CN111519618A - Post-grouting device for prestressed pipe pile and construction method thereof - Google Patents

Post-grouting device for prestressed pipe pile and construction method thereof Download PDF

Info

Publication number
CN111519618A
CN111519618A CN202010492842.9A CN202010492842A CN111519618A CN 111519618 A CN111519618 A CN 111519618A CN 202010492842 A CN202010492842 A CN 202010492842A CN 111519618 A CN111519618 A CN 111519618A
Authority
CN
China
Prior art keywords
grouting
pile
pipe
steel pipe
post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010492842.9A
Other languages
Chinese (zh)
Inventor
胡玉银
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Tongrenli Geotechnical Engineering Technology Co ltd
Original Assignee
Shanghai Feisheng Enterprise Management Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Feisheng Enterprise Management Co ltd filed Critical Shanghai Feisheng Enterprise Management Co ltd
Priority to CN202010492842.9A priority Critical patent/CN111519618A/en
Priority to CN202510860204.0A priority patent/CN120443637A/en
Publication of CN111519618A publication Critical patent/CN111519618A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/50Piles comprising both precast concrete portions and concrete portions cast in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/58Prestressed concrete piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明公开了一种预应力管桩后注浆装置,涉及建筑施工领域,包括:出浆钢管、出浆钢管封板、肋板、桩封板、注浆器、注浆管;所述出浆钢管的一端与所述桩封板的一面连接,所述出浆钢管的另一端通过所述出浆钢管封板封闭,所述出浆钢管管壁包括出浆孔,所述桩封板与所述出浆钢管相对的另一面开设通孔,所述注浆器穿过所述通孔插入所述出浆钢管中,所述出浆钢管内部灌入所述粗砂,所述注浆管与所述注浆器连接;所述肋板与所述桩封板垂直连接,所述肋板为至少一个。本发明的技术效果在于:无需进行水泥土搅拌桩施工,桩底后注浆可随时进行,不占用绝对工期,施工更高效。且相对于现有后注浆装置,减少了材料使用,加工简单,安装成本低。

Figure 202010492842

The present invention discloses a post-grouting device for prestressed pipe piles, which relates to the field of building construction and includes: a slurry discharge steel pipe, a slurry discharge steel pipe sealing plate, a rib plate, a pile sealing plate, a grouting device, and a grouting pipe; one end of the slurry discharge steel pipe is connected to one side of the pile sealing plate, and the other end of the slurry discharge steel pipe is closed by the slurry discharge steel pipe sealing plate. The wall of the slurry discharge steel pipe includes a slurry discharge hole, and a through hole is provided on the other side of the pile sealing plate opposite to the slurry discharge steel pipe. The grouting device is inserted into the slurry discharge steel pipe through the through hole, and the coarse sand is poured into the interior of the slurry discharge steel pipe. The grouting pipe is connected to the grouting device; the rib plate is vertically connected to the pile sealing plate, and there is at least one rib plate. The technical effect of the present invention is that: there is no need to carry out cement-soil mixing pile construction, and the post-grouting of the pile bottom can be carried out at any time, does not occupy an absolute construction period, and is more efficient in construction. Compared with the existing post-grouting device, the material usage is reduced, the processing is simple, and the installation cost is low.

Figure 202010492842

Description

一种预应力管桩后注浆装置及其施工方法Post-grouting device for prestressed pipe pile and construction method thereof

技术领域technical field

本发明涉及建筑施工领域,尤其涉及一种预应力管桩后注浆装置及其施工方法。The invention relates to the field of building construction, in particular to a post-grouting device for prestressed pipe piles and a construction method thereof.

背景技术Background technique

预应力空心方桩和预应力管桩为工厂加工而成,采用静压、锤击方法沉桩,具有桩身强度高、施工高效、质量可靠特点。因其采用高标号混凝土、桩身抗压承载力高,而被广泛应用于工程建设中的抗压桩。但是,受制于桩身与软弱土层结合力比较弱,很多工程中地基承载力远远小于其桩身强度,从而造成资源浪费。为此工程技术人员亟需开发提高预制桩地基承载力的方法,现有的方法主要有两种:The prestressed hollow square piles and prestressed tubular piles are processed by the factory, and the piles are driven by static pressure and hammering methods. They have the characteristics of high pile body strength, efficient construction and reliable quality. Because of its high-grade concrete and high compressive bearing capacity, it is widely used in compressive piles in engineering construction. However, due to the weak bond between the pile body and the weak soil layer, the bearing capacity of the foundation in many projects is far less than the strength of the pile body, resulting in a waste of resources. For this reason, engineers and technicians urgently need to develop methods to improve the bearing capacity of precast pile foundations. There are mainly two existing methods:

