CN111230349A - Lightning-arrest earth mat installation device - Google Patents

Lightning-arrest earth mat installation device Download PDF

Info

Publication number
CN111230349A
CN111230349A CN202010232794.XA CN202010232794A CN111230349A CN 111230349 A CN111230349 A CN 111230349A CN 202010232794 A CN202010232794 A CN 202010232794A CN 111230349 A CN111230349 A CN 111230349A
Authority
CN
China
Prior art keywords
plate
clamping
limit
bottom plate
screw
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010232794.XA
Other languages
Chinese (zh)
Other versions
CN111230349B (en
Inventor
郑淑华
吕东迎
郑全吉
王兆龙
陈洪涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Lu Sheng Electrical Equipment Co Ltd
Original Assignee
Shandong Lu Sheng Electrical Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Lu Sheng Electrical Equipment Co Ltd filed Critical Shandong Lu Sheng Electrical Equipment Co Ltd
Priority to CN202010232794.XA priority Critical patent/CN111230349B/en
Publication of CN111230349A publication Critical patent/CN111230349A/en
Application granted granted Critical
Publication of CN111230349B publication Critical patent/CN111230349B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K31/00Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups
    • B23K31/02Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups relating to soldering or welding
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G13/00Installations of lightning conductors; Fastening thereof to supporting structure
    • H02G13/40Connection to earth

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)
  • Clamps And Clips (AREA)

Abstract

The invention provides a lightning-protection ground net installation device, and belongs to the technical field of building construction. The technical scheme is as follows: the utility model provides a lightning-arrest ground net installation device, its characterized in that, includes the frame, the frame includes the bottom plate, the fixed riser that is provided with in one end top of bottom plate, the other end both sides of bottom plate are provided with outer fishplate bar, the top of riser is provided with the horizontal plate, the bottom plate with be provided with elevating system between the horizontal plate, the last clamping structure who reciprocates that is provided with of elevating system, two all be provided with anchor clamps on the outer fishplate bar. The invention has the beneficial effects that: can assist the manual work to install the angle steel and the band iron of ground net, the input of using manpower sparingly.

Description

一种避雷地网安装装置A lightning protection ground net installation device

技术领域technical field

本发明涉及建筑施工技术领域,尤其涉及一种避雷地网安装装置。The invention relates to the technical field of building construction, in particular to a lightning protection ground net installation device.

背景技术Background technique

“地网”建筑防雷设备地埋件,一般用良导体做成网状埋于地下,俗称地网。地网包括水平接地极和垂直接地极,水平接地极一般采用扁钢,垂直接地极一般采用角钢,扁钢和角钢通过焊接连接。在安装角钢和扁钢之前需要预先开挖沟槽并将沟底的石子清除,以便与安装角钢,角钢一般需要通过人工将角钢垂直打入地下,在没有特殊情况下,打入的深度一般为0.6M,角钢完成之后,需要将扁钢焊接在角钢上,由于扁钢的长度较长,在焊接时,需要至少两人进行扶正,一人进行焊接,安装起来比较麻烦。"Ground net" building lightning protection equipment buried parts, generally made of good conductors to make a mesh buried underground, commonly known as ground net. The ground grid includes a horizontal ground electrode and a vertical ground electrode. The horizontal ground electrode is generally made of flat steel, and the vertical ground electrode is generally made of angle steel. The flat steel and the angle steel are connected by welding. Before installing angle steel and flat steel, it is necessary to excavate the trench in advance and remove the stones at the bottom of the trench, so as to install the angle steel, the angle steel generally needs to be manually driven into the ground vertically. 0.6M, after the angle steel is completed, the flat steel needs to be welded on the angle steel. Due to the long length of the flat steel, during welding, at least two people are required for righting and one person for welding, which is more troublesome to install.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于提供一种可以辅助人工对地网的角钢和扁铁进行安装,节省人力的投入的避雷地网安装装置。The purpose of the present invention is to provide a lightning arrester ground net installation device which can assist in manually installing the angle steel and flat iron of the ground net and save manpower input.

本发明是通过如下措施实现的:一种避雷地网安装装置,其特征在于,包括机架,所述机架包括底板,所述底板的一端上方固定设置有立板,所述底板的另一端两侧设置有外接板,所述立板的上方设置有水平板,所述底板和所述水平板之间设置有升降机构,所述升降机构上设置有上下移动的夹持结构,两个所述外接板上均设置有夹具,两个所述外接板之间具有间距。The invention is realized by the following measures: a lightning protection ground net installation device is characterized in that it includes a frame, the frame includes a bottom plate, a vertical plate is fixed above one end of the bottom plate, and the other end of the bottom plate is fixed External plates are arranged on both sides, a horizontal plate is arranged above the vertical plate, a lifting mechanism is arranged between the bottom plate and the horizontal plate, and a clamping structure that moves up and down is arranged on the lifting mechanism. Clamps are arranged on the external boards, and there is a gap between the two external boards.

所述升降机构包括转动设置在所述底板和所述水平板之间的螺杆一,所述螺杆一的上端伸出所述水平板与驱动装置连接;所述驱动装置为带有减速器的电机。The lifting mechanism includes a screw rod 1 which is rotatably arranged between the bottom plate and the horizontal plate, and the upper end of the screw rod 1 extends out of the horizontal plate and is connected to a driving device; the driving device is a motor with a reducer .

所述夹持结构包括夹持底板,所述夹持底板的一端上方固定设置有横向柱,所述横向柱上插接设置有斜杆一和斜杆二,所述斜杆一和斜杆二对称设置,所述斜杆一上位于所述横向柱内侧的一端固定设置有内套杆,所述斜杆二上位于所述横向柱内侧的一端固定设置有外套杆,所述内套杆和所述外套杆水平设置且所述内套杆插接在所述外套杆内,所述倾斜杆一和倾斜杆二的另一端内侧均固定设置有夹持板,所述横向柱上设置夹持立板,所述夹持立板上转动设置有螺杆二,所述螺杆二上通过螺纹连接设置有推板,所述夹持底板上设置有对所述推板进行限位的凹槽,所述内套杆和所述外套杆位于所述推板和所述夹持立板之间;The clamping structure includes a clamping bottom plate, a transverse column is fixedly arranged above one end of the clamping bottom plate, and a diagonal rod 1 and a diagonal rod 2 are inserted on the transverse column, and the diagonal rod 1 and the diagonal rod 2 are inserted. Symmetrically arranged, an inner sleeve rod is fixedly arranged at one end of the first inclined rod on the inner side of the transverse column, and an outer sleeve rod is fixedly arranged at the end of the second inclined rod at the inner side of the transverse column, and the inner sleeve rod and The outer sleeve rod is arranged horizontally and the inner sleeve rod is inserted into the outer sleeve rod, the inner side of the other end of the inclined rod 1 and the inclined rod 2 are fixedly provided with a clamping plate, and a clamping plate is arranged on the transverse column. The vertical plate, the second screw is rotatably arranged on the clamping vertical plate, the second screw is provided with a push plate through screw connection, and the clamping bottom plate is provided with a groove for limiting the position of the push plate, so The inner sleeve rod and the outer sleeve rod are located between the push plate and the clamping vertical plate;

