CN111254979B - A cable anchor system for an underwater cable-stayed suspension tunnel - Google Patents

A cable anchor system for an underwater cable-stayed suspension tunnel Download PDF

Info

Publication number
CN111254979B
CN111254979B CN202010063372.4A CN202010063372A CN111254979B CN 111254979 B CN111254979 B CN 111254979B CN 202010063372 A CN202010063372 A CN 202010063372A CN 111254979 B CN111254979 B CN 111254979B
Authority
CN
China
Prior art keywords
cable
tunnel
stay
underwater
pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010063372.4A
Other languages
Chinese (zh)
Other versions
CN111254979A (en
Inventor
徐立新
邱松
张继彪
傅一帆
孙洪春
孙旭
谢锦波
于文津
程云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Third Harbor Engineering Co Ltd
Original Assignee
CCCC Third Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Third Harbor Engineering Co Ltd filed Critical CCCC Third Harbor Engineering Co Ltd
Priority to CN202010063372.4A priority Critical patent/CN111254979B/en
Publication of CN111254979A publication Critical patent/CN111254979A/en
Application granted granted Critical
Publication of CN111254979B publication Critical patent/CN111254979B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/063Tunnels submerged into, or built in, open water
    • E02D29/067Floating tunnels; Submerged bridge-like tunnels, i.e. tunnels supported by piers or the like above the water-bed
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

本发明公开了一种水下斜拉式悬浮隧道的拉索锚锭系统,包括四个拉索接收井、四组拉索转向墩、拉索坡道和多道斜拉索。四个拉索接收井各自设在隧道两侧的此岸侧海岸上和对岸侧海岸上;每个拉索接收井包括拉索锚碇墩和监控室;四组拉索转向墩各自设在隧道两侧的此岸侧海岸的岸坡上和对岸侧海岸的岸坡上并一一对应地靠近四个拉索接收井;拉索坡道设在每组拉索转向墩与对应的拉索接收井之间的岸坡上;斜拉索的一端锚固于水中悬浮隧道的两侧面,另一端穿过拉索转向墩中的转向导缆器后沿着水下的拉索坡道引伸至地面,再锚固于拉索锚碇墩上。本发明的拉索锚锭系统,在隧道管节安装时可用于隧道定位;在隧道营运期又可进行索力监测与斜拉索维护及更换。

Figure 202010063372

The invention discloses a cable anchor system for an underwater cable-stayed suspension tunnel, comprising four cable receiving wells, four groups of cable steering piers, cable ramps and multiple cables. Four cable receiving wells are respectively set on the shore side of the two sides of the tunnel and on the opposite bank side; each cable receiving well includes cable anchoring piers and monitoring room; four groups of cable steering piers are respectively located on the two sides of the tunnel. The bank slope of this side coast on the side and the bank slope of the opposite bank side are close to the four cable receiving wells in one-to-one correspondence; the cable ramps are located between each group of cable steering piers and the corresponding cable receiving wells. One end of the stay cable is anchored on both sides of the floating tunnel in the water, and the other end passes through the steering fairlead in the steering pier of the stay cable and extends to the ground along the underwater stay cable ramp, and then anchors On the cable anchor pier. The cable anchor system of the invention can be used for tunnel positioning when the tunnel pipe section is installed; during the tunnel operation period, it can also perform cable force monitoring and stay cable maintenance and replacement.

Figure 202010063372

Description

一种水下斜拉式悬浮隧道的拉索锚锭系统A cable anchor system for an underwater cable-stayed suspension tunnel

技术领域technical field

本发明涉及一种水下悬浮隧道,具体涉及一种水下斜拉式悬浮隧道的拉索锚锭系统。The invention relates to an underwater suspension tunnel, in particular to a cable anchor system for an underwater cable-stayed suspension tunnel.

背景技术Background technique

水中悬浮隧道,英文名称为“Submerged Floating Tunnel”,简称“SFT”。在意大利又称“阿基米德桥”,简称“PDA”桥。一般由浮在水中一定深度的管状体(该管状体的空间较大,足以适应道路和铁道交通的要求)、支撑系统(锚固在海底基础上的锚缆、墩柱或水上的浮箱)及与两岸的构筑物组成。它是交通运输工具跨越被深水分隔的两岸之间的一种新型结构物,适用于所有需在水中穿行的交通运载工具,可通行火车、汽车、小型机动车和行人,还可以做成穿行各种管道和电缆的服务通道。水中悬浮隧道和传统的沉埋隧道或掘进隧道的区别是:悬浮隧道结构被水包围着,既不是位于地层上也不穿越地层,而是主要依靠其自身结构的重力、结构受到的浮力以及支撑系统的锚固力来保持在固定的位置上。悬浮隧道四周密封,这种结构具有普通隧道的所有特点,从使用的观点来看应被认为是“隧道”而不是“桥梁”。Submerged Floating Tunnel, the English name is "Submerged Floating Tunnel", or "SFT" for short. In Italy, it is also known as "Archimedes Bridge", referred to as "PDA" bridge. Generally, it consists of a tubular body floating at a certain depth in the water (the tubular body has a large space enough to meet the requirements of road and railway traffic), a support system (anchor cables anchored on the seabed foundation, piers or floating boxes on water) and It is composed of structures on both sides of the strait. It is a new type of structure for transportation vehicles to cross between the two banks separated by deep water. It is suitable for all transportation vehicles that need to pass through water. It can pass trains, cars, small motor vehicles and pedestrians. It can also be used to pass through various Service channels for pipes and cables. The difference between a suspended tunnel in water and a traditional submerged tunnel or excavated tunnel is that the suspended tunnel structure is surrounded by water, neither on the stratum nor through the stratum, but mainly depends on the gravity of its own structure, the buoyancy of the structure and the support The anchoring force of the system to hold it in a fixed position. Suspended tunnels are sealed all around, this structure has all the characteristics of a normal tunnel and should be considered a "tunnel" rather than a "bridge" from a usage point of view.