(一)劲性复合桩:即首先在设计桩位施工水泥土搅拌桩,然后将预制桩身植入水泥土搅拌桩中,从而形成一种劲性复合桩。该方法主要是预先对软弱土层进行水泥土搅拌桩加固,从而提高了桩身与土体的咬合力,从而提高地基承载力。(1) Stiff composite pile: First, construct a cement-soil mixing pile at the design pile position, and then implant the prefabricated pile body into the cement-soil mixing pile to form a rigid composite pile. The method is mainly to reinforce the soft soil layer with cement-soil mixing piles in advance, thereby improving the occlusal force between the pile body and the soil body, thereby improving the bearing capacity of the foundation.

该方法存在需要改进的缺陷:①增加了一个施工环节,降低了施工工效;②水泥土搅拌桩施工需要消耗大量水泥,费用高;③预制桩植入水泥土搅拌桩也会排出大量水泥土,环境影响大。This method has defects that need to be improved: 1) a construction link is added, which reduces the construction work efficiency; 2) the construction of cement-soil mixing piles requires a large amount of cement, and the cost is high; 3. Prefabricated piles implanted in cement-soil mixing piles will also discharge a large amount of cement and soil. Great environmental impact.

(二)桩底后注浆:该方法是受钻孔灌注桩后注浆技术提高桩基承载力的启发,比较适合于场地土层在桩身范围内为粘性土、粉土、碎石土。主要采用预制桩带注浆器施工工艺,在静压沉桩完成后,进行桩侧后注浆和桩底后注浆,从而提高地基承载力。(2) Post-grouting at the bottom of the pile: This method is inspired by the post-grouting technology of bored piles to improve the bearing capacity of the pile foundation. . The construction technology of prefabricated piles with grouting device is mainly used. After the static pressure pile driving is completed, the post-grouting of the pile side and the post-grouting of the pile bottom are carried out, so as to improve the bearing capacity of the foundation.

该方法主要应用于预应力管桩,其关键技术为后注浆装置,可以同时进行桩底后注浆和桩侧后注浆。其主要组成为两端均有封板的钢管,其中与预制桩底板焊接的一端焊接穿过注浆管,后续与桩身插入的注浆导管螺纹连接,从而进行注浆,另一端可焊接桩尖,以便沉桩;注浆器四周开设出浆孔,对桩底进行后注浆,出浆孔附近设置了护耳板,防止压桩过程中侧壁土方挤密后对桩底注浆压力产生影响;注浆器靠近预制桩的一侧焊接开设2根桩侧出浆管,以便桩侧后注浆;注浆器外侧焊接加劲钢板,提高注浆器的强度和刚度,确保压桩过程承载能力;注浆器内部同时用石子填充,提高注浆器的抗压强度。The method is mainly applied to prestressed pipe piles, and its key technology is a post-grouting device, which can perform post-grouting at the bottom of the pile and post-grouting at the side of the pile at the same time. Its main composition is a steel pipe with sealing plates at both ends, in which the end welded with the prefabricated pile bottom plate is welded through the grouting pipe, and then connected with the grouting pipe inserted into the pile body by threaded connection, so as to carry out grouting, and the other end can be welded to the pile. The grouting hole is set around the grouting device, and the bottom of the pile is grouted. The ear guards are set near the grouting hole to prevent the grouting pressure on the bottom of the pile after the earthwork of the side wall is compacted during the pile pressing process. Influence; 2 pile side grouting pipes are welded on the side of the grouting device close to the prefabricated pile, so that the pile side can be grouted after the pile side; the outer side of the grouting device is welded with a stiffened steel plate to improve the strength and rigidity of the grouting device and ensure the bearing during the pile pressing process. Capability; the inside of the grouting device is filled with stones at the same time to improve the compressive strength of the grouting device.

发明内容SUMMARY OF THE INVENTION

有鉴于现有技术的上述缺陷,本发明所要解决的技术问题是提供一种节省材料且环境友好的预应力管桩后注浆装置。In view of the above-mentioned defects of the prior art, the technical problem to be solved by the present invention is to provide a material-saving and environmentally friendly post-grouting device for prestressed pipe piles.