所述夹持底板通过螺纹连接设置在螺杆一上,所述水平板的下方且位于所述螺杆一的两侧固定设置有所述夹持底板的限位柱。The clamping bottom plate is provided on the first screw rod through screw connection, and the limit posts of the clamping bottom plate are fixedly arranged below the horizontal plate and on both sides of the screw rod one.

任一所述限位柱与所述底板之间具有间隔,另一所述限位柱的底端固定在所述底板,所述夹持底板通过所述间隔旋出。There is a gap between any one of the limiting columns and the bottom plate, the bottom end of the other limiting column is fixed on the bottom plate, and the clamping bottom plate is screwed out through the gap.

所述夹持立板的上端固定设置有限位板,所述限位板上通过螺纹连接设置有限位螺柱一,所述限位螺柱一的下端固定设置有对扁铁和角钢进行限位的限位盘。The upper end of the clamping vertical plate is fixedly provided with a limit plate, the limit plate is provided with a limit stud 1 through threaded connection, and the lower end of the limit stud 1 is fixed with a limit for the flat iron and the angle steel. the limit plate.

所述夹具包括矩形块,所述矩形块的上方一侧设置有高挡板,另一侧设置有低挡板,所述矩形块靠近所述低挡板的一侧对称设置铰接板,两个所述铰接板之间铰接设置有夹板,所述夹板的上端高于所述低挡板,两个所述铰接板的下部设置有固定板,所述固定板与所述夹板之间通过弹簧连接,所述弹簧设置在所述夹板的下部,所述矩形块的下部开通有螺纹孔,所述螺纹孔内设置有限位螺柱二,所述限位螺柱二的内端可顶在所述夹板上,所述固定板设置在所述外接板上。The fixture includes a rectangular block, a high baffle is arranged on one side of the upper side of the rectangular block, and a low baffle is arranged on the other side, and a hinge plate is symmetrically arranged on one side of the rectangular block close to the low baffle, and two A splint is hingedly arranged between the hinge plates, the upper end of the splint is higher than the low baffle plate, the lower part of the two hinge plates is provided with a fixed plate, and the fixed plate and the splint are connected by a spring , the spring is arranged at the lower part of the splint, the lower part of the rectangular block is provided with a threaded hole, a second limit stud is arranged in the threaded hole, and the inner end of the second limit stud can be pressed against the On the splint, the fixing plate is arranged on the external plate.

所述固定板上设置有矩形口,所述外接板上设置有矩形立柱,所述矩形口滑动设置在所述矩形立柱上,所述矩形口的侧壁通过螺纹连接设置有限位螺柱三,所述固定板的外侧设置有连接板,所述连接板上通过螺纹连接设置有连接螺杆,所述横向柱的两端均设置有螺纹盲孔,所述连接螺杆穿过所述连接板可设置在所述螺纹盲孔内。The fixing plate is provided with a rectangular opening, the external plate is provided with a rectangular column, the rectangular opening is slidably arranged on the rectangular column, and the side wall of the rectangular opening is provided with a limit stud 3 through threaded connection, The outer side of the fixing plate is provided with a connecting plate, the connecting plate is provided with a connecting screw through screw connection, both ends of the transverse column are provided with threaded blind holes, and the connecting screw can be set through the connecting plate in the threaded blind hole.

所述夹持底板以及所述外接板的下方固定设置有若干个立柱。Several uprights are fixedly arranged below the clamping bottom plate and the external plate.

与所述底板之间具有间隔的所述限位柱上开通有底端敞开的条形口,所述条形口的侧壁上开通有若干个调节孔,所述条形口内设置有调节块,所述调节块通过螺栓设置在所述限位柱上,所述调节块的内壁与所述限位柱的内壁齐平。A bar-shaped opening with an open bottom end is opened on the limiting column with an interval from the bottom plate, a number of adjustment holes are opened on the side wall of the bar-shaped opening, and an adjustment block is arranged in the bar-shaped opening. , the adjusting block is arranged on the limiting column through bolts, and the inner wall of the adjusting block is flush with the inner wall of the limiting column.

任一所述限位柱与所述底板之间具有间隔,另一所述限位柱的底端固定在所述底板,所述夹持底板通过所述间隔旋出;旋出的目的在于方便后期进行焊接。There is an interval between any one of the limiting columns and the bottom plate, the bottom end of the other limiting column is fixed on the bottom plate, and the clamping bottom plate is unscrewed through the interval; the purpose of unscrewing is to facilitate Welding at a later stage.

所述夹持立板的上端固定设置有限位板,所述限位板上通过螺纹连接设置有限位螺柱一,所述限位螺柱一的下端固定设置有对扁铁和角钢进行限位的限位盘;The upper end of the clamping vertical plate is fixedly provided with a limit plate, the limit plate is provided with a limit stud 1 through threaded connection, and the lower end of the limit stud 1 is fixed with a limit for the flat iron and the angle steel. the limit plate;

所述夹持底板以及所述外接板的下方固定设置有若干个立柱;A number of uprights are fixedly arranged below the clamping bottom plate and the external plate;

与所述底板之间具有间隔的所述限位柱上开通有底端敞开的条形口,所述条形口的侧壁上开通有若干个调节孔,所述条形口内设置有调节块,所述调节块通过螺栓设置在所述限位柱上,所述调节块的内壁与所述限位主的内壁齐平。这样可以根据角钢旋进的深度,调节所述底板与限位柱之间的间隔,这样可以控制所述夹持结构旋出的位置。A bar-shaped opening with an open bottom end is opened on the limiting column with an interval from the bottom plate, a number of adjustment holes are opened on the side wall of the bar-shaped opening, and an adjustment block is arranged in the bar-shaped opening. , the adjusting block is arranged on the limiting column through bolts, and the inner wall of the adjusting block is flush with the inner wall of the limiting main. In this way, the interval between the bottom plate and the limiting column can be adjusted according to the screw-in depth of the angle steel, so that the screw-out position of the clamping structure can be controlled.

所述的避雷地网安装装置的地网安装方法,具体步骤包括:The method for installing the ground grid of the lightning protection ground grid installation device, the specific steps include:

(1)初始位置,所述夹持结构位于所述螺杆一的上部,将所述立柱插入地面以下进行定位,将角钢一边的钢板设置在两个所述夹持板之间,转动所述螺杆二,所述推板沿着所述凹槽移动并推动所述内套杆和外套杆移动,所述内套杆沿着所述外套杆移动,两个所述倾斜杆相对运动,两个所述夹持板靠近直到将角钢夹紧,所述夹持板夹持在角钢的上部;因为需要预先挖至沟槽,沟槽内的土湿度较大,角钢比较好插入,为了方便角钢的旋进地面,可以将角钢的下端切割成锥形。另外,如果沟槽的土还是很硬,最好对预先进行松土。(1) In the initial position, the clamping structure is located on the upper part of the screw one, insert the column below the ground for positioning, set the steel plate on one side of the angle steel between the two clamping plates, and rotate the screw Second, the push plate moves along the groove and pushes the inner sleeve rod and the outer sleeve rod to move, the inner sleeve rod moves along the outer sleeve rod, the two inclined rods move relative to each other, and the two The clamping plate is close until the angle steel is clamped, and the clamping plate is clamped on the upper part of the angle steel; because it needs to be dug to the groove in advance, the soil humidity in the groove is relatively large, and the angle steel is better inserted, in order to facilitate the rotation of the angle steel. Into the ground, the lower end of the angle steel can be cut into a cone. In addition, if the soil in the trench is still very hard, it is best to loosen the soil beforehand.

(2)转动所述限位螺柱一,直到所述限位盘顶在所述角钢上;(2) Rotate the limit stud 1 until the limit plate rests on the angle steel;

(3)通过所述驱动装置带动所述螺杆一转动,所述夹持结构沿着两个所述限位柱下移,带动角钢下移并插入地面,直到预定位置;(3) When the screw rod is driven to rotate by the driving device, the clamping structure moves down along the two limit posts, and drives the angle steel to move down and insert into the ground until it reaches a predetermined position;

(4)将扁钢与角钢的另一边的外侧连接,并通过调节所述夹具的位置,通过转动所述限位螺柱二,使所述限位螺柱二的内端顶在所述夹板上,所述夹板转动对扁钢进行夹紧;(4) Connect the flat steel to the outside of the other side of the angle steel, and adjust the position of the clamp and rotate the second limit stud so that the inner end of the second limit stud is on the splint. On, the splint rotates to clamp the flat steel;

(5)反转所述螺杆二,手动将所述内套杆和外套杆复位,使两个所述夹持板脱离所述角钢,调节所述调节块的位置,使所述夹持结构旋出所述限位柱;(5) Reverse the second screw, manually reset the inner sleeve rod and the outer sleeve rod, release the two clamping plates from the angle steel, adjust the position of the adjustment block, and make the clamping structure rotate. out the limit post;

(6)通过焊接将所述扁钢焊接在所述角钢上;焊接时为了保证连接的稳固,还需要直角扁钢将角钢的另一边与扁钢焊接在一起。(6) Weld the flat steel on the angle steel by welding; in order to ensure the stability of the connection during welding, a right-angle flat steel is also required to weld the other side of the angle steel with the flat steel.

(7)将所述夹持结构复位,使所述夹持板再次夹住角钢,通过调节所述调节块进行限位,并通过所述连接螺杆将所述夹持结构和所述夹具连接;(7) Reset the clamping structure, make the clamping plate clamp the angle steel again, limit the position by adjusting the adjustment block, and connect the clamping structure and the clamp through the connecting screw;

(8)转动所述螺杆一,对角钢和扁钢的位置进行微调。进行微调时,可以多个装置同时进行。(8) Turn the screw one to fine-tune the position of the angle steel and the flat steel. When fine-tuning is performed, multiple devices can be performed at the same time.

与现有技术相比,本发明的有益效果是:可以辅助人工对地网的角钢和扁铁进行安装,节省人力;通过电机将角钢插入地面并且还能控制插入的深度,同时设置了夹持结构以及限位圆盘对角钢进行双重限制,方便角钢的插入;夹具可以与夹持结构连接同时升降方便对角钢和扁钢的位置进行微调。Compared with the prior art, the present invention has the beneficial effects that: it can assist in manually installing the angle steel and flat iron of the ground net, saving manpower; the angle steel can be inserted into the ground through the motor and the depth of the insertion can be controlled, and a clamping device is provided at the same time. The structure and the limit disc double limit the angle steel, which is convenient for the insertion of the angle steel; the clamp can be connected with the clamping structure and lift at the same time to facilitate the fine-tuning of the position of the angle steel and the flat steel.

附图说明Description of drawings

图1为本发明的整体结构示意图。FIG. 1 is a schematic diagram of the overall structure of the present invention.

图2为与图1角度不同的结构示意图。FIG. 2 is a schematic diagram of a structure with an angle different from that of FIG. 1 .

图3为图2中A处的局部放大图。FIG. 3 is a partial enlarged view of A in FIG. 2 .

图4为夹持底板部分相关件的结构示意图。FIG. 4 is a schematic view of the structure of the relevant parts of the clamping bottom plate.

图5为矩形块的部分相关件的结构示意图。FIG. 5 is a schematic structural diagram of some related parts of the rectangular block.

图6为机架的结构示意图。FIG. 6 is a schematic diagram of the structure of the rack.

图7为使用状态参考图。FIG. 7 is a reference diagram of the use state.

其中,附图标记为:1、机架;2、升降机构;3、夹持结构;4、夹具;5、连接螺杆;6、角钢;7、扁钢;101、底板;102、立板;103、水平板;104、外接板;105、限位柱;106、条形口;107、调节孔;108、调节块;109、立柱;110、矩形立柱;201、螺杆一;202、电机;301、夹持底板;302、横向柱;303、斜杆一;304、外套杆;305、夹持板;306、夹持立板;307、推板;308、螺杆二;309、凹槽;310、限位板;311、限位螺柱一;312、限位盘;313、内套杆;314、螺纹盲孔;315、斜杆二;401、矩形块;402、低挡板;403、高挡板;404、铰接板;405、夹板;406、固定板;407、弹簧;408、连接板;409、限位螺柱三;410、限位螺柱二;411、矩形口。Wherein, the reference signs are: 1, frame; 2, lifting mechanism; 3, clamping structure; 4, clamp; 5, connecting screw; 6, angle steel; 7, flat steel; 101, bottom plate; 102, vertical plate; 103, horizontal plate; 104, external plate; 105, limit column; 106, bar mouth; 107, adjustment hole; 108, adjustment block; 109, column; 110, rectangular column; 201, screw one; 202, motor; 301, clamping bottom plate; 302, horizontal column; 303, inclined rod one; 304, outer rod; 305, clamping plate; 306, clamping vertical plate; 307, push plate; 308, screw two; 309, groove; 310, limit plate; 311, limit stud one; 312, limit plate; 313, inner sleeve rod; 314, threaded blind hole; 315, inclined rod two; 401, rectangular block; 402, low baffle; 403 404, hinge plate; 405, splint; 406, fixed plate; 407, spring; 408, connecting plate; 409, limit stud three; 410, limit stud two; 411, rectangular mouth.

具体实施方式Detailed ways

为能清楚说明本方案的技术特点,下面通过具体实施方式,对本方案进行阐述。In order to clearly illustrate the technical features of the solution, the solution will be described below through specific implementations.

参见图1-图7,一种避雷地网安装装置,其特征在于,包括机架1,机架1包括底板101,底板101的一端上方固定设置有立板102,底板101的另一端两侧设置有外接板104,立板102的上方设置有水平板103,底板101和水平板103之间设置有升降机构2,升降机构2上设置有上下移动的夹持结构3,两个外接板104上均设置有夹具4,两个外接板104之间具有间距,方便后期角钢插入土中。1 to 7, a lightning protection ground grid installation device is characterized in that it includes a rack 1, the rack 1 includes a bottom plate 101, a vertical plate 102 is fixed above one end of the bottom plate 101, and the other end of the bottom plate 101 is on both sides. An external plate 104 is arranged, a horizontal plate 103 is arranged above the vertical plate 102, a lifting mechanism 2 is arranged between the bottom plate 101 and the horizontal plate 103, the lifting mechanism 2 is provided with a clamping structure 3 that moves up and down, and two external plates 104 Clamps 4 are provided on both, and there is a space between the two external plates 104, which is convenient for the angle steel to be inserted into the soil in the later stage.

升降机构2包括转动设置在底板101和水平板103之间的螺杆一201,螺杆一201的上端伸出水平板103与驱动装置连接;驱动装置为带有减速器的电机202。The lifting mechanism 2 includes a screw rod 1 201 rotatably arranged between the bottom plate 101 and the horizontal plate 103. The upper end of the screw rod one 201 extends out of the horizontal plate 103 and is connected to a driving device; the driving device is a motor 202 with a reducer.

夹持结构3包括夹持底板301,夹持底板301的一端上方固定设置有横向柱302,横向柱302上插接设置有斜杆一303和斜杆二315,斜杆一303和斜杆二315对称设置,斜杆一303上位于横向柱302内侧的一端固定设置有内套杆313,斜杆二315上位于横向柱302内侧的一端固定设置有外套杆304,内套杆313和外套杆304水平设置且内套杆313插接在外套杆304内,倾斜杆一303和倾斜杆二315的另一端内侧均固定设置有夹持板305,横向柱302上设置夹持立板306,夹持立板306上转动设置有螺杆二308,螺杆二308上通过螺纹连接设置有推板307,夹持底板301上设置有对推板307进行限位的凹槽309,内套杆313和外套杆304位于推板307和夹持立板306之间;The clamping structure 3 includes a clamping bottom plate 301 , a transverse column 302 is fixed above one end of the clamping bottom plate 301 , and a diagonal rod 303 and a diagonal rod 2 315 are inserted on the transverse column 302 , and the diagonal rod 1 303 and the diagonal rod 2 are inserted. 315 are symmetrically arranged, one end of the oblique rod 303 on the inner side of the transverse column 302 is fixedly provided with an inner sleeve rod 313, and one end of the inclined rod 315 on the inner side of the transverse column 302 is fixedly provided with an outer sleeve rod 304, the inner sleeve rod 313 and the outer sleeve rod 304 is horizontally arranged and the inner sleeve rod 313 is inserted into the outer sleeve rod 304, the inner side of the other end of the inclined rod 1 303 and the inclined rod 2 315 are fixedly provided with a clamping plate 305, and a clamping vertical plate 306 is set on the transverse column 302, and the clamping plate 306 is installed on the horizontal column 302. The second screw 308 is rotatably arranged on the holding plate 306, and the second screw 308 is provided with a push plate 307 through threaded connection. The rod 304 is located between the push plate 307 and the clamping vertical plate 306;

夹持底板301通过螺纹连接设置在螺杆一201上,水平板103的下方且位于螺杆一201的两侧固定设置有夹持底板301的限位柱105。The clamping bottom plate 301 is provided on the screw one 201 by screw connection, and the limit posts 105 for clamping the bottom plate 301 are fixedly arranged below the horizontal plate 103 and on both sides of the screw one 201 .

任意限位柱105与底板101之间具有间隔,另一限位柱的底端固定在底板1,夹持底板301通过间隔旋出。旋出的目的在于方便后期进行焊接。There is a space between any limit post 105 and the bottom plate 101 , the bottom end of another limit post is fixed on the bottom plate 1 , and the clamping bottom plate 301 is screwed out through the space. The purpose of unscrewing is to facilitate later welding.

夹持立板306的上固定设置有限位板310,限位板310上通过螺纹连接设置有限位螺柱一311,限位螺柱一311的下端固定设置有对扁铁和角钢进行限位的限位盘312。A limiting plate 310 is fixedly arranged on the upper portion of the clamping vertical plate 306, a limiting stud 311 is arranged on the limiting plate 310 through a screw connection, and the lower end of the limiting stud 1 311 is fixedly provided with a limiter for limiting the flat iron and the angle steel. Limit plate 312 .

夹具4包括矩形块401,矩形块401的上方一侧设置有高挡板403,另一侧设置有低挡板402,矩形块401靠近低挡板402的一侧对称设置铰接板404,两个铰接板404之间铰接设置有夹板405,夹板405的上端高于低挡板402,两个铰接板404的下部设置有固定板406,固定板406与夹板405之间通过弹簧407连接,弹簧407设置在夹板405的下部,矩形块401的下部开通有螺纹孔,螺纹孔内设置有限位螺柱二410,限位螺柱二410的内端可顶在夹板405上,固定板406设置在外接板104上。The fixture 4 includes a rectangular block 401, a high baffle 403 is arranged on one side of the upper side of the rectangular block 401, and a low baffle 402 is arranged on the other side, and a hinge plate 404 is symmetrically arranged on the side of the rectangular block 401 close to the low baffle 402. A splint 405 is hinged between the hinge plates 404. The upper end of the splint 405 is higher than the lower baffle 402. The lower part of the two hinge plates 404 is provided with a fixed plate 406. The fixed plate 406 and the splint 405 are connected by a spring 407. The spring 407 It is arranged at the lower part of the splint 405, the lower part of the rectangular block 401 is provided with a threaded hole, and the second limit stud 410 is arranged in the threaded hole. on board 104 .

固定板406上设置有矩形口411,外接板104上设置有矩形立柱110,矩形口411滑动设置在矩形立柱110上,矩形口411的侧壁通过螺纹连接设置有限位螺柱三409,固定板406的外侧设置有连接板408,连接板408上通过螺纹连接设置有连接螺杆5,横向柱302的两端均设置有螺纹盲孔314,连接螺杆5穿过连接板408可设置在螺纹盲孔314内。The fixing plate 406 is provided with a rectangular opening 411, the external plate 104 is provided with a rectangular column 110, the rectangular opening 411 is slidably arranged on the rectangular column 110, and the side wall of the rectangular opening 411 is threadedly connected with a limiting stud 3 409, the fixing plate The outer side of the 406 is provided with a connecting plate 408, the connecting plate 408 is provided with a connecting screw 5 through a threaded connection, and both ends of the transverse column 302 are provided with threaded blind holes 314. within 314.

夹持底板301以及外接板104的下方固定设置有若干个立柱109。A number of uprights 109 are fixedly arranged below the clamping bottom plate 301 and the external plate 104 .

与底板101之间具有间隔的限位柱105上开通有底端敞开的条形口106,条形口106的侧壁上开通有若干个调节孔107,条形口106内设置有调节块108,调节块108通过螺栓设置在限位柱105上,调节块108的内壁与限位柱105的内壁齐平。这样可以根据角钢旋进的深度,调节所述底板与限位柱之间的间隔,这样可以控制所述夹持结构旋出的位置。A bar-shaped opening 106 with an open bottom end is opened on the limiting column 105 with an interval from the bottom plate 101 , a plurality of adjusting holes 107 are opened on the side wall of the bar-shaped opening 106 , and an adjusting block 108 is arranged in the bar-shaped opening 106 , the adjusting block 108 is arranged on the limiting column 105 through bolts, and the inner wall of the adjusting block 108 is flush with the inner wall of the limiting column 105 . In this way, the interval between the bottom plate and the limiting column can be adjusted according to the screw-in depth of the angle steel, so that the screw-out position of the clamping structure can be controlled.

所述的避雷地网安装装置的地网安装方法,具体步骤包括:The method for installing the ground grid of the lightning protection ground grid installation device, the specific steps include:

(1)初始位置,夹持结构3位于螺杆一201的上部,将立柱109插入地面以下进行定位,将角钢6一边的钢板设置在两个夹持板305之间,转动螺杆二308,推板307沿着凹槽309移动并推动内套杆313和外套杆304移动,内套杆313沿着外套杆304移动,两个倾斜杆相对运动,两个夹持板305靠近直到将角钢6夹紧,夹持板305夹持在角钢6的上部;因为需要预先挖至沟槽,沟槽内的土湿度较大,角钢6比较好插入,为了方便角钢6的旋进地面,可以将角钢6的下端切割成锥形。另外,如果沟槽的土还是很硬,最好对预先进行松土。(1) In the initial position, the clamping structure 3 is located on the upper part of the first screw 201, insert the column 109 below the ground for positioning, set the steel plate on one side of the angle steel 6 between the two clamping plates 305, rotate the second screw 308, push the plate 307 moves along the groove 309 and pushes the inner sleeve rod 313 and the outer sleeve rod 304 to move, the inner sleeve rod 313 moves along the outer sleeve rod 304, the two inclined rods move relative to each other, and the two clamping plates 305 approach until the angle steel 6 is clamped , the clamping plate 305 is clamped on the upper part of the angle steel 6; because it needs to be dug to the groove in advance, the soil humidity in the groove is relatively large, and the angle steel 6 is better inserted. In order to facilitate the screwing of the angle steel 6 into the ground, the angle steel 6 can be The lower end is cut into a tapered shape. In addition, if the soil in the trench is still very hard, it is best to loosen the soil beforehand.

(2)转动限位螺柱一311,直到限位盘312顶在角钢6上;(2) Rotate the limit stud 1 311 until the limit plate 312 rests on the angle steel 6;

(3)通过电机202带动螺杆一201转动,夹持结构3沿着两个限位柱105下移,带动角钢6下移并插入地面,直到预定位置;(3) The screw 1 201 is driven to rotate by the motor 202, the clamping structure 3 moves down along the two limit posts 105, and drives the angle steel 6 to move down and insert into the ground until the predetermined position;

(4)将扁钢7与角钢7的另一边的外侧连接,并通过调节夹具4的位置,通过转动限位螺柱二410,使限位螺柱二410的内端顶在夹板405上,夹板405转动对扁钢7进行夹紧;(4) Connect the flat steel 7 to the outside of the other side of the angle steel 7, and adjust the position of the clamp 4 and rotate the second limit stud 410 to make the inner end of the second limit stud 410 abut on the clamp plate 405, The splint 405 rotates to clamp the flat steel 7;

(5)反转螺杆二308,手动将内套杆313和外套杆304复位,使两个夹持板305脱离角钢6,调节调节块108的位置,使夹持结构3旋出限位柱105;(5) Reverse the second screw 308, manually reset the inner sleeve rod 313 and the outer sleeve rod 304, so that the two clamping plates 305 are separated from the angle steel 6, adjust the position of the adjustment block 108, and rotate the clamping structure 3 out of the limit post 105. ;

(6)通过焊接将扁钢7焊接在角钢6上;焊接时为了保证连接的稳固,还需要直角扁钢将角钢6的另一边与扁钢焊接在一起。(6) Weld the flat steel 7 on the angle steel 6 by welding; in order to ensure the stability of the connection during welding, a right-angle flat steel is also required to weld the other side of the angle steel 6 with the flat steel.