悬浮隧道可以穿越不同的水域,如河流、峡湾、海峡、湖泊等,对那些由于考虑深水或两岸距离太大而认为不可跨越的地方提供了可能和可以接受的固定跨越结构形式。悬浮隧道修建在水下一定深度,相比于水面敞开式通道和轮渡运输,恶劣的风浪、雾、雨、雪等天气不会对悬浮隧道的全天候运营带来影响。在保证相同通航能力的前提下,与桥梁相比悬浮隧道的坡度较为平缓而且总长度也减小,悬浮隧道在修建过程和投入使用都不会对环境和自然景观造成影响;当超过一定的跨度和水深时,悬浮隧道的单位造价不会随着跨越通道长度或水道深度的增加有显著提高,而斜拉桥和悬索桥的单位造价则会随着跨度的增加明显地增加。Suspended tunnels can pass through different waters, such as rivers, fjords, straits, lakes, etc., and provide a possible and acceptable fixed spanning structure form for those places that are considered insurmountable due to the consideration of deep water or the distance between the two banks is too large. The suspension tunnel is built at a certain depth underwater. Compared with the open channel on the water surface and ferry transportation, severe wind and waves, fog, rain, snow and other weather will not affect the all-weather operation of the suspension tunnel. On the premise of ensuring the same navigable capacity, compared with bridges, the slope of suspension tunnels is gentler and the overall length is also reduced. The suspension tunnels will not have any impact on the environment and natural landscape during the construction process or when they are put into use; when the span exceeds a certain span When the water depth increases, the unit cost of the suspension tunnel will not increase significantly with the increase of the spanning channel length or the channel depth, while the unit cost of the cable-stayed bridge and the suspension bridge will increase significantly with the increase of the span.

虽然悬浮隧道与沉管隧道、深埋隧道、桥梁等跨海通道方案相比,具有一定优势,但悬浮隧道的设计、施工仍然是一个世界性的难题,至今尚无建成的悬浮隧道。目前世界上主要有7个国家(挪威、意大利、日本、中国、瑞士、巴西、美国)在研究,研究发现的诸多技术问题主要有:总体结构布置、隧道材料、锚固系统结构型式、隧道连接型式及接岸结构设计、隧道结构可实施性、施工与营运风险等。这些问题能否解决,决定了悬浮隧道能否从可行性方案走向实际工程。Although suspended tunnels have certain advantages compared with immersed tunnels, deep buried tunnels, bridges and other cross-sea passage schemes, the design and construction of suspended tunnels are still a worldwide problem, and no suspended tunnels have been built yet. At present, there are 7 countries in the world (Norway, Italy, Japan, China, Switzerland, Brazil, and the United States). And the design of the landing structure, the feasibility of the tunnel structure, the construction and operation risks, etc. Whether these problems can be solved determines whether the suspension tunnel can move from a feasible solution to an actual project.

迄今为止,悬浮隧道研究中,根据悬浮隧道自身重力与所受浮力之间的关系,提出的结构型式大致可分为三类:浮筒式、锚固式、墩柱式。浮筒式悬浮隧道是通过锚索或锚链把隧道悬挂于水面的浮筒上,隧道重力大于浮力,垂直方向受潮位涨落影响很大;锚固式悬浮隧道是通过张力腿或锚索把隧道锚固于海床以下的锚碇基础上,隧道重力小于浮力,隧道会在水动力作用下发生位移或晃动;墩柱式其实是支承在水下墩柱上的隧道桥,施工难度大且造价昂贵。由于隧道漂浮于水中,隧道安装施工受风、浪、流及船行波等影响,三种型式的隧道水下定位、水下或水上对接施工难度都很大,且水下营运期舒适度及安全风险均难以预估。So far, in the study of suspended tunnels, according to the relationship between the gravity of the suspended tunnel itself and the buoyant force, the proposed structural types can be roughly divided into three categories: buoyant type, anchored type, and pier-column type. The buoy-type suspension tunnel is to suspend the tunnel on the buoy on the water surface through the anchor cable or anchor chain. The gravity of the tunnel is greater than the buoyancy, and the vertical direction is greatly affected by the fluctuation of the tide level. On the anchorage foundation below the bed, the gravity of the tunnel is less than the buoyancy, and the tunnel will be displaced or shaken under the action of hydrodynamics; the pier-column type is actually a tunnel bridge supported on underwater piers, which is difficult and expensive to construct. Since the tunnel floats in the water, the installation and construction of the tunnel is affected by wind, waves, currents and ships traveling waves. The three types of tunnels are difficult to locate underwater and connect underwater or above the water, and the comfort and safety during the underwater operation period are very difficult. Risks are difficult to predict.

为了使悬浮隧道的受力更为合理,减小施工期不利海况的影响,更有利于施工期的控制、营运期的维护与零部件更换,提出了一种水下斜拉式缆索体系悬浮隧道结构及隧道管节顶推安装的施工方法。水下斜拉式缆索体系悬浮隧道由水中悬浮隧道1、接岸结构2、斜拉索锚碇系统、浮重比调节系统、防撞警示系统、逃生系统、隧道附属设施等组成。水中悬浮隧道1与接岸结构2相连,通过陆域斜坡隧道6与地面道路连接,水中悬浮隧道1上设斜拉索3并固于隧道两侧岸5上的拉索锚碇墩4上形成稳定的受力体系(见图1)。斜拉式悬浮隧道的管节顶推安装的施工方法为:所有的管节在隧道陆域进(或出)口后方预制场预制后,经由陆域斜坡隧道6运输至接岸结构2内,进行逐节对接、二次舾装、密封入水,然后逐节顶推至对岸的接岸结构2内,顶推完成后,在接岸结构2内浇灌接岸段管节外表面的混凝土,完成水中悬浮隧道1两端的接岸段管节与接岸结构2的固结。In order to make the force of the suspension tunnel more reasonable, reduce the influence of the unfavorable sea conditions during the construction period, and be more conducive to the control during the construction period, the maintenance during the operation period and the replacement of parts, an underwater cable-stayed cable system suspension tunnel is proposed. Structure and construction method of jack-up installation of tunnel pipe sections. The underwater cable-stayed cable system suspension tunnel is composed of an underwater suspension tunnel 1, a shore connection structure 2, a cable-stayed anchor system, a floating-weight ratio adjustment system, an anti-collision warning system, an escape system, and tunnel auxiliary facilities. The underwater suspension tunnel 1 is connected to the shore connection structure 2, and is connected to the ground road through the land slope tunnel 6. The underwater suspension tunnel 1 is provided with stay cables 3 and fixed on the cable anchor piers 4 on the banks 5 on both sides of the tunnel to form a stable structure. the force system (see Figure 1). The construction method of pushing and installing the pipe sections of the cable-stayed suspension tunnel is as follows: after all the pipe sections are prefabricated in the prefabrication field behind the entrance (or exit) of the land area of the tunnel, they are transported to the shore connection structure 2 through the land area slope tunnel 6 for Docking section by section, outfitting for the second time, sealing into the water, and then pushing it into the landing structure 2 on the opposite bank one by one. After the jacking is completed, pour the concrete on the outer surface of the pipe section of the landing section in the landing structure 2 to complete the floating tunnel 1 in the water. Consolidation of the pipe joints of the landing section at both ends and the landing structure 2.