为实现上述目的,本发明提供了一种预应力管桩后注浆装置,包括:出浆钢管、出浆钢管封板、肋板、桩封板、注浆器、注浆管、粗砂;In order to achieve the above purpose, the present invention provides a post-grouting device for prestressed pipe piles, including: grout-out steel pipe, grout-out steel pipe sealing plate, rib plate, pile sealing plate, grouting device, grouting pipe, and coarse sand;

所述出浆钢管的一端与所述桩封板的一面连接,所述出浆钢管的另一端通过所述出浆钢管封板封闭,所述出浆钢管管壁包括出浆孔,所述桩封板与所述出浆钢管相对的另一面开设通孔,所述注浆器穿过所述通孔插入所述出浆钢管中,所述出浆钢管内部灌入所述粗砂,所述注浆管与所述注浆器连接;所述肋板与所述桩封板的表面和所述出浆钢管的周边垂直连接,所述肋板为至少一个。One end of the slurrying steel pipe is connected to one side of the pile sealing plate, the other end of the slurrying steel pipe is closed by the slurrying steel pipe sealing plate, the wall of the slurrying steel pipe includes a slurrying hole, and the pile A through hole is formed on the opposite side of the sealing plate and the slurry steel pipe, the grouting device is inserted into the slurry steel pipe through the through hole, and the coarse sand is poured into the slurry steel pipe. The grouting pipe is connected with the grouting device; the rib is vertically connected with the surface of the pile sealing plate and the periphery of the grouting steel pipe, and the rib is at least one.

进一步地,所述肋板为十字形。Further, the ribs are cross-shaped.

进一步地,所述出浆孔为多个。Further, there are multiple pulping holes.

进一步地,所述注浆器包括止回阀。Further, the grouting device includes a check valve.

进一步地,所述注浆管与所述注浆器连接的一端包括连接螺纹。Further, one end of the grouting pipe connected to the grouting device includes a connecting thread.

进一步地,所述肋板的角部为倒角。Further, the corners of the ribs are chamfered.

本发明还公开了一种使用前述预应力管桩后注浆装置的施工方法,包括:The invention also discloses a construction method using the aforementioned prestressed pipe pile post-grouting device, comprising:

将所述预应力管桩后注浆装置与桩身焊接;Weld the post-grouting device of the prestressed pipe pile with the pile body;

将注浆管与注浆器连接;Connect the grouting pipe to the grouting device;

采用直接沉桩工艺将所述注浆挤扩预应力管桩和所述注浆管沉入土体,直至沉桩至设计标高;The grouting-expanded prestressed pipe pile and the grouting pipe are sunk into the soil by the direct pile driving process until the pile is driven to the design elevation;

注入水泥浆,所述水泥浆通过所述注浆管及预应力管桩后注浆装置对桩底进行注浆,在桩底形成挤扩段。The cement slurry is injected, and the cement slurry is grouted to the bottom of the pile through the grouting pipe and the post-grouting device of the prestressed pipe pile to form a squeeze-expanded section at the bottom of the pile.

进一步地,所述水泥浆采用P42.5水泥,水灰比为0.55至0.60之间。Further, the cement slurry adopts P42.5 cement, and the water-cement ratio is between 0.55 and 0.60.

进一步地,所述直接沉桩工艺为静压工艺或锤击工艺。Further, the direct pile driving process is a static pressure process or a hammering process.

本发明的技术效果在于:无需进行水泥土搅拌桩施工,桩底后注浆可随时进行,不占用绝对工期,施工更高效。尤其是相对于现有后注浆装置,减少了材料使用,加工简单,安装成本低。The technical effect of the invention is that: no cement-soil mixing pile construction is required, grouting after the pile bottom can be carried out at any time, no absolute construction period is occupied, and construction is more efficient. Especially compared with the existing post-grouting device, the material usage is reduced, the processing is simple, and the installation cost is low.

以下将结合附图对本发明的构思、具体结构及产生的技术效果作进一步说明,以充分地了解本发明的目的、特征和效果。The concept, specific structure and technical effects of the present invention will be further described below in conjunction with the accompanying drawings, so as to fully understand the purpose, characteristics and effects of the present invention.

附图说明Description of drawings

通过阅读参照以下附图所作的对非限制性实施例所作的详细描述,本发明的其它特征、目的和优点将会变得更明显:Other features, objects and advantages of the present invention will become more apparent by reading the detailed description of non-limiting embodiments made with reference to the following drawings:

图1为本发明一实施例的后注浆装置的剖视图;1 is a cross-sectional view of a post-grouting device according to an embodiment of the present invention;

图2为本发明一实施例的后注浆装置的俯视图;2 is a top view of a post-grouting device according to an embodiment of the present invention;

图3为本发明一实施例的施工状态剖视图。3 is a sectional view of an embodiment of the present invention in a construction state.

