CN110905065B - 塑料排水管道不断管连续施工方法 - Google Patents
塑料排水管道不断管连续施工方法 Download PDFInfo
- Publication number
- CN110905065B CN110905065B CN201911149352.2A CN201911149352A CN110905065B CN 110905065 B CN110905065 B CN 110905065B CN 201911149352 A CN201911149352 A CN 201911149352A CN 110905065 B CN110905065 B CN 110905065B
- Authority
- CN
- China
- Prior art keywords
- pipeline
- pipelines
- well
- inspection well
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F3/00—Sewer pipe-line systems
- E03F3/06—Methods of, or installations for, laying sewer pipes
Abstract
本发明公开了一种塑料排水管道不断管连续施工方法,包括:在沟槽开挖完成并复测高程、坡度之后,进行管道摆放;将摆放好的管道组队安装,管道安装到达设计的检查井位置时连续安装,不断管留口,直到完成整个作业段的管道安装;在设计的检查井位置进行检查井砌筑,以管道为内壁砌筑流槽;在检查井砌筑完成后,对管道及检查井的井室进行功能性试验,试验合格后,将井室内流槽外部管道多余的部分切除,打开井内管道。本发明适用于市政道路排水管道或建筑工程排水二次管网使用塑料管道的施工,管道安装快速,安装后有利于保证管道内洁净。
Description
技术领域
本发明涉及一种市政道路排水管道或建筑工程排水二次管网的施工方法,具体说,涉及一种塑料排水管道不断管连续施工方法。
背景技术
目前,大多数工程的塑料排水管道在施工中到检查井位置时,都在检查井处切断管道,根据检查井的大小留出适当的空隙,再砌筑检查井。在多雨地区或多地下水地区非常容易导致管道内灌入泥水,清洁非常困难。
发明内容
本发明所解决的技术问题是提供一种塑料排水管道不断管连续施工方法,适用于市政道路排水管道或建筑工程排水二次管网使用塑料管道的施工,安装快速,安装后有利于保证管道内洁净。
技术方案如下:
一种塑料排水管道不断管连续施工方法,包括:
在沟槽开挖完成并复测高程、坡度之后,进行管道摆放;
将摆放好的管道组队安装,管道安装到达设计的检查井位置时连续安装,不断管留口,直到完成整个作业段的管道安装;
在设计的检查井位置进行检查井砌筑,以管道为内壁砌筑流槽;
在检查井砌筑完成后,对管道及检查井的井室进行功能性试验,试验合格后,将井室内流槽外部管道多余的部分切除,打开井内管道。
进一步,管道摆放时,按照设计图纸要求的管道型号规格,将管道摆放到对应位置,承插连接管道按照流水方向由承口到插口摆放。
进一步,作业段管道的首尾管口处使用编织袋包裹严密,防止进入杂物。
进一步,流槽砌筑完成后,在流槽外侧抹防水砂浆,管道闭水试验合格后进行沟槽回填,回填至管道上方300-500mm,分层夯实,待闭水试验合格后进行管道接口处回填。
进一步,管道安装同时砌筑检查井,此时部分位置渗水已到达管身位置,但采用不断管施工方法后,泥水无法进入管道内部。
进一步,沟槽开挖前先进行井点降水,经观测地下水位降到沟槽底部500mm以下后,进行沟槽开挖。
本发明技术效果包括:
本发明适用于市政道路排水管道或建筑工程排水二次管网使用塑料管道的施工,安装快速;管道容易控制整体坡度,安装后有利于保证管内洁净;流槽砌筑方便,以管道做为流槽内壁,平整光滑;在交叉作业中(如检查井砌筑、道路施工等)能保证管道内干净整洁,节省清理费用;适用于地下水位高、地质条件差的施工环境。
具体实施方式
以下描述充分地示出本发明的具体实施方案,以使本领域的技术人员能够实践和再现。
塑料排水管道不断管连续施工方法,具体包括以下步骤:
步骤1:在管道基础铺设完成并复测高程、坡度之后,进行管道摆放;
管道摆放时,按照设计图纸要求的管道型号规格,将管道摆放到对应位置,承插连接管道需要按照流水方向由承口到插口摆放。
步骤2:将摆放好的管道组队安装,管道安装到达设计的检查井位置时连续安装,不断管留口,直到完成整个作业段的管道安装;
作业段首尾管口处使用编织袋包裹严密,防止进入杂物。如此,整个作业段的管道安装完后是连成一体的。
步骤3:在设计的检查井位置进行检查井砌筑,以管道为内壁砌筑流槽;