(7)将夹持结构3复位,使夹持板305再次夹住角钢6,通过调节调节块108进行限位,并通过连接螺杆5将夹持结构3和夹具4连接;(7) Reset the clamping structure 3 so that the clamping plate 305 clamps the angle steel 6 again, limit the position by adjusting the adjusting block 108 , and connect the clamping structure 3 and the clamp 4 through the connecting screw 5;

(8)转动螺杆一201,对角钢6和扁钢7的位置进行微调。进行微调时,可以多个装置同时进行。(8) Turn the screw 1 201 to fine-tune the positions of the angle steel 6 and the flat steel 7. When fine-tuning is performed, multiple devices can be performed at the same time.

本发明未经描述的技术特征可以通过或采用现有技术实现,在此不再赘述,当然,上述说明并非是对本发明的限制,本发明也并不仅限于上述举例,本技术领域的普通技术人员在本发明的实质范围内所做出的变化、改型、添加或替换,也应属于本发明的保护范围。The undescribed technical features of the present invention can be realized by or using the existing technology, and will not be repeated here. Of course, the above description is not a limitation of the present invention, and the present invention is not limited to the above examples. Those skilled in the art Changes, modifications, additions or substitutions made within the essential scope of the present invention shall also belong to the protection scope of the present invention.

Claims (10)

1.一种避雷地网安装装置,其特征在于,包括机架,所述机架包括底板,所述底板的一端上方固定设置有立板,所述底板的另一端两侧设置有外接板,所述立板的上方设置有水平板,所述底板和所述水平板之间设置有升降机构,所述升降机构上设置有上下移动的夹持结构,两个所述外接板上均设置有夹具,两个所述外接板之间具有间距。1. a lightning arrester ground net installation device, is characterized in that, comprises rack, and described rack comprises bottom plate, and one end of described bottom plate is fixedly provided with vertical plate, and the other end of described bottom plate is provided with external plate on both sides, A horizontal plate is arranged above the vertical plate, a lifting mechanism is arranged between the bottom plate and the horizontal plate, a clamping structure that moves up and down is arranged on the lifting mechanism, and two external plates are provided with a lifting mechanism. a clamp, and there is a space between the two external boards. 2.根据权利要求1所述的避雷地网安装装置,其特征在于,所述升降机构包括转动设置在所述底板和所述水平板之间的螺杆一,所述螺杆一的上端伸出所述水平板与驱动装置连接;2 . The lightning protection ground net installation device according to claim 1 , wherein the lifting mechanism comprises a screw rod 1 which is rotatably arranged between the bottom plate and the horizontal plate, and the upper end of the screw rod 1 protrudes out of the space. 3 . The horizontal plate is connected with the driving device; 所述夹持结构包括夹持底板,所述夹持底板的一端上方固定设置有横向柱,所述横向柱上插接设置有斜杆一和斜杆二,所述斜杆一和斜杆二对称设置,所述斜杆一上位于所述横向柱内侧的一端固定设置有内套杆,所述斜杆二上位于所述横向柱内侧的一端固定设置有外套杆,所述内套杆和所述外套杆水平设置且所述内套杆插接在所述外套杆内,所述倾斜杆一和倾斜杆二的另一端内侧均固定设置有夹持板,所述横向柱上设置夹持立板,所述夹持立板上转动设置有螺杆二,所述螺杆二上通过螺纹连接设置有推板,所述夹持底板上设置有对所述推板进行限位的凹槽,所述内套杆和所述外套杆位于所述推板和所述夹持立板之间;The clamping structure includes a clamping bottom plate, a transverse column is fixedly arranged above one end of the clamping bottom plate, and a diagonal rod 1 and a diagonal rod 2 are inserted on the transverse column, and the diagonal rod 1 and the diagonal rod 2 are inserted. Symmetrically arranged, an inner sleeve rod is fixedly arranged at one end of the first inclined rod on the inner side of the transverse column, and an outer sleeve rod is fixedly arranged at the end of the second inclined rod at the inner side of the transverse column, and the inner sleeve rod and The outer sleeve rod is arranged horizontally and the inner sleeve rod is inserted into the outer sleeve rod, the inner side of the other end of the inclined rod 1 and the inclined rod 2 are fixedly provided with a clamping plate, and a clamping plate is arranged on the transverse column. The vertical plate, the second screw is rotatably arranged on the clamping vertical plate, the second screw is provided with a push plate through screw connection, and the clamping bottom plate is provided with a groove for limiting the position of the push plate, so The inner sleeve rod and the outer sleeve rod are located between the push plate and the clamping vertical plate; 所述夹持底板通过螺纹连接设置在螺杆一上,所述水平板的下方且位于所述螺杆一的两侧固定设置有所述夹持底板的限位柱。The clamping bottom plate is provided on the first screw rod through screw connection, and the limit posts of the clamping bottom plate are fixedly arranged below the horizontal plate and on both sides of the screw rod one. 3.根据权利要求2所述的避雷地网安装装置,其特征在于,任一所述限位柱与所述底板之间具有间隔,另一所述限位柱的底端固定在所述底板,所述夹持底板通过所述间隔旋出。3 . The lightning protection ground net installation device according to claim 2 , wherein there is a space between any one of the limiting posts and the bottom plate, and the bottom end of the other limiting post is fixed on the bottom plate. 4 . , the clamping bottom plate is screwed out through the interval. 4.根据权利要求2所述的避雷地网安装装置,其特征在于,所述夹持立板的上端固定设置有限位板,所述限位板上通过螺纹连接设置有限位螺柱一,所述限位螺柱一的下端固定设置有对扁铁和角钢进行限位的限位盘。4. The lightning protection ground net installation device according to claim 2, wherein a limit plate is fixedly arranged on the upper end of the clamping vertical plate, and a limit stud is set on the limit plate through screw connection, so The lower end of the first limiting stud is fixedly provided with a limiting disk for limiting the position of the flat iron and the angle steel. 5.根据权利要求2所述的避雷地网安装装置,其特征在于,所述夹具包括矩形块,所述矩形块的上方一侧设置有高挡板,另一侧设置有低挡板,所述矩形块靠近所述低挡板的一侧对称设置铰接板,两个所述铰接板之间铰接设置有夹板,所述夹板的上端高于所述低挡板,两个所述铰接板的下部设置有固定板,所述固定板与所述夹板之间通过弹簧连接,所述弹簧设置在所述夹板的下部,所述矩形块的下部开通有螺纹孔,所述螺纹孔内设置有限位螺柱二,所述限位螺柱二的内端可顶在所述夹板上,所述固定板设置在所述外接板上。5. The lightning protection ground net installation device according to claim 2, wherein the clamp comprises a rectangular block, a high baffle is arranged on one side of the upper side of the rectangular block, and a low baffle is arranged on the other side, so that the A hinge plate is symmetrically arranged on one side of the rectangular block close to the low baffle plate, a splint is hinged between the two hinge plates, the upper end of the splint plate is higher than the low baffle plate, and the two hinge plates The lower part is provided with a fixing plate, the fixing plate and the clamping plate are connected by a spring, the spring is arranged at the lower part of the clamping plate, the lower part of the rectangular block is provided with a threaded hole, and the threaded hole is provided with a limit The second stud, the inner end of the second limiting stud can be pressed against the clamping plate, and the fixing plate is arranged on the external plate. 6.根据权利要求5所述的避雷地网安装装置,其特征在于,所述固定板上设置有矩形口,所述外接板上设置有矩形立柱,所述矩形口滑动设置在所述矩形立柱上,所述矩形口的侧壁通过螺纹连接设置有限位螺柱三,所述固定板的外侧设置有连接板,所述连接板上通过螺纹连接设置有连接螺杆,所述横向柱的两端均设置有螺纹盲孔,所述连接螺杆穿过所述连接板可设置在所述螺纹盲孔内。6 . The lightning protection ground net installation device according to claim 5 , wherein a rectangular opening is provided on the fixing plate, a rectangular column is provided on the external plate, and the rectangular opening is slidably arranged on the rectangular column. 7 . On the upper side, the side wall of the rectangular opening is provided with three limiting studs through threaded connection, the outer side of the fixing plate is provided with a connecting plate, and the connecting plate is provided with a connecting screw through threaded connection, and the two ends of the transverse column are Both are provided with threaded blind holes, and the connecting screw can be disposed in the threaded blind holes through the connecting plate. 7.根据权利要求2所述的避雷地网安装装置,其特征在于,所述夹持底板以及所述外接板的下方固定设置有若干个立柱。7 . The lightning protection ground net installation device according to claim 2 , wherein a plurality of uprights are fixedly arranged below the clamping bottom plate and the external plate. 8 . 8.根据权利要求3所述的避雷地网安装装置,其特征在于,与所述底板之间具有间隔的所述限位柱上开通有底端敞开的条形口,所述条形口的侧壁上开通有若干个调节孔,所述条形口内设置有调节块,所述调节块通过螺栓设置在所述限位柱上,所述调节块的内壁与所述限位柱的内壁齐平。8 . The lightning protection ground net installation device according to claim 3 , wherein a bar-shaped opening with an open bottom end is opened on the limiting column with a space between the bottom plate and the bottom-end of the bar-shaped opening. A number of adjustment holes are opened on the side wall, an adjustment block is arranged in the bar-shaped mouth, and the adjustment block is arranged on the limit column through bolts, and the inner wall of the adjustment block is aligned with the inner wall of the limit column. flat. 9.根据权利要求6所述的避雷地网安装装置,其特征在于,任一所述限位柱与所述底板之间具有间隔,另一所述限位柱的底端固定在所述底板,所述夹持底板通过所述间隔旋出;9 . The lightning protection ground net installation device according to claim 6 , wherein there is a space between any one of the limiting posts and the bottom plate, and the bottom end of the other limiting post is fixed on the bottom plate. 10 . , the clamping bottom plate is screwed out through the interval; 所述夹持立板的上端固定设置有限位板,所述限位板上通过螺纹连接设置有限位螺柱一,所述限位螺柱一的下端固定设置有对扁铁和角钢进行限位的限位盘;The upper end of the clamping vertical plate is fixedly provided with a limit plate, the limit plate is provided with a limit stud 1 through threaded connection, and the lower end of the limit stud 1 is fixed with a limit for the flat iron and the angle steel. the limit plate; 所述夹持底板以及所述外接板的下方固定设置有若干个立柱;A number of uprights are fixedly arranged below the clamping bottom plate and the external plate; 与所述底板之间具有间隔的所述限位柱上开通有底端敞开的条形口,所述条形口的侧壁上开通有若干个调节孔,所述条形口内设置有调节块,所述调节块通过螺栓设置在所述限位柱上,所述调节块的内壁与所述限位主的内壁齐平。A bar-shaped opening with an open bottom end is opened on the limiting column with an interval from the bottom plate, a number of adjustment holes are opened on the side wall of the bar-shaped opening, and an adjustment block is arranged in the bar-shaped opening. , the adjusting block is arranged on the limiting column through bolts, and the inner wall of the adjusting block is flush with the inner wall of the limiting main. 10.一种基于权利要求9所述的避雷地网安装装置的地网安装方法,具体步骤包括:10. A ground net installation method based on the lightning protection ground net installation device according to claim 9, the concrete steps comprising: (1)初始位置,所述夹持结构位于所述螺杆一的上部,将所述立柱插入地面以下进行定位,将角钢一边的钢板设置在两个所述夹持板之间,转动所述螺杆二,所述推板沿着所述凹槽移动并推动所述内套杆和外套杆移动,所述内套杆沿着所述外套杆移动,两个所述倾斜杆相对运动,两个所述夹持板靠近直到将角钢夹紧,所述夹持板夹持在角钢的上部;(1) In the initial position, the clamping structure is located on the upper part of the screw one, insert the column below the ground for positioning, set the steel plate on one side of the angle steel between the two clamping plates, and rotate the screw Second, the push plate moves along the groove and pushes the inner sleeve rod and the outer sleeve rod to move, the inner sleeve rod moves along the outer sleeve rod, the two inclined rods move relative to each other, and the two The clamping plate is approached until the angle steel is clamped, and the clamping plate is clamped on the upper part of the angle steel; (2)转动所述限位螺柱一,直到所述限位盘顶在所述角钢上;(2) Rotate the limit stud 1 until the limit plate rests on the angle steel; (3)通过所述驱动装置带动所述螺杆一转动,所述夹持结构沿着两个所述限位柱下移,带动角钢下移并插入地面,直到预定位置;(3) When the screw rod is driven to rotate by the driving device, the clamping structure moves down along the two limit posts, and drives the angle steel to move down and insert into the ground until it reaches a predetermined position; (4)将扁钢与角钢的另一边的外侧连接,并通过调节所述夹具的位置,通过转动所述限位螺柱二,使所述限位螺柱二的内端顶在所述夹板上,所述夹板转动对扁钢进行夹紧;(4) Connect the flat steel to the outside of the other side of the angle steel, and adjust the position of the clamp and rotate the second limit stud so that the inner end of the second limit stud is on the splint. On, the splint rotates to clamp the flat steel; (5)反转所述螺杆二,手动将所述内套杆和外套杆复位,使两个所述夹持板脱离所述角钢,调节所述调节块的位置,使所述夹持结构旋出所述限位柱;(5) Reverse the second screw, manually reset the inner sleeve rod and the outer sleeve rod, release the two clamping plates from the angle steel, adjust the position of the adjustment block, and make the clamping structure rotate. out the limit post; (6)通过焊接将所述扁钢焊接在所述角钢上;(6) Welding the flat steel on the angle steel by welding; (7)将所述夹持结构复位,使所述夹持板再次夹住角钢,通过调节所述调节块进行限位,并通过所述连接螺杆将所述夹持结构和所述夹具连接;(7) Reset the clamping structure, make the clamping plate clamp the angle steel again, limit the position by adjusting the adjustment block, and connect the clamping structure and the clamp through the connecting screw; (8)转动所述螺杆一,对角钢和扁钢的位置进行微调。(8) Turn the screw one to fine-tune the position of the angle steel and the flat steel.
CN202010232794.XA 2020-03-28 2020-03-28 A lightning protection ground network installation device Active CN111230349B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010232794.XA CN111230349B (en) 2020-03-28 2020-03-28 A lightning protection ground network installation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010232794.XA CN111230349B (en) 2020-03-28 2020-03-28 A lightning protection ground network installation device

