CN111424644B - Carrier pile construction process - Google Patents

Carrier pile construction process Download PDF

Info

Publication number
CN111424644B
CN111424644B CN202010314170.2A CN202010314170A CN111424644B CN 111424644 B CN111424644 B CN 111424644B CN 202010314170 A CN202010314170 A CN 202010314170A CN 111424644 B CN111424644 B CN 111424644B
Authority
CN
China
Prior art keywords
pile
carrier
steel
pulling
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010314170.2A
Other languages
Chinese (zh)
Other versions
CN111424644A (en
Inventor
邵良荣
张聪辰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei Hainei Wushuang Construction Engineering Co ltd
Original Assignee
Wuhan Concrete Source Hi Tech Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Concrete Source Hi Tech Co ltd filed Critical Wuhan Concrete Source Hi Tech Co ltd
Priority to CN202010314170.2A priority Critical patent/CN111424644B/en
Priority to CN202011409155.2A priority patent/CN112593549B/en
Priority to CN202011417924.3A priority patent/CN112482359B/en
Publication of CN111424644A publication Critical patent/CN111424644A/en
Application granted granted Critical
Publication of CN111424644B publication Critical patent/CN111424644B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/385Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to a construction process of a pulling-resistant reinforcing steel bar, a carrier pile, a hollow column hammer for construction and the carrier pile, which relates to the technical field of the carrier pile and comprises a plurality of tensile longitudinal ribs with bent bottom ends; the carrier pile comprises a concrete pile body, an influence soil body, a compaction soil body and a filler fixedly connected with the bottom end of the uplift steel bar; the hollow column hammer for construction comprises a steel cylinder and an expansion disc which are jointly provided with a through hole, and a carrier pile construction process comprises the following steps: s1: measuring and paying off to form a hole; s2: sinking the steel sleeve; s3: tamping a filler; s4: measuring the penetration of the three shots; s5: lowering tensile longitudinal bars; s6: tamping the filler by a hollow column hammer; s7: installing a reinforcement cage; s8: pouring concrete S9: and pulling the sleeve. The invention leads the concrete pile body and the composite carrier to be tightly connected into a whole, leads the carrier pile to have the functions of compression resistance and pulling resistance at the same time, solves the problem that the pile body and the carrier are easy to be separated, reduces the cost of foundation treatment, and is environment-friendly and energy-saving.

Description

一种载体桩施工工艺A kind of carrier pile construction technology

技术领域technical field

本发明涉及载体桩的技术领域,尤其是涉及抗拔钢筋、载体桩、施工用空心柱锤及载体桩施工工艺。The invention relates to the technical field of carrier piles, in particular to a pull-resistant steel bar, a carrier pile, a hollow column hammer for construction and a construction process of the carrier pile.

背景技术Background technique

载体桩是一种不同于普通意义上的桩,载体桩主要由上部桩身和下部“复合载体”两部分组成,桩身一般为现浇混凝土结构或高强预应力预制桩,“复合载体”是位于桩身底部、经深层填料夯实的复合体,利用重锤的自由落体运动对桩端深层土体进行反复地填料夯实挤密操作,使桩端以下一定范围内的土体得到最为有效地加固挤密,形成“复合载体”,是该种桩型的技术核心,可以使桩端的应力逐层地进行扩散和降低,改变了传统的桩端与地基土体之间的作用关系,充分调动了桩端地基土体的承载力,使得桩的承载能力大大提高。The carrier pile is a kind of pile that is different from the general sense. The carrier pile is mainly composed of the upper pile body and the lower "composite carrier". The pile body is generally a cast-in-place concrete structure or a high-strength prestressed prefabricated pile. The "composite carrier" is The composite body located at the bottom of the pile body and tamped by the deep filler, the free fall motion of the heavy hammer is used to repeatedly fill and compact the deep soil at the end of the pile, so that the soil within a certain range below the end of the pile can be most effectively reinforced Compacting to form a "composite carrier" is the technical core of this type of pile, which can diffuse and reduce the stress at the pile end layer by layer, change the traditional interaction between the pile end and the foundation soil, and fully mobilize the The bearing capacity of the foundation soil at the pile end greatly improves the bearing capacity of the pile.

由于现有载体桩技术主要由上部桩身和下部“复合载体”两部分组成,上部桩身与载体不能很好的连接,经常导致桩身与载体产生脱离,影响承载力的发挥;桩身与载体没有连接,几乎没有抗拔力。Since the existing carrier pile technology is mainly composed of the upper pile body and the lower "composite carrier", the upper pile body and the carrier cannot be well connected, which often leads to the separation of the pile body and the carrier, which affects the bearing capacity; The carrier is not connected and has little resistance to pull-out.

现有技术中有人提出了一种锚杆桩的施工方法,提出了改进上述问题的技术方案,1.在桩位处,将护筒沉入至设定深度,2.在护筒内填入水泥拌合物,3.在护筒中沉入特制的锚固件,锚固件由竖向锚固杆和底部锚固盘构成,锚固盘由钢筋或钢板制作,4.以锚固件的竖向锚固杆为中心,在护筒中沉入穿心锤,5.在护筒中填入水泥拌合物,6.在护筒中提升穿心锤,小能量夯击所填入的水泥拌合物,7.重复上述步骤5和步骤6的填入水泥拌合物并以穿心锤夯击的操作,在桩端逐渐形成具备一定体积和密实度的载体。In the prior art, some people have proposed a construction method for anchor piles, and proposed technical solutions to improve the above problems. 1. At the pile position, the casing is sunk to a set depth, and 2. the casing is filled with Cement mixture, 3. A special anchor is sunk into the casing. The anchor is composed of a vertical anchor rod and a bottom anchor plate. The anchor plate is made of steel bars or steel plates. 4. The vertical anchor rod of the anchor is centered. , sink the penetrating hammer into the casing, 5. Fill the casing with cement mixture, 6. Lift the penetrating hammer in the casing, ram the filled cement mixture with low energy, 7. Repeat the above steps In the operations of filling in the cement mixture and ramming with a piercing hammer in step 5 and step 6, a carrier with a certain volume and density is gradually formed at the end of the pile.

上述中的现有技术方案仍存在以下缺陷:锚固件是有竖向锚固杆和底部锚固盘两部分焊接构成,利用重锤夯击锚固件使其沉入桩孔内,施工过程中,容易导致竖向锚固杆和底部锚固盘受到重力在桩孔内脱离,施工完成后,相互脱离的锚固件在桩孔容易受力不均甚至失效,影响载体桩整体的承载力,造成资源浪费,同时该施工工艺也不具有同时抗压特点。The above-mentioned prior art scheme still has the following defects: the anchor is composed of a vertical anchor rod and a bottom anchoring plate welded by two parts, and the anchor is rammed with a heavy hammer to sink it into the pile hole. During the construction process, it is easy to cause The vertical anchor rod and the bottom anchor plate are detached in the pile hole by gravity. After the construction is completed, the detached anchors are prone to uneven force or even failure in the pile hole, which affects the overall bearing capacity of the carrier pile and causes waste of resources. The construction process does not have the characteristics of simultaneous compression.

发明内容SUMMARY OF THE INVENTION

针对现有技术存在的不足,本发明的目的之一是提供位于载体桩内,提高载体桩整体稳定性以及提高载体桩耐受力的抗拔钢筋。In view of the deficiencies in the prior art, one of the objectives of the present invention is to provide a pull-out steel bar located in the carrier pile to improve the overall stability of the carrier pile and improve the bearing capacity of the carrier pile.

本发明的上述发明目的是通过以下技术方案得以实现的:抗拔钢筋,位于载体桩内部且被锤入桩孔内,其特征在于:包括多跟固定呈一束的抗拉纵筋,多个抗拉纵筋的底端均朝向相互背离的方向呈85-95度弯曲状设置,相邻所述抗拉纵筋的底端沿桩孔的内径方向间隔排布。The above-mentioned purpose of the present invention is achieved through the following technical solutions: the pull-out steel bars are located inside the carrier pile and are hammered into the pile holes, and are characterized in that: comprising multiple tensile longitudinal bars that are fixed in a bundle, a plurality of The bottom ends of the tensile longitudinal bars are arranged in a curved shape of 85-95 degrees in the direction away from each other, and the bottom ends of the adjacent tensile longitudinal bars are arranged at intervals along the inner diameter direction of the pile hole.

通过采用上述技术方案,利用底端弯折成型的抗拉纵筋作为联接件,结构稳定,整体受力均匀,抗拉纵筋底端85-95度弯曲状,从而当抗拉纵筋的底端处于桩孔底端时,抗拉纵筋与桩孔底端的填料相互的牵引力和约束力更大,使得载体桩整体稳定性更强。By adopting the above technical solution, the tensile longitudinal rib formed by bending the bottom end is used as the connecting piece, the structure is stable, the overall force is uniform, and the bottom end of the tensile longitudinal rib is bent at 85-95 degrees, so that the bottom end of the anti-tensile longitudinal rib is bent at 85-95 degrees. When the end is at the bottom end of the pile hole, the mutual traction force and binding force of the tensile longitudinal reinforcement and the filler at the bottom end of the pile hole are larger, which makes the overall stability of the carrier pile stronger.

本发明在一较佳示例中可以进一步配置为:多根所述抗拉纵筋周侧共同环绕有定位环,所述抗拉纵筋之间固定连接有帮焊钢筋。In a preferred example of the present invention, it can be further configured that: a plurality of the tensile longitudinal bars are jointly surrounded by a positioning ring on the peripheral sides, and a welding helper steel bar is fixedly connected between the tensile longitudinal bars.

通过采用上述技术方案,定位环和帮焊钢筋实现相邻抗拉纵筋的固定连接,同时起到减少抗拉纵筋变形的作用,分散施加至抗拉纵筋上的载荷整体结构承载能力和抗剪能力更强。By adopting the above technical solution, the positioning ring and the welding helper bars realize the fixed connection of the adjacent tensile longitudinal bars, and at the same time play the role of reducing the deformation of the tensile longitudinal bars, dispersing the loads applied to the tensile longitudinal bars. The overall structural bearing capacity and Stronger shear resistance.

本发明的目的之一是提供受力更加均匀、单桩抗压抗拔承载能力强的载体桩。One of the objectives of the present invention is to provide a carrier pile with more uniform stress and strong compressive and pull-out bearing capacity of a single pile.

本发明的上述发明目的是通过以下技术方案得以实现的:载体桩,包括沿桩孔的轴向从上至下依次排布的混凝土桩身、填充料、挤密土体、影响土体,所述混凝土桩身的抗拔钢筋采用的是如上所述的抗拉纵筋,所述抗拉纵筋的底端延伸至所述填充料内。The above-mentioned invention purpose of the present invention is achieved through the following technical solutions: the carrier pile includes the concrete pile body, the filler, the compacted soil body, and the influence soil body, which are arranged in sequence from top to bottom along the axial direction of the pile hole, so the The anti-pulling reinforcement of the concrete pile body is the above-mentioned tensile longitudinal reinforcement, and the bottom end of the tensile longitudinal reinforcement extends into the filler.

通过采用上述技术方案,利用影响土体、挤密土体、填充料共同形成复合载体球体,该球体直径远远大于混凝土桩身,利用重锤夯击,将一体成型的底端一定角度弯折的抗拉纵筋嵌入到填充料中,通过抗拉纵筋将复合载体和混凝土桩身紧密连接,增大了桩身底端的等效直径,最终极大的增大载体桩竖向抗拔和抗压承载力,结构经济简单,施工速度快,成桩效率高。By adopting the above technical scheme, the impacted soil, the compacted soil and the filler are used to form a composite carrier sphere. The diameter of the sphere is much larger than that of the concrete pile body. The bottom end of the integrally formed is bent at a certain angle by ramming with a heavy hammer. The tensile longitudinal reinforcement is embedded in the filler, and the composite carrier and the concrete pile body are closely connected by the tensile longitudinal reinforcement, which increases the equivalent diameter of the bottom end of the pile body, and finally greatly increases the vertical pull-out resistance of the carrier pile. Compressive bearing capacity, economical and simple structure, fast construction speed and high pile forming efficiency.

本发明在一较佳示例中可以进一步配置为:所述混凝土桩身包括设置于抗拔钢筋周侧的多个钢筋笼体,多个钢筋笼体沿桩孔的轴向从上至下依次排布设置,桩孔内于抗拔钢筋和所述钢筋笼体之间现浇有混凝土。In a preferred example of the present invention, the concrete pile body can be further configured as follows: the concrete pile body includes a plurality of reinforcing bar cages arranged on the peripheral side of the pull-out steel bars, and the plurality of reinforcing bar cages are arranged in sequence from top to bottom along the axial direction of the pile hole In the pile hole, concrete is poured in-situ between the pull-out reinforcement and the reinforcement cage.

通过采用上述技术方案,利用钢筋笼体和混凝土形成载体桩上部的主要承载结构,与抗拔钢筋结合后,锚固力更强,抗拔承载能力更加稳定。By adopting the above technical scheme, the steel cage and concrete are used to form the main bearing structure of the upper part of the carrier pile. After combining with the pull-resistant steel bars, the anchoring force is stronger and the pull-resistant bearing capacity is more stable.

本发明在一较佳示例中可以进一步配置为:所述混凝土桩身包括预制桩和水泥砂浆注浆体,所述预制桩由混凝土和多个钢筋笼体预制而成,所述预制桩中心形成用于容纳抗拉纵筋的管桩孔,管桩孔内于抗拉纵筋周围浇注有水泥砂浆形成水泥砂浆注浆体。In a preferred example of the present invention, it can be further configured as follows: the concrete pile body includes a prefabricated pile and a cement mortar grouting body, the prefabricated pile is prefabricated by concrete and a plurality of steel cages, and the center of the prefabricated pile is formed The pipe pile hole is used for accommodating the tensile longitudinal reinforcement, and the cement mortar is poured around the tensile longitudinal reinforcement in the pipe pile hole to form a cement mortar grouting body.

通过采用上述技术方案,通过在预制形成结构稳定的预制桩,受力较为稳定,具有较好的支承力和抗剪力,适应能力强,使用预制的预制桩,施工方式简单,提高了施工效率,降低了施工成本。By adopting the above technical scheme, by forming prefabricated prefabricated piles with stable structure in prefabrication, the force is relatively stable, with better supporting force and shear resistance, strong adaptability, using prefabricated prefabricated piles, the construction method is simple, and the construction efficiency is improved. , reducing the construction cost.

本发明在一较佳示例中可以进一步配置为:所述钢筋笼体包括多个钢筋笼纵筋、螺旋箍筋、加劲筋,多个所述钢筋笼纵筋沿桩孔轴线方向等间距套设于抗拔钢筋周侧,所述钢筋笼纵筋的周侧共同环绕固定连接有所述螺旋箍筋,多个所述钢筋笼纵筋的内壁共同连接有多个所述加劲筋。In a preferred example of the present invention, it can be further configured that: the reinforcing bar cage body includes a plurality of reinforcing bar cage longitudinal bars, spiral stirrups, and stiffening bars, and a plurality of the reinforcing bar cage longitudinal bars are sleeved at equal intervals along the axis direction of the pile hole On the peripheral side of the pull-resistant steel bar, the spiral stirrups are connected together around the peripheral side of the longitudinal bars of the reinforcement cage, and the inner walls of the longitudinal bars of the reinforcement cage are jointly connected with a plurality of the stiffening bars.

通过采用上述技术方案,利用多个钢筋笼纵筋共同构成钢筋笼体,结构简单易于制作,利用螺旋箍筋和加劲筋实现钢筋笼纵筋的加强连接,减少相邻钢筋笼纵筋的变形以及脱落的情况,使得钢筋笼体结构更加稳定。By adopting the above technical scheme, a plurality of longitudinal bars of the steel cage are used to form a steel cage body, the structure is simple and easy to manufacture, and the reinforcement connection of the longitudinal bars of the steel cage is realized by using the spiral stirrups and the stiffening bars, and the deformation of the longitudinal bars of the adjacent steel cages is reduced. The situation of falling off makes the steel cage structure more stable.

本发明在一较佳示例中可以进一步配置为:所述混凝土桩身的桩端设置有承台和筏板,所述混凝土桩身内的多个所述抗拉纵筋远离弯折段的一端均向上延伸至所述承台内,或者多个所述抗拉纵筋不延伸至所述承台和所述筏板内。In a preferred example of the present invention, it can be further configured that: the pile end of the concrete pile body is provided with a cap and a raft, and one end of the plurality of tensile longitudinal bars in the concrete pile body away from the bending section is Extend upwards into the deck, or a plurality of the tensile longitudinal bars do not extend into the deck and the raft.

通过采用上述技术方案,利用筏板与钢筋笼体和抗拉纵筋的连接,加强载体桩整体结构强度,在出现桩长长度大小大于空心柱锤长度大小时,抗拉纵筋实现复合载体和混凝土桩身连接,可选择抗拉纵筋不延伸至承台和筏板内,减小抗拉纵筋对空心柱锤的连接杆与卷扬机连接的影响,更好地满足实际施工工艺需求,保障施工效率本发明的目的之一是提供便于贯入本发明的抗拔钢筋,便于对抗拔钢筋底端周围的填料进行锤击,保障抗拔钢筋底端与填料的连接强度,同时减少锤击填料时对抗拔钢筋的影响的施工用空心柱锤。By adopting the above technical scheme, the overall structural strength of the carrier pile is strengthened by using the connection between the raft, the steel cage and the tensile longitudinal reinforcement. For concrete pile body connection, the tensile longitudinal reinforcement can be selected not to extend into the bearing platform and the raft, so as to reduce the influence of the tensile longitudinal reinforcement on the connection between the connecting rod of the hollow column hammer and the hoist, so as to better meet the actual construction process requirements and ensure Construction Efficiency One of the objectives of the present invention is to provide a pull-resistant steel bar that is easy to penetrate into the present invention, to facilitate hammering of the filler around the bottom end of the pull-resistant steel bar, to ensure the connection strength between the bottom end of the pull-resistant steel bar and the filler, and to reduce the hammering of the filler. Hollow column hammer for construction when resisting the influence of pulling out steel bars.

本发明的上述发明目的是通过以下技术方案得以实现的:施工用空心柱锤,包括钢筒,所述钢筒的一端同轴固定连接有扩大盘,所述钢筒和所述扩大盘共同同轴开设有便于如上技术方案所述的抗拔钢筋贯入的贯入通孔。The above-mentioned purpose of the present invention is achieved through the following technical solutions: a hollow column hammer for construction, including a steel cylinder, one end of the steel cylinder is fixedly connected with an expansion plate, and the steel cylinder and the expansion plate are coaxially connected with each other. The shaft is provided with a through hole which is convenient for the penetration of the pull-out steel bar described in the above technical solution.

通过采用上述技术方案,钢筒和扩大盘实现了基础锤击功能,扩大盘便于对桩孔底部更大面积的填料进行锤击,结构简单易于制作,锤击效果稳定,与现有的重锤相比,特点在于贯入通孔便于贯入抗拔钢筋,抗拔钢筋处于桩孔内时,同时能够对桩孔底部填料进行锤击,减少了施工难度和人工劳作力,抗拉纵筋为一体成型,在重锤夯击作用下不会发生断裂等情况,同时方便了抗拔钢筋底端与填料的紧密连接,保障了本发明载体桩的底端结构强度,减少对抗拔钢筋本身的影响。By adopting the above technical solution, the steel cylinder and the expansion disc realize the basic hammering function, the expansion disc is convenient for hammering a larger area of the filler at the bottom of the pile hole, the structure is simple and easy to manufacture, and the hammering effect is stable, which is different from the existing heavy hammer. In contrast, the characteristic is that the penetration through hole is convenient for penetrating the anti-pulling steel bar. When the anti-pulling steel bar is in the pile hole, the bottom filler of the pile hole can be hammered at the same time, which reduces the difficulty of construction and manual labor. It is integrally formed, and will not break under the action of heavy hammer ramming. At the same time, it is convenient for the close connection between the bottom end of the anti-pulling steel bar and the filler, which ensures the structural strength of the bottom end of the carrier pile of the present invention, and reduces the influence of the anti-pulling steel bar itself. .

本发明的目的之一是提供所成桩的土层比常规桩成桩方法的土层浅且单桩承载力高、质量稳定可靠、节能环保、造价低的载体桩施工工艺。One of the objectives of the present invention is to provide a carrier pile construction process with a shallower soil layer than conventional pile forming methods, high single pile bearing capacity, stable and reliable quality, energy saving and environmental protection, and low cost.

本发明的上述发明目的是通过以下技术方案得以实现的:载体桩施工工艺,所述载体桩为如上任一技术方案所述的载体桩,其特征在于,包括以下步骤:The above-mentioned purpose of the present invention is achieved through the following technical solutions: a carrier pile construction process, the carrier pile is the carrier pile described in any of the above technical solutions, and is characterized in that, comprising the following steps:

S1:测量放线成孔,准确设置桩孔标记,在桩孔标记位置重锤土层逐段锤击成孔;S1: Measure the line to form a hole, accurately set the pile hole mark, and hammer the soil layer section by section to form a hole at the position of the pile hole mark;

S2:沉放钢套筒,重锤成孔过程中,将钢套筒沉至设计标高;S2: sink the steel sleeve, and sink the steel sleeve to the design elevation during the process of hammering the hole;

S3:填料夯击,钢套筒沉放至持力层后,进行分次填入填料,并多次夯击填料;S3: The packing is rammed. After the steel sleeve is placed in the bearing layer, the packing is filled in stages, and the packing is rammed several times;

S4:测量三击贯入度,填料完成形成密实载体状态后,测量三击贯入度,若不满足设计要求,继续在桩孔内填充并锤击填料,直至满足三击贯入度要求;S4: Measure the three-strike penetration. After the filler is formed into a dense carrier state, measure the three-strike penetration. If it does not meet the design requirements, continue to fill and hammer the filler in the pile hole until it meets the three-strike penetration requirements;

S5:下放抗拉纵筋,在桩孔内下放抗拔钢筋;S5: Lay down the tensile longitudinal reinforcement, and lower the pullout reinforcement in the pile hole;

S6:空心柱锤夯击填料,抗拔钢筋下放后,将空心柱锤沉放至桩孔内,同时抗拔钢筋处于贯入通孔内,继续分次填入填料,多次夯击填料直至抗拉纵筋进入载体不小于40-60cm;S6: The hollow column hammer rams the filler. After the anti-pulling steel bar is lowered, the hollow column hammer is lowered into the pile hole. At the same time, the anti-pulling steel bar is in the through hole. The length of the tensile reinforcement into the carrier is not less than 40-60cm;

S7:安装钢筋笼,现场预制钢筋笼体,将钢筋笼体吊起并放入钢套筒内,并将抗拉纵筋穿入钢筋笼体的内侧定位环内,测量钢筋笼体标高并调整钢筋笼标高在允许误差范围内;S7: Install the reinforcement cage, prefabricate the reinforcement cage on site, hoist the reinforcement cage and put it into the steel sleeve, insert the tensile longitudinal reinforcement into the inner positioning ring of the reinforcement cage, measure the elevation of the reinforcement cage and adjust it The elevation of the steel cage is within the allowable error range;

S8:浇注混凝土,在钢套筒内浇筑混凝土浆,测量并控制浇筑混凝土桩身的标高,控制桩顶标高在允许误差范围内,按规范超灌0.8m以上;S8: pour concrete, pour concrete slurry in the steel sleeve, measure and control the elevation of the poured concrete pile body, control the elevation of the pile top within the allowable error range, and overfill it by more than 0.8m according to the specification;

S9:拔套筒,将钢套筒从桩孔内拔出,控制拔出速度,必要时采用停拔措施。S9: Pull out the sleeve, pull out the steel sleeve from the pile hole, control the pull-out speed, and take measures to stop pulling if necessary.

通过采用上述技术方案,利用复合载体形成的球体,该球体直径远远大于混凝土桩身,利用重锤夯击将一体成型的底端一定角度弯折的抗拉纵筋嵌入到填充料中,通过抗拉纵筋将复合载体和混凝土桩身紧密连接,增大了桩身底端的等效直径,最终极大的增大载体桩竖向抗压和抗拔承载力,结构经济简单,施工速度快,成桩效率高。By adopting the above technical scheme, a sphere formed by a composite carrier, the diameter of which is much larger than the concrete pile body, is used to embed the integrally formed tensile longitudinal reinforcement at a certain angle at the bottom end into the filler by ramming with a heavy hammer. The tensile longitudinal reinforcement closely connects the composite carrier and the concrete pile body, which increases the equivalent diameter of the bottom end of the pile body, and ultimately greatly increases the vertical compressive and uplift bearing capacity of the carrier pile. The structure is economical and simple, and the construction speed is fast. , the pile forming efficiency is high.

本发明在一较佳示例中可以进一步配置为:在步骤S6中,所述填料为水泥砂拌合物或干硬性混凝土,抗拉纵筋在重锤带动下,底部一定角度弯曲部分嵌入填料中,上部嵌入混凝土桩身中,使混凝土桩身与填料牢固连接。In a preferred example of the present invention, it can be further configured as follows: in step S6, the filler is a cement-sand mixture or dry-hard concrete, and the tensile longitudinal reinforcement is driven by a heavy hammer, and the bent part of the bottom at a certain angle is embedded in the filler , the upper part is embedded in the concrete pile body, so that the concrete pile body and the filler are firmly connected.

综上所述,本发明包括以下至少一种益技术效果:1.底部一体弯折成型的抗拉纵筋结构更加稳定,克服了现有技术中焊接的竖向锚固杆和底部锚固盘容易脱落的缺陷,结构简单易于制作,更加便于在桩孔内施工,降低了施工成本、环保节能;To sum up, the present invention includes at least one of the following beneficial technical effects: 1. The structure of the tensile longitudinal rib formed by integral bending at the bottom is more stable, which overcomes the easy falling off of the welded vertical anchor rod and bottom anchor plate in the prior art The structure is simple and easy to manufacture, and it is more convenient for construction in the pile hole, which reduces the construction cost, environmental protection and energy saving;

2.抗拔钢筋、钢筋笼、混凝土桩身与载体共同构成载体桩,实现桩体基本的支撑承载功能,抗拉纵筋的两端与混凝土桩身、水泥砂浆拌合物的连接,锚固力更强,根据需要,抗拉纵筋可向上延伸进入承台或筏板,进一步加强本发明载体桩的整体承载能力;2. The uplift steel bar, steel cage, concrete pile body and the carrier together form the carrier pile, which realizes the basic support and bearing function of the pile body. Stronger, according to needs, the tensile longitudinal reinforcement can extend upward into the platform or the raft, further enhancing the overall bearing capacity of the carrier pile of the present invention;

3.采用空心柱锤对本发明的载体桩进行施工,在抗拔钢筋处于桩孔内时,同样能够对桩孔底部填料进行锤击,方便了抗拔钢筋底端与填料的紧密连接,降低了施工难度,减少了人工劳作力,提高了工作效率,保障了本发明载体桩的底端结构强度,减少对抗拔钢筋本身的影响;3. The carrier pile of the present invention is constructed by using a hollow column hammer. When the pull-resistant steel bar is in the pile hole, the bottom filler of the pile hole can also be hammered, which facilitates the close connection between the bottom end of the pull-resistant steel bar and the filler, and reduces the impact of the pull-resistant steel bar. The construction difficulty is reduced, the manual labor is reduced, the work efficiency is improved, the bottom end structural strength of the carrier pile of the present invention is guaranteed, and the influence of the anti-pulling steel bar itself is reduced;

4.本发明充分将地基处理和基础施工合二为一,降低地基处理费用,极大改善了载体桩的承载性能,因地制宜,能够根据不同地形条件,调整载体桩的施工控制参数,能够任意改变单桩竖向承载力极限特征值,更好地满足工程需要。4. The present invention fully integrates foundation treatment and foundation construction, reduces the cost of foundation treatment, greatly improves the bearing performance of the carrier pile, and can adjust the construction control parameters of the carrier pile according to different terrain conditions according to local conditions, and can be arbitrarily changed. The limit characteristic value of the vertical bearing capacity of a single pile can better meet the engineering needs.

附图说明Description of drawings

图1是本发明中实施例一的载体桩整体结构示意图;图2是本发明中抗拉纵筋与帮焊钢筋的连接结构示意图;1 is a schematic diagram of the overall structure of the carrier pile according to the first embodiment of the present invention; FIG. 2 is a schematic diagram of the connection structure of the tensile longitudinal reinforcement and the welding reinforcement in the present invention;

图3是本发明中抗拉纵筋与钢筋笼体的连接结构示意图;Fig. 3 is the connection structure schematic diagram of tensile longitudinal reinforcement and reinforcement cage in the present invention;

图4是本发明中空心柱锤的结构示意图一;Fig. 4 is the structural representation one of the hollow cylinder hammer of the present invention;

图5是本发明中空心柱锤的结构示意图二;Fig. 5 is the structural representation two of the hollow cylinder hammer of the present invention;

图6是本发明中空心柱锤的结构示意图三;Fig. 6 is the structural representation three of the hollow cylinder hammer of the present invention;

图7是图4中A部分的局部放大示意图;Fig. 7 is the partial enlarged schematic diagram of A part in Fig. 4;

图8是本发明中实施例一的施工工艺流程示意图;8 is a schematic diagram of a construction process flow diagram of Embodiment 1 of the present invention;

图9是本发明中实施例二的载体桩整体结构示意图;9 is a schematic diagram of the overall structure of the carrier pile of the second embodiment of the present invention;

图10是本发明中实施例三的载体桩整体结构示意图;Figure 10 is a schematic diagram of the overall structure of the carrier pile according to the third embodiment of the present invention;

图11是本发明中实施例二和实施例三的施工工艺流程示意图;11 is a schematic diagram of the construction process flow of Embodiment 2 and Embodiment 3 of the present invention;

图12是本发明中实施例五的载体桩整体结构示意图。12 is a schematic diagram of the overall structure of the carrier pile according to the fifth embodiment of the present invention.

附图标记:1、抗拉纵筋;2、定位环;3、帮焊钢筋;4、混凝土桩身;5、填充料;6、挤密土体;7、影响土体;8、钢筋笼体;9、预制桩;10、水泥砂浆注浆体;11、管桩孔;12、钢筋笼纵筋;13、螺旋箍筋;14、加劲筋;15、承台;16、筏板;17、钢筒;18、扩大盘;19、贯入通孔;20、保护垫块;21、支耳;22、连接杆;23、抵接钢片;24、加强钢筋。Reference signs: 1. Tensile longitudinal reinforcement; 2. Positioning ring; 3. Welding reinforcement; 4. Concrete pile body; 5. Filling material; 6. Compacted soil; 7. Influenced soil; 8. Steel cage 9. Prefabricated piles; 10. Cement mortar grouting body; 11. Pipe pile holes; 12. Longitudinal reinforcement of steel cages; 13. Spiral stirrups; 14. Stiffeners; 15. Caps; 16. Rafts; 17 , steel cylinder; 18, expansion plate; 19, through hole; 20, protective pad; 21, lug; 22, connecting rod; 23, abutting steel sheet; 24, reinforcing steel bar.

具体实施方式Detailed ways

以下结合附图对本发明作进一步详细说明。The present invention will be further described in detail below with reference to the accompanying drawings.

实施例一本发明公开的抗拔钢筋、载体桩、施工用空心柱锤及载体桩施工工艺。Embodiment 1 The invention discloses the construction process of the anti-pulling steel bar, the carrier pile, the hollow column hammer for construction and the carrier pile.

抗拔钢筋,参照图1,位于载体桩内部且被捶入桩孔内,抗拉钢筋包括多根固定成一束的抗拉纵筋1,抗拉纵筋1采用的是HRB400级的螺纹钢,参照图2,本实施例中的抗拉纵筋1优选为三个,三个抗拉纵筋1相互夹角成120度排列,三个抗拉纵筋1通过中间的帮焊钢筋3双面焊接实现连接,抗拉纵筋1的底端均为85-95度弯曲状设置。参照图1,本实施例中优选为90度弯折设置,三个抗拉纵筋1的弯折段均朝向远离帮焊钢筋3的方向延伸,且相邻抗拉纵筋1的底端沿桩孔的内径方向间隔排布,间隔角度为120度。利用底端弯折成型的抗拉纵筋1作为联接件,结构稳定,整体受力均匀,抗拉纵筋1底端呈85-95度弯曲状,使得抗拉纵筋1的底端处于桩孔底端时,抗拉纵筋1与桩孔底端的填料相互的牵引力和约束力更大,使得载体桩整体稳定性更强。The pull-out steel bar, referring to Figure 1, is located inside the carrier pile and is hammered into the pile hole. The tensile steel bar includes a plurality of tensile longitudinal bars 1 fixed into a bundle. Referring to FIG. 2 , the number of tensile longitudinal ribs 1 in this embodiment is preferably three, and the three tensile longitudinal ribs 1 are arranged at a 120-degree angle to each other. The connection is realized by welding, and the bottom ends of the tensile longitudinal bars 1 are all bent at 85-95 degrees. Referring to FIG. 1 , in this embodiment, it is preferably set by bending at 90 degrees, and the bending sections of the three tensile longitudinal bars 1 all extend in the direction away from the welding reinforcement bars 3, and the bottom ends of the adjacent tensile longitudinal bars 1 are along the The inner diameter of the pile holes is arranged at intervals, and the interval angle is 120 degrees. The tensile longitudinal rib 1 formed by bending the bottom end is used as a connecting piece, the structure is stable, and the overall force is uniform. At the bottom end of the hole, the mutual traction force and binding force of the tensile longitudinal reinforcement 1 and the filler at the bottom end of the pile hole are greater, so that the overall stability of the carrier pile is stronger.

参照图3,多根抗拉纵筋1共同周侧环绕有定位环2。通过定位环2和帮焊钢筋3实现相邻抗拉纵筋1的固定连接,同时起到减少抗拉纵筋1变形的作用,分散施加至抗拉纵筋1上的载荷整体结构承载能力,抗剪能力更强。Referring to FIG. 3 , a positioning ring 2 surrounds the common peripheral side of the plurality of tensile longitudinal ribs 1 . The fixed connection of the adjacent tensile bars 1 is achieved through the positioning ring 2 and the welding reinforcement bars 3, and at the same time, the deformation of the tensile bars 1 is reduced, and the overall structural bearing capacity of the load applied to the tensile bars 1 is dispersed. Stronger shear resistance.

载体桩,参照图1,包括沿桩孔的轴向从上至下依次排布的混凝土桩身4、填充料5、挤密土体6、影响土体7,混凝土桩身4的桩芯采用的是抗拉纵筋1,抗拉纵筋1的底端延伸至填充料5内,混凝土桩身4还包括设置于抗拔钢筋周侧的多个钢筋笼体8,多个钢筋笼体8沿抗拔钢筋的轴线方向依次排布设置,桩孔内于抗拔钢筋和钢筋笼体8之间填充有混凝土,挤密土体6采用水泥砂干硬性混凝土和原状土混合挤密而成,影响土体7为桩孔底部受到夯击的原状土体。本发明利用底端弯折成型的抗拉纵筋1作为抗拉钢筋,通过抗拉纵筋1与钢筋笼、混凝土桩身4共同构成载体桩的上部载体,实现桩体上部基本的支撑承载功能,结合填充料5、挤密土体6、影响土体7形成载体桩的下部复合载体球体,该下部复合载体球体直径远远大于上部载体,结合抗拉纵筋1将上部混凝土桩身4和下部填充料5的连接牵制,最终极大地增大了载体桩整体的竖向抗压和抗拔承载力,本发明具备抗压抗拔的功能,因桩身和载体连成一体增加了桩身的抗剪切能力,结构经济简单,施工速度快。The carrier pile, referring to Figure 1, includes a concrete pile body 4, a filler 5, a compacted soil body 6, and an impact soil body 7, which are sequentially arranged along the axial direction of the pile hole from top to bottom. The core of the concrete pile body 4 adopts The bottom end of the tensile longitudinal reinforcement 1 extends into the filler 5, and the concrete pile body 4 also includes a plurality of reinforcement cages 8 arranged on the peripheral side of the pullout reinforcement. They are arranged in sequence along the axial direction of the pull-up steel bars. The pile holes are filled with concrete between the pull-up steel bars and the steel cage body 8. The compacted soil body 6 is made of cement sand dry hard concrete and undisturbed soil. The affected soil body 7 is the undisturbed soil body subjected to ramming at the bottom of the pile hole. The present invention utilizes the anti-tensile longitudinal bars 1 formed by bending the bottom end as the anti-tensile steel bars, and the upper carrier of the carrier pile is formed by the anti-tensile longitudinal bars 1, the reinforcement cage and the concrete pile body 4 together, so as to realize the basic supporting and bearing function of the upper part of the pile body. , combined with filler 5, compacted soil 6, and affected soil 7 to form the lower composite carrier sphere of the carrier pile. The diameter of the lower composite carrier sphere is much larger than that of the upper carrier. Combined with the tensile longitudinal reinforcement 1, the upper concrete pile body 4 and the The connection and restraint of the lower filling material 5 ultimately greatly increases the vertical compressive and uplift bearing capacity of the whole carrier pile. High shear resistance, economical and simple structure, and fast construction speed.

参照图3,钢筋笼体8包括多个钢筋笼纵筋12、螺旋箍筋13、加劲筋14,多个钢筋笼纵筋12沿桩孔轴线方向等间距排列于抗拔钢筋周侧,钢筋笼纵筋12的周侧共同环绕固定连接有螺旋箍筋13,多个钢筋笼纵筋12的内壁共同连接有多个所述加劲筋14。利用多个钢筋笼纵筋12共同构成钢筋笼体8,结构简单易于制作,利用螺旋箍筋13和加劲筋14实现钢筋笼纵筋12的加强连接,减少相邻钢筋笼纵筋12的变形以及脱落的情况,使得钢筋笼体8结构更加稳定。3, the reinforcement cage body 8 includes a plurality of reinforcement cage longitudinal bars 12, spiral stirrups 13, and stiffeners 14. A plurality of reinforcement cage longitudinal reinforcement bars 12 are arranged at equal intervals along the axis direction of the pile hole on the periphery of the pull-out reinforcement bars. The circumferential sides of the longitudinal bars 12 are jointly connected with the spiral stirrups 13 , and the inner walls of the plurality of longitudinal bars 12 of the reinforcing cage are commonly connected with a plurality of the stiffening bars 14 . The reinforcement cage body 8 is formed by using a plurality of reinforcement cage longitudinal bars 12, and the structure is simple and easy to manufacture. The spiral stirrups 13 and the stiffeners 14 are used to realize the reinforced connection of the reinforcement cage longitudinal reinforcement bars 12, thereby reducing the deformation of the adjacent reinforcement cage longitudinal reinforcement bars 12 and the In the case of falling off, the structure of the steel cage body 8 is more stable.

相邻钢筋笼体8之间以及钢筋笼纵筋12的纵筋与加劲筋14之间均采用单面搭接焊实现连接。采用单面搭接焊的方式实现钢筋笼体8连接,连接稳定,便于现场快速操作,施工效率高。The connection between the adjacent reinforcement cage bodies 8 and the longitudinal reinforcement of the reinforcement cage longitudinal reinforcement 12 and the reinforcement reinforcement 14 is realized by single-sided lap welding. The steel cage body 8 is connected by single-sided lap welding, the connection is stable, it is convenient for on-site quick operation, and the construction efficiency is high.

螺旋箍筋13的外周侧固定连接有多个保护垫块20,多个保护垫块20沿抗拉纵筋1的周向方向等间距排列设置。在桩孔内下放钢筋笼时,利用保护垫块20对螺旋箍筋13进一步进行限位,使钢筋笼体8位于桩孔的正中心,保证钢筋笼纵筋12混凝土保护层厚度,保持钢筋笼纵筋12的承载能力,受力更加均匀。A plurality of protective pad blocks 20 are fixedly connected to the outer peripheral side of the spiral stirrup 13 , and the plurality of protective pad blocks 20 are arranged at equal intervals along the circumferential direction of the tensile longitudinal rib 1 . When laying down the reinforcement cage in the pile hole, the spiral stirrup 13 is further limited by the protective pad 20, so that the reinforcement cage body 8 is located in the center of the pile hole, so as to ensure the thickness of the concrete protective layer of the longitudinal reinforcement of the reinforcement cage 12 and keep the reinforcement cage. The bearing capacity of the longitudinal bars 12 is more uniform.

施工用空心柱锤,参照图4与图5,包括钢筒17,钢筒17的一端同轴固定连接有扩大盘18,扩大盘18的直径大小大于钢筒17直径大小设置,参照图6,钢筒17和扩大盘18共同同轴开设有便于抗拔钢筋贯入的贯入通孔19。钢筒17和扩大盘18实现了基础锤击功能,扩大盘18便于对桩孔底部更大面积的填料进行锤击,结构简单易于制作,锤击效果稳定,与现有的重锤相比,特点在于贯入通孔19便于贯入抗拔钢筋,空心柱锤较好地解决了因本发明结构的特殊性而带来的施工困难,抗拔钢筋处于桩孔内时,同时能够对桩孔底部填料进行锤击,方便了抗拔钢筋底端与填料的紧密连接,减少了施工难度和人工劳作力,抗拉纵筋1为一体成型,在重锤夯击作用下不会发生断裂等情况,同时方便了抗拔钢筋底端与填料的紧密连接,保障了本发明载体桩的底端结构强度,减少对抗拔钢筋本身的影响。The hollow column hammer for construction, referring to Figure 4 and Figure 5, includes a steel cylinder 17, one end of the steel cylinder 17 is fixedly connected with an enlarged disk 18, and the diameter of the enlarged disk 18 is set larger than the diameter of the steel cylinder 17, with reference to Figure 6, The steel cylinder 17 and the enlarged disc 18 are coaxially provided with through holes 19 for facilitating the penetration of the pull-out steel bars. The steel cylinder 17 and the expansion plate 18 realize the basic hammering function. The expansion plate 18 is convenient for hammering a larger area of filler at the bottom of the pile hole. The structure is simple and easy to manufacture, and the hammering effect is stable. Compared with the existing heavy hammer, The characteristic is that the penetration through hole 19 is convenient for penetrating the anti-pulling steel bar, and the hollow column hammer can better solve the construction difficulties caused by the particularity of the structure of the present invention. When the anti-pulling steel bar is in the pile hole, it can simultaneously The bottom filler is hammered, which facilitates the close connection between the bottom end of the anti-pulling steel bar and the filler, and reduces the difficulty of construction and manual labor. At the same time, the close connection between the bottom end of the anti-pulling steel bar and the filler is facilitated, the structural strength of the bottom end of the carrier pile of the present invention is guaranteed, and the influence of the anti-pulling steel bar itself is reduced.

钢筒17与扩大盘18为焊接连接。焊接连接的钢筒17和扩大盘18便于后期将钢筒17和扩大盘18进行裁断,根据桩孔以及填料的规格大小,在钢筒17上更换面积大小、厚度大小等参数不同的扩大盘18,更加实用,应用范围更加广泛。The steel cylinder 17 and the expansion disc 18 are connected by welding. The steel cylinder 17 and the expansion disc 18 connected by welding are convenient for cutting the steel cylinder 17 and the expansion disc 18 in the later stage. According to the specifications of the pile hole and the filler, the expansion disc 18 with different parameters such as area size and thickness is replaced on the steel cylinder 17. , which is more practical and has a wider range of applications.

参照图7,钢筒17远离扩大盘18的一端固定连接有两个支耳21,两个支耳21沿钢筒17的轴线对称设置,两个支耳21共同预制穿有连接杆22,连接杆22的轴线与钢筒17的轴线垂直设置,连接杆22的两端同轴固定连接有抵接于支耳21的抵接钢片23,两个支耳21和连接杆22共同构成“门”字形结构。应用过程中,通过卷扬机与连接杆22的连接,实现空心柱锤的吊装,从而便于后续的锤击工作。Referring to FIG. 7 , two lugs 21 are fixedly connected to one end of the steel cylinder 17 away from the expansion plate 18 . The two lugs 21 are symmetrically arranged along the axis of the steel cylinder 17 . The axis of the rod 22 is perpendicular to the axis of the steel cylinder 17, and both ends of the connecting rod 22 are coaxially and fixedly connected with abutting steel sheets 23 abutting against the lugs 21. The two lugs 21 and the connecting rod 22 together form a "door". ” glyph structure. During the application process, the hoisting of the hollow column hammer is realized through the connection between the hoist and the connecting rod 22, so as to facilitate the subsequent hammering work.

连接钢管于两个支耳21所处的一端且于两个支耳21之间固定连接有加强钢筋24,加强钢筋24呈“T”字形设置。利用加强钢筋24和加强肋板加强两个支耳21与钢筒17之间的连接面更大,连接强度更高,更加稳定。The connecting steel pipe is at one end where the two lugs 21 are located, and a reinforcing bar 24 is fixedly connected between the two lugs 21 , and the reinforcing bars 24 are arranged in a "T" shape. The connection surface between the two lugs 21 and the steel cylinder 17 is strengthened by the reinforcing steel bar 24 and the reinforcing rib plate, the connection strength is higher, and the connection is more stable.

载体桩施工工艺,参照图8,包括以下步骤:S1:测量放线成孔,依据规划定点将建筑物的总平图上的主控点测放完毕,经监理验线合格后,再进行桩位点的测放,误差控制在2cm之内,在土层准确设置锤出钢套筒底的标记,预备钢套筒、重锤、主卷扬机和副卷扬机,将钢套筒中心与桩位中心点对齐下压,上部土层一米低锤重压,调整钢套筒垂直度,使其严格控制在1%范围内,同时在下钢套筒过程中要随时调整其垂直度,以防止钢套筒垂直度超偏,通过主卷扬机快速提升及快速落放重锤,重锤土层逐段锤击成孔;The construction process of the carrier pile, referring to Fig. 8, includes the following steps: S1: measure and lay out the line to form a hole, complete the measurement and release of the main control point on the general plan of the building according to the planning and fixed point, and then carry out the pile after passing the line inspection by the supervisor. The measurement and placement of the site, the error is controlled within 2cm, the mark on the bottom of the hammered steel sleeve is accurately set in the soil layer, the steel sleeve, the heavy hammer, the main hoist and the auxiliary hoist are prepared, and the center of the steel sleeve is aligned with the center of the pile position. Points are aligned and pressed down, the upper soil layer is pressed with a low hammer of one meter, and the verticality of the steel sleeve is adjusted to be strictly controlled within the range of 1%. The verticality of the drum is over-biased, and the main hoist is used to quickly lift and quickly drop the heavy hammer, and the heavy hammer hammers the soil layer by section to form holes;

S2:沉放钢套筒,重锤成孔过程中,利用副卷扬机反压钢套筒,在沉管过程中要随时从两个方向观测钢套筒垂直度和沉管对位偏移情况,当钢套筒接近桩底标高时,控制重锤落距,准确将钢套筒沉至设计标高,主要采用锤击跟管、振动锤、柴油锤、液压锤等沉管方式,也可采用旋挖、长螺旋等辅助引孔方式沉孔;S2: sink the steel sleeve, and use the auxiliary winch to counter pressure the steel sleeve during the process of hammering the hole. During the sinking process, observe the verticality of the steel sleeve and the alignment offset of the sinking tube from two directions at any time. When the steel sleeve is close to the elevation of the pile bottom, control the drop distance of the heavy hammer to accurately sink the steel sleeve to the design elevation. Auxiliary drilling methods such as digging and long spiral countersinking;

S3:填充料5夯击,钢套筒沉放至持力层后,提升重锤,并往钢套筒内投入一定量填充料S3: The filler 5 is rammed. After the steel sleeve is placed on the bearing layer, the weight is lifted, and a certain amount of filler is put into the steel sleeve.

5,每次填料量为0.015 0.045立方米,必要时为了防水和清泥可以使用少量的砖渣和石块,~5. The amount of each filling is 0.015 0.045 cubic meters. If necessary, a small amount of brick slag and stones can be used for waterproofing and mud removal. ~

主卷扬机下放重锤做自由落体动作,多次夯击填充料5,使得桩孔底端的土体被夯实挤密形成挤密土体6和影响土体7,其中,填充料5为水泥砂拌合物或干硬性混凝土;The main hoist lowers the heavy hammer to perform a free-fall action, ramming the filler 5 for many times, so that the soil at the bottom of the pile hole is compacted and compacted to form the compacted soil 6 and the affected soil 7, wherein the filler 5 is a cement-sand mix. composite or dry hard concrete;

S4:测量三击贯入度,填充料5完成形成密实载体状态后,主卷扬机提升重锤底至孔底S4: Measure the penetration of the three strikes. After the filler 5 is formed into a dense carrier state, the main hoist lifts the bottom of the heavy hammer to the bottom of the hole

5-7m的高度,快速落放重锤,使重锤做自由落体运动,测量三击贯入度,若不满足设计要求,继续在桩孔内填充料5并锤击填充料5,直至满足三击贯入度要求;At a height of 5-7m, drop the heavy hammer quickly, make the heavy hammer do free fall movement, measure the penetration of the three strikes, if it does not meet the design requirements, continue to fill the pile hole with filler 5 and hammer the filler 5 until it meets the requirements. Three-strike penetration requirements;

S5:下放抗拉纵筋1,在桩孔内下放抗拔钢筋;S5: Lower the tensile longitudinal reinforcement 1, and lower the tensile reinforcement in the pile hole;

S6:空心柱锤夯击填料,抗拔钢筋下放后,主卷扬机将空心柱锤沉放至桩孔内,同时抗拔钢筋处于贯入通孔19内,继续分次填入填充料5,主卷扬机提升及快速落放空心柱锤,多次夯击填充料5直至抗拉纵筋1进入载体不小于40-60cm,抗拉纵筋1在重锤带动下,底部一定角度弯曲部分嵌入填充料5中,上部嵌入混凝土桩身4中,使混凝土桩身4与填充料5牢固连接;S6: The hollow column hammer rams the filler, and after the pull-out steel bars are lowered, the main winch sinks the hollow column hammer into the pile hole, while the pull-out steel bars are in the through-hole 19, and the filling material 5 is filled in stages. The hoist lifts and quickly drops the hollow column hammer, and rams the filler material 5 several times until the tensile longitudinal rib 1 enters the carrier of not less than 40-60cm. 5, the upper part is embedded in the concrete pile body 4, so that the concrete pile body 4 and the filler 5 are firmly connected;

S7:安装钢筋笼,现场预制钢筋笼体8,通过卷扬机将钢筋笼体8吊起并放入钢套筒内,并将抗拉纵筋1穿入钢筋笼体8的内侧定位环2内,测量钢筋笼体8标高并调整钢筋笼标高在允许误差范围内;S7: Install the reinforcement cage, prefabricate the reinforcement cage body 8 on site, hoist the reinforcement cage body 8 by the hoist and put it into the steel sleeve, and insert the tensile longitudinal reinforcement 1 into the inner positioning ring 2 of the reinforcement cage body 8, Measure the height of the steel cage body 8 and adjust the height of the steel cage within the allowable error range;

S8:浇注混凝土,在钢套筒内浇筑混凝土浆,测量并控制浇筑混凝土桩身4的标高,控制桩顶标高在允许误差范围内,控制每根桩实测混凝土塌落度180 220mm,灌注好的桩身混凝~S8: Pour concrete, pour concrete slurry in the steel sleeve, measure and control the elevation of the poured concrete pile body 4, control the elevation of the top of the pile within the allowable error range, and control the measured concrete slump of each pile to 180-220mm. Pile body concrete~

土充盈系数大于1.1,按规范超灌0.8m以上;The soil filling coefficient is greater than 1.1, and the overfill is more than 0.8m according to the specification;

S9:拔套筒,通过桩机副卷扬将钢套筒从桩孔内拔出,控制拔出速度,必要时采用停拔措施。S9: Pull out the sleeve, pull out the steel sleeve from the pile hole through the auxiliary winch of the pile driver, control the pull-out speed, and take measures to stop pulling if necessary.

钢套筒全部拔出后,人工用振捣棒振捣。振捣基本采用一插到底,快插慢拔的原则。如有少量桩振捣不下的,将振捣棒放在钢筋笼上适当振捣,用来保证桩身混凝土密实度和达到设计强度。After all the steel sleeves are pulled out, manually vibrate with a vibrator. The vibrator basically adopts the principle of one insertion to the end, fast insertion and slow extraction. If there is a small amount of piles that cannot be vibrated, place the vibrating rod on the steel cage to vibrate properly to ensure the concrete density of the pile body and the design strength.

本实施例的实施原理为:本发明利用底端弯折成型的抗拉纵筋1作为抗拉钢筋,通过抗拉纵筋1与钢筋笼、混凝土桩身4与载体共同构成载体桩。实现桩体上部基本的支撑承载功能,结合水泥砂浆拌合物或干硬性混凝土、挤密土体6、影响土体7形成载体桩的复合载体,本发明利用抗拉纵筋1将上部混凝土桩身4和下部水泥浆拌合物或干硬性混凝土的连接牵制,本发明解决了载体桩同时具备抗压抗拔的功能,因桩身和载体连成一体增加了桩身的抗剪切能力;The implementation principle of this embodiment is as follows: the present invention uses the tensile longitudinal reinforcement 1 formed by bending the bottom end as the tensile reinforcement, and the tensile longitudinal reinforcement 1 and the reinforcement cage, the concrete pile body 4 and the carrier together constitute the carrier pile. To realize the basic support and bearing function of the upper part of the pile body, combined with the cement mortar mixture or dry hard concrete, the compacted soil body 6, and the impact soil body 7 to form a composite carrier of the carrier pile, the present invention uses the tensile longitudinal reinforcement 1 to connect the upper concrete pile. The connection and restraint between the body 4 and the lower cement slurry mixture or dry-hard concrete, the invention solves the problem that the carrier pile has the functions of resisting compression and uplift at the same time, and the shear resistance of the pile body is increased because the pile body and the carrier are integrated into one body;

空心柱锤较好地解决了因本发明结构的特殊性而带来的施工困难,在抗拔钢筋处于桩孔内时,同样能够对桩孔底部填料进行锤击,方便了抗拔钢筋底端与填料的紧密连接,保障施工质量的基础上,提高了施工效率,本发明充分将地基处理和基础施工合二为一,降低地基处理费用,极大改善了载体桩的承载性能,更好地满足工程需要。The hollow column hammer can better solve the construction difficulties caused by the particularity of the structure of the present invention. When the anti-pulling steel bars are in the pile holes, they can also hammer the bottom fillers of the pile holes, which is convenient for the bottom ends of the anti-pulling steel bars. The close connection with the filler improves the construction efficiency on the basis of ensuring the construction quality. The invention fully integrates the foundation treatment and the foundation construction, reduces the foundation treatment cost, greatly improves the bearing performance of the carrier pile, and better meet engineering needs.

实施例二与实施例一的不同之处在于:The difference between the second embodiment and the first embodiment is:

参照图9,混凝土桩身4包括预制桩9和水泥砂浆注浆体10,预制桩9由混凝土和多个钢筋笼体8预制而成,预制桩9为圆管状管桩或方管状管桩,预制桩9中心形成用于容纳抗拉纵筋1的管桩孔11,管桩孔11内于抗拉纵筋1周围浇注有水泥砂浆形成水泥砂浆注浆体10,混凝土桩身4的桩端设置有承台15和筏板16,混凝土桩身4内的多个抗拉纵筋1远离弯折段的一端均向上延伸至承台15内。9, the concrete pile body 4 includes a prefabricated pile 9 and a cement mortar grouting body 10, the prefabricated pile 9 is prefabricated by concrete and a plurality of steel cages 8, and the prefabricated pile 9 is a round tubular pipe pile or a square tubular pipe pile, A pipe pile hole 11 for accommodating the tensile longitudinal reinforcement 1 is formed in the center of the prefabricated pile 9, and cement mortar is poured around the tensile longitudinal reinforcement 1 in the pipe pile hole 11 to form a cement mortar grouting body 10. The pile end of the concrete pile body 4 A cap 15 and a raft 16 are provided, and the ends of the plurality of tensile longitudinal bars 1 in the concrete pile body 4 away from the bending section all extend upward into the cap 15 .

实施例三与实施例二的不同之处在于:The difference between the third embodiment and the second embodiment is:

参照图10,混凝土桩身4内的多个抗拉纵筋1远离弯折段的一端均未进入至承台15和筏板16内。Referring to FIG. 10 , one end of the plurality of tensile longitudinal bars 1 in the concrete pile body 4 away from the bending section does not enter into the bearing platform 15 and the raft 16 .

实施例二和实施例三的载体桩施工工艺相同,具体为:上述两实施例的步骤S1-S6以及步骤S9与实施例一的步骤S1-S6和步骤S9相同,参照图11,与实施例一的不同之处在于:The construction techniques of the carrier piles in the second embodiment and the third embodiment are the same, specifically: the steps S1-S6 and step S9 of the above two embodiments are the same as the steps S1-S6 and step S9 of the first embodiment, referring to FIG. 11, the same as the embodiment The difference is that:

S7:安装预制桩9,将多个钢筋笼体8和混凝土预制形成预制桩9,通过卷扬机将预制桩9吊起并放入钢套筒内,并将抗拉纵筋1穿入预制桩9的管桩孔11内,测量预制桩9标高并调整预制桩9在允许误差范围内,控制桩顶标高在允许误差范围内,控制每根桩实测混凝土塌落度180 220mm;S7: Install the prefabricated piles 9, prefabricate a plurality of reinforcement cages 8 and concrete to form the prefabricated piles 9, hoist the prefabricated piles 9 through a hoist and put them into the steel sleeve, and thread the tensile longitudinal bars 1 into the prefabricated piles 9 In the pipe pile hole 11, measure the elevation of the prefabricated pile 9 and adjust the prefabricated pile 9 within the allowable error range, control the pile top elevation within the allowable error range, and control the measured concrete slump of each pile to 180-220mm;

S8:浇筑水泥砂浆,在预制桩9内浇筑水泥砂浆,测量并控制浇筑水泥砂浆的标高;S8: pouring cement mortar, pouring cement mortar in the prefabricated pile 9, measuring and controlling the elevation of the pouring cement mortar;

上述两实施例的实施原理及有益效果为:The implementation principles and beneficial effects of the above two embodiments are:

通过在预制形成结构稳定的预制桩9,受力较为稳定,具有较好的支承力和抗剪力,适应能力强,使用预制的预制桩,施工方式简单,提高了施工效率,降低了施工成本。By forming prefabricated prefabricated piles 9 with stable structure in prefabrication, the force is relatively stable, with better supporting force and shear resistance, and strong adaptability. Using prefabricated prefabricated piles, the construction method is simple, the construction efficiency is improved, and the construction cost is reduced. .

实施例四与实施例一的不同之处在于:The difference between the fourth embodiment and the first embodiment is:

参照图1,混凝土桩身4的桩端设置有承台15和筏板16,混凝土桩身4内的多个抗拉纵筋Referring to FIG. 1 , the pile end of the concrete pile body 4 is provided with a bearing platform 15 and a raft 16 , and a plurality of tensile longitudinal bars in the concrete pile body 4 are provided.

1远离弯折段的一端均向上延伸至承台15内。利用筏板16与钢筋笼体8和抗拉纵筋1的连接,加强载体桩整体结构强度。1. One end away from the bending section extends upward into the platform 15. The overall structural strength of the carrier pile is strengthened by the connection between the raft 16 and the reinforcement cage 8 and the tensile longitudinal reinforcement 1 .

实施例五与实施例四的不同之处在于:The difference between the fifth embodiment and the fourth embodiment is:

参照图12,混凝土桩身4内的多个抗拉纵筋1远离弯折段的一端均未进入至承台15和筏板16内。Referring to FIG. 12 , one end of the plurality of tensile longitudinal bars 1 in the concrete pile body 4 away from the bending section does not enter into the bearing platform 15 and the raft 16 .

本实施例的实施原理及有益效果为:施工过程中,出现桩长长度大小大于空心柱锤长度大小时,在抗拉纵筋1实现复合载体和混凝土桩身4连接后,可选择抗拉纵筋1不延伸至承台15和筏板16内,减小抗拉纵筋1对空心柱锤的连接杆22与卷扬机连接的影响,更好地满足实际施工工艺需求,保障施工效率。The implementation principle and beneficial effects of this embodiment are: in the construction process, when the length of the pile is greater than the length of the hollow column hammer, after the tensile longitudinal reinforcement 1 realizes the connection between the composite carrier and the concrete pile body 4, the tensile longitudinal reinforcement can be selected. The rib 1 does not extend into the platform 15 and the raft 16, reducing the influence of the tensile longitudinal rib 1 on the connection between the connecting rod 22 of the hollow column hammer and the hoist, better meeting the actual construction process requirements and ensuring construction efficiency.

实施例六与实施例一的不同之处在于:The difference between the sixth embodiment and the first embodiment is:

多个抗拉纵筋1的数量选择为四个、五个、六个中的其中一种数量,四个抗拉纵筋1相互夹角呈90度排列设置,五个抗拉纵筋1的相互夹角呈72度排列设置,以此类推。The number of the plurality of tensile longitudinal ribs 1 is selected as one of four, five, and six. The four tensile longitudinal ribs 1 are arranged at a 90-degree angle to each other. They are arranged at an angle of 72 degrees to each other, and so on.

本实施例的实施原理及有益效果为:不同数量的抗拉纵筋1构成的抗拔钢筋具有不同的抗拉力值,根据现场计算出的不同载体桩的抗拔力的不同,选择不同数量的抗拉纵筋1,保障载体桩的结构稳定性,更好地满足施工需求。The implementation principle and beneficial effects of this embodiment are as follows: the pull-out steel bars composed of different numbers of tensile longitudinal bars 1 have different tensile force values. The tensile longitudinal reinforcement 1 ensures the structural stability of the carrier pile and better meets the construction needs.

实施例七与实施例一的不同之处在于:The difference between Embodiment 7 and Embodiment 1 is:

多个抗拉纵筋1采用捆绑钢筋围绕扎紧实现连接,并在捆绑钢筋与抗拉纵筋1的贴合处采用单面搭接焊进行焊接。操作方便,便于现场施工,连接强度高。The plurality of tensile longitudinal bars 1 are connected by bundling steel bars around and fastened, and are welded by single-sided lap welding at the joint of the bundled steel bars and the tensile longitudinal bars 1 . It is easy to operate, convenient for on-site construction, and has high connection strength.

实施例八与实施例一的不同之处在于:The difference between the eighth embodiment and the first embodiment is:

抗拉纵筋1的底端为85-90度弯曲状设置。抗拉纵筋1的底端于远离帮焊钢筋3的一侧弯曲角度为锐角,使得抗拉纵筋1的弯折部与复合载体之间的抗拉强度更高,进一步加强载体桩整体的抗拉强度和抗剪力。The bottom end of the tensile longitudinal rib 1 is bent at an angle of 85-90 degrees. The bending angle of the bottom end of the tensile longitudinal reinforcement 1 is an acute angle on the side away from the welding reinforcement 3, so that the tensile strength between the bending part of the tensile longitudinal reinforcement 1 and the composite carrier is higher, and the overall strength of the carrier pile is further strengthened. Tensile strength and shear resistance.

本具体实施方式的实施例均为本发明的较佳实施例,并非依此限制本发明的保护范围,故:凡依本发明的结构、形状、原理所做的等效变化,均应涵盖于本发明的保护范围之内。The embodiments of this specific embodiment are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore: all equivalent changes made according to the structure, shape and principle of the present invention should be covered in within the protection scope of the present invention.

Claims (5)

1. The carrier pile construction process comprises a concrete pile body (4), a filling material (5), an influence soil body (7) and a compaction soil body (6), and is characterized by comprising the following steps:
s1: measuring and paying off for pore forming, accurately setting a pile hole mark, and hammering a heavy hammer soil layer section by section at the pile hole mark position for pore forming;
s2: sinking a steel sleeve, and sinking the steel sleeve to a design elevation in a heavy punch hole forming process;
s3: tamping the filler, namely filling the filler by times after the steel sleeve is sunk to the bearing stratum, and tamping the filler for multiple times;
s4: measuring the three-hit penetration degree, after the filling is finished to form a compact carrier state, lifting the bottom of a heavy hammer to the height of 5-7m of the bottom of the hole by a main winch, quickly dropping the heavy hammer to enable the heavy hammer to do free-fall motion, measuring the three-hit penetration degree, and if the design requirement is not met, continuously filling and hammering the filling material (5) in the pile hole until the three-hit penetration degree requirement is met;
s5: lowering the tensile longitudinal bar (1), and lowering the anti-pulling steel bar in the pile hole;
s6: tamping filler by a hollow column hammer, after the anti-pulling steel bars are lowered, sinking the hollow column hammer into a pile hole, wherein the hollow column hammer comprises a steel cylinder (17), one end of the steel cylinder (17) is coaxially and fixedly connected with an expansion disc (18), the steel cylinder (17) and the expansion disc (18) are coaxially provided with a through hole (19) which is convenient for the anti-pulling steel bars to be injected into, meanwhile, the anti-pulling steel bars are positioned in the through hole (19), continuously filling the filler in batches, and tamping the filler for multiple times until the tensile longitudinal bars (1) enter a carrier and are not less than 40-60 cm; the anti-pulling steel bar comprises a plurality of anti-pulling longitudinal bars (1) and is welded and fixed into a bundle by utilizing a middle side welding steel bar (3), the periphery sides of the anti-pulling longitudinal bars (1) are also commonly surrounded by positioning rings (2), the bottom ends of the anti-pulling longitudinal bars (1) extend into the filling material (5) under the driving of a heavy hammer, the bottom ends of the anti-pulling longitudinal bars (1) are all arranged in a bending shape of 85-95 degrees towards the directions deviating from each other, and the bottom ends of the adjacent anti-pulling longitudinal bars (1) are arranged at intervals along the inner diameter direction of the pile hole;
s7: installing a reinforcement cage, prefabricating a reinforcement cage body (8) on site, hoisting the reinforcement cage body (8) and placing the reinforcement cage body into the steel sleeve, penetrating a tensile longitudinal bar (1) into an inner positioning ring (2) of the reinforcement cage body (8), measuring the elevation of the reinforcement cage body (8) and adjusting the elevation of the reinforcement cage to be within an allowable error range;
s8: pouring concrete, pouring concrete slurry in the steel sleeve, measuring and controlling the elevation of a poured concrete pile body (4), controlling the elevation of the pile top within an allowable error range, and performing over-pouring for more than 0.8m according to the standard;
s9: pulling the sleeve, pulling the steel sleeve out of the pile hole, controlling the pulling speed, and adopting a pulling stopping measure if necessary;
wherein, steel cylinder (17) are kept away from two journal stirrup (21) of one end fixedly connected with of expansion dish (18), two journal stirrup (21) are followed the axis symmetry of steel cylinder (17) sets up, connecting rod (22) have been worn in two common prefabrication of journal stirrup (21), the axis of connecting rod (22) with the axis of steel cylinder (17) sets up perpendicularly, the coaxial fixedly connected with butt in the butt steel sheet of two journal stirrup (21) in both ends of connecting rod (22), two journal stirrup (21) with connecting rod (22) constitute "door" font structure jointly.
2. The carrier pile construction process according to claim 1, wherein in step S6, the filling material (5) is cement mortar mixture or dry hard concrete, the tensile longitudinal bar (1) is driven by a heavy hammer, the bottom 85-95 degree angle bending part of the tensile longitudinal bar (1) is embedded into the filling material (5), and the upper part of the tensile longitudinal bar (1) is embedded into the concrete pile body (4), so that the concrete pile body (4) is firmly connected with the filling material.
3. The carrier pile construction process according to claim 1, wherein the concrete pile body (4) comprises a precast pile (9) and a cement mortar grouting body (10), the precast pile (9) is precast by concrete and a plurality of reinforcement cages (8), a pipe pile hole (11) for accommodating the tensile longitudinal rib (1) is formed in the center of the precast pile (9), and cement mortar is poured around the tensile longitudinal rib (1) in the pipe pile hole (11) to form the cement mortar grouting body (10).
4. The carrier pile construction process according to claim 3, wherein the reinforcement cage body (8) comprises a plurality of reinforcement cage longitudinal bars (12), spiral stirrups (13) and stiffening ribs (14), the reinforcement cage longitudinal bars (12) are sleeved at equal intervals along the pile hole axis direction around the periphery of the uplift reinforcement, the periphery of the reinforcement cage longitudinal bars (12) jointly surrounds the spiral stirrups (13), and the inner walls of the reinforcement cage longitudinal bars (12) are jointly connected with the stiffening ribs (14).
5. The carrier pile construction process according to claim 3, wherein a pile end of the concrete pile body (4) is provided with a bearing platform (15) and a raft (16), and one ends, away from the bending section, of the tensile longitudinal ribs (1) in the concrete pile body (4) extend upwards into the bearing platform (15), or the tensile longitudinal ribs (1) do not extend into the bearing platform (15) and the raft (16).
CN202010314170.2A 2020-04-20 2020-04-20 Carrier pile construction process Active CN111424644B (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
CN202010314170.2A CN111424644B (en) 2020-04-20 2020-04-20 Carrier pile construction process
CN202011409155.2A CN112593549B (en) 2020-04-20 2020-04-20 Carrier pile construction process
CN202011417924.3A CN112482359B (en) 2020-04-20 2020-04-20 Carrier pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010314170.2A CN111424644B (en) 2020-04-20 2020-04-20 Carrier pile construction process

Related Child Applications (2)

Application Number Title Priority Date Filing Date
CN202011417924.3A Division CN112482359B (en) 2020-04-20 2020-04-20 Carrier pile
CN202011409155.2A Division CN112593549B (en) 2020-04-20 2020-04-20 Carrier pile construction process

Publications (2)

Publication Number Publication Date
CN111424644A CN111424644A (en) 2020-07-17
CN111424644B true CN111424644B (en) 2020-12-15

Family

ID=71554185

Family Applications (3)

Application Number Title Priority Date Filing Date
CN202011409155.2A Active CN112593549B (en) 2020-04-20 2020-04-20 Carrier pile construction process
CN202010314170.2A Active CN111424644B (en) 2020-04-20 2020-04-20 Carrier pile construction process
CN202011417924.3A Active CN112482359B (en) 2020-04-20 2020-04-20 Carrier pile

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN202011409155.2A Active CN112593549B (en) 2020-04-20 2020-04-20 Carrier pile construction process

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN202011417924.3A Active CN112482359B (en) 2020-04-20 2020-04-20 Carrier pile

Country Status (1)

Country Link
CN (3) CN112593549B (en)

Families Citing this family (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112459048B (en) * 2020-11-24 2022-10-28 嘉兴市康立德构件股份有限公司 High-efficiency energy-saving concrete pipe pile and forming process
CN112554214B (en) * 2020-12-10 2022-03-11 江苏省华厦工程项目管理有限公司 Deep foundation pit water seepage treatment structure and construction method thereof
CN112523215B (en) * 2020-12-25 2021-12-31 湖北波森特岩土工程有限公司 Multi-equipment efficient construction method for carrier pile
CN113106969A (en) * 2021-04-08 2021-07-13 胡海滨 Stiff carrier pile and construction process
CN113653032A (en) * 2021-08-27 2021-11-16 北京波森特岩土工程有限公司 Construction method of uplift carrier pile
CN114486526B (en) * 2022-01-26 2023-08-25 唐山市市场监管综合执法局 Measuring instrument for detecting bearing limit value of steel pipe and using method thereof
CN114606933A (en) * 2022-01-28 2022-06-10 赵关保 Concrete filling pile for reinforcing pile bottom by adopting cement-soil mixing pile and construction method
CN114482027A (en) * 2022-03-07 2022-05-13 中部城市建设有限公司 Construction method of concrete pile body carrier pile
CN114808950A (en) * 2022-05-22 2022-07-29 赵关保 Concrete cast-in-place pile with pile end reinforcing body capable of providing uplift resistance and construction method
CN114991130B (en) * 2022-06-17 2023-11-10 邵良荣 Pulling-resistant carrier pile and construction method thereof
CN115030141B (en) * 2022-07-21 2023-11-17 邵良荣 Cast-in-situ pile body carrier pile and construction method thereof
CN115467357B (en) * 2022-10-26 2024-03-12 深圳市勘察测绘院(集团)有限公司 Pile cap pile anchor structure suitable for relief topography
CN115977085A (en) * 2023-01-17 2023-04-18 中地互联科技发展有限公司 Carrier anchor rod and construction method thereof
CN116220006B (en) * 2023-03-07 2024-09-17 广州市市政工程试验检测有限公司 A post-tensioned slow-bonding prestressed combined rammed-expanded pile and its construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1282825A (en) * 2000-07-20 2001-02-07 蒋永华 Vibration compacted galet pile resisting pull-up and floatation, and its forming method
CN201165661Y (en) * 2008-03-11 2008-12-17 中国矿业大学 A kind of anti-pull high-pressure rotary grouting pile
CN102383420A (en) * 2011-08-17 2012-03-21 江苏建华管桩有限公司 High-strength concrete prefabricated pile doped with fiber-reinforced plastic bar
CN105735253A (en) * 2016-03-01 2016-07-06 江苏东合南岩土科技股份有限公司 Construction method for expansion head anti-pressing and anti-pulling pile
CN106192999A (en) * 2016-08-18 2016-12-07 王继忠 The construction method of uplift pile
CN106337411A (en) * 2016-08-30 2017-01-18 中国十七冶集团有限公司 Precast pile of carrier pile and construction method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1172194A (en) * 1996-07-31 1998-02-04 杨文杰 Pile-formation process for reinforced concrete ram-expanded cast-in-situ pile and its equipment
CN100360745C (en) * 2004-12-28 2008-01-09 王继忠 Concrete pile construction method
CN100564695C (en) * 2007-12-11 2009-12-02 中机工程勘察设计研究院 The job practices of carrier pile
CN103171982A (en) * 2013-04-18 2013-06-26 云南冶金昆明重工有限公司 Hinge assembly of flat-top tower crane
CN108049401A (en) * 2018-01-26 2018-05-18 刘淼 A kind of screw thread rammed bulb pile and its construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1282825A (en) * 2000-07-20 2001-02-07 蒋永华 Vibration compacted galet pile resisting pull-up and floatation, and its forming method
CN201165661Y (en) * 2008-03-11 2008-12-17 中国矿业大学 A kind of anti-pull high-pressure rotary grouting pile
CN102383420A (en) * 2011-08-17 2012-03-21 江苏建华管桩有限公司 High-strength concrete prefabricated pile doped with fiber-reinforced plastic bar
CN105735253A (en) * 2016-03-01 2016-07-06 江苏东合南岩土科技股份有限公司 Construction method for expansion head anti-pressing and anti-pulling pile
CN106192999A (en) * 2016-08-18 2016-12-07 王继忠 The construction method of uplift pile
CN106337411A (en) * 2016-08-30 2017-01-18 中国十七冶集团有限公司 Precast pile of carrier pile and construction method

Also Published As

Publication number Publication date
CN112482359A (en) 2021-03-12
CN112593549A (en) 2021-04-02
CN112593549B (en) 2022-05-27
CN111424644A (en) 2020-07-17
CN112482359B (en) 2022-07-08

Similar Documents

Publication Publication Date Title
CN111424644B (en) Carrier pile construction process
US7201540B2 (en) Construction process for composite pile foundation
CN205369231U (en) Steel -pipe pile is filled in drilling
CN112523215B (en) Multi-equipment efficient construction method for carrier pile
CN102787595A (en) Double-acting self-stressing combined uplift pile and pile forming method
CN110777836A (en) Reinforced concrete plate-anchor rod composite foundation and using method thereof
CN217974323U (en) Interior prefabricated tubular pile structure of back slip casting and pile foundation of hammering stake point into rock
CN106968245A (en) The uplift pile of prestress anchorage cable manually digging hole and its construction method
CN113653032A (en) Construction method of uplift carrier pile
CN114606934A (en) Telescopic pipe pile and its pile forming method
CN104196013B (en) A kind of composite Y shape stake and construction method thereof
CN109024721A (en) A kind of underpinning and improve the method that ability is cut in the bending resistance of existing building rigid foundation
CN108914947A (en) Foundation pit anchor wall draws the construction method of anchor supporting and its supporting construction of drilling tool and formation
CN212335996U (en) Resistance to compression resistance to plucking variable diameter steel reinforcement cage club-footed pile
CN207160041U (en) Anchor rod type artificial digging pile
CN220550544U (en) Beaded karst cave pile foundation structure
CN111962522A (en) A combined support structure of inclined wedge piles and vertical pipe piles and construction method thereof
CN217378870U (en) Major diameter prestressed steel pipe concrete friction pile
CN215105479U (en) Foundation rock anchor pile plate type foundation of tower crane
CN109898505A (en) With the compound tubular pole of reinforced structure in soft stratum
CN212506308U (en) A combined support structure of inclined pipe piles and vertical wedge piles
CN213952209U (en) PSB finish rolling screw-thread steel pipe pile prestressing force anti-floating pile structure
CN105178311B (en) Partially prefabricated friction pile and construction method thereof
CN108532621A (en) A kind of assembled drilledpier foundation and its construction method
CN218027734U (en) Embedded type isolation pile embedded into grouting pipe

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20220609

Address after: No. 58, Shaoxiang group, Shuangshan village, Ganquan Town, Hanjiang District, Yangzhou City, Jiangsu Province 225002

Patentee after: Shao Liangrong

Patentee after: Hubei bosent Geotechnical Engineering Co.,Ltd.

Address before: 430070 No.1, 10th floor, Wujiawan private hi tech building (United International), Hongshan District, Wuhan City, Hubei Province

Patentee before: Wuhan concrete source Hi Tech Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20230728

Address after: Business 2 (124), Floor 1, Building 2, Hannan Homeland Phase III, No. 39, Hannan Avenue, Shamao Street, Hannan District, Wuhan City, Hubei Province, 430000

Patentee after: Hubei Hainei Wushuang Construction Engineering Co.,Ltd.

Address before: No. 58, Shaoxiang group, Shuangshan village, Ganquan Town, Hanjiang District, Yangzhou City, Jiangsu Province 225002

Patentee before: Shao Liangrong

Patentee before: Hubei bosent Geotechnical Engineering Co.,Ltd.

TR01 Transfer of patent right