附图标记说明:100-后注浆装置;200-桩身;1-桩封板;2-肋板;3-出浆钢管;4-出浆钢管封板;5-注浆器;6-注浆管;7-粗砂;10-开口;20-焊接面。Description of reference numerals: 100-post grouting device; 200-pile body; 1-pile sealing plate; 2-rib plate; 3-grouting steel pipe; 4-grouting steel pipe sealing plate; 5-grouting device; 6- Grouting pipe; 7-coarse sand; 10-opening; 20-welding surface.

具体实施方式Detailed ways

以下参考说明书附图介绍本发明的多个优选实施例,使其技术内容更加清楚和便于理解。本发明可以通过许多不同形式的实施例来得以体现,本发明的保护范围并非仅限于文中提到的实施例。The following describes several preferred embodiments of the present invention with reference to the accompanying drawings, so as to make its technical content clearer and easier to understand. The present invention can be embodied in many different forms of embodiments, and the protection scope of the present invention is not limited to the embodiments mentioned herein.

在附图中,结构相同的部件以相同数字标号表示,各处结构或功能相似的组件以相似数字标号表示。附图所示的每一组件的尺寸和厚度是任意示出的,本发明并没有限定每个组件的尺寸和厚度。为了使图示更清晰,附图中有些地方适当夸大了部件的厚度。In the drawings, structurally identical components are denoted by the same numerals, and structurally or functionally similar components are denoted by like numerals throughout. The size and thickness of each component shown in the drawings are arbitrarily shown, and the present invention does not limit the size and thickness of each component. In order to make the illustration clearer, the thicknesses of components are appropriately exaggerated in some places in the drawings.

如图1和图2所示,本发明公开了一种预应力管桩后注浆装置,包括:出浆钢管3、出浆钢管封板4、肋板2、桩封板1、注浆器5、注浆管6、粗砂7。As shown in Figures 1 and 2, the present invention discloses a post-grouting device for prestressed pipe piles, comprising: a grout-out steel pipe 3, a grout-out steel pipe sealing plate 4, a rib plate 2, a pile sealing plate 1, and a grouting device 5. Grouting pipe 6, Coarse sand 7.

出浆钢管3为中空钢管,出浆钢管3的一端与桩封板1的一面连接,出浆钢管3的另一端通过出浆钢管封板4封闭,出浆钢管3的管壁包括多个出浆孔30;桩封板1与出浆钢管3相对的另一面开设通孔10,注浆器5穿过通孔10插入出浆钢管3中,出浆钢管3内部灌入粗砂7,注浆管6与注浆器7连接;肋板2与桩封板1垂直连接,肋板2为至少一个。优选的,粗砂7的粒径应当大于出浆孔30的直径,避免粗砂从出浆孔30中漏出。The pulping steel pipe 3 is a hollow steel pipe, one end of the pulping steel pipe 3 is connected to one side of the pile sealing plate 1, the other end of the pulping steel pipe 3 is closed by the pulping steel pipe sealing plate 4, and the pipe wall of the pulping steel pipe 3 includes a plurality of outlet pipes. Slurry hole 30; a through hole 10 is provided on the opposite side of the pile sealing plate 1 and the slurry steel pipe 3, the grouting device 5 is inserted into the slurry steel pipe 3 through the through hole 10, and the slurry steel pipe 3 is filled with coarse sand 7, and the injection The slurry pipe 6 is connected with the grouting device 7; the rib plate 2 is vertically connected with the pile sealing plate 1, and the rib plate 2 is at least one. Preferably, the particle size of the coarse sand 7 should be larger than the diameter of the slurry outlet hole 30 to prevent the coarse sand from leaking out of the slurry outlet hole 30 .

出浆孔30可以为多个并分布在出浆钢管30管壁周围,用于在注浆器5注浆时,水泥浆从出浆孔30溢出进入土体,对桩周的土体进行渗透和挤密作用,由此,桩身周围的土体即在高压水泥浆的作用下发生顶压、扩挤,逐渐加固桩周,改变桩周土体的固结状态。由此增加了管桩的抗拔性以及承载力。在一个优选实施例中,出浆孔30为多个,每个出浆孔30的直径为8~10mm。The grout hole 30 can be multiple and distributed around the pipe wall of the grout steel pipe 30, for when the grout 5 is grouting, the cement slurry overflows from the grout hole 30 into the soil, and penetrates the soil around the pile. Therefore, the soil around the pile body undergoes top pressure and expansion under the action of high-pressure cement slurry, and gradually strengthens the circumference of the pile and changes the consolidation state of the soil around the pile. This increases the pullout resistance and bearing capacity of the pipe pile. In a preferred embodiment, there are multiple pulping holes 30, and the diameter of each pulping hole 30 is 8-10 mm.