步骤4:在检查井砌筑完成后,对管道及检查井的井室进行功能性试验,试验合格后,将井室内流槽外部管道多余的部分切除,打开井内管道。
实施例1
将本发明应用于龙山北路道路工程的雨污水管线施工,施工地点地质条件较差,工程施工地点靠近岱河水系,地质勘探发现有淤泥质土及流砂层,土方含水率高,出水速度快。管道沟槽开挖前先进行井点降水,经观测地下水位降到沟槽底500mm以下后,进行沟槽开挖。沟槽开挖后进行管道基础施工,期间沟壁有渗水现象,采取加快工序衔接,立刻进行管道不断管连续安装作业的施工方法,将本作业段管道连成一体,首尾处使用编织袋包裹严密,防止进入杂物。及时进行人工回填砂,回填至管道上方500mm,分层夯实,管道接口处空开不填,待闭水试验合格后回填。同时快速砌筑检查井,此时部分位置渗水已到达管身位置,但采用不断管施工方法后,泥水无法进入管道内部。检查井内流槽砌筑以管道为内壁,管道两侧砌筑至管身中线位置,抹防水砂浆。检查井砌筑完成后盖好井口,做好警示标志,既保证安全,又保证不掉入杂物。闭水试验合格后进行沟槽回填,分层压实。
本次施工在各项分项工程检查验收中合格率100%,施工速度快,在进行单位工程验收前,将井内管道流槽以上多余部分切割,完成全部工序。井内与管道内干净整洁,功能性试验全部合格,验收一次通过。
本发明所用的术语是说明和示例性、而非限制性的术语。由于本发明能够以多种形式具体实施而不脱离发明的精神或实质,所以应当理解,上述实施例不限于任何前述的细节,而应在随附权利要求所限定的精神和范围内广泛地解释,因此落入权利要求或其等效范围内的全部变化和改型都应为随附权利要求所涵盖。
Claims (6)
1.一种塑料排水管道不断管连续施工方法,包括:
在沟槽开挖完成并复测高程、坡度之后,进行管道摆放;
将摆放好的管道组队安装,管道安装到达设计的检查井位置时连续安装,不断管留口,直到完成整个作业段的管道安装;
在设计的检查井位置进行检查井砌筑,以管道为内壁砌筑流槽;
在检查井砌筑完成后,对管道及检查井的井室进行功能性试验,试验合格后,将井室内流槽外部管道多余的部分切除,打开井内管道。
2.如权利要求1所述塑料排水管道不断管连续施工方法,其特征在于,管道摆放时,按照设计图纸要求的管道型号规格,将管道摆放到对应位置,承插连接管道按照流水方向由承口到插口摆放。
3.如权利要求1所述塑料排水管道不断管连续施工方法,其特征在于,作业段管道的首尾管口处使用编织袋包裹严密,防止进入杂物。
4.如权利要求3所述塑料排水管道不断管连续施工方法,其特征在于,流槽砌筑完成后,在流槽外侧抹防水砂浆,管道闭水试验合格后进行沟槽回填,回填至管道上方300-500mm,分层夯实,待闭水试验合格后进行管道接口处回填。
5.如权利要求1所述塑料排水管道不断管连续施工方法,其特征在于,管道安装同时砌筑检查井,此时部分位置渗水已到达管身位置,但采用不断管施工方法后,泥水无法进入管道内部。
6.如权利要求1所述塑料排水管道不断管连续施工方法,其特征在于,沟槽开挖前先进行井点降水,经观测地下水位降到沟槽底部500mm以下后,进行沟槽开挖。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911149352.2A CN110905065B (zh) | 2019-11-21 | 2019-11-21 | 塑料排水管道不断管连续施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911149352.2A CN110905065B (zh) | 2019-11-21 | 2019-11-21 | 塑料排水管道不断管连续施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110905065A CN110905065A (zh) | 2020-03-24 |
CN110905065B true CN110905065B (zh) | 2021-06-08 |
Family
ID=69818537
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911149352.2A Active CN110905065B (zh) | 2019-11-21 | 2019-11-21 | 塑料排水管道不断管连续施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110905065B (zh) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1100493A (zh) * | 1994-05-26 | 1995-03-22 | 庞学雷 | 直接在顶管管道上设井建管道的方法 |
