CN111271123A - Subway station prefabricated rail top air duct structure and construction method - Google Patents
Subway station prefabricated rail top air duct structure and construction method Download PDFInfo
- Publication number
- CN111271123A CN111271123A CN202010040049.5A CN202010040049A CN111271123A CN 111271123 A CN111271123 A CN 111271123A CN 202010040049 A CN202010040049 A CN 202010040049A CN 111271123 A CN111271123 A CN 111271123A
- Authority
- CN
- China
- Prior art keywords
- hole
- top air
- air duct
- prefabricated rail
- middle plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
- E21F17/02—Suspension devices for tubes or the like, e.g. for ventilating ducts
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F1/00—Ventilation of mines or tunnels; Distribution of ventilating currents
- E21F1/04—Air ducts
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
Description
技术领域technical field
本发明涉及建筑领域,具体涉及一种地铁车站预制轨顶风道结构及施工方法。The invention relates to the field of construction, in particular to a prefabricated rail top air duct structure of a subway station and a construction method.
背景技术Background technique
地铁车站轨顶风道为悬挂于中板下的U型结构,其作为车站的二次结构,往往需要在结构施工完成后二次重新搭设脚手架和模板后施工,施工时需提前在中板下部预留钢筋实现与中板结构相连,由于施工空间狭小,且支模和浇筑受中板影响,施工费时费力,施工质量通常难以保证。The rail roof air duct of the subway station is a U-shaped structure suspended under the middle plate. As the secondary structure of the station, it is often necessary to re-install the scaffolding and formwork after the structural construction is completed. Retaining steel bars to connect with the mid-slab structure, because the construction space is small, and the formwork and pouring are affected by the mid-slab, the construction is time-consuming and laborious, and the construction quality is usually difficult to guarantee.
发明内容SUMMARY OF THE INVENTION
鉴于现有技术中存在的技术缺陷和技术弊端,本发明实施例提供克服上述问题或者至少部分地解决上述问题的一种地铁车站预制轨顶风道结构及施工方法,具体方案如下:In view of the technical defects and technical drawbacks existing in the prior art, the embodiments of the present invention provide a prefabricated rail-top air duct structure and a construction method for a subway station that overcomes the above-mentioned problems or at least partially solves the above-mentioned problems. The specific solutions are as follows:
作为本发明的第一方面,提供一种地铁车站预制轨顶风道结构,还包括安装于中板下的预制轨顶风道结构,所述中板中预留有多个间隔且贯穿所述中板的通孔,所述预制轨顶风道结构中预埋有多个与所述通孔位置一一对应的螺栓,所述螺栓的螺帽完全预埋于所述预制轨顶风道结构内,所述螺栓的螺杆自所述预制轨顶风道结构内向上延伸并穿过对应的通孔,并通过螺母固定于所述中板上,所述通孔包括位于上部的具有第一孔径的第一通孔和位于下部的具有第二孔径的第二通孔,所述第一孔径大于所述第二孔径,所述螺母的直径大于第二孔径且小于第一孔径,所述第一通孔和第二通孔的过渡处形成平台,所述螺母位于所述第一通孔中且支撑于所述平台上。As a first aspect of the present invention, a prefabricated rail-top air duct structure for a subway station is provided, further comprising a prefabricated rail-top air duct structure installed under a middle plate, wherein a plurality of intervals are reserved in the middle plate and penetrate through the middle plate There are a plurality of bolts corresponding to the positions of the through holes in the prefabricated rail top air duct structure, and the nuts of the bolts are completely embedded in the prefabricated rail top air duct structure. The screw rod of the bolt extends upward from the prefabricated rail-top air duct structure and passes through the corresponding through hole, and is fixed on the middle plate by a nut, and the through hole includes a first through hole with a first hole diameter located at the upper part. and a second through hole with a second aperture located at the lower part, the first aperture is larger than the second aperture, the diameter of the nut is larger than the second aperture and smaller than the first aperture, the first through hole and the second aperture are A platform is formed at the transition of the through hole, and the nut is located in the first through hole and supported on the platform.
进一步地,所述中板与所述预制轨顶风道结构之间的缝隙中填充有细石混凝土。Further, the gap between the middle plate and the prefabricated rail-top air duct structure is filled with fine stone concrete.
进一步地,每个第二通孔的上端面处水平设置有预埋钢板,所述预埋钢板具有与第二通孔孔径大小相同的第三通孔,所述第三通孔与第二通孔重叠。Further, a pre-embedded steel plate is horizontally arranged at the upper end face of each second through hole, and the pre-embedded steel plate has a third through hole with the same size as the second through hole, and the third through hole is connected to the second through hole. Holes overlap.
进一步地,所述第一通孔为第一长条孔,所述螺母的直径小于第一长条孔的宽度。Further, the first through hole is a first elongated hole, and the diameter of the nut is smaller than the width of the first elongated hole.
进一步地,所述第二通孔为第二长条孔,所述螺母的直径大于第二长条孔的宽度。Further, the second through hole is a second elongated hole, and the diameter of the nut is larger than the width of the second elongated hole.
作为本发明的第二方面,提供一种地铁车站预制轨顶风道的施工方法,所述方法包括:As a second aspect of the present invention, a construction method for a prefabricated rail-top air duct in a subway station is provided, the method comprising:
在中板中预留多个间隔且贯穿所述中板的通孔;Reserving a plurality of intervals in the middle plate and passing through the through holes of the middle plate;
在工厂预先施作好如上述任一种所述的预制轨顶风道结构;The prefabricated rail-top air duct structure as described in any of the above is prefabricated in the factory;
将施作好的预制轨顶风道结构输送到中板下,使预制轨顶风道结构中预埋的螺栓的螺杆向上穿过对应的通孔,并通过螺母固定于所述中板上,从而将预制轨顶风道结构安装于所述中板下。The prefabricated prefabricated rail-top air duct structure is transported under the middle plate, so that the screws of the bolts embedded in the prefabricated rail-top air duct structure pass upward through the corresponding through holes, and are fixed on the middle plate by nuts, so that the The prefabricated rail-top air duct structure is installed under the middle plate.
进一步地,所述方法还包括:在预制轨顶风道结构安装完成后,在所述中板与所述预制轨顶风道结构之间的缝隙中浇筑细石混凝土。Further, the method further includes: after the installation of the prefabricated rail-top air duct structure is completed, pouring fine stone concrete in the gap between the middle plate and the prefabricated rail-top air duct structure.
进一步地,每个第二通孔的上端面处水平设置有预埋钢板,所述预埋钢板具有与第二通孔孔径大小相同的第三通孔,所述第三通孔与第二通孔重叠。Further, a pre-embedded steel plate is horizontally arranged at the upper end face of each second through hole, and the pre-embedded steel plate has a third through hole with the same size as the second through hole, and the third through hole is connected to the second through hole. Holes overlap.
进一步地,所述第一通孔为第一长条孔,所述螺母的直径小于第一长条孔的宽度。Further, the first through hole is a first elongated hole, and the diameter of the nut is smaller than the width of the first elongated hole.
进一步地,所述第二通孔为第二长条孔,所述螺母的直径大于第二长条孔的宽度。Further, the second through hole is a second elongated hole, and the diameter of the nut is larger than the width of the second elongated hole.
本发明具有以下有益效果:The present invention has the following beneficial effects:
本发明提出了一种预制装配式轨顶风道结构及施工方法,克服了现有的技术偏见,很好的解决了原有轨顶风道的一系列缺点,质量可靠,施工便捷,安全经济,对于方案制定、成熟施工和控制风险有良好的作用,该方法简便易行、经济合理、技术成熟、前景广阔且效益良好。The invention proposes a prefabricated rail-top air duct structure and a construction method, which overcomes the existing technical prejudice, well solves a series of shortcomings of the original rail-top air duct, has reliable quality, convenient construction, safety and economy, and is suitable for Scheme formulation, mature construction and risk control have a good effect. The method is simple and easy to implement, economical and reasonable, with mature technology, broad prospects and good benefits.
附图说明Description of drawings
为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作一简单地介绍,显而易见地,下面描述中的附图是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动性的前提下,还可以根据这些附图获得其他的附图In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the accompanying drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description These are some embodiments of the present invention. For those of ordinary skill in the art, other drawings can also be obtained from these drawings without creative labor.
图1为本发明实施例提供的中板的平面布置图;1 is a plan layout diagram of a midplane provided by an embodiment of the present invention;
图2为本发明实施例提供的通孔的结构示意图;2 is a schematic structural diagram of a through hole provided by an embodiment of the present invention;
图3为本发明实施例提供的预制轨顶风道结构与中板的连接示意图;3 is a schematic diagram of the connection between the prefabricated rail top air duct structure and the middle plate provided by the embodiment of the present invention;
图4为本发明实施例提供的节点A的放大示意图;FIG. 4 is an enlarged schematic diagram of a node A according to an embodiment of the present invention;
附图标记说明:1、中板,2、预制轨顶风道结构,3、节点A,4、螺母,11、通孔,12、预埋钢板,111、第一通孔,112、第二通孔,113、平台,21、螺栓。Description of reference numerals: 1, middle plate, 2, prefabricated rail-top air duct structure, 3, node A, 4, nut, 11, through hole, 12, embedded steel plate, 111, first through hole, 112, second through hole Hole, 113, Platform, 21, Bolt.
具体实施方式Detailed ways
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其它实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.
如图1-4所示,作为本发明的第一实施例,提供一种地铁车站预制轨顶风道结构,包括中板1,还包括安装于中板1下的预制轨顶风道结构2,所述中板1中预留有多个间隔且贯穿所述中板1的通孔11,所述预制轨顶风道结构2中预埋有多个与所述通孔11位置一一对应的螺栓21,如图4所示,为对图3中节点A3的放大图,所述螺栓21的螺帽完全预埋于所述预制轨顶风道结构2内,所述螺栓21的螺杆自所述预制轨顶风道结构2内向上延伸并穿过对应的通孔11,并通过螺母4固定于所述中板1上,所述通孔11包括位于上部的具有第一孔径的第一通孔111和位于下部的具有第二孔径的第二通孔112,所述第一孔径大于所述第二孔径,所述第一通孔111和第二通孔112的过渡处形成一个平台113,所述螺母4位于所述第一通孔111中且支撑于所述平台113上,所述螺母4的直径大于第二孔径且小于第一孔径。As shown in Figures 1-4, as the first embodiment of the present invention, a prefabricated rail-top air duct structure of a subway station is provided, which includes a
优选地,所述中板1与所述预制轨顶风道结构2之间的缝隙中浇筑有细石混凝土。Preferably, fine stone concrete is poured in the gap between the
本发明提出了一种预制装配式轨顶风道结构,克服了现有的技术偏见,很好的解决了原有轨顶风道的一系列缺点,质量可靠,施工便捷,安全经济,对于方案制定、成熟施工和控制风险有良好的作用,该方法简便易行、经济合理、技术成熟、前景广阔且效益良好。The invention proposes a prefabricated rail-top air duct structure, which overcomes the existing technical prejudices, and well solves a series of shortcomings of the original rail-top air duct, and has reliable quality, convenient construction, safety and economy. Mature construction and risk control have a good effect. The method is simple and easy to implement, economical and reasonable, with mature technology, broad prospects and good benefits.
优选地,每个第二通孔112的上端面处水平设置有预埋钢板12,所述预埋钢板12具有与第二通孔112孔径大小相同的第三通孔11,所述第三通孔11与第二通孔112重叠,通过设置预埋钢板12,提供中板1与预制轨顶风道结构2的连接稳固性。Preferably, a
优选地,所述第一通孔111为第一长条孔,所述第二通孔112为第二长条孔,所述螺母4的直径小于第一长条孔的宽度,大于第二长条孔的宽度,通过将通孔11设置成长条形,有利于在中板1与预制轨顶风道结构2连接时,可以左右移动对准。Preferably, the first through
作为本发明的第二实施例,提供一种地铁车站预制轨顶风道的施工方法,所述方法包括:As a second embodiment of the present invention, a construction method for a prefabricated rail-top air duct in a subway station is provided, the method comprising:
在中板1中预留多个间隔且贯穿所述中板1的通孔11;A plurality of intervals are reserved in the
在工厂预先施作好如上述任一种所述的预制轨顶风道结构2;The prefabricated rail-top
将施作好的预制轨顶风道结构2输送到中板1下,使预制轨顶风道结构2中预埋的螺栓21的螺杆向上穿过对应的通孔11,并通过螺母4固定于所述中板1上,从而将预制轨顶风道结构2安装于所述中板1下。The prefabricated rail top
优选地,所述方法还包括:在预制轨顶风道结构2安装完成后,在所述中板1与所述预制轨顶风道结构2之间的缝隙中浇筑细石混凝土。Preferably, the method further includes: pouring fine stone concrete in the gap between the
优选地,每个第二通孔112的上端面处水平设置有预埋钢板12,所述预埋钢板12具有与第二通孔112孔径大小相同的第三通孔11,所述第三通孔11与第二通孔112重叠。Preferably, a
优选地,所述第一通孔111为第一长条孔,所述螺母4的直径小于第一长条孔的宽度。Preferably, the first through
优选地,所述第二通孔112为第二长条孔,所述螺母4的直径大于第二长条孔的宽度。Preferably, the second through
本发明,中板1在施工时预留多个间隔的长条形通孔11,同时于长条孔下部预埋钢板12;在工厂分节预制轨顶风道结构2,同时在预制轨顶风道结构2中预埋螺栓21,最后将轨顶风道分节吊装于中板1下方,通过螺母4固定后在缝隙中填充细石混凝土,解决了原有轨顶风道的一系列缺点,质量可靠,施工便捷,安全经济,对于方案制定、成熟施工和控制风险有良好的作用,该方法简便易行、经济合理、技术成熟、前景广阔且效益良好。In the present invention, the
最后应说明的是:以上各实施例仅用以说明本发明的技术方案,而非对其限制;尽管参照前述各实施例对本发明进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分或者全部技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本发明各实施例技术方案的范围。Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, but not to limit them; although the present invention has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that: The technical solutions described in the foregoing embodiments can still be modified, or some or all of the technical features thereof can be equivalently replaced; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the technical solutions of the embodiments of the present invention. scope.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010040049.5A CN111271123A (en) | 2020-01-15 | 2020-01-15 | Subway station prefabricated rail top air duct structure and construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010040049.5A CN111271123A (en) | 2020-01-15 | 2020-01-15 | Subway station prefabricated rail top air duct structure and construction method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN111271123A true CN111271123A (en) | 2020-06-12 |
Family
ID=70994801
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202010040049.5A Pending CN111271123A (en) | 2020-01-15 | 2020-01-15 | Subway station prefabricated rail top air duct structure and construction method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN111271123A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN112593991A (en) * | 2020-12-22 | 2021-04-02 | 广东省重工建筑设计院有限公司 | Prefabricated rail top air duct structure and construction method thereof |
| CN113863372A (en) * | 2021-10-28 | 2021-12-31 | 中交一航局城市交通工程有限公司 | Installation method of prefabricated structure of air duct at top of underground station rail |
Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR20020033125A (en) * | 2002-03-06 | 2002-05-04 | 전병철 | supporting structure for slab form of steel frame concrete structure |
| KR101005606B1 (en) * | 2010-06-07 | 2011-02-07 | 김태균 | Wind tunnel slab construction method of shield tunnel |
| CN205116508U (en) * | 2015-11-18 | 2016-03-30 | 江苏筑森建筑设计有限公司 | Full precast floor plank dry -type joint construction |
| CN107100661A (en) * | 2017-04-28 | 2017-08-29 | 上海城建物资有限公司 | A kind of prefabricated assembled ultra-high performance concrete flue sheet structure |
| CN208578267U (en) * | 2018-01-31 | 2019-03-05 | 杨晓剑 | A kind of precast stair connecting node |
| CN208702444U (en) * | 2018-06-15 | 2019-04-05 | 中铁第四勘察设计院集团有限公司 | A kind of prefabricated rail top air channel structure of postposition |
| CN110042862A (en) * | 2019-04-29 | 2019-07-23 | 中铁第四勘察设计院集团有限公司 | The prefabricated rail in subway station against the wind road, with prefabricated middle plate connecting node and construction method |
| CN110273531A (en) * | 2019-07-17 | 2019-09-24 | 董宏波 | A kind of prefabricated rail in subway station pipeline construction method against the wind |
| CN110359672A (en) * | 2019-07-12 | 2019-10-22 | 中铁第四勘察设计院集团有限公司 | A kind of prefabricated rail road assembling structure and its construction method against the wind |
| CN211950590U (en) * | 2020-01-15 | 2020-11-17 | 中铁第四勘察设计院集团有限公司 | Subway station prefabricated rail top air duct structure |
-
2020
- 2020-01-15 CN CN202010040049.5A patent/CN111271123A/en active Pending
Patent Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR20020033125A (en) * | 2002-03-06 | 2002-05-04 | 전병철 | supporting structure for slab form of steel frame concrete structure |
| KR101005606B1 (en) * | 2010-06-07 | 2011-02-07 | 김태균 | Wind tunnel slab construction method of shield tunnel |
| CN205116508U (en) * | 2015-11-18 | 2016-03-30 | 江苏筑森建筑设计有限公司 | Full precast floor plank dry -type joint construction |
| CN107100661A (en) * | 2017-04-28 | 2017-08-29 | 上海城建物资有限公司 | A kind of prefabricated assembled ultra-high performance concrete flue sheet structure |
| CN208578267U (en) * | 2018-01-31 | 2019-03-05 | 杨晓剑 | A kind of precast stair connecting node |
| CN208702444U (en) * | 2018-06-15 | 2019-04-05 | 中铁第四勘察设计院集团有限公司 | A kind of prefabricated rail top air channel structure of postposition |
| CN110042862A (en) * | 2019-04-29 | 2019-07-23 | 中铁第四勘察设计院集团有限公司 | The prefabricated rail in subway station against the wind road, with prefabricated middle plate connecting node and construction method |
| CN110359672A (en) * | 2019-07-12 | 2019-10-22 | 中铁第四勘察设计院集团有限公司 | A kind of prefabricated rail road assembling structure and its construction method against the wind |
| CN110273531A (en) * | 2019-07-17 | 2019-09-24 | 董宏波 | A kind of prefabricated rail in subway station pipeline construction method against the wind |
| CN211950590U (en) * | 2020-01-15 | 2020-11-17 | 中铁第四勘察设计院集团有限公司 | Subway station prefabricated rail top air duct structure |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN112593991A (en) * | 2020-12-22 | 2021-04-02 | 广东省重工建筑设计院有限公司 | Prefabricated rail top air duct structure and construction method thereof |
| CN112593991B (en) * | 2020-12-22 | 2025-04-25 | 广东省重工建筑设计院有限公司 | Prefabricated rail top air duct structure and construction method thereof |
| CN113863372A (en) * | 2021-10-28 | 2021-12-31 | 中交一航局城市交通工程有限公司 | Installation method of prefabricated structure of air duct at top of underground station rail |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110004832B (en) | Large-span cantilever truss type bent cap bracket system and construction method | |
| CN211517947U (en) | Bridge case roof beam is prefabricated with shaped steel pedestal | |
| CN106149540A (en) | Assembling steel plate composite beam bridge and construction method thereof based on steel reinforced concrete combined bridge deck | |
| CN106192620A (en) | A kind of railway ballastless track supporting layer and substructure change method | |
| CN111271123A (en) | Subway station prefabricated rail top air duct structure and construction method | |
| CN210066504U (en) | Large-span cantilever truss type bent cap support system | |
| CN114657905A (en) | A kind of integral box culvert vertical combined prefabricated platform and preparation method thereof | |
| CN112069586B (en) | Design and construction method for installing section steel cantilever scaffold on cantilever structure | |
| CN211389346U (en) | Outer side template structure of large box girder | |
| CN205821975U (en) | A kind of assembling steel plate composite beam bridge based on bolted steel reinforced concrete combined bridge deck | |
| JP3238487U (en) | Adjustable support system for defect repair of secondary lining of tunnels | |
| CN110043035B (en) | Post-cast strip construction supporting method | |
| CN211950590U (en) | Subway station prefabricated rail top air duct structure | |
| CN215857255U (en) | A revolvable No. 0 corbel bracket | |
| CN203639841U (en) | Steel plate-concrete combined reinforcement structure of hollow plate beam | |
| CN206418523U (en) | A kind of liftable post-cast strip template structure and system | |
| CN113524386A (en) | Steel bench for precast beam construction and precast beam construction method | |
| CN211395387U (en) | Cast-in-place pi type platform roof beam construction support | |
| CN204626965U (en) | For the steel stair template of poured up at a time between architectural stair | |
| CN221659638U (en) | Movable prefabricated box girder steel pedestal | |
| CN219012628U (en) | Shield tunnel beam support, flue plate beam matched with same and flue plate structure | |
| CN217811195U (en) | Circulated formula does not have flagging barricade subway rail top wind channel and hangs mould subassembly | |
| CN115262397B (en) | An integral drop method for cast-in-place beam supports of a tied arch bridge across a highway | |
| CN110486042A (en) | Hole for hoist hangs mold device and fills up construction method | |
| CN112252209B (en) | A method of dragging and replacing steel truss beams |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200612 |
|