CN111441499A - Joint structure and method for common concrete and iron ore sand concrete super-thick wall - Google Patents
Joint structure and method for common concrete and iron ore sand concrete super-thick wall Download PDFInfo
- Publication number
- CN111441499A CN111441499A CN202010306492.2A CN202010306492A CN111441499A CN 111441499 A CN111441499 A CN 111441499A CN 202010306492 A CN202010306492 A CN 202010306492A CN 111441499 A CN111441499 A CN 111441499A
- Authority
- CN
- China
- Prior art keywords
- concrete
- iron ore
- ore sand
- super
- wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/84—Walls made by casting, pouring, or tamping in situ
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Building Environments (AREA)
Abstract
Description
技术领域technical field
本发明涉及建筑混凝土墙浇筑的技术领域,尤其是涉及一种普通混凝土和铁矿砂混凝土超厚墙体交接结构及方法。The invention relates to the technical field of building concrete wall pouring, in particular to an ordinary concrete and iron ore concrete super-thick wall handover structure and method.
背景技术Background technique
目前,医院中的质子维护楼的浇筑墙体的厚度很大,分为普通混凝土墙和铁矿石混凝土墙,质子维护楼存在普通混凝土墙及铁矿石混凝土墙交接,其中普通混凝土墙厚3075mm,铁矿石混凝土墙厚2550mm。At present, the thickness of the poured walls of the proton maintenance building in the hospital is very large, and it is divided into ordinary concrete walls and iron ore concrete walls. There are ordinary concrete walls and iron ore concrete walls in the proton maintenance building. , The thickness of the iron ore concrete wall is 2550mm.
对于普通混凝土墙及铁矿石混凝土墙,由于二者材料不同,普通混凝土采用普通砂石制成,混凝土干密度约为2.3吨/每立方米;而铁矿石混凝土采用铁矿砂和铁矿石制成,干密度重达3.9吨/每立方米,约为普通混凝土的1.7倍。For ordinary concrete walls and iron ore concrete walls, due to their different materials, ordinary concrete is made of ordinary sand and gravel, and the dry density of concrete is about 2.3 tons per cubic meter; while iron ore concrete is made of iron ore and iron ore. It is made of stone, with a dry density of 3.9 tons per cubic meter, which is about 1.7 times that of ordinary concrete.
由于结构功能是用于质子放疗,会产生大量放射性粒子,混凝土必须满足防辐射要求,不能产生裂缝,因此两者交界处难以施工。Since the structural function is used for proton radiotherapy, a large amount of radioactive particles will be generated, and the concrete must meet the requirements of radiation protection and cannot produce cracks, so it is difficult to construct the junction between the two.
现有技术中存在的超厚墙体交接处采用以下方式:The super-thick wall junction existing in the prior art adopts the following methods:
1、分开浇筑两个墙体,这种方式存在以后问题:由于墙厚均超过2.5m,加上墙钢筋直径较大,分布密集,若两者分开浇筑,必会由于不同混凝土的不均匀收缩产生裂缝,影响结构防辐射效果。1. Two walls are separately poured. This method has future problems: because the wall thickness is more than 2.5m, and the diameter of the wall steel bars is large and densely distributed, if the two are poured separately, there will be uneven shrinkage of different concretes. Cracks occur, affecting the radiation protection effect of the structure.
2、直接同时浇筑普通混凝土和铁矿砂混凝土超厚墙体,这种方式存在以下问题:若同时浇筑,则会因为铁矿石混凝土密度较大,流入普通混凝土,导致两种混凝土糅合,无法保证结构的功能性。2. Directly pouring ordinary concrete and iron ore concrete super-thick walls at the same time has the following problems: if they are poured at the same time, due to the high density of iron ore concrete, it will flow into ordinary concrete, resulting in the mixing of the two kinds of concrete, which cannot be Ensure the functionality of the structure.
因此,有必要提出一种新的普通混凝土和铁矿砂混凝土超厚墙体交接结构,以解决结构整体性差导致防辐射效果不佳的技术问题。Therefore, it is necessary to propose a new super-thick wall interface structure of ordinary concrete and iron ore sand concrete to solve the technical problem of poor radiation protection due to poor structural integrity.
发明内容SUMMARY OF THE INVENTION
针对现有技术存在的不足,本发明的目的之一是提供一种普通混凝土和铁矿砂混凝土超厚墙体交接结构,解决了普通混凝土和铁矿石混凝土交接处施工难的问题,避免了分次浇筑产生的竖向施工缝,增加了结构的整体性及稳定性,提高了结构的防辐射性能,交接处的施工方法简便易行。Aiming at the deficiencies in the prior art, one of the objects of the present invention is to provide a common concrete and iron ore concrete super-thick wall joint structure, which solves the problem of difficult construction at the joint of common concrete and iron ore concrete, and avoids the The vertical construction joints produced by staged pouring increase the integrity and stability of the structure, improve the radiation protection performance of the structure, and the construction method at the junction is simple and easy to implement.
本发明的上述发明目的是通过以下技术方案得以实现的:The above-mentioned purpose of the present invention is achieved through the following technical solutions:
一种普通混凝土和铁矿砂混凝土超厚墙体交接结构,包括普通混凝土墙和铁矿砂混凝土墙,所述普通混凝土墙和铁矿砂混凝土墙的交接处设有的若干个防止浇筑时铁矿砂混凝土流向普通混凝土的阻流结构,所述阻流结构布满普通混凝土墙和铁矿砂混凝土墙的交接面。An ordinary concrete and iron ore sand concrete super-thick wall interface structure, including ordinary concrete wall and iron ore sand concrete wall, the junction of the ordinary concrete wall and iron ore sand concrete wall is provided with several anti-iron during pouring. The ore sand concrete flows to the blocking structure of the ordinary concrete, and the blocking structure is covered with the interface of the ordinary concrete wall and the iron ore sand concrete wall.
通过采用上述技术方案,在预浇筑的普通混凝土墙和铁矿砂混凝土墙的交接处布置上述阻流结构,可以防止较为重的铁矿砂混凝土流向较轻的普通混凝土内,两者可以同时浇筑,避免了分次浇筑产生的竖向施工缝,增加了结构的整体性及稳定性,提高了结构的防辐射性能。By adopting the above technical solution, the above-mentioned blocking structure is arranged at the junction of the pre-cast ordinary concrete wall and the iron ore concrete wall, which can prevent the heavier iron ore concrete from flowing into the lighter ordinary concrete, and the two can be poured at the same time. , to avoid the vertical construction joints produced by staged pouring, increase the integrity and stability of the structure, and improve the radiation protection performance of the structure.
本发明在一较佳示例中可以进一步配置为:所述阻流结构包括阻流板、固定所述阻流板的若干钢筋,所述钢筋固定在预浇筑墙体的钢筋笼网上。In a preferred example of the present invention, it can be further configured that: the flow blocking structure includes a flow blocking plate, a plurality of reinforcing bars for fixing the flow blocking plate, and the reinforcing bars are fixed on the steel cage net of the precast wall.
通过采用上述技术方案,阻流板可以防止较重的铁矿砂混凝土流向普通混凝土,钢筋用于加固阻流板,防止当较重的铁矿砂混凝土浇筑较快时,带来的侧压力对阻流板造成的冲击,损毁阻流板或者造成其移位。By adopting the above technical solution, the baffle plate can prevent the heavier iron ore concrete from flowing to the ordinary concrete, and the steel bars are used to reinforce the baffle plate to prevent the lateral pressure caused when the heavier iron ore concrete is poured quickly. Impact from the spoiler, which damages or displaces the spoiler.
本发明在一较佳示例中可以进一步配置为:所述阻流板包括阻流部以及设置在阻流部的两边侧的固定部。In a preferred example of the present invention, it can be further configured that: the baffle plate includes a baffle portion and a fixing portion disposed on both sides of the baffle portion.
通过采用上述技术方案,阻流部主要起到防止较重的铁矿砂混凝土流向普通混凝土的功能,固定部用于与钢筋的连接,保证了阻流板的连接牢固度。By adopting the above technical solution, the blocking part mainly plays the function of preventing the heavier iron ore concrete from flowing to the ordinary concrete, and the fixing part is used for connection with the steel bar, which ensures the connection firmness of the blocking plate.
本发明在一较佳示例中可以进一步配置为:所述阻流部上设有若干个快易收口。In a preferred example of the present invention, it can be further configured that: the flow blocking portion is provided with a plurality of quick and easy closing openings.
通过采用上述技术方案,快易收口可以使得12mm以下的钢筋稍微用力便可穿过,便于穿筋和连续捆扎钢筋。By adopting the above technical solution, the quick and easy closing can make the steel bars under 12mm pass through with a little force, which is convenient for piercing the steel bars and continuously bundling the steel bars.
本发明在一较佳示例中可以进一步配置为:所述固定部包括呈弯曲状、可卷绕在钢筋上的卷绕部以及相邻阻流板之间连接的搭接部。In a preferred example of the present invention, it can be further configured that: the fixing portion includes a curved portion that can be wound around the steel bar and a lap portion that connects adjacent spoilers.
通过采用上述技术方案,卷绕部用于将单个阻流板固定在钢筋上,搭接部用于相邻阻流板之间的连接,保证相邻阻流板之间的无缝连接,防止较重的铁矿砂混凝土通过缝隙流向普通混凝土。By adopting the above technical solution, the winding portion is used to fix a single spoiler on the steel bar, and the overlapping portion is used for the connection between adjacent spoilers to ensure the seamless connection between adjacent spoilers and prevent the The heavier iron ore concrete flows through the gaps to the normal concrete.
本发明在一较佳示例中可以进一步配置为:所述阻流部上设有至少一个定位槽,所述定位槽内卡设定钢筋。In a preferred example of the present invention, it can be further configured that: the blocking part is provided with at least one positioning groove, and the steel bar is clamped in the positioning groove.
通过采用上述技术方案,定位槽用于固定和定位阻流板,防止阻流板在普通混凝土和较重的铁矿砂混凝土在同时浇筑时,由于稍微的速度偏差,造成阻流板的移位。By adopting the above technical solution, the positioning groove is used to fix and locate the spoiler to prevent the spoiler from shifting due to a slight speed deviation when ordinary concrete and heavier iron ore concrete are poured at the same time. .
本发明在一较佳示例中可以进一步配置为:所述阻流板的厚度为1-2mm。In a preferred example of the present invention, it can be further configured that: the thickness of the spoiler is 1-2mm.
通过采用上述技术方案,阻流板的重量较轻,可直接固定在钢筋上,安装迅速运输方便,易于加工。By adopting the above technical solution, the spoiler is light in weight, can be directly fixed on the steel bars, is fast in installation, convenient in transportation, and easy in processing.
本发明在一较佳示例中可以进一步配置为:所述快易收口为5mm*5mm的方孔。In a preferred example of the present invention, it can be further configured that: the quick and easy closing mouth is a square hole of 5mm*5mm.
通过采用上述技术方案, 便于交接处的钢筋插入,使得整个阻流结构的安装更为便捷,省时省力。By adopting the above technical solution, the insertion of the reinforcing bars at the junction is facilitated, which makes the installation of the entire flow blocking structure more convenient and saves time and effort.
本发明在一较佳示例中可以进一步配置为:所述的阻流板的截面呈弓形,其内凹面朝向铁矿砂混凝土墙。In a preferred example of the present invention, it can be further configured that: the cross section of the baffle plate is arcuate, and its inner concave surface faces the iron ore sand concrete wall.
通过采用上述技术方案,在浇筑较重的铁矿砂混凝土时,弓形的阻流板首先能够对混凝土产生一定的缓冲,不至于使混凝土直接冲击阻流板。By adopting the above technical solution, when pouring heavier iron ore concrete, the bow-shaped spoiler can firstly buffer the concrete to prevent the concrete from directly impacting the spoiler.
本发明的另一目的在于,提供一种普通混凝土和铁矿砂混凝土超厚墙体交接处施工方法,包括以下步骤:Another object of the present invention is to provide a kind of ordinary concrete and iron ore concrete super thick wall junction construction method, comprising the following steps:
S1、在浇筑普通混凝土墙和铁矿砂混凝土墙之前,在两者的交接处,设置阻流结构,具体设置方法为:铺设上述阻流板,阻流板的内凹面朝向铁矿砂混凝土墙,阻流板的卷绕部卷绕在钢筋上,然后定位槽也卡接在有钢筋,钢筋通过捆扎的方式固定在钢筋笼网上,相邻两个阻流板通过各自的搭接部进行搭接,钢筋笼的横向钢筋穿过快易收口;S1. Before pouring the ordinary concrete wall and the iron ore concrete wall, set up a blocking structure at the junction of the two. The specific setting method is: laying the above blocking plate, and the inner concave surface of the blocking board faces the iron ore sand concrete wall. , the winding part of the spoiler is wound on the steel bar, and then the positioning groove is also clamped to the steel bar, the steel bar is fixed on the steel cage net by bundling, and the two adjacent spoilers are overlapped by their respective lap joints. The transverse reinforcement of the reinforcement cage passes through the quick and easy closing opening;
S2、固定好上述结构后,采取同时浇筑普通混凝土墙和铁矿砂混凝土墙的方式进行浇筑,一体成型。S2. After the above structure is fixed, the method of pouring the ordinary concrete wall and the iron ore concrete wall at the same time is used for pouring, and it is integrally formed.
综上所述,本发明包括以下至少一种有益技术效果:To sum up, the present invention includes at least one of the following beneficial technical effects:
解决了普通混凝土和铁矿石混凝土交接处施工难的问题,避免了分次浇筑产生的竖向施工缝,增加了结构的整体性及稳定性,提高了结构的防辐射性能;It solves the problem of difficult construction at the junction of ordinary concrete and iron ore concrete, avoids vertical construction joints caused by staged pouring, increases the integrity and stability of the structure, and improves the radiation protection performance of the structure;
结构简单、施工方便易行,可以同时进行普通混凝土墙和铁矿砂混凝土墙的浇筑,一次成型。The structure is simple, the construction is convenient and easy, and the pouring of the ordinary concrete wall and the iron ore concrete wall can be carried out at the same time, and it can be formed at one time.
附图说明Description of drawings
图1是本发明整体墙体俯视结构示意图。FIG. 1 is a schematic top view of the overall wall structure of the present invention.
图2是本发明普通混凝土墙和铁矿砂混凝土墙交接处的放大结构示意图。FIG. 2 is an enlarged structural schematic diagram of the junction of the ordinary concrete wall and the iron ore sand concrete wall of the present invention.
图3是本发明的阻流结构的示意图。FIG. 3 is a schematic diagram of the flow blocking structure of the present invention.
图4是本发明阻流板的截面结构示意图FIG. 4 is a schematic view of the cross-sectional structure of the spoiler of the present invention
图5是本发明的阻流板的平面视图。Figure 5 is a plan view of the spoiler of the present invention.
其中,图中标记如下:Among them, the marks in the figure are as follows:
1、普通混凝土墙,2、铁矿砂混凝土墙,3、阻流结构;1. Ordinary concrete wall, 2. Iron ore concrete wall, 3. Blocking structure;
31、阻流板,32、钢筋;31, spoiler, 32, steel bars;
311、阻流部,3111、快易收口,3112、定位槽,312、固定部,3121、卷绕部,3122、搭接。311, blocking part, 3111, quick and easy closing, 3112, positioning groove, 312, fixing part, 3121, winding part, 3122, lap joint.
具体实施方式Detailed ways
以下结合附图对本发明作进一步详细说明。The present invention will be further described in detail below with reference to the accompanying drawings.
参照图1和图2,为本实施例公开的一种普通混凝土和铁矿砂混凝土超厚墙体交接结构,包括普通混凝土墙1和铁矿砂混凝土墙2,在普通混凝土墙1和铁矿砂混凝土墙2的交接处设有的若干个防止浇筑时铁矿砂混凝土流向普通混凝土的阻流结构3,所述阻流结构3布满普通混凝土墙2和铁矿砂混凝土墙3的交接面。阻流结构3,可以防止较为重的铁矿砂混凝土流向较轻的普通混凝土内,两者可以同时浇筑,避免了分次浇筑产生的竖向施工缝,增加了结构的整体性及稳定性,提高了结构的防辐射性能。1 and 2, the present embodiment discloses a common concrete and iron ore concrete ultra-thick wall interface structure, including common
参照图3,为了进一步加固阻流结构3,所述阻流结构包括阻流板31、固定所述阻流板31的若干钢筋32,所述钢筋32固定在预浇筑墙体的钢筋笼网上,阻流板31可以防止较重的铁矿砂混凝土流向普通混凝土,钢筋用于加固阻流板31,防止当较重的铁矿砂混凝土浇筑较快时,带来的侧压力对阻流板31造成的冲击,损毁阻流板31或者造成其移位。3, in order to further strengthen the blocking
参照图4,为了进一步固定阻流板31,所述阻流板31包括阻流部311以及设置在阻流部311的两边侧的固定部312。固定部312包括呈弯曲状、可卷绕在钢筋32上的卷绕部3121以及相邻阻流板31之间连接的搭接部3122。卷绕部3121用于将单个阻流板31固定在钢筋32上,搭接部3122用于相邻阻流板31之间的连接,保证相邻阻流板31之间的无缝连接,防止较重的铁矿砂混凝土通过缝隙流向普通混凝土。Referring to FIG. 4 , in order to further fix the
阻流部311上设有至少一个定位槽3112,定位槽3112内卡钢筋32,进一步加固了阻流板31。其中,阻流板31的厚度为1-2mm,阻流板31的重量较轻,可直接固定在钢筋上,安装迅速运输方便,易于加工,为了实现上述目的,本实施例所采用的阻流板的厚度为1mm。The blocking
作为优选的,快易收口3111为5mm*5mm的方孔,快易收口3111可以使得12mm以下的钢筋稍微用力便可穿过,便于穿筋和连续捆扎钢筋。其中,阻流板31的截面呈弓形,其内凹面朝向铁矿砂混凝土墙2,在浇筑较重的铁矿砂混凝土时,弓形的阻流板31首先能够对混凝土产生一定的缓冲,不至于使混凝土直接冲击阻流板31。Preferably, the quick and
参照图5,为了便于插设横向钢筋,所述阻流部311上设有若干个快易收口3111。Referring to FIG. 5 , in order to facilitate the insertion of transverse steel bars, the blocking
本实施例的工作原理为:通过在预浇筑普通混凝土墙1和铁矿砂混凝土墙2之间设置阻流结构3,在进行同时浇筑时,能够防止铁矿砂混凝土流向普通混凝土,实现同时浇筑,保证了墙体的结构稳定性,提高了墙体的防辐射效果。The working principle of the present embodiment is as follows: by setting the blocking
本实施例的另一个方面,提供了一种普通混凝土和铁矿砂混凝土超厚墙体交接处施工方法,包括以下步骤:Another aspect of the present embodiment provides a method for constructing a joint between ordinary concrete and iron ore concrete super-thick wall, comprising the following steps:
在浇筑普通混凝土墙1和铁矿砂混凝土墙2之前,在两者的交接处,设置阻流结构3,具体设置方法为:先铺设上述阻流板31,阻流板31的卷绕部3121卷绕在钢筋32上,然后定位槽3112也卡接在有钢筋32,对阻流板31进一步固定,钢筋32通过捆扎的方式固定在钢筋笼网上,相邻两个阻流板31通过各自的搭接部3122进行搭接,避免产生缝隙,钢筋笼的横向钢筋穿过快易收口3111,固定好上述结构后,采取同时浇筑普通混凝土墙1和铁矿砂混凝土墙2的方式进行浇筑,墙体一体成型,其中的阻流结构3可以横向布置,也可纵向布置,整个施工方法简便易行。Before pouring the ordinary
本具体实施方式的实施例均为本发明的较佳实施例,并非依此限制本发明的保护范围,故:凡依本发明的结构、形状、原理所做的等效变化,均应涵盖于本发明的保护范围之内。The embodiments of this specific embodiment are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore: all equivalent changes made according to the structure, shape and principle of the present invention should be covered in within the protection scope of the present invention.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010306492.2A CN111441499A (en) | 2020-04-17 | 2020-04-17 | Joint structure and method for common concrete and iron ore sand concrete super-thick wall |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010306492.2A CN111441499A (en) | 2020-04-17 | 2020-04-17 | Joint structure and method for common concrete and iron ore sand concrete super-thick wall |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN111441499A true CN111441499A (en) | 2020-07-24 |
Family
ID=71656024
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202010306492.2A Pending CN111441499A (en) | 2020-04-17 | 2020-04-17 | Joint structure and method for common concrete and iron ore sand concrete super-thick wall |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN111441499A (en) |
Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2008014047A (en) * | 2006-07-06 | 2008-01-24 | Okumura Corp | Beam-column joint structure and construction method thereof |
| CN201162343Y (en) * | 2008-03-03 | 2008-12-10 | 南通华新建工集团有限公司 | Quickly and easily closing net template |
| CN101498172A (en) * | 2008-02-03 | 2009-08-05 | 汤卫华 | Fast easy-to-closing in net stencil |
| CN101761187A (en) * | 2010-02-08 | 2010-06-30 | 龙元建设集团股份有限公司 | Construction separating device for concrete of vertical structure in same wall body with different labels as well as pouring and tamping method thereof |
| CN103938870A (en) * | 2014-03-27 | 2014-07-23 | 焦作建工集团有限公司 | Lightweight concrete and normal concrete synchronously-pouring method |
| CN204552084U (en) * | 2015-04-16 | 2015-08-12 | 中天建设集团有限公司天津分公司 | A kind of formwork structure of concrete construction joint |
| CN110777983A (en) * | 2019-11-12 | 2020-02-11 | 中国新兴建筑工程有限责任公司 | Synchronous construction structure and method for concrete filled wall and cast-in-place structure |
| CN212453181U (en) * | 2020-04-17 | 2021-02-02 | 中建一局集团第一建筑有限公司 | An ordinary concrete and iron ore sand concrete super-thick wall interface structure |
-
2020
- 2020-04-17 CN CN202010306492.2A patent/CN111441499A/en active Pending
Patent Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2008014047A (en) * | 2006-07-06 | 2008-01-24 | Okumura Corp | Beam-column joint structure and construction method thereof |
| CN101498172A (en) * | 2008-02-03 | 2009-08-05 | 汤卫华 | Fast easy-to-closing in net stencil |
| CN201162343Y (en) * | 2008-03-03 | 2008-12-10 | 南通华新建工集团有限公司 | Quickly and easily closing net template |
| CN101761187A (en) * | 2010-02-08 | 2010-06-30 | 龙元建设集团股份有限公司 | Construction separating device for concrete of vertical structure in same wall body with different labels as well as pouring and tamping method thereof |
| CN103938870A (en) * | 2014-03-27 | 2014-07-23 | 焦作建工集团有限公司 | Lightweight concrete and normal concrete synchronously-pouring method |
| CN204552084U (en) * | 2015-04-16 | 2015-08-12 | 中天建设集团有限公司天津分公司 | A kind of formwork structure of concrete construction joint |
| CN110777983A (en) * | 2019-11-12 | 2020-02-11 | 中国新兴建筑工程有限责任公司 | Synchronous construction structure and method for concrete filled wall and cast-in-place structure |
| CN212453181U (en) * | 2020-04-17 | 2021-02-02 | 中建一局集团第一建筑有限公司 | An ordinary concrete and iron ore sand concrete super-thick wall interface structure |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102635118A (en) | Square steel pipe concrete supporting structure for foundation pit support | |
| CN106400799A (en) | Cast-in-situ dado structure for manually excavated pile and construction method | |
| WO2021023245A1 (en) | Pile slab-type soil retaining wall integral casting formwork structure and construction method therefor | |
| CN114411945A (en) | Bin jump construction method based on BIM technology | |
| KR101625995B1 (en) | Precast deck and slab having the same | |
| CN209760544U (en) | Floor slab with overhanging rectangular ribs and shear wall structure | |
| CN111335355A (en) | Special-shaped block post-pouring type light retaining wall supporting structure and construction method thereof | |
| CN111441499A (en) | Joint structure and method for common concrete and iron ore sand concrete super-thick wall | |
| CN212453181U (en) | An ordinary concrete and iron ore sand concrete super-thick wall interface structure | |
| CN215330742U (en) | A formwork-free fabricated steel truss-recycled concrete composite shear wall | |
| CN209443637U (en) | A kind of precast floor slab | |
| CN207363074U (en) | A kind of connection structure of prefabricated regeneration monolith plate and composite beam | |
| CN106939586B (en) | A faceplate structure of a concrete face rockfill dam | |
| CN218643534U (en) | Assembly type hybrid beam with steel pipe concrete structure as connecting node | |
| CN206873734U (en) | With the prefabricated shear wall and overlapping plate node of Combined grouting sleeve connection | |
| CN115341714A (en) | Fabricated hybrid beam with steel pipe concrete structure as connecting node and method | |
| CN210134346U (en) | An ultra-high performance bridge deck structure | |
| CN107988872A (en) | Assembled temporary road plate | |
| CN207314561U (en) | Ultra-high performance concrete plate seam connection structure | |
| CN219568938U (en) | Pit-in-pit variable-section raft inclined plane reinforcing steel bar positioning structure | |
| CN207077584U (en) | Cross celluar concrete stake template | |
| CN106703196B (en) | Interior ring type steel tube regeneration monolith assembling structure | |
| CN117868370B (en) | Prefabricated H-shaped groove recycled concrete floor slab and construction method thereof | |
| CN206646646U (en) | Interior ring type steel tube regeneration monolith assembling structure | |
| CN205400120U (en) | A reinforced structure for reinforcing concrete post roof beam |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200724 |