由于出浆钢管3为中空钢管,由于出浆钢管3与土体直接接触并且受力最多,因此在沉桩时,需要进行加固。本实施例中采用粗砂7充填出浆钢管3,加强出浆钢管3的刚度,保证沉桩时不损坏,同时在注浆时,水泥浆可通过粗砂7颗粒之间的缝隙流动,也不会影响注浆压力。此外粗砂7也在沉桩时用于堵住出浆孔30,避免在沉桩过程中土体随着沉桩的进行压入出浆钢管3,因此粗砂7在出浆钢管3中应当是致密的。Since the slurrying steel pipe 3 is a hollow steel pipe, since the slurrying steel pipe 3 is in direct contact with the soil and bears the most force, it needs to be reinforced during pile driving. In this embodiment, coarse sand 7 is used to fill the grout steel pipe 3 to strengthen the rigidity of the grout steel pipe 3 to ensure that the pile is not damaged. Does not affect grouting pressure. In addition, the coarse sand 7 is also used to block the slurry hole 30 during pile driving, so as to avoid the soil mass being pressed into the slurry steel pipe 3 with the pile driving during the pile driving process. Therefore, the coarse sand 7 should be in the slurry steel pipe 3. dense.

进一步地,肋板2为多个并且为十字形,以进一步破开土体,增加沉桩过程中管桩的压强。Further, the ribs 2 are multiple and cross-shaped, so as to further break the soil and increase the pressure of the pipe pile during the pile driving process.

进一步地,出浆钢管封板4的直径大于出浆钢管3的管径。由此便于将出浆钢管封板4与出浆钢管3进行连接处理,优选为焊接。Further, the diameter of the slurry steel pipe sealing plate 4 is larger than the diameter of the slurry steel pipe 3 . Therefore, it is convenient to connect the slurry steel pipe sealing plate 4 and the slurry steel pipe 3, preferably by welding.

进一步地,注浆器5包括止回阀,以防止由注浆管7注入的水泥浆回流。Further, the grouting device 5 includes a check valve to prevent backflow of the cement slurry injected from the grouting pipe 7 .

进一步地,为了固定注浆管7与注浆器5,防止注浆管7在沉桩过程中偏离注浆器5,可在注浆管7的端部上车加工螺纹,注浆管7与注浆器5螺纹连接。Further, in order to fix the grouting pipe 7 and the grouting device 5 and prevent the grouting pipe 7 from deviating from the grouting device 5 during the pile driving process, threads can be machined on the end of the grouting pipe 7. The grouting device 5 is screwed.

进一步的,肋板2的角部为倒角,以减小沉桩时桩身受到土体的阻力。Further, the corners of the rib 2 are chamfered to reduce the resistance of the pile body to the soil when the pile is driven.

进一步地,桩身200与后注浆装置100为分离式,由此桩身200和后注浆装置100可在工厂分别制造并运输至施工地点,并在施工地点直接焊接连接,图3示出了桩身200以及与后注浆装置100的焊接面20。Further, the pile body 200 and the rear grouting device 100 are separated, so the pile body 200 and the rear grouting device 100 can be manufactured separately in the factory and transported to the construction site, and directly welded and connected at the construction site, as shown in FIG. 3 . The pile body 200 and the welding surface 20 with the post grouting device 100 are formed.

本发明还公开了一种使用前述预应力管桩后注浆装置的施工方法,包括:The invention also discloses a construction method using the aforementioned prestressed pipe pile post-grouting device, comprising:

步骤S201:将后注浆装置100与桩身200焊接;Step S201: welding the post-grouting device 100 and the pile body 200;

步骤S202:将注浆管6与注浆器5连接;Step S202: connect the grouting pipe 6 to the grouting device 5;

步骤S203:采用直接沉桩工艺将所述注浆挤扩预应力管桩和所述注浆管沉入土体,直至沉桩至设计标高;Step S203: using the direct pile driving process to sink the grouting-expanded prestressed pipe pile and the grouting pipe into the soil until the pile is driven to the design elevation;

步骤S204:注入水泥浆,所述水泥浆沿所述注浆管向预应力管桩后注浆装置底部流动,在桩底形成挤扩段。Step S204 : injecting cement slurry, and the cement slurry flows along the grouting pipe to the bottom of the post-grouting device for the prestressed pipe pile to form a squeeze-expanded section at the bottom of the pile.

水泥浆可使用高压注浆泵注入注浆管6。上述施工方法减少了常规沉桩中的混凝土灌注或泥浆置换环节,施工方法简单,并且水泥浆通过注浆管6直接注入,并且从出浆孔30溢出,减小了水泥浆的用量,并且控制了水泥浆的流动路径,减少了水泥浆的材料消耗,降低了成本,对环境影响也非常小,同时预应力管桩的抗拔性和稳定性并未受到影响,仍然具有较大的地基承载力。施工方法所采用的直接沉桩工艺包括静压或锤击工艺,施工设备简易,适应性广泛。The cement slurry can be injected into the grouting pipe 6 using a high pressure grouting pump. The above construction method reduces the concrete pouring or mud replacement link in the conventional pile driving, the construction method is simple, and the cement slurry is directly injected through the grouting pipe 6 and overflows from the grout hole 30, which reduces the amount of cement slurry and controls. The flow path of the cement slurry is reduced, the material consumption of the cement slurry is reduced, the cost is reduced, and the impact on the environment is also very small. force. The direct pile driving process adopted in the construction method includes static pressure or hammering process, the construction equipment is simple and the adaptability is wide.

进一步地,水泥浆采用P42.5水泥,水灰比为0.55至0.60之间。其中P42.5是指普通硅酸盐水泥强度等级,即普通硅酸盐水泥的28天抗压强度标准不低于42.5兆帕。Further, the cement slurry adopts P42.5 cement, and the water-cement ratio is between 0.55 and 0.60. Among them, P42.5 refers to the strength grade of ordinary Portland cement, that is, the 28-day compressive strength standard of ordinary Portland cement is not less than 42.5 MPa.

准备水泥浆时应注意搅拌,保证浆液不离析。使用的搅拌系统应有两个浆液桶(搅拌桶、盛浆桶),水泥砂浆液须在搅拌桶搅拌后,通过滤网过滤后,进入专门的盛浆桶;同时盛浆桶中浆液也应设有搅拌系统,盛浆桶中浆液放置时间不应大于3小时。注浆时应严格控制注浆压力和注浆速率,终止注浆控制标准采用注浆量与注浆压力的双控制标准,注浆流量不应超过50L/min且不低于设计要求,注浆压力控制在1.0~1.8Mpa。When preparing the cement slurry, attention should be paid to stirring to ensure that the slurry does not segregate. The mixing system used should have two slurry buckets (mixing bucket and slurry bucket). Equipped with a stirring system, the slurry storage time in the slurry bucket should not exceed 3 hours. During grouting, the grouting pressure and grouting rate should be strictly controlled. The control standard for termination of grouting adopts the double control standard of grouting amount and grouting pressure. The grouting flow should not exceed 50L/min and not lower than the design requirements. The pressure is controlled at 1.0~1.8Mpa.

以上详细描述了本发明的较佳具体实施例。应当理解,本领域的普通技术无需创造性劳动就可以根据本发明的构思作出诸多修改和变化。因此,凡本技术领域中技术人员依本发明的构思在现有技术的基础上通过逻辑分析、推理或者有限的实验可以得到的技术方案,皆应在由权利要求书所确定的保护范围内。The preferred embodiments of the present invention have been described in detail above. It should be understood that many modifications and changes can be made according to the concept of the present invention by those skilled in the art without creative efforts. Therefore, all technical solutions that can be obtained by those skilled in the art through logical analysis, reasoning or limited experiments on the basis of the prior art according to the concept of the present invention shall fall within the protection scope determined by the claims.

Claims (9)

1. The utility model provides a slip casting device behind prestressed pipe pile which characterized in that includes: the grouting steel pipe, the grouting steel pipe sealing plate, the rib plate, the pile sealing plate, the grouting device, the grouting pipe and coarse sand;
one end of the grout outlet steel pipe is connected with one surface of the pile sealing plate, the other end of the grout outlet steel pipe is sealed through the grout outlet steel pipe sealing plate, the pipe wall of the grout outlet steel pipe comprises a grout outlet, the other surface, opposite to the grout outlet steel pipe, of the pile sealing plate is provided with a through hole, the grouting device penetrates through the through hole and is inserted into the grout outlet steel pipe, coarse sand is poured into the grout outlet steel pipe, and the grouting pipe is connected with the grouting device; the ribbed slab is vertically connected with the surface of the pile sealing plate and the periphery of the slurry outlet steel pipe, and at least one ribbed slab is arranged.
2. The post-grouting device for the prestressed pipe pile of claim 1, wherein the rib plate is cross-shaped.
3. The post-grouting device for the prestressed pipe pile according to claim 1, wherein the number of the grout outlet holes is plural.
4. The post-grouting device for a prestressed pipe pile according to claim 1, wherein said grouting device includes a check valve.
5. The post-grouting device for a prestressed pipe pile according to claim 1, wherein one end of the grouting pipe connected with the grouting device includes a connection thread.
6. The post-grouting device for the prestressed pipe pile according to claim 1, wherein the corners of the rib plates are chamfered.
7. A construction method using the post-grouting apparatus for a prestressed pipe pile according to any one of claims 1 to 6, comprising:
welding the post-grouting device of the prestressed pipe pile with a pile body;
connecting the grouting pipe with a grouting device;
adopting a direct pile sinking process to sink the grouting squeezing-expanding prestressed pipe pile and the grouting pipe into a soil body until the pile is sunk to the designed elevation;
and (3) injecting cement slurry, wherein the cement slurry flows to the bottom of the post-grouting device of the prestressed pipe pile along the grouting pipe, and a squeezing and expanding section is formed at the bottom of the pile.
8. The construction method using the post-grouting device for the prestressed pipe pile as claimed in claim 7, wherein the cement paste is P42.5 cement, and the water cement ratio is between 0.55 and 0.60.
9. The construction method using the post-grouting device for the prestressed pipe pile according to claim 7, wherein the direct pile sinking process is a static pressure process or a hammering process.
CN202010492842.9A 2020-06-02 2020-06-02 Post-grouting device for prestressed pipe pile and construction method thereof Pending CN111519618A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN202010492842.9A CN111519618A (en) 2020-06-02 2020-06-02 Post-grouting device for prestressed pipe pile and construction method thereof
CN202510860204.0A CN120443637A (en) 2020-06-02 2020-06-02 Prestressed pipe pile post-grouting device and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010492842.9A CN111519618A (en) 2020-06-02 2020-06-02 Post-grouting device for prestressed pipe pile and construction method thereof