Publications (2)

Publication Number Publication Date
CN111230349A true CN111230349A (en) 2020-06-05
CN111230349B CN111230349B (en) 2024-12-13

Family

ID=70870560

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010232794.XA Active CN111230349B (en) 2020-03-28 2020-03-28 A lightning protection ground network installation device

Country Status (1)

Country Link
CN (1) CN111230349B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114243411A (en) * 2021-12-28 2022-03-25 山东中恒建设集团有限公司 Device is used in construction of building ground connection

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106271353A (en) * 2015-05-29 2017-01-04 安顺市晶英科技研发有限责任公司 A kind of pipe welding clamp being applicable to T-shaped structure
CN206614284U (en) * 2017-04-06 2017-11-07 南京农业大学 A kind of wedge clamping device
CN107717310A (en) * 2017-11-20 2018-02-23 佛山迅奥捷自动化科技有限公司 Height adjustable holding fixed mechanism is used in a kind of metal plates combine welding
CN108321654A (en) * 2018-03-06 2018-07-24 李猛 A kind of power ground system fitting machine
CN108526790A (en) * 2018-05-22 2018-09-14 常州机电职业技术学院 Universal clamp for T-shaped structural member
CN108808424A (en) * 2018-05-25 2018-11-13 北京兴天通电讯科技有限公司 Earthing pole installs equipment
CN208117102U (en) * 2018-02-08 2018-11-20 青岛金泰瑞金属制品有限公司 T-shaped steel-pipe welding tooling
CN209256196U (en) * 2018-12-13 2019-08-16 天津市津菱机电工程有限公司 A kind of positioning clamping device of elevator parts welding
CN211966369U (en) * 2020-03-28 2020-11-20 山东鲁圣电力器材有限公司 Lightning-arrest earth mat installation device

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106271353A (en) * 2015-05-29 2017-01-04 安顺市晶英科技研发有限责任公司 A kind of pipe welding clamp being applicable to T-shaped structure
CN206614284U (en) * 2017-04-06 2017-11-07 南京农业大学 A kind of wedge clamping device
CN107717310A (en) * 2017-11-20 2018-02-23 佛山迅奥捷自动化科技有限公司 Height adjustable holding fixed mechanism is used in a kind of metal plates combine welding
CN208117102U (en) * 2018-02-08 2018-11-20 青岛金泰瑞金属制品有限公司 T-shaped steel-pipe welding tooling
CN108321654A (en) * 2018-03-06 2018-07-24 李猛 A kind of power ground system fitting machine
CN108526790A (en) * 2018-05-22 2018-09-14 常州机电职业技术学院 Universal clamp for T-shaped structural member
CN108808424A (en) * 2018-05-25 2018-11-13 北京兴天通电讯科技有限公司 Earthing pole installs equipment
CN209256196U (en) * 2018-12-13 2019-08-16 天津市津菱机电工程有限公司 A kind of positioning clamping device of elevator parts welding
CN211966369U (en) * 2020-03-28 2020-11-20 山东鲁圣电力器材有限公司 Lightning-arrest earth mat installation device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114243411A (en) * 2021-12-28 2022-03-25 山东中恒建设集团有限公司 Device is used in construction of building ground connection
CN114243411B (en) * 2021-12-28 2024-07-23 山东中恒建设集团有限公司 Device for building grounding construction

Also Published As

Publication number Publication date
CN111230349B (en) 2024-12-13

Similar Documents

Publication Publication Date Title
CN111230349A (en) Lightning-arrest earth mat installation device
CN211898386U (en) Pipe pile verticality adjustment device
CN211966369U (en) Lightning-arrest earth mat installation device
CN210684727U (en) Construction safety supporting construction
CN111335317A (en) Tubular pile perpendicularity adjusting device
CN209585815U (en) An indoor activity enclosure
CN212773786U (en) Protective guardrail for construction engineering foundation pit
CN214498492U (en) An adjustable temporary support device for housing construction
CN213115576U (en) Device that first floor steel column takes one's place fast
CN204370834U (en) Supporting tool at the bottom of superposed beam beam
CN221920419U (en) An adjustable temporary support structure
CN209114981U (en) A kind of construction protection fence
CN217001165U (en) An electronic information engineering communication tower connection device
CN221682691U (en) A construction protection fence
CN214576217U (en) Foundation ditch guardrail convenient to equipment is dismantled
CN214401804U (en) Foundation pit supporting device
CN221421688U (en) Efficient formwork erecting and removing construction device for bridge guardrail
CN118943979B (en) Supporting device for installing buried power tube
CN218713169U (en) A new type of slope support structure
CN219654437U (en) A warning bar for construction sites
CN221823338U (en) Scaffold for construction engineering
CN216406269U (en) Auxiliary support device for ramp poles
CN215369104U (en) Enclose fender fixed baseplate and enclose fender
CN220927901U (en) Grille fixing device for side slope support
CN216713947U (en) A kind of support device with high stability for steel structure construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant