CN111424869A - Concrete floor secondary beam combined prefabricated part and manufacturing method - Google Patents

Concrete floor secondary beam combined prefabricated part and manufacturing method Download PDF

Info

Publication number
CN111424869A
CN111424869A CN202010238752.7A CN202010238752A CN111424869A CN 111424869 A CN111424869 A CN 111424869A CN 202010238752 A CN202010238752 A CN 202010238752A CN 111424869 A CN111424869 A CN 111424869A
Authority
CN
China
Prior art keywords
prefabricated
slab
concrete
steel
concrete slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010238752.7A
Other languages
Chinese (zh)
Inventor
刘学春
杜胜权
邓玉萍
邓刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing University of Technology
Original Assignee
Beijing University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing University of Technology filed Critical Beijing University of Technology
Priority to CN202010238752.7A priority Critical patent/CN111424869A/en
Publication of CN111424869A publication Critical patent/CN111424869A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/02Load-carrying floor structures formed substantially of prefabricated units
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B13/00Feeding the unshaped material to moulds or apparatus for producing shaped articles; Discharging shaped articles from such moulds or apparatus
    • B28B13/02Feeding the unshaped material to moulds or apparatus for producing shaped articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/02Load-carrying floor structures formed substantially of prefabricated units
    • E04B5/10Load-carrying floor structures formed substantially of prefabricated units with metal beams or girders, e.g. with steel lattice girders

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

本发明公开了一种混凝土楼板次梁组合预制构件和制作方法,其中预制构件包括:预制混凝土板和H型钢次梁,预制混凝土板由混凝土浇筑而成;H型钢次梁的钢梁上翼缘上表面焊接有栓钉,栓钉埋置于预制混凝土板的下表面。通过本发明的技术方案,组合预制构件整体吊装,通过预留钢筋组装成整体并与结构主梁连接,通过少量的现浇混凝土形成整体楼板体系,减少了现场支模的繁琐工序,避免现场浇筑混凝土,楼板次梁组合预制构件的强度和刚度显著提高,楼板不会在吊装时因自重影响发生破坏,提高了构件的整体性能。

Figure 202010238752

The invention discloses a composite prefabricated component of a concrete floor sub-beam and a manufacturing method, wherein the prefabricated component comprises: a prefabricated concrete slab and an H-shaped steel secondary beam, the prefabricated concrete slab is formed by pouring concrete; the upper surface of the upper flange of the steel beam of the H-shaped steel secondary beam The studs are welded, and the studs are embedded in the lower surface of the precast concrete slab. Through the technical scheme of the present invention, the combined prefabricated components are hoisted as a whole, assembled into a whole by reserved steel bars and connected with the main beam of the structure, and a small amount of cast-in-place concrete is used to form an integral floor system, which reduces the tedious process of on-site formwork and avoids on-site pouring. The strength and rigidity of the concrete and floor sub-beam composite prefabricated components are significantly improved, the floor will not be damaged due to the influence of its own weight during hoisting, and the overall performance of the components is improved.

Figure 202010238752

Description

混凝土楼板次梁组合预制构件和制作方法Concrete floor sub-beam composite prefabricated member and fabrication method

技术领域technical field

本发明涉及建筑结构技术领域,尤其涉及一种混凝土楼板次梁组合预制构件和一种混凝土楼板次梁组合预制构件的制作方法。The invention relates to the technical field of building structures, in particular to a concrete floor sub-beam composite prefabricated component and a manufacturing method of a concrete floor sub-beam composite prefabricated component.

背景技术Background technique

目前,钢框架受水平力作用时,钢预制构件主梁所受到的最大弯矩为支座处的负弯矩,支座截面处,上部受拉,下部受压。由于混凝土的受拉能力较小,且板内配置的钢筋无法承受这个拉力,所以在做钢框架的强柱弱梁设计时,不考虑预制构件主梁与楼板的组合作用,节点处的负弯矩全部由预制构件主梁承担。但是在传统的现浇混凝土楼板中,楼板的混凝土及钢筋会承担部分负弯矩,板确实与预制构件主梁有一定的组合作用,所以在地震发生时,一般发生的破坏为强梁弱柱的破坏。At present, when the steel frame is subjected to a horizontal force, the maximum bending moment of the main beam of the steel prefabricated member is the negative bending moment at the support. At the cross-section of the support, the upper part is tensioned and the lower part is compressed. Since the tensile capacity of concrete is small, and the steel bars arranged in the slab cannot bear this tensile force, when designing the strong column and weak beam of the steel frame, the combined effect of the main beam of the prefabricated member and the floor slab is not considered, and the negative bending at the node is not considered. The moment is all borne by the main beam of the prefabricated member. However, in the traditional cast-in-place concrete floor, the concrete and steel bars of the floor will bear part of the negative bending moment, and the slab does have a certain combined effect with the main beam of the prefabricated member, so when an earthquake occurs, the damage that generally occurs is that of strong beams and weak columns. destroy.

传统的现浇楼板,楼板与次梁可以实现无应力下组合,但是作为现浇结构,楼板与次梁有应力下的组合,组合作用弱,考虑组合不安全,导致次梁截面高,挠度大。而且现浇现场支模工序繁琐,混凝土养护条件有限制,容易产生环境污染。The traditional cast-in-place floor, the floor and the secondary beam can be combined without stress, but as a cast-in-place structure, the floor and the secondary beam are combined under stress, and the combined effect is weak. Considering the combination is unsafe, the secondary beam has a high section and large deflection. . In addition, the cast-in-place formwork support process is cumbersome, and the concrete curing conditions are limited, which is prone to environmental pollution.

发明内容SUMMARY OF THE INVENTION

针对上述问题中的至少之一,本发明提供了一种混凝土楼板次梁组合预制构件和制作方法,通过预制混凝土板与H型钢次梁采用工厂化预制技术,减少现场支模的繁琐工序,避免现场浇筑混凝土过多,钢梁与混凝土在无应力下形成可靠的组合作用,使钢梁强度和刚度显著提高,楼板不会在吊装时因自重影响发生破坏,由于预留板缝及外伸钢筋的连接作用,使之平面内成为一个整体,提高了构件的整体性能。Aiming at at least one of the above problems, the present invention provides a concrete floor sub-beam composite prefabricated component and a manufacturing method. By adopting factory prefabrication technology for the prefabricated concrete slab and the H-shaped steel sub-beam, the tedious process of on-site formwork is reduced, avoiding the need for Too much concrete is poured on site, and the steel beam and concrete form a reliable combination without stress, which significantly improves the strength and stiffness of the steel beam, and the floor slab will not be damaged due to the influence of its own weight during hoisting. The connection function makes it a whole in the plane and improves the overall performance of the component.

为实现上述目的,本发明提供了一种混凝土楼板次梁组合预制构件,包括:预制混凝土板和H型钢次梁,所述预制混凝土板由混凝土浇筑而成;所述H型钢次梁的钢梁上翼缘上表面焊接有栓钉,所述栓钉埋置于所述预制混凝土板的下表面。In order to achieve the above purpose, the present invention provides a concrete floor sub-beam composite prefabricated component, including: a prefabricated concrete slab and an H-shaped steel secondary beam, the prefabricated concrete slab is formed by pouring concrete; the steel beam upper wing of the H-shaped steel secondary beam The upper surface of the edge is welded with studs, and the studs are embedded in the lower surface of the precast concrete slab.

在上述技术方案中,优选地,所述栓钉完全预埋于所述预制混凝土板中且所述预制混凝土板的下表面与所述钢梁上翼缘的上支承面齐平;所述钢梁上翼缘的两端与所述预制混凝土板的边缘齐平,所述H型钢次梁的钢梁腹板两端开设螺栓孔,所述钢梁腹板与预制构件主梁通过主次梁连接板相连,并通过高强螺栓固定于所述钢梁腹板的螺栓孔中。In the above technical solution, preferably, the studs are completely embedded in the precast concrete slab and the lower surface of the precast concrete slab is flush with the upper bearing surface of the upper flange of the steel beam; the upper flange of the steel beam Both ends of the steel beam are flush with the edge of the prefabricated concrete slab, bolt holes are provided at both ends of the steel beam web of the H-shaped steel secondary beam, and the steel beam web is connected to the main beam of the prefabricated member through the primary and secondary beam connecting plates. and fixed in the bolt holes of the steel beam web by high-strength bolts.

在上述技术方案中,优选地,所述预制混凝土板沿跨度方向的边缘设置为两层台阶结构,使得所述预制混凝土板沿跨度方向的板面相接处下层台阶边缘相接、上层台阶边缘间形成板缝,以进一步浇筑混凝土形成混凝土连接部;所述预制混凝土板的上部沿板面方向横纵双向布设板面钢筋,沿跨度方向的所述板面钢筋两端伸出所述预制混凝土板边缘并超出下层台阶边缘,沿垂直于跨度方向的所述板面钢筋两端与所述预制混凝土板的下层台阶边缘对齐,所述预制混凝土板的下部沿板面方向横纵双向布设板底钢筋,沿跨度方向的所述板底钢筋两端与所述预制混凝土板的下层台阶边缘对齐,沿横向跨度方向的所述板底钢筋两端伸出所述预制混凝土板边缘。In the above technical solution, preferably, the edge of the precast concrete slab along the span direction is set as a two-layer stepped structure, so that the edge of the lower step and the edge of the upper step are connected where the board surfaces of the precast concrete slab meet along the span direction. A slab gap is formed between the slabs to further pour concrete to form a concrete connection part; the upper part of the precast concrete slab is arranged with slab reinforcement along the slab surface horizontally, vertically and in both directions, and the two ends of the slab reinforcement along the span direction protrude from the precast concrete. The edge of the slab extends beyond the edge of the lower step, and the two ends of the slab surface reinforcement perpendicular to the span direction are aligned with the edge of the lower step of the precast concrete slab, and the bottom of the prefabricated concrete slab is arranged horizontally and vertically along the slab surface direction. Steel bars, the two ends of the bottom steel bars along the span direction are aligned with the edge of the lower step of the precast concrete slab, and the two ends of the bottom steel bars along the transverse span direction protrude from the edge of the precast concrete slab.

在上述技术方案中,优选地,所述H型钢次梁的所述钢梁腹板上开孔,以穿过管线。In the above technical solution, preferably, holes are opened on the steel beam web of the H-shaped steel secondary beam to pass through the pipeline.

在上述技术方案中,优选地,所述预制构件主梁的上表面焊接有栓钉,所述预制构件主梁的上下翼缘之间焊接有边缘齐平的加劲肋,所述H型钢次梁的钢梁腹板与所述预制构件主梁的上翼缘和加劲肋对齐,并通过所述主次梁连接板将所述钢梁腹板和所述加劲肋固定连接。In the above technical solution, preferably, the upper surface of the main beam of the prefabricated member is welded with studs, the upper and lower flanges of the main beam of the prefabricated member are welded with stiffeners with flush edges, and the H-shaped steel secondary beam is welded. The steel beam web is aligned with the upper flange of the prefabricated main beam and the stiffener, and the steel beam web and the stiffener are fixedly connected through the primary and secondary beam connecting plates.

在上述技术方案中,优选地,所述板面钢筋和所述板底钢筋伸出所述预制混凝土板边缘的部分不小于50毫米。In the above technical solution, preferably, the part of the slab surface reinforcement and the slab bottom reinforcement extending beyond the edge of the precast concrete slab is not less than 50 mm.

本发明还提出一种混凝土楼板次梁组合预制构件,相比于上述技术方案中任一项所述的混凝土楼板次梁组合预制构件:所述H型钢次梁的钢梁上翼缘不设置栓钉,所述钢梁上翼缘以及所述H型钢次梁的钢梁腹板的上半部分预埋入所述预制混凝土板中。The present invention also provides a concrete floor sub-beam composite prefabricated component, compared with the concrete floor sub-beam composite prefabricated component described in any one of the above technical solutions: the upper flange of the steel beam of the H-shaped steel sub-beam is not provided with studs, The upper flange of the steel beam and the upper half of the steel beam web of the H-shaped steel secondary beam are pre-embedded in the precast concrete slab.

在上述技术方案中,优选地,所述H型钢次梁的所述钢梁腹板上部两侧焊接附加钢筋,所述钢梁上翼缘两端伸出所述预制混凝土板的边缘,伸出部分搭设于所述预制构件的主梁上。In the above technical solution, preferably, additional reinforcing bars are welded on both sides of the upper part of the steel beam web of the H-shaped steel secondary beam, the two ends of the upper flange of the steel beam protrude from the edge of the precast concrete slab, and the protruding part is erected on the main beam of the prefabricated member.

本发明还提出一种混凝土楼板次梁组合预制构件的制作方法,应用于如上述技术方案中任一项所述的混凝土楼板次梁组合预制构件,包括:确定混凝土板预制模板的位置,以预制混凝土板的上表面朝下的方向安装所述混凝土板预制模板;在所述混凝土板预制模板内浇筑混凝土的同时在预设位置插放H型钢次梁以形成所述预制混凝土板。The present invention also provides a method for making a concrete floor sub-beam composite prefabricated member, which is applied to the concrete floor sub-beam composite prefabricated member according to any one of the above technical solutions. The prefabricated formwork of the concrete slab is installed with the upper surface of the concrete slab facing downward; while the concrete is poured in the prefabricated concrete slab formwork, the H-shaped steel secondary beam is inserted at a preset position to form the prefabricated concrete slab.

在上述技术方案中,优选地,所述预制混凝土板按照预设位置与预制构件主梁固定或搭接,所述预制混凝土板之间相互拼接并在所述预制混凝土板相接处的板缝间浇筑混凝土,在所述预制构件主梁与立柱相连接处浇筑混凝土,形成板面平齐的组合预制构件。In the above technical solution, preferably, the prefabricated concrete slabs are fixed or overlapped with the main beams of the prefabricated components according to a preset position, the prefabricated concrete slabs are spliced with each other and the slab joints of the prefabricated concrete slabs Concrete is poured between, and concrete is poured at the connection between the main beam of the prefabricated component and the column to form a combined prefabricated component with a flush plate surface.

与现有技术相比,本发明的有益效果为:Compared with the prior art, the beneficial effects of the present invention are:

1)本发明对组合预制构件中的预制混凝土板和H型钢次梁采用工厂化预制技术,在工厂内整体预制、整体吊装,楼板可以做到很大跨度,减少现场支模的繁琐工序,避免了现场浇筑混凝土,这样既可以改善混凝土养护条件,又可以减少环境污染。1) The present invention adopts factory prefabrication technology for prefabricated concrete slabs and H-shaped steel secondary beams in combined prefabricated components, which are prefabricated and hoisted as a whole in the factory. Concrete is poured on site, which can not only improve concrete curing conditions, but also reduce environmental pollution.

2)由于在工厂预制组合预制构件,混凝土的施工速度和质量可以大大提高,钢梁与混凝土在无应力下形成可靠的组合作用,组合作用强,在相同外荷载作用下,使钢梁强度和刚度显著提高。混凝土结硬之前处于施工阶段的楼板及次梁的挠度问题,可以通过增加预制板块尺寸或者利用反拱作用,达到施工阶段及正常使用阶段的挠度要求。钢梁腹板开有孔洞,方便管线铺设,可以解决全预制楼板不好预埋管线的问题,还可以有效地减轻自重,节省钢材用料。2) Due to the prefabrication of prefabricated components in the factory, the construction speed and quality of concrete can be greatly improved. The steel beam and concrete form a reliable combination under no stress, and the combination is strong. Under the same external load, the strength of the steel beam and Stiffness is significantly improved. For the deflection problem of the floor slab and the secondary beam in the construction stage before the concrete hardens, the deflection requirements of the construction stage and the normal use stage can be achieved by increasing the size of the prefabricated slab or using the reverse arch effect. There are holes in the web of the steel beam, which is convenient for pipeline laying, which can solve the problem that the fully prefabricated floor is not good for pre-embedding pipelines, and can also effectively reduce the self-weight and save steel materials.

3)现场进行吊装,在没有次梁时,较大的纯混凝土楼板中间没有支撑,吊装时容易被破坏。而本发明有次梁支撑时,楼板不会在吊装时因自重影响发生破坏,在预制混凝土板的连接处浇筑少量混凝土,由于预留凹槽及外伸钢筋的连接作用,使之平面内成为一个整体,平面外能承担一部分弯矩,提高构件的整体性能。3) On-site hoisting, when there is no secondary beam, there is no support in the middle of the larger pure concrete floor, which is easily damaged during hoisting. When the present invention is supported by secondary beams, the floor slab will not be damaged due to the influence of its own weight during hoisting, and a small amount of concrete is poured at the connection of the precast concrete slab. As a whole, it can bear part of the bending moment out of plane, and improve the overall performance of the component.

4)无论是H型钢次梁依靠栓钉与预制混凝土板连接还是钢梁上翼缘及腹板上半部分埋入预制混凝土板中,都可以形成良好的组合作用,混凝土可以帮助次梁上翼缘受压,由此可以减少钢次梁上翼缘的尺寸,同时减小楼板次梁组合预制构件的高度,为建筑提供更高的空间。4) Whether the H-beam secondary beam is connected to the precast concrete slab by means of studs or the upper flange of the steel beam and the half part of the web are embedded in the precast concrete slab, a good combined effect can be formed, and the concrete can help the upper flange of the secondary beam to be compressed, As a result, the size of the upper flange of the steel secondary beam can be reduced, and the height of the composite prefabricated component of the floor slab secondary beam can be reduced to provide a higher space for the building.

5)楼板在主梁与立柱连接的区域由于后浇混凝土,主梁与楼板没有形成良好的组合作用,主梁的截面抵抗矩较小,有利于保证强柱弱梁的机制。但楼板与次梁有良好的组合作用,并且次梁与主梁有可靠的连接,即使楼板与主梁没有良好的组合作用,楼板也不会脱落,这样很好的保证了该装配框架体系良好的抗震的性能。5) In the area where the main beam and the column are connected to the floor slab, the main beam and the floor slab do not form a good combination due to the post-cast concrete, and the cross-sectional resistance moment of the main beam is small, which is conducive to ensuring the mechanism of strong columns and weak beams. However, the floor slab and the secondary beam have a good combination effect, and the secondary beam and the main beam have a reliable connection. Even if the floor slab and the main beam do not have a good combination effect, the floor slab will not fall off, which ensures a good assembly frame system. seismic performance.

附图说明Description of drawings

图1为本发明一种实施例公开的混凝土楼板次梁组合预制构件的整体拼接结构示意图;1 is a schematic diagram of the overall splicing structure of a concrete floor sub-beam composite prefabricated member disclosed in an embodiment of the present invention;

图2为本发明一种实施例公开的预制混凝土板-H型钢次梁结构件的结构示意图;2 is a schematic structural diagram of a precast concrete slab-H-shaped steel secondary beam structural member disclosed in an embodiment of the present invention;

图3为本发明另一种实施例公开的预制混凝土板-H型钢次梁结构件的结构示意图;3 is a schematic structural diagram of a precast concrete slab-H-shaped steel secondary beam structural member disclosed in another embodiment of the present invention;

图4为图2所示实施例公开的预制构件主梁与次梁的连接形式示意图;4 is a schematic diagram of the connection form of the main beam and the secondary beam of the prefabricated member disclosed in the embodiment shown in FIG. 2;

图5为图3所示实施例公开的预制构件主梁与次梁的连接形式示意图;5 is a schematic diagram of the connection form of the main beam and the secondary beam of the prefabricated member disclosed in the embodiment shown in FIG. 3;

图6为本发明一种实施例公开的预制构件与预制构件主梁的搭接结构示意图;6 is a schematic diagram of the overlapping structure of a prefabricated component and a main beam of the prefabricated component disclosed in an embodiment of the present invention;

图7为图2所示实施例公开的预制混凝土板长边与预制构件主梁的搭接结构剖面图;7 is a cross-sectional view of the overlapping structure of the long side of the precast concrete slab and the main beam of the precast member disclosed in the embodiment shown in FIG. 2;

图8为图3所示实施例公开的预制混凝土板长边与预制构件主梁的搭接结构剖面图;8 is a cross-sectional view of the overlapping structure of the long side of the precast concrete slab and the main beam of the precast member disclosed in the embodiment shown in FIG. 3;

图9为图2所示实施例公开的预制混凝土板短边与预制构件主梁的搭接结构剖面图;9 is a cross-sectional view of the overlapping structure of the short side of the precast concrete slab and the main beam of the precast member disclosed in the embodiment shown in FIG. 2;

图10为图3所示实施例公开的预制混凝土板短边与预制构件主梁的搭接结构剖面图。FIG. 10 is a cross-sectional view of the overlapping structure of the short side of the precast concrete slab and the main beam of the precast member disclosed in the embodiment shown in FIG. 3 .

图中,各组件与附图标记之间的对应关系为:In the figure, the corresponding relationship between each component and the reference sign is:

1.预制混凝土板,2.H型钢次梁,3.预制构件主梁,4.板面钢筋,5.板底钢筋,6.栓钉,7.主次梁连接板,8.主梁柱连接板,9.高强螺栓,10.附加钢筋,11.立柱。1. Precast concrete slab, 2. H-beam secondary beam, 3. Precast member main beam, 4. Slab surface reinforcement, 5. Slab bottom reinforcement, 6. Stud, 7. Primary and secondary beam connecting plate, 8. Main beam column Connecting plate, 9. High-strength bolts, 10. Additional reinforcing bars, 11. Upright columns.

具体实施方式Detailed ways

为使本发明实施例的目的、技术方案和优点更加清楚,下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明的一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动的前提下所获得的所有其他实施例,都属于本发明保护的范围。In order to make the purposes, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments These are some embodiments of the present invention, but not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative work fall within the protection scope of the present invention.

下面结合附图对本发明做进一步的详细描述:Below in conjunction with accompanying drawing, the present invention is described in further detail:

如图1所示,根据本发明提供的一种混凝土楼板次梁组合预制构件,包括:预制混凝土板1和H型钢次梁2,所述预制混凝土板由混凝土浇筑而成;所述H型钢次梁的钢梁上翼缘上表面焊接有栓钉,所述栓钉埋置于所述预制混凝土板的下表面。As shown in FIG. 1 , a concrete floor sub-beam composite prefabricated component provided according to the present invention includes: a prefabricated concrete slab 1 and an H-shaped steel secondary beam 2, wherein the prefabricated concrete slab is formed by pouring concrete; the H-shaped steel sub-beam The upper surface of the upper flange of the steel beam of the beam is welded with studs, and the studs are embedded in the lower surface of the precast concrete slab.

在该实施例中,通过对预制混凝土板1与H型钢次梁2采用工厂化预制技术,减少现场支模的繁琐工序,避免现场浇筑混凝土过多,钢梁与混凝土在无应力下形成可靠的组合作用,使钢梁强度和刚度显著提高,楼板不会在吊装时因自重影响发生破坏,提高了构件的整体性能。混凝土结硬之前处于施工阶段的楼板及次梁的挠度问题,可以通过增加预制混凝土板1的尺寸或者利用反拱作用,达到施工阶段及正常使用阶段的挠度要求。现场进行吊装,在没有次梁时,较大的纯混凝土楼板中间没有支撑,吊装时容易被破坏。而有次梁支撑时,楼板不会在吊装时因自重影响发生破坏。In this embodiment, by adopting the factory prefabrication technology for the precast concrete slab 1 and the H-shaped steel secondary beam 2, the tedious process of on-site formwork support is reduced, and excessive concrete pouring on site is avoided, and the steel beam and the concrete form a reliable connection under no stress. Combined action, the strength and stiffness of the steel beams are significantly improved, the floor will not be damaged due to the influence of its own weight during hoisting, and the overall performance of the components is improved. For the deflection problem of the floor slab and the secondary beam in the construction stage before the concrete hardens, the deflection requirements of the construction stage and the normal use stage can be achieved by increasing the size of the precast concrete slab 1 or using the reverse arch effect. On-site hoisting, when there is no secondary beam, there is no support in the middle of the larger pure concrete floor slab, which is easily damaged during hoisting. When supported by secondary beams, the floor slab will not be damaged due to its own weight during hoisting.

如图2所示,上述实施例中H型钢次梁2与预制混凝土板1的连接方案一具体包括:As shown in FIG. 2 , the connection scheme 1 of the H-shaped steel secondary beam 2 and the precast concrete slab 1 in the above embodiment specifically includes:

H型钢次梁2的钢梁上翼缘上支承面焊接有两排栓钉6,栓钉6高度优选为12毫米,栓钉6预埋入预制混凝土板1内,预制混凝土板1的下表面与钢梁上翼缘的上支承面齐平,钢梁上翼缘两端与预制混凝土板1的边缘齐平。Two rows of studs 6 are welded on the supporting surface of the upper flange of the steel beam of the H-shaped steel secondary beam 2. The height of the studs 6 is preferably 12 mm. The studs 6 are pre-embedded in the precast concrete slab 1. The upper bearing surface of the upper flange of the beam is flush, and both ends of the upper flange of the steel beam are flush with the edge of the precast concrete slab 1 .

在上述实施例中,优选地,栓钉6完全预埋于预制混凝土板1中且预制混凝土板1的下表面与钢梁上翼缘的上支承面齐平;钢梁上翼缘的两端与预制混凝土板1的边缘齐平,H型钢次梁2的钢梁腹板两端开设螺栓孔,钢梁腹板与预制构件主梁3通过主次梁连接板7相连,并通过高强螺栓9固定于钢梁腹板的螺栓孔中。具体地,预制构件主梁3的上表面焊接有栓钉6,预制构件主梁3的上下翼缘之间焊接有边缘齐平的加劲肋,H型钢次梁2的钢梁腹板与预制构件主梁3的上翼缘和加劲肋对齐,并通过主次梁连接板7将钢梁腹板和加劲肋固定连接。In the above embodiment, preferably, the studs 6 are completely embedded in the precast concrete slab 1 and the lower surface of the precast concrete slab 1 is flush with the upper bearing surface of the upper flange of the steel beam; both ends of the upper flange of the steel beam are flush with the precast concrete slab The edges of 1 are flush, and the two ends of the steel beam web of the H-shaped steel secondary beam 2 are provided with bolt holes. in the bolt holes of the web. Specifically, studs 6 are welded on the upper surface of the prefabricated main beam 3, stiffeners with flush edges are welded between the upper and lower flanges of the prefabricated main beam 3, and the steel beam web of the H-shaped steel secondary beam 2 is connected to the prefabricated member. The upper flange of the main beam 3 is aligned with the stiffener, and the steel beam web and the stiffener are fixedly connected through the primary and secondary beam connecting plates 7 .

其中,预制混凝土板1内设置的板面钢筋4,两端伸出预制混凝土板1边缘并与预制构件主梁3边缘对齐,相同方向伸出的板底钢筋5也与预制构件主梁3边缘对齐。预制构件主梁3也为H型钢结构,预制构件主梁3的中部设置加劲肋,加劲肋的边缘与H型钢的上翼缘和下翼缘的宽度对齐,这样,H型钢次梁2与预制混凝土板1的结合构件能够与预制构件主梁3及其加劲肋的边缘对齐。主次梁连接板7与两侧的钢梁腹板和加劲肋通过高强螺栓9固定,使得H型钢次梁2的钢梁腹板与预制构件主梁3的加劲肋能够通过该主次梁连接板7连接为一体,形成完整的传力体系。The steel bar 4 on the surface of the precast concrete slab 1 extends from the edge of the prefabricated concrete slab 1 and is aligned with the edge of the main beam 3 of the prefabricated member. Align. The main girder 3 of the prefabricated member is also an H-shaped steel structure. The middle of the main girder of the prefabricated member 3 is provided with a stiffening rib, and the edge of the stiffening rib is aligned with the width of the upper flange and the lower flange of the H-shaped steel. The joining elements of the concrete slab 1 can be aligned with the edges of the prefabricated element main beams 3 and their stiffeners. The primary and secondary beam connecting plates 7 and the steel beam webs and stiffeners on both sides are fixed by high-strength bolts 9, so that the steel beam webs of the H-shaped steel secondary beam 2 and the stiffeners of the prefabricated main beam 3 can be connected through the primary and secondary beams. The plate 7 is connected as a whole to form a complete force transmission system.

在上述实施例中,优选地,预制混凝土板1沿跨度方向的边缘设置为两层台阶结构,使得预制混凝土板1沿跨度方向的板面相接处下层台阶边缘相接、上层台阶边缘间形成板缝,以进一步浇筑混凝土形成混凝土连接部。在使用过程中,由于预留板缝及外伸钢筋的连接作用,使之平面内成为一个整体,使整体作用更强,提高了构件的整体性能。In the above embodiment, preferably, the edge of the precast concrete slab 1 along the span direction is set as a two-layer stepped structure, so that the edge of the lower step of the precast concrete slab 1 along the span direction is connected, and the edge of the upper step is formed. Slab joints to further pour concrete to form concrete joints. In the process of use, due to the connection between the reserved plate seam and the overhanging steel bar, it becomes a whole in the plane, which makes the overall effect stronger and improves the overall performance of the component.

预制混凝土板1的上部沿板面方向横纵双向布设板面钢筋4,沿跨度方向的板面钢筋4两端伸出预制混凝土板1边缘并超出下层台阶边缘,沿垂直于跨度方向的板面钢筋4两端与预制混凝土板1的下层台阶边缘对齐,预制混凝土板1的下部沿板面方向横纵双向布设板底钢筋5,沿跨度方向的板底钢筋5两端与预制混凝土板1的下层台阶边缘对齐,沿横向跨度方向的板底钢筋5两端伸出预制混凝土板1边缘。在预制混凝土板1内设置伸出边缘的板面钢筋4和板底钢筋5,既可以增加附加钢筋10绑扎钢筋,又加大了后浇混凝体带的宽度,使整体作用更强。The upper part of the precast concrete slab 1 is provided with slab reinforcement bars 4 horizontally, vertically and bidirectionally along the slab surface direction. The two ends of the steel bar 4 are aligned with the edge of the lower step of the precast concrete slab 1. The lower part of the precast concrete slab 1 is arranged with the bottom steel bar 5 along the horizontal and vertical directions of the slab surface. The edges of the lower steps are aligned, and the two ends of the steel bars 5 at the bottom of the slab along the transverse span direction protrude from the edge of the precast concrete slab 1 . In the precast concrete slab 1, the surface reinforcement bars 4 and the slab bottom reinforcement bars 5 are arranged protruding from the edge, which can not only increase the additional reinforcement bars 10 to bind the reinforcement bars, but also increase the width of the post-cast concrete belt, so that the overall effect is stronger.

在上述实施例中,优选地,H型钢次梁2的钢梁腹板上开孔,以穿过管线,同时可以减轻自重,但开孔的同时应注意在不影响其整体强度的基础上进行。In the above embodiment, preferably, holes are opened on the steel beam web of the H-shaped steel secondary beam 2 to pass through the pipeline, and the self-weight can be reduced at the same time, but attention should be paid to the opening without affecting its overall strength. .

在上述实施例中,优选地,板面钢筋4和板底钢筋5伸出预制混凝土板1边缘的部分不小于50毫米。In the above-mentioned embodiment, preferably, the part of the slab surface reinforcement 4 and the slab bottom reinforcement 5 protruding from the edge of the precast concrete slab 1 is not less than 50 mm.

如图3所示,上述实施例中H型钢次梁2与预制混凝土板1的连接方案二具体包括:As shown in FIG. 3 , the connection scheme 2 of the H-shaped steel secondary beam 2 and the precast concrete slab 1 in the above embodiment specifically includes:

H型钢次梁2的钢梁腹板上部两侧焊接附加钢筋10,钢梁上翼缘和钢梁腹板的上半部分预埋入预制混凝土板1中,钢梁上翼缘两端伸出预制混凝土板1的边缘。Additional reinforcing bars 10 are welded on both sides of the upper part of the steel beam web of the H-shaped steel secondary beam 2, the upper flange of the steel beam and the upper half of the steel beam web are pre-buried in the precast concrete slab 1, and both ends of the upper flange of the steel girder protrude from the precast concrete slab 1. the edge of.

在H型钢次梁2与预制混凝土板1的连接方案二中,H型钢次梁2的钢梁上翼缘伸出预制混凝土板1两端部分搭设于预制构件的预制构件主梁3上。具体地,由于钢梁上翼缘两端伸出预制混凝土板1的边缘,H型钢次梁2不需要如方案一中与预制构件主梁3通过主次梁连接板7进行螺栓固定连接,只需要其伸出边缘部分搭接在预制构件主梁3上,即可形成完整的传力体系。In the second connection scheme between the H-shaped steel secondary beam 2 and the precast concrete slab 1 , the upper flange of the steel beam of the H-shaped steel secondary beam 2 protrudes from the two ends of the precast concrete slab 1 and is placed on the precast member main beam 3 of the precast member. Specifically, since both ends of the upper flange of the steel beam protrude from the edge of the precast concrete slab 1, the H-shaped steel secondary beam 2 does not need to be bolted and connected to the precast member main beam 3 through the primary and secondary beam connecting plates 7 as in the scheme 1, and only needs its The protruding edge portion is overlapped on the main beam 3 of the prefabricated member, and a complete force transmission system can be formed.

在上述两种H型钢次梁2与预制混凝土板1的连接方案中,无论是H型钢次梁2依靠栓钉6与预制混凝土板1连接还是钢梁上翼缘及腹板上半部分埋入预制混凝土板1中,都可以形成良好的组合作用,预制混凝土板1可以帮助H型钢次梁2的上翼缘受压,由此可以减少H型钢次梁2上翼缘的尺寸,同时减小钢梁-楼板组合件的高度,为建筑提供更高的空间。In the above two connection schemes of the H-shaped steel secondary beam 2 and the precast concrete slab 1, whether the H-shaped steel secondary beam 2 is connected with the precast concrete slab 1 by means of the studs 6 or the upper flange of the steel beam and the upper half of the web are embedded in the precast concrete In the plate 1, a good combination can be formed. The precast concrete plate 1 can help the upper flange of the H-shaped steel secondary beam 2 to be compressed, thereby reducing the size of the upper flange of the H-shaped steel secondary beam 2 and reducing the steel beam at the same time. -The height of the slab assembly, which provides a higher space for the building.

本发明还提出一种混凝土楼板次梁组合预制构件的制作方法,应用于如上述实施例中任一项的混凝土楼板次梁组合预制构件,包括:确定混凝土板预制模板的位置,以预制混凝土板1的上表面朝下的方向安装混凝土板预制模板;在混凝土板预制模板内浇筑混凝土的同时在预设位置插放H型钢次梁2以形成预制混凝土板1。The present invention also provides a method for making a concrete floor sub-beam composite prefabricated member, which is applied to the concrete floor sub-beam composite prefabricated member according to any one of the above embodiments, including: determining the position of the prefabricated formwork of the concrete slab, and using the prefabricated concrete slab The upper surface of 1 is installed with the prefabricated formwork of the concrete slab in a downward direction; while the concrete is poured in the prefabricated concrete slab formwork, the H-shaped steel secondary beam 2 is inserted at the preset position to form the prefabricated concrete slab 1 .

在上述实施例中,优选地,预制混凝土板1按照预设位置与预制构件主梁3固定或搭接,预制混凝土板1之间相互拼接并在预制混凝土板1相接处的板缝间浇筑混凝土,在预制构件主梁3与立柱11连接处通过主梁柱连接板8相连接并浇筑混凝土,形成板面平齐的组合预制构件。In the above embodiment, preferably, the precast concrete slab 1 is fixed or overlapped with the main beam 3 of the prefabricated member according to the preset position, and the precast concrete slabs 1 are spliced with each other and poured between the slab joints where the precast concrete slabs 1 meet. For concrete, the main beam 3 of the prefabricated component is connected with the column 11 through the main beam-column connecting plate 8 and concrete is poured to form a combined prefabricated component with a flush plate surface.

根据上述实施例提供的混凝土楼板次梁组合预制构件,在具体实施过程中,实施方案如下:According to the concrete floor sub-beam composite prefabricated component provided by the above embodiment, in the specific implementation process, the implementation is as follows:

1)如图4所示,上述H型钢次梁2与预制混凝土板1的连接方案一中,预制混凝土板1构件按普通钢框架结构制作H型钢次梁2和预制构件主梁3,在预制构件主梁3及次梁上翼缘表面均焊接好栓钉6,栓钉6取13mm,高度不小于60毫米;1) As shown in Figure 4, in the connection scheme 1 of the above-mentioned H-shaped steel secondary beam 2 and the precast concrete slab 1, the precast concrete slab 1 member is made of the H-shaped steel secondary beam 2 and the precast member main beam 3 according to the ordinary steel frame structure. The main beam 3 and the upper flange surface of the secondary beam are welded with studs 6, and the studs 6 are 13mm and the height is not less than 60mm;

2)如图5所示,上述H型钢次梁2与预制混凝土板1的连接方案二中,预制混凝土板1构件按普通钢框架结构制作H型钢次梁2和预制构件主梁3,只需在预制构件主梁3上翼缘表面焊接好栓钉6,栓钉6取13mm,高度不小于60毫米;次梁上翼缘及腹板的上半部分埋入混凝土楼板中。2) As shown in Figure 5, in the connection scheme 2 of the above-mentioned H-shaped steel secondary beam 2 and the precast concrete slab 1, the precast concrete slab 1 member is made of the ordinary steel frame structure to make the H-shaped steel secondary beam 2 and the prefabricated member main beam 3, only need Weld studs 6 on the surface of the upper flange of the prefabricated main beam 3, the stud 6 is 13mm, and the height is not less than 60mm; the upper flange of the secondary beam and the upper half of the web are buried in the concrete floor.

3)具体预制构件的预制过程为:首先放线,确定模板的位置;模板的制立安装,之后插筋,钢筋按设计位置安放绑扎,放置好H型钢梁,浇筑混凝土;混凝土的保湿养护对其强度增长和各类性能的提高十分重要,所以,混凝土浇筑完后必须保证必要的养护,待楼板强度达到75%以上方可拆模;3) The prefabrication process of the specific prefabricated components is as follows: first lay out the line to determine the position of the formwork; erect and install the formwork, then insert the reinforcement, place the reinforcement according to the design position and bind it, place the H-shaped steel beam, and pour the concrete; Concrete moisturizing and curing It is very important to increase its strength and improve various properties. Therefore, after the concrete is poured, the necessary maintenance must be ensured, and the formwork can be removed when the floor strength reaches more than 75%;

如图6所示,其中,预制混凝土板1的制作方法为,与预制混凝土板1的上表面朝下设置模板,即制作时楼板在下,钢梁在上,与安装时的位置相反。这样做可以使楼板上表面直接与钢模板接触,表面会很平整,不用再做处理。由于有T型槽存在,倒过来制作更容易支模板,并且H型钢次梁2在上部更容易放置。As shown in FIG. 6 , the manufacturing method of the precast concrete slab 1 is to set the formwork with the upper surface of the precast concrete slab 1 facing down, that is, the floor slab is down and the steel beam is up, which is opposite to the position during installation. In this way, the surface of the floor can be directly contacted with the steel formwork, and the surface will be very flat, and no further treatment is required. Due to the existence of T-shaped grooves, it is easier to support the formwork by inverting it, and it is easier to place the H-shaped steel secondary beam 2 in the upper part.

板底是浇筑时的上表面,其表面会比较粗糙。一般在建筑中会直接做吊顶,上表面粗糙也不会影响使用,可以不必再做处理。除此之外,现在越来越多的建筑不做吊顶,特意将屋顶表面做的粗糙,这样可以形成漫反射,减少室内回声。The bottom of the slab is the upper surface during pouring, and its surface will be rough. Generally, the ceiling will be directly used in the building, and the rough upper surface will not affect the use, so there is no need to do any treatment. In addition, more and more buildings now do not have suspended ceilings, and the roof surface is deliberately made rough, which can form diffuse reflection and reduce indoor echoes.

4)根据建筑立柱11间距确定H型钢次梁2的布置方案,确定单块预制混凝土板1的宽度,单块板宽不大于2.4米,可通过高速公路运输,使其满足预制、运输、吊装的要求,根据结构布置方案及荷载计算,确定板内配筋,使其满足现行规范要求,交给预制厂加工制作;对结构的楼板设计方案确定,能实现整板预制的直接按原设计进行预制。4) Determine the layout plan of the H-shaped steel secondary beam 2 according to the spacing of the building columns 11, and determine the width of a single precast concrete slab 1. The width of a single slab is not greater than 2.4 meters, which can be transported by expressway to meet the requirements of prefabrication, transportation, and hoisting. According to the requirements of the structure layout and load calculation, the reinforcement in the slab is determined to meet the requirements of the current specification, and then handed over to the prefabrication factory for processing and production; the floor design plan of the structure is determined, and the whole slab can be prefabricated directly according to the original design. prefab.

5)预制混凝土板1按照上述H型钢次梁2与预制混凝土板1的连接方案分为两类,在跨度方向,一类是板一侧与预制构件主梁3相接、一侧与板相接的预制混凝土板1,另一类是板两侧边缘均与板相接的预制混凝土板1。这两类板在垂直于跨度方向板边缘构造相同,均搭置在预制构件主梁3上,搭置长度50mm。预制组合次梁构件吊装至指定高度,沿垂直于跨度方向搁置在预制构件主梁3上,该方向的上层板面钢筋4及下层板底钢筋5均伸出预制混凝土板1的边缘形成胡子钢筋,胡子钢筋长度不小于50mm。5) The precast concrete slab 1 is divided into two types according to the connection scheme of the above-mentioned H-shaped steel secondary beam 2 and the precast concrete slab 1. In the span direction, one side of the slab is connected to the main beam 3 of the prefabricated member, and one side is connected to the slab. The other type is the precast concrete slab 1 in which the edges on both sides of the slab are connected to the slab. These two types of panels have the same structure at the edge of the panels perpendicular to the span direction, and are placed on the main beam 3 of the prefabricated member with a length of 50 mm. The prefabricated composite secondary beam member is hoisted to a specified height, and rests on the prefabricated member main beam 3 along the direction perpendicular to the span. The upper deck surface reinforcement 4 and the lower deck bottom reinforcement 5 in this direction both protrude from the edge of the precast concrete slab 1 to form a beard reinforcement. , the length of the beard steel bar is not less than 50mm.

如图7至图10所示,第一类板沿跨度方向的板边构造如下:与预制构件主梁3搭接一侧,无需设计成台阶状,板的上部与下部边缘对齐,由于立柱11宽度比预制构件主梁3的宽度大,所以板需要设置凹角,以满足装配的要求。凹角的宽度为立柱11与预制构件主梁3边距加上搭置长度,跨度方向的板面钢筋4及板底钢筋5均伸出板的边缘不小于50mm,末端平齐;与板搭接一侧(即垂直于跨度方向),由于要形成较宽的混凝土后浇带,并方便连接钢筋的布置,做成台阶状,其上层台阶边缘距下层台阶边缘宽度不小于50mm,板上层受力钢筋伸出上层台阶边缘,伸出长度为下层台阶的宽度,从而在板与板交接处形成板缝以浇筑混凝土。As shown in Fig. 7 to Fig. 10, the plate edge structure of the first type of plate along the span direction is as follows: the side that overlaps with the main beam 3 of the prefabricated member does not need to be designed as a step, and the upper part of the plate is aligned with the lower edge, because the column 11 The width is larger than that of the main beam 3 of the prefabricated member, so the plate needs to be provided with a concave corner to meet the assembly requirements. The width of the concave corner is the distance between the column 11 and the main beam 3 of the prefabricated member plus the overlapping length, and the steel bars 4 and 5 at the bottom of the slab in the span direction protrude from the edge of the slab by not less than 50mm, and the ends are flush; overlap with the slab. On one side (that is, perpendicular to the span direction), due to the need to form a wider concrete post-casting belt, and to facilitate the arrangement of connecting steel bars, it is made into a step shape, and the width of the upper step edge is not less than 50mm from the lower step edge, and the upper layer of the board is stressed. The steel bars protrude from the edge of the upper step by the width of the lower step, thereby forming a slab joint at the junction of the slab for pouring concrete.

第二类板沿垂直于跨度方向两端均与板连接,其构造与第一类板与板搭接一侧的构造一致。Both ends of the second type of board are connected with the board along the span direction perpendicular to the span, and its structure is consistent with the structure of the overlapped side of the first type of board and the board.

6)测量确定各个板块吊装位置,从一侧向另一侧逐块吊装,当一根预制构件主梁3上的板块全部吊装完成后,校核预制混凝土板1的位置,位置确定后,便将H型钢梁与预制构件主梁3通过螺栓连接,只连接腹板便于传力。6) Measure and determine the hoisting position of each slab, and hoist it one by one from one side to the other. When all slabs on the main beam 3 of a prefabricated member are hoisted, check the position of the precast concrete slab 1. The H-shaped steel beam and the main beam 3 of the prefabricated member are connected by bolts, and only the web is connected to facilitate the transmission of force.

7)按照设计要求相邻两板板端伸出的胡子钢筋与另一端胡子钢筋通过附加钢筋10进行连接,防止支座区域混凝土开裂。7) According to the design requirements, the beard steel bar protruding from the end of the adjacent two plates and the beard steel bar at the other end are connected by the additional steel bar 10 to prevent the concrete from cracking in the support area.

8)待某一楼层的组合梁全部或部分安装完成后,调整尺寸达到设计要求。在板梁交接处,板与板交接处后浇混凝土,混凝土的强度与预制混凝土楼板的混凝土强度一致且强度不低于C40,后浇混凝土上表面与预制板面平齐,使整个楼面标高一致。等到现浇混凝土固化后,对其及时养护,防止混凝土开裂。当楼板间拼缝过大或局部现浇出现开裂现象时,可在楼板面上铺设钢丝网片后再做找平层。8) After all or part of the composite beams of a certain floor are installed, adjust the size to meet the design requirements. At the junction of slab and beam, concrete is poured after slab and slab. The strength of concrete is the same as that of precast concrete floor slab and the strength is not lower than C40. Consistent. After the cast-in-place concrete is cured, it should be maintained in time to prevent the concrete from cracking. When the joints between the floors are too large or the local cast-in-place cracks occur, the steel mesh can be laid on the floor surface and then the leveling layer can be made.

根据上述实施例的记载,为了加快钢结构装配式的推广,同时为了改变现代行业中钢结构和混凝土现浇不协调的问题,本发明将组合梁技术与钢框架结构相结合,实现了两者的工业化技术,加快了钢结构工业化的进程,组合梁中楼板与楼板之间的连接处采用现浇混凝土的方式,将各块楼板重新拼接成完整的楼盖结构,保证了建筑结构现有的功能,使整体结构受力体系更加完整,抗震性能更加优越,同时大大缩短了工期,减少了现场混凝土的浇筑量。According to the records of the above embodiments, in order to speed up the promotion of the prefabricated steel structure, and at the same time to change the problem of the incongruity between the steel structure and the cast-in-place concrete in the modern industry, the present invention combines the composite beam technology with the steel frame structure, and realizes both The industrialization technology has accelerated the process of industrialization of the steel structure. The connection between the floor and the floor in the composite beam is cast-in-place concrete. function, so that the overall structural stress system is more complete, the seismic performance is more superior, and the construction period is greatly shortened, and the amount of on-site concrete pouring is reduced.

以上仅为本发明的优选实施例而已,并不用于限制本发明,对于本领域的技术人员来说,本发明可以有各种更改和变化。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above are only preferred embodiments of the present invention, and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.

Claims (10)

1.一种混凝土楼板次梁组合预制构件,其特征在于,包括:预制混凝土板和H型钢次梁,1. a concrete floor sub-beam composite prefabricated member is characterized in that, comprising: prefabricated concrete slab and H-shaped steel sub-beam, 所述预制混凝土板由混凝土浇筑而成;The precast concrete slab is formed by pouring concrete; 所述H型钢次梁的钢梁上翼缘上表面焊接有栓钉,所述栓钉埋置于所述预制混凝土板的下表面。The upper surface of the upper flange of the steel beam of the H-shaped steel secondary beam is welded with studs, and the studs are embedded in the lower surface of the precast concrete slab. 2.根据权利要求1所述的混凝土楼板次梁组合预制构件,其特征在于,所述栓钉完全预埋于所述预制混凝土板中且所述预制混凝土板的下表面与所述钢梁上翼缘的上支承面齐平;2 . The composite prefabricated component of concrete floor sub-beam according to claim 1 , wherein the studs are completely embedded in the prefabricated concrete slab and the lower surface of the prefabricated concrete slab is connected to the upper flange of the steel beam. 3 . The upper bearing surface is flush; 所述钢梁上翼缘的两端与所述预制混凝土板的边缘齐平,所述H型钢次梁的钢梁腹板两端开设螺栓孔,所述钢梁腹板与预制构件主梁通过主次梁连接板相连,并通过高强螺栓固定于所述钢梁腹板的螺栓孔中。The two ends of the upper flange of the steel beam are flush with the edge of the precast concrete slab, the two ends of the steel beam web of the H-shaped steel secondary beam are provided with bolt holes, and the steel beam web and the prefabricated main beam pass through the primary and secondary beams. The beam connecting plates are connected and fixed in the bolt holes of the steel beam web by high-strength bolts. 3.根据权利要求1或2所述的混凝土楼板次梁组合预制构件,其特征在于,所述预制混凝土板沿跨度方向的边缘设置为两层台阶结构,使得所述预制混凝土板沿跨度方向的板面相接处下层台阶边缘相接、上层台阶边缘间形成板缝,以进一步浇筑混凝土形成混凝土连接部;3. The concrete floor sub-beam composite prefabricated member according to claim 1 or 2, wherein the edge of the prefabricated concrete slab along the span direction is set as a two-layer stepped structure, so that the prefabricated concrete slab along the span direction Where the slabs meet, the edges of the lower steps are connected, and the edges of the upper steps are formed with slab joints, so as to further pour concrete to form a concrete connection part; 所述预制混凝土板的上部沿板面方向横纵双向布设板面钢筋,沿跨度方向的所述板面钢筋两端伸出所述预制混凝土板边缘并超出下层台阶边缘,沿垂直于跨度方向的所述板面钢筋两端与所述预制混凝土板的下层台阶边缘对齐,所述预制混凝土板的下部沿板面方向横纵双向布设板底钢筋,沿跨度方向的所述板底钢筋两端与所述预制混凝土板的下层台阶边缘对齐,沿横向跨度方向的所述板底钢筋两端伸出所述预制混凝土板边缘。The upper part of the prefabricated concrete slab is arranged with slab surface reinforcement along the slab surface direction, both ends of the slab surface reinforcement bar along the span direction protrude from the edge of the prefabricated concrete slab and beyond the edge of the lower step, along the direction perpendicular to the span direction. The two ends of the steel bars on the slab are aligned with the edge of the lower step of the precast concrete slab, and the lower part of the prefabricated concrete slab is provided with slab bottom steel bars along the horizontal and vertical directions of the slab surface. The edges of the lower steps of the precast concrete slab are aligned, and the two ends of the steel bars at the bottom of the slab along the transverse span direction protrude from the edge of the precast concrete slab. 4.根据权利要求1或2所述的混凝土楼板次梁组合预制构件,其特征在于,所述H型钢次梁的所述钢梁腹板上开孔,以穿过管线。4 . The composite prefabricated component of concrete floor sub-beams according to claim 1 or 2 , wherein the steel beam webs of the H-shaped steel sub-beams have holes to pass through the pipelines. 5 . 5.根据权利要求2所述的混凝土楼板次梁组合预制构件,其特征在于,所述预制构件主梁的上表面焊接有栓钉,所述预制构件主梁的上下翼缘之间焊接有边缘齐平的加劲肋,所述H型钢次梁的钢梁腹板与所述预制构件主梁的上翼缘和加劲肋对齐,并通过所述主次梁连接板将所述钢梁腹板和所述加劲肋固定连接。5 . The composite prefabricated component of concrete floor and secondary beams according to claim 2 , wherein the upper surface of the main beam of the prefabricated component is welded with studs, and the upper and lower flanges of the main beam of the prefabricated component are welded with edges. Flush stiffeners, the steel beam webs of the H-shaped steel secondary beams are aligned with the upper flanges and stiffeners of the prefabricated main beams, and the steel beam webs and the stiffeners are connected by the primary and secondary beam connecting plates. The stiffening ribs are fixedly connected. 6.根据权利要求3所述的混凝土楼板次梁组合预制构件,其特征在于,所述板面钢筋和所述板底钢筋伸出所述预制混凝土板边缘的部分不小于50毫米。6 . The composite prefabricated component of sub-beams of concrete floor according to claim 3 , characterized in that, the part of said slab surface reinforcement and said slab bottom reinforcement extending beyond the edge of said prefabricated concrete slab is not less than 50 mm. 7 . 7.一种混凝土楼板次梁组合预制构件,其特征在于,相比于权利要求1至6中任一项所述的混凝土楼板次梁组合预制构件:7. A concrete floor sub-beam composite prefabricated member, characterized in that, compared to the concrete floor sub-beam composite prefabricated member described in any one of claims 1 to 6: 所述H型钢次梁的钢梁上翼缘不设置栓钉,The upper flange of the steel beam of the H-shaped steel secondary beam is not provided with studs, 所述钢梁上翼缘以及所述H型钢次梁的钢梁腹板的上半部分预埋入所述预制混凝土板中。The upper flange of the steel beam and the upper half of the steel beam web of the H-shaped steel secondary beam are pre-embedded in the precast concrete slab. 8.根据权利要求7所述的混凝土楼板次梁组合预制构件,其特征在于,所述H型钢次梁的所述钢梁腹板上部两侧焊接附加钢筋,所述钢梁上翼缘两端伸出所述预制混凝土板的边缘,伸出部分搭设于所述预制构件的主梁上。8 . The composite prefabricated component of concrete floor sub-beam according to claim 7 , wherein additional steel bars are welded on both sides of the upper part of the steel beam web of the H-shaped steel sub-beam, and both ends of the upper flange of the steel beam protrude. 9 . The protruding part of the edge of the prefabricated concrete slab is placed on the main beam of the prefabricated member. 9.一种混凝土楼板次梁组合预制构件的制作方法,应用于如权利要求1至8中任一项所述的混凝土楼板次梁组合预制构件,其特征在于,包括:9. A method for making a concrete floor sub-beam composite prefabricated member, applied to the concrete floor sub-beam composite prefabricated member as claimed in any one of claims 1 to 8, characterized in that, comprising: 确定混凝土板预制模板的位置,以预制混凝土板的上表面朝下的方向安装所述混凝土板预制模板;determining the position of the prefabricated formwork of the concrete slab, and installing the prefabricated formwork of the concrete slab with the upper surface of the prefabricated concrete slab facing downward; 在所述混凝土板预制模板内浇筑混凝土的同时在预设位置插放H型钢次梁以形成所述预制混凝土板。While pouring concrete in the prefabricated formwork of the concrete slab, insert H-shaped steel secondary beams at preset positions to form the prefabricated concrete slab. 10.根据权利要求9所述的混凝土楼板次梁组合预制构件的制作方法,其特征在于,所述预制混凝土板按照预设位置与预制构件主梁固定或搭接,所述预制混凝土板之间相互拼接并在所述预制混凝土板相接处的板缝间浇筑混凝土,在所述预制构件主梁与立柱相连接处浇筑混凝土,形成板面平齐的组合预制构件。10. The method for manufacturing a concrete floor sub-beam composite prefabricated member according to claim 9, wherein the prefabricated concrete slab is fixed or overlapped with the prefabricated member main beam according to a preset position, and the prefabricated concrete slab is between Splicing each other and pouring concrete between the slab joints of the prefabricated concrete slabs, pouring concrete at the connection between the prefabricated component main beam and the upright column, to form a combined prefabricated component with a flush slab surface.
CN202010238752.7A 2020-03-30 2020-03-30 Concrete floor secondary beam combined prefabricated part and manufacturing method Pending CN111424869A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010238752.7A CN111424869A (en) 2020-03-30 2020-03-30 Concrete floor secondary beam combined prefabricated part and manufacturing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010238752.7A CN111424869A (en) 2020-03-30 2020-03-30 Concrete floor secondary beam combined prefabricated part and manufacturing method

Publications (1)

Publication Number Publication Date
CN111424869A true CN111424869A (en) 2020-07-17

Family

ID=71549296

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010238752.7A Pending CN111424869A (en) 2020-03-30 2020-03-30 Concrete floor secondary beam combined prefabricated part and manufacturing method

Country Status (1)

Country Link
CN (1) CN111424869A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111962767A (en) * 2020-08-17 2020-11-20 东华理工大学 Web plate open-hole section steel partially-wrapped concrete composite beam and construction method thereof
CN113957999A (en) * 2021-11-03 2022-01-21 中机中联工程有限公司 Rigid connection joint structure and construction method of steel secondary beam and precast concrete main beam
CN114232783A (en) * 2021-12-16 2022-03-25 中南大学 A prefabricated beam-slab system of a fully assembled building and a beam-slab module prefabrication method thereof
CN116815937A (en) * 2023-06-29 2023-09-29 中国铁路设计集团有限公司 Irregular atrium hole assembled type rapid temporary plugging structure and construction method
CN117188612A (en) * 2023-09-19 2023-12-08 中国化学工程第十一建设有限公司 Connection nodes, connection node construction methods and connection node design methods
CN120906286A (en) * 2025-09-30 2025-11-07 中建三局集团有限公司 Full prefabricated steel beam dense rib combined floor system

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10147980A (en) * 1996-11-18 1998-06-02 Sumitomo Forestry Co Ltd Beam joint structure
US20060230697A1 (en) * 2003-02-25 2006-10-19 James Lupton Deck structure
CN203701387U (en) * 2014-02-06 2014-07-09 李健鹏 Floor slab structure with embedded heat preservation cavities
CN205444613U (en) * 2015-12-31 2016-08-10 浙江绿筑建筑系统集成有限公司 Be applied to prefabricated coincide floor connecting piece of assembled steel construction building
CN205663076U (en) * 2016-05-31 2016-10-26 安徽富煌建筑设计研究有限公司 Can reduce steel and concrete composite roof beam of cross -sectional height
CN206000061U (en) * 2016-08-10 2017-03-08 山东鲁帆集团有限公司 Floor splicing construction and building template
CN107795056A (en) * 2017-11-09 2018-03-13 浙江绿筑集成科技有限公司 A kind of special full precast floor slab of assembling type steel structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10147980A (en) * 1996-11-18 1998-06-02 Sumitomo Forestry Co Ltd Beam joint structure
US20060230697A1 (en) * 2003-02-25 2006-10-19 James Lupton Deck structure
CN203701387U (en) * 2014-02-06 2014-07-09 李健鹏 Floor slab structure with embedded heat preservation cavities
CN205444613U (en) * 2015-12-31 2016-08-10 浙江绿筑建筑系统集成有限公司 Be applied to prefabricated coincide floor connecting piece of assembled steel construction building
CN205663076U (en) * 2016-05-31 2016-10-26 安徽富煌建筑设计研究有限公司 Can reduce steel and concrete composite roof beam of cross -sectional height
CN206000061U (en) * 2016-08-10 2017-03-08 山东鲁帆集团有限公司 Floor splicing construction and building template
CN107795056A (en) * 2017-11-09 2018-03-13 浙江绿筑集成科技有限公司 A kind of special full precast floor slab of assembling type steel structure

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111962767A (en) * 2020-08-17 2020-11-20 东华理工大学 Web plate open-hole section steel partially-wrapped concrete composite beam and construction method thereof
CN113957999A (en) * 2021-11-03 2022-01-21 中机中联工程有限公司 Rigid connection joint structure and construction method of steel secondary beam and precast concrete main beam
CN114232783A (en) * 2021-12-16 2022-03-25 中南大学 A prefabricated beam-slab system of a fully assembled building and a beam-slab module prefabrication method thereof
CN116815937A (en) * 2023-06-29 2023-09-29 中国铁路设计集团有限公司 Irregular atrium hole assembled type rapid temporary plugging structure and construction method
CN117188612A (en) * 2023-09-19 2023-12-08 中国化学工程第十一建设有限公司 Connection nodes, connection node construction methods and connection node design methods
CN120906286A (en) * 2025-09-30 2025-11-07 中建三局集团有限公司 Full prefabricated steel beam dense rib combined floor system
CN120906286B (en) * 2025-09-30 2025-12-30 中建三局集团有限公司 Full prefabricated steel beam dense rib combined floor system

Similar Documents

Publication Publication Date Title
CN111424869A (en) Concrete floor secondary beam combined prefabricated part and manufacturing method
CN106677049B (en) Assembled steel-concrete combined structure bridge and construction method
CN108360721B (en) Precast concrete ultra-thin two-way load-bearing prefabricated reinforced truss composite floor
CN111411721A (en) A prefabricated prefabricated sub-beam composite member
CN110670770A (en) Combined structure and construction method of solid shear wall and laminated plate edge member
CN108222347A (en) A kind of big module welding overlapping beam slab of the assembled with plane girder temporary support
CN104088221A (en) T-shaped plate girder segment prefabricating unit based on steel truss and combined bridge deck slab
CN218643645U (en) Full-assembly type reinforced concrete floor connected by steel-concrete combined structure
CN108301545A (en) A kind of big module overlapping contignation of the assembled with space truss temporary support
CN111794423A (en) A steel-concrete composite beam structure, building and construction method
CN108978856A (en) A kind of assembled Honeycomb Beam panel structure system
CN108360723A (en) A kind of half welding overlapping contignation of the big module of the assembled with space truss temporary support
CN108265626A (en) Reinforcing steel bar-steel plate skeleton combined bridge deck and its construction method
CN108301546A (en) A kind of big module overlapping contignation of the assembled with plane girder temporary support
CN111648512A (en) A kind of assembly tool type truss laminated board and construction method thereof
CN115961719A (en) Prefabricated shear wall system and construction method thereof
CN207405842U (en) An integral fully prefabricated floor slab unsupported connection structure
CN113802726A (en) Edge member of superimposed integral prefabricated shear wall and installation method
CN209703805U (en) A new type of composite floor suitable for H-shaped steel beams in steel structures
CN219863582U (en) Assembled self-supporting prestress stacking bearing plate
CN114164978B (en) One-way dense-rib cavity floor module for steel structure and construction method thereof
CN218345930U (en) Bridge structure
CN110725439A (en) A prefabricated steel-concrete shear wall and its construction method
CN216740000U (en) Assembly system
CN110080455A (en) A kind of precast shear wall, connecting node and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200717