CN101565964A (zh) * | 2009-05-25 | 2009-10-28 | 青岛恒生源集团建设有限公司 | 室外埋地高密度聚乙烯双壁波纹排水管安装施工方法 |
CN107587524A (zh) * | 2017-08-18 | 2018-01-16 | 新地能源工程技术有限公司 | 一种穿越海堤的排水管施工方法 |
CN107724405A (zh) * | 2017-09-29 | 2018-02-23 | 兰州理工大学 | 一种地埋管施工中管地基降水施工方法 |
CN107761911A (zh) * | 2016-08-17 | 2018-03-06 | 彭建明 | 一种提高安装质量的排污管网的施工方法 |
-
2019
- 2019-11-21 CN CN201911149352.2A patent/CN110905065B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1100493A (zh) * | 1994-05-26 | 1995-03-22 | 庞学雷 | 直接在顶管管道上设井建管道的方法 |
CN101565964A (zh) * | 2009-05-25 | 2009-10-28 | 青岛恒生源集团建设有限公司 | 室外埋地高密度聚乙烯双壁波纹排水管安装施工方法 |
CN107761911A (zh) * | 2016-08-17 | 2018-03-06 | 彭建明 | 一种提高安装质量的排污管网的施工方法 |
CN107587524A (zh) * | 2017-08-18 | 2018-01-16 | 新地能源工程技术有限公司 | 一种穿越海堤的排水管施工方法 |
CN107724405A (zh) * | 2017-09-29 | 2018-02-23 | 兰州理工大学 | 一种地埋管施工中管地基降水施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN110905065A (zh) | 2020-03-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102486247B (zh) | 浆膜内衬法供排水管道修复工艺方法 | |
CN109881694A (zh) | 一种针对基坑基底涌水涌砂进行封堵的施工结构及方法 | |
US4329083A (en) | Methods of laying underground conduits | |
CN101775826A (zh) | 一种铺设输水管道的施工方法 | |
CN111853418B (zh) | 一种用于管道修复的施工方法 | |
CN104482298B (zh) | 一种hdpe钢塑复合螺旋缠绕排水管安装施工方法 | |
CN104005419A (zh) | 下沉法施工的箱涵构造及施工方法 | |
CN112252973A (zh) | 一种用于管道埋设通道的非开挖定向钻进施工方法 | |
CN110878697A (zh) | 高富水砂卵石地层中紧邻城市主干道的盾构水下接收方法 | |
CN207121916U (zh) | 封井结构 | |
CN110905065B (zh) | 塑料排水管道不断管连续施工方法 | |
CN106545070B (zh) | 既有检查井中采用顶管增设管道时的导流方法 | |
CN110965487B (zh) | 一种下穿通道大流量倒吸虹污水管及包封处理施工方法 | |
CN111335445B (zh) | 一种利用钢管作内模的混凝土雨水井施工方法 | |
CN113863268A (zh) | 一种防疫应急工程装配式污水处理站施工与调试工艺 | |
CN218911599U (zh) | 一种给水管保护结构 | |
CN204252254U (zh) | 用于污水管网的内衬、污水管网 | |
CN103982707A (zh) | 临场现铺混凝土包围柔管导流系统 | |
CN218346364U (zh) | 一种便于施工的道路收水支管 | |
CN220598632U (zh) | 一种大口径雨污水管道的回填结构 | |
TWI710725B (zh) | 地下管線重組工法及其構造 | |
CN201390975Y (zh) | 非开挖玻璃钢检查井 | |
CN211849870U (zh) | 一种污水管道的防渗阻渗结构 | |
CN115198864B (zh) | 一种污水管道改造带水作业施工方法 | |
CN113833524B (zh) | 一种处理岩溶区隧道涌水的双孔箱涵及其施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |