CN111441790A - Prefabricated lining of city gate-shaped tunnel and construction method of lining of city gate-shaped tunnel - Google Patents

Prefabricated lining of city gate-shaped tunnel and construction method of lining of city gate-shaped tunnel Download PDF

Info

Publication number
CN111441790A
CN111441790A CN202010386402.5A CN202010386402A CN111441790A CN 111441790 A CN111441790 A CN 111441790A CN 202010386402 A CN202010386402 A CN 202010386402A CN 111441790 A CN111441790 A CN 111441790A
Authority
CN
China
Prior art keywords
shaped tunnel
lining
side wall
gate
connecting piece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010386402.5A
Other languages
Chinese (zh)
Inventor
张金良
曹国利
王美斋
吕小龙
田丰
陈丹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yellow River Engineering Consulting Co Ltd
Original Assignee
Yellow River Engineering Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yellow River Engineering Consulting Co Ltd filed Critical Yellow River Engineering Consulting Co Ltd
Priority to CN202010386402.5A priority Critical patent/CN111441790A/en
Publication of CN111441790A publication Critical patent/CN111441790A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • E21D11/083Methods or devices for joining adjacent concrete segments
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

本发明涉及一种城门洞形隧洞装配式衬砌,包括至少一个形状与所述城门洞形隧洞适配的衬砌单元,并且所述衬砌单元由多块预制钢筋混凝土管片装配形成。该城门洞形隧洞装配式衬砌是采用在洞外预制钢筋混凝土管片,然后再在洞内进行装配的方式形成的,无需在洞内进行钢筋网片的绑扎和焊接,装配过程简单高效,这不仅可以有效提高施工效率,而且还有效降低了施工过程中对施工人员的健康所造成的影响。本发明还涉及一种城门洞形隧洞衬砌施工方法。

Figure 202010386402

The invention relates to an assembled lining for a city gate-shaped tunnel, comprising at least one lining unit whose shape is adapted to the city gate-shaped tunnel, and the lining unit is assembled and formed by a plurality of prefabricated reinforced concrete segments. The prefabricated lining of the city gate-shaped tunnel is formed by prefabricating reinforced concrete segments outside the tunnel and then assembling them inside the tunnel. There is no need to bind and weld reinforced mesh sheets inside the tunnel. The assembly process is simple and efficient. It can not only effectively improve the construction efficiency, but also effectively reduce the impact on the health of construction workers during the construction process. The invention also relates to a construction method for the lining of a city gate-shaped tunnel.

Figure 202010386402

Description

城门洞形隧洞装配式衬砌及城门洞形隧洞衬砌施工方法Prefabricated lining of city gate-shaped tunnel and construction method of lining of city gate-shaped tunnel

技术领域technical field

本发明涉及水利工程建设技术领域,特别涉及一种城门洞形隧洞装配式衬砌及城门洞形隧洞衬砌施工方法。The invention relates to the technical field of water conservancy engineering construction, in particular to an assembled lining for a city gate-shaped tunnel and a construction method for the lining of a city gate-shaped tunnel.

背景技术Background technique

城门洞形隧洞为水工隧洞中较为常见的类型。隧洞衬砌的施工速度对工程进度与安全的影响较大,目前洞内衬砌通常是现浇形成,具体步骤为:先在靠近隧洞内壁的位置绑扎钢筋网片,然后再将钢模台车移动到预定位置以对钢筋网片进行支撑,进而向钢筋网片位置浇筑混凝土,待混凝土达到拆模强度之后撤掉钢模台车才能进行下一段浇筑。Shing Mun-shaped tunnels are the most common type of hydraulic tunnels. The construction speed of the tunnel lining has a great impact on the progress and safety of the project. At present, the lining of the tunnel is usually formed by cast-in-place. The specific steps are: first tie the steel mesh near the inner wall of the tunnel, and then move the steel formwork trolley to the A predetermined position is used to support the steel mesh, and then concrete is poured to the position of the steel mesh. After the concrete reaches the strength of the formwork removal, the steel form trolley can be removed before the next stage of pouring.

制约衬砌施工速度的最重要因素是洞内钢筋网片的绑扎。目前,隧洞衬砌的钢筋网片绑扎和焊接均是在洞内进行,由于洞内空间狭小,施工作业面有限,钢筋网片的绑扎效率极低;钢筋网片绑扎过程中需要进行焊接,焊接产生的烟雾、粉尘以及有害气体在隧洞内消散缓慢,这会严重危害现场工作人员的身体健康;另外,钢模台车需要等待混凝土达到拆模强度之后才能进行下一段浇筑,模板利用率较低。The most important factor restricting the construction speed of lining is the binding of steel mesh in the hole. At present, the binding and welding of the steel mesh for the tunnel lining are carried out in the tunnel. Due to the narrow space in the tunnel and the limited construction work area, the binding efficiency of the steel mesh is extremely low; welding is required during the binding process of the steel mesh. The smoke, dust and harmful gases dissipated slowly in the tunnel, which will seriously endanger the health of the on-site workers; in addition, the steel formwork trolley needs to wait for the concrete to reach the formwork strength before proceeding to the next stage of pouring, and the formwork utilization rate is low.

因此,如何有效提高隧洞衬砌的施工效率并降低对施工人员的身体健康的影响是目前本领域技术人员亟需解决的技术问题。Therefore, how to effectively improve the construction efficiency of tunnel lining and reduce the impact on the health of construction workers is a technical problem that those skilled in the art need to solve urgently.

发明内容SUMMARY OF THE INVENTION

本发明的目的之一是提供一种城门洞形隧洞装配式衬砌,以便能够有效提高隧洞衬砌的施工效率并降低施工过程中对施工人员的身体健康的影响。One of the objectives of the present invention is to provide an assembled lining for a city gate-shaped tunnel, so as to effectively improve the construction efficiency of the tunnel lining and reduce the impact on the health of construction workers during the construction process.

本发明的另一目的是提供一种城门洞形隧洞衬砌施工方法。Another object of the present invention is to provide a construction method for the lining of a city gate-shaped tunnel.

为达到上述目的,本发明提供的城门洞形隧洞装配式衬砌,包括至少一个形状与所述城门洞形隧洞适配的衬砌单元,并且所述衬砌单元由多块预制钢筋混凝土管片装配形成。In order to achieve the above object, the present invention provides a city gate-shaped tunnel assembled lining, comprising at least one lining unit whose shape is adapted to the city gate-shaped tunnel, and the lining unit is assembled from a plurality of prefabricated reinforced concrete segments.

优选的,所述预制钢筋混凝土管片至少包括:Preferably, the prefabricated reinforced concrete segment at least includes:

用于设置于所述城门洞形隧洞底部的底块;A bottom block for being arranged at the bottom of the city gate-shaped tunnel;

对称装配在所述底块左右两侧的侧墙块;side wall blocks symmetrically assembled on the left and right sides of the bottom block;

与所述城门洞形隧洞的顶部形状适配的顶块,所述顶块的左右两侧分别装配在两个所述侧墙块的顶端。The top block is adapted to the shape of the top of the city gate-shaped tunnel, and the left and right sides of the top block are respectively assembled on the top ends of the two side wall blocks.

优选的,所述侧墙块包括侧墙块本体以及脚块,所述脚块包括底块连接片和与所述底块连接片垂直的下端侧墙连接片,其中,Preferably, the side wall block includes a side wall block body and a foot block, the foot block includes a bottom block connecting piece and a lower end side wall connecting piece perpendicular to the bottom block connecting piece, wherein,

所述脚块位于所述城门洞形隧洞的底部与侧墙所形成的直角弯处,并且所述底块连接片与所述底块装配连接,所述下端侧墙连接片与所述侧墙块本体的下端装配连接。The foot block is located at the right-angle bend formed by the bottom of the city gate-shaped tunnel and the side wall, and the bottom block connecting piece is assembled and connected with the bottom block, and the lower end side wall connecting piece is connected with the side wall. The lower end of the block body is assembled and connected.

优选的,所述顶块包括顶块本体和对称分布于所述顶块本体两端的肩块,所述肩块包括上端侧墙连接片和与所述上端侧墙连接片相连的顶块连接片,其中,Preferably, the top block includes a top block body and shoulder blocks symmetrically distributed at both ends of the top block body, the shoulder blocks include an upper end side wall connecting piece and a top block connecting piece connected to the upper end side wall connecting piece ,in,

所述肩块位于所述城门洞形隧洞的侧墙与顶部所形成的弯折处,并且所述上端侧墙连接片与所述侧墙块本体的上端装配连接,所述顶块连接片与所述顶块本体装配连接。The shoulder block is located at the bend formed by the side wall and the top of the city gate-shaped tunnel, and the upper end side wall connecting piece is assembled and connected to the upper end of the side wall block body, and the top block connecting piece is connected to the upper end of the side wall block body. The top block body is assembled and connected.

优选的,所述底块与所述底块连接片的对接位置、所述侧墙块本体与所述下端侧墙连接片的对接位置、所述侧墙块本体与所述上端侧墙连接片的对接位置以及所述顶块本体与所述顶块连接片的对接位置均形成倾斜对接缝,且形成所述倾斜对接缝的两个部件均通过垂直于所述倾斜对接缝的螺栓装配连接。Preferably, the docking position of the bottom block and the bottom block connecting piece, the docking position of the side wall block body and the lower end side wall connecting piece, the side wall block body and the upper end side wall connecting piece The docking position of the top block body and the top block connecting piece form an inclined butt joint, and the two components that form the inclined butt joint pass through bolts perpendicular to the inclined butt joint. Assembly connection.

优选的,所述底块与所述底块连接片的对接位置、所述侧墙块本体与所述上端侧墙连接片的对接位置以及所述顶块本体与所述顶块连接片的对接位置均形成倾斜对接缝,且形成所述倾斜对接缝的两个部件均通过垂直于所述倾斜对接缝的螺栓装配连接;所述侧墙块本体与所述下端侧墙连接片的对接位置形成水平对接缝,且形成所述水平对接缝的两个部件通过插接件装配连接。Preferably, the butting position of the bottom block and the bottom block connecting piece, the butting position of the side wall block body and the upper side wall connecting piece, and the butting position of the top block body and the top block connecting piece All positions form inclined butt joints, and the two components forming the inclined butt joints are assembled and connected by bolts perpendicular to the inclined butt joints; the side wall block body and the lower end side wall connecting piece are connected. The butt joints form a horizontal butt seam, and the two parts forming said horizontal butt seam are connected by a plug fitting assembly.

优选的,所述倾斜对接缝与水平面的夹角为45°。Preferably, the angle between the inclined butt seam and the horizontal plane is 45°.

优选的,所述顶块本体与左右两个所述顶块连接片形成两个左右对称的所述倾斜对接缝,且两个所述倾斜对接缝底端之间的间距小于顶端之间的间距,以在所述顶块本体插入两个所述顶块连接片之间的空间后被所述顶块连接片承托。Preferably, the top block body and the left and right two top block connecting pieces form two left-right symmetrical inclined butt joints, and the distance between the bottom ends of the two inclined butt joints is smaller than that between the top ends. The distance between the top block body and the top block connecting piece is supported by the top block connecting piece after the top block body is inserted into the space between the two top block connecting pieces.

本发明中所公开的城门洞形隧洞衬砌施工方法,采用上述任意一项中所公开的城门洞形隧洞衬砌,该城门洞形隧洞衬砌施工方法包括步骤:The construction method for the lining of the gate-shaped tunnel disclosed in the present invention adopts the gate-shaped tunnel lining disclosed in any one of the above, and the construction method for the gate-shaped tunnel lining comprises the steps:

1)在所述城门洞形隧洞的内部将所述预制钢筋混凝土管片装配形成一个与所述城门洞形隧洞形状适配并在轴向上覆盖所述城门洞形隧洞的所述衬砌单元,并使所述衬砌单元的顶部和侧面与所述隧洞的内壁之间预留灌浆间隙;或者,在所述城门洞形隧洞的内部将所述预制钢筋混凝土管片装配形成多个与所述城门洞形隧洞形状适配的衬砌单元,多个所述衬砌单元在轴向上拼接以在轴向上覆盖所述城门洞形隧洞,并使所述衬砌单元的顶部和侧面与所述隧洞的内壁之间预留灌浆间隙;1) assembling the prefabricated reinforced concrete segments inside the city gate-shaped tunnel to form a lining unit which is adapted to the shape of the city-gate-shaped tunnel and covers the city-gate-shaped tunnel in the axial direction, A grouting gap is reserved between the top and side surfaces of the lining unit and the inner wall of the tunnel; or, the prefabricated reinforced concrete segments are assembled inside the city gate-shaped tunnel to form multiple A lining unit adapted to the shape of a gate-shaped tunnel, a plurality of the lining units are spliced in the axial direction to cover the gate-shaped tunnel in the axial direction, and the top and side of the lining unit are connected with the inner wall of the tunnel Reserve grouting gaps between;

2)在所述灌浆间隙内灌注浆料即完成城门洞形隧洞衬砌的施工。2) The construction of the lining of the gate-shaped tunnel is completed by pouring the slurry into the grouting gap.

优选的,所述灌浆间隙为90mm~110mm。Preferably, the grouting gap is 90mm˜110mm.

优选的,所述灌浆间隙为100mm。Preferably, the grouting gap is 100mm.

优选的,任意一所述衬砌单元的轴向长度为2m~4m。Preferably, the axial length of any one of the lining units is 2m-4m.

由以上技术方案可以看出,本发明中所公开的城门洞形隧的衬砌,包括一个或多个衬砌单元,而每一个衬砌单元是由多块预制钢筋混凝土管片装配形成的;It can be seen from the above technical solutions that the lining of the city gate tunnel disclosed in the present invention includes one or more lining units, and each lining unit is formed by assembling a plurality of prefabricated reinforced concrete segments;

按照城门洞形隧洞的形状,将整个衬砌分在城门洞形隧洞的轴向上分为一个或多个衬砌单元,然后再将每一个衬砌单元分割为多块管片进行预制,预制过程通常是在隧洞外的钢筋混凝土管片加工厂进行,完成预制的多块钢筋混凝土管片在城门洞形隧洞内装配后即可形成衬砌单元,然后再灌浆完成城门洞形隧洞的施工。According to the shape of the gate-shaped tunnel, the entire lining is divided into one or more lining units in the axial direction of the gate-shaped tunnel, and then each lining unit is divided into multiple segments for prefabrication. The prefabrication process is usually as follows: It is carried out in the reinforced concrete segment processing factory outside the tunnel. The prefabricated multiple reinforced concrete segments are assembled in the gate-shaped tunnel to form a lining unit, and then grouted to complete the construction of the gate-shaped tunnel.

可见,本案所公开的城门洞形隧洞装配式衬砌是采用在洞外预制钢筋混凝土管片,然后再在洞内进行装配的方式形成的,无需在洞内进行钢筋网片的绑扎和焊接,装配过程简单高效,这不仅可以有效提高施工效率,而且还有效降低了施工过程中对施工人员的健康的影响。It can be seen that the prefabricated lining of the city gate-shaped tunnel disclosed in this case is formed by prefabricating reinforced concrete segments outside the tunnel and then assembling them inside the tunnel. The process is simple and efficient, which can not only effectively improve construction efficiency, but also effectively reduce the impact on the health of construction workers during the construction process.

本发明所公开的城门洞形隧洞衬砌施工方法中,采用了上述城门洞形隧洞装配式衬砌,并且在城门洞内将预制钢筋混凝土管片装配形成的衬砌单元的顶部和侧面与隧洞的内壁之间预留有灌浆间隙;然后在灌浆间隙内灌注浆料,即完成城门洞形隧洞衬砌的施工,可见,该施工方法施工过程简便高效,有效降低了施工过程中对施工人员的健康的影响。In the lining construction method of the city gate-shaped tunnel disclosed in the present invention, the above-mentioned city gate-shaped tunnel assembled lining is adopted, and the top and side of the lining unit formed by assembling prefabricated reinforced concrete segments in the city gate hole are connected to the inner wall of the tunnel. A grouting gap is reserved between them; then the slurry is poured into the grouting gap, that is, the construction of the lining of the gate-shaped tunnel is completed. It can be seen that the construction process of this construction method is simple and efficient, and the impact on the health of the construction workers is effectively reduced.

附图说明Description of drawings

图1为本发明实施例中所公开的完成装配后的衬砌单元的主视示意图;1 is a schematic front view of the assembled lining unit disclosed in the embodiment of the present invention;

图2为底块与脚块的装配示意图;Fig. 2 is the assembly schematic diagram of the bottom block and the foot block;

图3为侧墙块本体与脚块的装配示意图;Fig. 3 is the assembly schematic diagram of side wall block body and foot block;

图4为肩块与侧墙块本体的装配示意图;Fig. 4 is the assembly schematic diagram of shoulder block and side wall block body;

图5为顶块本体与肩块的装配示意图。FIG. 5 is a schematic view of the assembly of the top block body and the shoulder block.

其中,1为底块,2为脚块,3为侧墙块本体,4为肩块,5为顶块本体。Among them, 1 is the bottom block, 2 is the foot block, 3 is the side wall block body, 4 is the shoulder block, and 5 is the top block body.

具体实施方式Detailed ways

本发明的核心之一是提供一种城门洞形隧洞装配式衬砌,以便能够有效提高隧洞衬砌的施工效率并降低施工过程中对施工人员的身体健康的影响。One of the cores of the present invention is to provide an assembled lining for a city gate-shaped tunnel, so as to effectively improve the construction efficiency of the tunnel lining and reduce the impact on the health of construction workers during the construction process.

本发明的另一核心在于提供一种城门洞形隧洞衬砌施工方法。Another core of the present invention is to provide a method for lining a city gate-shaped tunnel.

请参考图1至图5,一种实施例中所公开的城门洞形隧洞装配式衬砌,该衬砌至少包括一个形状与城门洞形隧洞适配的衬砌单元,并且该衬砌单元由多块预制钢筋混凝土管片装配形成。Please refer to FIG. 1 to FIG. 5 , an assembled lining for a gate-shaped tunnel disclosed in an embodiment, the lining includes at least one lining unit whose shape is adapted to the shape of the gate-shaped tunnel, and the lining unit is composed of a plurality of prefabricated steel bars Concrete segment assembly is formed.

实际进行衬砌预制之前,需要根据城门洞形隧洞的设计与开挖尺寸、以及制造和运输的便利情况来将衬砌设计成沿城门洞形隧洞的轴向2~4米一个衬砌单元,例如,当城门洞形隧洞的轴向长度为2~4米时,可以仅设计一个衬砌单元,当城门洞隧道的轴向长度大于4米时,应当设置多个衬砌单元,通过多个衬砌单元在城门洞形隧道的轴向上顺序布置来形成整个衬砌。Before the actual prefabrication of the lining, it is necessary to design the lining into a lining unit of 2 to 4 meters along the axial direction of the gate-shaped tunnel according to the design and excavation size of the gate-shaped tunnel, as well as the convenience of manufacturing and transportation. When the axial length of the Shingmen-shaped tunnel is 2 to 4 meters, only one lining unit can be designed. When the axial length of the Shingmen-shaped tunnel is greater than 4 meters, multiple lining units should be set up, and through multiple lining units The axial direction of the shaped tunnel is sequentially arranged to form the entire lining.

由以上实施例可以看出,本发明中所公开的城门洞形隧的衬砌,包括一个或多个衬砌单元,而每一个衬砌单元是由多块预制钢筋混凝土管片装配形成的;It can be seen from the above embodiments that the lining of the city gate tunnel disclosed in the present invention includes one or more lining units, and each lining unit is formed by assembling a plurality of prefabricated reinforced concrete segments;

按照城门洞形隧洞的形状,将整个衬砌分在城门洞形隧洞的轴向上分为一个或多个衬砌单元,然后再将每一个衬砌单元分割为多块管片进行预制,预制过程通常是在隧洞外的钢筋混凝土管片加工厂进行,完成预制的多块钢筋混凝土管片在城门洞形隧洞内装配后即可形成衬砌单元,然后再灌浆完成城门洞形隧洞的施工。According to the shape of the gate-shaped tunnel, the entire lining is divided into one or more lining units in the axial direction of the gate-shaped tunnel, and then each lining unit is divided into multiple segments for prefabrication. The prefabrication process is usually as follows: It is carried out in the reinforced concrete segment processing factory outside the tunnel. The prefabricated multiple reinforced concrete segments are assembled in the gate-shaped tunnel to form a lining unit, and then grouted to complete the construction of the gate-shaped tunnel.

可见,上述实施例所公开的城门洞形隧洞装配式衬砌是采用在洞外预制钢筋混凝土管片,然后再在洞内进行装配的方式形成的,无需在洞内进行钢筋网片的绑扎和焊接,装配过程简单高效,这不仅可以有效提高施工效率,而且还有效降低了施工过程中对施工人员的健康的影响。It can be seen that the prefabricated lining of the city gate-shaped tunnel disclosed in the above embodiment is formed by prefabricating reinforced concrete segments outside the hole and then assembling them in the hole, and there is no need to bind and weld the reinforced mesh in the hole. , the assembly process is simple and efficient, which can not only effectively improve the construction efficiency, but also effectively reduce the impact on the health of the construction workers during the construction process.

组成每个衬砌单元的预制混凝土管片的数量、形状以及位置需要根据城门洞形隧洞方便运输以及快速安装的基本要求,并结合城门洞形隧洞的受力特点进行设计,例如在一些实施例中,预制混凝土管片至少包括底块1、侧墙块以及顶块,底块1用于设置在城门洞形隧洞的底部,以用于形成城门洞形隧洞内的地面,侧墙块包括两个,两个侧墙块分别对称装配在底块1的左右两侧,侧墙块用于形成城门洞形形隧道的侧墙,顶块的形状与城门洞形隧洞的顶部形状适配,并且顶块的左右两侧分别装配在两个侧墙块的顶端,顶块用于形成城门洞形隧道的顶面。The number, shape and position of the precast concrete segments that make up each lining unit need to be designed according to the basic requirements of convenient transportation and quick installation of the gate-shaped tunnel, and combined with the stress characteristics of the gate-shaped tunnel, for example, in some embodiments , the precast concrete segment includes at least a bottom block 1, a side wall block and a top block, the bottom block 1 is used to be arranged at the bottom of the city gate-shaped tunnel to form the ground in the city gate-shaped tunnel, and the side wall block includes two , the two side wall blocks are symmetrically assembled on the left and right sides of the bottom block 1, the side wall blocks are used to form the side walls of the gate-shaped tunnel, the shape of the top block is adapted to the shape of the top of the gate-shaped tunnel, and the top The left and right sides of the block are respectively assembled on the top of the two side wall blocks, and the top block is used to form the top surface of the gate-shaped tunnel.

在另外一种实施例中,当城门洞形隧洞的高度不大于5m时,可以按照如下方式进行:侧墙块进一步划分为侧墙块本体3和脚块2,顶块进一步划分为顶块本体5和肩块4,脚块2具体呈L型,如图1至图5中所示,脚块2包括底块连接片和与底块连接片垂直的下端侧墙连接片,并且脚块2位于城门洞形隧洞的底部与侧墙所形成的直角弯处,底块连接片与底块1装配连接,下端侧墙连接片与侧墙块本体3的下端装配连接;In another embodiment, when the height of the gate-shaped tunnel is not greater than 5m, the following method can be used: the side wall block is further divided into a side wall block body 3 and a foot block 2, and the top block is further divided into a top block body 5 and the shoulder block 4, the foot block 2 is specifically L-shaped, as shown in Figures 1 to 5, the foot block 2 includes a bottom block connecting piece and a lower end side wall connecting piece perpendicular to the bottom block connecting piece, and the foot block 2 It is located at the right-angle bend formed by the bottom of the city gate-shaped tunnel and the side wall, the bottom block connecting piece is assembled and connected with the bottom block 1, and the lower end side wall connecting piece is assembled and connected with the lower end of the side wall block body 3;

肩块4包括上端侧墙连接片和与上端侧墙连接片相连的顶块连接片,侧墙连接片为平面形,顶块连接片呈与城门洞形隧洞的顶部适应的弧形,肩块4位于城门洞形隧洞的侧墙与顶部所形成的弯折处,并且上端侧墙连接片与侧墙本体的上端装配连接,顶块连接片与顶块本体5装配连接。The shoulder block 4 includes an upper end side wall connecting piece and a top block connecting piece connected with the upper end side wall connecting piece. The side wall connecting piece is a plane shape, and the top block connecting piece is in an arc shape adapted to the top of the city gate-shaped tunnel. 4 is located at the bend formed by the side wall and the top of the city gate-shaped tunnel, and the upper end side wall connecting piece is assembled and connected to the upper end of the side wall body, and the top block connecting piece is assembled and connected to the top block body 5 .

该种衬砌单元的装配顺序可参照图2至图5进行,放置好脚块2后进行底块1的装配,然后进行侧墙块本体3的装配,进而进行肩块4的装配,最后进行顶块本体5的装配。The assembly sequence of this kind of lining unit can be carried out with reference to Fig. 2 to Fig. 5. After placing the foot block 2, the bottom block 1 is assembled, then the side wall block body 3 is assembled, and then the shoulder block 4 is assembled, and finally the top block is carried out. Assembly of the block body 5 .

一种实施例中,底块1与所述底块连接片的对接位置、侧墙块本体3与下端侧墙连接片的对接位置、侧墙块本体3与上端侧墙连接片的对接位置以及顶块本体5与顶块连接片的对接位置均形成倾斜对接缝,且形成倾斜对接缝的两个部件均通过垂直于倾斜对接缝的螺栓装配连接进一步的,请参考图5,顶块本体5与左右两个顶块连接片形成两个左右对称的倾斜对接缝,且两个倾斜对接缝底端之间的间距小于顶端之间的间距,以在顶块本体5插入两个所述顶块连接片之间的空间后被顶块连接片承托,也就是说,顶块本体5最后可沿轴向插入两个顶块连接片之间的空间,并能够在顶块连接片的承托作用下保持稳定,以方便顶块本体5与顶块连接片之间的螺栓安装。In one embodiment, the docking position of the bottom block 1 and the bottom block connecting piece, the docking position of the side wall block body 3 and the lower end side wall connecting piece, the butting position of the side wall block body 3 and the upper end side wall connecting piece, and The butt joints between the top block body 5 and the top block connecting piece all form inclined butt joints, and the two components that form the inclined butt joints are assembled and connected by bolts perpendicular to the inclined butt joints. Further, please refer to Figure 5, the top The block body 5 and the left and right top block connecting pieces form two left-right symmetrical inclined butt joints, and the distance between the bottom ends of the two inclined butt joints is smaller than the distance between the top ends, so as to insert two left and right into the top block body 5. The space between the top block connecting pieces is supported by the top block connecting piece, that is to say, the top block body 5 can finally be inserted into the space between the two top block connecting pieces in the axial direction, and can be inserted into the space between the two top block connecting pieces in the axial direction. Under the supporting action of the connecting piece, it remains stable, so as to facilitate the installation of bolts between the top block body 5 and the top block connecting piece.

本领域技术人员可以理解的是,为了保持安装可靠性,任意一倾斜对接缝中沿城门洞式隧洞的轴向上可设置多个上述螺栓。It can be understood by those skilled in the art that, in order to maintain the reliability of installation, a plurality of the above-mentioned bolts may be arranged in any inclined butt joint along the axial direction of the city gate-type tunnel.

在另外一种实施例中,底块1与底块连接片的对接位置、侧墙块本体3与上端侧墙连接片的对接位置以及顶块本体5与顶块连接片的对接位置均形成倾斜对接缝,且形成倾斜对接缝的两个部件均通过垂直于倾斜对接缝的螺栓装配连接;侧墙块本体3与下端侧墙连接片的对接位置形成水平对接缝,且形成水平对接缝的两个部件通过插接件装配连接。In another embodiment, the butting position of the bottom block 1 and the bottom block connecting piece, the butting position of the side wall block body 3 and the upper end side wall connecting piece, and the butting position of the top block body 5 and the top block connecting piece are all inclined. butt joints, and the two components that form the inclined butt joints are assembled and connected by bolts perpendicular to the inclined butt joints; the butt joint positions of the side wall block body 3 and the lower end side wall connecting piece form a horizontal butt joint, and form a horizontal joint. The two parts of the butt joint are connected by means of a connector assembly.

请参考图1至图5,侧墙块本体3与下端侧墙连接片的对接位置形成水平对接缝,以保证受力的稳定性,避免侧墙块本体3及以上的预制钢筋混凝土管片滑移,为了能够实现侧墙块本体3与下端侧墙连接片之间的对接,侧墙块本体3与脚块2中的一者上应当预制或者安装插杆,另外一者上应当预制或安装有与插杆适配的插槽,以实现两者之间的插接装配。Please refer to Fig. 1 to Fig. 5, the butting position of the side wall block body 3 and the lower end side wall connecting piece forms a horizontal butt joint to ensure the stability of the force and avoid the prefabricated reinforced concrete segments of the side wall block body 3 and above. Sliding, in order to realize the butt joint between the side wall block body 3 and the lower end side wall connecting piece, one of the side wall block body 3 and the foot block 2 should be prefabricated or installed with a plunger, and the other one should be prefabricated or installed. A slot that is adapted to the insertion rod is installed to realize the plug-in assembly between the two.

当然,若城门洞形隧洞的高度大于5米时,可进一步对底块1以及侧墙块本体3进行拆分,以方便预制、运输和安装。Of course, if the height of the gate-shaped tunnel is greater than 5 meters, the bottom block 1 and the side wall block body 3 can be further disassembled to facilitate prefabrication, transportation and installation.

倾斜对接缝的目的是为了方便螺栓安装,因此上述实施例中的任意两个倾斜对接缝的角度可以相等也可以不等,一种推荐的实施例中,倾斜对接缝的倾斜角度为45°。The purpose of the inclined butt joint is to facilitate bolt installation, so the angles of any two inclined butt joints in the above embodiment may be equal or unequal. In a recommended embodiment, the inclination angle of the inclined butt joint is 45°.

另外需要进行说明的是,本文中以城门洞形隧洞的轴向为前后方向,因此城门洞形隧洞的侧墙即为左右方向。In addition, it should be noted that in this article, the axial direction of the gate-shaped tunnel is taken as the front-rear direction, so the side wall of the gate-shaped tunnel is the left-right direction.

本发明中所公开的城门洞形隧洞衬砌施工方法采用上述任意一实施例中所公开的城门洞形隧洞衬砌,包括步骤:The construction method for the lining of the gate-shaped tunnel disclosed in the present invention adopts the gate-shaped tunnel lining disclosed in any one of the above-mentioned embodiments, and includes the steps:

1)在城门洞形隧洞的内部将预制钢筋混凝土管片装配形成一个与城门洞形隧洞形状适配并在轴向上覆盖城门洞形隧洞的衬砌单元,并使衬砌单元的顶部和侧面与城门洞形隧洞的内壁之间预留灌浆间隙;或者,在城门洞形隧洞的内部将预制钢筋混凝土管片装配形成多个与城门洞形隧洞形状适配的衬砌单元,多个衬砌单元在轴向上拼接以在轴向上覆盖所述城门洞形隧洞,并使衬砌单元的顶部和侧面与城门洞形隧洞的内壁之间预留灌浆间隙,多个衬砌单元之间也通过连接件或插接件相连,或者多个衬砌单元之间也可以没有连接关系;1) Assemble the prefabricated reinforced concrete segments inside the gate-shaped tunnel to form a lining unit that fits the shape of the gate-shaped tunnel and covers the gate-shaped tunnel in the axial direction, and makes the top and side of the lining unit meet the A grouting gap is reserved between the inner walls of the gate-shaped tunnel; alternatively, the prefabricated reinforced concrete segments are assembled inside the gate-shaped tunnel to form a plurality of lining units that are adapted to the shape of the gate-shaped tunnel, and the multiple lining units are axially aligned. The upper splicing is used to cover the city gate-shaped tunnel in the axial direction, and a grouting gap is reserved between the top and side of the lining unit and the inner wall of the city gate-shaped tunnel, and a plurality of lining units are also connected by connectors or plugs. The parts are connected, or there may be no connection between multiple lining units;

2)在所述灌浆间隙内灌注浆料,即完成城门洞形隧洞衬砌的施工。2) Pour slurry into the grouting gap, that is, complete the construction of the lining of the city gate-shaped tunnel.

灌注浆料时优选采用豆砾石吹填灌浆,灌浆间隙在90~110mm之间,优选的为100mm,以保证衬砌与城门洞形隧洞内壁的受力均匀性。When pouring the slurry, it is preferred to use bean gravel to fill the grouting, and the grouting gap is between 90 and 110 mm, preferably 100 mm, to ensure the uniformity of the force between the lining and the inner wall of the gate-shaped tunnel.

上述实施例中的城门洞形隧洞衬砌施工方法中,采用了上述城门洞形隧洞衬砌,并且在城门洞内将预制钢筋混凝土管片装配形成的衬砌单元的顶部和侧面与隧洞的内壁之间预留有灌浆间隙;然后在灌浆间隙内灌注浆料,即完成城门洞形隧洞衬砌的施工,可见,该施工方法简便高效,可有效降低施工过程中对施工人员的身体健康所产生的影响,具有较大的推广应用价值。In the construction method for the lining of the city gate hole-shaped tunnel in the above-mentioned embodiment, the above-mentioned city gate hole-shaped tunnel lining is adopted, and the top and side surfaces of the lining unit formed by assembling the prefabricated reinforced concrete segments and the inner wall of the tunnel are pre-prepared in the city gate hole. Leave a grouting gap; then pour the slurry into the grouting gap to complete the construction of the gate-shaped tunnel lining. It can be seen that this construction method is simple and efficient, and can effectively reduce the impact on the health of the construction workers during the construction process. Great promotion and application value.

以上对本发明所提供的城门洞形隧洞装配式衬砌及城门洞形隧洞衬砌施工方法进行了详细介绍。本文中应用了具体个例对本发明的原理及实施方式进行了阐述,以上实施例的说明只是用于帮助理解本发明的方法及其核心思想。应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以对本发明进行若干改进和修饰,这些改进和修饰也落入本发明权利要求的保护范围内。The prefabricated lining of the city gate-shaped tunnel and the construction method of the lining of the city gate-shaped tunnel provided by the present invention are described in detail above. The principles and implementations of the present invention are described herein by using specific examples, and the descriptions of the above embodiments are only used to help understand the method and the core idea of the present invention. It should be pointed out that for those skilled in the art, without departing from the principle of the present invention, several improvements and modifications can also be made to the present invention, and these improvements and modifications also fall within the protection scope of the claims of the present invention.

Claims (10)

1.一种城门洞形隧洞装配式衬砌,其特征在于,包括至少一个形状与所述城门洞形隧洞适配的衬砌单元,并且所述衬砌单元由多块预制钢筋混凝土管片装配形成。1. An assembled lining for a city gate-shaped tunnel, characterized in that it comprises at least one lining unit whose shape is adapted to the city gate-shaped tunnel, and the lining unit is assembled from a plurality of prefabricated reinforced concrete segments. 2.根据权利要求1所述的城门洞形隧洞装配式衬砌,其特征在于,所述预制钢筋混凝土管片至少包括:2. The prefabricated lining for a city gate-shaped tunnel according to claim 1, wherein the prefabricated reinforced concrete segment at least comprises: 用于设置于所述城门洞形隧洞底部的底块(1);A bottom block (1) for being arranged at the bottom of the city gate-shaped tunnel; 对称装配在所述底块(1)左右两侧的侧墙块;side wall blocks symmetrically assembled on the left and right sides of the bottom block (1); 与所述城门洞形隧洞的顶部形状适配的顶块,所述顶块的左右两侧分别装配在两个所述侧墙块的顶端。The top block is adapted to the shape of the top of the city gate-shaped tunnel, and the left and right sides of the top block are respectively assembled on the top ends of the two side wall blocks. 3.根据权利要求2所述的城门洞形隧洞装配式衬砌,其特征在于,所述侧墙块包括侧墙块本体(3)以及脚块(2),所述脚块(2)包括底块连接片和与所述底块连接片垂直的下端侧墙连接片,其中,3. The prefabricated lining for a city gate-shaped tunnel according to claim 2, wherein the side wall block comprises a side wall block body (3) and a foot block (2), and the foot block (2) comprises a bottom A block connecting piece and a lower end side wall connecting piece perpendicular to the bottom block connecting piece, wherein, 所述脚块(2)位于所述城门洞形隧洞的底部与侧墙所形成的直角弯处,并且所述底块连接片与所述底块(1)装配连接,所述下端侧墙连接片与所述侧墙块本体(3)的下端装配连接。The foot block (2) is located at the right-angle bend formed by the bottom of the city gate-shaped tunnel and the side wall, and the bottom block connecting piece is assembled and connected to the bottom block (1), and the lower end side wall is connected The sheet is assembled and connected with the lower end of the side wall block body (3). 4.根据权利要求3所述的城门洞形隧洞装配式衬砌,其特征在于,所述顶块包括顶块本体(5)和对称分布于所述顶块本体(5)两端的肩块(4),所述肩块(4)包括上端侧墙连接片和与所述上端侧墙连接片相连的顶块连接片,其中,4. The prefabricated lining for a city gate-shaped tunnel according to claim 3, wherein the top block comprises a top block body (5) and shoulder blocks (4) symmetrically distributed at both ends of the top block body (5). ), the shoulder block (4) comprises an upper end side wall connecting piece and a top block connecting piece connected with the upper end side wall connecting piece, wherein, 所述肩块(4)位于所述城门洞形隧洞的侧墙与顶部所形成的弯折处,并且所述上端侧墙连接片与所述侧墙块本体(3)的上端装配连接,所述顶块连接片与所述顶块本体(5)装配连接。The shoulder block (4) is located at the bend formed by the side wall and the top of the city gate-shaped tunnel, and the upper end side wall connecting piece is assembled and connected to the upper end of the side wall block body (3), so The top block connecting piece is assembled and connected with the top block body (5). 5.根据权利要求4所述的城门洞形隧洞装配式衬砌,其特征在于,所述底块(1)与所述底块连接片的对接位置、所述侧墙块本体(3)与所述下端侧墙连接片的对接位置、所述侧墙块本体(3)与所述上端侧墙连接片的对接位置以及所述顶块本体(5)与所述顶块连接片的对接位置均形成倾斜对接缝,且形成所述倾斜对接缝的两个部件均通过垂直于所述倾斜对接缝的螺栓装配连接。5. The prefabricated lining for a city gate-shaped tunnel according to claim 4, characterized in that the butt joint position of the bottom block (1) and the bottom block connecting piece, the side wall block body (3) and the The docking position of the lower end side wall connecting piece, the butting position of the side wall block body (3) and the upper end side wall connecting piece, and the butting position of the top block body (5) and the top block connecting piece are all An oblique butt joint is formed, and the two components forming the oblique butt joint are both assembled and connected by bolts perpendicular to the oblique butt joint. 6.根据权利要求4所述的城门洞形隧洞装配式衬砌,其特征在于,所述底块(1)与所述底块连接片的对接位置、所述侧墙块本体(3)与所述上端侧墙连接片的对接位置以及所述顶块本体(5)与所述顶块连接片的对接位置均形成倾斜对接缝,且形成所述倾斜对接缝的两个部件均通过垂直于所述倾斜对接缝的螺栓装配连接;所述侧墙块本体(3)与所述下端侧墙连接片的对接位置形成水平对接缝,且形成所述水平对接缝的两个部件通过插接件装配连接。6. The prefabricated lining for a city gate-shaped tunnel according to claim 4, characterized in that the butting position of the bottom block (1) and the bottom block connecting piece, the side wall block body (3) and the The butting position of the upper end side wall connecting piece and the butting position of the top block body (5) and the top block connecting piece all form inclined butt joints, and the two components forming the inclined butt joints pass through vertical joints. The bolts are assembled and connected at the inclined butt joints; the docking position of the side wall block body (3) and the lower end side wall connecting piece forms a horizontal butt joint, and forms two components of the horizontal butt joint The connection is made by means of a plug-in connector. 7.根据权利要求5或6所述的城门洞形隧洞装配式衬砌,其特征在于,所述倾斜对接缝与水平面的夹角为45°。7 . The prefabricated lining for a city gate-shaped tunnel according to claim 5 or 6 , wherein the angle between the inclined butt joint and the horizontal plane is 45°. 8 . 8.根据权利要求5或6所述的城门洞形隧洞装配式衬砌,其特征在于,所述顶块本体(5)与左右两个所述顶块连接片形成两个左右对称的所述倾斜对接缝,且两个所述倾斜对接缝底端之间的间距小于顶端之间的间距,以在所述顶块本体(5)插入两个所述顶块连接片之间的空间后被所述顶块连接片承托。8. The prefabricated lining for a city gate-shaped tunnel according to claim 5 or 6, wherein the top block body (5) and the left and right two top block connecting pieces form two left-right symmetrical inclinations butt joints, and the distance between the bottom ends of the two inclined butt joints is smaller than the distance between the top ends, so that after the top block body (5) is inserted into the space between the two top block connecting pieces supported by the top block connecting piece. 9.一种城门洞形隧洞衬砌施工方法,采用如权利要求1-8任意一项所述的城门洞形隧洞衬砌,其特征在于,包括步骤:9. A construction method for a gate-shaped tunnel lining, adopting the gate-shaped tunnel lining according to any one of claims 1-8, characterized in that, comprising the steps: 1)在所述城门洞形隧洞的内部将所述预制钢筋混凝土管片装配形成一个与所述城门洞形隧洞形状适配并在轴向上覆盖所述城门洞形隧洞的所述衬砌单元,并使所述衬砌单元的顶部和侧面与所述城门洞形隧洞的内壁之间预留灌浆间隙;或者,在所述城门洞形隧洞的内部将所述预制钢筋混凝土管片装配形成多个与所述城门洞形隧洞形状适配的衬砌单元,多个所述衬砌单元在轴向上拼接以在轴向上覆盖所述城门洞形隧洞,并使所述衬砌单元的顶部和侧面与所述城门洞形隧洞的内壁之间预留灌浆间隙;1) assembling the prefabricated reinforced concrete segments inside the city gate-shaped tunnel to form a lining unit which is adapted to the shape of the city-gate-shaped tunnel and covers the city-gate-shaped tunnel in the axial direction, A grouting gap is reserved between the top and side of the lining unit and the inner wall of the city gate-shaped tunnel; or, the prefabricated reinforced concrete segments are assembled inside the city gate-shaped tunnel to form a plurality of A lining unit adapted to the shape of the city gate hole-shaped tunnel, a plurality of the lining units are spliced in the axial direction to cover the city gate hole-shaped tunnel in the axial direction, and the top and side of the lining unit are connected to the A grouting gap is reserved between the inner walls of the gate-shaped tunnel; 2)在所述灌浆间隙内灌注浆料即完成城门洞形隧洞衬砌的施工。2) The construction of the lining of the gate-shaped tunnel is completed by pouring the slurry into the grouting gap. 10.根据权利要求9所述的城门洞形隧洞衬砌施工方法,其特征在于,所述灌浆间隙为90mm~110mm。10 . The method for lining a city gate-shaped tunnel according to claim 9 , wherein the grouting gap is 90 mm to 110 mm. 11 .
CN202010386402.5A 2020-05-09 2020-05-09 Prefabricated lining of city gate-shaped tunnel and construction method of lining of city gate-shaped tunnel Pending CN111441790A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010386402.5A CN111441790A (en) 2020-05-09 2020-05-09 Prefabricated lining of city gate-shaped tunnel and construction method of lining of city gate-shaped tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010386402.5A CN111441790A (en) 2020-05-09 2020-05-09 Prefabricated lining of city gate-shaped tunnel and construction method of lining of city gate-shaped tunnel

Publications (1)

Publication Number Publication Date
CN111441790A true CN111441790A (en) 2020-07-24

Family

ID=71648353

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010386402.5A Pending CN111441790A (en) 2020-05-09 2020-05-09 Prefabricated lining of city gate-shaped tunnel and construction method of lining of city gate-shaped tunnel

Country Status (1)

Country Link
CN (1) CN111441790A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111411982A (en) * 2020-05-09 2020-07-14 黄河勘测规划设计研究院有限公司 Egg-shaped tunnel fabricated lining and egg-shaped tunnel lining construction method

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205012283U (en) * 2015-07-24 2016-02-03 中国十九冶集团有限公司 Large-volume concrete blocking body structure in hydraulic tunnel
CN205089333U (en) * 2015-08-31 2016-03-16 中国电建集团成都勘测设计研究院有限公司 Pressure tunnel atress structure
CN105484761A (en) * 2015-04-16 2016-04-13 中铁隧道勘测设计院有限公司 Lining structure of single-tube double-tunnel rectangular shield tunnel and assembly method thereof
CN207348879U (en) * 2017-10-27 2018-05-11 中国电建集团成都勘测设计研究院有限公司 Tailwater tunnel structure
CN109578017A (en) * 2018-12-28 2019-04-05 中国电建集团贵阳勘测设计研究院有限公司 Quick lining structure of extra-long small-section hydraulic tunnel and construction method thereof
CN209569014U (en) * 2018-12-06 2019-11-01 中建地下空间有限公司 A kind of tubular tunnel segment structure suitable for Circular Shaft
CN209816911U (en) * 2019-01-31 2019-12-20 沈阳建筑大学 A prefabricated concrete comprehensive pipe gallery structure
CN110685255A (en) * 2019-11-09 2020-01-14 黄河勘测规划设计研究院有限公司 Assembled reinforced concrete segment suitable for quick lining of horseshoe tunnel
CN110778330A (en) * 2019-11-09 2020-02-11 黄河勘测规划设计研究院有限公司 Prefabricated reinforced concrete bottom plate for rapid lining of horseshoe tunnel and construction method
CN110778337A (en) * 2019-11-09 2020-02-11 黄河勘测规划设计研究院有限公司 Fabricated steel segment template construction method suitable for rapid lining of circular tunnel
CN210127857U (en) * 2019-07-01 2020-03-06 四川省交通勘察设计研究院有限公司 Steel beam-concrete combined assembly type tunnel component suitable for highway tunnel
CN212027800U (en) * 2020-05-09 2020-11-27 黄河勘测规划设计研究院有限公司 Assembled lining of tunnel in shape of city portal

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105484761A (en) * 2015-04-16 2016-04-13 中铁隧道勘测设计院有限公司 Lining structure of single-tube double-tunnel rectangular shield tunnel and assembly method thereof
CN205012283U (en) * 2015-07-24 2016-02-03 中国十九冶集团有限公司 Large-volume concrete blocking body structure in hydraulic tunnel
CN205089333U (en) * 2015-08-31 2016-03-16 中国电建集团成都勘测设计研究院有限公司 Pressure tunnel atress structure
CN207348879U (en) * 2017-10-27 2018-05-11 中国电建集团成都勘测设计研究院有限公司 Tailwater tunnel structure
CN209569014U (en) * 2018-12-06 2019-11-01 中建地下空间有限公司 A kind of tubular tunnel segment structure suitable for Circular Shaft
CN109578017A (en) * 2018-12-28 2019-04-05 中国电建集团贵阳勘测设计研究院有限公司 Quick lining structure of extra-long small-section hydraulic tunnel and construction method thereof
CN209816911U (en) * 2019-01-31 2019-12-20 沈阳建筑大学 A prefabricated concrete comprehensive pipe gallery structure
CN210127857U (en) * 2019-07-01 2020-03-06 四川省交通勘察设计研究院有限公司 Steel beam-concrete combined assembly type tunnel component suitable for highway tunnel
CN110685255A (en) * 2019-11-09 2020-01-14 黄河勘测规划设计研究院有限公司 Assembled reinforced concrete segment suitable for quick lining of horseshoe tunnel
CN110778330A (en) * 2019-11-09 2020-02-11 黄河勘测规划设计研究院有限公司 Prefabricated reinforced concrete bottom plate for rapid lining of horseshoe tunnel and construction method
CN110778337A (en) * 2019-11-09 2020-02-11 黄河勘测规划设计研究院有限公司 Fabricated steel segment template construction method suitable for rapid lining of circular tunnel
CN212027800U (en) * 2020-05-09 2020-11-27 黄河勘测规划设计研究院有限公司 Assembled lining of tunnel in shape of city portal

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111411982A (en) * 2020-05-09 2020-07-14 黄河勘测规划设计研究院有限公司 Egg-shaped tunnel fabricated lining and egg-shaped tunnel lining construction method

Similar Documents

Publication Publication Date Title
CN103835283B (en) Full wet joint prefabricated prestressed underground continuous wall and construction method thereof
CN102425433B (en) Minus-ring-free originating construction method for constructing sectional shield tunnel
CN111411982A (en) Egg-shaped tunnel fabricated lining and egg-shaped tunnel lining construction method
CN102635118B (en) Square steel pipe concrete supporting structure for foundation pit support
CN104563299B (en) Reinforced concrete prefabricated components and installation method
CN211257077U (en) Prefabricated assembly and cast-in-place utility tunnel who mixes construction
CN103741810B (en) Method for horizontally connecting precast concrete members
CN110552722B (en) Fabricated reinforcement cage construction method for rapid tunnel lining
CN104695968B (en) Method for in-tunnel starting of shield tunneling machine
CN106013237A (en) Precast concrete component assembly type subway station and installation method
CN207829150U (en) A kind of sliding installation system of fabricated construction
CN110700211A (en) Construction method of fabricated steel tube sheet formwork suitable for rapid lining of horseshoe-shaped tunnels
CN103726589B (en) I-shaped steel and steel and steel pipe framework interface drum projection diagonal reinforcement assembling shear wall and the practice
CN102051931B (en) Steel reinforcement cage for multi-ribbed composite wall and installation method of steel reinforcement cage
CN111441790A (en) Prefabricated lining of city gate-shaped tunnel and construction method of lining of city gate-shaped tunnel
CN210152316U (en) A prefabricated reinforcement device for reinforced concrete beams
CN206409743U (en) The steel pipe pile-supported structure of underground utilities
CN212054723U (en) Egg-shaped tunnel fabricated lining
CN113175329A (en) Tunnel portal construction method for parallel pipe-jacking tunnel
CN212027800U (en) Assembled lining of tunnel in shape of city portal
CN204511457U (en) Class oval top tube method tube coupling
CN111022084A (en) Large-section loess tunnel excavation primary support arch frame single truss and method
CN110158464A (en) A kind of novel shear key combination beam and its construction method
CN113482661B (en) Multi-arch tunnel assembled intermediate wall and construction method
CN211257075U (en) Assembled utility tunnel coincide wall structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination