CN111287757A - Pipe jacking construction method for penetrating through long mortar layer - Google Patents

Pipe jacking construction method for penetrating through long mortar layer Download PDF

Info

Publication number
CN111287757A
CN111287757A CN202010093933.5A CN202010093933A CN111287757A CN 111287757 A CN111287757 A CN 111287757A CN 202010093933 A CN202010093933 A CN 202010093933A CN 111287757 A CN111287757 A CN 111287757A
Authority
CN
China
Prior art keywords
mortar layer
jacking
pipe
long
head
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010093933.5A
Other languages
Chinese (zh)
Inventor
盛夏一
李煜峰
邹峰
罗云峰
唐江国
刘桂荣
陈志强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Foundation Engineering Group Co Ltd
Original Assignee
Shanghai Foundation Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Foundation Engineering Group Co Ltd filed Critical Shanghai Foundation Engineering Group Co Ltd
Priority to CN202010093933.5A priority Critical patent/CN111287757A/en
Publication of CN111287757A publication Critical patent/CN111287757A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0642Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield having means for additional processing at the front end
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0642Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield having means for additional processing at the front end
    • E21D9/0671Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield having means for additional processing at the front end with means for consolidating the rock in front of the shield by injection of consolidating substances through boreholes
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/08Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/08Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield
    • E21D9/087Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield with a rotary drilling-head cutting simultaneously the whole cross-section, i.e. full-face machines
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/06Accessories therefor, e.g. anchors

Abstract

The invention relates to a pipe jacking construction method for penetrating through a long mortar layer, which comprises the following steps: 1. detecting the length and the specific position of the encountered mortar layer before construction so as to confirm the long mortar layer area containing the barrier; 2. adopting a muddy water balance top pipe machine head to dig in the long mortar layer area, and 3, additionally arranging an air pressure bin, adopting an air pressure barrier removal process to manually remove the rock blocks and check the condition of a cutter head of the muddy water balance top pipe machine head, thereby ensuring the digging efficiency; 4. the grouting in the jacking process is divided into two stages, in the first stage, fly ash mixed slurry is synchronously injected close to the front part of the machine head, the gap of the over-excavation part is filled, the pipeline is prevented from being wrapped by mortar, a grouting anti-drag channel is formed, and the instability of the pipeline is prevented; thixotropic slurry is injected in the second stage, so that the supporting and lubricating effects are achieved, and the resistance is reduced. The invention can ensure that the jacking pipe can smoothly pass through the long-distance mortar layer, avoid delay of construction period due to the fact that jacking is blocked, save cost for project construction, and obtain economic, reasonable and practical effects.

Description

Pipe jacking construction method for penetrating through long mortar layer
Technical Field
The invention relates to a pipe jacking construction method, in particular to a pipe jacking construction method for enabling a pipe jacking to penetrate through a long mortar layer.
Background
At present, block stones cannot penetrate through the pipe jacking construction, construction can be continued only after obstacles are removed, and long-distance mortar left by obstacles removal can form a long mortar layer in a channel, so that certain difficulty is caused in jacking. Under the engineering background, no systematic efficient construction method for coping treatment exists at present, the single measure adopted has extremely poor implementation effect, and the progress of the engineering project is seriously influenced, so that a targeted systematic construction method is needed to solve the problem.
Disclosure of Invention
Aiming at the current situation that no proper systematic measures are taken to solve the problem that the jacking pipe penetrates through the long mortar layer at present, the invention provides a concrete and effective jacking pipe construction method for penetrating through the long mortar layer.
In order to realize the construction purpose, the invention adopts the following technical scheme:
a pipe-jacking construction method for penetrating through a long mortar layer comprises the following steps:
(1) detecting the length and specific position of the encountered mortar layer before construction so as to confirm the long sand containing the obstacles
A slurry layer region;
(2) adopting a mud-water balance top pipe machine head to tunnel in the long mortar layer area,
(3) an air pressure bin is additionally arranged, the block stone is manually removed by adopting an air pressure obstacle clearing process, the condition of a cutter head of a muddy water balance ejector pipe head is checked, and the tunneling efficiency is ensured;
(4) the grouting in the jacking process is divided into two stages, in the first stage, fly ash mixed slurry is synchronously injected close to the front part of the machine head, the gap of the over-excavation part is filled, the pipeline is prevented from being wrapped by mortar, a grouting anti-drag channel is formed, and the instability of the pipeline is prevented; thixotropic slurry is injected in the second stage, so that the supporting and lubricating effects are achieved, and the resistance is reduced.
Furthermore, the muddy water balance jacking pipe head is a muddy water balance jacking pipe head with 3cm of over-excavation capacity in one-side tunneling mode, and the problem that the jacking pipe is difficult to correct in a mortar layer can be solved.
Furthermore, after the cutter head of the muddy water balance jacking pipe machine head is decelerated by 3 motors through a planetary reducer, a pinion on a main shaft of the planetary reducer drives a large gear in the middle of a cutter rest reduction box, and then the main shaft arranged at the center of the large gear drives the cutter rest and the cutter head to rotate.
Further, the torque of the cutter head is 180KN m.
Compared with the prior art, the invention has the beneficial effects that:
1. the invention can effectively solve the construction problem that the jacking pipe passes through the long mortar layer, and avoids economic loss caused by engineering stagnation.
2. The construction method provided by the invention is a measure which can be used for construction more quickly and conveniently, is high in applicability and can ensure high efficiency of tunneling.
Detailed Description
The invention is further illustrated by the following examples.
A pipe jacking construction method for solving the problem of penetrating through a long mortar layer comprises the following steps:
1. detecting the length and the specific position of the encountered mortar layer before construction so as to confirm the long mortar layer area containing the barrier;
2. tunneling in the long mortar layer area, adopting an improved new slurry water balance jacking pipe head, and solving the problem that the jacking pipe is difficult to correct in the mortar layer due to the fact that one side of the jacking pipe head has 3cm of overbreak capacity;
3. an air pressure bin is additionally arranged, and an air pressure barrier removal process is adopted to manually remove the rock blocks and check the condition of a cutter head, so that the tunneling efficiency of the equipment is ensured;
4. the grouting in the jacking process is divided into two stages, in the first stage, fly ash mixed slurry is synchronously injected close to the front part of the machine head, the gap of the over-excavation part is filled, the pipeline is prevented from being wrapped by mortar, a grouting anti-drag channel is formed, and the instability of the pipeline is prevented; thixotropic slurry is injected in the second stage, so that the supporting and lubricating effects are achieved, and the resistance is reduced.
Specifically, a 58.5m long mortar layer is detected to exist after a well top pipe is taken out of a hole in a certain project, the sand layer is taken as a barrier removing range in a riprap area, then the sand layer enters the sludge layer, when the well top pipe is jacked to 135.3m, the barrier removing mortar layer meets a rock stratum area, the sand layer is jacked to 27m and then enters the hole, and according to geological data, a top pipe mainly penetrates ② 2 sludge 77 m long mortar layer and 85.5m long mortar layer.
According to the characteristics of the stratum penetrated by the pipeline, the improved mud-water balance pipe jacking machine is adopted for construction according to requirements, the number and hardness of super digging cutters and cutter heads are increased, and the air pressure cabin is additionally arranged, so that the barrier removing function is achieved. The front end of the pipe jacking tunneling machine head is provided with a conical cutter rest, and an alloy cutter on the cutter rest is used for cutting soil and mortar with lower strength. The single side has 3cm of overbreak ability, solves the difficult problem of rectifying of push pipe in the mortar layer. The cutter head is decelerated by 3 motors through a planetary reducer, a pinion on a main shaft of the planetary reducer drives a large gear in the middle of a cutter rest reduction box, and then the main shaft arranged at the center of the large gear drives a cutter rest to rotate. The cutter head is driven by the cutter frame. The cutter head torque is 180KN m.
And an air pressure barrier removing method is adopted in jacking, when the pressure rises, the air pressure can keep and judge that the machine head enters a mortar layer, and when jacking is difficult, barrier removing and cutter disc cleaning are carried out after manual pressure rising.
Arranging a grouting hole close to the front part of the machine head, dividing grouting into two stages, and synchronously injecting fly ash mixed slurry close to the front part of the machine head in the first stage to fill a gap of an overbreak part, so as to prevent a pipeline from being wrapped by mortar, form a grouting anti-drag channel and prevent the pipeline from being unstable; thixotropic slurry is injected in the second stage, so that the supporting and lubricating effects are achieved, and the resistance is reduced. The slurry ratio is determined through experiments, and the strength of the slurry reaches 0.2-0.3 MPA after 2-3 d.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and the technical solutions and the inventive concepts thereof according to the present invention should be equivalent or changed within the scope of the present invention.

Claims (4)

1. A pipe-jacking construction method for penetrating through a long mortar layer is characterized by comprising the following steps:
(1) detecting the length and the specific position of the encountered mortar layer before construction so as to confirm the long mortar layer area containing the barrier;
(2) adopting a mud-water balance top pipe machine head to tunnel in the long mortar layer area,
(3) an air pressure bin is additionally arranged, the block stone is manually removed by adopting an air pressure obstacle clearing process, the condition of a cutter head of a muddy water balance ejector pipe head is checked, and the tunneling efficiency is ensured;
(4) the grouting in the jacking process is divided into two stages, in the first stage, fly ash mixed slurry is synchronously injected close to the front part of the machine head, the gap of the over-excavation part is filled, the pipeline is prevented from being wrapped by mortar, a grouting anti-drag channel is formed, and the instability of the pipeline is prevented; thixotropic slurry is injected in the second stage, so that the supporting and lubricating effects are achieved, and the resistance is reduced.
2. The pipe-jacking construction method for penetrating through a long mortar layer according to claim 1, characterized in that: the muddy water balance jacking pipe head is a muddy water balance jacking pipe head with 3cm of over-excavation capacity in one-side tunneling mode, and the problem that a jacking pipe is difficult to rectify in a mortar layer can be solved.
3. The pipe-jacking construction method for penetrating through a long mortar layer according to claim 1, characterized in that: after the cutter head of the muddy water balance ejector pipe head is decelerated by 3 motors through a planetary reducer, a pinion on a main shaft of the planetary reducer drives a large gear in the middle of a cutter rest reduction box, and then the main shaft arranged at the center of the large gear drives the cutter rest and the cutter head to rotate.
4. The pipe jacking construction method for penetrating through a long mortar layer according to claim 3, wherein the construction method comprises the following steps: the torque of the cutter head is 180KN m.
CN202010093933.5A 2020-02-14 2020-02-14 Pipe jacking construction method for penetrating through long mortar layer Pending CN111287757A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010093933.5A CN111287757A (en) 2020-02-14 2020-02-14 Pipe jacking construction method for penetrating through long mortar layer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010093933.5A CN111287757A (en) 2020-02-14 2020-02-14 Pipe jacking construction method for penetrating through long mortar layer

Publications (1)

Publication Number Publication Date
CN111287757A true CN111287757A (en) 2020-06-16

Family

ID=71021988

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010093933.5A Pending CN111287757A (en) 2020-02-14 2020-02-14 Pipe jacking construction method for penetrating through long mortar layer

Country Status (1)

Country Link
CN (1) CN111287757A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105240019A (en) * 2015-09-24 2016-01-13 中国石油天然气集团公司 Pipe jacking construction method
CN110030430A (en) * 2019-03-12 2019-07-19 上海城建水务工程有限公司 A kind of pipe jacking construction method for cylinder concrete pipe
CN110259475A (en) * 2019-05-31 2019-09-20 武汉市武昌市政建设(集团)有限公司 A kind of head is removed obstacles method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105240019A (en) * 2015-09-24 2016-01-13 中国石油天然气集团公司 Pipe jacking construction method
CN110030430A (en) * 2019-03-12 2019-07-19 上海城建水务工程有限公司 A kind of pipe jacking construction method for cylinder concrete pipe
CN110259475A (en) * 2019-05-31 2019-09-20 武汉市武昌市政建设(集团)有限公司 A kind of head is removed obstacles method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
中铁电气化局集团建设管理分办司: "《城市轨道交通工程投融资及建设管理》", 31 August 2015, 中国铁道出版社 *
曹德意: "某原水输水管道工程施工方案的优化", 《中国设备工程》 *
葛克水: "《地下建筑工程施工》", 30 June 2014, 地质出版社 *

Similar Documents

Publication Publication Date Title
CN101781991B (en) Double-well type reinforcement method of shield arrival or starting end and double-well type shield arrival method
CN104213833B (en) Pipeline Crossing by Horizontal Directional Drilling construction method and rig thereof
CN111335902B (en) Construction method for shield tunneling ground connection wall underpass operation subway station
CN110374606B (en) Advanced grouting pressure maintaining construction method for broken seabed stratum of slurry shield
CN103899318B (en) The milling of medium ground tunnel is dug and supporting machinery construction
CN103244133B (en) The milling of coal measure strata tunnel is dug and is combined construction with explosion
CN107355226B (en) Broken area hole section processing structure of TBM construction tunnel fault
CN108708743B (en) Method for treating tunnel collapse by grouting
CN109322671B (en) Method for getting rid of worn and trapped shield cutter
CN110630271B (en) Construction method for water-rich sand layer shield to penetrate through steel pipe soil nail area
CN103510957A (en) Combined rock cross-cut coal uncovering method
CN102787846A (en) Upper-blocking and lower-draining construction method for undersea tunnel fault fracture zone
AU2021105800A4 (en) Treatment method for side roof collapse of water-bearing broken soft rock tunnel
CN113775345A (en) Method for improving full-section muck in silt layer in construction of connecting channel pipe jacking machine
CN210564541U (en) Quick heading machine
CN105019917A (en) Impact drilling type advanced jet grouting pipe shed construction device and construction method
CN218934444U (en) High-pressure horizontal jet grouting pile tunnel reinforcing structure in frozen soil area
CN109958448B (en) Rock breaking method for composite stratum pipe jacking construction
CN111287757A (en) Pipe jacking construction method for penetrating through long mortar layer
CN204920977U (en) Spray tube canopy construction equipment is revolved in advance to percussion drilling formula
CN103277109A (en) Shield excavation construction method used for big-stickiness soil layer
CN112709579A (en) Quick-forming development machine for river and canal
CN207111096U (en) TBM construction tunnel fault belts hole section processing structure
CN111042820B (en) Construction method for sand layer with oversized pilot hole by vertical shaft raise-shaft method
CN109707394B (en) Construction method for subway tunnel shield receiving end tunnel portal

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200616