籍此需要提出一种与水下斜拉式缆索体系悬浮隧道结构及施工方法相对应的拉索锚锭系统。Therefore, it is necessary to propose a cable anchor system corresponding to the suspended tunnel structure and construction method of the underwater cable-stayed cable system.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于填补现有技术的空白而提供一种水下斜拉式悬浮隧道的拉索锚锭系统,它在隧道管节安装时,可用于隧道定位;在隧道营运期,又可进行索力监测与拉索维护及更换。The purpose of the present invention is to fill the gap of the prior art and provide a cable anchor system for an underwater cable-stayed suspension tunnel, which can be used for tunnel positioning when the tunnel pipe section is installed; Cable force monitoring and cable maintenance and replacement.

本发明的目的是这样实现的:一种水下斜拉式悬浮隧道的拉索锚锭系统,所述水下斜拉式悬浮隧道包括隧道本体、一对接岸结构、拉索锚碇系统和浮重比调节系统;所述隧道本体包括水中悬浮隧道和陆域斜坡隧道;The purpose of the present invention is to achieve this: a cable anchor system for an underwater cable-stayed suspension tunnel, the underwater cable-stayed suspension tunnel includes a tunnel body, a pair of shore structures, a cable anchor system and a floating Gravity ratio adjustment system; the tunnel body includes a water suspension tunnel and a land slope tunnel;

所述拉索锚碇系统采用双向单索面或双向双索面并包括四个拉索接收井、四组拉索转向墩、拉索坡道和多道斜拉索;其中,The cable anchor system adopts bidirectional single cable plane or bidirectional double cable plane and includes four cable receiving wells, four groups of cable steering piers, cable ramps and multi-channel stay cables; wherein,

四个拉索接收井一一对应设在隧道两侧的此岸侧海岸上和隧道两侧的对岸侧海岸上;每个所述拉索接收井包括拉索锚碇墩和监控室;所述拉索锚碇墩设在拉索接收井的下部;所述拉索锚碇墩的临水侧设有导缆器;拉索锚碇墩的中部开设索力监测槽,索力监测槽内设置索力监测器,索力监测槽的两端为锚碇块;拉索锚碇墩的后端设置电动锚机;所述监控室设在拉索接收井的上部,该监控室内设置斜拉索监控装置;Four cable receiving wells are located on the shore on both sides of the tunnel and on the opposite bank on both sides of the tunnel in one-to-one correspondence; each cable receiving well includes cable anchoring piers and a monitoring room; The cable anchor pier is arranged at the lower part of the cable receiving well; the water-facing side of the cable anchor pier is provided with a fairlead; the middle part of the cable anchor pier is provided with a cable force monitoring slot, and the cable force monitoring slot is arranged in the cable force monitoring slot. Force monitor, the two ends of the cable force monitoring slot are anchor blocks; the rear end of the cable anchor pier is provided with an electric windlass; the monitoring room is set at the upper part of the cable receiving well, and the monitoring room is provided with a stay cable monitoring device;

四组拉索转向墩一一对应设在隧道两侧的此岸侧海岸岸坡上和隧道两侧的对岸侧海岸岸坡上并一一对应地靠近四个拉索接收井;每组拉索转向墩均位于航道最大深度处;每组拉索转向墩的数量为斜拉索总道数的一半;每个拉索转向墩的底部均高于水中悬浮隧道的高程且不高于航道最小底高程;每个拉索转向墩的内部沿斜拉索方向设置拉索通道,拉索通道上预埋有转向导缆器;Four groups of cable steering piers are located on the shore slope on both sides of the tunnel and on the opposite shore side of the tunnel in a one-to-one correspondence, and are close to the four cable receiving wells in a one-to-one correspondence; each group of cable steering The piers are located at the maximum depth of the channel; the number of cable steering piers in each group is half of the total number of stay cables; the bottom of each cable steering pier is higher than the elevation of the suspended tunnel in the water and not higher than the minimum bottom elevation of the channel ;In the interior of each stay cable steering pier, a cable channel is set along the direction of the stay cable, and a steering fairlead is pre-embedded on the cable channel;

所述拉索坡道设在每组拉索转向墩与对应的拉索接收井之间的岸坡上;The cable ramp is arranged on the bank slope between each group of cable steering piers and the corresponding cable receiving well;

多道斜拉索的一半为此岸侧斜拉索,另一半为对岸侧斜拉索;每道斜拉索包括两根各自连接在水中悬浮隧道两侧的斜拉索或四根以两两一对各自连接在水中悬浮隧道两侧的斜拉索;所述此岸侧斜拉索的一端间隔地锚固在靠近此岸的一半长度的水中悬浮隧道的两侧外表面的拉索锚上,此岸侧斜拉索的另一端各自穿过设在此岸的两组拉索转向墩后沿拉索坡道引伸至地面,再锚固于设在此岸的两个拉索锚碇墩上;所述对岸侧斜拉索的一端间隔地锚固在靠近对岸的水中悬浮隧道的两侧外表面的拉索锚上,对岸侧斜拉索的另一端各自穿过设在对岸的两组拉索转向墩后沿拉索坡道引伸至地面,再锚固于设在对岸的两个拉索锚碇墩上。Half of the multi-channel stay cable is the bank side stay cable, and the other half is the opposite bank side stay cable; For the stay cables connected to the two sides of the water suspension tunnel respectively; one end of the shore side stay cable is anchored at intervals on the stay cable anchors on the outer surfaces of both sides of the water suspension tunnel near the half length of the bank, and the bank side is inclined. The other end of the stay cable passes through the two sets of stay-cable steering piers on the bank, and then extends to the ground along the stay-cable ramp, and then anchors on the two stay-cable anchor piers on the bank. One end of the cable is anchored at intervals on the cable anchors on the outer surfaces of the two sides of the water suspension tunnel close to the opposite bank. The road is extended to the ground, and then anchored on the two cable anchor piers on the opposite bank.

上述的水下斜拉式悬浮隧道的拉索锚锭系统,其中,所述拉索锚锭系统还包括四个各自设在四个拉索接收井的后方的陆上地面上的动力站。In the above-mentioned cable anchor system for an underwater cable-stayed suspension tunnel, the cable anchor system further includes four power stations each provided on the land behind the four cable receiving wells.

上述的水下斜拉式悬浮隧道的拉索锚锭系统,其中,所述拉索锚碇墩为下部设桩基础的钢筋混凝土墩式结构。In the above-mentioned cable anchor system of an underwater cable-stayed suspension tunnel, the cable anchor pier is a reinforced concrete pier structure with a pile foundation at the lower part.

上述的水下斜拉式悬浮隧道的拉索锚锭系统,其中,每个拉索转向墩为下部设桩基础的钢筋混凝土墩式结构。In the above-mentioned cable anchor system of an underwater cable-stayed suspension tunnel, each cable steering pier is a reinforced concrete pier structure with a pile foundation at the bottom.

上述的水下斜拉式悬浮隧道的拉索锚锭系统,其中,所述拉索坡道的结构至下而上依次为抛石护坡、碎石垫层和混凝土面层。In the above-mentioned cable anchor system of an underwater cable-stayed suspension tunnel, the structure of the cable ramp is composed of riprap slope protection, crushed stone cushion and concrete surface layer in order from bottom to top.

上述的水下斜拉式悬浮隧道的拉索锚锭系统,其中,所述斜拉索采用超高分子量聚乙烯纤维缆,斜拉索的水中浮重比为1。In the above-mentioned cable anchor system of an underwater cable-stayed suspension tunnel, the cable-stayed cable adopts an ultra-high molecular weight polyethylene fiber cable, and the water-floating-to-weight ratio of the cable-stayed cable is 1.

本发明的水下斜拉式悬浮隧道的拉索锚锭系统具有以下特点:The cable anchor system of the underwater cable-stayed suspension tunnel of the present invention has the following characteristics:

1)本发明的水下悬浮隧道拉索锚碇系统适用于斜拉式水下悬浮隧道型式,尤其适用于采用顶推安装工艺的斜拉式悬浮隧道型式。1) The underwater suspension tunnel cable anchor system of the present invention is suitable for the cable-stayed underwater suspension tunnel type, especially suitable for the cable-stayed suspension tunnel type using the jacking installation process.

2)本发明的拉索锚碇系统在隧道管节安装时,可用于隧道定位;在隧道营运期,又可进行索力监测与拉索维护及更换。2) The cable anchor system of the present invention can be used for tunnel positioning when the tunnel pipe section is installed; during the tunnel operation period, it can also perform cable force monitoring and cable maintenance and replacement.

3)本发明的水下悬浮隧道拉索锚碇系统将斜拉索引伸至水面以上,且拉索锚碇墩位于拉索监控室内,因此,悬浮隧道管节安装不受外海水文、气象条件制约,大大减少工期。3) The cable anchor system of the underwater suspension tunnel of the present invention extends the cable-stayed index to above the water surface, and the cable anchor pier is located in the cable monitoring room. Therefore, the installation of the suspension tunnel pipe joint is not restricted by the climatic and meteorological conditions of the open sea , greatly reducing the construction period.

4)本发明的水下悬浮隧道拉索锚碇系统能在施工期与营运期对悬浮隧道浮重比调节时相应调整斜拉索的长度和拉力。4) The stay cable anchorage system of the underwater suspension tunnel of the present invention can adjust the length and tension of the stay cable correspondingly when adjusting the buoyancy-to-weight ratio of the suspension tunnel during the construction period and the operation period.

附图说明Description of drawings

图1是水下斜拉式悬浮隧道的平面图;Fig. 1 is the plan view of underwater cable-stayed suspension tunnel;

图2是本发明的水下斜拉式悬浮隧道的拉索锚锭系统的结构示意图;Fig. 2 is the structural representation of the cable anchor system of the underwater cable-stayed suspension tunnel of the present invention;

图3是本发明的水下斜拉式悬浮隧道的拉索锚锭系统中拉索接收井的结构示意图;Fig. 3 is the structural representation of the cable receiving well in the cable anchor system of the underwater cable-stayed suspension tunnel of the present invention;

图4是本发明的水下斜拉式悬浮隧道的拉索锚锭系统中拉索锚碇墩的结构示意图;Fig. 4 is the structural representation of the cable anchor pier in the cable anchor system of the underwater cable-stayed suspension tunnel of the present invention;

图5是本发明的水下斜拉式悬浮隧道的拉索锚锭系统中拉索转向墩的结构示意图。5 is a schematic structural diagram of a cable steering pier in the cable anchor system of the underwater cable-stayed suspension tunnel of the present invention.

具体实施方式Detailed ways

下面将结合附图对本发明作进一步说明。The present invention will be further described below with reference to the accompanying drawings.

请参阅图1至图5,本发明的水下斜拉式悬浮隧道的拉索锚锭系统,适用的水下斜拉式悬浮隧道由隧道本体、一对接岸结构2、斜拉索锚碇系统和浮重比调节系统、防撞警示系统、逃生系统、隧道附属设施等组成。隧道本体包括水中悬浮隧道1和陆域斜坡隧道6,水中悬浮隧道1由预制的多段隧道管节连接而成;一对接岸结构2各自设在两岸岸坡5附近的稳定地基上。Please refer to FIG. 1 to FIG. 5 , the cable anchor system of the underwater cable-stayed suspension tunnel of the present invention is suitable for the underwater cable-stayed suspension tunnel. It is composed of float-weight ratio adjustment system, anti-collision warning system, escape system, tunnel auxiliary facilities, etc. The tunnel body includes an underwater suspension tunnel 1 and a land slope tunnel 6. The underwater suspension tunnel 1 is connected by prefabricated multi-section tunnel pipe joints;

本发明的拉索锚碇系统采用双向单索面或双向双索面并包括四个拉索接收井4、四个动力站7、四组拉索转向墩8、拉索坡道9和多道斜拉索3。The cable anchoring system of the present invention adopts two-way single cable plane or two-way double cable plane and includes four cable receiving wells 4, four power stations 7, four groups of cable steering piers 8, cable ramps 9 and multiple channels stay cable 3.

四个拉索接收井4一一对应设在隧道两侧的此岸侧海岸上和隧道两侧的对岸侧海岸上;每个拉索接收井4包括拉索锚碇墩4A和监控室4B;其中,The four cable receiving wells 4 are located on the shore on both sides of the tunnel and on the opposite bank on both sides of the tunnel in one-to-one correspondence; each cable receiving well 4 includes a cable anchor pier 4A and a monitoring room 4B; ,

拉索锚碇墩4A设在拉索接收井4的下部;拉索锚碇墩4A为下部设桩基础40的钢筋混凝土墩式结构,以增加抗拔力并保证岸坡稳定;拉索锚碇墩4A的临水侧设有导缆器41,使斜拉索3转向水平方向;拉索锚碇墩4A的中部设有索力监测槽42,索力监测槽42内设置索力监测器43;索力监测槽42的两端为锚碇块,锚碇块均用于斜拉索3锚固;拉索锚碇墩4A的后端设置电动锚机44,用于斜拉索3张紧;The cable anchor pier 4A is located at the lower part of the cable receiving well 4; the cable anchor pier 4A is a reinforced concrete pier structure with a pile foundation 40 at the lower part to increase the pullout resistance and ensure the stability of the bank slope; A fairlead 41 is provided on the waterside side of the pier 4A to turn the stay cable 3 in the horizontal direction; a cable force monitoring slot 42 is arranged in the middle of the cable anchor pier 4A, and a cable force monitor 43 is arranged in the cable force monitoring slot 42 The two ends of the cable force monitoring groove 42 are anchor blocks, and the anchor blocks are all used for the anchoring of stay cables 3;

监控室4B设在拉索接收井4的上部,监控室4B内设置斜拉索监控装置45。The monitoring room 4B is arranged on the upper part of the cable receiving well 4, and the monitoring device 45 for the stay cable is arranged in the monitoring room 4B.

四个动力站7一一对应地设在四个拉索接收井4的后方的陆上地面上。The four power stations 7 are provided on the land behind the four cable receiving wells 4 in a one-to-one correspondence.

四组拉索转向墩8一一对应设在隧道两侧的此岸侧海岸岸坡上和隧道两侧的对岸侧海岸岸坡上并一一对应地靠近四个拉索接收井4;每组拉索转向墩8均位于航道最大深度处;每组拉索转向墩4的数量为斜拉索3总道数的一半;每个拉索转向墩8为下部设桩基础80的钢筋混凝土墩式结构;每个拉索转向墩8的底部均高于水中悬浮隧道1的高程且不高于航道最小底高程;每个拉索转向墩8的内部沿斜拉索3方向设置拉索通道,拉索通道上预埋有转向导缆器81。The four groups of cable steering piers 8 are located on the shore slope on both sides of the tunnel and on the opposite shore side of the tunnel in a one-to-one correspondence, and are close to the four cable receiving wells 4 in a one-to-one correspondence; The cable steering piers 8 are all located at the maximum depth of the channel; the number of each group of cable steering piers 4 is half of the total number of stay cables 3; each cable steering pier 8 is a reinforced concrete pier structure with a pile foundation 80 at the bottom ; The bottom of each cable steering pier 8 is higher than the elevation of the water suspension tunnel 1 and not higher than the minimum bottom elevation of the channel; the interior of each cable steering pier 8 is set along the direction of the stay cable 3. A steering fairlead 81 is pre-embedded on the channel.

拉索坡道9设在每组拉索转向墩8与对应的拉索接收井4之间的岸坡上;拉索坡道9的结构至下而上依次为抛石护坡、碎石垫层和混凝土面层。The cable ramp 9 is arranged on the bank slope between each group of cable steering piers 8 and the corresponding cable receiving well 4; and concrete surface.

多道斜拉索3的一半为此岸侧斜拉索,另一半为对岸侧斜拉索;若采用双向单索面,每道斜拉索3包括两根各自连接在水中悬浮隧道1两侧的斜拉索;若采用双向双索面,每道斜拉索3包括四根以两两一对各自连接在水中悬浮隧道1两侧的斜拉索;此岸侧斜拉索的一端间隔地锚固在靠近此岸的一半长度的水中悬浮隧道1的两侧外表面的拉索锚上,此岸侧斜拉索的另一端各自通穿过设在此岸的两组拉索转向墩8后沿拉索坡道9引伸至地面,再锚固于设在此岸的两个拉索锚碇墩4A上;对岸侧斜拉索3的一端间隔地锚固在靠近对岸的水中悬浮隧道1的两侧外表面的拉索锚上,对岸侧斜拉索的另一端各自穿过设在对岸的两组拉索转向墩8后沿拉索坡道9引伸至地面,再锚固于设在对岸的两个拉索锚碇墩4A上。Half of the multi-channel stay cables 3 are the bank side stay cables, and the other half are the opposite bank side stay cables; Stay cables; if two-way double cable planes are used, each stay cable 3 includes four stay cables connected to both sides of the water suspension tunnel 1 in pairs; one end of the shore-side stay cables is anchored at intervals On the cable anchors on the outer surfaces of the two sides of the water suspension tunnel 1 near the half length of the bank, the other ends of the stay cables on the bank side respectively pass through the two sets of cable steering piers 8 set on the bank and then follow the cable ramp. 9. Extend to the ground, and then anchor on the two stay cable anchor piers 4A set on this bank; one end of the stay cable 3 on the opposite bank is anchored at intervals on the outer surfaces of the two sides of the water suspension tunnel 1 close to the opposite bank. On the other side, the other ends of the stay cables on the opposite bank respectively pass through the two sets of cable steering piers 8 located on the opposite bank, and then extend to the ground along the cable ramp 9, and then anchor to the two cable anchor piers 4A located on the opposite bank. superior.

斜拉索3主要用于抵抗水流力等水平力,同时为了保持水中悬浮隧道1的水下稳定,水中悬浮隧道1的重力略大于浮力,同时考虑到营运期水中悬浮隧道1的自重可能会加大,因此斜拉索3同时承受部分隧道管节的重量产生的垂直力,斜拉索3必须具备耐磨、耐腐、抗拉强度高及便于更换等性能要求,因此斜拉索3采用超高分子量聚乙烯纤维缆,并且斜拉索3的水中浮重比为1。The stay cable 3 is mainly used to resist horizontal forces such as water flow force, and at the same time, in order to maintain the underwater stability of the suspended tunnel 1 in the water, the gravity of the suspended tunnel 1 in the water is slightly larger than the buoyancy. Therefore, the stay cable 3 bears the vertical force generated by the weight of part of the tunnel pipe at the same time. The stay cable 3 must have the performance requirements of wear resistance, corrosion resistance, high tensile strength and easy replacement. High molecular weight polyethylene fiber cable, and the floating weight ratio of the stay cable 3 in water is 1.

本发明的水下斜拉式悬浮隧道的拉索锚锭系统,主要用于固定水中悬浮隧道1,其基本原理是斜拉索3提供给水中悬浮隧道1斜向上的拉力,与隧道管节所承受的重力、水流力、波浪力等产生力的平衡,使水中悬浮隧道1能够稳定于设计位置。力的传递方式为隧道管节所受的荷载通过斜拉索3传递至拉索锚定墩4A。拉索锚碇系统需满足悬浮隧道施工期隧道管节水下顶推安装工艺要求和悬浮隧道使用期斜拉索3的锚碇与受力监控要求。设计的基本原则是受力体系合理、技术可靠、施工方便,同时具备良好的耐久性及可维护。The cable anchor system of the underwater cable-stayed suspension tunnel of the present invention is mainly used for fixing the underwater suspension tunnel 1. The balance of the generated forces such as gravity, water flow force, wave force, etc., enables the underwater suspension tunnel 1 to be stable in the design position. The force transmission mode is that the load on the tunnel pipe section is transmitted to the stay cable anchor pier 4A through the stay cable 3 . The cable anchor system needs to meet the technical requirements of underwater jacking and installation of the tunnel pipe section during the construction period of the suspension tunnel and the anchorage and force monitoring requirements of the stay cable 3 during the service period of the suspension tunnel. The basic principles of design are reasonable force system, reliable technology, convenient construction, good durability and maintainability.

斜拉索3锚固于岸上的拉索锚碇墩4A上,拉索锚碇墩4A必须位于海岸地面稳定的地基上,且满足边坡稳定的要求,必须进行抗拔力及对岸坡稳定性验算。拉索锚碇墩4A上布置索力监测器43与电动锚机44,用于索力监控。斜拉索3的索力监控、营运期的更换在拉索锚碇墩4A上的拉索监控室4B内进行。斜拉索3通过拉索转向墩8中的转向导缆器81沿着水下的拉索坡道9引伸至地面,锚固于拉索锚碇墩4A上;每道斜拉索3单独配置一个拉索转向墩8,拉索转向墩8是用于斜拉索3的转向并且是为了降低斜拉索3在水中的标高,使之不影响通航;斜拉索3由拉索转向墩8中的转向导缆器81的下部穿过,然后沿着拉索坡道9引伸至水面之上,以便于斜拉索3的张紧操作;当张紧斜拉索3时,拉索转向墩8受到向上的拉力,因此拉索转向墩8必须具有足够的抗拔力和承受水平荷载的能力。拉索转向墩8的底部高于隧道高程,且不高于航道最小底高程,拉索面与水平方向夹角不大于45°且拉索转向墩8必须位于岸坡内稳定的地基上,满足边坡稳定的要求,必须进行抗拔力及岸坡稳定性验算。拉索坡道9的坡面为整体式,即包括单侧所有斜拉索3的范围,既防止斜拉索3受到磨损,又对岸坡进行防护。The stay cable 3 is anchored on the cable anchor pier 4A on the shore. The cable anchor pier 4A must be located on a stable foundation on the coast and meet the requirements of slope stability. The pullout resistance and the stability of the bank slope must be checked. . A cable force monitor 43 and an electric windlass 44 are arranged on the cable anchor pier 4A for monitoring the cable force. The monitoring of the cable force of the stay cable 3 and the replacement during the operation period are carried out in the cable monitoring room 4B on the cable anchor pier 4A. The stay cable 3 is extended to the ground along the underwater stay cable ramp 9 through the steering fairlead 81 in the stay cable steering pier 8, and is anchored on the stay cable anchor pier 4A; each stay cable 3 is individually configured with one The cable steering pier 8, the cable steering pier 8 is used for the steering of the stay cable 3 and is to reduce the elevation of the stay cable 3 in the water, so that it does not affect the navigation; the stay cable 3 is turned from the stay cable to the pier 8 The lower part of the steering fairlead 81 is passed through, and then extended along the cable ramp 9 to above the water surface, so as to facilitate the tensioning operation of the stay cable 3; when the stay cable 3 is tensioned, the stay cable turns to the pier 8 Due to the upward pulling force, the cable steering pier 8 must have sufficient pull-out resistance and the ability to bear horizontal loads. The bottom of the cable steering pier 8 is higher than the tunnel elevation, and not higher than the minimum bottom elevation of the channel, the angle between the cable surface and the horizontal direction is not greater than 45°, and the cable steering pier 8 must be located on a stable foundation within the bank slope, satisfying To meet the requirements of slope stability, the pullout resistance and bank slope stability must be checked. The slope surface of the stay cable ramp 9 is integral, that is, it includes the range of all the stay cables 3 on one side, which not only prevents the stay cables 3 from being worn, but also protects the bank slope.

本发明的水下斜拉式悬浮隧道的拉索锚锭系统的施工步骤如下:The construction steps of the cable anchor system of the underwater cable-stayed suspension tunnel of the present invention are as follows:

步骤一:拉索转向墩8的桩基水上沉桩。Step 1: The cable turns the pile foundation of the pier 8 to sink the pile on the water.

步骤二:拉索转向墩8围堰施工;Step 2: Construction of cofferdam 8 for cable steering pier;

步骤三:拉索转向墩8现浇施工;Step 3: Cast-in-place construction of the cable steering pier 8;

步骤四:拉索坡道9施工;Step 4: Construction of cable ramp 9;

步骤五:拉索锚碇墩4A的混凝土现浇施工;Step 5: Concrete cast-in-place construction of cable anchor pier 4A;

步骤六:拉索转向墩8上的斜拉索3的临时导缆索安装;Step 6: The temporary fairlead installation of the stay cable 3 on the cable steering pier 8;

步骤七:拉索转向墩8的围堰拆除;Step 7: Remove the cofferdam of the cable steering pier 8;

步骤八:隧道管节安装,斜拉索3安装、初张拉;Step 8: Installation of tunnel pipe sections, installation of stay cables 3, and initial tensioning;

步骤九:水中悬浮隧道1的索力调节;Step 9: Adjust the cable force of the suspended tunnel 1 in the water;

步骤十:斜拉索3的锚固端保险索安装、封锚。Step 10: Install and seal the safety cable at the anchoring end of the stay cable 3.

