of the double glazing.

优选的,所述固定件的一侧外表面固定安装在墙面上。Preferably, one outer surface of the fixing member is fixedly installed on the wall.

通过采用上述技术方案,该结构便于固定件的固定,从而给与双层玻璃的支撑力。By adopting the above technical solution, the structure facilitates the fixing of the fixing member, thereby giving the support force to the double-layer glass.

优选的,所述固定件的一侧外表面设置有螺孔,所述连接螺母贯穿螺孔至连接梁的内部。Preferably, one outer surface of the fixing member is provided with a screw hole, and the connecting nut penetrates the screw hole to the inside of the connecting beam.

通过采用上述技术方案,该结构便于连接梁与固定件的限定一起。By adopting the above technical solution, the structure facilitates the definition of the connecting beam and the fixing member.

一种装配式插入钢结构雨篷的工艺方法,包括如下步骤:A process method for assembling a steel structure awning, comprising the following steps:

S1:安插件一侧外表面胶接在墙面上,再将固定件的一侧外表面固定安装在墙面上,安插件在固定件的正上方;S1: The outer surface of one side of the plug-in is glued to the wall, and then the outer surface of one side of the fixing part is fixedly installed on the wall, and the plug-in is installed directly above the fixing part;

S2:连接梁的上端外表面和前端外表面均开设圆孔,连接梁的一侧插入固定件的内部,连接梁前端靠近一侧的圆孔与固定件上的螺孔相对应,若干个连接螺母贯穿螺孔螺纹连接在圆孔的内部;S2: There are round holes on the outer surface of the upper end and the outer surface of the front end of the connecting beam. One side of the connecting beam is inserted into the interior of the fixing piece. The nut is screwed through the screw hole and connected inside the round hole;

S3:双层玻璃的一侧外表面卡进安插件的内部,双层玻璃的前端外表面靠近两侧和中间的位置卡进不锈钢驳接件的内部。S3: The outer surface of one side of the double-glazed glass is clamped into the interior of the insert, and the outer surface of the front end of the double-glazed glass is clamped into the interior of the stainless steel connecting piece near the two sides and the middle.

与现有技术相比,本发明的有益效果是:Compared with the prior art, the beneficial effects of the present invention are:

1、推动装配式钢结构的整体装配率,减少污染;1. Promote the overall assembly rate of fabricated steel structures and reduce pollution;

1、对装配式钢结构进行补充扩展,减少了繁琐的装配工序和工期。1. Supplement and expand the prefabricated steel structure, reducing the tedious assembly process and construction period.

附图说明Description of drawings

为了更清楚地说明本发明具体实施方式或现有技术中的技术方案,下面将对具体实施方式或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图是本发明的一些实施方式,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to illustrate the specific embodiments of the present invention or the technical solutions in the prior art more clearly, the following briefly introduces the accompanying drawings that need to be used in the description of the specific embodiments or the prior art. Obviously, the accompanying drawings in the following description The drawings are some embodiments of the present invention. For those of ordinary skill in the art, other drawings can also be obtained based on these drawings without creative efforts.

图1为本发明的结构示意图。FIG. 1 is a schematic structural diagram of the present invention.

附图标记说明:Description of reference numbers:

1、安插件;2、双层玻璃;3、不锈钢驳接件;4、连接梁;5、固定件; 6、连接螺母;1. Plug-in; 2. Double glass; 3. Stainless steel connecting piece; 4. Connecting beam; 5. Fixing piece; 6. Connecting nut;

具体实施方式Detailed ways

下面将结合实施例对本发明的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions of the present invention will be clearly and completely described below with reference to the embodiments. Obviously, the described embodiments are part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

在本发明的描述中,需要理解的是,术语"中心"、"纵向"、"横向"、" 长度"、"宽度"、"厚度"、"上"、"下"、"前"、"后"、"左"、"右"、"竖直"、" 水平"、"顶"、"底"、"内"、"外"、"顺时针"、"逆时针"等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "top", "bottom", "front", " Rear", "left", "right", "vertical", "horizontal", "top", "bottom", "in", "outer", "clockwise", "counterclockwise" The positional relationship is based on the orientation or positional relationship shown in the accompanying drawings, which is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, Therefore, it should not be construed as a limitation of the present invention.

此外,术语"第一"、"第二"仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有"第一"、 "第二"的特征可以明示或者隐含地包括一个或者更多个所述特征。在本发明的描述中,"多个"的含义是两个或两个以上,除非另有明确具体的限定。此外,术语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本发明中的具体含义。Furthermore, the terms "first" and "second" are only used for descriptive purposes, and should not be understood as indicating or implying relative importance or implying the number of indicated technical features. Thus, features defined as "first", "second" may expressly or implicitly include one or more of said features. In the description of the present invention, "plurality" means two or more, unless otherwise expressly and specifically defined. In addition, the terms "installed", "connected" and "connected" should be understood in a broad sense, for example, it may be a fixed connection, a detachable connection, or an integral connection; it may be a mechanical connection or an electrical connection; it may be It is directly connected, or it can be indirectly connected through an intermediate medium, and it can be the internal connection of two components. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood in specific situations.

请参阅图1,本发明提供一种技术方案:Please refer to Fig. 1, the present invention provides a kind of technical scheme:

一种装配式插入钢结构雨篷及工艺方法,如图1所示,包括安插件1,所述安插件1的一侧外表面靠近中间的位置卡接有双层玻璃2,且双层玻璃 2的前端外表面靠近两侧和中间的位置均活动连接有不锈钢驳接件3,所述不锈钢驳接件3的数量有三个,且不锈钢驳接件3的一侧外表面靠近中间的位置与双层玻璃2相卡接,所述不锈钢驳接件3的下端活动连接有连接梁4,所述连接梁4的上端外表面靠近两侧和中间的位置均设有圆孔,且不锈钢驳接件3的下端外表面安插在圆孔的内部,所述连接梁4的一侧外表面活动连接有固定件5,所述固定件5与连接梁4之间活动连接有连接螺母 6,且连接螺母6的数量为若干;A prefabricated insert steel structure awning and a process method, as shown in FIG. 1, includes an insert 1, and the outer surface of one side of the insert 1 is clamped with a double-layer glass 2 at a position close to the middle, and the double-layer glass The outer surface of the front end of the front end 2 is movably connected to the two sides and the middle with a stainless steel connecting piece 3. The number of the stainless steel connecting piece 3 is three, and the outer surface of one side of the stainless steel connecting piece 3 is close to the middle. The double-layer glass 2 is clamped, the lower end of the stainless steel connecting piece 3 is movably connected with a connecting beam 4, and the outer surface of the upper end of the connecting beam 4 is provided with circular holes near both sides and the middle, and the stainless steel connecting The outer surface of the lower end of the member 3 is inserted into the inside of the circular hole, the outer surface of one side of the connecting beam 4 is movably connected with a fixing member 5, and a connecting nut 6 is movably connected between the fixing member 5 and the connecting beam 4, and is connected The number of nuts 6 is several;

如图1所示,安插件1一侧外表面与墙体为胶接。As shown in FIG. 1 , the outer surface of one side of the plug-in 1 is glued to the wall.

通过采用上述技术方案,该结构便于安插件1的固定,从而便于双层玻璃2的限定。By adopting the above technical solution, the structure facilitates the fixing of the insert 1 and thus facilitates the definition of the double glazing 2 .

具体的,如图1所示,固定件5的一侧外表面固定安装在墙面上。Specifically, as shown in FIG. 1 , one outer surface of the fixing member 5 is fixedly installed on the wall.

通过采用上述技术方案,该结构便于固定件5的固定,从而给与双层玻璃2的支撑力。By adopting the above technical solution, the structure facilitates the fixing of the fixing member 5 , thereby giving the double-layer glass 2 a supporting force.

具体的,如图1所示,固定件5的一侧外表面设置有螺孔,所述连接螺母6贯穿螺孔至连接梁4的内部。Specifically, as shown in FIG. 1 , one outer surface of the fixing member 5 is provided with a screw hole, and the connecting nut 6 penetrates through the screw hole to the inside of the connecting beam 4 .

通过采用上述技术方案,该结构便于连接梁与4固定件5的限定一起。By adopting the above technical solution, the structure facilitates the limitation of the connecting beam and the fixing member 5 together.

一种装配式插入钢结构雨篷的工艺方法,包括如下步骤:A process method for assembling a steel structure awning, comprising the following steps:

S1:安插件1一侧外表面胶接在墙面上,再将固定件5的一侧外表面固定安装在墙面上,安插件1在固定件5的正上方;S1: The outer surface of one side of the plug-in 1 is glued on the wall, and then the outer surface of one side of the fixing member 5 is fixedly installed on the wall, and the plug-in 1 is directly above the fixing member 5;

S2:连接梁4的上端外表面和前端外表面均开设圆孔,连接梁4的一侧插入固定件5的内部,连接梁4前端靠近一侧的圆孔与固定件5上的螺孔相对应,若干个连接螺母6贯穿螺孔螺纹连接在圆孔的内部;S2: Round holes are set on the outer surface of the upper end and the outer surface of the front end of the connecting beam 4, one side of the connecting beam 4 is inserted into the interior of the fixing member 5, and the circular hole on the front end of the connecting beam 4 close to one side is in line with the screw hole on the fixing member 5. Correspondingly, several connecting nuts 6 are threadedly connected inside the round hole through the screw hole;

S3:双层玻璃2的一侧外表面卡进安插件1的内部,双层玻璃2的前端外表面靠近两侧和中间的位置卡进不锈钢驳接件3的内部。S3: The outer surface of one side of the double-glazed glass 2 is clamped into the interior of the insert 1, and the outer surface of the front end of the double-glazed glass 2 is clamped into the interior of the stainless steel connecting piece 3 near the two sides and the middle.

工作原理:钢构制作和组装、不锈钢驳接件安装、雨棚双层钢化玻璃拼装,整体工厂化制作,最大程度上保证雨棚整体平整性及可观性,质量控制有保障,从而推动装配式钢结构的整体装配率,减少污染,同时对装配式钢结构进行补充扩展,减少了繁琐的装配工序和工期。Working principle: steel structure fabrication and assembly, stainless steel connecting parts installation, canopy double-layer tempered glass assembly, and overall factory production to ensure the overall flatness and observability of the canopy to the greatest extent, and the quality control is guaranteed, thereby promoting prefabricated The overall assembly rate of the steel structure reduces pollution, and at the same time supplements and expands the prefabricated steel structure, reducing the tedious assembly process and construction period.

最后应说明的是:以上各实施例仅用以说明本发明的技术方案,而非对其限制;尽管参照前述各实施例对本发明进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分或者全部技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本发明各实施例技术方案的范围。Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, but not to limit them; although the present invention has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that: The technical solutions described in the foregoing embodiments can still be modified, or some or all of the technical features thereof can be equivalently replaced; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the technical solutions of the embodiments of the present invention. scope.

Claims (5)

1. The utility model provides an assembled inserts steel construction canopy, a serial communication port, including ann plug-in components (1), the position joint that one side surface of ann plug-in components (1) is close to the centre has double glazing (2), and the equal swing joint in position that the front end surface of double glazing (2) is close to both sides and centre has stainless steel to refute union piece (3), the quantity of stainless steel refute piece (3) has threely, and one side surface of stainless steel refute union piece (3) is close to centre position and double glazing (2) looks joint, the lower extreme swing joint of stainless steel refute union piece (3) has tie-beam (4), the upper end surface of tie-beam (4) is close to both sides and centre position and all is equipped with the round hole, and the lower extreme surface of stainless steel refute union piece (3) is inserted in the inside of round hole, one side surface swing joint of tie-beam (4) has mounting (5), and a plurality of connecting nuts (6) are movably connected between the fixing piece (5) and the connecting beam (4).
2. The assembled insertion steel structure awning as claimed in claim 1, wherein the outer surface of one side of the insertion member (1) is glued to the wall.
3. An assembled insertion steel structure awning as claimed in claim 1, wherein one side outer surface of said fixing member (5) is fixedly mounted on the wall surface.
4. An assembled insertion steel structure awning as claimed in claim 1, wherein one side outer surface of said fixing member (5) is provided with a screw hole through which said coupling nut (6) is passed to the inside of the coupling beam (4).
5. A process of assembling insertion of a steel structural awning as claimed in any one of claims 1 to 4, comprising the steps of:
s1: the outer surface of one side of the plug-in (1) is glued to the wall surface, then the outer surface of one side of the fixing piece (5) is fixedly arranged on the wall surface, and the plug-in (1) is arranged right above the fixing piece (5);
s2: round holes are formed in the outer surface of the upper end and the outer surface of the front end of the connecting beam (4), one side of the connecting beam (4) is inserted into the fixing piece (5), the round hole, close to one side, in the front end of the connecting beam (4) corresponds to a screw hole in the fixing piece (5), and a plurality of connecting nuts (6) penetrate through the screw hole and are in threaded connection with the inside of the round hole;
s3: the outer surface of one side of the double-layer glass (2) is clamped into the interior of the plug-in (1), and the outer surface of the front end of the double-layer glass (2) is clamped into the interior of the stainless steel refuting piece (3) at the positions close to the two sides and the middle.
CN202010373613.5A 2020-05-06 2020-05-06 Assembled inserted steel structure awning and technological method Pending CN111519847A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010373613.5A CN111519847A (en) 2020-05-06 2020-05-06 Assembled inserted steel structure awning and technological method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010373613.5A CN111519847A (en) 2020-05-06 2020-05-06 Assembled inserted steel structure awning and technological method

Publications (1)

Publication Number Publication Date
CN111519847A true CN111519847A (en) 2020-08-11

Family

ID=71908542

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010373613.5A Pending CN111519847A (en) 2020-05-06 2020-05-06 Assembled inserted steel structure awning and technological method

Country Status (1)

Country Link
CN (1) CN111519847A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE202008013886U1 (en) * 2008-10-20 2009-12-03 Pauli + Sohn Gmbh Metallwaren Canopy and cantilever for this
CN203320855U (en) * 2013-05-17 2013-12-04 郑金弟 Rain shed for buildings
CN205153372U (en) * 2015-11-12 2016-04-13 文登蓝岛建筑工程有限公司 3d house canopy
CN205777180U (en) * 2016-05-10 2016-12-07 深圳广田装饰集团股份有限公司 A building structure and canopy with a keelless glass canopy
CN205894526U (en) * 2016-06-28 2017-01-18 南京三惠建设工程股份有限公司 Point type doubling glass canopy
CN213115261U (en) * 2020-05-06 2021-05-04 河南远大可持续建筑科技有限公司 Assembled inserts steel construction canopy

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE202008013886U1 (en) * 2008-10-20 2009-12-03 Pauli + Sohn Gmbh Metallwaren Canopy and cantilever for this
CN203320855U (en) * 2013-05-17 2013-12-04 郑金弟 Rain shed for buildings
CN205153372U (en) * 2015-11-12 2016-04-13 文登蓝岛建筑工程有限公司 3d house canopy
CN205777180U (en) * 2016-05-10 2016-12-07 深圳广田装饰集团股份有限公司 A building structure and canopy with a keelless glass canopy
CN205894526U (en) * 2016-06-28 2017-01-18 南京三惠建设工程股份有限公司 Point type doubling glass canopy
CN213115261U (en) * 2020-05-06 2021-05-04 河南远大可持续建筑科技有限公司 Assembled inserts steel construction canopy

Similar Documents

Publication Publication Date Title
CN213115261U (en) Assembled inserts steel construction canopy
CN109339280A (en) A frame type prefabricated wall panel and its installation method
CN220790287U (en) Assembled light indoor ceiling structure
CN111749380B (en) Curtain wall system capable of being installed and replaced indoor and outdoor
CN218406211U (en) Assembled kitchen wall connecting piece of making level
CN217379390U (en) Integrated wall structure of standard section member bar
CN114482437B (en) Anti-drop concrete external wall insulation board and construction method thereof
CN215716342U (en) Glass curtain wall frame and glass curtain wall with same
CN215213013U (en) Hook type curtain wall window
CN116290516A (en) A Design Structure of Hidden Frame Glass Curtain Wall with Flexible Connection of Glass Plates
CN218843478U (en) Mounting structure of metal face heat preservation decoration intergral template
CN222101326U (en) A fixed light-weight sunshade grille system
CN218861835U (en) A composite partition wall structure of lightweight slats and glass panels
CN218405956U (en) Stainless steel cellular board grafting system
CN218643752U (en) Wallboard mounting structure
CN114215215B (en) Assembled wallboard heat-bridge-free mounting structure with door and window holes and construction method
CN220036494U (en) Heating and ventilating device for building engineering
CN217269635U (en) High stability light partition wall door frame reinforcing member
CN223135428U (en) An integrated installation structure of assembled triangular curtain wall
CN216239234U (en) Interlayer cell body curtain wall fixing system
CN204960692U (en) A fenestrato for color plate housing outer wall
CN224173571U (en) A decorative wing structure independent of the exterior of the glass curtain wall
CN216195781U (en) Curved unit grating curtain wall mounting structure
CN222477873U (en) A vertical sunshade curtain wall system
CN223893570U (en) Modular wall body assembling structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200811