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN202510860204.0A Division CN120443637A (en) 2020-06-02 2020-06-02 Prestressed pipe pile post-grouting device and construction method thereof

Publications (1)

Publication Number Publication Date
CN111519618A true CN111519618A (en) 2020-08-11

Family

ID=71911299

Family Applications (2)

Application Number Title Priority Date Filing Date
CN202010492842.9A Pending CN111519618A (en) 2020-06-02 2020-06-02 Post-grouting device for prestressed pipe pile and construction method thereof
CN202510860204.0A Pending CN120443637A (en) 2020-06-02 2020-06-02 Prestressed pipe pile post-grouting device and construction method thereof

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN202510860204.0A Pending CN120443637A (en) 2020-06-02 2020-06-02 Prestressed pipe pile post-grouting device and construction method thereof

Country Status (1)

Country Link
CN (2) CN111519618A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113832956A (en) * 2021-11-02 2021-12-24 上海斐晟企业管理有限公司 Pile end grouting device and using method thereof
CN114908756A (en) * 2021-02-09 2022-08-16 上海斐晟企业管理有限公司 A post-grouting device for prefabricated solid square pile and its construction method
CN114908755A (en) * 2021-02-09 2022-08-16 上海斐晟企业管理有限公司 A cavity post-grouting device for hollow prefabricated piles and its construction method
CN115467322A (en) * 2021-05-28 2022-12-13 上海同人里岩土工程技术有限公司 Grouting prefabricated pile after mixing and implanting into pile end and its construction method
CN115977096A (en) * 2023-01-18 2023-04-18 上海勘察设计研究院(集团)有限公司 Hollow pile post-grouting device and pile bottom post-grouting method thereof
CN116122289A (en) * 2023-01-18 2023-05-16 上海勘察设计研究院(集团)有限公司 Pile Bottom Side Bag Grouting Device and Pile Bottom Side Grouting Method Based on Hollow Pile

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100079506A (en) * 2008-12-31 2010-07-08 대림산업 주식회사 Post grouting system of cast-in-place concrete piles and the post grouting method for increasing end bearing capacity at pile base
CN103184737A (en) * 2011-12-28 2013-07-03 上海市基础工程有限公司 Grouting machine for post grouting under embedded rock geological condition
CN103469792A (en) * 2013-09-09 2013-12-25 广东省第二建筑工程公司 Method for conducting grouting construction at back of pile bottom of cast-in-place pile
CN206319313U (en) * 2016-12-26 2017-07-11 山西六建集团有限公司 Pipe pile end post-grouting device
CN209179009U (en) * 2018-11-23 2019-07-30 中国有色金属长沙勘察设计研究院有限公司 A kind of grouting device in slope reinforcement construction system
CN212452609U (en) * 2020-06-02 2021-02-02 上海斐晟企业管理有限公司 Post-grouting device for prestressed pipe pile

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100079506A (en) * 2008-12-31 2010-07-08 대림산업 주식회사 Post grouting system of cast-in-place concrete piles and the post grouting method for increasing end bearing capacity at pile base
CN103184737A (en) * 2011-12-28 2013-07-03 上海市基础工程有限公司 Grouting machine for post grouting under embedded rock geological condition
CN103469792A (en) * 2013-09-09 2013-12-25 广东省第二建筑工程公司 Method for conducting grouting construction at back of pile bottom of cast-in-place pile
CN206319313U (en) * 2016-12-26 2017-07-11 山西六建集团有限公司 Pipe pile end post-grouting device
CN209179009U (en) * 2018-11-23 2019-07-30 中国有色金属长沙勘察设计研究院有限公司 A kind of grouting device in slope reinforcement construction system
CN212452609U (en) * 2020-06-02 2021-02-02 上海斐晟企业管理有限公司 Post-grouting device for prestressed pipe pile

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114908756A (en) * 2021-02-09 2022-08-16 上海斐晟企业管理有限公司 A post-grouting device for prefabricated solid square pile and its construction method
CN114908755A (en) * 2021-02-09 2022-08-16 上海斐晟企业管理有限公司 A cavity post-grouting device for hollow prefabricated piles and its construction method
CN115467322A (en) * 2021-05-28 2022-12-13 上海同人里岩土工程技术有限公司 Grouting prefabricated pile after mixing and implanting into pile end and its construction method
CN113832956A (en) * 2021-11-02 2021-12-24 上海斐晟企业管理有限公司 Pile end grouting device and using method thereof
CN115977096A (en) * 2023-01-18 2023-04-18 上海勘察设计研究院(集团)有限公司 Hollow pile post-grouting device and pile bottom post-grouting method thereof
CN116122289A (en) * 2023-01-18 2023-05-16 上海勘察设计研究院(集团)有限公司 Pile Bottom Side Bag Grouting Device and Pile Bottom Side Grouting Method Based on Hollow Pile

Also Published As

Publication number Publication date
CN120443637A (en) 2025-08-08

Similar Documents

Publication Publication Date Title
CN111519618A (en) Post-grouting device for prestressed pipe pile and construction method thereof
CN104612134A (en) Cast-in place pile post-grouting construction method for pouring construction
CN101260672B (en) Grouting method for rocky slope with weak surface and anchor pipe used for grouting
CN102587361B (en) A construction method of high polymer material grouting wedge-shaped prefabricated pile
CN102605767A (en) Precast pile reserved with grouting pipe and piling process of precast pile
CN101761345A (en) Reinforcement device for tunnel top soil and construction method thereof
CN101736738B (en) Production method of pressure resistance and pull-out resistance grouted gravel pile
CN112144511B (en) Vacuum-assisted post grouting device and method for cast-in-situ bored pile
CN101487254A (en) Construction method of vibrating immersed tube gravel slip-casting pile
CN114517472B (en) Construction method of a carrier pile
CN112900512A (en) Basement bottom plate crack punching, reinforcing and repairing construction method
CN107417182A (en) Intumescent high polymer cement mortar, grouting and reinforcing device and grouting strengthening method
CN101021157A (en) Omnibearing high-pressure injection slip casting construction method with orifice grout stop
CN114370275B (en) Bedrock anchor grouting impervious support structure and construction method thereof
CN112081158B (en) Construction method for forming reinforced composite pile foundation by advanced grouting of high-rise building
CN111809611A (en) Construction method of jet grouting prefabricated composite pile
CN101532291B (en) Reinforcement of thick overburden layer and deep buried soft soil layer variable-diameter plastic casing hybrid pile and its pile-forming method
CN108386217A (en) A kind of the automatic classification expansion head Pulling-Resistant Anchor Rod and its application method of reinforcing soft rock mass
CN215165624U (en) Grouting device behind cavity of hollow precast pile
CN108797578A (en) Crushed stone grouting pile and its construction method with classification enlarged footing
CN218597130U (en) Side expands resistance to plucking rubble pile foundation structure that slip casting combines
CN217870641U (en) Rock-socketed cast-in-place uplift pile with embedded anchor rod
CN101545255B (en) Method for manufacturing a PHC tubular pile in soft soil region through chambering and grouting
CN111236211B (en) A grouting and extrusion prestressed pipe pile and its construction method
CN212772306U (en) Device for improving vertical compression-resistant bearing capacity of steel pipe anchor rod static pressure pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20221116

Address after: 201304 floors 1-2, building 4, No. 1628, Lizheng Road, Lingang xinpian District, Pudong New Area, Shanghai

Applicant after: Shanghai tongrenli Geotechnical Engineering Technology Co.,Ltd.

Address before: 200086 room 3653q, No.9, Lane 360, Feihong Road, Hongkou District, Shanghai

Applicant before: SHANGHAI FEISHENG ENTERPRISE MANAGEMENT Co.,Ltd.