本发明的水下斜拉式悬浮隧道的拉索锚锭系统的施工要求是:The construction requirements of the cable anchor system of the underwater cable-stayed suspension tunnel of the present invention are:

斜拉索3与隧道管节的对接端在接岸结构2安装,并将其全部临时固定在隧道管节上,斜拉索3的另一端用牵引绳穿过拉索转向墩8并引至拉索锚定墩4A上。斜拉索3随隧道管节顶推出接岸结构2后张拉牵引绳将斜拉索3引至拉索锚定墩4A,然后根据隧道管节顶推及斜拉索3的受力要求调节斜拉索3的长度和拉力。斜拉索3的长度和拉力通过拉索锚定墩4A上的电动锚机44调整,斜拉索3的拉力大小通过索力监测器43实时测得。The butt end of the stay cable 3 and the tunnel tube section is installed on the shore connection structure 2, and all of them are temporarily fixed on the tunnel tube section. The cable is anchored to the pier 4A. The stay cable 3 is pushed out of the landing structure 2 along with the top of the tunnel tube section, and then the traction rope is stretched to guide the stay cable 3 to the cable anchor pier 4A, and then the slope is adjusted according to the push of the tunnel tube section and the force requirements of the stay cable 3. Length and tension of cable 3. The length and tension of the stay cable 3 are adjusted by the electric windlass 44 on the cable anchor pier 4A, and the tension of the stay cable 3 is measured in real time by the cable force monitor 43 .

拉索转向墩8位于水中,桩基80可以采用打桩船施工或水上搭设临时平台施工,混凝土墩台及附属设施安装可采用围堰法形成干施工条件后施工。The cable steering pier 8 is located in the water, the pile foundation 80 can be constructed by a piling boat or a temporary platform on the water, and the concrete pier and ancillary facilities can be installed by using the cofferdam method to form dry construction conditions.

拉索坡道9的水面以下部分可以由挖泥船进行基槽开挖,水上抛石护坡,潜水员水下整平碎石基础,混凝土面层采用预制安装方法施工;水面以上部分采用挖机进行土方开挖及基础换填,混凝土采用现浇工艺,必要时可以设置临时支护结构。The part below the water surface of the cable ramp 9 can be excavated by a dredger for foundation trenches, riprap on the water for slope protection, divers to level the gravel foundation underwater, and the concrete surface layer is constructed by prefabricated installation method; the part above the water surface is carried out by excavators Earthwork excavation and foundation replacement, the concrete is cast-in-place, and temporary support structures can be set up if necessary.

拉索锚碇井4的结构施工位于岸边,拉索锚定墩4A的施工可采用围堰内现浇法,其余结构均位于陆上地面以上,施工方法简便。The structural construction of the cable anchor shaft 4 is located on the shore, and the construction of the cable anchor pier 4A can adopt the cast-in-place method in the cofferdam.

以上实施例仅供说明本发明之用,而非对本发明的限制,有关技术领域的技术人员,在不脱离本发明的精神和范围的情况下,还可以作出各种变换或变型,因此所有等同的技术方案也应该属于本发明的范畴,应由各权利要求所限定。The above embodiments are only for illustrating the present invention, rather than limiting the present invention. Those skilled in the relevant technical field can also make various changes or modifications without departing from the spirit and scope of the present invention. Therefore, all equivalents The technical solution of the invention should also belong to the scope of the present invention and should be defined by the claims.

Claims (6)

1. A guy cable anchor system of an underwater cable-stayed suspension tunnel comprises a tunnel body, a butt-joint shore structure, a guy cable anchor system and a floating weight ratio adjusting system; the tunnel body comprises an underwater suspension tunnel and a land slope tunnel; it is characterized in that the preparation method is characterized in that,
the cable anchorage system adopts a bidirectional single cable surface or a bidirectional double cable surface and comprises four cable receiving wells, four groups of cable steering piers, a cable ramp and a plurality of stay cables; wherein,
the four inhaul cable receiving wells are correspondingly arranged on the shore side seashore at two sides of the tunnel and the opposite shore side seashore at two sides of the tunnel one by one; each cable receiving well comprises a cable anchorage pier and a monitoring room; the guy cable anchorage pier is arranged at the lower part of the guy cable receiving well; a cable guide device is arranged on the water side of the guy cable anchorage pier; a cable force monitoring groove is formed in the middle of the cable anchorage pier, a cable force monitor is arranged in the cable force monitoring groove, and anchorage blocks are arranged at two ends of the cable force monitoring groove; the rear end of the guy cable anchorage pier is provided with an electric anchor machine; the monitoring chamber is arranged at the upper part of the inhaul cable receiving well, and the inhaul cable monitoring device is arranged in the monitoring chamber;
the four groups of cable steering piers are correspondingly arranged on the bank side coast bank slopes on two sides of the tunnel and the opposite bank side coast bank slopes on two sides of the tunnel one by one and are close to the four cable receiving wells one by one; each group of stay cable steering piers are positioned at the maximum depth of the channel; the number of the stay cable steering piers in each group is half of the total number of the stay cables; the bottom of each guy cable steering pier is higher than the elevation of the underwater suspended tunnel and not higher than the minimum bottom elevation of the channel; a stay cable channel is arranged in each stay cable steering pier along the direction of a stay cable, and a steering cable guide is embedded in each stay cable channel;
the stay cable ramp is arranged on a bank slope between each group of stay cable steering piers and the corresponding stay cable receiving well;
one half of the plurality of stay cables is the shore side stay cable, and the other half is the opposite shore side stay cable; each stay cable comprises two stay cables which are respectively connected with two sides of the underwater suspension tunnel or four stay cables which are respectively connected with two sides of the underwater suspension tunnel in pairs; one end of the bank side inclined guy cable is anchored on guy cable anchors on the outer surfaces of two sides of the underwater suspended tunnel which is close to the half length of the bank at intervals, and the other end of the bank side inclined guy cable penetrates through two groups of guy cable steering piers arranged on the bank respectively and then extends to the ground along guy cable ramp ways and is anchored on two guy cable anchor piers arranged on the bank; one end of each opposite bank side inclined guy cable is anchored on guy cable anchors on the outer surfaces of the two sides of the water suspension tunnel close to the opposite bank at intervals, and the other end of each opposite bank side inclined guy cable penetrates through two groups of guy cable steering piers arranged on the opposite bank and then extends to the ground along a guy cable ramp and is anchored on two guy cable anchor piers arranged on the opposite bank.
2. A cable anchor system for an underwater cable-stayed suspension tunnel according to claim 1, wherein the cable anchor system further comprises four power stations each provided on the land ground behind the four cable receiving wells.
3. The cable anchor system of the underwater cable-stayed suspension tunnel according to claim 1 or 2, wherein the cable anchor pier is a reinforced concrete pier structure with a pile foundation at the lower part.
4. The cable anchor system of an underwater cable-stayed suspension tunnel according to claim 1 or 2, wherein each cable deflector pier is a reinforced concrete pier structure having a pile foundation at the lower part.
5. The cable anchor system of the underwater cable-stayed suspension tunnel according to claim 1 or 2, wherein the structure of the cable ramp is a riprap slope, a gravel cushion layer and a concrete surface layer in sequence from bottom to top.
6. A cable anchor system for an underwater cable-stayed suspension tunnel according to claim 1 or 2, wherein the stay cable is an ultra-high molecular weight polyethylene fiber cable, and the underwater buoyant weight ratio of the stay cable is 1.
CN202010063372.4A 2020-01-20 2020-01-20 A cable anchor system for an underwater cable-stayed suspension tunnel Active CN111254979B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010063372.4A CN111254979B (en) 2020-01-20 2020-01-20 A cable anchor system for an underwater cable-stayed suspension tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010063372.4A CN111254979B (en) 2020-01-20 2020-01-20 A cable anchor system for an underwater cable-stayed suspension tunnel

Publications (2)

Publication Number Publication Date
CN111254979A CN111254979A (en) 2020-06-09
CN111254979B true CN111254979B (en) 2021-05-07

Family

ID=70923668

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010063372.4A Active CN111254979B (en) 2020-01-20 2020-01-20 A cable anchor system for an underwater cable-stayed suspension tunnel

Country Status (1)

Country Link
CN (1) CN111254979B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111851587B (en) * 2020-07-23 2021-06-29 浙江大学 Telescopic vibration-damping mooring-type suspension tunnel end connecting device and construction method
CN112554056B (en) * 2020-12-16 2022-04-22 长江水利委员会长江科学院 Horizontal anchorage structure of suspension bridge and construction method
CN112832323B (en) * 2021-02-24 2022-06-24 河南省水利勘测设计研究有限公司 Floating dock adaptive balancing system and balancing method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0898625A1 (en) * 1996-05-15 1999-03-03 Giulio Cambiuzzi A submerged tunnel with buoyant suspension
CN201554037U (en) * 2009-11-12 2010-08-18 陈�峰 Marine traffic submerged passage
CN205636492U (en) * 2016-05-09 2016-10-12 上海振华重工(集团)股份有限公司 Suspension cable bridge anchor case member
CN106958190A (en) * 2017-05-03 2017-07-18 中交第二公路勘察设计研究院有限公司 A kind of ground anchor type single pylon cable stayed bridge structure
CN107618622A (en) * 2017-08-31 2018-01-23 中交第四航务工程局有限公司 A kind of traversing mooring fairlead of immersed tube
CN107761542A (en) * 2017-11-14 2018-03-06 江苏科技大学 One kind arch oblique pull combined system bridge and its construction method
CN208441142U (en) * 2018-07-02 2019-01-29 四川锦城智信建设工程有限公司 A kind of shield tunnel pipe gallery

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0898625A1 (en) * 1996-05-15 1999-03-03 Giulio Cambiuzzi A submerged tunnel with buoyant suspension
CN201554037U (en) * 2009-11-12 2010-08-18 陈�峰 Marine traffic submerged passage
CN205636492U (en) * 2016-05-09 2016-10-12 上海振华重工(集团)股份有限公司 Suspension cable bridge anchor case member
CN106958190A (en) * 2017-05-03 2017-07-18 中交第二公路勘察设计研究院有限公司 A kind of ground anchor type single pylon cable stayed bridge structure
CN107618622A (en) * 2017-08-31 2018-01-23 中交第四航务工程局有限公司 A kind of traversing mooring fairlead of immersed tube
CN107761542A (en) * 2017-11-14 2018-03-06 江苏科技大学 One kind arch oblique pull combined system bridge and its construction method
CN208441142U (en) * 2018-07-02 2019-01-29 四川锦城智信建设工程有限公司 A kind of shield tunnel pipe gallery

Also Published As

Publication number Publication date
CN111254979A (en) 2020-06-09

Similar Documents

Publication Publication Date Title
EP3865627B1 (en) Submerged cable-stayed floating tunnel structure
EP3882399B1 (en) Incremental launching process for a submerged cable-stayed floating tunnel
CN111254984B (en) A tube joint connection structure of an underwater cable-stayed suspension tunnel
CN111424716B (en) An artificial island relay extension cable-stayed anchor-type suspension tunnel structure
CN111254979B (en) A cable anchor system for an underwater cable-stayed suspension tunnel
CN114855707A (en) Silt-promoting repair device and method for local erosion pit
CN111252196B (en) An anti-collision warning system for an underwater cable-stayed suspension tunnel
Rasmussen Concrete immersed tunnels—Forty years of experience
CN111254983B (en) A shore connection structure of an underwater cable-stayed suspension tunnel
CN108239998A (en) A kind of underwater bridge structure and its construction method
CN116290104B (en) Construction method for underwater section-by-section installation of anchored suspension tunnel
CN111254980B (en) Floating weight ratio adjusting system of underwater suspension tunnel
CN115787728A (en) A combined floating tunnel in water
CN111424715B (en) An artificial island pipe joint connection system for relay extension of suspension tunnel
CN111424714B (en) Guy cable anchorage system of diagonal-pulling anchorage type suspended tunnel with relay extension of artificial island
CN116464099B (en) A connect bank structure that is used for anchor suspension tunnel to install under water section by section
CN113585343B (en) A cable-stayed floating tunnel with cable flow piers and its construction method
CN111485579B (en) A bridge-tunnel transition structure between a suspension tunnel and a deep-water suspension bridge
WO1990015223A1 (en) Submerged bridge tunnel
CN111424719B (en) An external supply system for artificial island pipe sections for relay extension of suspension tunnels
Skorpa Developing new methods to cross wide and deep Norwegian fjords
LU600839B1 (en) Combined submerged floating tunnel and installation methodthereof
CN111485481B (en) A sea-crossing channel with suspended tunnels and deep-water suspension bridges
CN111424717B (en) A self-supply system of artificial island pipe section for relay extension of suspension tunnel
Crisp et al. DESIGN AND CONSTRUCTION OF A SUBMARINE SEA OUTFALL AT HASTINGS.

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant